ID Task Name Duration Start Finish Jan 10, '10 Jan 17, '10 Jan 24, '10 Jan

Jan 10, '10 Jan 17, '10 Jan 24, '10 Jan 31, '10 Feb 7, '10 Feb 14,
F S T T S M W F S T T S M W F S T T S M
1
INTERIOR 29 days Mon 1/11/10 Fri 2/12/10

2 GROUND FLOOR 22 days Mon 1/11/10 Thu 2/4/10


3 walls, columns and hallway p 10 days Mon 1/11/10 Thu 1/21/10
4 beams and slab plastering 14 days Mon 1/11/10 Tue 1/26/10
5 slab on fill concreting 8 days Mon 1/11/10 Tue 1/19/10
6 blackboards 5 days Fri 1/22/10 Wed 1/27/10
7 stairs finishing 8 days Wed 1/27/10 Thu 2/4/10
8 SECOND FLOOR 15 days Wed 1/27/10 Fri 2/12/10
9 columns and hallway plasteri 5 days Wed 1/27/10 Mon 2/1/10
10 under slab plastering 14 days Wed 1/27/10 Thu 2/11/10
11 floor topping 5 days Tue 2/2/10 Sat 2/6/10
12 blackboards 5 days Thu 1/28/10 Tue 2/2/10
13 stairs finishing 5 days Mon 2/8/10 Fri 2/12/10
14 THIRD FLOOR 29 days Mon 1/11/10 Fri 2/12/10
15 hallway CHB installation 2 days Mon 1/11/10 Tue 1/12/10
16 walls, columns and hallway p 7 days Wed 1/27/10 Wed 2/3/10
17 floor topping 5 days Tue 2/2/10 Sat 2/6/10
18 roofing 7 days Wed 1/20/10 Wed 1/27/10
19 ceiling and eaves 14 days Thu 1/28/10 Fri 2/12/10
20 blackboards 5 days Wed 2/3/10 Mon 2/8/10
21 EXTERIOR 25 days Thu 1/14/10 Thu 2/11/10
22 plastering 20 days Wed 1/20/10 Thu 2/11/10
23 concreting of canopies 7 days Thu 1/14/10 Thu 1/21/10
24 PAINTING 20 days Sat 1/16/10 Mon 2/8/10
25 interior 20 days Sat 1/16/10 Mon 2/8/10
26 exterior 20 days Sat 1/16/10 Mon 2/8/10
27 ELECTRICAL 10 days Thu 1/28/10 Mon 2/8/10
28 fixtures 10 days Thu 1/28/10 Mon 2/8/10
29 PLUMBING 10 days Thu 1/28/10 Mon 2/8/10
30 fixtures 10 days Thu 1/28/10 Mon 2/8/10
31
DEMOBILIZATION 1 day Sat 2/13/10 Sat 2/13/10

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: NHA 45DAYS
Progress Rolled Up Milestone Group By Summary
Date: Sat 1/9/10
Milestone Rolled Up Progress Deadline
Summary Split