You are on page 1of 30

Net work Analysis CPM/PERT

Project

A project is a series of activities directed to accomplishment of a desired objective.

Work break down structure

Project can be splitted into small tasks with sequence of the their execution. This process is known as work break down structure
Plan your work first..then work your plan

Network analysis
Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects. Main objectives are: 1. Complete the project within stipulated period..

2. Optimize resources utilization.


3. Better coordination in interdependent activities C.P.M & P.E.R.T are two methodologies to analyze the network

PERT Project Evaluation & Review Techniques

Definition: In PERT activities are shown as a network of precedence relationships in which successive events are joined by arrows. Probabilistic activity times Optimistic time, pessimistic time, most likely time. Event oriented diagram

USED IN : Project management - for non-repetitive jobs (research and development work), where the time and cost estimates tend to be quite uncertain. This technique uses probabilistic time estimates.

CPM - Critical Path Method

Definition: CPM activities are shown as a network of precedence relationships in which successive activities are represented by arrows. .also called PPS Single estimate of activity time Deterministic activity times Activity oriented diagram

USED IN : Production management - for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience.

Terminologies used in C.P.M

Use of nodes and arrows


An arrow leads from tail to head directionally Indicate ACTIVITY, a time or resource consuming effort that is required to perform a part of the work. Direction of the progress of the project A node is represented by a circle - Indicate EVENT, a point in time where one or more activities start and/or finish. - Some part of the project has been complete - Merge events, brust events.

Arrows

Nodes

Terminologies used in C.P.M

Relation ship between Events: 1. Successor Events 2. Predecessor Events Activity: 1. Successor Activity 2. Predecessor Activity 3. Dummy Activity 4. Concurrent Activity

Activity on Node & Activity on Arrow


Activity on Node
- A completion of an activity is represented by a node

Activity on Arrow
- An arrow represents a task, while a node is the completion of a task - Arrows represent order of events

Rules to draw the network


1. Each event is presented by the nodes & activity by an

arrow 2. The starting event should be represented by i 3. The completion of project should be assigned highest number in the network 4. The activities emerging from event i should have no predecessor activities & event having highest number in diagram should have no successor activity 5. The activity must have highest number for its head (arrow) than its tail 6. Network diagram cannot have more than one starting node or end node

Rules to draw the network


7.

8.

7. There should not be a loop in diagram 8. An event cannot occur or an activity cannot start unless all its preceding activities have been completed (not applicable on dummy activity )

Fulkersons Rule
The starting event(having no predecessor activity is numbered as 1 ) other events are numbered in increasing order from 1 to rightwards , if there are more then 1 initial event found in a diagram , anywhere they are to be numbered fro top to bottom in increase order no two events can have the same number in any case

Question 1
Activity A B C D E F G H I J Draw the network diagram Predecessor --A B C,E B C,E F G H,D I

Question 2
A project consist of 7 activities .Activities P,Q,R run simultaneously . The relationship among the various activities is as follow Activity successor P S Q T R U Activity V is the immediate successor to S, T, & U Draw the network diagram

Question 3
Activity A B C D E F G H I J K Draw the network diagram Predecessor ----A C A E B G C,E F D,G,J

Estimation activity time


Most optimistic completion time Most pessimistic completion time Most likely completion time te = a+4m+b 6

Where, a = Most optimistic completion time b = Most pessimistic completion time m = Most likely completion time

Question 4
Q: Draw the network, labeling activities

Job Activity

Immediate Predecessor

Optimistic time a

Most likely m

Pessimistic time b

A B C D E F G H

A B C, D B E F, G

5 2 6 1 3 6 1 4

6 5 7 2 3 8 4 5

7 8 14 3 3 10 7 6

Activity Slack

Earliest starting time (EST) , which is a calendar time when a


event can occur when all the predecessor events completed at the earliest possible times

Earliest finish time (EFT)

* Preceding from start to finish

Activity Slack

Latest starting time (LST): The latest time by which an activity


is started with out delaying the total project completion.

Latest finish time (LFT):

* Start working from finish to start

Determination of critical path


Critical Path: Critical path is the series of connecting activities from starting to end for which the total time of completion of all activities is maximum Critical activities /Bottle neck : All activities come in the way of critical path are called critical activities Non Critical activities : All activities do not come in the way of critical path are called non critical activities

Float/ Slacks

Slack is the amount of time an event can be delayed without delaying the project completion Positive slack Negative slack Zero slack Slack = LST EST LFT EFT

Question 4
Activities Predecessor activities Activity Time L ---3 M ---4 N L 9 O L 3 P O 3 Q N,M 6 R N,M 4 S R 2 T R 5 U P,Q,S 6 Draw the network diagram Calculate EST,EFT,LST,LFT ,activity slack & high light the critical path

Crash Time
Crash time = Crashed Cost Normal Cost Normal Time Crashed Time

Nodes 1-2 2-3 2-4 2-5 3-5 4-5 5-6 6-7 6-8 7-8

Normal Time 3 3 7 9 5 0 6 4 13 10

Question 5
Cost 300 30 420 720 250 0 320 400 780 1000 Time 2 3 5 7 4 0 4 3 10 9

Crash

Cost 400 30 580 810 300 0 410 470 900 1200

Project indirect cost is 50Rs. Per week. Draw the network diagram & identify the critical path ? What are the normal project duration and associated Cost ? Find total float associated with each activity Crash the relevant activities systemically and determine the optimal project completion and cost

Question 6
On May 1,Arnie Watson sent a memo to his boss, the director of the project (6) management. Stating that the MX project would require 13 weeks for the completion. Arnie realized that customer wanted the job completed in less time, after discussions with the functional managers,Arnie developed the table shown. According to the contract there is a penalty payment of $5,000 per week for every week over six. What is the minimum amount of additional funding that arnie should request.

Job Activity

A B C D E F

Predecessor Activity A A A C,D B,E

Time 3 5 5 4 2 3

Normal Cost ($.) Time


6,000 12,000 16,000 8,000 6,000 14,000 2 4 3 2 1 1

Crash Cost ($.)


8,000 13,500 22,000 10,000 7,500 20,000

Benefits of CPM/PERT

Interdependencies of activity Project completion time Impact of late start Impact of early start what if exercise Evaluation of performance

Questions Answered by CPM & PERT

Completion date? On Schedule? Within Budget? Critical Activities? How can the project be finished early at the least cost?

Limitations to CPM/PERT

Clearly defined, independent and stable activities Specified precedence relationships Over emphasis on critical paths

Thank you

You might also like