Client Name : M/s Hindustan Coca-Cola Beverages Pvt.

Ltd Project Name : Bangalore Green Field Project Number : 012 - 01137 - 00

Date: 08.08.2012 NATURAL VENTILATION CALCULATION SHEET


SR NO 1 Description of Area Ground Floor Total Area ft2 60,000 60,000 Height ft 50 Volume ft3 3,011,040 ACPH Ventilation cfm 602,208 602,208 Selected fan cfm 2,164 Nos. 92.76 200,736

12

SR.NO

AREA FRESH AIR OPENING REQUIRED 1,721 SQ.FT 160 Sq.Mtr. 131 MTR LENGTH

REMARK

1] 1.2MTR HIGH LOUVER REQUIRED

67 NOS. 2M x 1.2M VENTILATION LOUVERS TO BE PROVIDED ON BUILDING WALL AT 1.0 MTR. FROM FFL

EXHAUST AIR OPENING REQUIRED 2] 1.5MTR HIGH LOUVER REQUIRED

2,581 SQ.FT 240 SQ.MTR. 197 MTR LENGTH

80 NOS. 2M x 1.5M VENTILATION LOUVERS TO BE PROVIDED ON BUILDING WALL + 91 NOS TURBO VENTILATIOR FANS COSIDERED ON THE ROOF [ CAP:2161 CFM EACH ].EXHUAST LOUVER SHALL BE AT THE LEVEL OF 10 MTR FROM FFL.

3]

Required wall Opening for Natural Smoke Ventilation ( As per NBC Chapter-4 FIRE AND LIFE SAFETY ) 3% of total floor area.

1,800 SQ.FT

VENTILATION EXHAUST AIR OPENING IS MORE THAN SMOKE EXHAUST OPENING, HENCE NO NEED ANOTHER OPENING.NATURAL VENTILATION WILL SERVE DUAL PURPOSE OF NORMAL & SMOKE VENTILATION.

Expected Tropical Summer Index (TSI)

REF: NBC Part-8 , 2.2.23

TSI= 0.745 x DB + 0.308 x WB - 2.06 x v + 0.841 TSI= 0.745 x 35.6 + 0.308 x 25.6 - 2.06 x 2.82 + 0.841 TSI= 31.8 31.8 C INSIDE EXPECTED TEMPRATURE IN PROCESS AREA DURING PEAK AMBIENT TEMPERATURE