You are on page 1of 242

ISLAMIA UNIVERSITY BAHAWALPUR

RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING & FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.
Description
1.

Supply and Eraction of duct work for wiring (Dura Adamgee) with rawal plugs,Screws and specials complete in all respects.

Unit of Rate = Per Rft

i) 16 x 16 mm
Cost of Material Labour Charages for Fixing Add 10% Contractor Profit

11.00 Per Rft 2.00 Per Rft Total Total

11.00 2.00 13.00 1.30 14.30 14.00 2.00 16.00 1.60 17.60 38.00 2.00 40.00 4.00 44.00

Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft

ii) 16 x 25 mm
Cost of Material Labour Charages for Fixing Add 10% Contractor Profit

14.00 Per Rft 2.00 Per Rft Total Total

iii) 40 x 40 mm
Cost of Material Labour Charages for Fixing Add 10% Contractor Profit

38.0 Per Rft 2.00 Per Rft Total Total

Sub Engineer

Assistant Engineer

Executive Engineer

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING & FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.
Description
2 Supply and Eraction deodar wood box 9"x4"x3" deep I/c bekolite sheet 4mm thick I/c making holes for switches .

Unit of Rate = Each


Cost of Deodar wood Board 9"x4"x3" Cost of Bekolite sheet 4mm thick 9"x4" Labour Charages for Fixing Add 10% Contractor Profit 1 1 1

No No No Total Total

40 30 15

40.00 30.00 15.00 85.00 8.50 93.50

Each Each Each Each Each Each

Sub Engineer

Assistant Engineer

Executive Engineer

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING & FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.
Description 3 Supply and Eraction 2 Pins 10/15 AMPS Socket imported (TURKY) complete in all respects. Unit of Rate = Each Cost of Material 1 No 65 65.00 Each Labour Charages for Fixing 1 No 5 5.00 Each Total 70.00 Each
Add 10% Contractor Profit

Total

7.00 Each 77.00 Each

Sub Engineer

Assistant Engineer

Executive Engineer

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING & FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.
Description 4 Supply and Eraction Switches 10/15 AMPS Piano type (Best quality) Unit of Rate = Each Cost of Material 1 No 20 20.00 Each Labour Charages for Fixing 1 No 5 5.00 Each Total 25.00 Each
Add 10% Contractor Profit

Total

2.50 Each 27.50 Each

Sub Engineer

Assistant Engineer

Executive Engineer

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING & FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.
Description
5 Supply and Eraction Switche,plug combined Power plug 30/35 AMPS (Bush Company)

Unit of Rate = Each


Cost of Material Labour Charages for Fixing Add 10% Contractor Profit 1 1

No No Total Total

220 10

220.00 10.00 230.00 23.00 253.00

Each Each Each Each Each

Sub Engineer

Assistant Engineer

Executive Engineer

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING & FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.
Description
6 Supply and Eraction distribution board (D.B) 2'x1.50' Size with following detail.

100 AMPS MCCB 3-Phase 240 Volts Circuit breaker 20 AMPS MCB 1-Phase 240 Volts Circuits breaker 10 AMPS MCB 1-Phase 240 Volts Circuits breaker 6 AMPS MCB 1-Phase 240 Volts Circuits breaker All Circuit breakers Terasaki/Mitsubishi (Black) Japan to be used. Iron Box 2'x1.50' with Stove enameled paint. Unit of Rate = Each Cost of Iron Box 2'x1.50' 1 No 1800 1800.00 Cost of 100 AMPS 3-Phase Circuit breaker 1 No 2850 2850.00 Cost of 20 AMPS 1-Phase Circuit breaker 2 No 225 450.00 Cost of 10 AMPS 1-Phase Circuit breaker 12 No 225 2700.00 Cost of 6 AMPS 1-Phase Circuit breaker 4 No 225 900.00 Cost of Thimbles 9 No 20 180.00 Labour Charages for Fixing 1 No 400 400.00 Total 9280.00
Add 10% Contractor Profit

Each Each Each Each Each Each Each Each 928.00 Each

Total

10208.00 Each

Sub Engineer

Assistant Engineer

Executive Engineer

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING & FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.
Description
7 Supply and Eraction Ceiling lights 2'x2' size with reflective grill phlips rod 2' size 20 Watt,

Philps Chock 40 Watt,Phlips Startar 20 Watt Patty Fitting (Frame of light 2'x2') Pak light/Equaliant i/c hanging arrangement. Unit of Rate = Each
Cost of Light with Chock, Rod & Starter complete Labour Charages for Fixing Add 10% Contractor Profit 1 1

No No Total Total

1300 100

1380.00 100.00 1480.00 148.00 1628.00

Each Each Each Each Each

Sub Engineer

Assistant Engineer

Executive Engineer

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING & FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.
Description Providing & Fixing Wall Bracket Fan with Plastic Body (Pak Fan, G.F.C or Royal Co. of 18" Sweep. Complete in all respects. Unit of Rate = Each
Cost of Fan Labour Charages for Fixing Add 10% Contractor Profit 1 1

No No Total Total

1500 50

1500.00 50.00 1550.00 155.00 1705.00

Each Each Each Each Each

Sub Engineer

Assistant Engineer

Executive Engineer

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS FOR UP-GRADITION OF LABS, ELECTRIC WIRING & FALSE CIELING FOR VIROUS COMPUTER LABS AT B.J. CAMPUS.
Description Providing & Fixing False ciling of plaster of paris with hanging arrangements and design and samples as approved by the Engineer Incharge Complete in all respects. Unit of Rate = Per Sft
Cost of Material Labour Charages for Fixing Add 10% Contractor Profit 1 1

Sft Sft Total Total

12.00 4.00

12.00 4.00 16.00 1.60 17.60

Each Each Each Each Each

Sub Engineer

Assistant Engineer

Executive Engineer

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS FOR PROVIDING & FIXING ELECTRIC LINE FOR CENTRAL LIBRARY AT B.J. CAMPUS.
Description
1.

Supply and Eraction of duct work for wiring (Dura Adamgee) with rawal plugs,Screws and specials complete in all respects.

Unit of Rate = Per Rft

i) 16 x 16 mm
Cost of Material Labour Charages for Fixing Add 10% Contractor Profit

11.00 Per Rft 2.00 Per Rft Total Total

11.00 2.00 13.00 1.30 14.30 14.00 2.00 16.00 1.60 17.60 38.00 2.00 40.00 4.00 44.00

Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft

ii) 16 x 25 mm
Cost of Material Labour Charages for Fixing Add 10% Contractor Profit

14.00 Per Rft 2.00 Per Rft Total Total

iii) 40 x 40 mm
Cost of Material Labour Charages for Fixing Add 10% Contractor Profit

38.0 Per Rft 2.00 Per Rft Total Total

Sub Engineer

Assistant Engineer

Executive Engineer

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS FOR PROVIDING & FIXING ELECTRIC LINE FOR CENTRAL LIBRARY AT B.J. CAMPUS.
Description
2 Supply and Eraction deodar wood box 9"x4"x3" deep I/c bekolite sheet 4mm thick I/c making holes for

Unit of Rate = Each


Cost of Deodar wood Board 9"x4"x3" Cost of Bekolite sheet 4mm thick 9"x4" Labour Charages for Fixing Add 10% Contractor Profit 1 1 1

No No No Total Total

40 30 15

40.00 30.00 15.00 85.00 8.50 93.50

Each Each Each Each Each Each

Sub Engineer

Assistant Engineer

Executive Engineer

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS FOR PROVIDING & FIXING ELECTRIC LINE FOR CENTRAL LIBRARY AT B.J. CAMPUS.
Description 5 Supply and Eraction Power plug, Switche Plug combined 30/35 AMPS (Bush Company) including shoe 3 pins 20 AMPS Unit of Rate = Each Cost of Material 1 No 270 270.00 Each Labour Charages for Fixing 1 No 10 10.00 Each Total 280.00 Each
Add 10% Contractor Profit

Total

28.00 Each 308.00 Each

Sub Engineer

Assistant Engineer

Executive Engineer

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS FOR PROVIDING & FIXING ELECTRIC LINE FOR CENTRAL LIBRARY AT B.J. CAMPUS.
Description 6 Supply and Eraction distribution board (D.B) 18"'x15" Size with following detail. 100 AMPS MCCB 3-Phase 240 Volts Circuit breaker 20 AMPS MCB 1-Phase 240 Volts Circuits breaker All Circuit breakers Terasaki/Mitsubishi (Black) Japan to be used. Iron Box 18"x15" with Stove enameled paint. Unit of Rate = Each Cost of Iron Box 18"x15" 1 No 1350 1350.00 Each Cost of 100 AMPS 3-Phase Circuit breaker 1 No 2850 2850.00 Each Cost of 20 AMPS 1-Phase Circuit breaker 8 No 225 1800.00 Each Labour Charages for Fixing 1 No 400 400.00 Each Total 6400.00 Each
Add 10% Contractor Profit 640.00 Each

Total

7040.00 Each

Sub Engineer

Assistant Engineer

Executive Engineer

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS FOR PROVIDING & FIXING ELECTRIC LINE FOR CENTRAL LIBRARY AT B.J. CAMPUS.
Description
Supply and Eraction of "U" Clamp for Shackle insulators with Nut bolts and Pins etc complete.

Unit of Rate = Each

Cost of "U" Clamp and Nut bolts & Pins Cost of Labour for fixing Add 10% Contractor Profit

1 1

No No Total Total

130 10

130.00 10.00 140.00 14.00 154.00

Each Each Each Each Each

Sub Engineer

Assistant Engineer

Executive Engineer

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS FOR PROVIDING & FIXING ELECTRIC LINE FOR CENTRAL LIBRARY AT B.J. CAMPUS.
Description
Supply and Eraction of pole stay including enchor rod 3/4" dia with MS Plate galvanized as per Wapda standard with concrete block (1:2:4) 2' dia 6" thick including stay wire complete in all respects.

Unit of Rate = Each


Cost of Stay Rod 3/4" dia with MS Plate Cost of Stay Wire Cost of Concrete Block 2' dia 6" thick Labour charges for fixing Add 10% Contractor Profit 1 1 1 1

No No No No Total Total

400 600 300 400

400.00 600.00 300.00 400.00 1700.00 170.00 1870.00

Each Each Each Each Each Each Each

Sub Engineer

Assistant Engineer

Executive Engineer

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS
CIVIL WORKS
Description

Excavation in foundation of building


Unit of Rate = 1000 Cft

Labour Charages:
Excavation TNP Charges Add 10% Contractor Profit Add 10% Overhead Charges

1000.00 @ 1000.00 @ Total

148.00 % Cft 45.00 %o Cft

Total
Rate Rs. 1830/- %o Cft

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved for

Rs.1,830.00

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS

CIVIL WORKS
Description

Cement Concrete Brick or Stone Ballast 1.5" to 2" gauge 1:6:12


Unit of Rate = 100 Cft

Material Cost:
Brick Ballast Cement Sand 97.00 Cft 6.50 Bag 48.00 Cft 9.00 Per Cft 333.00 Per Bag 9.00 Per Cft

Total Labour Charages:


TNP Charges

100.00 Cft 100.00 Cft Total

700.00 % Cft 81.00 % Cft

Add 10% Contractor Profit Add 10% Overhead Charges

Total
Say Rs.5100/-

ASSISTANT ENGINEER

SUB-ENGINEER

DEPUTY PROJECT DIRECTOR

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Spraying antitermite

Unit of Rate = 100 Cft

Per Sft. (for 3oo Sft) 1 Ltr 100.00 Sft 100.00 Sft 310.00 Per Lit 10.00 100 Sft 15.00 100 Sft

Material Cost:
TNP Charges

Labour Charages:

Total

Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft. Rs. 1.24 1.53

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS
CIVIL WORKS
Description

Pacca Brick work in foundation and plinth. 1:6


Unit of Rate = 100 Cft 100 Cft

Material Cost:
Bricks 5% Wastage 1350.00 68.00 1418.00 Nos

2200.00 1000 No

Cement Sand TNP

3.50 Bag 26.00 Cft

333.00 P/Bag 9.00 P/Cft

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Say

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS
CIVIL WORKS
Description

Pacca Brick work in Ground Floor 1:5


Unit of Rate = 100 Cft 100 Cft

Material Cost:
Bricks 5% Wastage 1350.00 68.00 1418.00 Nos 4.00 Bag 26.00 Cft

2200.00 1000 No 333.00 P/Bag 9.00 P/Cft

Cement Sand TNP

Labour Charges:

Total
Add 10% Contractor Profit Add 10% Overhead Charges

Total
Say

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS
CIVIL WORKS
Description

Damp Proof Course 2" thick I/c bitumen coating and polythene sheet
Unit of Rate = 100 Cft 100 Sft

Material Cost:
Crush Cement Sand Bitumen Polythene Sheet 500 guage TNP 15.00 2.75 28.00 10.00 100.00 Cft Bag Cft Kg Sft 28.00 333.00 9.00 45.90 1.00 Per Cft P/Bag P/Cft Per Kg Per Sft

Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total Say

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Reinforced Cement Concrete in foundation 1:2:4


Unit of Rate = 100 Cft Per Cft

Material Cost:
Crush 5% Wastage Total Cement Sand TNP 88.00 4.00 92.00 17.60 44.00 Cft Cft Cft Bag Cft

30.00 Per Cft 325.00 P/Bag 9.00 P/Cft

Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Cft 121.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Reinforced Cement Concrete in foundation 1:1.5:3


Unit of Rate = 100 Cft Per Cft

Material Cost:
Crush 5% Wastage Total Cement Sand TNP 84.00 4.00 88.00 22.40 42.00 Cft Cft Cft Bag Cft

30.00 Per Cft 325.00 P/Bag 9.00 P/Cft

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Cft 139.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS

Description

Reinforced Cement Concrete in foundation 1:2:4


Unit of Rate = 100 Cft

Material Cost:
Crush 5% Wastage Total Cement Sand TNP 88.00 4.00 92.00 17.60 44.00 Cft Cft Cft Bag Cft

30.00 Per Cft 325.00 P/Bag 9.00 P/Cft

Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Cft 121.00

ASSISTANT ENGINEER

SUB-ENGINEER

DEPUTY PROJECT DIRECTOR

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Reinforced Cement Concrete in Ground Floor 1:1.5:3


Unit of Rate = 100 Cft Per Cft

Material Cost:
Crush 5% Wastage Total Cement Sand TNP Shuttering Charges 84.00 4.00 88.00 22.40 42.00 Cft Cft Cft Bag Cft

30.00 Per Cft 325.00 P/Bag 9.00 P/Cft

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Cft 175.00

ASSISTANT ENGINEER

SUB-ENGINEER

DEPUTY PROJECT DIRECTOR

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS

Description

Reinforced Cement Concrete in Ground Floor 1:2:4


Unit of Rate Per Cft

Material Cost:
Crush 5% Wastage Total Cement Sand TNP Shuttering Charges 88.00 4.00 92.00 17.60 44.00 Cft Cft Cft Bag Cft

23.00 Per Cft 180.00 P/Bag 9.00 P/Cft

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total Rate Per Cft 111.36

ASSISTANT ENGINEER

SUB-ENGINEER

DEPUTY PROJECT DIRECTOR

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Fabrication of mild steel (40 grade) Prime Steel, Afco Steel

Unit of Rate = 100 Cft

Per kg

Material Cost:
Steel 5% Wastage Total Steel Binding Wire TNP 100.00 5.00 105.00 3.00 Kg Kg Kg Kg

3880.00 100 Kg 70.00 Per Kg

I Labour Charges: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Kg 55.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Fabrication of mild steel (40 grade)


Unit of Rate Per kg

Material Cost:
Steel 5% Wastage Total Steel Binding Wire TNP 100.00 5.00 105.00 3.00 Kg Kg Kg Kg

3200.00 100 Kg 60.00 Per Kg

I Labour Charges: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Kg 46.08

ASSISTANT ENGINEER

SUB-ENGINEER

DY. PROJECT DIRECTOR

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Fabrication of High Tensile steel (60 grade)


Unit of Rate = 100 Cft Per kg

Material Cost:
Steel 5% Wastage Total Steel Binding Wire TNP 100.00 5.00 105.00 3.00 Kg Kg Kg Kg

4200.00 100 Kg 70.00 Per Kg

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Kg 59.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Cement plaster 1:5


Unit of Rate = 100 Cft

1/2" thick 0' to 20' height


Per Sft

Material Cost:
Cement Sand TNP 1.00 Bag 3.00 Cft 333.00 Per Bag 9.00 Per Cft

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft 12.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS
CIVIL WORKS
Description

Cement plaster 1:3


Unit of Rate = 100 Cft

3/8" thick
Per Sft

Material Cost:
Cement Cement for neru Sand TNP 1.00 0.25 1.25 2.50 Bag Bag Bag Cft

333.00 Per Bag 9.00 Per Cft

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft 12.50

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Cement plaster 1:5


Unit of Rate = 100 Cft

3/4" thick
Per Sft

Material Cost:
Cement Sand TNP 1.50 Bag 4.00 Cft 310.00 Per Bag 8.00 Per Cft

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft 12.86

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

DEPUTY PROJECT DIRECTO

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Dry brick ballast 1.5" to 2" gauge


Unit of Rate = 100 Cft Per Cft 100.00 Cft 12.00 Per Cft

Material Cost:
TNP

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Cft 16.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Polythene Sheet 500 Gauge


Unit of Rate = 100 Cft Per Sft 100.00 Sft 1.00 Per Sft

Material Cost: I Labour Charages:

Total
Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft 1.32

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS

CIVIL WORKS
Description

Vertical DPC 1:3


Unit of Rate = 100 Cft

1/2" thick with 2 coat bitumen


Per Sft

Material Cost:
Cement Sand Bitumen TNP 1.25 Bag 3.00 Cft 16.00 Kg 333.00 Per Bag 9.00 Per Cft 45.90 Per Kg

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft 22.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Rubber Water Stopper 10" wide 1/4" thick

Unit of Rate = 100 Cft

Per Rft 1.00 Rft 50.00 Per Rft

Material Cost: I Labour Charages:

Total
Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Rft 62.40

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Bitumen Coating 20 Lbs per 100 Sft.


Unit of Rate = 100 Cft Per Sft 16.00 Lbs 1.00 ltr 25.00 Per Lbs 40.00 Per Ltr

Material Cost Bitumen: Carocine oil TNP I Labour Charages:

Total
Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per sft 10.50

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

First Class Brick walling 4.5" thick 1:3 hoop iron 12" apart
Unit of Rate = 100 Cft 100 Sft

Material Cost:
Bricks 5% Wastage 518.00 26.00 544.00 Nos 2.25 Bag 13.00 Cft 100.00 Rft

2200.00 1000 No 333.00 P/Bag 9.00 P/Cft 5.00 Per Rft

Cement Sand Hoop Iron

TNP

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft. 40.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR


RATE ANALYSIS
CIVIL WORKS
Description

Spray plaster
Unit of Rate = 100 Cft Per Sft

Material Cost:
Cement Marble Chips TNP 1.00 Bag 5.00 Bag 333.00 Per Bag 25.00 Per Bag

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft 13.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Mosaic Dado or Skirting 1/2" thick (grey cement)


Unit of Rate = 100 Cft 1 Material Cost: Cement Sand TNP 1.25 Bag 3.00 Cft 333.00 Per Bag 9.00 Per Cft Per Sft

I Labour Charages: Total


2 Material Cost: Cement Marble Chips Marble Powder TNP 3.00 Bag 8.00 Bag 2.00 Bag 333.00 Per Bag 25.00 Per Bag 25.00 Per Bag

I Labour Charages:
Griding Charges Polish Charges

Total Gramd Total A+B


Add 10% Contractor Profit

Add 10% Overhead Charges

Total
Rate Per Sft 38.50

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Extra Labour for Arch Work


Unit of Rate = 100 Cft Per Cft

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Cft 6.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Pacca Brick work in foundation and plinth. 1:3


Unit of Rate = 100 Cft 100 Cft

Material Cost:
Bricks 5% Wastage 1350.00 68.00 1418.00 Nos 6.00 Bag 25.00 Cft

2200.00 1000 No 333.00 P/Bag 9.00 P/Cft

Cement Sand TNP

Labour Charges: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total Say

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Earth filling under floor


Unit of Rate = 100 Cft 1000 Cft

1 Surplus earth from foundation TNP

1000.00 Cft 1000.00 Cft

I Labour Charages:

Total
Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per 1000 Cft 1400.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Sand filling under floor


Unit of Rate = 100 Cft 1 sand TNP Per Cft 100.00 Cft 100.00 Cft 100.00 Cft 9.00 Per Cft

I Labour Charages:

Total
Add 10% Contractor Profit Add 10% Overhead Charges

Total Rate Per Cft.


11.5

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Brick on edge floor


Unit of Rate = 100 Cft 1 Material Brick 5% Wastage Per Sft

550.00 No 28.00 578.00 No 1.25 Bag 3.00 Cft 100.00 Sft 100.00 Cft

2200.00 Per 1000 333.00 Per Bag 9.00 Per Cft

Cement Sand TNP

I Labour Charages:

5.00 Per Sft

Total
Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft 26.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS

CIVIL WORKS
Description

Mosaic Floor 1.5" thick, 1" thick


Unit of Rate = 100 Cft 1 Material Cement Sand Crush Cement Powder Chips TNP Per Sft

1:2:4 1/2" Mosaic Topping

(100 Sft) 1:2:4

Mosaic toping

2.11 5.38 10.56 2.00 2.00 8.00

Bag Cft Cft Bag Bag Bag

333.00 9.00 28.00 333.00 25.00 25.00

Per Bag Per Cft Per Cft Per Bag Per Bag Per Bag

I Labour Charages: Griding Polish

100.00 Cft

8.00 Per Sft

Total
Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft 37.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

1/4" thick glazed coloured tile for Dado & Skirting.

Unit of Rate = 100 Cft 1 Material Tile 5% Wastage Cement Sand Cement TNP

Per Sft

(100 Sft) 100.00 5.00 105.00 1.50 3.00 Sft Sft Bag Cft 41.50 Per Sft 333.00 Per Bag 9.00 Per Cft

(Grey) White

I Labour Charages:

100.00 Sft

9.00 Per Sft

Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft 73.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description Providing and fixing cement jali 3''thick of 1:3 morter with steel wires at each edge ,
approved design and finished product from moulding patern, laid over 1:3 c/s morter for bonding with the structure i/c cuting finishing curing with entire satisfaction of engineer Incharge. Unit of Rate = 10 sft Cost of jali Carriage at site Cement morter 1:3 Mason Labour : 10.00 10.00 10.00 1.00 1.00 Sft Sft Sft Sft Sft 40.00 20.00 10.00 300.00 150.00 Per Sft Per Sft Per Sft Per Sft Per Sft

S.Total
Add 10% scafolding charges

Total
Add 10% Contractor Profit Add 10% Overhead Charges

Total

Rate per sft

SAY

ASSISTANT ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Marble Strip 1.5" x 3/8" size


Unit of Rate = 100 Cft 1 Material Marble strip Cement Sand TNP Per Rft

(100 Sft) (100 Rft) 100.00 Rft (Grey) 2.00 Per Rft

I Labour Charages:
Add 10% Contractor Profit Add 10% Overhead Charges

100.00 Rft

1.50 Per Rft

Total
Rate Per Rft 5.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Roof Insulation
Unit of Rate = 100 Cft 1 Material Tile 9"x4.5"x1.5" 5% Wastage Per Sft

(100 Sft) (100 Sft) 350.00 18.00 368.00 20.00 100.00 16.00 100.00 1.00 3.00

Bitumen Polythene Sheet 500 Gauge Earth jumbo lawn 1" thick Cement Sand TNP

No Lbs Sft Cft Sft Bag Cft

2200.00 25.00 1.00 3.00 30.00 333.00 9.00

Per 1000 Per Lbs Per Sft Per Cft Per Sft Per Bag Per Cft

I Labour Charages:
Add 10% Contractor Profit Add 10% Overhead Charges

100.00 Sft

4.15 Per Sft

Total
Rate Per sft 63.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Khurras on roof 2'x2'x4"


Unit of Rate = 100 Cft 1 Material Cement Crush Sand TNP Per No

0.30 Bag 1.20 Cft 0.60 Cft 1.00 No

333.00 Per Bag 28.00 Per Cft 9.00 Per Cft 93.00 Per No

I Labour Charages:
Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per No 290.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Bottom Khurras
Unit of Rate = 100 Cft 1 Material Cement Brick Crush Sand TNP Per No

0.50 42.00 2.00 2.00

Bag No Cft Cft

333.00 2200.00 28.00 9.00

Per Bag Per 1000 Per Cft Per Cft

Labour Charges:
Add 10% Contractor Profit Add 10% Overhead Charges

1.00 No

78.00 Per No

Total
Rate Per No 505.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Cost Iron Rain Water Down Pipe 4" dia


Unit of Rate = 100 Cft 1 Material (6 Rft) CI Pipe 4" dia (Tipu) Clamp Paint Cement TNP Per Rft

1.00 2.00 9.00 0.10

Pipe No Sft Bag

800.00 30.00 7.00 310.00

Per Pipe Per No Per Sft Per Bag

I Labour Charages:
Add 10% Contractor Profit Add 10% Overhead Charges

1.00 No

75.00 Per No

Total
Rate Per Rft 208/-

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur

RATE ANALYSIS
CIVIL WORKS
Description

Cost Iron Bend 4" dia


Unit of Rate = 100 Cft 1 Material CI bend 4" dia (Tipu) Paint Per No

I Labour Charages:
Add 10% Contractor Profit Add 10% Overhead Charges

1.00 No 2.00 Sft 1.00 No

190.00 Per No 7.00 Per Sft 30.00 Per No

Total
Rate Per No 281/-

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Solid Flush Door

Unit of Rate = 100 Cft 1 Material Pertal Wood 30% Wastage Deodar Wood 30% Wastage

Per Sft (7'x4') 2.24 0.67 2.91 0.08 0.02 0.10 56.00 2.00 8.00 2.00 2.00 1.00 3.00

Cft

600.00 Per Cft

Commercial Ply 5 mm thick Gelu Kick Plate Handle Finger Plate Tower Bolt Hinges Screws

Cft Sft Kg Rft No No No No

1600.00 15.00 50.00 20.00 15.00 25.00 30.00 25.00

Per Cft Per Sft Per Kg Per Rft Per No Per No Per No Per No

Labour Charges:
Add 10% Contractor Profit Add 10% Overhead Charges

28.00 Sft

20.00 Per Sft

Total
Rate Per Sft 162/-

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Safety Grill
Unit of Rate = 100 Cft 1 Material Angle Iron 1"x1"x1/8" Square Bar 3/8"x3/8" Labour for welding Per Sft (6'x6') 6.00 Kg 30.00 Kg 36.00 Sft 38.00 Per Kg 38.00 Per Kg 20.00 Per Sft

Paint Cement Crush Sand Labour for fixing at site Add 10% Contractor Profit Add 10% Overhead Charges

36.00 Sft

8.00 Per Sft

Total

Total
Rate Per Sft 86.70

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Sliding Bolt 10"/12"


Unit of Rate = 100 Cft Sliding Bolt Cromium Labour for fixing at site Total Add 10% Contractor Profit Add 10% Overhead Charges Per No 1.00 No 1.00 No 92.50 Per No 20.00 Per No

Total
Rate Per No 135.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Enamel Paint 3 Coat for doors and windows etc


Unit of Rate = 100 Cft Material (4'X7') Primer Paint Paint (ICI,Robilac) Tarbine Oil TNP Labour Total Add 10% Contractor Profit Add 10% Overhead Charges Per Sft

1.00 Qtr 1.00 Qtr 1.00 Qtr 28.00 Sft

35.00 Per Qtr 130.00 Per Qtr 10.00 Per Qtr 2.00 Per Sft

Total
Rate Per Sft ASSISTANT ENGINEER 10.00 SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Terrace Railing
Unit of Rate = 100 Cft Per Rft

Material (10 Rft) M.S Condute Pipe 2" dia 16 SWG M.S Bar 5/8"x5/8" M.S. Flat 1"x1/8" Labour for welding TNP Labour for fixing at site Total Add 10% Contractor Profit Add 10% Overhead Charges

10.00 29.00 2.00 10.00

Rft Kg Kg Rft

50.00 38.00 38.00 30.00

Per Rft Per Kg Per Kg Per Rft

Total
Rate Per Rft ASSISTANT ENGINEER 261.00 SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Cement Pointing Deep Struck Joint 1:2


Unit of Rate = 100 Cft Material (100 Sft) Cement Sand TNP Labour charges Total Add 10% Contractor Profit Add 10% Overhead Charges Per Sft

1.00 Bag 3.00 Cft 100.00 Sft

333.00 Per Bag 9.00 Per Cft 4.00 Per Sft

Total
Rate Per Sft ASSISTANT ENGINEER 10.00 SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Extra Cost for red oxide


Unit of Rate = 100 Cft Material (100 Sft) Red Oxide Pigment TNP Labour charges Total Add 10% Contractor Profit Add 10% Overhead Charges Per Sft

4.00 Kg 100.00 Sft

30.00 Per Kg 1.00 Per Sft

Total
Rate Per Sft ASSISTANT ENGINEER 2.00 SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Distempering of walls 3 Coat including preparation of Surface complete


in all respect.Colour Scheme as approved by the Engineer Incharge. Unit of Rate = 100 Cft Per Sft Material (100 Sft) Distemper T&P, Colour Change Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

0.50 G 100.00 Sft Total

Rs. Rs.

155.00 Per G 1.00 Per Sft

Total
Rate Per Sft. 225/100 = 2.25

SUB-ENGINEER

Deputy Project Director

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

White Washing 3 Coat


Unit of Rate = 100 Cft Material (100 Sft) Gelu Blue Powder TNP Labour charges Total Add 10% Contractor Profit Add 10% Overhead Charges Per Sft 5.00 Kg 2.00 Per Kg

100.00 Sft

0.50 Per Sft

Total
Rate Per Sft ASSISTANT ENGINEER 1.00 SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

P/F aluminium strip 3"x1/8" on Expension Joint


Unit of Rate = 100 Cft Material (10 Rft) Strip 3"x1/8" Screw/Rawal plug TNP Labour charges Total Add 10% Contractor Profit Add 10% Overhead Charges Per Rft

10.00 Rft

20.40 Per Rft

10.00 Rft

5.00 Per Rft

Total
Rate Per Rft ASSISTANT ENGINEER 34.00 SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Thermopore sheet 1-1/2" thick for expension joint


Unit of Rate = 100 Cft Material Thermopore 1-1/2" Labour charges Total Add 10% Contractor Profit Add 10% Overhead Charges Per Sft

1.00 Sft 1.00 Sft

8.20 Per Sft 1.00 Per Sft

Total
Rate Per Sft ASSISTANT ENGINEER 11.00 SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS

CIVIL WORKS
Description

6" Wide Curved Sheet on Expension Joint


Unit of Rate = 100 Cft Material Sheet 18 Swg Screw/Rawal Plug TNP Labour charges Total Add 10% Contractor Profit Add 10% Overhead Charges Per Rft

10.00 Rft

25.00 Per Rft

Total
Rate Per Rft ASSISTANT ENGINEER 40.00 SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Cement Concrete plain 1:2:4

Unit of Rate = 100 Cft Material (100 Cft) Cement Crush Sand TNP Labour charges

Per Cft

17.60 Bag 92.00 Cft 44.00 Cft

333.00 Per Bag 28.00 Per Cft 9.00 Per Cft

Total Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Cft ASSISTANT ENGINEER 120.00 SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

P/F Wardrobe.
Unit of Rate = 100 Cft Per Sft

Material 3'x7' M.S pipe 3"x1.5" 18 SWG Labour welding Commercial Win Board 3/4" thick 10% Wastage

20.00 Rft 21.00 Sft 2.00 23.00 Sft

32.15 Per Rft

27.25 Per Sft

Deodar Wood 30% Wastage Aluminium Rod Bracket Tower Bolt Lock 808 Handle Hardware Charges Paint Labour charges Total Add 10% Contractor Profit Add 10% Overhead Charges

0.04 0.01 0.05 3.00 2.00 2.00 1.00 1.00

Cft Cft Rft No No No No 1600.00 12.00 20.00 20.00 35.00 20.00 Per Cft Per Rft Per No Per No Per No Per No

42.00 Sft 21.00 Sft

10.00 Per Sft 15.00 Per Sft

Total
Rate Per Sft 146.00

SUB-ENGINEER

DEPUTY PROJECT DIRECTOR

Submitted for Approval

PROEJCT DIRECTOR

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

P/F STEEL GRATED DOOR.


Unit of Rate = 100 Cft Per Sft

Material 4'x7' M.S angle iron 1.5"x1.5"x3/16" M.S Sheet 1/16" Welding Labour Charges Red Oxide Paint Sliding Bolt. TNP Labour for fixing at site Total Add 10% Contractor Profit

25.00 30.00 55.00 55.00

Kg Kg Kg Kg

40.00 Per Kg 9.00 Per Kg 138.00 Each

2.00 No

Add 10% Overhead Charges

Total
Rate Per Sft 150.89

SUB-ENGINEER

DEPUTY PROJECT DIRECTOR

Approved

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Steel Windwos Openable


Unit of Rate = 100 Cft Per Sft

Material (6'x6') M.S Box pipe 2"x1.5" (16 SWG) M.S Box Pipe 1.5"x1" (16 SWG) M.S Box Ppipe 1/2"x1/2" (18 SWG) M.S Box Ppipe 3/8"x3/8" (18 SWG) M.S Flat 1"x1/8" M.S Flat 3/4"x1/8" 5 mm thick glass Hinges Handle Stay Rod Wire Gauze 24 SWG Painting Labour for welding Labour for fixing at site Add 10% Contractor Profit Add 10% Overhead Charges

48.00 72.00 72.00 72.00 72.00 48.00 36.00 16.00 4.00 8.00 36.00 108.00 36.00

Rft Rft Rft Rft Rft Rft Sft No No No Sft Sft Sft

25.00 20.00 10.00 8.00 5.00 4.00 30.00 20.00 20.00 25.00 15.00 10.00 29.00

Per Rft Per Rft Per Rft Per Rft Per Rft Per Rft Per Sft Per No Per No Per No Per Sft Per Sft Per Sft

Total
Rate Per Sft 300.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur


SNACK BARE OF ENGINEERING COLLEGE

RATE ANALYSIS
CIVIL WORKS
Description

Providing & Fixing Kitchen Cabinet


Unit of Rate = 100 Cft Size 3' x 7'

Material M.S pipe 3"x1.25" 18 SWG Labour welding Lamination Board 3/4" thick 10% Wastage Deodar Wood 30% Wastage Tower Bolt Lock 808 Handle Hardware Charges Paint Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

20.00 Rft 21.00 2.00 23.00 0.04 0.01 0.05 2.00 1.00 1.00 Sft Sft Cft Cft No No No

35.00 Per Rft

32.00 Per Sft

1600.00 18.00 32.00 15.00

Per Cft Per No Per No Per No

42.00 Sft 21.00 Sft Total

10.00 Per Sft 15.00 Per Sft

Total
Rate Per Cft 148.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Durocem Paint 3 Coat.


Unit of Rate = 100 Sft Material (100 Sft) Durocem Paint TNP Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

10.00 Kg 100.00 Sft Total

20.00 Per Kg 1.00 Per Sft

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur


Name of Work:Construction Faculty Hostel for Women at B.J.Campus RATE ANALYSIS
NON SCHEDULE CIVIL WORKS
Description

Providing & Fixing open able Wardrobe Commercial Vin Board 3/4" thick for A/C Openg duct.
Unit of Rate = P sft Materials 2.25x2.75' MS pipe 1.5''x1.5'' 18 SWG Labour rate welding Commercial Vin Board 3/4" thick Wooden Beading Tower Bolts Handle Labour charges Total Add 10% Contractor Profit Add 10% Overhead Charges

12.38 Rft 5.00 Sft LS 4.00 Nos 2.00 Nos

47.5 P.Rft LS 50.00 Per Sft 50.00 35.00 each 20.00 each

Total
RATE PSFT ASSISTANT ENGINEER RATE P.SFT RS= SUB-ENGINEER

EXECUTIVE ENGINEER

Project Director

Approved

Director Engineering

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

Cement plaster 1:5


Unit of Rate = 100 Cft

1/2" thick
Per Sft

Material Cost:
Cement Sand TNP 1.00 Bag 3.00 Cft 333.00 Per Bag 9.00 Per Cft

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft 13.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


CIVIL WORKS
Description

Cement plaster 1:3


Unit of Rate = 100 Cft

3/8" thick
Per Sft

Material Cost:
Cement Cement for neru Sand TNP 1.00 0.25 1.25 2.50 Bag Bag Bag Cft

333.00 Per Bag 9.00 Per Cft

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft 13.50

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


CIVIL WORKS
Description

1/4" thick mat coloured tile for floor.


Unit of Rate = 100 Cft 1 Material Tile 5% Wastage Cement Sand Cement TNP Per Sft

(100 Sft) 100.00 5.00 105.00 1.50 3.00 Sft Sft Bag Cft 40.70 Per Sft 333.00 Per Bag 9.00 Per Cft

(Grey) White

I Labour Charages:

100.00 Sft

9.00 Per Sft

Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft 72.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS

CIVIL WORKS
Description

Cement plaster 1:3


Unit of Rate = 100 Cft

3/4" thick
Per Sft

Material Cost:
Cement Sand TNP 1.25 Bag 3.00 Cft 333.00 Per Bag 9.00 Per Cft

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft 14.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


CIVIL WORKS
Description

Earth filling under floor lead 3 mile.


Unit of Rate = 1000 Cft Earth 1000.00 Cft 2.65 Cft

Labour Charges: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft ######

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


CIVIL WORKS
Description

Pacca Brick work in foundation and plinth. 1:5


Unit of Rate = 100 Cft 100 Cft

Material Cost:

Bricks 5% Wastage

1350.00 68.00 1418.00 Nos 4.00 Bag 26.00 Cft

2200.00 1000 No 333.00 P/Bag 9.00 P/Cft

Cement Sand TNP

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Say

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

DEPUTY PROJECT DIRECTO

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


CIVIL WORKS
Description

Cement pointing struck joint on walls up to 20' height ratio 1:2


Unit of Rate = 100 Cft Per Sft

Material Cost:
Cement Sand TNP 1.50 Bag 4.00 Cft 333.00 Per Bag 9.00 Per Cft

I Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Sft 14.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

DEPUTY PROJECT DIRECTO

Submitted for Approval

Project Director

The Islamia University of Bahawalpur

Construction of Administrative Block for University College of Engineering & Technology at Baghdad-ul-Jadeed Campus

RATE ANALYSIS
CIVIL WORKS
Description

Providing and fixing botiseana/fency marble for stair steps 3/4" thick with floating coat of cement over a bed of 3/4" thick cement sand mortar 1:2 including colour pigment to match with the colour of marble tiles, laid with cement sand mortor 1:2 rubbing and chemical polishing complete in all respects as directed and approved by the Engineer incharge.

Unit of Rate = 100 Cft 1 Cost of Morble 3/4" 2 Carriage

Per Sft 1.00 Sft 1.00 Sft 1.00 Sft 1.00 Sft 1.00 Sft 1.00 Sft 1.00 Sft 1.00 Sft 140.00 3.00 5.00 336.10 7.88 336.10 4.50 24.00 Total

3 Loading, unloading and stacking 4 Material Cost of Floating Coat (MRS July 2005) 5 Cost of Martor under marble 3/4" thick (MRS Jul 05) 6 Ratio 1:2 7 Cost of floating coat (MRS July 2005). 8 Cost of Pigment 9 Cost of Labour for fixing & chemical polishing (10+14)

Add 10% Contractor Profit on Items No. 1-3, 8 & 9 Add 10% over head charges on Items No. 1-4, 8 & 9 G. Total

SAY Rs.

ASSISTANT ENGINEER

SUB-ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur

Construction of Administration Block for University College of Engineering and Technology a Baghdad-ul-Jadeed Campus

RATE ANALYSIS
CIVIL WORKS
Description
Providing and fixing marble 3/4" thick 12" long 3" wide with pure chocklate colour with floating coat of cement over a bed of 3/4" thick cement sand mortar 1:2 over 1" thick PCC 1:2:4 Gray cement, including colour pigment to match with the colour of marble tiles, laid with cement sand mortor 1:2 rubbing and chemical polishing complete in all respects as directed and approved by the Engineer incharge.

Unit of Rate = 100 Cft 1 2 3 4 5 6 7 8 9 10

Per Rft 1.00 No. 1.00 No. 0.25 Sft 0.25 0.25 0.25 0.25 0.25 Sft Sft Sft Sft Sft 62.50 0.66 336.10 7.88 336.10 1103.90 4.50 24.00 Total

Cost of Morble 3"x12"x3/4" Wastage 3% Carriage Material Cost of Floating Coat (MRS July 2005) Cost of Martor under marble 3/4" thick (MRS Jul 05) Ratio 1:2 Cost of floating coat (MRS July 2005). Cost of PCC 1:2:4 1" thick (MRS July 2005) Cost of Pigment Cost of Labour for fixing & chemical polishing (10+14)

Add 10% Contractor Profit on Items No. 1-3, 9 & 10 Add 10% over head charges on Items No. 1-3, 9 & 10 G. Total

SAY Rs. 93.00 Per Rft

ASSISTANT ENGINEER

SUB-ENGINEER

DEPUTY PROJECT DIRECTOR

Approved

Project Director

The Islamia University of Bahawalpur

Construction of Administrative Block for University College of Engineering & Technology at

RATE ANALYSIS
CIVIL WORKS
Description

Providing and fixing botiseana/fency marble for stair steps 3/4" thick 36"-60"/13.5" with floating coat of cement over a b of 3/4" thick cement sand mortar 1:2 including colour pigment to match with the colour of marble tiles, laid with cement sand mortor 1:2 rubbing and chemical polishing complete in all respects as directed and approved by the Engineer incharge. Unit of Rate = 100 Cft 1 2 3 4 5 Per Sft 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Sft Sft Sft Sft Sft Sft Sft Sft 135.00 3.00 5.00 336.10 7.88 336.10 4.50 10.00 Total

Cost of Marble 3/4" thick 36"-60"/13.5" i/c chemical polishing

Carriage Loading, unloading and stacking Material Cost of Floating Coat (MRS July 2005) Cost of Martor under marble 3/4" thick (MRS Jul 05) Ratio 1:2 6 Cost of floating coat (MRS July 2005). 7 Cost of Pigment 8 Cost of Labour for fixing & chemical polishing (10+14)

Add 10% Contractor Profit on Items No. 1-3, 7 & 8 Add 10% over head charges on Items No. 1-4, 7 & 8 G. Total

SAY Rs.

ASSISTANT ENGINEER

SUB-ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description
Providing and fixing barbed wire fencing on compound 'wall, consisting of 1"x1"x3/16" (40x40x5 mm), angle iron post 3 ft. (990 mm) long, 5 to 6 ft. (1500 to 1800 mm) centre to centre, embedded in cement concrete 1:4:8, base of size 9"x9"x12" (225x225x3 Unit of Rate = 100 Cft Sliding Bolt Cromium Labour for fixing at site Total Add 10% Contractor Profit Add 10% Overhead Charges Per No 1.00 No 1.00 No 92.50 Per No 20.00 Per No

Total
Rate Per No 135.00

SUB-ENGINEER

ASSISTANT ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

LPUR

1480.00 45.00 1525.00 152.50 152.50 1830.00

SUB-ENGINEER

1000 Cft

873.00 2164.50 432.00 3469.50 700.00 81.00 4250.50

425.05 425.05 5100.60

SUB-ENGINEER

awalpur

103.00 10.00 15.00 128.00

12.80 12.80 153.60

SUB-ENGINEER

WALPUR

3119.60

1165.50 234.00 148.00 1000.00 5667.10 566.71 566.71 6800.52 6800.00

SUB-ENGINEER

WALPUR

3119.60 1332.00 234.00 200.00 948.00

5833.60 583.36 583.36 7000.32 7000.00

SUB-ENGINEER

WALPUR

420.00 915.75 252.00 459.00 100.00 50.00 400.00 2596.75 259.68 259.68 3116.10 3116.00

SUB-ENGINEER

awalpur

2760.00 5720.00 396.00 200.00 1000.00 10076.00 1007.60 1007.60 12091.20

SUB-ENGINEER

awalpur

2640.00 7280.00 378.00 200.00 1100.00 11598.00 1159.80 1159.80 13917.60

SUB-ENGINEER

alpur

2760.00 5720.00 396.00 200.00 1000.00 10076.00 1007.60 1007.60 12091.20 120.912

SUB-ENGINEER

awalpur

2640.00 7280.00 378.00 200.00 3000.00 1100.00 14598.00 1459.80 1459.80 17517.60

SUB-ENGINEER

awalpur

2116.00 3168.00 396.00 100.00 3000.00 500.00 9280.00 928.00 928.00 11136.00

SUB-ENGINEER

awalpur

4074.00 210.00 100.00 200.00 4584.00 458.40 458.40 5500.80

SUB-ENGINEER

awalpur

3360.00 180.00 100.00 200.00 3840.00 384.00 384.00 4608.00

SUB-ENGINEER

awalpur

4410.00 210.00 100.00 200.00 4920.00 492.00 492.00 5904.00

SUB-ENGINEER

awalpur

333.00 27.00 50.00 590.00 1000.00 100.00 100.00 1200.00

SUB-ENGINEER

WALPUR

416.25 22.50 75.00 528.00 1041.75 104.18 104.18 1250.10

SUB-ENGINEER

awalpur

465.00 32.00 75.00 500.00 1072.00 107.20 107.20 1286.40

SUB-ENGINEER

DEPUTY PROJECT DIRECTOR

awalpur

1200.00 34.00 100.00 1334.00 133.40 133.40 1600.80

SUB-ENGINEER

awalpur

100.00 10.00 110.00 11.00 11.00 132.00

SUB-ENGINEER

awalpur

416.25 27.00 734.40 156.00 500.00 1833.65 183.37 183.37 2200.38

SUB-ENGINEER

awalpur

50.00 2.00 52.00 5.20 5.20 62.40

SUB-ENGINEER

awalpur

400.00 40.00 150.00 285.00

875.00 87.50 87.50 1050.00

SUB-ENGINEER

awalpur

1196.80 749.25 117.00 500.00

150.00 620.00 3333.05 333.31 333.31 3999.66

SUB-ENGINEER

WALPUR

333.00 125.00 150.00 475.00 1083.00 108.30 108.30 1299.60

SUB-ENGINEER

awalpur

416.25 27.00 50.00 400.00 893.25

999.00 200.00 50.00 200.00 566.00 200.00 100.00 2315.00 3208.25 320.83

320.83 3849.90

SUB-ENGINEER

awalpur

500.00 500.00 50.00 50.00 600.00

SUB-ENGINEER

awalpur

2836.00 1998.00 225.00 100.00 675.00 5834.00 583.40 583.40 7000.80 7000.00

SUB-ENGINEER

awalpur

45.00 1122.00 1167.00 116.70 116.70 1400.40

SUB-ENGINEER

awalpur

900.00 20.00 38.50 958.50 95.85 95.85 1150.20

SUB-ENGINEER

awalpur

1271.60 416.25 27.00 52.00 400.00 2166.85 216.69 216.69 2600.22

SUB-ENGINEER

awalpur

702.63 48.42 295.68 666.00 50.00 200.00 100.00 720.00 200.00 100.00 3082.73 308.27 308.27 3699.28

SUB-ENGINEER

awalpur

4357.50 499.50 27.00 150.00 150.00 900.00 6084.00

608.40 608.40 7300.80

SUB-ENGINEER

awalpur

orter for bonding with the structure

400.00 200.00 100.00 300.00 150.00 1150.00 115.00 1265.00 126.50 126.50 1518.00

151.80

awalpur

200.00 49.00 8.00 10.00 150.00 417.00 41.70 41.70 500.40

SUB-ENGINEER

awalpur

809.60 500.00 100.00 48.00 3000.00 333.00 27.00 50.00 415.00 5282.60 528.26 528.26 6339.12

SUB-ENGINEER

99.90 33.60 5.40 10.00 93.00 241.90 24.14 24.14 290.18

SUB-ENGINEER

awalpur

166.50 92.40 56.00 18.00 10.00 78.00 420.90 42.09 42.09 505.08

SUB-ENGINEER

awalpur

800.00 60.00 63.00 31.00 10.00 75.00 1039.00 103.90 103.90 1246.80

SUB-ENGINEER

awalpur

190.00 14.00 30.00 234.00 23.40 23.40 280.80

SUB-ENGINEER

awalpur

1746.00

163.20 840.00 100.00 160.00 30.00 50.00 30.00 75.00 30.00 560.00 3784.20 378.42 378.42 4541.04

SUB-ENGINEER

awalpur

228.00 1140.00 720.00

288.00 50.00 20.00 5.00 150.00 2601.00 260.10 260.10 3121.20

SUB-ENGINEER

awalpur

92.50 20.00 112.50 11.25 11.25 135.00

SUB-ENGINEER

awalpur

35.00 130.00 10.00 10.00 56.00 241.00 24.10 24.10 289.20

SUB-ENGINEER

awalpur

500.00 1102.00 76.00 300.00 50.00 150.00 2178.00 217.80 217.80 2613.60

SUB-ENGINEER

awalpur

333.00 27.00 74.00 400.00 834.00 83.40 83.40 1000.80

SUB-ENGINEER

awalpur

120.00 10.00 100.00 230.00 18.00 18.00 266.00

SUB-ENGINEER

awalpur

77.50 10.00 100.00 187.50 18.75 18.75 225.00

Deputy Project Director

awalpur

10.00 8.00 8.00 8.00 49.50 83.50 8.35 8.35 100.20

SUB-ENGINEER

awalpur

204.00 20.00 10.00 50.00 284.00 28.40 28.40 340.80

SUB-ENGINEER

awalpur

8.20 1.00 9.20 0.92 0.92 11.04

SUB-ENGINEER

awalpur

250.00 20.00 10.00 53.00 333.00 33.30 33.30 399.60

SUB-ENGINEER

awalpur

5860.80 2576.00 396.00 175.00 1000.00 10007.80 1000.78 1000.78 12009.36

SUB-ENGINEER

awalpur

643.00 100.00

626.75

80.00 36.00 40.00 40.00 35.00 20.00 200.00 420.00 315.00 2555.75 255.58 255.58 3066.90

SUB-ENGINEER

awalpur

2200.00 495.00 300.00 276.00 50.00 200.00 3521.00 352.10

352.10 4225.20

SUB-ENGINEER

awalpur

1200.00 1440.00 720.00 576.00 360.00 192.00 1080.00 320.00 80.00 200.00 540.00 1080.00 1044.00 150.00 8982.00 901.80 901.80 10785.60

SUB-ENGINEER

awalpur

LEGE

700.00 100.00

736.00

80.00 36.00 32.00 15.00 150.00 420.00 315.00 2584.00 258.40 258.40 3100.80

SUB-ENGINEER

awalpur

200.00 10.00 100.00 310.00 31.00 31.00 372.00

SUB-ENGINEER

awalpur

omen at B.J.Campus

4" thick for A/C Openg duct.

587.81 125.00 250.00 50.00 39.00 22.00 50.00 1123.81 11.24 11.24 1146.29 229 SUB-ENGINEER

Project Director

awalpur

333.00 27.00 50.00 674.00 1084.00 108.40 108.40 1300.80

SUB-ENGINEER

LPUR

416.25 22.50 75.00 612.00 1125.75 112.58 112.58 1350.90

SUB-ENGINEER

LPUR

4273.50 499.50 27.00 150.00 150.00 900.00 6000.00

600.00 600.00 7200.00

SUB-ENGINEER

LPUR

416.25 27.00 50.00 674.00 1167.25 116.73 116.73 1400.70

SUB-ENGINEER

LPUR

2650.00 175.00 2825.00 282.50 282.50 3390.00

SUB-ENGINEER

3119.60 1332.00 234.00 150.00 1000.00 5835.60 583.56 564.11 6983.27 7000.00

SUB-ENGINEER

DEPUTY PROJECT DIRECTOR

LPUR

499.50 36.00 50.00

590.00 1175.50 117.55 117.55 1410.60

SUB-ENGINEER

DEPUTY PROJECT DIRECTOR

alpur
Engineering & Technology at

coat of cement over a bed of 3/4" thick ble tiles, laid with cement sand mortor roved by the Engineer incharge.

Per Sft Per Sft Per Sft % Sft Per Sft % Sft Per Sft Per Sft

125.00 3.00 5.00 3.36 7.88 3.36 4.50 24.00 176.10

16.15
16.15 208.40

SAY Rs.

208

SUB-ENGINEER

alpur

Engineering and Technology at

ating coat of cement over a bed our pigment to match with the omplete in all respects as

Each Each % Sft Per Sft % Sft % Sft Per Sft Per Sft

62.50 1.88 0.66 0.84 1.97 0.84 2.76 1.13 6.00 78.570

7.22
7.22 93.002

SAY Rs. 93.00 Per Rft

SUB-ENGINEER

alpur
Engineering & Technology at

5" with floating coat of cement over a bed colour of marble tiles, laid with cement cted and approved by the Engineer

Per Sft Per Sft Per Sft % Sft Per Sft % Sft Per Sft Per Sft

135.00 3.00 5.00 3.36 7.88 3.36 4.50 10.00 172.10

15.75
15.75 203.60

SAY Rs.

204

SUB-ENGINEER

awalpur

"x3/16" (40x40x5 o centre, embedded in

92.50 20.00 112.50 11.25 11.25 135.00

ASSISTANT ENGINEER

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

G.I Pipe (Medium Quality).


Unit of Rate Per Foot. G.I Pipe Accessores/Fittings. Labour charges 1/2" I/d 25.00 5.00 5.00 35.00 3/4" I/d 32.00 7.00 5.00 44.00 1" I/d 45.00 10.00 8.00 63.00 1.25" I/d 1.50" I/d 60.00 20.00 8.00 88.00 75.00 30.00 10.00 115.00 2" I/d 95.00 35.00 10.00 140.00

Add 10% Contractor Profit Add 10% Overhead Charges

Total

3.50 3.50 42.00

4.40 4.40 52.80

6.30 8.80 11.50 14.00 6.30 8.80 11.50 14.00 75.60 105.60 138.00 168.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

Water Closet European type


Unit of Rate Per No W.C (3 star-Master) Coloured Bend Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 1.00 1.00 No No No 1600.00 150.00 100.00 Per No Per No Per No 1600.00 150.00 100.00 1850.00 185.00 185.00 2220.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Rate approved for

Rs.2,220.00

per No.

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

Water Closet Orisa Pattern type


Unit of Rate Per No W.C (3 star-Master) Coloured Cement Sand PVC Bend Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1 1 1 1 No No No No 650.00 100.00 40.00 150.00 Per No Each Each Per No 650.00 100.00 10.00 40.00 150.00 950.00 95.00 95.00 1140.00

Total

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

Seat & Cover for European.


Unit of Rate Per No Seat & Cover coloured Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1 1 No No 250.00 25.00 Per No Per No 250.00 25.00 275.00 27.50 27.50 330.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

Wash hand Basin 24" x 20"


Unit of Rate Per No Wash hand Basin Coloured (Master-3 Star) Bracket Set Waste Pipe Waste Coupline Padestel TNP Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1 1 1 1 1 1 No Set No No No No 850.00 75.00 40.00 125.00 350.00 150.00 Per No Each Each Each Each Per No 850.00 75.00 40.00 125.00 350.00 50.00 150.00 1640.00 164.00 164.00 1968.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

P Trap Glazed
Unit of Rate Per No P Trap (Full size) Cement Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1 1 No No 60.00 20.00 Each Per No 60.00 20.00 20.00 100.00 10.00 10.00 120.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR

RATE ANALYSIS
Plumbing Work
Description

Plastic made Flushing cistern (3 gallons) Master.


Unit of Rate Per No Flushing Cistern (Coloured) Brecket PVC Pipe Rubber Connection Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1 1 1 1 1 Total No Set No No No 825.00 75.00 50.00 50.00 75.00 Each Each Each Each Each 825.00 75.00 50.00 50.00 75.00 1075.00 107.50 107.50 1290.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS

Plumbing Work
Description

Toilet Paper holder (Fasil/Alyas)


Unit of Rate Per No Toilet Paper Holder Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1 1 Total No No 200.00 50.00 Each Each 200.00 50.00 250.00 25.00 25.00 300.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work

Description

Chromium Plated Towel Rail 24" x 3/4".


Unit of Rate Per No Rod Brecket Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 No 2.00 No 1.00 No Total 200.00 40.00 30.00 Each Each Each 200.00 80.00 30.00 310.00 31.00 31.00 372.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

Looking Glass Plastic Body (Master).

Unit of Rate Per No Looking Glass 2' x 2' Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

1.00 No 1.00 No Total

350.00 50.00

Each Each

Total

350.00 50.00 400.00 40.00 40.00 480.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

Plastic Soap Dish (Master).


Unit of Rate Per No Soap Dish Labour charges 1.00 1.00 No No 75.00 20.00 Each Each 75.00 20.00

Total Add 10% Contractor Profit Add 10% Overhead Charges

Total

95.00 9.50 9.50 114.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

Plastic Shelf (Master).


Unit of Rate Per No Plastic Shelf Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 No 1.00 No Total 150.00 20.00 Each Each 150.00 20.00 170.00 17.00 17.00

Total

204.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

Stop Cock Plastic Head 1/2" size (Fasil/Alyas).


Unit of Rate Per No Stop Cock Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 No 1.00 No Total 250.00 20.00 Each Each 250.00 20.00 270.00 27.00 27.00 324.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

Under Ground Stop Cock Plastic Head 1/2" size (Fasil/Alyas).


Unit of Rate Per No Stop Cock Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 No 1.00 No Total 410.00 20.00 Each Each 410.00 20.00 430.00 43.00 43.00 516.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

Bib Cock Plastic Head 1/2" size (Fasil/Alyas).


Unit of Rate Per No Bib Cock Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 No 1.00 No Total 220.00 20.00 Each Each 220.00 20.00 240.00 24.00 24.00 288.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

Tee Stop Cock Plastic Head 1/2" size (Fasil/Alyas).


Unit of Rate Per No Tee Stop Cock Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 No 1.00 No Total 200.00 20.00 Each Each 200.00 20.00 220.00 22.00 22.00 264.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

Shower Roase 4" x 1/2" size adjustable (Fasil/Alyas).


Unit of Rate Per No Shower Roase Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 No 1.00 No Total 180.00 20.00 Each Each 180.00 20.00 200.00 20.00 20.00 240.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

Mixing Valve Plastic Head (Fasil/Alyas).


Unit of Rate Per No Mixing Valve Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 No 1.00 No Total 650.00 50.00 Each Each 650.00 50.00 700.00 70.00 70.00 840.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

Gun metal Peat/Gate Valve 1.5" to 2" (Anwar).


Unit of Rate Per No Gun metal Peat/Gate Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 No 1.00 No Total 375.00 100.00 Each Each 375.00 100.00 475.00 47.50 47.50 570.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

4" size glazed gully trap with chamber 12" x 12" I/c 9" dia C.I Cover & Frame.
Unit of Rate Per No Gully trap Bricks Cement Sand C.I Frame with Cover Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 20.00 0.25 No No Bag 75.00 2.00 310.00 250.00 100.00 Each Each Each Each Each 75.00 40.00 77.50 10.00 250.00 100.00 552.50 55.25 55.25 663.00

1.00 No 1.00 No Total

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

RATE ANALYSIS
Plumbing Work
Description

P/L 3'' I/d Upvc Pressure Pipe class B (Dadex) in trench


i/c jointing pipe with collers.clamps i/c testing. and entire satisfaction of Engineer Incharg. Unit of Rate =20 Rft 3'' i/d uPVC pressur Pipe class B(Dadex).@1182/-per length 1182.00 3''i/d ,ELBOW etc 275.00 3''i/d ,TEE etc 450.00 Solution dadex 10.00 Labour lowering pipe and jointing 20.00 1937.00 Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Rft =

193.70 193.70 2324.40 116

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Project Director

Approved

Director Engineeing

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

P/L 3'' I/d Upvc double union valve


i/c jointing pipe with flange i/c testing. and entire satisfaction of Engineer Incharg. Unit of Rate =I job P/L 3'' I/d Upvc double union valve 3''Upvc Flange Solution dadex Labour jointing 7560.00 972.00 10.00 50.00 8592.00

Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per job =

859.20 859.20 10310.40 10310

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Project Director

Approved

Director Engineeing

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

Brass Gas Cock


Unit of Rate Per Foot. 1/2" I/d 65.00 20.00 85.00 3/4" I/d 80.00 28.50 108.50 10.85 10.85 130.20

Gas Cock
Labour charges

Add 10% Contractor Profit Add 10% Overhead Charges

8.50 8.50
102.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Plumbing Work
Description

RCC Pipe 1:1.5:3 as per specification BS 5911 class L.


Unit of Rate Per Foot. 6" I/d 50.00 15.00 20.00 85.00 9" I/d 56.70 15.00 20.00 91.70 9.17 9.17 110.04

Market Rate Cement


Labour charges

Add 10% Contractor Profit Add 10% Overhead Charges

8.50 8.50
102.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electrical Work
Description

RCC Pipe 1:1.5:3 as per specification BS 5911 class L 4" dia


Unit of Rate Per Foot.

Market Rate Cement


Labour charges

50.00 15.00 20.00 85.00 8.50 8.50 102.00

Add 10% Contractor Profit Add 10% Overhead Charges

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


PLUMBING WORKS
Description

P/F 3" thick RCC main hole cover with tee shaped C.I Frame of 20" Clear (37.32 Kg)
Unit of Rate = Per No. Material C.I Frame MS Angle Iron & Steel Bar Cement Crush Sand TNP

1.00 1.00 0.25 1.00 1.00

No No Bag Cft Cft

400.00 450.00 310.00 28.00 50.00

Each Each Per Bag Per Cft Per Cft

400.00 450.00 77.50 28.00 50.00 50.00

Labour Charages: Total


Add 10% Contractor Profit Add 10% Overhead Charges

150.00
1205.50 120.55 120.55 1446.60

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electrical WORKS Description: PVC Pipe 20 mm dia including all specials (Beta/Galco/shaval)
Unit of Rate = PVC Pipe 10 Rft Accessores/Fittings. Labour charges Per Foot. 60.00 10.00 5.00 75.00

TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges

TOTAL
Rate Per Rft

7.50 7.50 90.00


9.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved Rate of

Rs.9.00

per Rft

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electrical WORKS Description: PVC Pipe 25 mm dia including all specials (Beta/Galco/shaval
Unit of Rate = PVC Pipe 10 Rft Accessores/Fittings. Labour charges Per Foot. 70.00 10.00 5.00 85.00

TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges

TOTAL
Rate Per Rft

8.50 8.50 102.00


10.20

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved Rate of

Rs.10.20

per Rft

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electrical WORKS Description: PVC Pipe 1.25" dia including all specials (Beta/Galco/shaval
Unit of Rate = PVC Pipe 10 Rft Accessores/Fittings. Labour charges Per Foot. 95.00 12.00 8.00 115.00

TOTAL

Add 10% Contractor Profit Add 10% Overhead Charges

TOTAL
Rate Per Rft

11.50 11.50 138.00


13.80

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved Rate of

Rs.13.80

per Rft

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS

Electrical WORKS Description: PVC Pipe 40 mm dia including all specials (Beta/Galco/shaval
Unit of Rate = PVC Pipe 10 Rft Accessores/Fittings. Labour charges Per Foot. 95.00 12.00 8.00 115.00

TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges

TOTAL
Rate Per Rft

11.50 11.50 138.00


13.80

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved Rate of

Rs.13.80

per Rft

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electrical WORKS Description: PVC Pipe 2" dia including all specials (Beta/Galco/shaval
Unit of Rate = PVC Pipe 10 Rft Accessores/Fittings. Labour charges Per Foot. 150.00 15.00 10.00 175.00

Total
Add 10% Contractor Profit Add 10% Overhead Charges

Total
Rate Per Rft

17.50 17.50 210.00


21.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved Rate of

Rs.21.00

per Rft

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electrical WORKS Description: PVC Pipe 3" dia including all specials (Beta/Galco/shaval
Unit of Rate = PVC Pipe 10 Rft Accessores/Fittings. Labour charges Per Foot. 250.00 15.00 10.00 275.00

Total
Add 10% Contractor Profit Add 10% Overhead Charges

Total

27.50 27.50 330.00

Rate Per Rft

33.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved Rate of

Rs.33.00

per Rft

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electrical WORKS Description:
Single Core PVC insulatted Copper conductor 3/0.029" Cable (Pakistan,New age)

Unit of Rate = Cable (one coil 90 meter) Wastage 5% Accessores/Fittings. TNP Labour charges

Per Metre 710.00 35.50 20.00 30.00 100.00 895.50

TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges

TOTAL
Rate Per Mater

89.55 89.55 1074.60


11.94

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved Rate of

Rs.11.94

per Rft

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electrical WORKS Description:
Single Core PVC insulatted Copper conductor 3/0.029" Cable (Pakistan,New age)
Unit of Rate = Cable (one coil 90 meter) Wastage 5% Accessores/Fittings. TNP Labour charges Per Metre 710.00 35.50 20.00 30.00 100.00 895.50

TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges

TOTAL
Rate Per Mater

89.55 89.55 1074.60


11.94

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved Rate of

Rs.11.94

per Rft

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electrical WORKS Description:
Single Core PVC insulatted Copper conductor 7/0.029" Cable (Pakistan,New age)
Unit of Rate = Cable (one coil 90 meter) Wastage 5% Accessores/Fittings. TNP Labour charges Per Metre 1250.00 62.50 20.00 25.00 125.00 1482.50

TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges

TOTAL
Rate Per Mater

148.25 148.25 1779.00


19.77

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved Rate of

Rs.19.77

per Rft

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electrical WORKS Description:
Single Core PVC insulatted Copper conductor 7/0.044" Cable (Pakistan,New age)
Unit of Rate = Cable (one coil 90 meter) Wastage 5% Accessores/Fittings. TNP Labour charges Per Metre 2175.00 108.75 40.00 50.00 150.00

TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges

2523.75

TOTAL
Rate Per Mater

252.38 252.38 3028.50


33.65

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved Rate of

Rs.33.65

per Rft

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electrical WORKS

Description:
Single Core PVC insulatted Copper conductor 7/0.064" Cable (Pakistan,New age)
Unit of Rate = Cable (one coil 90 meter) Wastage 5% Accessores/Fittings. TNP Labour charges Per Metre 2850.00 142.50 40.00 60.00 200.00 3292.50

TOTAL
Add 10% Contractor Profit Add 10% Overhead Charges

TOTAL
Rate Per Mater

329.25 329.25 3951.00


43.90

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved Rate of

Rs.43.90

per Rft

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electrical WORKS Description: M.S Sheet Box 16 SWG 4" deep with Bakolite Sheet 5 mm thick.
Unit of Rate Per No Steel Box Bakolite Sheet TNP Labour charges 4" x 4" 25.00 20.00 5.00 10.00 60.00 7" x 4" 35.00 25.00 5.00 15.00 80.00 9" x 4" 40.00 28.00 8.00 15.00 91.00 8" x 10" 50.00 40.00 10.00 25.00 125.00

Add 10% Contractor Profit Add 10% Overhead Charges

Total

6.00 6.00 72.00

8.00 8.00 96.00

9.10 9.10 109.20

12.50 12.50 150.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electrical WORKS Description: 3 Pin switch socket & Plug combined (PPI/BBI)
Unit of Rate Per No Plug combined switch Labour charges 5 Amp 55.00 10.00 65.00 10/15 Amp 125.00 20.00 145.00

Add 10% Contractor Profit Add 10% Overhead Charges

Total

6.50 6.50 78.00

14.50 14.50 174.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electrical WORKS Description: Swithches Piano type PPI/BBI
Unit of Rate Per No Market Rate Labour charges Piano type 12.00 2.00 14.00 Double Control Piano type 15.00 5.00 20.00

Add 10% Contractor Profit Add 10% Overhead Charges

Total

1.40 1.40 16.80

2.00 2.00 24.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur

RATE ANALYSIS
Electrical WORKS Description: Providing & Fixing Kit Type Switches sheet & plastic board imported.
Unit of Rate Per No Cost of Material Labour charges 5 No. 165.00 10.00 175.00 6 No. 198.33 10.00 208.33 8 No. 248.33 10.00 258.33

Add 10% Contractor Profit Add 10% Overhead Charges

Total

17.50 17.50 210.00

20.83 20.83 250.00

25.83 25.83 310.00

ASSISTANT ENGINEER

SUB-ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electric Work
Description

Coper Conducter Cables for service connection PVC Sheeted armoured 4 core
70mm Unit of Rate Per Rft. Cable (Pakistan-New age) 70mm Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 1.00 Ft. Ft. 270.00 25.00 Per Rft. Per Rft.

Total

Total
Rate Per Rft. 350/-

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS

Electric Work
Description
Shifting of Transformer of education faculty with in distance of 300' i/c disconecting,demolishing H.T steel wire and other electrical asessories like jumpers fuses insulators ic lowering of transformer with chain cupy in the supervision of experts and skilled labour i/c errection and placing transformer at new site with providing same actvity as mension above i/c errection of new steel cables jumpers fuses stays etc complete in all respect.i/c Providing & Fixing H.T Galvanized Steel structure single pole as per WAPDA specifications. a) H.T. Pole 35' Height with Concrete Foundation (1:2:4), 2' x 2' x 6' size using Angle Iron 2" x 2" x 5/32" size for Legs and Angle Iron 1.375" x 1.375" x 1/8" size for Bracing as per Standard Drawings. Unit Shifting of Transformer=1 No. Disconecting and demolishing of H.T wire i/c old electrical asessories like jumpers insulators fuses etc. 1.00 Job 4000.00 Per job lowering of transformer with chain cupy in the supervision of experts and skilled labour Shifting of transformer with in Distance of 300 ft. in the supervision of experts and skilled labour Errection of transformer with chain cupy in the supervision of experts and skilled labour at new site Errection of electrical asessories jumpers insulators fuses and H.T wire in the supervision of experts and skilled labour at new site Providing & Fixing H.T Galvanized Steel structure single pole as per WAPDA specifications. a) H.T. Pole 35' Height with Concrete Foundation (1:2:4), 2' x 2' x 6' size using Angle Iron 2" x 2" x 5/32" size for Legs and Angle Iron 1.375" x 1.375" x 1/8" s ize for Bracing as per Standard Drawings. Add 10% Contractor Profit Add 10% Overhead Charges Rate Shifting of Transformer=1 No.

1.00

Job

8000.00

Per job

1.00

Job

3000.00

Per job

1.00

Job

8000.00

Per job

1.00

Job

5000.00

Per job

1.00

Job

13000.00

Per job

Total

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electric Work
Description

Tube Light (Pak Light, GFC, Super Asia)


Unit of Rate Per No Tube Light Patti Choke 40 W Rod 40 W Philips Starter TNP Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 1.00 1.00 1.00 1.00 1.00 No No No No No No 65.00 95.00 65.00 20.00 20.00 50.00 Per No Per No Per No Per No Per No Per No

Total

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electric Work
Description

Fan Hock with Plastic Box.


Unit of Rate Per No Fan Hock Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1 1 No No 25.00 5.00 Per No Per No Total

Total
Rate Per No. 36/-

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electric Work
Description

Ceiling Fan Asia, Climax, Millat with dimmer 56" size


Unit of Rate Per No Market Rate Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1 1 No No 1575.00 50.00 Per No Per No Total

Total Rate Per No. Say

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Electric Work
Description
Providing, Installing & connecting up of Exhaust Fan alongwith shutter mounting bracket etc. G.F.C. company 12" dia plastic body.

Unit of Rate Per No Market Rate Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

1 1

No No

1,075.00 Per No 50.00 Per No Total

Total Rate Per No. Say

SUB-ENGINEER

ASSISTANT ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Electric Work
Description
Providing & fixing wall bracket fan 18" size Pak Fan

Unit of Rate Per No Market Rate Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

1 1

No No

1,325.00 Per No 50.00 Per No Total

Total Rate Per No. Say

SUB-ENGINEER

ASSISTANT ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Electric Work
Description
Providing & fixing Power Plug with plastic board 20 Amp (Kit Type) imported.

Unit of Rate Per No Market Rate Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

1 1

No No

200.00 Per No 8.50 Per No Total

Total Rate Per No. Say

SUB-ENGINEER

ASSISTANT ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Electric Work
Description
Providing & fixing Light Plug with plastic board 10 Amp (Kit Type) imported.

Unit of Rate Per No Market Rate Labour charges Add 10% Contractor Profit

1 1

No No

137.50 Per No 8.50 Per No Total

Add 10% Overhead Charges

Total Rate Per No. Say

SUB-ENGINEER

ASSISTANT ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Electric Work
Description

Providing & fixing flase ceiling light with Energy saver.

Unit of Rate Per No. Market Rate Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

1 1

No. No.

525.00 Per No 50.00 Per No Total

Total Rate Per No. Say

SUB-ENGINEER

ASSISTANT ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Electric Work
Description Supply & Fixing of Ceiling light 2'x2' (Ali Light) with 4 Nos. Tube rod of 20 watt & Choke & Startar of Philips with cover & grill complete in all respects.

Unit of Rate Per No. Market Rate Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1 1 No. No. 1,992.00 Per No 50.00 Per No Total

Total Rate Per No. Say

SUB-ENGINEER

ASSISTANT ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Electric Work
Description Providing & fixing Ceiling fans of 56" size i/c speed dimmer complete G.F.C/Pak Fan

Unit of Rate Per No. Cost of Fan Cost of Dimmer Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

1 1 1

No. No. No.

1,483.50 Per No 50.00 Per No 50.00 Per No Total

Total Rate Per No. Say

SUB-ENGINEER

ASSISTANT ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Electric Work
Description Providing and laying sekamant chemical applying in walls

Unit of Rate Per No. Cost of Fan Cost of Dimmer Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

1 1 1

No. No. No.

1,483.50 Per No 50.00 Per No 50.00 Per No Total

Total Rate Per No. Say

SUB-ENGINEER

ASSISTANT ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Electric Work
Description

P/F marble tile 12"x12"x3/8" fency brance with grey cement, grouted with white cement including colour pig to match with the colour of tiles, with PCC 2" thick 1:2:4 rubbing and chemical polishing complete in all resp as pproved by the Engineer Incharge.

Unit of Rate Per No. Cost of Fan Cost of Dimmer Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

1 1 1

No. No. No.

1,483.50 Per No 50.00 Per No 50.00 Per No Total

Total Rate Per No. Say

SUB-ENGINEER

ASSISTANT ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur


ANALYSIS OF RATES

Description

Iron Notice Board for Examination Branch Size 6' x 4'

Unit Rate Per No.


MS Angle 1.5"x1.5"x3/16" MS Sheet 22 SWG Painting of Board Labour charges i/c Cutting, Welding & Fixing with cost of Electrode. 20.35 kg 16.28 kg 39.00 Sft 1.00 No. 43.50 Rs. Per kg 65.00 Rs. Per kg 7.00 Rs. Per Sft 800.00 Rs. Per No.

Total
Add 10% Contractor Profit Add 10% Overhead Charges

Total

Rate Per No.

Say

SUB-ENGINEER

ASSISTANT ENGINEER

The Islamia University of Bahawalpur ANALYSIS OF RATES


Electric Work
Description Providing & fixing Energy Saver Lamp (24 watt) Philips i/c large size holder complete in all respect.

Unit of Rate Per No. Cost of Lamp Cost of Holder Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

1 1 1

No. No. No.

208.50 Per No 25.00 Per No 25.00 Per No Total

Total Rate Per No. Say

SUB-ENGINEER

ASSISTANT ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
Electric Work

Description

P/F Main distribution Board Size 15"x12"


Unit of Rate Per No Steel Box 50 Amp Circuit Breaker 1 1 No No 850.00 1050.00 Per No Per No

10 Amp Circuit Breaker 6 Amp Circuit Breaker Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

2 4 1

No No No

350.00 250.00 150.00

Per No Per No Per No Total

Total Rate Per No. Say

SUB-ENGINEER

DEPUTY PROJECT DIRECTOR

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR

RATE ANALYSIS
Electric Work
Description

Providing & Fixing Ceiling light with energy saver lamp

Unit of Rate Per No Market rate Energy saver Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1.00 1.00 1.00 No No No 400.00 125.00 70.00 Per No Per No Per No

Total

Total

ASSISTANT ENGINEER

SUB-ENGINEER

DEPUTY PROJECT DIRECTOR

Approved

Project Director

The Islamia University of Bahawalpur RATE ANALYSIS

Civil Works
Description Supply & complete Eraction of Bus shed consisting of M.S square Pipe 3"x1.5", 18 SWG for bracings of short
span at 5' center to center as per drawings and M.S squre pipe 1.5"x1.5", 18SWG for bracing of long span 5' Unit of Rate = Per Sft Cost of Material

5" dia M.S Pipe 1/4" thick M.S Pipe 3"x1.5", 18 SWG M.S Pipe 1.5"x1.5",, 18 SWG M.S Plate 1'x1'x1/2" thick Fiber Glass 3 mm thick P.C.C. 1:2:4 Painting 3 coats on pipes Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

338 1487 1140 260 3672 234

Rft Rft Rft Kg Sft Cft

450.00 45.00 30.00 50.00 112.00 102.30

Per Rft Per Rft Per Rft Per Kg Per Sft Per Cft

Total

Total Rate Per Sft (1009796.64 / 3672) =

SUB-ENGINEER

ASSISTANT ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur RATE ANALYSIS


Civil Works
Description Supply & complete Eraction of Car shed consisting of M.S square Pipe 3"x1.5", 18 SWG for bracings of short
span at 5' center to center as per drawings and M.S squre pipe 1.5"x1.5", 18SWG for bracing of long span 5' Unit of Rate = Per Sft Cost of Material 5" dia M.S Pipe 1/4" thick M.S Pipe 3"x1.5", 18 SWG M.S Pipe 1.5"x1.5",, 18 SWG M.S Plate 1'x1'x1/2" thick Fiber Glass 3 mm thick P.C.C. 1:2:4 Painting 3 coats on pipes Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

2160 10155 6882 2160 22500 1728

Rft Rft Rft Kg Sft Cft

550.00 45.00 30.00 50.00 112.00 102.30

Per Rft Per Rft Per Rft Per Kg Per Sft Per Cft

Total

Total Rate Per Sft (6637451.28 / 22500) =

SUB-ENGINEER

ASSISTANT ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur RATE ANALYSIS


Plumbing Work
Description

Providing & Fixing Muslim Shawer complete in all respect


Unit of Rate Per No Muslim Shower Add 10% Contractor Profit Add 10% Overhead Charges 1.00 No 375.00 Per Rft

Total

Total

Rate Per No. =

450.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur RATE ANALYSIS

Plumbing Work
Description

Providing & Fixing "P" Trap of PVC polydex/Dadex (4") Size


Unit of Rate Per No P Trap 4" Size, PVC Polydex/Dadex Labour Charges 1.00 1.00 No No 725.00 75.00 Each Each

Total
Add 10% Contractor Profit Add 10% Overhead Charges

Total

Rate Per No. =

960.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur RATE ANALYSIS


Plumbing Work
Description

Providing & Fixing Chromium plated double bib cock 1/2" dia (Best quality)
Unit of Rate Per No Cost of Material Labour 1.00 1.00 No No 425.00 25.00 Each Each

Total
Add 10% Contractor Profit Add 10% Overhead Charges

Total

Rate Per No. =

540.00

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur RATE ANALYSIS


Plumbing Work
Description

Providing & Fixing Chromium plated wall shower SONEX company including all specials as
Unit of Rate Per No Wall Shower SONEX Company Labour Charges 1.00 1.00 No No 2800.00 200.00 Each Each

Total
Add 10% Contractor Profit Add 10% Overhead Charges

Total

Rate Per No. =

#####

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

PUR

270.00 21.70 291.70 29.17 29.17 350.04

SUB-ENGINEER

PUR

ng of transformer

ications. a) H.T. " x 2" x 5/32" size

4000.00

8000.00

3000.00

8000.00

5000.00

13000.00 41000.00 4100.00 4100.00 49200.00

SUB-ENGINEER

PUR

65.00 95.00 65.00 20.00 20.00 50.00 315.00 31.50 31.50 378.00

SUB-ENGINEER

PUR

25.00 5.00 30.00 3.00 3.00 36.00

SUB-ENGINEER

PUR

1575.00 50.00 1625.00 162.50 162.50 1950.00 Rs.1,950.00

SUB-ENGINEER

pur

1075.00 50.00 1125.00 112.50 112.50

1350.00 Rs.1,350.00

ASSISTANT ENGINEER

pur

1325.00 50.00 1375.00 137.50 137.50 1650.00 Rs.1,650.00

ASSISTANT ENGINEER

pur

200.00 8.50 208.50 20.85 20.85 250.20

Rs.250

ASSISTANT ENGINEER

pur

137.50 8.50 146.00 14.60

14.60 175.20

Rs.175

ASSISTANT ENGINEER

pur

525.00 50.00 575.00 57.50 57.50 690.00

Rs.690

EXECUTIVE ENGINEER

pur

1992.00 50.00 2042.00 204.20 204.20 2450.40

Rs.2,450

ASSISTANT ENGINEER

pur

1483.50 50.00 50.00 1583.50 158.35 158.35 1900.20

Rs.1,900

ASSISTANT ENGINEER

pur

1483.50 50.00 50.00 1583.50 158.35 158.35 1900.20

Rs.1,900

ASSISTANT ENGINEER

pur

hite cement including colour pigment cal polishing complete in all respects

1483.50 50.00 50.00 1583.50 158.35 158.35 1900.20

Rs.1,900

ASSISTANT ENGINEER

walpur

885.23 1058.20 273.00 800.00 3016.43 301.64 301.64 3619.71

Rs.3,620

ASSISTANT ENGINEER

pur

208.50 25.00 25.00 258.50 25.85 25.85 310.20

Rs.310

ASSISTANT ENGINEER

walpur

850.00 1050.00

700.00 1000.00 150.00 3750.00 375.00 375.00 4500.00 Rs.4,500.00

SUB-ENGINEER

PUR

400.00 125.00 70.00 595.00 59.50 59.50 714.00

SUB-ENGINEER

SWG for bracings of short or bracing of long span 5'

152,100.00 66,915.00 34,200.00 13,000.00 411,264.00 23,938.20 20,080.00 120,000.00 841,497.20 84,149.72 84,149.72 #########

275.00

ASSISTANT ENGINEER

SWG for bracings of short or bracing of long span 5'

######### 456,975.00 206,460.00 108,000.00 ######### 176,774.40 125,000.00 750,000.00 ######### 553,120.94 553,120.94 #########

295.00

ASSISTANT ENGINEER

375.00 375.00 37.50 37.50 450.00

SUB-ENGINEER

725.00 75.00 800.00 80.00 80.00 960.00

SUB-ENGINEER

425.00 25.00 450.00 45.00 45.00 540.00

SUB-ENGINEER

ncluding all specials as

2800.00 200.00 3000.00 300.00 300.00 3600.00

SUB-ENGINEER

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electric Work
Description

Exhaust Fan steel body 16" size Asia, Millat, Climax


Unit of Rate Per No Market Rate Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1 1 No 1250.00 Per No No 50.00 Per No Total 1250.00 50.00 1300.00 130.00 130.00 1560.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

ISLAMIA UNIVERSITY BAHAWALPUR RATE ANALYSIS


Electric Work
Description

Ceiling Fan Asia, Climax or GFC with dimmer Size 56".


Unit of Rate Per No Market Rate Labour charges Add 10% Contractor Profit Add 10% Overhead Charges 1 1 No 1250.00 Per No No 50.00 Per No Total 1250.00 50.00 1300.00 130.00 130.00 1560.00

Total

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Civil Works
Description Providing and Fixing Corrugated galvanized iron sheets with G.I Bolds, nuts, 24 SWG i/c M.S Pipe 1.5"x1.5" 18 gauge i/c cutting, bending laying in position as per drawing and design complete in all respect.

Unit of Rate Per Sft.


Material
i) M.S. Pipe 1.5"x1.5" 18 Gauge 10x3x17 = 510 11x2x17 = 374 10x5x16 = 800 11x15x1 = 165 Total = 1849 @ Rs. 25.00 Per Rft ii) G.I. galvanized iron sheets 24 SWG 10x3.14x5.50x17.50x0.05 kg = 1511.25 kg @ 70/- per kg iii) Screws 40 packet @ Rs. 40/vi) Carriage v) Labour Charges 3022.25 Sft @ Rs. 32.00 per Sft Total Add 10% Contractor Profit Add 10% Overhead Charges

46,225.00 105,787.50

1,600.00 5,000.00

96,712.00 255,324.50 25,532.45 25,532.45 306,389.40

G. Total Rate per sft (306389.40/3022.25)

101.38

SUB-ENGINEER

ASSISTANT ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Civil Works
Description Providing and fixing Muslim Shower (Sonex coloured) with bib cock complete in all respects.
Unit of Rate Per No. Muslim Shower Market Rate Labour for fixing

Rs. 350 Rs. 25 Total

Each

350.00 25.00 375.00 37.50 37.50 450.00

Add 10% Contractor Profit Add 10% Overhead Charges

G. Total

SUB-ENGINEER

ASSISTANT ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Plumbing Works
Description Providing and fixing Muslim Shower (Sonex coloured) with bib cock complete in
Unit of Rate Per No. Muslim Shower Market Rate Labour for fixing

Rs. 350 Rs. 25 Total

Each

350.00 25.00 375.00 37.50 37.50 450.00

Add 10% Contractor Profit Add 10% Overhead Charges

G. Total

SUB-ENGINEER

ASSISTANT ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Electrical Works
Description Supply, installation, fixing, Ceiling fans complete in all respects. Asia, Climix, Millat. 56" sweep ceiling fan.
Unit of Rate Per No. Ceiling Fan Market Rate Labour for fixing

Rs. 1575 Rs. 50 Total

Each

1,575.00 50.00 1,625.00 162.50 162.50 1,950.00

Add 10% Contractor Profit Add 10% Overhead Charges

G. Total

SUB-ENGINEER

ASSISTANT ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Electric Works
Description Supply, installation, fixing, Ceiling fans complete in all respects. Asia, Climix, Millat. General Exhaust Fan 12" sweep.
Unit of Rate Per No. Exhaust Fan Market Rate Labour for fixing

Rs. 1250 Rs. 50 Total

Each

1,250.00 50.00 1,300.00 130.00 130.00 1,560.00

Add 10% Contractor Profit Add 10% Overhead Charges

G. Total

SUB-ENGINEER

ASSISTANT ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur


RATE ANALYSIS
CIVIL WORKS
Description

P/F Wardrobe.
Unit of Rate Per = 100 Cft Sft Material 3'x7' M.S pipe 3"x1.5" 18 SWG Labour welding Commercial Win Board 3/4" thick 10% Wastage Deodar Wood 30% Wastage Aluminium Rod Bracket Tower Bolt Lock 808 Handle Hardware Charges Paint Labour charges Add 10% Contractor Profit Add 10% Overhead Charges

20.00 Rft 21.00 2.00 23.00 0.04 0.01 0.05 3.00 2.00 2.00 1.00 1.00 Sft Sft Cft Cft Rft No No No No

31.50 Per Rft

630.00 100.00

27.25 Per Sft

626.75

1600.00 12.00 20.00 20.00 35.00 20.00

Per Cft Per Rft Per No Per No Per No Per No

42.00 Sft 21.00 Sft Total

10.00 Per Sft 15.00 Per Sft

Total
Rate Per Sft 145.00

80.00 36.00 40.00 40.00 35.00 20.00 200.00 420.00 315.00 2542.75 254.28 254.28 3051.30

ASSISTANT ENGINEER

SUB-ENGINEER

EXECUTIVE ENGINEER

Submitted for Approval

Project Director

The Islamia University of Bahawalpur


ANALYSIS OF RATE Description:Providing & Fixing marble tile 3/8" thick fency brand with gray cement, grouted with white cement including colour pigment to match with the colour of tiles, laid with 1:2 cement sand martor i/c rubbing & polishing Complete in all respect as approved by the Engineer incharge. Unit = Per Sft Cost of marbel tile 3/8" thick Cost of Cement Mortor Ratio 1:2, 3/4" thick Labour for fixing Rubbing & Chemical Polishing. Total Add 10% Contractor Profit Add 10% Overhead Charges Total 40.00 Per Sft 8.00 Per Sft 7.30 Per Sft 8.00 Per Sft 63.30 6.33 6.33 75.96 Per Sft

SAY

76.00 Per Sft

Sub-Engineer

Assistant Engineer

Executive Engineer

Approved

Project Director

The Islamia University of Bahawalpur


ANALYSIS OF RATE Description:Grouting of old tile roofing with cement sand mortar 1:3

Unit of Rate %Sft Cost of Cement Cost of Sand Labour Charges 1.00 Bag 3.00 Cft 100.00 Sft 250.00 Per Bag 9.00 Per Cft 1.43 Per Sft Total 250.00 27.00 143.00 420.00 42.00 42.00 504.00

Add 10% Contractor Profit Add 10% Overhead Charges Total

SAY

504.00

Sub-Engineer

Assistant Engineer

Executive Engineer

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Civil Works
Description Providing and fixing M.S. sheet hollow pressed frame of doors, windows, C. windows, etc. (chowkat only) of 14 SWG welded with M.S. flat 9" M.S. holdfast 9"x1"x1/8" welded/screwed 4" (100 mm) long iron hinges, including filling chowkat with cement sand 'mortar 1:8 and embedding holdfast in cement concrete 1:2:4, complete in all respects. Single Rebate. Size of Chowket 2.50' x 7'
Unit of Rate Per Sft Market Rate Chowket Labour for fixing 32.6 kg @ Rs. Total Add 10% Contractor Profit Add 10% Overhead Charges 61.00 1,988.60 200.00 2,188.60 218.86 218.86 2,626.32 150.08

G. Total
Rate Per Sft = 2992.32/ 17.50

SAY

150.00 Per Sft

SUB-ENGINEER

ASSISTANT ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

The Islamia University of Bahawalpur ANALYSIS OF RATES


Civil Works
Description Providing and fixing M.S. sheet hollow pressed frame of doors, windows, C. windows, etc. (chowkat only) of 14 SWG welded with M.S. flat 9" M.S. holdfast 9"x1"x1/8" welded/screwed 4" (100 mm) long iron hinges, including filling chowkat with cement sand 'mortar 1:8 and embedding holdfast in cement concrete 1:2:4, complete in all respects. Double Rebate. Size of Chowket 3.50' x 7'
Unit of Rate Per Sft Market Rate Chowket Labour for fixing 57 kg @ Rs. Total Add 10% Contractor Profit Add 10% Overhead Charges 61.00 3,477.00 200.00 3,677.00 367.70 367.70 4,412.40 180.10

G. Total
Rate Per Sft = 2992.32/ 24.50

SAY

180.00 Per Sft

SUB-ENGINEER

ASSISTANT ENGINEER

EXECUTIVE ENGINEER

Approved

Project Director

You might also like