Assignment

Construction Contracts and Contracting

PGPM 14

NICMAR/CODE OFFICE
ASSIGNMENT

Course code : PGPM 14


Course title : Construction Contracts And Contracting
Assignment no : Four

Prepared By :

Rutvan Jariwala
211-08-31-9748-2131

Rutvan Jariwala
211-08-31-9748-2131

Page 1

Assignment
Construction Contracts and Contracting

PGPM 14

AIM

The assignment paper aims to understand the term contract, various


type of contract; contracting and issues occurred and resolved for
specified project.

METHODOLOGY

1. Explaining contract.
2. Types of contracts.
3. Scope of work and contract assigned for mentioned project.
4. Organisation charts.
5. Methods adopted by company.
6. Conclusions.

Rutvan Jariwala
211-08-31-9748-2131

Page 2

Assignment
Construction Contracts and Contracting

PGPM 14

CONTRACTS

A contract is a legally binding agreement between the parties


identified in the agreement to fulfill all the terms and conditions
outlined in the agreement.

A prerequisite requirement for the enforcement of a contract,


amongst other things, is the condition that all the parties to the
contract accept the terms of the claimed contract.

Contracts can be of many type, sales contracts (including leases),


purchasing contracts, partnership agreements, trade agreements, and
intellectual property agreements.

A sales contract is a contract between a company (the seller) and


a customer that where the company agrees to sell products and/or
services.

A purchasing contract is a contract between a company (the


buyer) and a supplier who is promising to sell products and/or
services within agreed terms and conditions.

A partnership agreement may be a contract which formally


establishes the terms of a partnership between two legal entities
such that they regard each other as 'partners' in a commercial
arrangement. However, those expressions may be merely a
business-expression to reflect the desire of the contracting parties
to act 'as if' both are in a partnership with common goals.
Therefore, it might not be the common law arrangement of a
partnership which by definition creates fiduciary duties and which
also has 'joint and several' liabilities.

In construction industries various type of contracts are done between


two or more than two legal parties.

Rutvan Jariwala
211-08-31-9748-2131

Page 3

Assignment
Construction Contracts and Contracting

PGPM 14

1. All in one contract


2. Lump sum contract
3. Item rate contract
4. Percentage rate contract
5. Cost plus percentage contract
6. Cost plus fixed fee contract
7. Cost plus fluctuating contract
8. Target contract
9. Labor contract
10. BOT contract

NAME OF PROJECT

Competition project from P.I.U-construction and


execution of new I.C.U. Building.

P.I.U., Gandhinagar has awarded the project of construction of new I.C.U.


Building, at Surat Municipal Government Medical Collage and Hospital to
Pankaj Patel & Associations, as their principal architects.
Some Information about Project
1.

Project is located in new civil campus, a 20 bed hospital for with


specified requirement with the provision for future growth.

2.

Requirements of project was parking ,site development, main I.C.U.


center, nursing staff facilities, facilities for doctors, facilities for
visitors and relatives, technical requirement for proper functioning of
unit, medical store, emergency and supplementary units, etc.

Rutvan Jariwala
211-08-31-9748-2131

Page 4

Assignment
Construction Contracts and Contracting

3.

Preparation

of

conceptual

PGPM 14

designs

with

3d

visionaries

and

presentation for design competition explaining design in brief with


primary technical bid and financial bid submitted separately.
4.

Selection and award of tender to selected party.

5.

Construction cost estimated for said project was 50 lakhs.

6.

Contract made was on item rate basis.

Scope of work for an architect finalized for the said project


1.

Site survey (for check)

2.

Digitizing the survey

3.

Preparing approval drawings.

4.

Getting approved from competent authority-that is in this case-P.I.U,


Gandhinagar

5.

Providing consultancy as an architect, principal designer of the


project.

6.

Preparing detail working drawings for tendering.

7.

Prepared structural design keeping in mind existing condition of site


and soil capacity.

8.

Preparing tender document*

9.

Provide all necessary drawings to contracted person, awarded as per


the Contract between authority and contractor on item rate basis.

10. Site supervision and quality control on site.


11. Acting as the moderator between contractor and PIU.
12. Checking of bills.
13. Preparing reports and submitting to authority.
14. Preparing completion report and get signed from authorized person
at the end.
Rutvan Jariwala
211-08-31-9748-2131

Page 5

Assignment
Construction Contracts and Contracting

PGPM 14

TENDER DOCUMENTS *

Tender notice

General rules and directions for the use of contractors

The letter of submission of tender

The letter of acceptance of tender

The addenda nos.

Form of contract

Conditions of contract

Schedule A showing the details of materials, if any , to be supplied


by the owner to the contractor

Schedule B bill of quantities

Specifications:
o General
o Detailed or particular

Contract drawings.

Rutvan Jariwala
211-08-31-9748-2131

Page 6

Assignment
Construction Contracts and Contracting

PGPM 14

IMPORTANT POINTS TO MENTION IN CONTRACT

Order approval: once

the

finalized

drawings

are

submitted

to

authorize body, architect is not liable to ask approval at all individual


stage. If changes in design or details occurred approval is needed.

Payment method: payment was finalized on the percentage basis of


total work to be carried out till completion of the project.
If authority suggests any changes in approved drawing would
considered as extra work and charged separately as it involves all
lengthy process of changes in specification to estimate.
Payment to be made in different stages as per percentages and
amount mutually agreed upon.

Site supervision: architect has to visit site on regular interval basis.


Site supervision charges are included in the professional charges.
Architect must appoint one qualified site supervisor on site for better
control.

Quality control: architect is responsible for providing quality work on


site. Architect is given rite to ask the agency to repair or change
(demolished and execute from start) for said work as and if required.
Agencies are bound to act accordingly as instructed by architect. No
claims for if changes suggested due to poor construction quality by
architect.

Material control: it is desired to apply the said material as per


specification .Material has to be approved by architect after on site
sampling. Changes in any material due to availability or so it needs to
bring in to awareness of architect.

Any changes or revision of quantity: if the quantum of worked to


be carried out remains same and just material changes contractor

Rutvan Jariwala
211-08-31-9748-2131

Page 7

Assignment
Construction Contracts and Contracting

PGPM 14

would pay the differences in the current rate. If new quantities are to
be added than contractor may charge as per current market rates. If
any quantity or work portion is omitted and material is purchased or
work carried out for the same, difference accruing is more than
25000/- (mutually agreed by both the parties) contractor can claim
profit. Owner has signed performance bond with contractor.

The Architect reserved the right to suggest modifications or make


complete changes in the methods proposed by the contractor.

Time line: contractor was given the time span of two years to
complete the building. If contractor fails to win time restriction he
cannot claim for profit he is liable to pay liquidated damages claimed
by owner. But if work needs to stop due to any natural calamities work
extension order may issued. Rates quoted by contractor were subject
to present market condition and valid for 1year time line only.

Technology: contract does not include any equipment installation. It


is purely a construction based contract. Installation of elevators and
HVAC control systems would require other tendering and specialized
agencies. And that was part of phase ii.

Damages due to installation: owner can claim from said agencies


for damages occurred during installation of any specialized equipment
during construction.

The contractor had to furnish sufficient plant, equipment and labour as


may be necessary to maintain the progress schedule, also he had
to submit the progress of work in prescribed forms and statements at
periodical intervals in the form of progress charts, forms, statements
and / or reports as may be approved by the engineer.

Contractor is responsible for Initial Mobilization, Establishments of


contractors

Rutvan Jariwala
211-08-31-9748-2131

camp,

work

sheds,

water

supply

arrangements,
Page 8

Assignment
Construction Contracts and Contracting

PGPM 14

electrification beyond the points of supply by the owners, internal


roads, plant, transport, foundations and erections, Purchase of plant
machinery and tools.

The contractor has to submit a monthly bill for the payment, for the
work done at site. The owner must commit himself to making
payments within a specified time. Interim or running bills should be
settled within six months, If the final bill is held by the client than an
advance to the extent of 90% may be payable to the contractor,
pending final settlement.

The most sensitive issues in contract management and many disputes


have their origin in delays in measurements or payments or
both. The engineer in charge does not turn up for measurements; bills
are prepared late, consequently delaying payments. It is necessary
that proper arrangements are made and enforced to ensure timely
measurements and payment. This will guarantee a smooth cash flow
for a contractor.

Breach of contract: if owner breach the contract after partially


executed work contractor is liable to claim the profit and damages.
Here architect is also liable to claim the fees as per work done and for
efforts given in. If contractor commits the breach of the contract than
owner is liable to receive the market price of correcting contractors
balance work.

Disputes are one of the common occurrences in construction


contracts. In construction and civil works projects execution periods
are long, many agencies get involved and imponderables are too
many. This inevitably led to extra costs, project delays and sometimes
suspension of work. Disputes arises when a demand is made by the

Rutvan Jariwala
211-08-31-9748-2131

Page 9

Assignment
Construction Contracts and Contracting

PGPM 14

party and denied by the other, one of the parties to the contract may
feel aggrieved that its rights and privileges have been violated or that
the dues payable have not been paid or short paid or paid late. All
such situations and others similar to these may lead to precipitation of
disputes.

Alternative methods of dispute resolution should be considered first.


By virtue of an agreement two parties can enter into a transaction
which may be selling, or buying any commodity, borrowing or
spending money, leasing or hiring any property, rendering any service
etc.

The legal system of a country gives its people freedom to enter into
such an agreement. Any valid agreement creates mutual rights and
obligations and also legal relations between parties entering into an
agreement. Thus the contract is an agreement, between two parties,
satisfying the conditions lay down by the contract law and hence can
be enforced by law.

In India the law of contracts is contained in the Indian Contract Act,


1872.

Different methods of dispute settlement are:

Negotiations

Mediations

Conciliation

Arbitration and

Adjudication

Rutvan Jariwala
211-08-31-9748-2131

Page 10

Assignment
Construction Contracts and Contracting

PGPM 14

ITEM RATE CONTRACT


This contract deals in measurements of each item of the work as given in bill
of quantities and sum to be paid is arrival at based on the rates quoted
against each item.
In the bill of quantities all are items are described in detail along with the
quantity.
Here the rates are part of the contract.
Problem an ambiguity occurred
Disputes raised between parties have been solved by Negotiation, is the
method of bi-party settlement of disputes without help or intervention of
third parties. While in some case architect has to act as a mediator to
resolve the issue.
While there are two three major issues where arbitrator was needed to
resolve the issues are mention below:

PROBLEM-1

Free board for tendering quantities: owner has omitted item of work and
decrease two quantities to 15% owner has increased one item as well.
Issues were variations of quantities and claims damages by contractor due
to same.
In the same way as mentioned in terms and condition owner is liable to pay
to the contractor item quoted under terms extra as per current market
rate.
Rutvan Jariwala
211-08-31-9748-2131

Page 11

Assignment
Construction Contracts and Contracting

PGPM 14

Solution:

Owner has rite to increase, decrease and omit any quantity or even
item of work. And contractor shall not claim for any damages due to
same.

Contractor is bound to execute

Such a small amount of variation from owner considered as a variation


not as error in quantity.

Contractor is only liable to claim differences as per quoted rates.

In the same way as mentioned in terms and condition owner is liable


to pay to the contractor item quoted under terms extra as per
current market rate. This clause is in support to contracture but the
added quantity was not costing more than 20,000/-. And contractor is
bound to complete the work in excess up to 10% of tendered quantity
without claiming the revised rate.

So in this case solution was contracture is bound to work on same rate


quoted in tender for increased quantities, just quantities are revised
not rate. And for new added item he can claim work on market rate
bases. But because of one extra item no need to revised tender.

Rutvan Jariwala
211-08-31-9748-2131

Page 12

Assignment
Construction Contracts and Contracting

PGPM 14

PROBLEM-2: MONITORING THE WORK

Quality and quantities:

To gain maximum out of project contractor has started manipulating


with the bills.

Using lower grade construction materials he tried to built up the profit.

Here architect has asked to change purchased material to specified


material as per the specification.

For poor construction quality he was charged for the damage and
revised the said work.

He even tried to manipulated the design given by avoiding special


techniques involves in to it.

Ex.: hand compacting rather machine compactor

Less watering to brick /masonry work

Poor plaster slurry ratio

As far as, the organisational structure for the management level is concern,
it can be talked upon as a satisfactory management achieving positive goals,
and within the stipulated area of project interest. As it is seen that the
project is running in profit and giving positive results and hence our
managers enjoy the level they are assigned to.
The SITE ORGANISATIONAL CHART is attached along herewith.

Rutvan Jariwala
211-08-31-9748-2131

Page 13

Assignment
Construction Contracts and Contracting

PGPM 14

ORGANIZATION CHART

Owner
Governing
authorityPIU

Bounded
under
contractual
obligations

Architect-As a planner
Team leader of various department such as
structural design dept, project management dept,
design and development dept, account dept, etc.
Providing detail working drawings,
working out details (dev. Department),
preparing estimate ,bill of quantity, specification,
site supervision, may/can appoint site supervisor
answerable to owner

Bounded under
contractual
obligations

CIVIL CONTRACTOR

Civil Construction as per finalized


rates and of desired quality
Material purchasing and getting
approved
Producing bills and site report
Heir agencies as and if required
for completion of the work
Answerable to both architect and
owner.

Site supervisor

Responsible for work on


site
Preparing reports
Maintains of materials
and equipments at site
level
He see to it that work do
happen as per mentioned
and specified.

Rutvan Jariwala
211-08-31-9748-2131

HVAC consultant

Responsible for HVACs


relate work proper
installation, Prepare
reports regarding same
Answerable to architect.

SPECIALISED EQUIPMENT

consultant

Responsible for
installation of the
equipments
Heir agencies as and if
required
Answerable to architect.

Electrical consultant

Responsible for work


related to electrical
installation
Report to site
supervisor
Answerable to
contractor

Plumbing and sanitation


consultant

Responsible for work


related to plumbing
and sanitation
Report to site
supervisor
Answerable to
contractor

Page 14

Assignment
Construction Contracts and Contracting

PGPM 14

CONCLUSION

Contract is the legal binding documents to all the parties.

Violence and over rule of contractual condition may lead to legal


problem.

Contract provides frame work, which distributes duties and liabilities to


all so, to run project easily and smoothly.

Contract documents are there to avoid any issues before it may


subject to occurs.

Rutvan Jariwala
211-08-31-9748-2131

Page 15

Assignment
Construction Contracts and Contracting

PGPM 14

REFERENCES

Dr.Roshan H.Namavati
Professional Practice, eighth revised edition
LAKAHNI BOOK DEPOT.

NICMAR lesson book-NCP23


JULY 2010
NICMAR PUBLICATION

Rutvan Jariwala
211-08-31-9748-2131

Page 16