Activity Predecessors Normal duration Crash duration Normal cost Crash cost Crash cost per day A 6 5 $60 $90 $30 B 7 4 $50 $150 $33 C A 6 4 $100 $160 $30 D A 7 7 $30 $30 N/A E B 5 4 $70 $85 $15 F C 9 7 $40 $120 $40 G D,E 7 4 $50 $230 $60 $400 ACTIVITY MAXIMUM CRASH DAYS NO OF DAYS CRASHED ACTUAL CRASH COST ACTUAL ACTIVITY DURATION NETWORK PATHS A 1 1 30.00 $ 5 ACF 17 B 3 0 $0 7 ADG 17 C 2 2 $60 4 BEG 17 D 0 0 N/A 7 E 1 0 $0 5 F 2 1 $40 8 G 3 2 $120 5 TOTAL CRASH COST 250.00 $