Start of Project
Start: 31-08-09 ID: 0 Start: 31-08-09 ID: 2
Finish: 28-02-13 Dur: 1096 days Milestone Date: 31-08-09 Finish: 30-09-09 Dur: 27 days
Comp: 0% ID: 1 Res:
Brick Work
Start: 02-05-11 ID: 15
Finish: 01-10-12 Dur: 445 days
Comp: 0%
Page 1
Sanitary & Plumbing
Start: 25-05-11 ID: 36
Finish: 15-11-12 Dur: 464 days
Comp: 0%
External
Start: 16-07-12 ID: 45
Finish: 15-11-12 Dur: 106 days
Res:
Flooring
Start: 30-05-11 ID: 46
Finish: 15-09-12 Dur: 408 days
Comp: 0%
Page 2
Page 3
Foundation RCC up to plinth
Start: 15-09-09 ID: 3 Start: 01-10-09 ID: 4
Finish: 31-10-09 Dur: 41 days Finish: 27-02-10 Dur: 129 days
Res: Res:
Stilt floor
Start: 01-03-10 ID: 6
Finish: 30-04-10 Dur: 53 days
Res:
Page 4
Page 5
Page 6
1st floor 2nd floor 3 floor
Start: 01-05-10 ID: 7 Start: 01-07-10 ID: 8 Start: 01-09-10 ID: 9
Finish: 30-06-10 Dur: 52 days Finish: 31-08-10 Dur: 53 days Finish: 30-10-10 Dur: 52 days
Res: Res: Res:
Page 7
Page 8
Page 9
4th floor 5th floor 6th floor
Start: 01-11-10 ID: 10 Start: 01-01-11 ID: 11 Start: 01-03-11 ID: 12
Finish: 31-12-10 Dur: 53 days Finish: 28-02-11 Dur: 50 days Finish: 30-04-11 Dur: 53 days
Res: Res: Res:
Page 10
Page 11
Page 12
7th floor Terrace floor
Start: 02-05-11 ID: 13 Start: 01-07-11 ID: 14
Finish: 30-06-11 Dur: 52 days Finish: 30-07-11 Dur: 26 days
Res: Res:
Stilt floor
Start: 10-05-11 ID: 26
Finish: 10-06-11 Dur: 28 days
Res:
Page 13
Page 14
Electrical
Start: 30-05-11 ID: 75
Finish: 30-01-13 Dur: 525 days
Res:
Page 15
2nd floor 3 floor 4th floor
Start: 01-09-11 ID: 18 Start: 01-11-11 ID: 19 Start: 02-01-12 ID: 20
Finish: 31-10-11 Dur: 52 days Finish: 31-12-11 Dur: 53 days Finish: 28-02-12 Dur: 50 days
Res: Res: Res:
Page 16
Stilt floor 1st floor 2nd floor
Start: 25-05-11 ID: 37 Start: 15-08-11 ID: 38 Start: 15-10-11 ID: 39
Finish: 15-06-11 Dur: 19 days Finish: 15-09-11 Dur: 28 days Finish: 15-11-11 Dur: 27 days
Res: Res: Res:
Stilt floor
Start: 30-05-11 ID: 56
Finish: 30-06-11 Dur: 28 days
Res:
Page 17
Page 18
5th floor 6th floor 7th floor
Start: 01-03-12 ID: 21 Start: 01-05-12 ID: 22 Start: 02-07-12 ID: 23
Finish: 30-04-12 Dur: 52 days Finish: 30-06-12 Dur: 53 days Finish: 31-08-12 Dur: 53 days
Res: Res: Res:
Page 19
3 floor 4th floor 5th floor
Start: 15-12-11 ID: 40 Start: 15-02-12 ID: 41 Start: 16-04-12 ID: 42
Finish: 16-01-12 Dur: 28 days Finish: 15-03-12 Dur: 26 days Finish: 15-05-12 Dur: 26 days
Res: Res: Res:
Page 20
Miscellaneous Work
Start: 15-12-11 ID: 74
Finish: 15-02-13 Dur: 368 days
Res:
Page 21
Terrace floor
Start: 01-09-12 ID: 24
Finish: 01-10-12 Dur: 26 days
Res:
Page 22
6th floor 7th floor
Start: 15-06-12 ID: 43 Start: 15-08-12 ID: 44
Finish: 16-07-12 Dur: 27 days Finish: 15-09-12 Dur: 28 days
Res: Res:
Page 23
Page 24
Page 25
7th floor
Start: 30-08-12 ID: 63
Finish: 15-09-12 Dur: 15 days
Res:
Page 26
Page 27
Page 28
Page 29
Handing over of building
Start: 01-01-13 ID: 76
Finish: 28-02-13 Dur: 51 days
Res:
Page 30
Critical Summary Critical External