Material

List of required material for construction is shown below:

When stored at site, materials such as rebar and Angle must be kept off the ground and
shall be covered by vinyl sheet. Other materials used for backfilling shall be timely transported
to the site.
Nominal diameter and permissible deviation are specified in table below:
No.

Internal diameter

Specified thickness

BxH (mm)

Permissible
deviation
(mm)

Specified
thickness
(mm)

Permissible
deviation (mm)

800x1400

10

150

+5

800x1650

10

150

+5

6. Equipment and Tools


List of required equipment and tools for construction is shown below:

7. Construction Procedure
Work Sequence for Technical Trench

Install Top
Install
Slab
Cable Support & Grounding

Survey
Backfill and Cleaning up Site
(Location & Line marking)

Casting conerete

Form Removal and Site Cleaning