Professional Documents
Culture Documents
MOTIVATION
kt / d
60
50
40
30
20
10
0
1
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Discount
rates
Years
10% 0.91 0.83 0.75 0.68 0.62 0.56 0.51 0.47 0.42 0.39 0.35 0.32 0.29 0.26 0.24 0.22 0.20 0.18 0.16 0.15 0.14 0.12 0.11 0.10 0.09 0.08 0.08 0.07 0.06 0.06 0.05 0.05
8% 0.93 0.86 0.79 0.74 0.68 0.63 0.58 0.54 0.50 0.46 0.43 0.40 0.37 0.34 0.32 0.29 0.27 0.25 0.23 0.21 0.20 0.18 0.17 0.16 0.15 0.14 0.13 0.12 0.11 0.10 0.09 0.09
6% 0.94 0.89 0.84 0.79 0.75 0.70 0.67 0.63 0.59 0.56 0.53 0.50 0.47 0.44 0.42 0.39 0.37 0.35 0.33 0.31 0.29 0.28 0.26 0.25 0.23 0.22 0.21 0.20 0.18 0.17 0.16 0.15
Discount factors
(Ref. 1)
Page 1 of 28
BC RAMP UPS
Production Ramp-up of BC Mines ____
140
130
120
110
Production, t/d
100
90
80
70
60
Teniente 4 S Sector
50
Dec. 1981
40
30
20
10
0
0
10
11
Years
(Ref. 2)
Page 2 of 28
BC RAMP UPS
Production Ramp-up of BC Mines ____
140
130
120
110
Production, t/d
100
90
80
70
Teniente 4 S Sector
60
Esmeralda, El Teniente
50
40
Sep. 1997
30
20
10
0
0
10
11
Years
(Ref. 2)
Page 3 of 28
BC RAMP UPS
Production Ramp-up of BC Mines ____
140
130
120
110
Production, t/d
100
90
Palabora Lift 1
80
Jun. 2001
70
Teniente 4 S Sector
60
50
Esmeralda, El Teniente
40
30
20
10
0
0
10
11
Years
(Ref. 3)
Page 4 of 28
BC RAMP UPS
Production, t/d
Cadia East
Dec. 2012
Palabora Lift 1
Teniente 4 S Sector
Esmeralda, El Teniente
10
11
Years
(Ref. 4)
Page 5 of 28
BC RAMP UPS
Production, t/d
NNM, El Teniente
10
2019
11
Years
(Ref. 5)
Page 6 of 28
BC RAMP UPS
Production, t/d
PMCHS,
Chuquicamata
2018
NNM, El Teniente
10
11
Years
(Ref. 6)
Page 7 of 28
BC RAMP UPS
Production, t/d
Palabora Lift 2
2018?
PMCHS, Chuquicamata
NNM, El Teniente
10
11
Years
(Ref. 3)
Page 8 of 28
BC RAMP UPS
Production, t/d
Oyu Tolgoi
2018?
Palabora Lift 2
PMCHS, Chuquicamata
NNM, El Teniente
10
11
Years
(Ref. 7)
Page 9 of 28
BC RAMP UPS
Production, t/d
Cadia East
Oyu Tolgoi
Palabora Lift 2
PMCHS, Chuquicamata
Palabora Lift 1
NNM, El Teniente
Teniente 4 S Sector
Esmeralda, El Teniente
0
10
Years
Page 10 of 28
11
ATTAINABLE BC RAMP UP
Production, t/d
Possible
Cadia East
Oyu Tolgoi
Palabora Lift 2
PMCHS, Chuquicamata
Palabora Lift 1
NNM, El Teniente
Teniente 4 S Sector
0
10
Years
Page 11 of 28
11
Esmeralda, El Teniente
How?
Extraction rate
Fragmentation size at draw point
Design of caving system
Design of materials handling system design
Risk prevention
Operational hazards: rockburst, airblast
Design hazards, due to incorrect assessment of the
ground conditions
Page 12 of 28
Preconditioning
Stresses
In situ stress
Induced stresses
Page 13 of 28
1,200 m to surface
took less than 3 years
Confined Blasting
450 m
150 m
(Ref. 3)
Page 14 of 28
Increase
undercutting rate
Increase
extraction rate
Page 15 of 28
FASTER RAMP UP
Increase undercutting rate:
Maximize undercutting velocity
Post undercutting, if possible
Establish more than one undercutting front
Undercutting front in spear shape
Split levels
Simple design
Enhance planning, equipment, services and logistics
240 m
30 m
To rim
crusher
Page 17 of 28
120 m
120 m
30 m
Ore passes to Haulage Level
Page 18 of 28
80 m
80 m
80 m
30 m
Ore passes to Haulage Level
Page 19 of 28
Productivity, t/d
4.500
4.000
3.500
3.000
2.500
2.000
0
30
60
90
120
% Extraction
(Ref. 8)
Page21 of 28
40 m
40 m
40 m
40 m
40 m
30 m
|
Page 22 of 28
0,80
0,70
0,60
0,50
0,40
0,30
0,20
0,10
0,00
LHD,
240m
LHD,
120m
LHD,
80m
RGO,
15%E
Page 23 of 28
RGO,
45%E
RGO,
75%E
RGO,
105%E
DRAW RATE:
Increased from
0.20 m/d to 0.40 m/d
RESULT:
Ramp up was shortened
from 9 to 4 years
Page 24 of 28
MUS$
455
100
1,009
222
Total increase:
554
122
400
88
154
34
Page 25 of 28
CONCLUSIONS
Intensive preconditioning of the rock mass green light for higher
extraction rates
High Undercut:
HF preconditioning:
Forced Fragmentation Blasting:
Vertical Shaft:
Page 26 of 28
REFERENCES
1.
2.
3.
4.
5.
6.
7.
8.
Mass caving maximum production capacity, Alfonso W. Ovalle, Amec International; University of Chile,
MASSMIN 2012, June 11-14, 2012, Sudbury, Ontario, CANADA
Lecciones Aprendidas Explotacin El Teniente, A. Ovalle, Set. 2006
Block caving with Rio and NCM, Credit Suisse, 27 Set 2012, Visit Report
Newcrest Mining Company Quarterly Reports
Presentacin NNM, J. Revuelta, Nov. 2013
Presentacin PMCHS, S. Fuentes, Abr. 2013
Turquoise Hill Resources Ltd. Oyu Tolgoi 2014 Technical Report, October 2014, Job N 14003, OreWin,
Independent Mining Consultants, Figure 1.7, 2014 Reserve Case processing, pg. 28
Martillos picadors semi-mviles en Teniente 4 Norte Fw, 1990. Comunicaciones con A. Moyano.
Page 27 of 28
END
Page 28 of 28