"Sharma, Shaleen - EOSIL - MUM" <shaleen.sharma@essar.com>, "Tennell, Jerry - EOL-E&P - Durgapur" <jerry.tennell@essar.com>, "sidhari.ram" <sidhari.ram@essar.com>, quippo limited rig2tp@gmail.

com Dear Dilipji, Please find attached herewith the DPR of Quippo 1300 Dated:17/Oct/2012. Thank you, Chintankumar

DDR-QUIPPO-1300 Dated:17/Oct/2012

Dear Zahid,

Please provide cementing program for well EDH 29 D4 (Pad EDP 51).
The rest details are as follows:1. Top most Coal Seam :- M.D. 975(GL) mtrs 2. Bottom most coal seam:- M.D. 1585 (GL) mtrs 3. Total Drilled Depth :- M.D. +/-1685 (GL) mtrs 4. Previous csg. shoe 520 (GL) mtrs. (9.625") 5. Cement Rise 725 mtrs Please consider excess percentage 20% All depths are from G.L.

Regards,