PROCEDURE

a) To located the suitable station for the pipeline passage the reconnaissance survey was do.
To give the different ratio between each passage, set the passage as figures below.
Marked them with wooden pickets.



b) Bench mark or temporary benchmark was choose to set the early back sight. Make sure
the bench mark or temporary bench mark is clear and fix.
c) The leveling survey from station P to station S was conducted. All readings are taken at
the same instrument position since the station still in sight.







d) The fly works was do to close back to station P, after all the readings has been settled.




e) All data in booking form was recorded.