CONSTRUCTION PROJECT MANAGEMENT


Seatwork no. 2
SEWER and WATER LINES
1. Draw the network diagram.
2. What is the earliest finish of the
project in days?
3. Which of the following gives the
critical path?
4. When will be the project
completion?
5. Tabulate activities schedule.

NOTE:
Project Start Date : April 1, 2002
5 working days
No work for holidays

Activit
y

Description

Duration

Predecesso
r

Move on Site

Survey Sewer Lines

Excavate for Manholes

Install Manhole
Formworks

Place Concrete Manhole

Trench Sewer line

10

Strip Manhole Formwork

Lay Sewer Pipe

15

Inspect Manhole

G, H

Remove trenching
Equipment

Backfill Sewer trench

Sewer Line Complete

I,J,K

Survey Water Line A

Survey Water Line B

Underground Electrical

Drill water well

12

Trench Water Line A

Lay pipe for Water Line


A

Trench Water Line B

16

N,Q

Backfill Water Line A

Lay pipe for Water Line


B

14

R,S

Backfill Water Line B

T,U

Install Water meters

Set Water pumps

Project Complete

V,W, X

prepared by

cHiNg

PROJECT SCHEDULING :
Activity

Description

Duration

Predecessor

Move on Site

Survey Sewer Lines

Excavate for Manholes

Install Manhole Formworks

Place Concrete Manhole

Trench Sewer line

10

Strip Manhole Formwork

Lay Sewer Pipe

15

Inspect Manhole

Remove trenching Equipment

Backfill Sewer trench

Sewer Line Complete

I,J,K

Survey Water Line A

Survey Water Line B

Underground Electrical

Drill Water well

12

Trench Water Line A

Lay pipe for Water Line A

Trench Water Line B

16

N,Q

Backfill Water Line A

Lay pipe for Water Line B

14

R,S

Backfill Water Line B

T,U

Install Water meters

Set Water pumps

Project Complete

V,W, X