MAADEN ALUMINA

REFINERY PROJECT

MAADEN ALUMINA
REFINERY PROJECT

CONTENTS
PROJECT HSE & QUALITY POLICY
ELECTRICAL WORK SCOPE
SITE PLOT PLAN & SUBSTATION LOCATION
AREA WORK PLAN
SUBSTATION HANDOVER FROM ARCHI
ENERGIZATION PLAN
STATUS OF MAJOR ELECTRICAL ITEMS
ELECTRICAL EQPT S/S DELIVERY PLAN
ELECTRICAL WORK SCHEDULE
ORGANIZATIONAL CHART
MANPOWER & EQUIPMENT MOBILIZATION
SITE LAYDOWN PLAN
WORK PROCEDURES

PROJECT HSE & QUALITY POLICY

ELECTRICAL WORK SCOPE

SITE PLOT PLAN & SUBSTATION LOCATION

AREA WORK PLAN

RED SIDE

WHITE
SIDE

Cooling Water (1100 S/S)


Digestion South (1130 S/S)
Bauxite Handling (1310 S/S)
Digestion North (1110 S/S)
Steam Plant (1350 S/S)
Bauxite Unloading (1300 S/S)
Bauxite Grinding (1320 S/S)
Residue Storage (1340 S/S)
Infra Bldg 1 (1010 S/S)
Infra Bldg 2 (1020 S/S)
Infra Bldg 3 (1030 S/S)

Main Plant (1200 S/S)


Mud Washing (1160 S/S)
Hydrate Product Washing (1220 S/S)
Hydrate Seed Filter (1240 S/S)
Precipitation (1260 S/S)
Mud Separation (1180 S/S)

AREA WORK PLAN

SUBSTATION HANDOVER FROM ARCHI


2013-Apr-30

2013-Jun-20

230kV / 34.5kV SS

Mud Separation(1180 S/S)


2013-May-15

Steam Plant(1350 S/S)

OUT OF SCOPE

2013-May-20

Precipitation(1260 S/S)

230kV

2013-May-20

Existing 230kV
Smelter SS

INFRA BLDG.1 (1010 S/S)


2013-June-15

INFRA BLDG.2 (1020 S/S)


34.5kV

2013-May-20

INFRA BLDG.3 (1030 S/S)


2013-May-20

Cooling Water (1100 S/S)


2013-May-20

Digestion North(1110 S/S)

2013-June-15

Digestion South(1110 S/S)


2013-June-30

Hydrate Seed Filter(1240 S/S)


2013-Jul-30

Bauxite Handling(1310 S/S)


2013-Jul-30

Bauxite Unloading(1300 S/S)


2013-Jul-30

Bauxite Grinding(1320 S/S)


2013-Jun-20

Mud Washing(1160 S/S)


2013-Jun-30

Hydrate Product Washing(1220 S/S)


2013-Aug-30

Residue Storage(1340 S/S)

ENERGIZATION PLAN
2013-Oct-30

2013-Dec-20

230kV / 34.5kV SS

Mud Separation(1180 S/S)


2013-Nov-10

Steam Plant(1350 S/S)

OUT OF SCOPE

2013-Nov-20

Precipitation(1260 S/S)

230kV

2014-Mar-15

Existing 230kV
Smelter SS

INFRA BLDG.1 (1010 S/S)


2014-Mar-20

INFRA BLDG.2 (1020 S/S)


2014-Mar-25

34.5kV

INFRA BLDG.3 (1030 S/S)


2013-Nov-30

Cooling Water (1100 S/S)


2013-Dec-10

Digestion North(1110 S/S)

2013-Dec-30

Digestion South(1110 S/S)


2014-Jan-10

Hydrate Seed Filter(1240 S/S)


2014-Jan-20

Bauxite Handling(1310 S/S)


2014-Jan-30

Bauxite Unloading(1300 S/S)


2014-Feb-10

Bauxite Grinding(1320 S/S)


2014-Feb-20

Mud Washing(1160 S/S)


2014-Feb-28

Hydrate Product Washing(1220 S/S)


2014-Mar-10

Residue Storage(1340 S/S)

10

STATUS OF MAJOR ELECTRICAL ITEMS

N
o

Description

Earthing

Uni
t

Qty

Start date
Plan

Actual
Jan-13

Finish date
Plan

210,058

Jan-13

34.5kV HV cable

77,677

Apr13

Aug13

4.16kV cable

36,680

Jul-13

Dec13

LV & control cable

1,380,96
5

May13

Apr-14

Cable tray

49,893

Feb13

Feb13

Dec13

Transformer

80

set

Feb13

Feb13

Sep13

Swgr, MCC, UPS,


etc.

1,071

set

May13

Nov13

Flood & Street


Lighting

819

no

Jun-13

Apr-14

Plant Lighting

6,895

no

Aug-

Apr-14

Actual

Remark
s

Oct13

2 SETS OF
100MVA POWER
T/R

11

ELECTRICAL EQUIPMENT S/S DELIVERY PLAN

12

ELECTRICAL WORK SCHEDULE

13

ORGANIZATIONAL CHART

14

MANPOWER MOBILIZATION PLAN

15

EQUIPMENT MOBILIZATION

16

SITE ELECTRICAL SHOP PLAN

17

WORK PROCEDURES

18

EARTHING WORK SEQUENCE

19

CABLE TRAY WORK SEQUENCE

20

TRANSFORMER WORK SEQUENCE

21

SWITCHGEAR WORK SEQUENCE

22

CABLE PULLING WORK SEQUENCE

23

CABLE TERMINATION WORK SEQUENCE

24

SAUDIAN ELECTRICAL TRAINING

25

SAUDIAN ELECTRICAL TRAINING

26

SAUDIAN ELECTRICAL TRAINING

27

SAUDIAN ELECTRICAL TRAINING

28