GOBIERNO REGIONAL PUNO


PRORRIDRE
OBRA : MODALIDAD DE EJECUCION : ADMINISTRACION DIRECTA DEPARTAMENTO : PUNO
ENT. EJEC. : PRORRIDRE FECHA DE INICIO DE OBRA : PROVINCIA :
ENT. FIN. : GOBIERNO REGIONAL PLAZO DE EJECUCION : DISTRITO :
FECHA : FECHA DE TERMINO DE LA OBRA : SECTOR :
UNIDAD METRADO C.U. PRESUPUESTO METRADO VALORIZADO %DE AVANCE METRADO VALORIZADO %DE AVANCE METRADO VALORIZADO %DE AVANCE METRADO VALORIZADO %DE AVANCE
CONSTRUCCION DE CANAL PRINCIPAL IRRIGACION YANARICO 2,308,688.76 - 0.00% 0.00 0.00% 0.00 0.00% 2,308,688.76 100.00%
01.00.00 TRABAJOS PRELIMINARES 62,472.76 0.00 0.00% 0.00 0.00% 0.00 0.00% 62,472.76 100.00%
01.01.00 CAMPAMENTO GLB 1.00 2,500.00 2,500.00 0.00% - 0.00 0.00% 1.00 2,500.00 100.00%
01.02.00 CARTEL DE OBRA 5.0X3.0 M UND 1.00 2,922.38 2,922.38 0.00% - 0.00 0.00% 1.00 2,922.38 1.00
01.03.00 TRANSPORTE DE MAQUINARIA Y EQUIPO_CP GLB 2.00 4,074.31 8,148.62 0.00% - 0.00 0.00% 2.00 8,148.62 100.00%
01.04.00 TRAZO Y REPLANTEO M 22,710.26 0.85 19,303.72 0.00% 0.00% 0.00 0.00% 22,710.26 19,303.72 100.00%
01.05.00 TRAZO Y REPLANTEO OBRAS DE ARTE M2 2,664.91 0.80 2,131.93 0.00% 0.00% 0.00 0.00% 2,664.91 2,131.93 100.00%
01.06.00 LIMPIEZA Y DESBROCE A MANO M2 2,589.91 0.99 2,564.01 0.00% 0.00% 0.00 0.00% 2,589.91 2,564.01 100.00%
01.07.00 LIMPIEZA Y DESBROCE A MAQUINA e=0.20M M2 88,936.07 0.28 24,902.10 0.00% 0.00% 0.00 0.00% 88,936.07 24,902.10 100.00%
02.00.00 MOVIMIENTO DE TIERRAS 740,627.32 0.00 0.00% 0.00 0.00% 0.00 0.00% 740,627.32 100.00%
02.01.00 DEMOLICION DE ESTRUCTURAS M3 34.42 32.38 1,114.52 0.00% - 0.00 0.00% 34.42 1,114.52 100.00%
02.02.00 EXCAVACION DE PLATAFORMA EN MATERIAL SUELTO A MAQ. M3 10,592.33 3.83 40,568.62 0.00% 0.00% 0.00 0.00% 10,592.33 40,568.62 100.00%
02.03.00 EXCAVACION DE CORTE PARA REEMPLAZO M3 15,660.75 4.07 63,739.25 0.00% 0.00% 0.00 0.00% 15,660.75 63,739.25 100.00%
02.04.00 TERRAPLEN COMPACTADO M3 50,179.95 7.14 358,284.84 0.00% 0.00% 0.00 0.00% 50,179.95 358,284.84 100.00%
02.05.00 EXCAVACION DE CAJA DE CANAL A MAQUINA M3 21,818.37 4.05 88,364.40 0.00% 0.00% 0.00 0.00% 21,818.37 88,364.40 100.00%
02.06.00 EXCAVACION Y REFINE DE CAJA DE CANAL EN MATERIAL SUELTO A MANO M3 9,350.73 15.95 149,144.14 0.00% 0.00% 0.00 0.00% 9,350.73 149,144.14 100.00%
02.07.00 EXCAVACION PARA CIMENTACION DE OBRAS DE ARTE M3 2,186.21 11.77 25,731.69 0.00% 0.00% 0.00 0.00% 2,186.21 25,731.69 100.00%
02.08.00 RELLENO COMPACTADO DE OBRAS DE ARTE M3 1,089.16 12.56 13,679.85 0.00% 0.00% 0.00 0.00% 1,089.16 13,679.85 100.00%
03.00.00 DRENAJES 9,273.50 - - - - - 9,273.50 100.00%
03.01.00 EXCAVACION DE ZANJA DE DRENAJE A MANO M3 225.00 9.74 2,191.50 - - - - - - 225.00 2,191.50 100.00%
03.02.00 COLOCACION DE DRENAJE EN ZONA DE BOFEDAL M 200.00 21.28 4,256.00 - - - - - - 200.00 4,256.00 100.00%
03.03.00 RELLENO COMPACTADO A MANO CON MATERIAL SELECCIONADO M3 225.00 12.56 2,826.00 - - - - - - 225.00 2,826.00 100.00%
04.00.00 CONCRETOS 1,190,358.54 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,190,358.54 100.00%
04.01.00 CONCRETO F'C= 210 Kg/cm2 M3 148.53 278.29 41,334.41 0.00% 0.00% 0.00 0.00% 148.53 41,334.41 100.00%
04.02.00 CONCRETO FC=175 KG/CM2 REVESTIDO DE CANAL M3 3,838.94 273.36 1,049,412.64 0.00% 0.00% 0.00 0.00% 3,838.94 1,049,412.64 100.00%
04.03.00 CONCRETO F'C= 175 Kg/cm2 EN OBRAS DE ARTE M3 234.95 254.07 59,693.75 0.00% 0.00% 0.00 0.00% 234.95 59,693.75 100.00%
04.05.00 CONCRETO F'C= 140 KG/CM2 + 30%PM M3 226.15 176.51 39,917.74 0.00% 0.00% 0.00 0.00% 226.15 39,917.74 100.00%
05.00.00 ENCOFRADO Y DESENCOFRADO 99,818.73 - 0.00% 0.00 0.00% 0.00 0.00% 99,818.73 100.00%
05.01.00 ENCOFRADO Y DESENCOFRADO DE OBRAS DE ARTE M2 3,920.61 25.46 99,818.73 0.00% 0.00% 0.00 0.00% 3,920.61 99,818.73 100.00%
06.00.00 ACERO DE REFUERZO 68,359.33 - 0.00% 0.00 0.00% 0.00 0.00% 68,359.33 100.00%
06.01.00 ACERO DE REFUERZO KG 19,365.25 3.53 68,359.33 0.00% 0.00% 0.00 0.00% 19,365.25 68,359.33 100.00%
07.00.00 JUNTAS Y SELLOS 98,350.94 - 0.00% 0.00 0.00% 0.00 0.00% 98,350.94 100.00%
07.01.00 JUNTA WATER STOP 6" M 288.77 26.54 7,663.96 0.00% 0.00% 0.00 0.00% 288.77 7,663.96 100.00%
07.02.00 JUNTAS ASFALTICAS e=1" M 20,704.79 4.38 90,686.98 0.00% 0.00% 0.00 0.00% 20,704.79 90,686.98 100.00%
08.00.00 VARIOS 29,903.62 0.00 0.00% 0.00 0.00% 0.00 0.00% 29,903.62 100.00%
08.01.00 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) UND 156.00 21.20 3,307.20 0.00% 0.00% 0.00 0.00% 156.00 3,307.20 100.00%
08.02.00 PRUEBAS DE CONTROL DE COMPACTACION DE TERRAPLEN UND 1,673.00 15.60 26,098.80 0.00% 0.00% 0.00 0.00% 1,673.00 26,098.80 100.00%
08.03.00 COMPUERTA LATER. TIPO IZAJE 0.40 X 0.40 M UND 1.00 497.62 497.62 - - - - 1.00 497.62 100.00%
09.00.00 MEDIDAS DE MITIGACION AMBIENTAL 9,524.02 0.00 0.00% - - 0.00 0.00% 9,524.02 100.00%
09.01.00 REMEDIACION AMBIENTAL 2,444.02
09.01.01 RIEGO PARA CAMINOS DE ACCESO HM 20.00 97.03 1,940.60 0.00% - - - 0.00 0.00 0.00% 20.00 1,940.60 100.00%
09.01.02 ESPARCIIMIENTO DE TERRENO CON MAQ. Y CUBRIR CON SUELO ORGANICO HA 2.00 251.71 503.42 - - - - - - - 2.00 503.42 100.00%
09.02.00 MANEJO AMBIENTAl 3,090.00
09.02.01 CAPACITACION EN CONSERV. DE RR. NN. Y MEDIO AMBIENTE EVT 1.00 2,090.00 2,090.00 - - - - - - - - - 1.00 2,090.00 100.00%
09.02.02 CONSTRUCCION DE LETRINAS EN CAMPAMENTO UND 2.00 500.00 1,000.00 0.00% - - - 0.00 0.00 0.00% 2.00 1,000.00 1.00
09.03.00 PLAN DE CONTINGENCIA 3,990.00
09.03.01 CAPACITACION EN MEDIDAS DE CONTINGENCIA EVT 1.00 2,090.00 2,090.00 - - - - - - - 1.00 2,090.00 100.00%
09.03.02 EQUIPOS DE EMERGENCIA GLB 1.00 1,900.00 1,900.00 - - - - - - - 1.00 1,900.00 100.00%
COSTO DIRECTO 2,308,688.76 - 0.00 0.00 2,299,164.74
GASTOS GENERALES 6.70% 0.00 - 0.00 0.00 0.00
SUPERVISION 1.46 % 2,308,688.76 - - - 2,299,164.74
VALORIZACION TOTAL S/. 4,617,377.51 - - - 4,598,329.47
% DE AVANCE FISICO DE OBRA % 0.00% 0.00% 0.00% 99.59%
VALORIZACION DE OBRA N 01
ING. RESIDENTE DE OBRA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS
ITEM DESCRIPCION
PRESUPUESTO ( S/. ) AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO ACTUAL
GOBIERNO REGIONAL PUNO
PRORRIDRE
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
EJECUTA FECHA DE INICIO DE OBRA PROVINCIA
ENTIDAD FINANCIERA PLAZO DE EJECUCION DISTRITOS
FECHA FECHA DE TERMINO DE LA OBRA LOCALIDAD
VALORIZACIONES
MENSUALES
FECHA DE
VALORIZACION
COSTO
DIRECTO PROGRAMADO
GASTOS
GENERALES
PROGRAAMADO
GASTOS DE
SUPERVISION
VALORIZACION
TOTAL
VALORIZACION
ACUMULADA
%DE AVANCE
MENSUAL
SALDO DE %DE AVANCE
PPTO. DE OBRA 3,052,785.50 204,437.22 44,509.14 3,301,731.86 100.00%
VALORIZACION N 01 SEPTIEMBRE 0.00% 100.00%
VALORIZACION N 02 OCTUBRE 0.00% 100.00%
VALORIZACION N 03 NOVIEMBRE 0.00% 100.00%
VALORIZACION N 04 DICIEMBRE 0.00% 100.00%
VALORIZACION N 05 ENERO 0.00% 100.00%
VALORIZACION N 06 FEBRERO
VALORIZACION N 07 MARZO
VALORIZACION N 08 ABRIL
VALORIZACION N 09 MAYO
0.00 0.00 0.00 0.00
3,052,785.50 204,437.22 44,509.14 3,301,731.86
0.00% 0.00% 0.00% 0.00% 0.00% 100.00%
ING. RESIDENTE DE OBRA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS
% DE AVANCE ACUMULADA
VALORIZACION ACUMULADA
VALORIZACION SALDO
RESUMEN DE VALORIZACIONES DE AVANCE DE OBRA N 05
PRORRIDRE PRASTER
Informe Mensual Construccin Canal Principal Irrigacin Yanarico Prog. 3+156.55 al 14+511.68 Correspondiente al Mes de Enero del 2,008
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITOS
FECHA FECHA DE TERMINO DE LA OBRA LOCALIDAD
1,800,000.00
1,600,000.00
1,400,000.00
1,200,000.00
1,000,000.00
800,000.00
600,000.00
400,000.00
200,000.00
18,923.09 166,399.33 1,161,152.75 1,360,209.18 532,606.90 62,440.61
18,923.09 166,453.41 572,188.62 688,842.77 717,762.05 -
565,870.95 1,020,458.64 295,214.10 585,427.38 - -
SEPTIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO
PROGRAMADO: EJECUTADO: DESEMBOLSO:
ING. RESIDENTE DE OBRA
ING. SUPERVISOR DE OBRA N VAL. ACTUAL VAL. ACUMUL. VAL. SALDO
01 18,923.09 18,923.09 3,282,808.77
02 166,453.41 185,376.50 3,116,355.36
03 572,188.62 757,565.11 2,544,166.75
04 688,842.77 1,446,407.89 -1,446,407.89
%AVANCE 20.86% 43.81% 77.06%
VALORIZAC. ACUMUL. PROGAMADA
VALORIZAC. ACUMUL. EJECUTADA
DESEMBOLSO
LEYENDA
GOBIERNO REGIONAL PUNO
PRORRIDRE - PRASTER
CUADRO DE CONTROL DE VALORIZACIONES ACUMULADAS
E
N


N
U
E
V
O
S


S
O
L
E
S
MES
AO
ING. RESIDENTE DE OBRA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS
2,007
VALORIZACION
2,008
0.00
500,000.00
1,000,000.00
1,500,000.00
2,000,000.00
2,500,000.00
3,000,000.00
3,500,000.00
SEPTIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO
M
O
N
T
O
S

(
N
/
S
.
)

MESES
PROGRAMADO
EJECUTADO
DESEMBOLSO
PRORRIDRE - PRASTER 2,008
Informe Mensual Construccin Canal Principal Irrigacin Yanarico Prog. 3+156.55 al 14+511.68 Correspondiente al Mes de Enero del 2,008
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR
CANT. % CANT. % CANT. % CANT. %
1 Construccin Canal Principal IRRIGACION YANARICO Ml. 11355.13 4,550.00 40.07% 2500.00 22.02% 7050 62.09% 4305.13 37.91%
Revestido de Canal Principal KM 3+156.55 al 14+511.68
seccion Trapezoidal
Ml. 11,355.13 4,550.00 40.07% 2500.00 22.02% 7,050.00 62.09% 4,305.13 37.91%
2 Obras de Arte Und 130 1.70 0.01 52.00 0.40 113.70 0.87 16.3 12.54%
Acueducto Und 1 - - - - - - 1 100.00%
Alcantarilla Und 11 1.70 0.15 3.00 0.27 4.70 0.43 6.3 57.27%
Cada Und 4 - - 1.00 0.25 1.00 0.25 3 75.00%
Canoa A = 1.5 m. Und 2 - - - - - - 2 100.00%
Canoa Tipo Vehicular Und 3 - - - - - - 3 100.00%
Cruce Puente Vehicular CABANA Und 1 1.00 1.00 - - 1.00 1.00 0 0.00%
Entrega Pluvial Und 13 - - 13.00 1.00 13.00 1.00 0 0.00%
Entrega Pluvial + Salvavidas Und 6 2.00 0.33 - - 2.00 0.33 4 66.67%
Pase Peatonal Und 47 42.00 0.89 23.00 0.49 65.00 1.38 -18 -38.30%
Puente Vehicular Und 4 1.00 0.25 - - 1.00 0.25 3 75.00%
Salvavidas Und 16 14.00 0.88 12.00 0.75 26.00 1.63 -10 -62.50%
Toma Lateral Und 11 - - - - - - 11 100.00%
Toma Simple Und 11 - - - - - - 11 100.00%
ING. RESIDENTE DE OBRA
DESCRIPCION DEL AVANCE DE
LA META FISICA
N
V B ING. SUPERVISOR V B DIRECTOR DE OBRAS
Revestido del canal principal
GOBIERNO REGIONAL PUNO
PRORRIDRE
CUADRO DE CONTROL DE METAS FISICAS
AVANCE
ANTERIOR
CANT.
PROG.
AVANCE
ACUMUL.
UND META FISICA
AVANCE
ACTUAL
SALDO
ACTUAL
PRORRIDRE - PRASTER 2,008
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
UBICACIN FECHA DE INICIO DE OBRA PROVINCIA
EJECUTA PLAZO DE EJECUCION DISTRITO
RESIDENTE FECHA DE TERMINO DE LA OBRA SECTOR
SUPERVISOR
PRESUPUESTO DEL
EXPEDIENTE TECNICO
Parcial Parcial % Parcial % Monto % Monto %
FORMULA 01 3,477,814.22 2,463,584.00 70.84%
COSTO DIRECTO (S/.) 3,477,814.22 250,000.00 7.19% 128,500.00 3.69% 378,500.00 10.88% 3,099,314.22 89.12%
GASTOS GENERALES (xxx %) 206,205.73 14,822.94 7,618.99 22,441.93 183,763.80
GASTOS DE SUPERVISIN DE OBRA (xxx %) 66,078.47 4,750.00 2,441.50 7,191.50 58,886.97
COSTO TOTAL (A) 3,750,098.42 269,573.01 138,560.53 408,133.54 3,341,965.88
PORCENTAJE DE AVANCE 100.00% 7.19% 3.69% 10.88%
FORMULA 02 OBRAS NECESARIAS POR MAYORES METRADOS (*) 350,000.00
COSTO DIRECTO (S/.) 350,000.00 150,000.00 42.86% 10,000.00 2.86% 160,000.00 45.71% 190,000.00 54.29%
GASTOS GENERALES (xxx %) 20,752.12 8,893.76 592.92 9,486.68 11,265.43
GASTOS DE SUPERVISIN DE OBRA (xxx %) 6,650.00 2,850.00 190.00 3,040.00 3,610.00
COSTO TOTAL (B) 377,402.12 161,743.76 10,782.92 172,526.68 204,875.98
FORMULA 03 OBRAS NECESARIAS POR PARTIDAS NUEVAS (*)
COSTO DIRECTO (S/.) 25,000.00 10,000.00 40.00% 3,500.00 14.00% 13,500.00 54.00% 11,500.00 46.00%
GASTOS GENERALES (xxx %) 1,482.29 592.92 207.52 800.44 681.86
GASTOS DE SUPERVISIN DE OBRA (xxx %) 475.00 190.00 66.50 256.50 218.50
COSTO TOTAL (C) 26,957.29 10,782.92 3,774.02 14,556.94 12,400.36
FORMULA 04 DEDUCTIVOS DE OBRAS POR PARTIDAS NO EJECUTADAS (*)
COSTO DIRECTO (S/.) 78,000.00 45,000.00 57.69% 7,000.00 8.97% 52,000.00 66.67% 26,000.00 33.33%
GASTOS GENERALES (xxx %) 4,624.76 2,668.13 415.04 3,083.17 1,541.59
GASTOS DE SUPERVISIN DE OBRA (xxx %) 1,482.00 855.00 133.00 988.00 494.00
COSTO TOTAL (D) 84,106.76 48,523.13 7,548.04 56,071.17 28,035.59
COSTO TOTAL DEDUCIDO ( E ) = (B+C-D) 320,252.65 131,012.45
COSTO TOTAL ACUMULADO (A) + (E) 4,070,351.07
PORCENTAJE ACUMULADO 108.54%
COSTO REFERENCIAL DEL EXPEDIENTE (A) 3,750,098.42
COSTO ADICIONAL EJECUTADO POR OBRAS NECESARIAS (E) 320,252.65
COSTO TOTAL DE OBRA ACUMULADO (A)+(E) 4,070,351.07
PORCENTAJE DE ADICIONAL EJECUTADO (E)/(A) 8.54%
VALORIZACIN ACUMULADA AL MES (E) 539,145.99
% AVANCE FISICO ACTUAL ACUMULADO (C)/(A)*100 14.38%
ING. RESIDENTE DE OBRA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS
CONSOLIDADO DE VALORIZACIN FISICA - MARZO 2010
ITEM DESCRIPCION DE PARTIDAS
ACUMULADO ANTERIOR
AVANCE
DEL MES
ACUMULADO ACTUAL SALDO
PARTIDAS EJECUTADAS DEL EXPEDIENTE APROBADO
89.12%
PARTIDAS EJECUTADAS POR SER OBRAS NECESARIAS
CUADRO DE RESUMEN
539,145.99
14.38%
.......................................
RESIDENTE DE OBRA
.............................................
SUPERVISOR DE OBRA
..............................................
VB GERENCIA DE INFRAESTRUCTURA
HOJA RESUMEN DE METRADOS DE OBRAS DE ARTE
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR
N Progrevisva Obra de Arte
T
r
a
z
o
s

y

r
e
p
l
a
n
t
e
o

d
e

o
b
r
a
s

d
e

a
r
t
e
L
i
m
p
i
e
z
a

y

d
e
s
b
r
o
c
e
E
n
r
r
o
c
a
d
o

d
e

p
r
o
t
e
c
c
i
o
n

(
m
3
)
E
x
c
a
v
a
c
i

n

M
a
n
u
a
l

P
/
E
s
t
r
u
c
.
R
e
l
l
e
n
o

C
o
m
p
.
P
/
E
s
t
r
u
c
t
u
r
a
sE
l
i
m
.

M
a
t
.
E
x
c
e
d
e
n
t
e
C


f
' c
=
1
4
0
+
3
0
%
P
M

k
g
/
c
m
2

C


f
' c
=
1
7
5
+
3
0
%
P
M

k
g
/
c
m
2
C

f
' c
=
1
7
5

k
g
/
c
m
2

C

f
' c
=
2
1
0

k
g
/
c
m
2
P
i
e
d
r
a

a
s
e
n
t
a
d
a

y

e
m
b
o
q
u
i
l
l
a
d
a
E
n
c
o
f
r
a
d
o

Y
d
e
s
e
n
c
o
f
.
A
c
e
r
o

d
e

R
e
f
u
e
r
z
o

J
.
W
.
s
t
o
p
J
.
A
s
f
a
l
t
i
c
a
B
a
r
a
n
d
a

M
e
t

l
i
c
a
P
l
a
n
c
h
a

M
e
t
a
l
i
c
a

6
.
1
0
x
1
.
2
5
m
P
l
a
n
c
h
a

M
e
t
a
l
i
c
a

3
.
8
0
x
1
.
2
0
m
C
o
m
p
u
e
r
t
a

T
i
p
o

I
z
a
j
e

0
.
5
0
x
0
.
5
0
C
o
m
p
u
e
r
t
a

T
i
p
o

I
z
a
j
e

0
.
5
0
x
0
.
4
0
C
o
m
p
u
e
r
t
a

T
i
p
o

I
z
a
j
e

0
.
4
0
x
0
.
3
0
C
o
m
p
u
e
r
t
a

T
i
p
o

I
z
a
j
e

0
.
4
0
x
0
.
3
5
C
o
m
p
u
e
r
t
a

T
i
p
o

I
z
a
j
e

0
.
2
0
x
0
.
2
0
1 6+275.80 Toma lateral 14 MD
2 6+536.05 Salvavidas
3 6+677.55 Alcantarilla (cruce ro porotoyo)
4 6+823.50 Toma lateral 15 MD
5 6+885.55 Pase peatonal 21.30 21.30 6.29 3.12 3.50 6.29 1.93 38.91 122.62 11.10
6 6+905.65 Salvavidas
7 7+066.75 Toma simple MD
8 7+153.00 Alcantarilla cruce dren
9 7+158.28 Partidor ( canal A Canal -B )
10 7+196.27 Puente vehicular
11 7+525.00 Toma lateral 16 MD
12 7+570.65 Pase peatonal 11.10
13 7+664.25 Toma simple - MI
14 7+674.45 Pase peatonal 11.10
15 7+750.00 Rpida
16 7+840.00 Puente vehicular
47 9+871.20 Toma simple MD
48 9+898.50 Rpida
49 9+997.50 Puente vehicular
51
0+235.40 Pase peatonal
52
0+239.15 Entrega superficial
53
0+477.50 Pase peatonal
54
0+557.75 Toma simple MD
55
0+691.55 Pase peatonal
56
0+704.25 Entrega superficial
57
0+793.55 Pase peatonal
58
0+933.50 Puente vehicular
59
0+983.00 Toma simple - MI
60
1+007.40 Pase peatonal
61 1+023.00 Partidor
TOTAL 21.30 21.30 0.00 6.29 3.12 3.50 0.00 6.29 1.93 0.00 0.00 38.91 122.62 0.00 0.00 33.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00
V B ING. SUPERVISOR V B DIRECTOR DE OBRAS ING. RESIDENTE DE OBRA
GOBIERNO REGIONAL PUNO
PRORRIDRE
HOJA RESUMEN DE METRADOS
Obra :
META
Departamento Puno Provincia LAMPA Distrito CABANILLA
Item Descripcin Nro. Veces Largo Ancho Alto Parcial Total Unidad
01.00.00 TRABAJOS PRELIMINARES
01.01.00 CAMPAMENTO 1.00 GLB
ubicado en la zona (alquilado) 1 1
01.02.00 CARTEL DE OBRA 1.00 UND
cartel de obra de 5x3 M 1 1.00 1
01.03.00 TRANSPORTE DE MAQUINARIA Y EQUIPO 2.00 GLB
2 2
01.04.00 TRAZO Y REPLANTEO 1.00 M
1 1
01.05.00 TRAZO Y REPLANTEO OBRAS DE ARTE 1,620.30 M2
de la hoja resumen de obras de arte 1 1,200.30 1200.3
de la alcantarilla de Collana 1 420.00 420
01.06.00 LIMPIEZA Y DESBROCE 620.45 M2
limpieza y desbroce de canal 2 0.75 1.50
limpieza y desbroce de obras de arte 1 618.95 618.95
01.07.00 APERTURA DE CAMINOS DE ACCESO 3,000.00 M
caminos de acceso hacia las canteras 1 3,000.00 3000
01.08.00 MANTENIMIENTO DE CAMINOS DE ACCESO 4,500.00 M
de todos los caminos dentro del proyecto 1 4,500.00 4500
02.00.00 MOVIMIENTO DE TIERRAS
02.01.00 EXCAVACION EN MATERIAL SUELTO PARA AMPLIACION DE PLATAFORMA #REF! M3
del movimiento de tierras 1 #REF! #REF!
02.02.00 EXCAVACION EN MATERIAL SUELTO 2,511.84 M3
de la alcantarilla de Collana 2,511.84 2511.84
1
02.03.00 RELLENO COMPACTADO PARA ESTRUCTURAS CON MATERIAL PROPIO 931.00 M3
de la hoja de metrados de la alcantarilla 1 931.00 931.00
02.04.00 TRANSPORTE DE MATERIAL DE PRESTAMO (1) 0.60 M3
de las canteras de material impermeable 0.5 1.00 1.20 0.60
02.05.00 TRANSPORTE DE MATERIAL DE PRESTAMO (2) 0.60 M3
de las canteras de material granular 0.5 1.20 0.60
02.06.00 TERRAPLEN COMPACTADO 1.00 M3
del movimiento de tierras 1 1.00
02.07.00 EXCAVACION DE CAJA DE CANAL A MAQUINA 1,732.19 M3
De excavacin de caja 1 1,732.19 1732.19
02.08.00 EXCAVACION DE CAJA DE CANAL A MANO 7,690.76 M3
De excavacin de caja 1 7,690.76 7690.76
02.09.00 EXCAVACION DE ZANJAS DE CORONACION 500.00 ML
metrado general 1 500.00 500
02.10.00 PICADO DE FISURAS DE CANAL 64.00 ML
de la hoja de metrado correspondiente 1 64.00 64
02.11.00 PICADO PARA ADHERENCIA DE ESTRUCTURAS 214.80 M2
tramo de canal en concreto a ser encimado 1 214.80 214.80
02.12.00 ACOMODO DE ENROCADO DE PROTECCION 54.00 M3
de la hoja resumen de metrado de obras de arte 1 54.00 54
02.13.00 EXCAVACION PARA CIMENTACION DE OBRAS DE ARTE 869.59 M3
de la hoja resumen de metrado de obras de arte 1 869.59 869.5941
02.14.00 RELLENO COMPACTADO DE OBRAS DE ARTE 140.64 M3
de la hoja resumen de metrado de obras de arte 1 140.64 140.6406
02.15.00 ELIMINACION DE MATERIAL EXCEDENTE DE CORTE (a carretilla) 499.42 M3
eliminaxion de material de corte para ampliar la plataforma 1 - 1.20 0.00
eliminacion de mat. excedente de obras de arte 1 416.18 1.20 499.42
02.16.00 ELIMINACION DE MAERIAL EXCEDENTE DE CORTE A MAQUINA 3,652.78 M3
de la eliminacion de material de la alcantarilla 1 3,652.78 3652.78
02.17.00 ELIMINACION Y REPOSICION DE MATERIAL SATURADO 843.70 M3
de la hoja de metrados respectiva 1 843.70 843.70
03.00.00 DEMOLICION DE ESTRUCTURAS
03.01.00 DEMOLICION DE ALBAILERIA 501.03 M3
demolicion de las obras de arte 1 308.34 308.34
del metrado de alcantarilla Illpa(Porotoyo) 192.69 192.69
HOJA RESUMEN DE METRADOS
Obra :
META
Departamento Puno Provincia LAMPA Distrito CABANILLA
Item Descripcin Nro. Veces Largo Ancho Alto Parcial Total Unidad
03.02.00 DEMOLICION DE ESTRUCTURAS 190.25 M3
demolicin de obras de arte de concreto armado 1 167.36 167.36
del metrado de alcantarilla Illpa(Porotoyo) 22.89 22.89
03.03.00 DEMOLICION DE CANAL EN CONCRETO A MAQUINA 240.44 M3
de la hoja de metrados respectiva 1 240.44 240.44
03.04.00 DEMOLICION DE CANAL EN CONCRETO A MANO 193.16 M3
de la hoja de metrados respectiva 1 193.16 193.16
03.05.00 DEMOLICION DE CANAL EN MAMPOSTERIA A MAQUINA 1,945.39 M3
de la hoja de metrados respectiva 1 1,945.39 1945.39
03.06.00 DEMOLICION DE CANAL EN MAMPOSTERIA A MANO 1,047.52 M3
de la hoja de metrados respectiva 1 1,047.52 1047.52
03.07.00 ELIMINACION DE DEMOLICIONES DE ESTRUCTURAS 982.74 M3
eliminacion de escombros
de albaileria 1.3 308.34 400.84
de estructuras 1.3 167.36 217.57
del metrado de alcantarilla Illpa(Porotoyo) 1.3 280.26 364.34
03.08.00 ELIMINACION DE DEMOL. DE CANAL EN CONCRETO 563.69 M3
de la hoja de metrados respectiva 1 563.69 563.69
03.09.00 ELIMINACION DE DEMOL. DE CANAL EN MAMPOSTERIA 3,890.79 M3
de la hoja de metrados respectiva 1 3,890.79 3890.79
04.00.00 CONCRETOS
04.01.00 CONCRETO F'C= 140 KG/CM2 + 30% PM - M3
de la hoja de metrados resumen de obras de arte 1 - 0.00
04.02.00 CONCRETO FC=175 KG/CM2 PARA REVESTIMIENTO DE CANALES 1,331.92 M3
de la hoja de metrados correspondiente 1 1,331.92 1331.92
04.03.00 CONCRETO F'C= 175 Kg/cm2 P/OBRAS DE ARTE 316.36 M3
de la hoja de metrados de obras de arte 1 104.87 104.8701
del metrado de la alcantarilla 1 211.49 211.49
04.04.00 CONCRETO F'C= 175 Kg/cm2 + 30% PM 426.55 M3
de la hoja de metrado de obras de arte 1 426.55 426.5506
04.05.00 CONCRETO F'C= 210 Kg/cm2 P/OBRAS DE ARTE 65.76 M3
de la hoja de metrado de obras de arte 1 65.76 65.75625
04.06.00 PIEDRA ASENTADA Y EMBOQUILLADA #REF! M3
de la relacion de obras de arte 1 20.90 20.9025
del metrado de movimiento de tierras 1 #REF! #REF!
04.07.00 RELLENO DE FISURAS 0.24 M3
en el canal lateral A en los tramos indicados en su resp. Metrado1 64.00 0.05 0.08 0.24
05.00.00 ENCOFRADO Y DESENCOFRADO
05.01.00 ENCOFRADO Y DESENCOFRADO NORMAL 2,565.62 M2
de la hoja de metrados de obras de arte 1 1,801.34 1801.3405
del metrado de alcantarilla Illpa(Porotoyo) 1 764.28 764.278
06.00.00 ACERO DE REFUERZO
06.01.00 ACERO DE REFUERZO 23,406.02 KG
de la hoja de metrados de obras de arte 1 10,774.23 10,774.23
del metrado de alcantarilla Illpa(Porotoyo) 1 12,631.79 12,631.79
07.00.00 JUNTAS Y SELLOS
07.01.00 JUNTA WATER STOP 274.50 ML
de la hoja de metrados de obras de arte 1 147.10 147.1
del metrado de alcantarilla Illpa(Porotoyo) 1 127.40 127.4
07.02.00 JUNTAS ASFALTICAS 7,895.99 ML
Total juntas asfalticas del canal 1 7,895.99 7895.99
de las obras de arte 1 - 0.00
08.00.00 VARIOS
08.01.00 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) 214.00 UND
de los volumenes de concreto 1 2,140.59 10.00 214.00
08.02.00 PRUEBAS DE CONTROL DE COMPACTACION - UND
en el canal principal y tramos a ser reemplazados 1 - 25.00 -
08.03.00 COMPUERTA LATERAL TIPO IZAJE0.50X0.50 M - UND
de la hoja resumen de metrados 0.00 0
08.04.00 COMPUERTA LATERAL TIPO IZAJE0.50X0.40 M - UND
de la hoja resumen de metrados 0.00 0
ING. RESIDENTE DE OBRA V B SUPERVISOR VB DIRECTOR DE OBRAS
OBRA :
META : 6+170 al 10+000 , 0+000 al 1+023 C.P. - A
PROGRESIVA : 6+885.55 , 7+570065, 7+674.45, y C.P. - A 0+235.40, 0+447.50, 0+691.55, 0+793.55, 1+007.40
N COQUIS OBRA ARTE PARTIDA UNIDAD CANTIDAD LARGO ANCHO ALTO PARCIAL TOTAL
1.00 MOVIMIENTO DE TIERRAS 0.00
1.01 Estribos m3 0.00
1.02 Zapata m3 0.00
2.00 C Fc`=175 kg/cm2 +30% PM 0.00
2.01 Estribos m3 0.00
2.02 Zapata m3 0.00
3.00 C Fc`=175 kg/cm2 0.00
3.01 losa m3 0.00
3.02 sardinel m3 0.00
4.00 ENCOFRADOS 0.00
4.01 losa m2 0
4.02 tapas costado m2 0
4.03 tapas interior m2 0
4.04 estribos m2 0
4.05 costados m2 0
4.06 tapas costado zapata m2 0
4.07 tapas laterales zapata m2 0
5.00 eliminacin mat. Excedente 0.00
5.01 estribos y zapata m3 0.00
6.00 relleno compactado 0.00
6.01 losa costados m3 0.00
7.00 barabndas 11.10
7.01 baranda F 1 1/2^ ML 2.00 5.55 11.10
ACEROS DE REFUERZO
N PARTIDA UNIDAD N VECES CANTIDADLONGITUD PESO F` PARCIAL TOTAL
1.00 ACEROS 0.00
1.01 f long. inferior losa kg 0.56 0.00
1.02 f trans. inferior losa kg 1.02 0.00
1.03 f long.superior losa kg 0.56 0.00
1.04 f trans.superior losa kg 0.56 0.00
1.05 As sardinel kg 1.02 0.00
1.06 As sardinel estribos kg 0.56 0.00
ING. RESIDENTE DE OBRA VB SUPERVISOR VB DIRECTOR DE OBRAS
CUADRO DE METRADOS PASE PEATONAL
GOBIERNO REGIONAL PUNO
PRORRIDRE
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR
AFEC. PPTAL :
D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
1
XXXXXXXX
TOPOGRAFO
01231736 01/11/09
5/20/1963 HORIZONTE 231491CSYMR0
X X X X X X D X X X X X X D X X X X X X D X X X X X X X
LEYENDA.
DIAS LABORADOS : (X), FERIADOS : (FE), DIAS NO LABORADOS : ( ) DOMINICALES (D)
ING. RESIDENTE
TAREO PERSONAL DEL MES DE NOVIEMBRE - 2009
MES - NOVIEMBRE
No APELLIDOS Y NOMBRES CARGO D.N.I.
FECHA
NACIMIENTO
AFP COD.AFILIADO
V B ING. SUPERVISOR
FECHA DE
INGRESO
V B DIRECTOR DE OBRAS ASISTENTE ADMINISTRATIVO
25
TAREO PERSONAL DEL MES DE NOVIEMBRE - 2009
MES - NOVIEMBRE
TOTAL
OBRA : CONSTRUCCION DE CANAL PRINCIPAL PROG. 10+820 AL 15+820 MODALIDAD DE EJECUCION : ADMINISTRACION DIRECTA DEPARTAMENTO : PUNO
ENT. EJEC. : PRORRIDRE - PRASTER FECHA DE INICIO DE OBRA : 17 DE ABRIL DEL 2010 PROVINCIA : AYAVIRI - AZANGARO
ENT. FIN. : GOBIERNO REGIONAL PLAZO DE EJECUCION : 165 DIAS CALENDARIOS DISTRITO : ORURILLO - ASILLO
FECHA : SETIEMBRE DEL 2010 FECHA DE TERMINO DE LA OBRA : 28 DE OCTUBRE DEL 2010 SECTOR : POSOCONI
N P N J N P N J N P N J N P N J N P N J N P N J N P N J N P N J N P N J
A) PERSONAL PROFESIONAL 3 495.00 3 0 0 0 0 0 0 0 0 0 - - - - - - - - 0 0.00% 495 100.00%
1 Ing. Supervisor 1 165 1 0 0.00% 165 100.00%
2 Ing Residente de Obra 1 165 1 0 0.00% 165 100.00%
3 Ing. Asistente de Obra 1 165 1 0 0.00% 165 100.00%
B) PERSONAL ADMINISTRATIVO 2 330.00 0 0 0 0 0 0 0 0 0 0 - - - - - - - - 0 0.00% 330 100.00%
1 Asistente Administrativo 1 165 0 0.00% 165 100.00%
2 Almacenero 1 165 0 0.00% 165 100.00%
3 Chofer Camioneta 1 165 0 0.00% 165 100.00%
C) PERSONAL TECNICO 6 825.00 0 0 0 0 0 0 0 0 0 0 - - - - - - - - 0 0.00% 660 80.00%
1 Topografo 1 165 0 0.00% 165 100.00%
2 Nivelador 1 165 0 0.00% 165 100.00%
3 Maestro de Obra/ Capataz 1 165 0 0.00% 165 100.00%
4 Tecnico Laboratorista 1 165 0 0.00% 165 100.00%
5 Tecnico en Ingenieria 1 165 0 0.00% 165 100.00%
6 Controlador Oficial 1 165 0 0.00% 165 100.00%
D) PERSONAL OBRERO 78 148,003.52 0 0 0 0 0 0 0 0 0 0 - - - - - - - - 0 0.00% 137,678 93.02%
1 Operario 10 19,641.60 0 0.00% 19,642 100.00%
2 Oficial 10 18,402.71 0 0.00% 18,403 100.00%
3 Peon 52 99,633.36 0 0.00% 99,633 100.00%
4 Peon (para curado y proteccion) 4 8,100.69 0 0.00% 8,101 100.00%
5 Auxiliar Perforista 1 24.94 - - 25 100.00%
6 Oficial Cerchero 1 2,200.23 - - 2,200 100.00%
TOTAL 89 149,654 3 0 0 0 0 0 0 0 0 0 - - - - - - - - 0 0.00% 139,163 92.99%
AVANCE (%) 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% - - - - 0.00% 100.00%
N P: N DE PERSONAL
N J: N DE JORNAL
ING. RESIDENTE
GOBIERNO REGIONAL PUNO
PRORRIDRE
N JORNAL
PROG.
N
PERSONAL
PROG.
DESCRIPCION DEL PERSONAL N
CUADRO CONTROL DE PERSONAL DE OBRA
SETIEMBRE NOVIEMBRE DICIEMBRE
JORNAL
ACUMULADO
JORNAL
SALDO
M E S E S
N J %
AGOSTO
NJ %
OCTUBRE ABRIL
V B DIRECTOR DE OBRAS
MAYO JUNIO JULIO
ASISTENTE ADMINISTRATIVO V B ING. SUPERVISOR
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA DE TERMINO DE LA OBRA SECTOR
ITEM CARGO CANT. MES COSTO CONTRATO DETALLE JUN JUL AGO SET OCT NOV DIC
SUB TOTAL
ACUMULADO
SUB TOTAL
OBS.
1 S/. 40,000.00 PORCENTAJE
MONTO - - - - -
2 S/. 40,000.00 PORCENTAJE 8.75% 5.25% 14.00% 14.00%
MONTO - - 3,499.90 2,100.00 - 5,599.90 5,599.90
3 S/. 40,000.00 PORCENTAJE -
MONTO - - - - - - -
4 S/. 20,000.00 PORCENTAJE
MONTO
5 S/. 20,000.00 PORCENTAJE
MONTO
6 S/. 20,000.00 PORCENTAJE
MONTO
7 S/. 22,000.00 PORCENTAJE
MONTO - - - - - -
TOTAL S/. - - - - 3,499.90 2,100.00 - 5,599.90 5,599.90
C.- PERSONAL OBRERO
ITEM CARGO HH COSTO JUN JUL AGO SET OCT NOV DIC CANT-HH SUB TOTAL EJECUTADO
1 TOPOGRAFO 4,004.70 CANTIDAD (HH) 313.04 313.04 313.04 939.13 23.45%
S/. 23,027.00 MONTO 1,800.00 1,800.00 1,800.00 5,400.00
2 NIVELADOR CANTIDAD (HH) 438.07 1,420.65 611.21 2,469.93 18.48%
MONTO 2,475.10 8,026.67 3,453.33 13,955.10
3 OPERARIO S/. 75,534.60 CANTIDAD (HH) 1,720.35 1,332.74 1,136.28 4,189.38 31.34%
MONTO 9,720.00 7,530.00 6,420.00 23,670.00
5 OFICIAL 13,172.40 CANTIDAD (HH) 1,438.89 1,188.89 1,194.44 3,822.22 29.02%
S/. 59,275.81 MONTO 6,475.00 5,350.00 5,375.00 17,200.00
6 PEON 47,257.91 CANTIDAD (HH) 3,631.75 2,838.10 3,873.02 10,342.86 21.89%
S/. 148,862.43 MONTO 11,440.00 8,940.00 12,200.00 32,580.00
7 TAREADOR PORCENTAJE
MONTO
TOTAL S/. 77,803.97 S/. 306,699.84 31,910.10 31,646.67 29,248.33 21,763.52 92,805.10 30.26%
31,910.10 31,646.67 29,248.33 21,763.52 92,805.10 30.26%
RESUMEN DE REPORTE DE PERSONAL TECNICO ADMINISTRATIVO RESUMEN DE REPORTE DE PERSONAL OBRERO
GASTO DE PERSONAL T. A. MENSUAL USO DE HORAS HOMBRE DE PERSONAL OBRERO 21,763.52
GASTO DE PERSONAL T.A. ACUMULADO S/. 5,599.90 GASTO DE MANO DE OBRA MENSUAL 29,248.33
PORCENTAJE DE GASTO DE PERSONAL T.A. ACUMULADO 559990.00% GASTO DE MANO DE OBRA ACUMULADO 92,805.10
PORCENTAJE DE USO DE MANO DE OBRA ACUMULADO 30.26%
ING. RESIDENTE ASISTENTE ADMINISTRATIVO
CUADRO DE RESUMEN DE PLANILLA DE PAGOS
ADMINISTRADOR DE OBRA
ASISTENTE ADMINISTRATIVO
A.- PERSONAL TEC. ADMINIS. SEGN EXP. TECNICO TIEMPO DE EJECUCION DE OBRA PROGRAMADO RESUMEN
SUPERVISOR DE OBRA
GOBIERNO REGIONAL PUNO
PRORRIDRE
EXPEDIENTE
V B ING. SUPERVISOR V B DIRECTOR DE OBRAS
MAESTRO DE OBRA B
TECNICO LABORATORISTA
RESIDENTE DE OBRA
ASISTENTE TECNICO DE OBRA 01
TOTAL PAGADO PLANILLAS S/.
DETALLE
TIEMPO DE EJECUCION DE OBRA PROGRAMADO RESUMEN
13,368.96
RESUMEN DE HORAS MAQUINA
OBRA :
EJECUTA : PRORRIDRE
EQUIPO : VOLQUETE DOBLE EJE MARCA : VOLVO MODELO :
PROPIETARIO PLACA :
OPERADOR MODELO :
FECHA PERIODO Desde: 01/09/09 Hasta: 30/09/09
FECHA HORAS CANT VIAJES TOTAL M3
9/1/2009 4:00:00 TRASLADO DE MATERIAL AGREGADO (HORMIGN) DESDE CANTERA - OBRA 10 150
9/2/2009 5:00:00 TRASLADO DE MATERIAL AGREGADO (HORMIGN) DESDE CANTERA - OBRA 9 135
9/3/2009 5:00:00 TRASLADO DE MATERIAL AGREGADO (HORMIGN) DESDE CANTERA - OBRA 6 90
9/4/2009
9/5/2009
9/7/2009
9/8/2009
9/9/2009
9/10/2009
9/11/2009
9/12/2009
9/14/2009
9/15/2009
9/16/2009
9/17/2009
9/18/2009
9/19/2009
TOTAL 14:00:00 25.00 375.00
VALORIZACION DE HORAS MAQUINA
MAQUINA TOTAL HORAS P.U. MONTO TOTAL OBSERVACION
14.00 120.00 1,680.00
ING. RESIDENTE ING. SUPERVISOR DIRECTOR DE OBRAS
DESCRIPCION
VOLQUETE CAP. 15 M3 SIN OBSERVACION
CONTROLADOR MAQUINARIA
RESUMEN DE HORAS MAQUINA
OBRA
EJECUTA : PRORRIDRE
EQUIPO : MEZCLADORA DE 9 P3 MARCA : MODELO :
PROPIET : PRORRIDRE CODIGO
OPERADOR MODELO :
FECHA PERIODO Desde: 01/09/09 Hasta: 30/09/09
FECHA HORAS COMBUSTIBLE
9/1/2009 8:00:00 2 Preparado de concreto para obras de arte Pase Peatonal Prog. 0+500 Ds- 01
9/2/2009 5:00:00 2 Preparado de concreto para obras de arte Pase Peatonal Prog. 0+750 Ds- 03
9/3/2009 5:00:00 1
9/4/2009 4:30:00 3
9/5/2009 4:00:00 2
TOTAL 26:30:00 10.00
VALORIZACION DE HORAS MAQUINA
MAQUINA TOTAL HORAS P.U. MONTO TOTAL OBSERVACION
0.00
ING. RESIDENTE ING. SUPERVISOR DIRECTOR DE OBRAS
MEZCLADORA DE CONCRETO SIN OBSERVACION
DESCRIPCION
CONTROLADOR MAQUINARIA
(EQUIPO LIVIANO)
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR
N MARCA PROPIETARIO UND. REND. TOTAL REND.
PLACA H-M/COMBUST. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 COMBUST.
PRORIDRE COMBUSTIBLE 2.00 2.00 2.00 2.00 2.00 2.00 2.00 14.000 0.24
HORAS 8:10:00 8:10:00 8:10:00 8:10:00 8:10:00 8:10:00 8:00:00 57:00:00 Gal./Hora
PRORIDRE COMBUSTIBLE 0.000
HORAS 0.000
PRORIDRE COMBUSTIBLE 0.000
HORAS 0.000
PRORIDRE COMBUSTIBLE 0.000
HORAS 0.000
COMISION DE REGANTES COMBUSTIBLE 0.000
HORAS 0.000
PRORIDRE COMBUSTIBLE 0.000
HORAS 0.000
TOTAL PETROLEO 200 GALONES
TOTAL GASOLINA 120 GALONES
CUADRO DEL CONTROL DEL EQUIPO MECANICO
(HORAS - COMBUSTIBLE - KILOMETRAJE)
CONTROLADOR DE MAQUINARIA
D I A S
EQUIPO Y/O MAQUINARIA
RESUMEN COMBUSTIBLE
ING RESIDENTE DE OBRA
MEZC. 01 DE CONCRETO DE 9 - 11 P3
MEZC. 02 DE CONCRETO DE 9 - 11 P3
MEZC. 03 DE CONCRETO DE 9 - 11 P3
CAMIONETA
CAMION DE APOYO
VPMPACTADORA
ING SUPERVISOR DE OBRA DIRECTOR DE OBRAS
1
2
3
4
5
6


OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR
SALDO TOTAL
RESPECTO AL
CONTRATO
CANT. P.U. PARCIAL DIC ENE FEB MAR ABR (H-M)
MONTO
(S/.)
(H - M) V-1 V-2 V-3 (H-M) (S/.) (H-M) (S/.)
1 TRACTOR SOBRE ORUGA MUNICIPALIDADA NUOA HM 1000.00 170.00 170,000.00 20.00 50.00 80.00 100.00 10.00 260.00 44,200.00 740.00 3,400 8,500 13,600 260.00 44,200.00 740.00 125,800.00
2 VOLQUETE MUNICIPALIDADA NUOA - 0.00 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
3 VOLQUETE MUNICIPALIDADA NUOA - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
4 CARGADOR FRONTAL MUNICIPALIDADA NUOA - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
5 VOLQUETE MUNICIPALIDADA NUOA - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
6 - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
7 - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
8 - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
9 - 0.00 0.00 0.00 0 0 0.00 0.00 0.00 0.00
S/. 170,000.00 44,200.00 44,200.00 125,800.00


ING. RESIDENTE DE OBRA
OBSERVACION
TOTAL
CONTROLADOR MAQUINARIA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS
TOTAL
ACUMULADO
VALORIZACIONES DE
ALQUILER DE MAQUINARIA
EN (S/.)
VALORIZACION
ACUMULADO
SALDO DE
VALORIZACION
GOBIERNO REGIONAL PUNO
PRORRIDRE
CONTROL DE VALORIZACION DE ALQUILER DE MAQUINARIA
N MAQUINARIA PROPIETARIO UND
CONTRATO TOTAL VALORIAZADO MENSUAL (HM)
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR
RESUMEN RESUMEN
HORAS MAQ CANT COMBUST
JUN JUL AG SET OCT NOV DIC ENE FEB MAR TOTAL
A EQUIPO PESADO
1.00 Volquete Volvo FM Petroleo Galn 320.00 320.00
Ope. Sr. Emiliano HM 96.66 96.66
2.00 Volquete Volvo FM Petroleo Galn 575.00 575.00
Ope. Sr. Emiliano HM 201.92 201.92
3.00 Volquete Volvo FM Petroleo Galn 585.00 585.00
Ope. Sr. Emiliano HM 193.42 193.42
4.00 Volquete Volvo FM Petroleo Galn - -
Ope. Sr. Emiliano HM - -
5.00 Cargador Frontal Cat 935G Petroleo Galn 385.00 385.00
Ope. Sr. Emiliano HM 130.00
130.00
6.00 Motoniveladora Komatsu Petroleo Galn 210.00 210.00
HM 126.75 126.75
7.00 Rodillo Liso Vibratorio Petroleo Galn 135.00 135.00
HM 84.66 84.66
8.00 Cisterna Ford Petroleo Galn 245.00 245.00
HM 69.75 69.75
9.00 cargador Frontal Fiattalis (agua) Petroleo Galn 20.00 20.00
HM 8.00
8.00
10.00 Tractor Oruga Petroleo Galn - -
HM -
-
11.00 Petroleo Galn 55.00 55.00
HM 36.00 36.00
13.00 otros (encofrado) Petroleo Galn 40.00 40.00
- - -
Total Combustible - 2,570.00 - - - 947.15 2,570.00
B EQUIPO PESADO ALQUILADO
1 Excavadora Sobre Oruga Volvo Petroleo Galn -
Ope. Sr. Emiliano HM -
2 Excavadora Sobre Oruga Cat 325 B Petroleo Galn -
Ope. Sr. Emiliano HM -
3 Cargador Frontal Cat 950F Petroleo Galn 315.00 315.00
Ope. Sr. Emiliano HM 90.00 90.00
4 Volquete F12 (Cisterna) Petroleo Galn 375.00 375.00
Ope. Sr. Emiliano HM 120.00 120.00
5 Excavadora Pequea Jhon Deeree 490E Petroleo Galn 410.00 410.00
Ope. Sr. Emiliano HM 91.83 91.83
TOTAL - 1,100.00 - - - 301.83 1,100.00
0.00 3,670.00 0.00 0.00 0.00
B EQUIPO LIVIANO
1.00 Mezcladora 11P3 -12 HP Gasolina Galn 20.50 20.50
HM 0.00
2.00 Vibradora de Mang . 1 1/2" - 8HP Gasolina Galn 9.00 9.00
HM 0.00
3.00 Motocicleta Fortte 200 Gasolina Galn 3.00 3.00
HM 0.00
4.00 Motobomba Gasolina Galn 7.00 7.00
HM 0.00
5.00 Otros(gasolina) Gasolina Galn 18.00 18.00
HM 0.00
Total Combustible 0.00 57.50 0.00 0.00 0.00 0.00 57.50
TIPO DE COMBUSTIBLE CANTIDAD H/M
PETROLEO 3,670.00 1,248.98
GASOLINA 57.50 0.00
AO 2,009 AO 2,010
R
E
S
U
M
E
N
RESUMEN DE RECURSOS DE MAQUINARIA Y EQUIPOS
MAQUINARIA, EQUIPO Y COMBUSTIBLE FECHA
N COMBUSTIBLE UNIDAD
GOBIERNO REGIONAL PUNO
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR
U.M. P.U. CANT. H/M MONTO S/. JUN JUL AGO SET OCT NOV H/M % H/M % MONTO. S/. % MONTO. S/. %
CAMIONETA PU-2325 HM 170.00 12000:00:00 85,000.00 158:20:00 158:20:00
MEZCALDORA DE CONCRETO
VIBRADORA DE CONCRETO
TEODOLITO
85,000.00 0.00 0.00 0.00 0.00
ING. RESIDENTE DE OBRA
DESCRIPCION EQUIPO LIVIANO TOTAL SALDO
TOTAL
SEGN EXPEDIENTE
PRORRIDRE
V B DIRECTOR DE OBRAS CONTROLADOR MAQUINARIA V B ING. SUPERVISOR
RESUMEN DE HORAS EQUIPO LIVIANO - MENSUAL
EJECUCION MENSUAL
SALDOS
TOTAL ACUMULADO TOTAL SALDO
SALDOS
TOTAL ACUMULADO
GOBIERNO REGIONAL DE PUNO
PRORRIDRE
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR
S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
MATERI DE FABRICACION DE BARANDA
SOLDADURA SUPERCITO E-7018 e=1/8 KLG 9 9.00 5 5 4
PINTURTA ESMALTE COLOR NARANJA GLN 2.00 2.00 0 2
PINTURA ANTI CORROSIVA GLN 2.00 2.00 0 2
THINER ESTNDAR GLN 4.00 4.00 0 4
BROCHA DE 4" UND. 6.00 6.00 0 6
MATERIALES DE FERRETERIA
CILINDROS VACIOS DE 55 gls. UND 0.00 0 0.00
BALDES VACIOS DE ACEITE DE 5 Gls. UND 0.00 0 0.00
LINTERNAS GRANDES UND 0 0 0
PILAS GRANDES X 24 UNIDADES CAJA 1 1.00 1 1 0
PLASTICO GRUESO DOBLE ANCHO, 2,5 X 100 M. ROLLO 1 1.00 1 1 0
COLCHONES DE ESPONJA PLAZA MEDIA UND 0 0 0
MATERIALES PARA CARTEL DE OBRA TOPGRAFIA
OCRE KG. 1.00 1.00 1 1 0
PINTURA ESMALTE SINTETICO ROJO GLN 2.00 2.00 1 1 1
PINTURA ESMALTE SINTETICO. BLANCO. GLN 0 0 0
PINTURA ESMALTE SINTETICO NEGRO. GLN 1 1.00 0 1
BROCHA DE 4". UND 0 0 0
BROCHA DE 2". UND 2 2.00 2 2 0
THINER GLN 3 3.00 0 3
MATERIAL PINTADO DE BARANDA
PINRURA ANTICORROSIVA ROJO OXIDO GLN 2.00 2.00 0 2
PINTURA SINTETICO ANARANJADO GLN 2.00 2.00 0 2
BROCHA DE 4" UND 0.00 0 0.00
BROCHA DE 2". UND 0.00 0 0.00
THINER GLN 4.00 4.00 0 4
4 MATERIALES DE CONSTRUCCION
YESO EN BOLSA DE 30KLG BOLSA 26 26.00 3 3 2 3 11 15
ADITIVO INCORPORADO
ATERE 2AER GLN 70 70.00 6 5 11 59
19 MATERIAL DE CONSTRUCCION
PLANCHA METALICA DE 2,40MX1,2MM E=1ASTM UND 1.00 1.00 0 1
TUBERIA DE FIERRO GALVANIZADO D=11/2 E=2,00MM,X6,40M UND 0.00 0.00 0 0
TUBERIA DE FIERRO GALVANIZADO D=1/2 E=2,00MM,X6,40M UND 2 2.00 0 2
20 MATERIALES DE CONSTRUCCION 0
WATER STOP PVC DE 6" METR 104 104.00 6 24 50 24 104 0
25 MATERIALES DE CONSTRUCCION
ALAMBRON DE CONSTRUCCION DE =1/4" KG. 800 800.00 50 100 100 50 100 70 470 330
FIERRO CORRUGADO DE 3/8 X9ML VARILLA 455 455.00 5 10 6 10 10 2 5 20 10 2 13 5 32 25 9 30 194 261
FIERRO CORRUGADO DE = 1/2 X 9 ml. VARILLA 557 557.00 10 5 10 8 8 30 21 10 32 51 8 50 243 314
FIERRO CORRUGADO DE = 5/8 X 9 ml. VARILLA 31 31.00 0 31
FIERRO CORRUGADO DE 3/4X9ML VARILLA 36 36.00 0 36
ALAMBRE NEGRO N 16 KG. 2 2.00 2 2 0
ALAMBRE NEGRO N 8 KG. 224.00 224.00 15 30 20 15 30 25 35 20 5 5 24 224 0
CLAVOS DE 2" KG. 0.00 0.00 0 0
CLAVOS DE 3" KG. 94.00 94.00 20 5 10 10 5 10 1 20 5 8 94 0
CLAVOS DE 4". KG. 312 312.00 10 10 10 10 10 20 5 40 10 125 187
26 MATERIALES DE CONSTRUCCION
CLAVO DE CALAMINA KG. 5 5.00 5 5 0
3
RESUMEN DE MOVIMIENTO MENSUAL DE ALMACEN CORRESPONDIENTE AL MES DE MARZO -2008
SALD
ACT
INGR
MAR.
TOTAL
INGR
MOVIMIENTO MES DE MARZO
SALID
MES
EG
O/C
DESCRIPCION (Especificaciones Tcnicas) UND.
SAL
FEB
GOBIERNO REGIONAL DE PUNO
PRORRIDRE
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR
S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
RESUMEN DE MOVIMIENTO MENSUAL DE ALMACEN CORRESPONDIENTE AL MES DE MARZO -2008
SALD
ACT
INGR
MAR.
TOTAL
INGR
MOVIMIENTO MES DE MARZO
SALID
MES
EG
O/C
DESCRIPCION (Especificaciones Tcnicas) UND.
SAL
FEB
27 MATERIALES DE CONSTRUCCION
MADERAS
MADERA 2" X 3"X 10' AGUANO. UND. 0 0.00 0 0
MADERA 1" X 8" X 10' AGUANO. UND. 50 50.00 5 15 5 8 2 10 5 50 0
MADERA 1 1/2" X 8" X 10' AGUANO. UND. 16 16.00 6 10 16 0
ESTACAS DE MADERA 2"X 2"X 30 CM. UND 175 175.00 25 25 50 125
TRIPAY DE 4' X 8' X 18 mm, LUPUNA, CLASES D/D, (para uso en agua) PLANCHA 20 20.00 5 8 5 2 20 0
MADERA 2" X 3"X 10' CORRIENTE UND. 387 387.00 22 55 20 15 10 40 30 30 20 40 30 312 75
28 MATERIALES DE CONSTRUCCION
MADERA RROLISO V=4"X5M UND 46 46.00 6 6 40
29 MATERIALES DE CONSTRUCCION
CEMENTO PORTLAND TIPE IP X42,5KG BOLSAS 382 3000 3,382.00 178 276 178 107 156 88 128 78 280 176 150 370 350 2,515 867
36 MATERIALES DE CONSTRUCCION
ASFALTO LIQUIDO RC-250 GLN 650 650.00 0 650
INSUMOS PARA MANTENIMIENTO DE TRACTOR ORUGA
ACEITE MOTOR SAE 15W40 CAT GLN 0 0.00 0
FILTRO DE ACEITE MOTOR 1R-0739 CAT UNID 3 3.00 0 3
FILTRO DE PETROLEO 1R-0750 CAT UNID 3 3.00 0 3
FILTRO DE AIRE PRIMARIO 61-2501 CAT UNID 3 3.00 0 3
GRASA VOLVO EP-2 (36 LIBR) libras 0 0.00 0 0
HIDROLINA SHELL DONAX TC-10 W GLN 30 30.00 10 10 30
INSUMO PARA MANTENIMIENTO DE VOLQUETE
ACEITE DE MOTOR 15W40 GENUINO VOLVO GLN 0 0.00 0.0 0
FILTRO DE ACEITE L466634-3 VOLVO UNID 0 0
FILTRO DE ACEITE BY PASS 477536 VOLVO UNID 0 0.00 0 0
PERNO DE 9/16 22 ORDINARIO UNID 15 15.00 0 15
PERNO DE 9/16 21/2 ORDINARIO GRADO 8 UNID 15 15.00 0 15
CORZETAS DE TREN JUEGO DE TOLVA UNID 0 0.00 0 0
MATERIALES DE CONSTRUCCION
TUBERIA CORRUGADO HDPE N12 IBWT SOLIDA 30"X20 0038-2007 UNID 53 53.00 4 2 2 8 45
INSUMOS PARA MANTENIMIENTO DE MOTONIVELADORA
ACEITE DE MOTOR 15W40 SAE GLN 7 7.00 0 7
ANTICONGELANTE GLN 2 2.00 0 2
ACCESORIOS DE TURBO GGO 1 1.00 0 1
FOCOS DE FAROS DELANTEROS UND 2 2.00 0 2
GRASA ROJA AMR-3 LBS 36 36.00 2 1 2 5 31
RETEN DE CIGEAL DELANTERO UND 1 1.00 0 1
GRASA EPMLG1 LBS 10 10.00 0 10
ALMECENERO DE OBRA ING. RESIDENTE DE OBRA ASISTENTE ADMINISTRATIVO V B ING. SUPERVISOR V B DIRECTOR DE OBRAS
GOBIERNO REGIONAL PUNO
PRORRIDRE
CONTROL DE COMBUSTIBLE DIARIO - MES DE FEBRERO DEL 2008
(GASOLINA DE 84 - OCT)
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR
AFEC. PPTAL . COSTO DIRECTO
V S D L M M J V S D L M M J V S D L M M J V S D L M M J V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
CARTAS DE ADMINISTRACION 27.5 250 277.5
1 CAMIONETA PU-2325 3 11 10 10 10 10 15 15 84
2 CAMIONETA PU-2326 0
3 MEZCLADORA DE PRORRIDRE N 01 8 8
4 MEZCLADORA DE PRORRIDRE N 02 0
5 MEZCLADORA MARCO A. ARI ARI 2 1 2 2 2 2 2 3 1 1 1 2 1 1 21
6 MEZCLADORA MARCO A. ARI ARI 2 1 1 1 5
7 MANTENIMIENTO DE VOLQUETE XU- 2885 2 2 3 2 3 3 3 3 3 4 3 2 33
8 MOTOCICLETA PRORRIBRE 2 2 4 4 12
9 MOTOBOMBA MUNICIPIO 5 5
TOTAL 2 0 0 0 0 0 0 0 0 0 0 13 6 9 8 3 0 5 5 6 7 16 19 0 16 11 11 16 17 0 0 168 109.50
CONTROL DE COMBUSTIBLE DIARIO - MES DE FEBRERO DEL 2008
(PETROLEO D-2)
AFEC. PPTAL . COSTO DIRECTO
V S D L M M J V S D L M M J V S D L M M J V S D L M M J V
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
CARTAS DE ADMINISTRACION 27.5 250 277.5
1 CAMION DE APOYO 3 11 10 10 10 10 15 15 84
2 0
3 2 2 4 4 12
4 5 5
TOTAL 0 0 0 0 0 0 0 0 0 0 0 2 2 4 4 0 0 0 0 0 3 11 15 0 10 10 10 15 15 0 0 101 176.50
ALMECENERO DE OBRA ING. RESIDENTE DE OBRA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS ASISTENTE ADMINISTRATIVO
SALIDA
TOTAL
MES
SALDO
ACTUAL
SALIDA
TOTAL
MES
SALDO
ACTUAL
N MAQUINARIA
SALD
DC
INGR
FEB.
TOTAL
INGR
MOVIMIENTO MES DE FEBRERO
N MAQUINARIA
SALD
DC
INGR
FEB.
TOTAL
INGR
MOVIMIENTO MES DE FEBRERO
GOBIERNO REGIONAL PUNO
PRORRIDRE
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR
AFEC. PPTAL :
FECHA PROVEEDOR CANT FECHA PARTIDAS CANT
1.00 CLAVO CON CABEZA DE 2 1/2 Kg 0 1-Apr 25 25
25 1-Apr 1
25 2-Apr 1
25 3-Apr 1
25 4-Apr 1/2
25 5-Apr 1
25 6-Apr 1
25 7-Apr 1
25 8-Apr 1
25 9-Apr 1
25 10-Apr 1
25 11-Apr 1
25 12-Apr 1/2
10 35 13-Apr 1
35 14-Apr 1
35 15-Apr 1
35 16-Apr 1/2
35 17-Apr 1/2
35 18-Apr 1/2
35 19-Apr 1/2
35 20-Apr 1/2
35 21-Apr 1
35 22-Apr 1/2
35 23-Apr 1/2
35 24-Apr 1/2
35 25-Apr 1
35 26-Apr 1
35 27-Apr 1/2
35 28-Apr 1
35 29-Apr 1/2
35 30-Apr 1
2.5 37.5 1-May 1/2
37.5 2-May 1
37.5 3-May 1/2
37.5 20-Oct 1/2
2.00 ALAMBRE N 16 KG 37.5 20-Oct 1/2
ALMACENERO DE OBRA ASISTENTE ADMINISTRATVO RESIDENTE DE OBRA SUPERVISOR DE OBRA DIRECTOR DE OBRAS
CUADRO DE RESUMEN DEL MOVIMIENTO DIARIO DE ALMACEN
ITEM MATERIAL UND
SALDO
ANTERIOR
INGRESO
INGRESO
ACUMULADO
EGRESO
25
24
23
22
21 1/2
20 1/2
19 1/2
18 1/2
17 1/2
16 1/2
15 1/2
14 1/2
14
23
22
21
20 1/2
20
19 1/2
19
18 1/2
17 1/2
17
16 1/2
16
15
14
13 1/2
12 1/2
12
11
13
12
11 1/2
11
10 1/2
CUADRO DE RESUMEN DEL MOVIMIENTO DIARIO DE ALMACEN
SALDO
GOBIERNO REGIONAL PUNO
PRORRIDRE
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR
AFEC. PPTAL :
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE
1.00 CLAVO CON CABEZA DE 2 1/2 Kg 0
2.00 CEMENTO PORTALND TIPO I X 42.5 KG.Und. 7000 100 250 350
3.00 FIERRO DE 3/8 Var. 250
4.00 FIERRO DE 1/2 Var. 300
5.00 FIERRO DE 5/8 Var. 200
6.00 FIERRO DE 3/4 Var. 30
7.00 ALAMBRE N 16 Kg 50
8.00
9.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
0
ALMACENERO DE OBRA ASISTENTE ADMINISTRATVO RESIDENTE DE OBRA SUPERVISOR DE OBRA DIRECTOR DE OBRAS
AO - 2010
CUADRO DE RESUMEN DEL MOVIMIENTO MENSUAL DE ALMACEN
ITEM MATERIALES UND
CANTIDAD
SEGN
EXPEDIENTE
CANTIDAD
ACUMULADA
6650
CUADRO DE RESUMEN DEL MOVIMIENTO MENSUAL DE ALMACEN
SALDO
Pgina 28
OBRA MODALIDAD DE EJECUCION
ENT. EJEC. FECHA DE INICIO DE OBRA
ENT. FIN. PLAZO DE EJECUCION
FECHA FECHA DE TERMINO DE LA OBRA
1.00 RECURSOS DE MANO DE OBRA
MONTO ANTERIOR DEL MES ACTUAL PRECIO PRECIO
REFERENCIAL ACUMULADO H/H ACUMULADO UNIT. REAL PARCIAL
(S/.) H/H H/H S/. S/.
6.5.11.10
1 23,027.00 1,643.86 313.04 1,956.90 5.75 11,252.20
2 3,155.89 611.21 3,767.10 5.65 21,284.10
3 75,534.60 6,159.29 1,136.28 7,295.58 5.65 41,220.00
4 59,275.81 7,300.00 1,194.44 8,494.44 4.50 38,225.00
5 OFICIAL 148,862.43 13,746.03 3,873.02 17,619.05 3.15 55,500.00
6 PEON 248.00 248.00 5.00 1,240.00
306,699.84 32,253.07 7,128.00 39381.07 168,721.30
(*) El Operador de Maquinaria segn Expediente Tcnico se considerara su aporte en el Rubro de Maquinaria y Equipo
2.00 RECURSOS DE MATERIALES
MONTO ANTERIOR DEL MES ACTUAL PRECIO PRECIO
N DESCRIPCIN UND REFERENCIAL ACUMULADO CANTIDAD ACUMULADO UNITARIO PARCIAL
CANTIDAD CANTIDAD S/. S/.
6.5.11.29 MATERIALES DE CONSTRUCCIN
MATERIAL CONSIDERADO EN EL EXPEDIENTE
1 Alambre negro # 16 kg S/. 8,939.51 447.00 80.00 527.00 3.30 S/. 1,739.10
2 Alambre negro # 8 kg S/. 2,961.56 499.00 86.00 585.00 3.20 S/. 1,872.00
3 Clavos para madera con cabeza de 3" kg S/. 2,190.81 221.00 58.00 279.00 3.50 S/. 976.50
4 Tuberia pvc sel para instalaciones electricas de 1" m S/. 1,859.55
65 Grass kg S/. 1,406.16
MATERIAL NO CONSIDERADO EN EL EXPEDIENTE
INSUMOS PARA REPARACION DE TUBERIAS
1 Tuberia Pvc Iso 4422 Uf C-7.5 Dn 200 Mm C/Anillo Und
6 Union De Reparacion Pvc Uf Dn 200 Mm C/Anillo Und.
7 Union Reparacion Pvc Uf Dn 63 Mm C/Anillo Und
SUB-TOTAL S./ S/. 17,357.58 #REF!
6.5.11.30 BIENES DE CONSUMO
1 Herramientas manuales Glb S/. 8,392.21 9,669.00 9,669.00 1.00 S/. 9,669.00
TOTAL S/. 8,392.21 S/. 9,669.00
6.5.11.32 PASAJES Y GASTOS DE TRANSPORTE
1 Transporte de materiales a obra Glb S/. 25,000.00
2 Movilizacion y desmovilizacion de maquinaria y equipo Glb S/. 60,000.00
TOTAL S/. 85,000.00
6.5.11.39 OTROS SERVICIOS DE TERCEROS
1 Control de calidad en conformacion de sub-base Glb S/. 7,500.00
2 Control de calidad en conformacion de base Glb S/. 10,000.00
3 Control de calidad en asfaltos Glb S/. 5,000.00
4 Control de calidad en concretos Glb 3000
TOTAL S/. 25,500.00
3.00 MAQUINARIAY EQUIPO
MONTO ANTERIOR DEL MES ACTUAL PRECIO PRECIO
UND REFERENCIAL ACUMULADO CANTIDAD ACUMULADO UNITARIO PARCIAL
CANTIDAD(HM/HH) (HM/HH) CANTIDAD (HM/HH) S/. S/.
EQUIPO PESADO (MAQUINARIA PROPIA)
1 Volquete Volvo FM 750006 (**) S/. 565,384.67 1,144.89 96.66 96.66 60.00 5,799.60
2 Volquete Volvo FM 750007 (**) 1,048.14 201.92 201.92 60.00 12,115.08
11 Camioneta Verde (**) - 36.00 36.00 14.10 507.50
12 Operadores de Maquinaria Pesada (*) 7,635.98 1,518.70 9,154.68 5.65 51,723.96
SUB-TOTAL S/. S/. 565,384.67 TOTAL S/. S/. 70,146.14
N CATEGORIA
RETRIBUCIONES Y COMPLEMENTOS - CONTRATOS A PLAZO FIJO
TOPOGRAFO
NEVELADOR
REPORTE FINANCIERO DE RECURSOS EMPLEADOS DEL COSTO DIRECTO
MAESTRO DE OBTRA / CAPATAZ
OPERARIO
TOTAL S./
6.5.11.52 ALQUILER DE DE BIENES MUEBLES
Pgina 29
EQUIPO PESADO (MAQUINARIA ALQUILADA)
1 Rodillo Neumatico Autopropulsado 81-100hp 5.5-20 Ton S/. 9,369.17 16.00
2 Rodillo Tandem Vibratorio Autopropulsado 70-100hp 7-9 Ton S/. 9,759.55 14.00
3 Excavadora Sobre Oruga Volvo S/. 305,938.19 199.91 199.91 206.00 41,181.46
Planta de asfalto de 30/60 ton/h S/. 32,792.09 13.00
Secador de aridos S/. 6,636.49 14.00
Camion cisterna F12 120.00 120.00 75.00 9,000.00
SUB-TOTAL S/. S/. 364,495.49 S/. 50,181.46
COMBUSTIBLES Y LUBRICANTES (CORRESPONDIENTE A LA MAQUINARIA Y EQUIPOS)
1 Petroleo(no contemplados en el expediente tecnico) 17,767.00 3,670.00 21,437.00 9.95 213,298.15
2 lubricantes y repuestos(no contemplados en el expediente tecnico) 18,295.93 18,295.93 1.00 18,295.93
3 Gasolina 57.50 57.50 10.00 575.00
4 OTROS GLB 1.00
SUB-TOTAL S/. S/. 232,169.08
(**); El costo de Hora Maquina del equipo pesado unicamente se asume el costo de mantenimiento aproximado
EQUIPO LIVIANO
1 Mezcladora De Concreto 9 -11 P3 17,099.18 -
2 Vibradora de Concreto 8HP con manguera de1 1/2 x6m (*) 1,105.41 4,224.00 4,224.00 1.00 4,224.00
4 Motobomba Cent. 4"x4" de 13HP Marca Honda(*) 2,121.95 3,996.00 3,996.00 1.00 3,996.00
5 Manguera de Succion de agua de 4" x 6m -
6 Manguera de Descarga de agua de 4" x 40m PVC Tipo Manga -
7 Miras y jalones 6,246.45 -
16 Tanque Estacionario/incluye pintado (*) 19,178.50 19,178.50 1.00 19,178.50
17 Cortadora de madera (encofrado)(*) 178.00 178.00 1.00 178.00
S/. 26,572.98 SUB-TOTAL S./ S/. 27,576.50
TOTAL BIENES MUEBLES S/. 956,453.13 S/. 380,073.18
(*); COMPRA DE EQUIPO LIVIANO
6.5.11.65 ALQUILER DE BIENES INMUEBLES
1 Amacen y/o residencia Glb 3,000.00 600.00 100.00 700.00 1.00 700.00
S/. 3,000.00 S/. 700.00
COSTO DIRECTO TOTAL S./ S/. 1,402,402.77 TOTAL S./ #REF!
SUB-TOTAL S/.
SUB-TOTAL S/.
OBRA MODALIDAD DE EJECUCION
ENT. EJEC. FECHA DE INICIO DE OBRA
ENT. FIN. PLAZO DE EJECUCION
FECHA FECHA DE TERMINO DE LA OBRA
1.00 GASTOS GENERALES
MONTO ANTERIOR ACTUAL PORCENTAJE
N SEGN EXPEDIENTE ACUMULADO MES ACTUAL ACUMULADO ACUMULADO
(S/.) (%)
6.5.11.27 SERVICIOS NO PERSONALES 136,000.00 21,889.36 7,220.00 29,109.36 21.40%
1.00 RESIDENTE DE OBRA 40,000.00
3.00 ASISTENTE TECNICO DE OBRA 01 40,000.00 3,253.23 1,600.00 4,853.23 12.13%
4.00 ASISTENTE ADMINISTRATIVO 3,253.23 1,600.00 4,853.23 12.13%
5.00 MAESTRO DE OBRA A 22,000.00
6.00 ALMACENERO DE OBRA 16,000.00 1,830.00 900.00 2,730.00 17.06%
7.00 GUARDIAN 18,000.00 3,074.00 1,730.00 4,804.00 26.69%
12.00 1,525.00 750.00 2,275.00 #REF!
13.00 5,273.90 640.00 5,913.90 #REF!
14.00 3,680.00 3,680.00 #REF!
6.5.11.30 BIENES DE CONSUMO 17,205.73 12,225.00 12,225.00 71.05%
1.00 Cuaderno de obra incluye legalizado 300.00 300.00 300.00 100.00%
2.00 Papel A4 ( 4 millares) 360.00 360.00 360.00 100.00%
3.00 toner para impresora laser 2,000.00
4.00 tinta para plotter(juego) 800.00
5.00 computadora c/impresora 2,750.00 2,648.00 2,648.00 96.29%
6.00 Utiles varios 3,495.73 2,802.00 2,802.00 80.15%
7.00 Implemento de Seguridad 7,500.00 6,115.00 6,115.00 81.53%
6.5.11.51 EQUIPAMIENTO Y BIENES DURADEROS 2,000.00 1,547.00 1,547.00 77.35%
2.00 Mobiliario de oficinas de supervision y Residencia 2,000.00 1,547.00 1,547.00 77.35%
TOTAL GASTOS GENERALES(S/.) 155,205.73 35,661.36 7,220.00 42,881.36 27.63%
3.00 SUPERVISION DE OBRA
MONTO ANTERIOR ACTUAL PORCENTAJE
N REFERENCIAL ACUMULADO MES ACTUAL ACUMULADO ACUMULADO
(S/.) (%)
6.5.11.33 GASTOS DE ESTUDIO 66,078.47
1.00 40,000.00
2.00 20,000.00
3.00 6,078.47
6.5.11.49 LIQUIDACION DE OBRA 27,822.51
1.00 Servicio de Liquidacion tecnico financiero 27,822.51
TOTAL MENSUAL DEL COSTO INDIRECTO DEL EXPEDIENTE S/. #REF!
TOTAL MENSUAL DEL COSTO INDIRECTO MENSUAl S/. #REF! #REF!
TOTAL MENSUAL DEL COSTO INDIRECTO ACUMULADO S/. #REF! #REF!
ING RESIDENTE ASIETNTE ADMINISTRATIVO VB SUPERVISOR V B DIRECTOR DE OBRAS
CATEGORIA
CATEGORIA
Ingeniero Supervisor de Obra
Asistente Tecnico de Supervision
Utiles de Escritorio
REPORTE FINANCIERO DE RECURSOS EMPLEADOS DEL COSTO INDIRECTO
OBRA MODALIDAD DE EJECUCION
ENT. EJEC. FECHA DE INICIO DE OBRA S/.
ENT. FIN. PLAZO DE EJECUCION
FECHA FECHA DE TERMINO DE LA OBRA
S/.
MONTO VALOR VALOR ACTUAL VALOR SALDOS
REFERENCIAL ANTERIOR ( Segn doc probatorios ) ACUMULADO %
S/- S/. S/. S/. S/.
1.0 3,477,814.22 139,472.97 (139,472.97) - 0.00% 3,477,814.22
2.6.23.43 306,699.84 139,472.97 (139,472.97) - 0.00% 306,699.84
2.6.23.44 BIENES
2.6.23.45 1,682,309.52 - 0.00 - 0.00% 1,682,309.52
2.6.23.46 1,488,804.86 - - - 0.00% 1,488,804.86
2.0 206,205.73 43,436.56 11,670.00 55,106.56 26.72% 151,099.17
2.6.23.43 306,699.84 PRECIO #VALUE! - 0.00% 306,699.84
2.6.23.44 BIENES
2.6.23.45 1,682,309.52 - 0.00 - 0.00% 1,682,309.52
2.6.23.46 1,488,804.86 - - - 0.00% 1,488,804.86
3.0 66,078.47 #REF! - - 0.00% 66,078.47
2.6.23.43 306,699.84 1,475.10 (1,475.10) - 0.00% 306,699.84
2.6.23.44 BIENES
2.6.23.45 1,682,309.52 - #VALUE! IMPORTE 0.00% -
2.6.23.46 1,488,804.86 - - - 0.00% 1,488,804.86
TOTAL INVERSION 10,705,726.86 0.00 127,802.97 - 55,106.56 0.51% 10,650,620.30
0.51%
1.41%
V B SUPWEVISOR
PERSONAL
SERVICIOS
OTROS
AVANCE FISICO ACUMULADO
ING. RESIDENTE V B DIRECCION DE OBRAS
SERVICIOS
AVANCE FINANCIERO ACUMULADO
OTROS
OTROS
GASTOS GENERALES (5.92918% CD)
PERSONAL
GASTOS DE SUPERVISION DE OBRA (1.90%)
SERVICIOS
ITEM R U B R O OBSERVACIONES
COSTO DIRECTO
PERSONAL
RESUMEN DE INVERSION - FINANCIERA
Monto de Financiamiento 3,795,310.00
Inversin Total 55,106.56
GASTO PORC. CALCULADO 1.45%