Scheduled Project Excavation

Start of Project
Start: 31-08-09 ID: 0 Start: 31-08-09 ID: 2
Finish: 28-02-13 Dur: 1096 days Milestone Date: 31-08-09 Finish: 30-09-09 Dur: 27 days
Comp: 0% ID: 1 Res:

R.C.C. WORK FOR SUPERSTRUCTURE


Start: 01-03-10 ID: 5
Finish: 30-07-11 Dur: 444 days
Comp: 0%

Brick Work
Start: 02-05-11 ID: 15
Finish: 01-10-12 Dur: 445 days
Comp: 0%

Internal Plastering & waterproofing


Start: 10-05-11 ID: 25
Finish: 15-10-12 Dur: 450 days
Comp: 0%

Page 1
Sanitary & Plumbing
Start: 25-05-11 ID: 36
Finish: 15-11-12 Dur: 464 days
Comp: 0%

External
Start: 16-07-12 ID: 45
Finish: 15-11-12 Dur: 106 days
Res:

Flooring
Start: 30-05-11 ID: 46
Finish: 15-09-12 Dur: 408 days
Comp: 0%

Doors & Windows


Start: 30-05-11 ID: 55
Finish: 15-09-12 Dur: 408 days
Comp: 0%

Painting ( Internal + External)


Start: 20-06-11 ID: 64
Finish: 28-01-13 Dur: 505 days
Comp: 0%

Page 2
Page 3
Foundation RCC up to plinth
Start: 15-09-09 ID: 3 Start: 01-10-09 ID: 4
Finish: 31-10-09 Dur: 41 days Finish: 27-02-10 Dur: 129 days
Res: Res:

Stilt floor
Start: 01-03-10 ID: 6
Finish: 30-04-10 Dur: 53 days
Res:

Page 4
Page 5
Page 6
1st floor 2nd floor 3 floor
Start: 01-05-10 ID: 7 Start: 01-07-10 ID: 8 Start: 01-09-10 ID: 9
Finish: 30-06-10 Dur: 52 days Finish: 31-08-10 Dur: 53 days Finish: 30-10-10 Dur: 52 days
Res: Res: Res:

Page 7
Page 8
Page 9
4th floor 5th floor 6th floor
Start: 01-11-10 ID: 10 Start: 01-01-11 ID: 11 Start: 01-03-11 ID: 12
Finish: 31-12-10 Dur: 53 days Finish: 28-02-11 Dur: 50 days Finish: 30-04-11 Dur: 53 days
Res: Res: Res:

Page 10
Page 11
Page 12
7th floor Terrace floor
Start: 02-05-11 ID: 13 Start: 01-07-11 ID: 14
Finish: 30-06-11 Dur: 52 days Finish: 30-07-11 Dur: 26 days
Res: Res:

Stilt floor 1st floor


Start: 02-05-11 ID: 16 Start: 01-07-11 ID: 17
Finish: 31-05-11 Dur: 26 days Finish: 31-08-11 Dur: 53 days
Res: Res:

Stilt floor
Start: 10-05-11 ID: 26
Finish: 10-06-11 Dur: 28 days
Res:

Page 13
Page 14
Electrical
Start: 30-05-11 ID: 75
Finish: 30-01-13 Dur: 525 days
Res:

Page 15
2nd floor 3 floor 4th floor
Start: 01-09-11 ID: 18 Start: 01-11-11 ID: 19 Start: 02-01-12 ID: 20
Finish: 31-10-11 Dur: 52 days Finish: 31-12-11 Dur: 53 days Finish: 28-02-12 Dur: 50 days
Res: Res: Res:

1st floor 2nd floor 3 floor


Start: 11-07-11 ID: 27 Start: 12-09-11 ID: 28 Start: 12-11-11 ID: 29
Finish: 10-09-11 Dur: 54 days Finish: 11-11-11 Dur: 53 days Finish: 12-01-12 Dur: 53 days
Res: Res: Res:

Page 16
Stilt floor 1st floor 2nd floor
Start: 25-05-11 ID: 37 Start: 15-08-11 ID: 38 Start: 15-10-11 ID: 39
Finish: 15-06-11 Dur: 19 days Finish: 15-09-11 Dur: 28 days Finish: 15-11-11 Dur: 27 days
Res: Res: Res:

Stilt floor 1st floor


Start: 30-05-11 ID: 47 Start: 30-08-11 ID: 48
Finish: 30-06-11 Dur: 28 days Finish: 15-09-11 Dur: 15 days
Res: Res:

Stilt floor
Start: 30-05-11 ID: 56
Finish: 30-06-11 Dur: 28 days
Res:

Page 17
Page 18
5th floor 6th floor 7th floor
Start: 01-03-12 ID: 21 Start: 01-05-12 ID: 22 Start: 02-07-12 ID: 23
Finish: 30-04-12 Dur: 52 days Finish: 30-06-12 Dur: 53 days Finish: 31-08-12 Dur: 53 days
Res: Res: Res:

4th floor 5th floor 6th floor


Start: 13-01-12 ID: 30 Start: 15-03-12 ID: 31 Start: 16-05-12 ID: 32
Finish: 14-03-12 Dur: 53 days Finish: 15-05-12 Dur: 53 days Finish: 16-07-12 Dur: 53 days
Res: Res: Res:

Page 19
3 floor 4th floor 5th floor
Start: 15-12-11 ID: 40 Start: 15-02-12 ID: 41 Start: 16-04-12 ID: 42
Finish: 16-01-12 Dur: 28 days Finish: 15-03-12 Dur: 26 days Finish: 15-05-12 Dur: 26 days
Res: Res: Res:

2nd floor 3 floor 4th floor


Start: 31-10-11 ID: 49 Start: 30-12-11 ID: 50 Start: 28-02-12 ID: 51
Finish: 15-11-11 Dur: 14 days Finish: 16-01-12 Dur: 15 days Finish: 15-03-12 Dur: 15 days
Res: Res: Res:

1st floor 2nd floor 3 floor


Start: 30-08-11 ID: 57 Start: 31-10-11 ID: 58 Start: 30-12-11 ID: 59
Finish: 15-09-11 Dur: 15 days Finish: 15-11-11 Dur: 14 days Finish: 16-01-12 Dur: 15 days
Res: Res: Res:

Stilt floor 1st floor 2nd floor


Start: 20-06-11 ID: 65 Start: 01-09-11 ID: 66 Start: 01-11-11 ID: 67
Finish: 05-07-11 Dur: 14 days Finish: 30-09-11 Dur: 26 days Finish: 30-11-11 Dur: 26 days
Res: Res: Res:

Page 20
Miscellaneous Work
Start: 15-12-11 ID: 74
Finish: 15-02-13 Dur: 368 days
Res:

Page 21
Terrace floor
Start: 01-09-12 ID: 24
Finish: 01-10-12 Dur: 26 days
Res:

7th floor Terrace floor


Start: 17-07-12 ID: 33 Start: 15-09-12 ID: 34
Finish: 17-09-12 Dur: 54 days Finish: 15-10-12 Dur: 26 days
Res: Res:

External Plastering & waterproofing


Start: 02-07-12 ID: 35
Finish: 30-10-12 Dur: 104 days
Res:

Page 22
6th floor 7th floor
Start: 15-06-12 ID: 43 Start: 15-08-12 ID: 44
Finish: 16-07-12 Dur: 27 days Finish: 15-09-12 Dur: 28 days
Res: Res:

5th floor 6th floor 7th floor


Start: 30-04-12 ID: 52 Start: 30-06-12 ID: 53 Start: 30-08-12 ID: 54
Finish: 15-05-12 Dur: 14 days Finish: 14-07-12 Dur: 13 days Finish: 15-09-12 Dur: 15 days
Res: Res: Res:

4th floor 5th floor 6th floor


Start: 28-02-12 ID: 60 Start: 30-04-12 ID: 61 Start: 30-06-12 ID: 62
Finish: 15-03-12 Dur: 15 days Finish: 15-05-12 Dur: 14 days Finish: 14-07-12 Dur: 13 days
Res: Res: Res:

3 floor 4th floor 5th floor


Start: 02-01-12 ID: 68 Start: 01-03-12 ID: 69 Start: 01-05-12 ID: 70
Finish: 30-01-12 Dur: 25 days Finish: 30-03-12 Dur: 26 days Finish: 30-05-12 Dur: 26 days
Res: Res: Res:

Page 23
Page 24
Page 25
7th floor
Start: 30-08-12 ID: 63
Finish: 15-09-12 Dur: 15 days
Res:

6th floor 7th floor External


Start: 02-07-12 ID: 71 Start: 01-09-12 ID: 72 Start: 01-10-12 ID: 73
Finish: 30-07-12 Dur: 25 days Finish: 29-09-12 Dur: 25 days Finish: 28-01-13 Dur: 103 days
Res: Res: Res:

Page 26
Page 27
Page 28
Page 29
Handing over of building
Start: 01-01-13 ID: 76
Finish: 28-02-13 Dur: 51 days
Res:

Page 30
Critical Summary Critical External

Noncritical Critical Inserted External


Project: Scheduled Project Critical Milestone Inserted Project Summary
Date: 11-06-14
Milestone Critical Marked Highlighted Critical

Critical Summary Marked Highlighted Noncritical