RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING & FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.
Description
1.
Supply and Eraction of duct work for wiring (Dura Adamgee) with rawal plugs,Screws and specials complete in all respects.
i) 16 x 16 mm
Cost of Material Labour Charages for Fixing Add 10% Contractor Profit
11.00 2.00 13.00 1.30 14.30 14.00 2.00 16.00 1.60 17.60 38.00 2.00 40.00 4.00 44.00
Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft
ii) 16 x 25 mm
Cost of Material Labour Charages for Fixing Add 10% Contractor Profit
iii) 40 x 40 mm
Cost of Material Labour Charages for Fixing Add 10% Contractor Profit
Sub Engineer
Assistant Engineer
Executive Engineer
Project Director
No No No Total Total
40 30 15
Sub Engineer
Assistant Engineer
Executive Engineer
Project Director
Total
Sub Engineer
Assistant Engineer
Executive Engineer
Project Director
Total
Sub Engineer
Assistant Engineer
Executive Engineer
Project Director
No No Total Total
220 10
Sub Engineer
Assistant Engineer
Executive Engineer
Project Director
100 AMPS MCCB 3-Phase 240 Volts Circuit breaker 20 AMPS MCB 1-Phase 240 Volts Circuits breaker 10 AMPS MCB 1-Phase 240 Volts Circuits breaker 6 AMPS MCB 1-Phase 240 Volts Circuits breaker All Circuit breakers Terasaki/Mitsubishi (Black) Japan to be used. Iron Box 2'x1.50' with Stove enameled paint. Unit of Rate = Each Cost of Iron Box 2'x1.50' 1 No 1800 1800.00 Cost of 100 AMPS 3-Phase Circuit breaker 1 No 2850 2850.00 Cost of 20 AMPS 1-Phase Circuit breaker 2 No 225 450.00 Cost of 10 AMPS 1-Phase Circuit breaker 12 No 225 2700.00 Cost of 6 AMPS 1-Phase Circuit breaker 4 No 225 900.00 Cost of Thimbles 9 No 20 180.00 Labour Charages for Fixing 1 No 400 400.00 Total 9280.00
Add 10% Contractor Profit
Each Each Each Each Each Each Each Each 928.00 Each
Total
10208.00 Each
Sub Engineer
Assistant Engineer
Executive Engineer
Project Director
Philps Chock 40 Watt,Phlips Startar 20 Watt Patty Fitting (Frame of light 2'x2') Pak light/Equaliant i/c hanging arrangement. Unit of Rate = Each
Cost of Light with Chock, Rod & Starter complete Labour Charages for Fixing Add 10% Contractor Profit 1 1
No No Total Total
1300 100
Sub Engineer
Assistant Engineer
Executive Engineer
Project Director
No No Total Total
1500 50
Sub Engineer
Assistant Engineer
Executive Engineer
Project Director
12.00 4.00
Sub Engineer
Assistant Engineer
Executive Engineer
Project Director
Supply and Eraction of duct work for wiring (Dura Adamgee) with rawal plugs,Screws and specials complete in all respects.
i) 16 x 16 mm
Cost of Material Labour Charages for Fixing Add 10% Contractor Profit
11.00 2.00 13.00 1.30 14.30 14.00 2.00 16.00 1.60 17.60 38.00 2.00 40.00 4.00 44.00
Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft
ii) 16 x 25 mm
Cost of Material Labour Charages for Fixing Add 10% Contractor Profit
iii) 40 x 40 mm
Cost of Material Labour Charages for Fixing Add 10% Contractor Profit
Sub Engineer
Assistant Engineer
Executive Engineer
Project Director
No No No Total Total
40 30 15
Sub Engineer
Assistant Engineer
Executive Engineer
Project Director
Total
Sub Engineer
Assistant Engineer
Executive Engineer
Project Director
Total
7040.00 Each
Sub Engineer
Assistant Engineer
Executive Engineer
Project Director
Cost of "U" Clamp and Nut bolts & Pins Cost of Labour for fixing Add 10% Contractor Profit
1 1
No No Total Total
130 10
Sub Engineer
Assistant Engineer
Executive Engineer
Project Director
No No No No Total Total
Sub Engineer
Assistant Engineer
Executive Engineer
Project Director
Labour Charages:
Excavation TNP Charges Add 10% Contractor Profit Add 10% Overhead Charges
Total
Rate Rs. 1830/- %o Cft
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved for
Rs.1,830.00
Project Director
CIVIL WORKS
Description
Material Cost:
Brick Ballast Cement Sand 97.00 Cft 6.50 Bag 48.00 Cft 9.00 Per Cft 333.00 Per Bag 9.00 Per Cft
Total
Say Rs.5100/-
ASSISTANT ENGINEER
SUB-ENGINEER
Project Director
Spraying antitermite
Per Sft. (for 3oo Sft) 1 Ltr 100.00 Sft 100.00 Sft 310.00 Per Lit 10.00 100 Sft 15.00 100 Sft
Material Cost:
TNP Charges
Labour Charages:
Total
Total
Rate Per Sft. Rs. 1.24 1.53
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Material Cost:
Bricks 5% Wastage 1350.00 68.00 1418.00 Nos
2200.00 1000 No
Total
Say
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Material Cost:
Bricks 5% Wastage 1350.00 68.00 1418.00 Nos 4.00 Bag 26.00 Cft
Labour Charges:
Total
Add 10% Contractor Profit Add 10% Overhead Charges
Total
Say
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Damp Proof Course 2" thick I/c bitumen coating and polythene sheet
Unit of Rate = 100 Cft 100 Sft
Material Cost:
Crush Cement Sand Bitumen Polythene Sheet 500 guage TNP 15.00 2.75 28.00 10.00 100.00 Cft Bag Cft Kg Sft 28.00 333.00 9.00 45.90 1.00 Per Cft P/Bag P/Cft Per Kg Per Sft
Total Say
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Material Cost:
Crush 5% Wastage Total Cement Sand TNP 88.00 4.00 92.00 17.60 44.00 Cft Cft Cft Bag Cft
Total
Rate Per Cft 121.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Material Cost:
Crush 5% Wastage Total Cement Sand TNP 84.00 4.00 88.00 22.40 42.00 Cft Cft Cft Bag Cft
Total
Rate Per Cft 139.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Description
Material Cost:
Crush 5% Wastage Total Cement Sand TNP 88.00 4.00 92.00 17.60 44.00 Cft Cft Cft Bag Cft
Total
Rate Per Cft 121.00
ASSISTANT ENGINEER
SUB-ENGINEER
Project Director
Material Cost:
Crush 5% Wastage Total Cement Sand TNP Shuttering Charges 84.00 4.00 88.00 22.40 42.00 Cft Cft Cft Bag Cft
Total
Rate Per Cft 175.00
ASSISTANT ENGINEER
SUB-ENGINEER
Project Director
Description
Material Cost:
Crush 5% Wastage Total Cement Sand TNP Shuttering Charges 88.00 4.00 92.00 17.60 44.00 Cft Cft Cft Bag Cft
ASSISTANT ENGINEER
SUB-ENGINEER
Project Director
Per kg
Material Cost:
Steel 5% Wastage Total Steel Binding Wire TNP 100.00 5.00 105.00 3.00 Kg Kg Kg Kg
Total
Rate Per Kg 55.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Material Cost:
Steel 5% Wastage Total Steel Binding Wire TNP 100.00 5.00 105.00 3.00 Kg Kg Kg Kg
Total
Rate Per Kg 46.08
ASSISTANT ENGINEER
SUB-ENGINEER
Project Director
Material Cost:
Steel 5% Wastage Total Steel Binding Wire TNP 100.00 5.00 105.00 3.00 Kg Kg Kg Kg
Total
Rate Per Kg 59.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Material Cost:
Cement Sand TNP 1.00 Bag 3.00 Cft 333.00 Per Bag 9.00 Per Cft
Total
Rate Per Sft 12.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
3/8" thick
Per Sft
Material Cost:
Cement Cement for neru Sand TNP 1.00 0.25 1.25 2.50 Bag Bag Bag Cft
Total
Rate Per Sft 12.50
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
3/4" thick
Per Sft
Material Cost:
Cement Sand TNP 1.50 Bag 4.00 Cft 310.00 Per Bag 8.00 Per Cft
Total
Rate Per Sft 12.86
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Material Cost:
TNP
Total
Rate Per Cft 16.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Total
Add 10% Contractor Profit Add 10% Overhead Charges
Total
Rate Per Sft 1.32
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
CIVIL WORKS
Description
Material Cost:
Cement Sand Bitumen TNP 1.25 Bag 3.00 Cft 16.00 Kg 333.00 Per Bag 9.00 Per Cft 45.90 Per Kg
Total
Rate Per Sft 22.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Total
Add 10% Contractor Profit Add 10% Overhead Charges
Total
Rate Per Rft 62.40
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Total
Add 10% Contractor Profit Add 10% Overhead Charges
Total
Rate Per sft 10.50
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
First Class Brick walling 4.5" thick 1:3 hoop iron 12" apart
Unit of Rate = 100 Cft 100 Sft
Material Cost:
Bricks 5% Wastage 518.00 26.00 544.00 Nos 2.25 Bag 13.00 Cft 100.00 Rft
TNP
Total
Rate Per Sft. 40.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Spray plaster
Unit of Rate = 100 Cft Per Sft
Material Cost:
Cement Marble Chips TNP 1.00 Bag 5.00 Bag 333.00 Per Bag 25.00 Per Bag
Total
Rate Per Sft 13.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
I Labour Charages:
Griding Charges Polish Charges
Total
Rate Per Sft 38.50
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Total
Rate Per Cft 6.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Material Cost:
Bricks 5% Wastage 1350.00 68.00 1418.00 Nos 6.00 Bag 25.00 Cft
Total Say
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
I Labour Charages:
Total
Add 10% Contractor Profit Add 10% Overhead Charges
Total
Rate Per 1000 Cft 1400.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
I Labour Charages:
Total
Add 10% Contractor Profit Add 10% Overhead Charges
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
550.00 No 28.00 578.00 No 1.25 Bag 3.00 Cft 100.00 Sft 100.00 Cft
I Labour Charages:
Total
Add 10% Contractor Profit Add 10% Overhead Charges
Total
Rate Per Sft 26.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
CIVIL WORKS
Description
Mosaic toping
Per Bag Per Cft Per Cft Per Bag Per Bag Per Bag
100.00 Cft
Total
Add 10% Contractor Profit Add 10% Overhead Charges
Total
Rate Per Sft 37.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Unit of Rate = 100 Cft 1 Material Tile 5% Wastage Cement Sand Cement TNP
Per Sft
(100 Sft) 100.00 5.00 105.00 1.50 3.00 Sft Sft Bag Cft 41.50 Per Sft 333.00 Per Bag 9.00 Per Cft
(Grey) White
I Labour Charages:
100.00 Sft
Total
Rate Per Sft 73.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
S.Total
Add 10% scafolding charges
Total
Add 10% Contractor Profit Add 10% Overhead Charges
Total
SAY
ASSISTANT ENGINEER
EXECUTIVE ENGINEER
(100 Sft) (100 Rft) 100.00 Rft (Grey) 2.00 Per Rft
I Labour Charages:
Add 10% Contractor Profit Add 10% Overhead Charges
100.00 Rft
Total
Rate Per Rft 5.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Roof Insulation
Unit of Rate = 100 Cft 1 Material Tile 9"x4.5"x1.5" 5% Wastage Per Sft
(100 Sft) (100 Sft) 350.00 18.00 368.00 20.00 100.00 16.00 100.00 1.00 3.00
Bitumen Polythene Sheet 500 Gauge Earth jumbo lawn 1" thick Cement Sand TNP
Per 1000 Per Lbs Per Sft Per Cft Per Sft Per Bag Per Cft
I Labour Charages:
Add 10% Contractor Profit Add 10% Overhead Charges
100.00 Sft
Total
Rate Per sft 63.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
333.00 Per Bag 28.00 Per Cft 9.00 Per Cft 93.00 Per No
I Labour Charages:
Add 10% Contractor Profit Add 10% Overhead Charges
Total
Rate Per No 290.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Bottom Khurras
Unit of Rate = 100 Cft 1 Material Cement Brick Crush Sand TNP Per No
Labour Charges:
Add 10% Contractor Profit Add 10% Overhead Charges
1.00 No
78.00 Per No
Total
Rate Per No 505.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
I Labour Charages:
Add 10% Contractor Profit Add 10% Overhead Charges
1.00 No
75.00 Per No
Total
Rate Per Rft 208/-
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
RATE ANALYSIS
CIVIL WORKS
Description
I Labour Charages:
Add 10% Contractor Profit Add 10% Overhead Charges
Total
Rate Per No 281/-
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Unit of Rate = 100 Cft 1 Material Pertal Wood 30% Wastage Deodar Wood 30% Wastage
Per Sft (7'x4') 2.24 0.67 2.91 0.08 0.02 0.10 56.00 2.00 8.00 2.00 2.00 1.00 3.00
Cft
Commercial Ply 5 mm thick Gelu Kick Plate Handle Finger Plate Tower Bolt Hinges Screws
Per Cft Per Sft Per Kg Per Rft Per No Per No Per No Per No
Labour Charges:
Add 10% Contractor Profit Add 10% Overhead Charges
28.00 Sft
Total
Rate Per Sft 162/-
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Safety Grill
Unit of Rate = 100 Cft 1 Material Angle Iron 1"x1"x1/8" Square Bar 3/8"x3/8" Labour for welding Per Sft (6'x6') 6.00 Kg 30.00 Kg 36.00 Sft 38.00 Per Kg 38.00 Per Kg 20.00 Per Sft
Paint Cement Crush Sand Labour for fixing at site Add 10% Contractor Profit Add 10% Overhead Charges
36.00 Sft
Total
Total
Rate Per Sft 86.70
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Total
Rate Per No 135.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
35.00 Per Qtr 130.00 Per Qtr 10.00 Per Qtr 2.00 Per Sft
Total
Rate Per Sft ASSISTANT ENGINEER 10.00 SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Terrace Railing
Unit of Rate = 100 Cft Per Rft
Material (10 Rft) M.S Condute Pipe 2" dia 16 SWG M.S Bar 5/8"x5/8" M.S. Flat 1"x1/8" Labour for welding TNP Labour for fixing at site Total Add 10% Contractor Profit Add 10% Overhead Charges
Rft Kg Kg Rft
Total
Rate Per Rft ASSISTANT ENGINEER 261.00 SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Total
Rate Per Sft ASSISTANT ENGINEER 10.00 SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Total
Rate Per Sft ASSISTANT ENGINEER 2.00 SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Rs. Rs.
Total
Rate Per Sft. 225/100 = 2.25
SUB-ENGINEER
Project Director
100.00 Sft
Total
Rate Per Sft ASSISTANT ENGINEER 1.00 SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
10.00 Rft
10.00 Rft
Total
Rate Per Rft ASSISTANT ENGINEER 34.00 SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Total
Rate Per Sft ASSISTANT ENGINEER 11.00 SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
CIVIL WORKS
Description
10.00 Rft
Total
Rate Per Rft ASSISTANT ENGINEER 40.00 SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Unit of Rate = 100 Cft Material (100 Cft) Cement Crush Sand TNP Labour charges
Per Cft
Total
Rate Per Cft ASSISTANT ENGINEER 120.00 SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
P/F Wardrobe.
Unit of Rate = 100 Cft Per Sft
Material 3'x7' M.S pipe 3"x1.5" 18 SWG Labour welding Commercial Win Board 3/4" thick 10% Wastage
Deodar Wood 30% Wastage Aluminium Rod Bracket Tower Bolt Lock 808 Handle Hardware Charges Paint Labour charges Total Add 10% Contractor Profit Add 10% Overhead Charges
Cft Cft Rft No No No No 1600.00 12.00 20.00 20.00 35.00 20.00 Per Cft Per Rft Per No Per No Per No Per No
Total
Rate Per Sft 146.00
SUB-ENGINEER
PROEJCT DIRECTOR
Material 4'x7' M.S angle iron 1.5"x1.5"x3/16" M.S Sheet 1/16" Welding Labour Charges Red Oxide Paint Sliding Bolt. TNP Labour for fixing at site Total Add 10% Contractor Profit
Kg Kg Kg Kg
2.00 No
Total
Rate Per Sft 150.89
SUB-ENGINEER
Approved
Project Director
Material (6'x6') M.S Box pipe 2"x1.5" (16 SWG) M.S Box Pipe 1.5"x1" (16 SWG) M.S Box Ppipe 1/2"x1/2" (18 SWG) M.S Box Ppipe 3/8"x3/8" (18 SWG) M.S Flat 1"x1/8" M.S Flat 3/4"x1/8" 5 mm thick glass Hinges Handle Stay Rod Wire Gauze 24 SWG Painting Labour for welding Labour for fixing at site Add 10% Contractor Profit Add 10% Overhead Charges
48.00 72.00 72.00 72.00 72.00 48.00 36.00 16.00 4.00 8.00 36.00 108.00 36.00
Rft Rft Rft Rft Rft Rft Sft No No No Sft Sft Sft
25.00 20.00 10.00 8.00 5.00 4.00 30.00 20.00 20.00 25.00 15.00 10.00 29.00
Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Sft Per No Per No Per No Per Sft Per Sft Per Sft
Total
Rate Per Sft 300.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
RATE ANALYSIS
CIVIL WORKS
Description
Material M.S pipe 3"x1.25" 18 SWG Labour welding Lamination Board 3/4" thick 10% Wastage Deodar Wood 30% Wastage Tower Bolt Lock 808 Handle Hardware Charges Paint Labour charges Add 10% Contractor Profit Add 10% Overhead Charges
20.00 Rft 21.00 2.00 23.00 0.04 0.01 0.05 2.00 1.00 1.00 Sft Sft Cft Cft No No No
Total
Rate Per Cft 148.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Providing & Fixing open able Wardrobe Commercial Vin Board 3/4" thick for A/C Openg duct.
Unit of Rate = P sft Materials 2.25x2.75' MS pipe 1.5''x1.5'' 18 SWG Labour rate welding Commercial Vin Board 3/4" thick Wooden Beading Tower Bolts Handle Labour charges Total Add 10% Contractor Profit Add 10% Overhead Charges
47.5 P.Rft LS 50.00 Per Sft 50.00 35.00 each 20.00 each
Total
RATE PSFT ASSISTANT ENGINEER RATE P.SFT RS= SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Approved
Director Engineering
1/2" thick
Per Sft
Material Cost:
Cement Sand TNP 1.00 Bag 3.00 Cft 333.00 Per Bag 9.00 Per Cft
Total
Rate Per Sft 13.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
3/8" thick
Per Sft
Material Cost:
Cement Cement for neru Sand TNP 1.00 0.25 1.25 2.50 Bag Bag Bag Cft
Total
Rate Per Sft 13.50
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
(100 Sft) 100.00 5.00 105.00 1.50 3.00 Sft Sft Bag Cft 40.70 Per Sft 333.00 Per Bag 9.00 Per Cft
(Grey) White
I Labour Charages:
100.00 Sft
Total
Rate Per Sft 72.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
CIVIL WORKS
Description
3/4" thick
Per Sft
Material Cost:
Cement Sand TNP 1.25 Bag 3.00 Cft 333.00 Per Bag 9.00 Per Cft
Total
Rate Per Sft 14.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Total
Rate Per Sft ######
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Material Cost:
Bricks 5% Wastage
Total
Say
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Material Cost:
Cement Sand TNP 1.50 Bag 4.00 Cft 333.00 Per Bag 9.00 Per Cft
Total
Rate Per Sft 14.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Construction of Administrative Block for University College of Engineering & Technology at Baghdad-ul-Jadeed Campus
RATE ANALYSIS
CIVIL WORKS
Description
Providing and fixing botiseana/fency marble for stair steps 3/4" thick with floating coat of cement over a bed of 3/4" thick cement sand mortar 1:2 including colour pigment to match with the colour of marble tiles, laid with cement sand mortor 1:2 rubbing and chemical polishing complete in all respects as directed and approved by the Engineer incharge.
Per Sft 1.00 Sft 1.00 Sft 1.00 Sft 1.00 Sft 1.00 Sft 1.00 Sft 1.00 Sft 1.00 Sft 140.00 3.00 5.00 336.10 7.88 336.10 4.50 24.00 Total
3 Loading, unloading and stacking 4 Material Cost of Floating Coat (MRS July 2005) 5 Cost of Martor under marble 3/4" thick (MRS Jul 05) 6 Ratio 1:2 7 Cost of floating coat (MRS July 2005). 8 Cost of Pigment 9 Cost of Labour for fixing & chemical polishing (10+14)
Add 10% Contractor Profit on Items No. 1-3, 8 & 9 Add 10% over head charges on Items No. 1-4, 8 & 9 G. Total
SAY Rs.
ASSISTANT ENGINEER
SUB-ENGINEER
Approved
Project Director
Construction of Administration Block for University College of Engineering and Technology a Baghdad-ul-Jadeed Campus
RATE ANALYSIS
CIVIL WORKS
Description
Providing and fixing marble 3/4" thick 12" long 3" wide with pure chocklate colour with floating coat of cement over a bed of 3/4" thick cement sand mortar 1:2 over 1" thick PCC 1:2:4 Gray cement, including colour pigment to match with the colour of marble tiles, laid with cement sand mortor 1:2 rubbing and chemical polishing complete in all respects as directed and approved by the Engineer incharge.
Per Rft 1.00 No. 1.00 No. 0.25 Sft 0.25 0.25 0.25 0.25 0.25 Sft Sft Sft Sft Sft 62.50 0.66 336.10 7.88 336.10 1103.90 4.50 24.00 Total
Cost of Morble 3"x12"x3/4" Wastage 3% Carriage Material Cost of Floating Coat (MRS July 2005) Cost of Martor under marble 3/4" thick (MRS Jul 05) Ratio 1:2 Cost of floating coat (MRS July 2005). Cost of PCC 1:2:4 1" thick (MRS July 2005) Cost of Pigment Cost of Labour for fixing & chemical polishing (10+14)
Add 10% Contractor Profit on Items No. 1-3, 9 & 10 Add 10% over head charges on Items No. 1-3, 9 & 10 G. Total
ASSISTANT ENGINEER
SUB-ENGINEER
Approved
Project Director
RATE ANALYSIS
CIVIL WORKS
Description
Providing and fixing botiseana/fency marble for stair steps 3/4" thick 36"-60"/13.5" with floating coat of cement over a b of 3/4" thick cement sand mortar 1:2 including colour pigment to match with the colour of marble tiles, laid with cement sand mortor 1:2 rubbing and chemical polishing complete in all respects as directed and approved by the Engineer incharge. Unit of Rate = 100 Cft 1 2 3 4 5 Per Sft 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Sft Sft Sft Sft Sft Sft Sft Sft 135.00 3.00 5.00 336.10 7.88 336.10 4.50 10.00 Total
Carriage Loading, unloading and stacking Material Cost of Floating Coat (MRS July 2005) Cost of Martor under marble 3/4" thick (MRS Jul 05) Ratio 1:2 6 Cost of floating coat (MRS July 2005). 7 Cost of Pigment 8 Cost of Labour for fixing & chemical polishing (10+14)
Add 10% Contractor Profit on Items No. 1-3, 7 & 8 Add 10% over head charges on Items No. 1-4, 7 & 8 G. Total
SAY Rs.
ASSISTANT ENGINEER
SUB-ENGINEER
Approved
Project Director
Total
Rate Per No 135.00
SUB-ENGINEER
ASSISTANT ENGINEER
EXECUTIVE ENGINEER
Project Director
LPUR
SUB-ENGINEER
1000 Cft
SUB-ENGINEER
awalpur
SUB-ENGINEER
WALPUR
3119.60
SUB-ENGINEER
WALPUR
SUB-ENGINEER
WALPUR
420.00 915.75 252.00 459.00 100.00 50.00 400.00 2596.75 259.68 259.68 3116.10 3116.00
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
alpur
2760.00 5720.00 396.00 200.00 1000.00 10076.00 1007.60 1007.60 12091.20 120.912
SUB-ENGINEER
awalpur
2640.00 7280.00 378.00 200.00 3000.00 1100.00 14598.00 1459.80 1459.80 17517.60
SUB-ENGINEER
awalpur
2116.00 3168.00 396.00 100.00 3000.00 500.00 9280.00 928.00 928.00 11136.00
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
WALPUR
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
WALPUR
SUB-ENGINEER
awalpur
999.00 200.00 50.00 200.00 566.00 200.00 100.00 2315.00 3208.25 320.83
320.83 3849.90
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
2836.00 1998.00 225.00 100.00 675.00 5834.00 583.40 583.40 7000.80 7000.00
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
702.63 48.42 295.68 666.00 50.00 200.00 100.00 720.00 200.00 100.00 3082.73 308.27 308.27 3699.28
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
400.00 200.00 100.00 300.00 150.00 1150.00 115.00 1265.00 126.50 126.50 1518.00
151.80
awalpur
SUB-ENGINEER
awalpur
809.60 500.00 100.00 48.00 3000.00 333.00 27.00 50.00 415.00 5282.60 528.26 528.26 6339.12
SUB-ENGINEER
SUB-ENGINEER
awalpur
166.50 92.40 56.00 18.00 10.00 78.00 420.90 42.09 42.09 505.08
SUB-ENGINEER
awalpur
800.00 60.00 63.00 31.00 10.00 75.00 1039.00 103.90 103.90 1246.80
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
1746.00
163.20 840.00 100.00 160.00 30.00 50.00 30.00 75.00 30.00 560.00 3784.20 378.42 378.42 4541.04
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
500.00 1102.00 76.00 300.00 50.00 150.00 2178.00 217.80 217.80 2613.60
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
643.00 100.00
626.75
80.00 36.00 40.00 40.00 35.00 20.00 200.00 420.00 315.00 2555.75 255.58 255.58 3066.90
SUB-ENGINEER
awalpur
352.10 4225.20
SUB-ENGINEER
awalpur
1200.00 1440.00 720.00 576.00 360.00 192.00 1080.00 320.00 80.00 200.00 540.00 1080.00 1044.00 150.00 8982.00 901.80 901.80 10785.60
SUB-ENGINEER
awalpur
LEGE
700.00 100.00
736.00
80.00 36.00 32.00 15.00 150.00 420.00 315.00 2584.00 258.40 258.40 3100.80
SUB-ENGINEER
awalpur
SUB-ENGINEER
awalpur
omen at B.J.Campus
587.81 125.00 250.00 50.00 39.00 22.00 50.00 1123.81 11.24 11.24 1146.29 229 SUB-ENGINEER
Project Director
awalpur
SUB-ENGINEER
LPUR
SUB-ENGINEER
LPUR
SUB-ENGINEER
LPUR
SUB-ENGINEER
LPUR
SUB-ENGINEER
3119.60 1332.00 234.00 150.00 1000.00 5835.60 583.56 564.11 6983.27 7000.00
SUB-ENGINEER
LPUR
SUB-ENGINEER
alpur
Engineering & Technology at
coat of cement over a bed of 3/4" thick ble tiles, laid with cement sand mortor roved by the Engineer incharge.
Per Sft Per Sft Per Sft % Sft Per Sft % Sft Per Sft Per Sft
16.15
16.15 208.40
SAY Rs.
208
SUB-ENGINEER
alpur
ating coat of cement over a bed our pigment to match with the omplete in all respects as
Each Each % Sft Per Sft % Sft % Sft Per Sft Per Sft
62.50 1.88 0.66 0.84 1.97 0.84 2.76 1.13 6.00 78.570
7.22
7.22 93.002
SUB-ENGINEER
alpur
Engineering & Technology at
5" with floating coat of cement over a bed colour of marble tiles, laid with cement cted and approved by the Engineer
Per Sft Per Sft Per Sft % Sft Per Sft % Sft Per Sft Per Sft
15.75
15.75 203.60
SAY Rs.
204
SUB-ENGINEER
awalpur
ASSISTANT ENGINEER
Total
6.30 8.80 11.50 14.00 6.30 8.80 11.50 14.00 75.60 105.60 138.00 168.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Rs.2,220.00
per No.
Project Director
Total
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
P Trap Glazed
Unit of Rate Per No P Trap (Full size) Cement Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1 1 No No 60.00 20.00 Each Per No 60.00 20.00 20.00 100.00 10.00 10.00 120.00
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
RATE ANALYSIS
Plumbing Work
Description
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Plumbing Work
Description
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Description
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Unit of Rate Per No Looking Glass 2' x 2' Labour charges Add 10% Contractor Profit Add 10% Overhead Charges
350.00 50.00
Each Each
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
204.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
4" size glazed gully trap with chamber 12" x 12" I/c 9" dia C.I Cover & Frame.
Unit of Rate Per No Gully trap Bricks Cement Sand C.I Frame with Cover Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 20.00 0.25 No No Bag 75.00 2.00 310.00 250.00 100.00 Each Each Each Each Each 75.00 40.00 77.50 10.00 250.00 100.00 552.50 55.25 55.25 663.00
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
RATE ANALYSIS
Plumbing Work
Description
Total
Rate Per Rft =
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Approved
Director Engineeing
Total
Rate Per job =
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
Approved
Director Engineeing
Gas Cock
Labour charges
8.50 8.50
102.00
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
8.50 8.50
102.00
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
P/F 3" thick RCC main hole cover with tee shaped C.I Frame of 20" Clear (37.32 Kg)
Unit of Rate = Per No. Material C.I Frame MS Angle Iron & Steel Bar Cement Crush Sand TNP
150.00
1205.50 120.55 120.55 1446.60
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges
TOTAL
Rate Per Rft
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved Rate of
Rs.9.00
per Rft
Project Director
TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges
TOTAL
Rate Per Rft
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved Rate of
Rs.10.20
per Rft
Project Director
TOTAL
TOTAL
Rate Per Rft
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved Rate of
Rs.13.80
per Rft
Project Director
Electrical WORKS Description: PVC Pipe 40 mm dia including all specials (Beta/Galco/shaval
Unit of Rate = PVC Pipe 10 Rft Accessores/Fittings. Labour charges Per Foot. 95.00 12.00 8.00 115.00
TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges
TOTAL
Rate Per Rft
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved Rate of
Rs.13.80
per Rft
Project Director
Total
Add 10% Contractor Profit Add 10% Overhead Charges
Total
Rate Per Rft
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved Rate of
Rs.21.00
per Rft
Project Director
Total
Add 10% Contractor Profit Add 10% Overhead Charges
Total
33.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved Rate of
Rs.33.00
per Rft
Project Director
Unit of Rate = Cable (one coil 90 meter) Wastage 5% Accessores/Fittings. TNP Labour charges
TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges
TOTAL
Rate Per Mater
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved Rate of
Rs.11.94
per Rft
Project Director
TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges
TOTAL
Rate Per Mater
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved Rate of
Rs.11.94
per Rft
Project Director
TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges
TOTAL
Rate Per Mater
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved Rate of
Rs.19.77
per Rft
Project Director
TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges
2523.75
TOTAL
Rate Per Mater
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved Rate of
Rs.33.65
per Rft
Project Director
Description:
Single Core PVC insulatted Copper conductor 7/0.064" Cable (Pakistan,New age)
Unit of Rate = Cable (one coil 90 meter) Wastage 5% Accessores/Fittings. TNP Labour charges Per Metre 2850.00 142.50 40.00 60.00 200.00 3292.50
TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges
TOTAL
Rate Per Mater
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved Rate of
Rs.43.90
per Rft
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
RATE ANALYSIS
Electrical WORKS Description: Providing & Fixing Kit Type Switches sheet & plastic board imported.
Unit of Rate Per No Cost of Material Labour charges 5 No. 165.00 10.00 175.00 6 No. 198.33 10.00 208.33 8 No. 248.33 10.00 258.33
Total
ASSISTANT ENGINEER
SUB-ENGINEER
Approved
Project Director
Coper Conducter Cables for service connection PVC Sheeted armoured 4 core
70mm Unit of Rate Per Rft. Cable (Pakistan-New age) 70mm Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 1.00 Ft. Ft. 270.00 25.00 Per Rft. Per Rft.
Total
Total
Rate Per Rft. 350/-
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Electric Work
Description
Shifting of Transformer of education faculty with in distance of 300' i/c disconecting,demolishing H.T steel wire and other electrical asessories like jumpers fuses insulators ic lowering of transformer with chain cupy in the supervision of experts and skilled labour i/c errection and placing transformer at new site with providing same actvity as mension above i/c errection of new steel cables jumpers fuses stays etc complete in all respect.i/c Providing & Fixing H.T Galvanized Steel structure single pole as per WAPDA specifications. a) H.T. Pole 35' Height with Concrete Foundation (1:2:4), 2' x 2' x 6' size using Angle Iron 2" x 2" x 5/32" size for Legs and Angle Iron 1.375" x 1.375" x 1/8" size for Bracing as per Standard Drawings. Unit Shifting of Transformer=1 No. Disconecting and demolishing of H.T wire i/c old electrical asessories like jumpers insulators fuses etc. 1.00 Job 4000.00 Per job lowering of transformer with chain cupy in the supervision of experts and skilled labour Shifting of transformer with in Distance of 300 ft. in the supervision of experts and skilled labour Errection of transformer with chain cupy in the supervision of experts and skilled labour at new site Errection of electrical asessories jumpers insulators fuses and H.T wire in the supervision of experts and skilled labour at new site Providing & Fixing H.T Galvanized Steel structure single pole as per WAPDA specifications. a) H.T. Pole 35' Height with Concrete Foundation (1:2:4), 2' x 2' x 6' size using Angle Iron 2" x 2" x 5/32" size for Legs and Angle Iron 1.375" x 1.375" x 1/8" s ize for Bracing as per Standard Drawings. Add 10% Contractor Profit Add 10% Overhead Charges Rate Shifting of Transformer=1 No.
1.00
Job
8000.00
Per job
1.00
Job
3000.00
Per job
1.00
Job
8000.00
Per job
1.00
Job
5000.00
Per job
1.00
Job
13000.00
Per job
Total
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
Rate Per No. 36/-
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Unit of Rate Per No Market Rate Labour charges Add 10% Contractor Profit Add 10% Overhead Charges
1 1
No No
SUB-ENGINEER
ASSISTANT ENGINEER
Approved
Project Director
Unit of Rate Per No Market Rate Labour charges Add 10% Contractor Profit Add 10% Overhead Charges
1 1
No No
SUB-ENGINEER
ASSISTANT ENGINEER
Approved
Project Director
Unit of Rate Per No Market Rate Labour charges Add 10% Contractor Profit Add 10% Overhead Charges
1 1
No No
SUB-ENGINEER
ASSISTANT ENGINEER
Approved
Project Director
Unit of Rate Per No Market Rate Labour charges Add 10% Contractor Profit
1 1
No No
SUB-ENGINEER
ASSISTANT ENGINEER
Approved
Project Director
Unit of Rate Per No. Market Rate Labour charges Add 10% Contractor Profit Add 10% Overhead Charges
1 1
No. No.
SUB-ENGINEER
ASSISTANT ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Unit of Rate Per No. Market Rate Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1 1 No. No. 1,992.00 Per No 50.00 Per No Total
SUB-ENGINEER
ASSISTANT ENGINEER
Approved
Project Director
Unit of Rate Per No. Cost of Fan Cost of Dimmer Labour charges Add 10% Contractor Profit Add 10% Overhead Charges
1 1 1
SUB-ENGINEER
ASSISTANT ENGINEER
Approved
Project Director
Unit of Rate Per No. Cost of Fan Cost of Dimmer Labour charges Add 10% Contractor Profit Add 10% Overhead Charges
1 1 1
SUB-ENGINEER
ASSISTANT ENGINEER
Approved
Project Director
P/F marble tile 12"x12"x3/8" fency brance with grey cement, grouted with white cement including colour pig to match with the colour of tiles, with PCC 2" thick 1:2:4 rubbing and chemical polishing complete in all resp as pproved by the Engineer Incharge.
Unit of Rate Per No. Cost of Fan Cost of Dimmer Labour charges Add 10% Contractor Profit Add 10% Overhead Charges
1 1 1
SUB-ENGINEER
ASSISTANT ENGINEER
Approved
Project Director
Description
Total
Add 10% Contractor Profit Add 10% Overhead Charges
Total
Say
SUB-ENGINEER
ASSISTANT ENGINEER
Unit of Rate Per No. Cost of Lamp Cost of Holder Labour charges Add 10% Contractor Profit Add 10% Overhead Charges
1 1 1
SUB-ENGINEER
ASSISTANT ENGINEER
Approved
Project Director
Description
10 Amp Circuit Breaker 6 Amp Circuit Breaker Labour charges Add 10% Contractor Profit Add 10% Overhead Charges
2 4 1
No No No
SUB-ENGINEER
Approved
Project Director
RATE ANALYSIS
Electric Work
Description
Unit of Rate Per No Market rate Energy saver Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 1.00 1.00 No No No 400.00 125.00 70.00 Per No Per No Per No
Total
Total
ASSISTANT ENGINEER
SUB-ENGINEER
Approved
Project Director
Civil Works
Description Supply & complete Eraction of Bus shed consisting of M.S square Pipe 3"x1.5", 18 SWG for bracings of short
span at 5' center to center as per drawings and M.S squre pipe 1.5"x1.5", 18SWG for bracing of long span 5' Unit of Rate = Per Sft Cost of Material
5" dia M.S Pipe 1/4" thick M.S Pipe 3"x1.5", 18 SWG M.S Pipe 1.5"x1.5",, 18 SWG M.S Plate 1'x1'x1/2" thick Fiber Glass 3 mm thick P.C.C. 1:2:4 Painting 3 coats on pipes Labour charges Add 10% Contractor Profit Add 10% Overhead Charges
Per Rft Per Rft Per Rft Per Kg Per Sft Per Cft
Total
SUB-ENGINEER
ASSISTANT ENGINEER
Approved
Project Director
Per Rft Per Rft Per Rft Per Kg Per Sft Per Cft
Total
SUB-ENGINEER
ASSISTANT ENGINEER
Approved
Project Director
Total
Total
450.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Plumbing Work
Description
Total
Add 10% Contractor Profit Add 10% Overhead Charges
Total
960.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Providing & Fixing Chromium plated double bib cock 1/2" dia (Best quality)
Unit of Rate Per No Cost of Material Labour 1.00 1.00 No No 425.00 25.00 Each Each
Total
Add 10% Contractor Profit Add 10% Overhead Charges
Total
540.00
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Providing & Fixing Chromium plated wall shower SONEX company including all specials as
Unit of Rate Per No Wall Shower SONEX Company Labour Charges 1.00 1.00 No No 2800.00 200.00 Each Each
Total
Add 10% Contractor Profit Add 10% Overhead Charges
Total
#####
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
PUR
SUB-ENGINEER
PUR
ng of transformer
4000.00
8000.00
3000.00
8000.00
5000.00
SUB-ENGINEER
PUR
65.00 95.00 65.00 20.00 20.00 50.00 315.00 31.50 31.50 378.00
SUB-ENGINEER
PUR
SUB-ENGINEER
PUR
SUB-ENGINEER
pur
1350.00 Rs.1,350.00
ASSISTANT ENGINEER
pur
ASSISTANT ENGINEER
pur
Rs.250
ASSISTANT ENGINEER
pur
14.60 175.20
Rs.175
ASSISTANT ENGINEER
pur
Rs.690
EXECUTIVE ENGINEER
pur
Rs.2,450
ASSISTANT ENGINEER
pur
Rs.1,900
ASSISTANT ENGINEER
pur
Rs.1,900
ASSISTANT ENGINEER
pur
hite cement including colour pigment cal polishing complete in all respects
Rs.1,900
ASSISTANT ENGINEER
walpur
Rs.3,620
ASSISTANT ENGINEER
pur
Rs.310
ASSISTANT ENGINEER
walpur
850.00 1050.00
SUB-ENGINEER
PUR
SUB-ENGINEER
152,100.00 66,915.00 34,200.00 13,000.00 411,264.00 23,938.20 20,080.00 120,000.00 841,497.20 84,149.72 84,149.72 #########
275.00
ASSISTANT ENGINEER
######### 456,975.00 206,460.00 108,000.00 ######### 176,774.40 125,000.00 750,000.00 ######### 553,120.94 553,120.94 #########
295.00
ASSISTANT ENGINEER
SUB-ENGINEER
SUB-ENGINEER
SUB-ENGINEER
SUB-ENGINEER
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Total
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
46,225.00 105,787.50
1,600.00 5,000.00
101.38
SUB-ENGINEER
ASSISTANT ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Each
G. Total
SUB-ENGINEER
ASSISTANT ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Each
G. Total
SUB-ENGINEER
ASSISTANT ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Each
G. Total
SUB-ENGINEER
ASSISTANT ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
Each
G. Total
SUB-ENGINEER
ASSISTANT ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
P/F Wardrobe.
Unit of Rate Per = 100 Cft Sft Material 3'x7' M.S pipe 3"x1.5" 18 SWG Labour welding Commercial Win Board 3/4" thick 10% Wastage Deodar Wood 30% Wastage Aluminium Rod Bracket Tower Bolt Lock 808 Handle Hardware Charges Paint Labour charges Add 10% Contractor Profit Add 10% Overhead Charges
20.00 Rft 21.00 2.00 23.00 0.04 0.01 0.05 3.00 2.00 2.00 1.00 1.00 Sft Sft Cft Cft Rft No No No No
630.00 100.00
626.75
Total
Rate Per Sft 145.00
80.00 36.00 40.00 40.00 35.00 20.00 200.00 420.00 315.00 2542.75 254.28 254.28 3051.30
ASSISTANT ENGINEER
SUB-ENGINEER
EXECUTIVE ENGINEER
Project Director
SAY
Sub-Engineer
Assistant Engineer
Executive Engineer
Approved
Project Director
Unit of Rate %Sft Cost of Cement Cost of Sand Labour Charges 1.00 Bag 3.00 Cft 100.00 Sft 250.00 Per Bag 9.00 Per Cft 1.43 Per Sft Total 250.00 27.00 143.00 420.00 42.00 42.00 504.00
SAY
504.00
Sub-Engineer
Assistant Engineer
Executive Engineer
Approved
Project Director
G. Total
Rate Per Sft = 2992.32/ 17.50
SAY
SUB-ENGINEER
ASSISTANT ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director
G. Total
Rate Per Sft = 2992.32/ 24.50
SAY
SUB-ENGINEER
ASSISTANT ENGINEER
EXECUTIVE ENGINEER
Approved
Project Director