Project Status Report

TapChat AAC
11/19/2015
PROJECT STATUS:

Yes

No

Status Summary

ON-TRACK

AT-RISK

CRITICAL ISSUES

Explanation
(If answered yes, provide a brief explanation.)

1. Has the scope changed or is it about to be


impacted?

Target audience for application has changed from autistic


users to users that have difficulty with vocal
communication.

2. Have the deliverables/objectives changed?

Client decided on additional change to user stories.

3. Are there sponsorship/stakeholder issues?

4. Are there new risks?

5. Are there productivity problems affecting the


team's ability to perform the work?
6. Are there resourcing problems?

X
X

7. Is a deliverable/milestone about to be missed?

8. Has the estimated schedule changed?

9. Is the quality of the deliverables being affected?

10. Are there any other major issues?

Translators to provide translations of sufficient quality for


all languages are not readily available.

KEY ACCOMPLISHMENTS

Implementation of ability to change application language to English (US), Spanish (Spain), Chinese (Simplified), German, and
Turkish
Functionality to reset application to defaults
Addition of tab for typed text-to-speech
Creation of test cases and acceptance tests for iteration
Update of paperwork on website

KEY ISSUES/CHALLENGES

Difficulty in contacting translator for French language


Change in user stories requested by client.

UPCOMING MILESTONES/ACTIVITIES

Completion of user manual/quick start guide (English only)


Continued work on tweaks to application based on user acceptance testing

Project Status Report


TapChat AAC
11/19/2015
Project Status Summary

Scope

Schedule

Phase Percent Complete:

Risks

90%

Quality

The phase is ahead of schedule. All languages have been implemented except for French due to no qualified translator
agreeing to provide translation at the time of this report. In addition, development time for this phase has exceeded
expected values. However, this is not expected to impact deliverables due to an estimated 90% completion rate for
features added this iteration. Additional features being added to this iteration are to replace unimplemented features
that are no longer desired by the client. User acceptance testing of the application with end users has led to a change in
the target audience of the application from individuals with autism to people who have difficulty with vocal
communication. This change should not affect the schedule due to functionality and user stories in the application
remaining unchanged for the iteration.

Work Planned for Last Week

Design of test cases and acceptance tests for iteration 3


Coding team will implement features for iteration 3
Coding team will work on customer modifications requests
Coding team will work on tweaks in functionality and presentation of application
Update of website

Work Completed Last Week

Design of test cases and acceptance tests for iteration 3


Coding team implemented functionality to reset application to default and functionality to change the
applications language setting
Update of website