You are on page 1of 46

PROJECT EXECUTION PLAN Rev.

00
ALABANG TOWN CENTER BPO 1
Alabang Town Center, Brgy, Ayala Alabang, Muntinlupa City
May 5, 2014

Makati Development Corporation

16 Pt. Project Execution Plan


Project Information

Temporary Works &


Site Logistics

Risk Management

Table of Organization

EHS Plan

Procurement

QA Plan

Asset Management

Program & Planning

Contract Management

Design Production

Operating Budget

Value Engineering &


Innovation

Sustainability, CSR &


Environment

Construction Methods

Project Close - Out

Makati Development Corporation

Project Information
Resource Assignment
OPCEN Head : Napoleon P. Micaller
Project Manager : Jodel M. Ebero
Project-in-Charge : Dennis I. Tomaneng

Contract Details
Contract Package : Fixed Lump Sum
Contract Amount : Php 956,170,901.47
Start Date

Design Consultants
Structural : TandeM Engineering
& Consultancy
Architectural : Aidea Architects

Completion Date :

Mechanical : Westrim

Duration

Electrical : EB Cruz

: 16 months

Plumbing/Sanitary : NBF Consulting Inc.


Fire Pro : NBF Consulting Inc.
Makati Development Corporation

Project Description
Project Name
: Alabang Town Center BPO 1
Project Location : Alabang Town Center, Brgy. Ayala Alabang, Muntinlupa City
Building Type
: Retail & Typical Office floors
Nature of Project : BPO Building
BUILDING CONFIGURATION:
No. of Floors
1
1
1
1
7
Total = 11 Floors

DESCRIPTION
1 - Lower Ground Floor (Parking + Utility rooms) with
provision for future tunnel connection to proposed adjacent
retail expansion
1 Ground floor (Retail)
1 - 2nd Floor (Parking + Admin office) with bridgeway
connection to existing mall
1 - 3rd Floor (Parking)
7 - 4th to 10th Floor (Office)

Total CFA: 33,083.82 sq.m.


Total GFA: 24,665.18 sq.m.
Makati Development Corporation

ALABANG TOWN CENTER


BPO - 1
ATC BPO
1

ALABANG TOWN CENTER BPO

is a 10 storey with

roofdeck building located along Madrigal Avenue and


supermarket drive. This composed of retail stores at ground
floor, parking floor levels and an office rental spaces.

Makati Development Corporation

PROGRAM AND PLANNING

VICINITY

Makati Development Corporation

PROJECT HIGHLIGHTS
PARKING AREA
CFA
Total No. of Slots
LEASABLE (RETAIL)
CFA

= 3,229.5 sqm.
= 266 slots
= 1,576.74 sqm.

Total No. of Spaces = 10 retail , 1 convenience store & 1 Bank spaces


LEASABLE (BPO)
CFA
Total No. of Office

= 15,943.83 sqm.
= 6 offices

COMMON AREA
CFA

= 8,737.94 sqm.

SERVICE AREA
CFA

= 3,035.22 sqm.

Makati Development Corporation

LOCATION MAP

MADRIGAL AVENUE

SUPERMARKET DRIVE

ATC BPO1
EXISTING
MALL

ATC MALL PARKING

Makati Development Corporation

PROJECT MILESTONES
GROUND BREAKING
:
05
GENCON AWARD DATE
:
START OF BULK EXCAVATION :
START OF STRUCTL EXCAVATION :
FIRST POURING
:
TOPPING - OFF
:
WATERTIGHNESS
:
ENERGIZATION
:
TESTING AND COMMISSIONING :
PROJECT COMPLETION
:
HANDOVER TO SBU
:
START OF TENANT FIT-OUT
:
Pre-requisites:
STRUCTURAL,
ARCHITECTURAL AND
MEPFS FCD
:
Contract awarding must be on or
before
:

APRIL 2014
21 APRIL 2014

15

Makati Development Corporation

TEMPORARY FACILITIES LAY-OUT


MC (160 TONNER)
Gate 1

PUMPCRETE STN. 1

Gate 3

PUMPCRETE
STN. 2

GENSET
TRANSLAB
FABRICATION AREA

FORMWORKS
FABRICATION AND
STAGING AREA

Gate 2
STRUCTURAL FILL
HOLDING AREA
TRANSLAB
STOCKPILE AREA
(Zone 1)
REBARS STOCKPILE
AREA

SATELLITE OFFICE
TRANSLAB
STOCKPILE AREA
(Zone 2 & 3)

CONSTRUCTION
ACCESS

Makati Development Corporation

3. CONSTRUCTION METHODS AND TEMPORARY WORKS


Start = May 19, 2014
End = June 18, 2014
4,511.86cu. m

Legend:

All excavated materials shall be hauled out a


total of 376 truck loads

Subject for excavation


Exit Point

Equipment Needed:
Item
No.
1
2
Stockpile Area

Description
Backhoe (PC
200)
Bulldozer

No. Of Units
1
1

Bulk Excavation Sequence


Makati Development Corporation

TOWER CRANE

TOWER CRANE
FOUNDATION
TOWER
CRANE MAST

30 MTS. 6.3T
40 MTS. 5.0T
50 MTS. 3.6T

TOWER CRANE LOCATION

TOWER CRANE FOUNDATION


Makati Development Corporation

PROGRAM AND PLANNING

TOWER CRANE FOUNDATION SECTION


SHOWING DISTANCE FROM LOWER GROUND FLOOR

TOWER CRANE
FOUNDATION PLAN

TOWER CRANE
FOUNDATION SECTION
Makati Development Corporation

TOWER CRANE UTILIZATION


TC
UTILIZATIO
N
SCHEDULE

7 AM to
8 AM to
9 AM to
10 AM to
11 AM to
12 NN to
13 PM to
14 PM to
15 PM to
16 PM to
17 PM to
18 PM to
19 PM to
20 PM to

ACTIVITIES


A
8 M Rebar
A
9 M Rebar
1A
0 M PRECAST TRANSLAB (STRIPPING)
1A
1 M FORMWORKS (Loose Forms)
1
2 NN FORMWORKS (Loose Forms)
1
3 PM BREAK TIME
1
4 PM REBARS
1
5 PM FORMWORKS (Gang Forms)
1
6 PM FORMWORKS (Gang Forms)
1
7 PM FORMWORKS (Gang Forms)
1
8 PM FORMWORKS (Gang Forms)
1
9 PM MEPFS
2
0 PM PRECAST WALL INSTALLATION
2
1 PM PRECAST WALL INSTALLATION

ELEVATION SHOWING
TOWER CRANE

Makati Development Corporation

Equipment Utilization Schedule


DURATION
ITEM

MAJOR EQUIPMENT

START

FINISH

2014

PEAK

2015

(mos.)
May Jun

Tower Crane - Luffer Type 50m


Radius (TC-1)

9.5

19-Jul-14

30-Apr-15

Genset 300KVA 440/220V 3PH

9.5

19-Jul-14

30-Apr-15

Genset 150KVA 230V 3PH Construction Power Source)

12.5

19-Jun-14 30-Jun-15

Genset 100KVA 230V 3PH - Off


Site Temporary Power Source)

7.0

19-Jun-14 15-Jan-15

Backhoe (PC 100)

1.0

19-Jun-14 19-Jul-14

Backhoe (PC 100)

1.0

10-Feb-15 12-Mar-15

Stake Truck

4.0

19-Sep-14 17-Jan-15

Mini-Dumptruck

3.0

19-Jun-14 18-Sep-14

Mini-Dumptruck

1.0

10-Feb-15 12-Mar-15

10 Skid Loader

3.0

19-Jun-14 18-Sep-14

11 Submersible Pump

10.0

5-Jul-14

12 Gondola (rental)

4.1

15-Apr-15 15-Aug-15

13 Air Compressor 185CFM

8.1

24-Jul-14

30-Apr-15

24-Mar-15

Jul

Aug Sept Oct

Nov Dec

Jan

Feb

Mar

Apr

1
1
1

1
1

2
3

May Jun July Aug

Makati Development Corporation

Concreting Schedule
2500

2099
2000

1358

1885

1885
1677

1554
1358

1500

1000

779.2

500

197.4
0
1

10

11

May

Jun

Jul

Aug

Sept

Oct

Nov

Dec

Jan

Feb

Mar

Makati Development Corporation

TRANSLAB FABRICATION AREA (ON-SITE)

TRANSLAB FABRICATION OUTPUT


Makati Development Corporation

TRANSLAB FABRICATION AREA (ON-SITE)


TURNAROUND
CYCLE

ACTIVITIES


7AM to 8 AM Rebar Fabrication
8 AM to 9 AM Rebar Fabrication
1
Rebar Fabrication/Formwork
9AM to 0 AM Installation/Stripping
10 AM to 11 AM Rebar Fabrication/Formwork Installation
1
11AM to 2 NN Rebar Fabrication/Formwork Installation
12 NN to 13 PM BREAK TIME
1
13PM to 4 PM Formworks/Rebar Fabrication
14 PM to 15 PM Rebar Fabrication/ MEPFS Insert
1
15PM to 6 PM Rebar Fabrication/ MEPFS Insert
16 PM to 17 PM Clean - Up
1
17PM to 8 PM Inspection
18 PM to 19 PM Concrete Pouring
2
19PM to 0 PM Concrete Pouring
20 PM to 21 PM Curing Time
2
21PM to 2 PM Curing Time
22 PM to 23 PM Curing Time
2
23PM to 4 AM Curing Time
24 PM to 1 AM Curing Time
1AM to 2 AM Curing Time
2 AM to 3 AM Curing Time
3AM to 4 AM Curing Time
4 AM to 5 AM Curing Time

TRANSLAB PRODUCTION CYCLE

TRANSLAB CASTING
BED PLAN

TRANSLAB CASTING BED SECTION


Makati Development Corporation

3. CONSTRUCTION METHODS AND TEMPORARY WORKS


ZONE 1
June 19 July 03,
2014

ZONE 4 ( Nov. 14 Nov.


21,For2014)
formworks fabrication and
staging Area
For structural backfill holding Area

Vol = 3408.21cum

re
EXCAVATION TRAFFIC SCHEME
EXIT POINT

ZONE 3

ZONE 2

July 05 July 18,


2014

July 04 July 14,


2014

Vol = 319.01 cum

Vol = 1747.35 cum

GATE 2

Structural Excavation Se
Makati Development Corporation

3. CONSTRUCTION METHODS AND TEMPORARY WORKS


ZONE 1
July 05 July 23,
2014

ZONE 4 ( Nov. 21 Nov.


28, 2014)

re

ZONE 3

ZONE 2

July 24 August 08,


2014

July 16 July 31,


2014

Foundation Concreting S
Makati Development Corporation

Cover Slab

* Imported Fill (for structural backfill) volume = 5474.57cum

ZONE 3

ZONE 2

ZONE 1

Aug. 27 Sept.
08, 2014

Aug. 22 Sept.
03, 2014

Aug. 20 Aug.
29, 2014

Slab on Grade Concreting S


Makati Development Corporation

STRUCTURAL MILESTONES
STRUCTURAL
(BELOW
GROUND)
1

EXCAVATION

FDN

Footing

Pedestal

Column 1st Lift

6
7

Cover Slab

Backfilling

11
12

ZONE 2

End

Start

End

Start

End

19-Jun-14

3-Jul-14

4-Jul-14

14-Jul-14

5-Jul-14

18-Jul-14

5-Jul-14

23-Jul-14

16-Jul-14

31-Jul-14

24-Jul-14

8-Aug-14

24-Jul-14

29-Jul-14

27-Jul-14

1-Aug-14

30-Jul-14

4-Aug-14

30-Jul-14

3-Aug-14

2-Aug-14

6-Aug-14

5-Aug-14

9-Aug-14

n/a

31-Jul-14

4-Aug-14

9-Aug-14 13-Aug-14

7-Aug-14

1-Sep-14

29-Aug14

6-Sep-14

3-Sep-14

27-Aug14

8-Sep-14

9-Aug-14 16-Aug-14

17-Aug-14 27-Aug-14 24-Aug-14

SOG/Underground
Utilities
20-Aug-14 29-Aug-14 22-Aug-14
Retaining Wall
2nd Lift
30-Aug-14 6-Sep-14 4-Sep-14
Column 2nd Lift

ZONE 3

Start

Retaining Wall 1st


Lift
n/a
Underground
Tanks
24-Jul-14

10

ZONE 1

30-Aug-14 6-Sep-14

4-Sep-14

11-Sep-14 9-Sep-14 16-Sep-14


11-Sep-14 9-Sep-14 16-Sep-14
Makati Development Corporation

ZONE 3

ZONE 2

ZONE 1

RL

Apr. 30, 2015

Apr. 23 , 2015

Apr. 25, 2015

Apr. 18, 2015

Apr. 11, 2015

Apr. 7, 2015

Mar. 31, 2015

Mar. 24, 2015

Mar. 20, 2015

Mar. 13, 2015

Mar. 6, 2015

Mar. 02, 2015

Feb. 23, 2015

Feb. 16, 2015

Feb. 12, 2015

Feb. 5, 2015

Jan. 29, 2015

Feb. 1, 2015

Jan. 25, 2015

Jan. 18, 2015

Jan. 16, 2015

Dec. 28, 2015

Dec.19, 2014

Dec. 17, 2014

Dec. 8, 2014

Dec. 1, 2014

Nov. 27, 2014

Nov. 20, 2014

Nov. 13, 2014

Nov. 11, 2014

Nov. 3, 2014

RD
10F
9F
8F
7F
6F
5F
4F
3F
2F

FW5

Oct. 26, 2014 FW4

UG

Oct. 22, 2014 FW3 Oct. 15, 2014 FW2


LG

Oct. 8, 2014 FW1

Concrete Pouring Seq


Makati Development Corporation

TABLE FORM FLY-OUT SCHEME

ZONE 3

ZONE 2

ZONE 1

Makati Development Corporation

STRUCTURAL MILESTONES
TOTAL SLAB FORMWORKS REQUIREMENTS
ZONE 1

STRUCTURAL
(ABOVE GROUND)

Start

End

ZONE 2
Start

ZONE 3
End

Start

UG

30-Aug-14 11-Sep-14

4-Sep-14

2F

14-Sep-14 26-Sep-14

19-Sep-14

1-Oct-14

24-Sep14

6-Oct-14

3F

29-Sep-14 11-Oct-14

4-Oct-14

16-Oct-14

9-Oct-14

21-Oct-14

4F

14-Oct-14 26-Oct-14

19-Oct-14

31-Oct-14

5F

29-Oct-14 11-Nov-14

5-Nov-14

17-Nov-14

6F

13-Nov-14 25-Nov-14 18-Nov-14

30-Nov-14

7F

28-Nov-14 10-Dec-14

15-Dec-14 8-Dec-14

8F

13-Dec-14 27-Dec-14 20-Dec-14

9F

28-Dec-14 13-Jan-15

10

10

16-Jan-15

28-Jan-15

11

RD

31-Jan-15 12-Feb-15

12

RL

15-Feb-15

1-Mar-15

3-Dec-14

6-Jan-15

16-Sep-14 9-Sep-14

End

5-Jan-15

24-Oct14
10-Nov14
23-Nov14
29-Dec14

21-Sep-14

6-Nov-14
22-Nov-14
5-Dec-14
20-Dec-14
14-Jan-15

18-Jan-15 11-Jan-15

23-Jan-15

21-Jan-15

2-Feb-15

26-Jan-15

7-Feb-15

5-Feb-15

17-Feb-15

10-Feb15

22-Feb-15

22-Feb-15

8-Mar-15

Makati Development Corporation

WORK ACTIVITY SEQUENCE (PER ZONE)


WORK CYCLE @ 12 DAYS
DAY
NO.
1
2
3
4
5
6
7
8
9
10

ACTIVITIES
Survey and Lay-out
Installation of Column Rebars
Installation of Column Rebars/Column
Formworks
Column Formworks/Column Concreting
Column Concreting/Preparation of Beam
Bottom and Shoring
Preparation of Beam Bottom and
Shoring/Beam Rebar Installation
Beam Rebar Installation/Installation of
Translab
Installation of Translab/Beam Siding
Beam Siding/Installation of PC Wall
Installation of PC Wall/Installation of Top
Bars
Installation of Top Bars/Electro-Mechanical
Makati Development Corporation

1. Program and Planning

ACTIVITY DESCRIPTION

Total
Quantity

Umeas

STRUCTURAL WORKS

Working
Actual
Reqd MANHours
Productivity HOURS
per day
MH/Umeas

MH

HRS

Reqd
MANDAYS

Total No.
of Days

MANPOWER

MD

Require
Current Balance
d

Concrete
13,283.86

5.00

66,419.30

10

6,641.93

246.00

27

27

65,472.35

5.00

327,361.75

10

32,736.18 246.00

134

134

kgs.

0.07

207,743.55

10

20,774.36 246.00

85

85

Formworks
Rebars
2,967,765.02

Basis for Manpower Loading


Makati Development Corporation

3. CONSTRUCTION METHODS AND TEMPORARY WORKS

ZONE 1
START

END

5-Jul-14
16-Aug-14
Concrete Vol= 569.30cum

Formworks: 2168.25sqm
Rebars: 129,714.48kgs

Underground Tanks
Makati Development Corporation

3. CONSTRUCTION METHODS AND TEMPORARY WORKS

re

ZONE 3
START

ZONE 2

END

24-Jul-14 8-Aug-14
Concrete Vol=
285.4 cum

Formworks: 313.5sqm
Rebars: 65,028.39kgs

START

END

16-Jul-14 31-Jul-14
Concrete Vol=
492.83 cum

Formworks: 323.28sqm
Rebars: 112291.6kgs

ZONE 1
START

END

5-Jul-14 23-Jul-14
Concrete Vol=
286.40 cum

Formworks: 344.9sqm
Rebars: 65256.24kgs

Foundation
Makati Development Corporation

Cover Slab

ZONE 3
START

END

27-Aug14
8-Sep-14
Concrete Vol=
122.46cum

Rebars: 27,902.35kgs

ZONE 2
START

END

22-Aug14
3-Sep-14
Concrete Vol=
122.63cum

Rebars:27,942.26kgs

ZONE 1
START

END

20-Aug-14 29-Aug-14
Concrete Vol=
87.47cum

Rebars: 19931.09kgs

Slab on Grade
Makati Development Corporation

PROJECT SCHEDULE (STRUCTURAL)

ZONEVol=
3
Concrete
Concrete
Vol=
START
END
21-Sep14
Concrete Vol=
483.21cum

9-Sep-14

Formworks: 2673.37sqm
Rebars: 110,099.39kgs

ZONE 2
START

ZONE 1

END

16-Sep14
Concrete Vol=
540.80cum

4-Sep-14

Formworks: 2892.3sqm
Rebars: 123,220.72kgs

START

END

30-Aug-14 11-Sep-14
Concrete Vol=
404.86cum

Formworks: 2336.25sqm
Rebars: 92,248.13kgs

Ground Floor
Makati Development Corporation

PROJECT SCHEDULE (STRUCTURAL)


ZONE 4
START

END

28-Nov12-20-14
14
Concrete Vol=
142.81cum

re

Formworks: 929.85sqm
Rebars: 32,538.57kgs

ZONE 3
START

ZONE 2

END

24-Sep6-Oct-14
14
Concrete Vol=
296.98cum

Formworks: 1666.25sqm
Rebars: 67,666.39kgs

START

ZONE 1

END

19-Sep1-Oct-14
14
Concrete Vol=
390.72cum

Formworks: 2148.54sqm
Rebars: 89,025.81kgs

START

END

14-Sep-14 26-Sep-14
Concrete Vol=
372.50cum

Formworks: 2122.11sqm
Rebars: 84,873.24kgs

Second Floor
Makati Development Corporation

PROJECT SCHEDULE (STRUCTURAL)

ZONE 3
START

ZONE 2

END

21-Oct14
Concrete Vol=
254.46cum

9-Oct-14

Formworks: 1493.91sqm
Rebars: 59,979.78kgs

START

END

16-Oct14
Concrete Vol=
380.68cum

4-Oct-14

Formworks: 1898.07sqm
Rebars: 86,738.67kgs

ZONE 1
START

END

29-Sep-14 11-Oct-14
Concrete Vol=
256.58cum

Formworks: 1499sqm
Rebars: 58,461.47kgs

Third Floor
Makati Development Corporation

PROJECT SCHEDULE (STRUCTURAL)

ZONE 3
START

ZONE 2

END

START

24-Oct6-Nov-14
14
Concrete Vol=
265.91cum

END

19-Oct- 31-Oct14
14
Concrete Vol=
394cum

Formworks: 1502.71sqm
Rebars: 58,436.50kgs

Formworks: 1892.65sqm
Rebars: 86,207.18kgs

ZONE 1
START

END

14-Oct-14 26-Oct-14
Concrete Vol=
295.13cum

Formworks: 1687.83sqm
Rebars: 64,678.87kgs

4th Floor
Makati Development Corporation

PROJECT SCHEDULE (STRUCTURAL)

ZONE 3
START

ZONE 2

END

START

10-Nov- 22-Nov14
14
Concrete Vol=
275.03cum

Formworks: 1549.32sqm
Rebars: 60,518.39kgs

END

17-Nov14
Concrete Vol=
359.49cum

5-Nov-14

Formworks: 1967.44sqm
Rebars: 78,178.53kgs

ZONE 1
START

END

29-Oct-14 11-Nov-14
Concrete Vol=
306.15cum

Formworks: 1744.88sqm
Rebars: 67,192.66kgs

5th Floor
Makati Development Corporation

PROJECT SCHEDULE (STRUCTURAL)

ZONE 3
START

ZONE 2

END

START

23-Nov5-Dec-14
14
Concrete Vol=
275.46cum

Formworks: 1551.66sqm
Rebars: 60,614.08kgs

END

18-Nov- 30-Nov14
14
Concrete Vol=
359.78cum

Formworks: 1968.79sqm
Rebars: 78,242.97kgs

ZONE 1
START

END

13-Nov-14 25-Nov-14
Concrete Vol=
306.58cum

Formworks: 1747.22sqm
Rebars: 67,288.36kgs

6th Floor
Makati Development Corporation

PROJECT SCHEDULE (STRUCTURAL)

ZONE 3
START

ZONE 2

END

START

20-Dec14
Concrete Vol=
275.46cum

8-Dec-14

Formworks: 1551.66sqm
Rebars: 60,614.08kgs

END

15-Dec14
Concrete Vol=
359.78cum

3-Dec-14

Formworks: 1968.79sqm
Rebars: 78,242.97kgs

ZONE 1
START

END

28-Nov-14 10-Dec-14
Concrete Vol=
306.58cum

Formworks: 1747.22sqm
Rebars: 67,288.36kgs

7th Floor
Makati Development Corporation

PROJECT SCHEDULE (STRUCTURAL)

ZONE 3
START

ZONE 2

END

START

29-Dec- 14-Jan14
15
Concrete Vol=
275.46cum

Formworks: 1551.66sqm
Rebars: 60,614.08kgs

END

20-Dec5-Jan-15
14
Concrete Vol=
359.78cum

Formworks: 1968.79sqm
Rebars: 78,242.97kgs

ZONE 1
START

END

13-Dec-14 27-Dec-14
Concrete Vol=
306.58cum

Formworks: 1747.22sqm
Rebars: 67,288.36kgs

8th Floor
Makati Development Corporation

PROJECT SCHEDULE (STRUCTURAL)

ZONE 3
START

ZONE 2

END

START

11-Jan- 23-Jan15
15
Concrete Vol=
275.46cum

Formworks: 1551.66sqm
Rebars: 60,614.08kgs

END

18-Jan15
Concrete Vol=
359.92cum

6-Jan-15

Formworks: 1969.22sqm
Rebars: 78,275.43kgs

ZONE 1
START

END

28-Dec-14 13-Jan-15
Concrete Vol=
306.73cum

Formworks: 1747.64
Rebars: 67,320.83kgs

9th Floor
Makati Development Corporation

PROJECT SCHEDULE (STRUCTURAL)

ZONE 3
START

ZONE 2

END

START

26-Jan7-Feb-15
15
Concrete Vol=
275.38cum

Formworks: 1549.53sqm
Rebars: 60,595.58kgs

END

21-Jan2-Feb-15
15
Concrete Vol=
364.18cum

Formworks: 1986.24sqm
Rebars: 79,246.3kgs

ZONE 1
START

END

16-Jan-15 28-Jan-15
Concrete Vol=
308.03cum

Formworks: 1751.82sqm
Rebars: 67618.52kgs

10th Floor
Makati Development Corporation

PROJECT SCHEDULE (STRUCTURAL)

ZONE 3
START

ZONE 2

END

START

10-Feb- 22-Feb15
15
Concrete Vol=
269.8cum

Formworks: 1569.31sqm
Rebars: 61,474.75kgs

END

17-Feb15
Concrete Vol=
357.21cum

5-Feb-15

Formworks: 2036.37sqm
Rebars: 81,390.9kgs

ZONE 1
START

END

31-Jan-15 12-Feb-15
Concrete Vol=
311.6cum

Formworks: 1839.47sqm
Rebars: 70,998.75kgs

Roof Deck
Makati Development Corporation

PROJECT SCHEDULE (STRUCTURAL)

ZONE 2
START

END

22-Feb8-Mar-15
15
Concrete Vol=
97.98cum

Formworks: 576.54sqm
Rebars: 22,325.26kgs

ZONE 1
START

END

15-Feb-15 1-Mar-15
Concrete Vol=
146.31cum

Formworks: 863.26sqm
Rebars: 33337.68kgs

Roof Level
Makati Development Corporation

TOPPING OFF
March 10,
2015

ZONE 3

ZONE 2

RDECK
10TH
9TH FLOOR

Architectural Wet Works

8TH FLOOR

ZONE 1

1.
2.
3.
4.
5.
6.
7.

Rubcon
Instln of Arty Wall
Instln of Steel Doors
Waterproofing
Conc. Topping/Tiling Works
Instln of Ceiling Frame
Initial Paint Application

1.
2.

Instln of Perporated ACP


Instln of Curtain Wall

1.
2.
3.
4.
5.

Drywall/Ceiling Works
Metals
Tiling Works/Granite
Specialty Works
Final Painting

7TH FLOOR
6TH FLOOR
5TH FLOOR

Building Envelope

4TH FLOOR
3RD FLOOR
2

ND

FLOOR

UG FLOOR

Architectural Dry Works

Project Schedule (Constructio


Makati Development Corporation

Roof Deck
Waterproofing (Apr.
21, 2015)
RDECK

ZONE 3

ZONE 2

ZONE 1

Mar. 22 Apr. 21, 2015

10TH FLOOR Mar. 08 Apr. 07, 2015


9TH FLOOR Feb. 21 Mar. 23, 2015
8TH FLOOR Feb. 06 Mar. 08, 2015
7TH FLOOR Jan. 28 Feb. 27, 2015
6TH FLOOR Jan. 03 Feb. 10, 2015
5TH FLOOR Dec. 19, - Jan. 26, 2015
4TH FLOOR Dec. 06 Jan. 13, 2015
3RD FLOOR Nov. 20 Dec. 30, 2014
2ND FLOOR Nov. 04 Dec. 26, 2014
UG FLOOR Oct. 20 Dec. 01, 2014
LG FLOOR Oct. 05 Nov. 14, 2014

Project Schedule (Architectural


Makati Development Corporation

Building
Watertightness
(May 18, 2014)
RDECK

May 04 May 18, 2015

10TH

Apr. 23 May 07, 2015

ZONE 3

ZONE 2

ZONE 1

9TH FLOOR Apr. 12 Apr. 26, 2015


8TH FLOOR Apr. 01 Apr. 15, 2015
7TH FLOOR

Mar. 21 Apr. 4, 2015

6TH FLOOR Mar. 10 Mar. 24, 2015


5TH FLOOR Feb. 27 Mar. 13, 2015
4TH FLOOR Feb. 16 Mar. 02, 2015
3RD FLOOR Feb. 05 Feb. 19, 2015
2ND FLOOR Jan. 25 Feb. 08, 2015
UG FLOOR Jan. 05 Jan. 28, 2015

Project Schedule (Building E


Makati Development Corporation

Building Handover

ZONE 3

ZONE 2

ZONE 1

(Aug. 21,
2015)
RDECK

Jul. 28 Aug. 21, 2015

10TH

Jul. 14 Aug. 11, 2015

9TH FLOOR Jun. 30 July 28, 2015


8TH FLOOR June 16 Jul. 14, 2015
7TH FLOOR Jun. 02 Jun. 30, 2015
6TH FLOOR May 19 Jun. 16, 2015
5TH FLOOR

May 05 June 2, 2015

4TH FLOOR Apr. 21 May 19, 2015


3RD FLOOR Apr. 07 May 05, 2015
2ND FLOOR Mar. 24 Apr. 21, 2015
UG FLOOR Mar. 10 Apr. 07, 2015
LG

Jul. 21 Aug. 21, 2015

Project Schedule (Architectural


Makati Development Corporation

You might also like