DEAD LINE 17

total cost $650


Activity Predecessors Normal duration Crash duration Normal cost Crash cost Crash cost per day
A 6 5 $60 $90 $30
B 7 4 $50 $150 $33
C A 6 4 $100 $160 $30
D A 7 7 $30 $30 N/A
E B 5 4 $70 $85 $15
F C 9 7 $40 $120 $40
G D,E 7 4 $50 $230 $60
$400
ACTIVITY MAXIMUM CRASH DAYS NO OF DAYS CRASHED ACTUAL CRASH COST ACTUAL ACTIVITY DURATION NETWORK PATHS
A 1 1 30.00 $ 5 ACF 17
B 3 0 $0 7 ADG 17
C 2 2 $60 4 BEG 17
D 0 0 N/A 7
E 1 0 $0 5
F 2 1 $40 8
G 3 2 $120 5
TOTAL CRASH COST 250.00 $