You are on page 1of 52

STARMALL PRIMA DAANG HARI

Daang Hari Corner Molino Blvd., Bacoor, Cavite

DAANG HARI

P R O J E C T CLOSE OUT R E P O R T
MASTERPIECE ASIA PROPERTIES INC.
MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

TABLE OF CONTENTS
EXECUTIVE SUMMARY

1.

PROJECT BACKGROUND
1.1

1.2

2.3

2.

Construction Phase
Project Milestone & Highlights
Construction Schedule vs Actual
Outstanding Issues
Reference Attachments

Post-Construction Phase
OSM Monitoring & Status
Hand-over of residential units and common areas status

CONTRACT CLOSE-OUT STATUS


2.1

2.1

3.

Pre-Construction Phase
Plans & Specifications
Procurement Schedule (Bidding & Award)

Technical
Technical Submittal Status
Testing & Commissioning Status
Certificate of Completion & Acceptance Summary and status
Financial
WAO & CO Summary and Status
Billing Summary and pending claims status

PROJECT TURNOVER FILES & RELEVANT INFORMATION

Project Team Directory

Project Fact Sheet

Copies of Government Permits & Licences

Site Instruction Log

Request for Information Log


Technical Submittal Log
Construction Bulletin Log

4.

PROJECT PHOTOGRAPHS (BEFORE & AFTER HANDOVER)

5.

REFERENCE ATTACHMENTS

Annex A Drawing Control Log


Annex B Procurement Schedule

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Annex C Construction Schedule

EXECUTIVE SUMMARY
The Beacon Roces Tower was substantially complete and now a landmark structure
in the area. The residential units had already been turned-over to GEDC- Customers
Relation Unit in which some of the unit owners had already move-in. Roces Tower is
now being managed by the Property Management Office, Neo Pacific.
With this, the Final Project Report will mark the end of the Post-Construction Phase of
Project Management Services.

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

This report highlights the project details, milestones, accomplishments and status for
The Beacon Roces Tower project wherein Asian Technicon Managers & Consultants
Inc has been engaged as Project Managers.
All data and information stipulated on this report will be part of Turnover Documents in
accordance to the project close-out requirements for reference and guidance of the
Owner.
Asian Technicon Managers & Consultants, Inc. and the Beacon Team are grateful to
have worked with New Pacific Resources Management Inc. together with Geo-Estate
Development Corporation and are keen, given the opportunity, to be of service with you
in the future.
Congratulations and Good Luck to New Pacific Resources Management Inc. and GeoEstate Development Corporation!

1.

PROJECT BACKGROUND

The Starmall Prima Daang Hari is a high-end mall constructed in Bacoor, Cavite,
Philippines. The Starmall Prima Daang Hari is owned and developed by Masterpiece
Asia Properties Inc.
It was designed by ASYA Design Partner (Principal Architect) with the engineering trades
A.C. Ong Consulting Inc. (Structural Design), D.L Lagman Engineering (Airconditioning
& Ventilation Design) , M.A Alix & Partners (Electrical Design), F.L Figueroa & Associates
(Plumbing & Fire Protection Design) and Meinhardt Philippines Inc (Faade and Elevator
Consultant). The interior design of lobbies and residential hallways was designed by
Asuncion Berenguer Inc. and landscape designed by E.A Aurelio.

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Construction and Project Management, Cost and Quantity Surveyor services for the
Phase 1 and Phase 2 of the development is provided by Masterpiece Asia Properties
Inc., while the general contractor for the project is Will Decena and Associates Inc.
Starmall Prima Daang Hari was composed of _ parking slots and ___ Tenant spaces on
ground floor, ____ on second floor and _____ on third floor. A total of 904 units in which
678 are studio units and 226 are combined units are semi-furnished with four (4)
different color schemes.
Also, the building features 4-high speed elevators, three (3) passenger elevators and
one (1) service elevator. Pressurized Fire Exits, Automatic Fire Suppression System and
Fire Detection & Alarm System were incorporated in the building to ensure safety and
CCTV was installed for building security. Also, Generator set was provided to back-up
power source in case of emergency.
The Beacon is located at the corner of Don Chino Roces and Antonio Arnaiz Avenues
near the heart of Makati, and is just a few meters away from commercial establishments
like Makati Cinema Square and Walter Mart - Makati; Don Bosco Parish and Don Bosco
Technical Institute, Makati, and a few blocks away from the Makati Central Business
District.
Further, summary of the project highlights are presented below as follows.

1.1. PRE-CONSTRUCTION PHASE

Plans and Specifications


Plans & Specifications was issued by ASYA within the period of August 2007 to October
2007 which was the reference in the formulation of Work Breakdown Structure (WBS)
and bidding of the major contract packages. However, due to revisions and changes on
the residential floors initiated by the Owner, ASYA issued the revised plans labeled as
Marketing Plans on a per batch basis starting January 2009 until June 2009. Detailed
Drawing control log of the Marketing plans are attached hereto as Annex A.

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Procurement (Bidding and Award)


The Work Breakdown Structure and Procurement Schedule was first established dated
20 November 2007 having 43 contract packages to be procured in 3 batches. With the
Owners direction to identify contract packages to be nominated and provided with
attendance by the General Contractor, the revised contract packaging and procurement
schedule was developed dated 10 March 2008 having 45 contract packages to be
procured in 2 batches. Detailed Procurement Schedule dated 20 November 2007 and 10
March 2008 are attached hereto as Annex B.

The contract packaging and procurement schedule was again revised due to the failure
and termination of the Architectural Works and Mechanical Contractor, Konstrak
International Inc. (KII) and Gentech Industrial Corp. (GIC). With the direction of the
Owner, the Architectural package was divided into sub-packages and the remaining
scope of works for mechanical was re-bided.

The updated contract packages including purchase orders endorsed by the Owner is
shown hereunder for reference.
Contract Packages as of 31 August 2012

CP
NO.
01
02a
02b
02b.1
a
02b.1
b
02b.1c
02b.1
d
02b.1
e

DESCRIPTION

AWARDED TO
(CONTRACTOR)

DATE
AWARDED

REMARK
S

Bored Pile
Works
Structural
Works
Architectural
Works
Masonry Works

Bauer Foundations Phils, Inc.

08-Feb-08

EEI Corporation

23-Jul-08

Konstrak International, Inc.

05-May-08

Multi Development &


Construction Corp.
JLD Design and Builders

08-Mar-10

08-Mar-10

Masonry Works

Strong World Construction


Corp.
El Acebuche Builders

Masonry Works

E2 Builders

28-Jun-10

Contract
Executed
Contract
Executed
Terminat
ed
Contract
Executed
Contract
Executed
terminat
ed
Contract
Executed
terminat
ed

Masonry Works
Masonry Works

04-Mar-10

28-Jun-10

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

02b.1f

Masonry Works

MRDE Builders & Trading

16-Aug-10

02b.1
g
02b.2
a

Masonry Works

Inext Finishing Works, Inc.

18-Aug-10

Installation of
tiles, Doors &
Jambs and
Door
Hardwares
Installation of
tiles, Doors &
Jambs and
Door
Hardwares
Installation of
tiles, Doors &
Jambs and
Door
Hardwares
Installation of
tiles, Doors &
Jambs and
Door
Hardwares
Installation of
tiles, Doors &
Jambs and
Door
Hardwares
Installation of
tiles, Doors &
Jambs and
Door
Hardwares;
Balance of
rectification
works at 35th
Floor

GMJ 2005 Contructors &


Development Corp.

20-Nov-10

MRDE

16-Aug-10

Works
takenover

Stratcon Grouppe, Inc.

23-Dec-10

Works
takenover

Santoni Construction &


General Services, Inc.

02-Feb-11

Works
takenover

RJ JEN

01-Feb-11

Contract
Executed

Coogee International
Development Inc.

02-Aug-11

Contract
Executed

CP
NO.

DESCRIPTION

AWARDED TO
(CONTRACTOR)

DATE
AWARDED

REMARK
S

02b.2
h

Installation of
tiles, Doors &
Jambs and
Door
Hardwares;
Balance of
rectification
works at 25th
Floor
Balance and
rectification

Rubyville Enterprises

10-Aug-11

Contract
Executed

RJ JEN Cost Plus

11-Mar-11

Short
Form

02b.2
b

02b.2
d

02b.2
e

02b.2f

02b.2
g

02b.5i

MASTERPIECE ASIA PROPERTIES INC.

Works
takenover
Contract
Executed
Contract
Executed

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Works
02d
02e
02f

04
10
11
12
13
14
14a
15
16

17
18
20

21
25

CP
NO.
27

Agreeme
nt
Contract
Executed
Contract
Executed

Pre-cast
Cladding Works
Metal
Fabrication
Works
Supply &
Installation of
Dry Walls &
Ceilings
Supply and
Installation of
Elevator (P/S)
Supply and
Installation of
Metal Doors
Electrical
Works
Plumbing and
Sanitary Works
Fire Protection
Works
Mechanical
Works
Mechanical
Works
Fire Detection
and Alarm
System (FDAS)
Auxiliary
System (CCTV,
Tel., CATV,
PA/BM,
Intercom)
Waterproofing
Works
Painting Works

Freysinnet Filipinas Corp.

12-Nov-08

Oro Filipino Enterprises &


Dev't. Corp.

17-May-10

Super Seven Sales Industrial


Corp.

13-Sep-10

Contract
Executed

KPI Elevators, Inc. (KONE)

01-Sep-08

Contract
Executed

Rapid Forming

30-Sep-10

Contract
Executed

Beta Electric Corp.

19-Nov-08

Agchem Construction &


Development Corp.
AAA Plumbing Services, Inc.

05-Jan-09

Gentech Industrial Corp.

13-Feb-09

Reform Construction

24-May-10

LM Integrated Systems and


Data Networking, Inc.

24-May-10

Contract
Executed
Contract
Executed
Contract
Executed
terminat
ed
Contract
Executed
Contract
Executed

LM Integrated Systems and


Data Networking, Inc.

24-May-10

Contract
Executed

Jan Owen Martin Construction


Corp.
Reform Construction

09-Dec-08

Aluminum
Windows, Glass
& Glazing
Works
Sewage
Treatment
Plant (STP)
Supply and
Installation of
Genset

Bradnam's Windows and


Doors Phils., Inc.

05-May-09

Contract
Executed
Contract
Executed
Contract
Executed

Eco-system Technologies.,
Inc.

01-Sep-08

Contract
Executed

MHI Engine System Phils., Inc.

22-Sep-08

Contract
Executed

DESCRIPTION

AWARDED TO
(CONTRACTOR)

DATE
AWARDED

REMARK
S

Supply and
Installation of

AC Technical Services
Incorporated

25-Nov-09

Contract
Executed

05-Jan-09

05-Jan-09

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Busways
28

38

Supply and
Installation of
Gondola (Davit
System)
Supply and
Installation of
Fuel Storage
Tank
Installation of
Tiles at
Hallways and
Elevator Lobby
Supply &
Installation of
Laminated
Flooring

Supply &
Installation of
Building &
Parking
Signages
Interior Fit-out
of ID Areas
Aluminum
Composite
Panel

MHE Demag (P), Incorporated

06-Jul-09

Reform Construction

22-Nov-10

Contract
Executed

DRF Solina

31-May-11

P.O. No.
M0500628

GS Go Bros

17-Mar-11

P.O. No.
M0300546

10-Aug-12

P.O. No.
M0802132012
P.O. No.
M1200867

Sofia Advertising

27-Dec-11

LJV Interiors

10-Jun-11

Morning Sun Aluminum &


Glass Contractor

18-Nov-11
12-Jan-12

Installation of
Shower
Enclosure
Installation of
T&B
Accessories
Supply &
Installation of
Modular
Kitchen
Cabinets

Le Eleglass Enterprises

07-Jun-11

Le Eleglass Enterprises

05-Oct-11

Phisra Espalux

07-Apr-11

29-Jul-11
32
38

Landscaping
Works
Supply and
Installation of

Contract
Executed

Bulacan Garden Corp.

11-Nov-11

Reform Construction

22-Nov-10

MASTERPIECE ASIA PROPERTIES INC.

P.O. No.
M0600647
P.O. No.
M1100824
P.O. No.
M0100182012
P.O. No.
M0600639
P.O. No.
M1000774
P.O. No.
M0400563
P.O. No.
M0700701
Contract
Executed
Contract
Executed

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Fuel Storage
Tank
Installation of
Tiles at
Hallways and
Elevator Lobby

CP
NO.

DESCRIPTION
Supply &
Installation of
Laminated
Flooring

Supply &
Installation of
Building &
Parking
Signages
Interior Fit-out
of ID Areas
Aluminum
Composite
Panel

DRF Solina

AWARDED TO
(CONTRACTOR)

31-May-11

DATE
AWARDED

GS Go Bros

P.O. No.
M0300546

10-Aug-12

P.O. No.
M0802132012
P.O. No.
M1200867

Sofia Advertising

27-Dec-11

LJV Interiors

10-Jun-11

Morning Sun Aluminum &


Glass Contractor

18-Nov-11

Le Eleglass Enterprises

07-Jun-11

Le Eleglass Enterprises

05-Oct-11

Phisra Espalux

07-Apr-11

29-Jul-11
05-Sep-11
07-Sep-11
11-Nov-11

MASTERPIECE ASIA PROPERTIES INC.

REMARK
S

17-Mar-11

12-Jan-12

Installation of
Shower
Enclosure
Installation of
T&B
Accessories
Supply &
Installation of
Modular
Kitchen
Cabinets

P.O. No.
M0500628

P.O. No.
M0600647
P.O. No.
M1100824
P.O. No.
M0100182012
P.O. No.
M0600639
P.O. No.
M1000774
P.O. No.
M0400563
P.O. No.
M0700701
P.O. No.
M0900739
P.O. No.
M0900743
P.O. No.
M09-

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

00778
16-Dec-11
03
09
10a
19

CP
NO.
23
29

33

34

37

39
40
41

Supply and
Delivery of
Rebars
Supply and
Delivery of
Wooden Doors
Supply and
Delivery of PVC
Doors
Supply and
Delivery of
Finishing
Hardwares

DESCRIPTION

P.O. No.
M120086-4

Steel Asia
OSM
OSM
OSM

AWARDED TO
(CONTRACTOR)

Supply and
Delivery of
Tiles
Supply &
Delivery of
Shower
Enclosures
Supply &
Delivery of
Plumbing
Fixtures &
Fittings
Supply and
Delivery of
Lighting
Fixtures
Supply and
Delivery of
Range Hoods

OSM

Supply and
Installation of
Transformers
Supply &
Delivery of
Sinks & Faucets
Supply &
Delivery of
Door Bells

OSM

DATE
AWARDED

REMARK
S

OSM

installatio
n by Le
Eleglass

OSM

installatio
n by
Agchem

OSM

Installati
on by
BETA

OSM

installatio
n by
Phisra
Espalux/
Reform
by
MERALCO

OSM
OSM

MASTERPIECE ASIA PROPERTIES INC.

installatio
n by
AGCHEM
Part of
Turn over
kit

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

1.2. CONSTRUCTION PHASE


Project Milestone and Highlights
New Pacific Resources Management Inc. and Geo Estate Development Corporation
held its Ground Breaking Ceremony dated 26 January 2008 which marked the start of
the construction of the Beacon Tower 1. Bauer Foundations Phils., Inc. started its
construction activity dated 08 February 2008 which marked the first day of the
construction period.
First concrete pouring on the pile cap (PC-9) was held on 30 August 2008 and Toppingoff ceremony was held 01 July 2009. Executives from NPRM, ATMCI, EEI and Design
Consultants attended both affairs.
Turn-over of units to GEDC Customers Relations Unit started August 2011, the
building was energized April 2012 and permit for full occupancy was issued and given
dated 04 July 2012.

Construction Schedule
The project completion based on the original construction schedule is on 27 May 2011.
However, due to various factors such as failure of the architectural contractor to perform
MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

on the masonry works, non-activity of the mechanical contractor and delays on the
fabrication and installation of windows which draws consequentially negative effects on
the fit-out works and other trade works, the project, as of 31 August 2012, had extended
462 calendar days from its original schedule.
Tabulated summary of revisions on construction schedule including percentage of
accomplishment during the period of project completion is shown hereunder. Detailed
approved original construction schedule, revised schedule and letter memo on the
adjustment of schedule from the Owner are attached hereto as Annex C for reference.

Summary of revisions on the original construction schedule

Description

Construction Schedule
Original

Revision 1

Revision 2

Revision 3

Project Start

08 Feb 2008

-same-

-same-

-same-

Project
Completion Date

27 May 2011

05 Dec 2011

31 May 2012

30 June 2012

1204

1396

1574

1604

Construction
Period
(Cal. Days)

Percentage of Accomplishment during the period of stated project completion

Construction Schedule
(Revision 1)
(Revision 2)
05 Dec 2011
31 May 2012

Description

(Original)
27 May 2011

Actual (%)
Accomplishment

86.50%

94.76%

99.18%

99.74%

Variance (%)

-11.22%

-2.80%

-0.66%

-0.26%

MASTERPIECE ASIA PROPERTIES INC.

(Revision 3)
30 June 2012

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Variance in Days

-163

-39

-10

-4

Further, below are the works which contributes to the consequential delays on the
project completion;
1. Architectural Works
Description

Commencement

Construction Schedule
Original

Actual

21 May 2009

22 June 2009

10 February 2011

99.50% as of 31 August 2012

Date
Project
Completion
Date
Variance from

568 days behind

Original
Schedule (Cal.
Days)
Variance from

62 days behind

Revised
Schedule 30
June 2012 (Cal.

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Days)

Originally, the architectural package which scope of works are masonry, installation of
doors, jambs, tiles and finishing hardwares was awarded to Konstrak International Inc.
(KII). They had introduced the Smart blocks system in lieu of conventional CHB system
which draws the attention of the Owner and later paved the way to the award of the
architectural package.
Since the start, KII has shown non-compliance to the project requirements resulted to
the late commencement which was supposedly 21 May 2009. Also, the smart blocks
required concrete strength of 3000 psi which was marketed and the basis of the award
were not mostly achieved resulting to the rejection of the blocks. This caused the delays
in the chb installation since the required quantity of chb to complete the floors was not
achieved. It is then the Owner decided and agreed to lower the concrete strength and
treat the installation as conventional type so as not hamper the other trade works and
entail more delays. The Project Manager issued notices to cope up delays to KII several
times for them to address their delays.
On 22 September 2009, the Project Manager serves the notice of termination to KII due
to the following reasons;

Low productivity rates

Undermanned site crew

Masons unfit to install Smart blocks

Inefficient construction methodology

Failure of Smart blocks to attain strength of at least 2000 psi

Poor workmanship

As a resolution on the matters at hand, the Owner decided to give chance to KII to
perform with the following agreement to wit;

EEI committed to provide Konstrak to have exclusive use of tower crane for its
masonry materials (Smart blocks, sand, Cement, rebars and skim coat) daily
lifting requirement from 9:00A.M to 12:00N.N, including times that the crane is
free from lifting activities of other sub-contractors on site. The commitment will
MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

take effect on 13 October 2009. In addition, 8-hour utilization of the construction


elevator was also agreed by the body to be utilized in hauling masonry materials
with an approximate combined output of 1,800 pcs per day.

Konstrak committed to deliver two (2) trucks of 19 palettes each with 80 pcs.
(3040 pcs.) Smart blocks a day and be unloaded in pallet fully secured with metal
strap. Lifting will be made using steel basket going to the designated floor and be
pulled in by a palette truck from the platform/loading bay.

EEI to install one (1) additional unit of loading bay which Konstrak will utilize to
expedite lifting, and which will be provided free of charge by GEDC.

Konstrak will mobilize full-time Project Manager and a superintendent who will be
in-charge of managing the project and site activities, respectively. Likewise, a
person who would monitor and supervise deliveries, hauling and lifting of all
masonry materials was also committed by Konstrak.

The body concurred that accomplishment will be monitored on a weekly basis on


weekly site construction meeting. As such, GEDC and Konstrak agreed that work
slippage must not exceed 15% of specific work item; such slippage is given two
(2) weeks to remedy. If such deficiency is not remedied in 2 weeks time, then
immediate termination of contract will be imposed. However, should such
deficiency be resolved, then the contract continues and accomplishment will be
evaluated every 2 weeks.

The body agreed that stiffener columns will not be required for smart blocks with
2,000 psi compressive strength and will start on 15 th floor and up. If succeeding
deliveries fail the compressive strength requirement, Konstrak will revert to
conventional system and provide lintel beams and stiffener columns where
needed. No floor will have mixed masonry system; it will be designated as either
conventional or Smart masonry system depending on compressive test results.

Konstrak to submit work sequence/methodology for all activities that will be


implemented in all floors on October 14, 2010.

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Konstrak agreed to comply with the masonry schedule and productivity rate,
including manpower complement as follows.

Work Item

Duration

Target (Sq.m/ wk)

Manpower

Block Laying

Sept. 1 2009 to Aug. 26,

767

62 (7- 12F)

958

78 (14- 45F)

2010

Skim coat

Nov. 4, 2009 to Sep. 11,

1,916

78

Floor Topping

2010
Nov. 12, 2009 to Sept. 19,

595

41

2010

Despite the above-mentioned agreement, KII continuously failed with their commitments.
On 29 January 2010, the Owner decided to temporarily limit the smart blocks installation
and skim coat application until 25th floor. The Owner will hire subcontractors to perform
the works on the succeeding floors. However, KII would supply all smart blocks required
to complete the project.
On 08 April 2010, KII agreed to voluntary relinquished all other scope in their contract
such as door/jamb installation, concrete floor topping and tiling works but with the
exception of masonry works up to 25 th floor which they committed to finish until 15 May
2010. However, KII was insistent on the continuous supply of 2000psi Smart blocks for
the remaining upper floors, claiming that the quantity required to complete the project
was already produced/manufactured. Full termination of KIIs contract took effect May
2010.

With the termination of KIIs contract, the remaining balance of work are divided into subpackages and awarded to the various contractors as follows;

CP NO.

DESCRIPTION

AWARDED TO
(CONTRACTOR)

MASTERPIECE ASIA PROPERTIES INC.

LOCATIO
N OF
WORK

REMAR
KS

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

02b.1a

Masonry Works

Multi Development &


Construction Corp.
JLD Design and Builders

08-Mar-10

02b.1b

Masonry Works

02b.1c

Masonry Works

08-Mar-10

Masonry Works

Strong World
Construction Corp.
El Acebuche Builders

02b.1d
02b.1e

Masonry Works

E2 Builders

28-Jun-10

02b.1f

Masonry Works

MRDE Builders &


Trading

16-Aug-10

02b.1g

Masonry Works

18-Aug-10

02b.2a

Installation of tiles,
Doors & Jambs and
Door Hardwares
Installation of tiles,
Doors & Jambs and
Door Hardwares
Installation of tiles,
Doors & Jambs and
Door Hardwares
Installation of tiles,
Doors & Jambs and
Door Hardwares
Installation of tiles,
Doors & Jambs and
Door Hardwares
Installation of tiles,
Doors & Jambs and
Door Hardwares;
Balance of
rectification works at
35th Floor
Installation of tiles,
Doors & Jambs and
Door Hardwares;
Balance of
rectification works at
25th Floor
Balance and
rectification Works

Inext Finishing Works,


Inc.
GMJ 2005 Contructors
& Development Corp.

02b.2b
02b.2d
02b.2e
02b.2f
02b.2g

02b.2h

02b.5a

P.O. No.
M0500628
P.O.
No.
M0600639
P.O.

Installation of Tiles at
Hallways and
Elevator Lobby
Installation of Shower
Enclosure
Installation of T&B

MRDE

04-Mar-10

28-Jun-10

20-Nov-10
16-Aug-10

Contract
Executed
Contract
Executed
terminat
ed
Contract
Executed
terminat
ed
Works
takenover
Contract
Executed
Contract
Executed
Works
takenover
Works
takenover
Works
takenover
Contract
Executed

Stratcon Grouppe, Inc.

23-Dec-10

Santoni Construction &


General Services, Inc.

02-Feb-11

RJ JEN

01-Feb-11

Coogee International
Development Inc.

02-Aug-11

Contract
Executed

Rubyville Enterprises

10-Aug-11

Contract
Executed

RJ JEN Cost Plus

11-Mar-11

DRF Solina

31-May-11

Short
Form
Agreeme
nt
Executed

Le Eleglass Enterprises

07-Jun-11

Executed

Le Eleglass Enterprises

05-Oct-11

Executed

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

No.
M1000774

Accessories

Contracts terminated are awarded to new contractors and thru variation order to existing
performing contractors. Contractors which reflect unsatisfactory performance were
taken-over by FIRM, GEDCs admin group or as variation order to performing
contractors.

2. Mechanical Works
Construction Schedule
Original
Actual

Description
Commencement Date

13 March 2009

25 March 2009

Project Completion Date

31 March 2011

98.00% as of 31 August

Variance from Original Schedule

2012
519 days behind

(Cal. Days)
Variance from Revised Schedule

62 days behind

30 June 2012 (Cal. Days)


Originally, the mechanical works package was awarded to Gentech Industrial
Corporation (GIC) dated 13 February 2009. GIC mobilized on site dated 25 March 2009
in which activities conducted are supervision and installation of pipe sleeves block-outs
on precast panels at FFCs plant. However, due to change in specification of pipe
sleeves from PVC to G.I. which they claim had a significant impact on their contract, GIC
opt to cease works and demobilized.
Last working day of GIC was recorded dated 28 July 2009. Despite PMs continuous
explanation and communication to GIC regarding the issuance and approval of the WAO
pertaining to the change in specifications on the pipe sleeves, GIC still shown no effort to
continue their construction activities.

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

With the recommendation by the PM to reconcile the claim in advance while waiting for
the approval of WAO, DLS and GIC had conducted reconciliation twice dated 25 August
2009 and 24 September 2009 yet nothing has agreed upon due to failure of GIC to
provide supporting documents to justify their excessive claims.
The PM issued notice to resume work to GIC and address the site issues dated 29
September 2009 in which they had responded dated 05 October 2009. Also, 3 rd
reconciliation meeting for variation in pipe sleeves was conducted dated 30 October
2009 yet failed again to come up with an agreement. GIC still continuously failed to
address the site issues and suspend its construction activity. This leads to the issuance
of 2nd notice to resume works and address site issues dated 09 November 2009 and
eventually notice of termination dated 17 November 2009.
On 25 November 2009, a meeting was held amongst GEDC, ATMCI, DLS, EEI and GIC
to discuss and resolve variation claim. GIC committed to return 26 November 2009
however failed to return to the negotiation table.
On 22 December 2009, DLS and GIC finally reconciled the cost of variation in pipe
sleeves. The PM also issued notice regarding the resumption of works twice dated 13
January 2010 and 20 January 2009.
A meeting was held on 16 February 2010 to formalize the mutual termination of GICs
contract. Full termination of GICs contract took effect March 2010.With the termination
of GICs contract, the remaining balance of work is awarded to Reform Construction.

3. Aluminum Glass and Glazing Works

Description
Commencement Date
Project Completion Date

Construction Schedule
Original (Based on
Actual
Amended Contract)
02 January 2010

25 March 2009

27 May 2011

100.00% as of 11

Variance from Original Schedule

August 2012
462 days behind

(Cal. Days)
Variance from Revised Schedule

62 days behind

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

30 June 2012 (Cal. Days)

Aluminum Glass Doors and Windows package was awarded to Bradnams Doors &
Windows, Phils as early as 09 May 2009. However with the Owners decision to re-hire
the services of Meinhardt Phils Inc as faade consultant to approve technical submittals
and change in specifications of aluminum frames and glass, the contract timetable was
amended with the following milestone dates:

Commencement Date

02 January 2010

Watertightness of Tower (7/F-45F)

30 November 2010

Watertightness of Ground Floor and Podium

30 December 2010

Completion of Testing and

30 January 2011

27 May 2011

Commissioning

Completion Date

The revised contract timetable did not materialize due to delay on Performance Mock-up
Test (PMU) which is the pre-requisite on the mass fabrication of the windows and doors.
PMU test was supposed to be conducted 30 March 2010 yet the actual PMU test was
conducted July 2010. This was due to delay of material delivery, die preparation, failure
on the initial PMU test and re-testing. First batch of windows were only delivered
September 2010 and installation of windows started on the same month.
Accomplishment to Date
As of 31 August 2012, the completion of the works for Beacon Tower 1 was still in
progress and has accomplished 99.87% registering a negative variance of -0.13% or 2
calendar days behind. Summary hereunder are the detailed accomplishment report.

Accomplishment Report as of 31 August 2012


Description
Target / Scheduled

Previous

This Week

To Date

100.00%

0.00%

100.00%

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Accomplishment
Actual accomplishment

99.79%

0.08%

99.87%

Variance, %

-0.21%

0.40%

-0.13%

-3

-2

Variance, days

Contract Package Accomplishment Breakdown as of 31 August 2012


Accomplishment To Date
Description

Target

Actual

Variance

No of
Days

% Weight

Target

Actual

Bored Piling
Works

100.00%

100.00%

0.00%

3.54%

3.54%

3.54%

General
Construction
Works

100.00%

100.00%

0.00%

29.23%

29.23%

29.23%

Architectural
Works

100.00%

99.50%

-0.50%

(5.23)

7.59%

7.59%

7.55%

Pre-cast
Cladding
Works

100.00%

100.00%

0.00%

3.23%

3.23%

3.23%

Miscellaneous
Metal Works

100.00%

100.00%

0.00%

0.75%

0.75%

0.75%

Drywall
partition/
ceiling

100.00%

100.00%

0.00%

1.57%

1.57%

1.57%

Installation of
Kitchen
cabinet and
range hood

100.00%

100.00%

0.00%

1.54%

1.54%

1.54%

Installation of
Shower
enclosures

100.00%

100.00%

0.00%

0.28%

0.28%

0.28%

Rebars

100.00%

100.00%

0.00%

13.29%

13.29%

13.29%

Supply &

100.00%

100.00%

0.00%

3.59%

3.59%

3.59%

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Installation of
Elevators
Supply &
Installation of
Metal Doors

100.00%

100.00%

0.00%

0.75%

0.75%

0.75%

Electrical
Works

100.00%

99.80%

-0.20%

(2.52)

8.25%

8.25%

8.24%

Plumbing and
Sanitary

100.00%

99.90%

-0.10%

(1.18)

7.38%

7.38%

7.37%

Fire Protection
Works

100.00%

100.00%

0.00%

2.70%

2.70%

2.70%

Mechanical
Works

100.00%

98.00%

-2.00%

(13.38)

1.14%

1.14%

1.12%

Fire Detection
& Alarm Sys.

100.00%

100.00%

0.00%

0.46%

0.46%

0.46%

Auxiliary
System Works

100.00%

100.00%

0.00%

0.58%

0.58%

0.58%

100.00% 100.00%

0.00%

0.34%

0.34%

0.34%

Painting
Works

100.00%

99.05%

-0.95%

(11.12)

2.25%

2.25%

2.23%

Supply &
Installation of
Window &
Glass

100.00% 100.00%

0.00%

3.63%

3.63%

3.63%

Sewage
Treatment
Plant

100.00% 100.00%

0.00%

0.28%

0.28%

0.28%

Interior Fit-out
of ID areas

100.00% 100.00%

0.00%

0.58%

0.58%

0.58%

Supply &
Installation of
Genset

100.00% 100.00%

0.00%

0.92%

0.92%

0.92%

Supply &
Installation of
PVC Doors

Waterproofing

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Supply &
Installation of
LVSG

100.00% 100.00%

0.00%

1.41%

1.41%

1.41%

Supply &
Installation of
Busways

100.00% 100.00%

0.00%

1.43%

1.43%

1.43%

Supply &
Installation of
Gondola

100.00% 100.00%

0.00%

0.29%

0.29%

0.29%

Supply &
Installation of
Signages

100.00% 100.00%

0.00%

0.35%

0.35%

0.35%

Landscaping
Works

100.00%

92.00%

-8.00%

(9.76)

0.28%

0.28%

0.26%

Fuel Storage
Tank

100.00% 100.00%

0.00%

0.08%

0.08%

0.08%

Wood Floors

100.00% 100.00%

0.00%

2.29%

2.29%

2.29%

100.00%

100.00%

99.87%

Total:

Balance of Works
The remaining 0.13% to complete the project comprises the balance of works for
architectural works, painting, mechanical works and landscaping works to wit;

MASTERPIECE ASIA PROPERTIES INC.

Contractor

PRIMA DAANG HARI


Location STARMALL
Description

Bulacan
Garden

Roof deck

1.) Provision of Groove Lines at Wooden Trellis Posts


2.) Polyurethane application at wooden trellis and deck
3.) Installation of tile cerujo at wooden deck steps

Beta
Electric

Roof deck

1.) Completion of devices, outlets, box covers at pump


room & storage
2.) Installation of special lighting fixtures (variation order)

Reform

Podium

1.) On-going painting of parking slot number


2.) Final Painting of Parking Area & Utility Rooms/ Ramps

Tower

1.) Painting of Metal Doors & Fire Exit Area


2.) Final Painting Exterior Part of Notch Wall
3. )Installation & Sealant Works of Dummy Vent Cap
4.) Final Painting of Exterior including Balconies

Roof deck

1.) Painting Works at Kitchen Area, Storage,


Pump Room & Common T&B

Bradnams

Tower

1.) Completion of Punch list at Windows of Elevator


Lobby and Hallways (Removal of Concrete Laitance,
Missing Handle, Rubber Gaskets and Limiters)

FIRM

Podium

1.) Rectification of Tiling Works at Elevator Lobby

Tower

1.) Provision of Opening for Steel Gate (Unit 601)


2.) Plastering Works inside EE Room

Roof
Deck

1.) Relocation of T&B Door at Common T&B


2.) Adjustment of Door at Storage Room
3.) Topping Works of Storage Room

Podium

1.) On-going Installation Plunger at Parking Area

Tower

1.) Installation of Remaining Balcony Steel Gate (Unit 601)


2.) On-going Installation of Remaining ACCU Grilles (43 pcs)
3.) On-going Installation of Remaining Secret Door (38 pcs)

Freyssinet

Tower

1.) Restoration of Exterior Sealant on Precast Cladding

Super 7

Tower

1.) Restoration of Damaged Flat Ceiling & Bulkheads


caused by Water Leaks at Residential areas
(due to Freyssinets defective sealant)

GS Go
Brothers

Tower

1.) Re-Installation of Damaged Laminated Flooring


caused by Water Leaks at Residential areas
(due to Freyssinets defective sealant)

Rapid
Forming

Podium/
Tower/
RD
Basement

1.) Completion of balance metal door hinges


(for utility rooms, EE rooms & fire exit doors)

Oro
Filipino

Agchem

Daang Hari Corner Molino Blvd., Bacoor, Cavite

1.) Completion of topping works at STP


2.) Restoration of Metal Doors & Openings
(STP & Pump Room)
MASTERPIECE ASIA PROPERTIES INC.
Roof deck 1.) Installation of plumbing fixtures and
kitchen accessories

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

This b

Balance of works were spearheaded and facilitated by GEDC Representatives since


June 2012, from monitoring of the completion, manpower deployment up to turn-over of
the areas to PMO.
Outstanding Issues
Description:

Remarks

Metal Door Hinges

Issued to GEDC ROSM No. 255 undelivered

Flush bolts for


metal doors

Issued ROSM No. undelivered

Special Lighting
Fixtures for RD

Awaiting for final design from lighting consultant

AAA Fire hose valve


(PMO Wish lists)

For Purchase Order

1.3. POST- CONSTRUCTION PHASE


OSM Monitoring & Status

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Door & Jambs


Description

Location

Required
Quantity
98

Quantity
Installed
98

Balance

Remarks

Delivered
& Installed
Delivered
& Installed
Delivered
& Installed

Main Door (D15)

End Units

Main Door
(D15A)
Bedroom

Residential Units

819

819

Residential Units

419

419

T&B Swing

Residential T&B

909

909

Delivered
& Installed

T&B Sliding

Residential (Unit 1 &


29)

70

70

Delivered
& Installed

Quantity
Installed
917

Balance

Remarks

Delivered
& Installed
Delivered
& Installed

Hardwares
Description
Door Viewer

Residential Main door

Required
Quantity
917

Main Lockset
(Left)

Residential Main Door

471

471

Main Lockset
(Right)

Residential Main Door

446

446

Delivered
& Installed

BR Lockset (Left)

Residential BR Door

216

216

Delivered
& Installed

BR Lockset
(Right)

Residential BR Door

203

203

Delivered
& Installed

T&B Lockset
(Left)

Residential T&B Door

469

469

Delivered
& Installed

T&B Lockset
(Right)

Residential T&B Door

440

440

Delivered
& Installed

Door Stopper

Residential Main , BR &


T&B Door

2245

2245

Delivered
& Installed

Required
Quantity
733

Quantity
Installed
733

Balance

Remarks

Delivered
& Installed
Delivered
& Installed

Kitchen Cabinets
Description

Location

Location

Kitchen Sink
(Round)
Kitchen Sink
(Rectangular)

Residential Studio
Residential Combined

176

176

Kitchen Faucet

Residential Units

909

909

MASTERPIECE ASIA PROPERTIES INC.

Delivered

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

& Installed
Kitchen Sink
P-Trap

Residential Units

909

909

Delivered
& Installed

Angle Valve w/
Hose (kitchen
sink)
Induction Cooker
(2 burner)

Residential Units

909

909

Delivered
& Installed

Residential Units
(Studio)

701

701

Delivered
& Installed

Induction Cooker
(4 burner)

Residential Units
(Combined)

208

208

Delivered
& Installed

Rangehood

Residential Units
(except end studios)

909

909

Delivered
& Installed

Rangehood with
Filter

Residential end units

51

51

Delivered
& Installed

Quantity
Installed
960

Balance

Remarks

Delivered
& Installed
Delivered
& Installed
Delivered
& Installed
Delivered
& Installed
Delivered
& Installed

T&B Accessories & Fixtures


Description
Location
Water Closet

Residential Units

Required
Quantity
960

Lavatory

Residential Units

954

954

Lavatory Faucet

Residential Units

954

954

Angle Valve w/
Hose (Lavatory)
Angle Valve w/
Hose (Water
Closet
Water Heater

Residential Units

960

960

Residential Units

968

968

Residential Units

949

949

Telephone Type
Shower

Residential Units

949

949

Shower Faucet

Residential Units

949

949

Towel Holder

Residential Units

949

949

Soap Holder

Residential Units

949

949

Tissue Holder

Residential Units

949

949

Shower
Enclosure

Residential Units

949

949

Attic Stock Provision

MASTERPIECE ASIA PROPERTIES INC.

Delivered
& Installed
Delivered
& Installed
Delivered
& Installed
Delivered
& Installed
Delivered
& Installed
Delivered
& Installed
Delivered
& Installed

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Asian Technicon Managers & Consultants, Inc. suggest to the owner to provide an attic
stock for the following Owner-Supplied Materials based on the report submitted last 22
October 2011.
OSM Description

Main Door (D15)


Main Door (D15A)
Bedroom Door
T&B Swing
T&B Sliding
Door Viewer
Main Lockset (Left)
Main Lockset (Right)
Bedroom Lockset (Left)
Bedroom Lockset (Right)
Door Stopper
Kitchen Sink (Round)
Kitchen Sink (Rectangular)
Kitchen faucet
Kitchen Sink P Trap
Angle Valve w/ Hose (Kitchen sink)
Induction Cooker (2 Burner)
Induction Cooker (4 Burner)
Rangehood
Rangehood with filter (for end units)
Water Closet
Lavatory
Lavatory Faucet
Angle Valve w/ Hose (lavatory)
Angle Valve w/ Hose (water closet)
Water Heater
Telephone Type
Shower faucet
Towel Holder
Soap Holder
Tissue Holder
Shower Enclosure

Total
Required
Quantity
98
819
419
909
70
917
471
446
216
440
2245
733
176
909
909
909
701
208
909
51
960
954
954
960
960
949
949
949
949
949
949
949

Attic Stock
(%)
5%
5%
5%
5%
5%
5%
5%
5%
5%
5%
5%
3%
3%
3%
5%
5%
3%
3%
3%
3%
5%
3%
3%
5%
5%
3%
5%
3%
3%
3%
3%
3%

Total Attic
Stock
Quantity
5
41
21
45
4
46
24
22
11
10
23
22
5
27
27
45
21
6
27
2
48
29
29
48
48
28
47
28
28
28
28
28

Hand-over of residential units and common areas status


Based on the given deadline to complete all the balance of works for respective
construction floor levels prior to punchlisting as agreed by the Team and to be followed
by EEI Corporation and sub-contractors, initially the priority levels 9F 14 F was
scheduled to be punch listed by GEDC-CRU Marketing spear-headed by Mr. Derryl
MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Camaclang starting 22 July 2011. Due to adjustments in deadline and contractors failure
to meet the given date, GEDC Marketing group originally started actual punchlisting a
week after dated 30 July 2011 as per assistance of ATMCI and EEI representatives.
Listed herewith are the complete schedule for punchlisting, rectification and acceptance
for the following marketing floor as follows;
Floor Level
(Marketing)

Punch listing

Rectification/ CRU
Acceptance

7F 12F

22 July 2011
22 August 2011

01 August 2011
03 September 2011

Months to be
Indicated on the 2nd
Turnover Notice
July August
2011

22 August 2011
01 October 2011

22 August 2011
08 October 2011

August October
2011

20F 28F

16 September 2011
31 October 2011

23 September 2011
31 October 2011

September October
2011

29F 37F

17 October 2011
30 November 2011

17 October 2011
30 November 2011

October November
2011

38F 42F

15 November 2011
10 December 2011

21 November 2011
17 December 2011

November December
2011

6F
12F 19 F

The 1st residential unit accepted by GEDC- CRU group was marketing unit 709 last
August 04, 2011 which also happens to be the 1 st Owner Accepted Unit by August 08,
2011. Unit 724AB which serves as GEDC CRU marketing temporary visitors lounge
was conditionally accepted last November 11, 2011 due to several remaining punch list
while it was finally turnover to Unit Owner last December 12, 2011.
As of latest update reflected on Handover of Units Report dated 31 August 2012, after
398 days elapsed since the day punch list period commenced, remaining original
unaccepted balance are 2 marketing units: 4214+15 and 4216+17. But due to recurring
issues majority are of water leak problems, GEDC-CRU returned units claiming to be
unaccepted to record a total of 38 out of 907 residential units overall.

Original
Due Recurring Issues

Total Units
907
907

CRU Accepted
905
869

MASTERPIECE ASIA PROPERTIES INC.

Total Balance
2
38

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

For the remaining 38 units balance unaccepted by GEDC-CRU, four (4) units are
returned to CMG Group due to balance of works noted by the Unit Owner, ten (10) units
have major and minor rectifications and twenty four (24) units are experiencing water
leaks.
Based on inspection, listed below are the residential units which are considered
unaccepted and involved issues stated herewit;
UNIT

Balance of work

603

Damaged Window Glass (Inc.)

707

Crack wall

1016+17

Scratches of AGD @ Balcony

1207

laminated flooring for


rectification
Damaged Laminated flooring

1614+15
1814+15
2516

Leak/Damage laminated
flooring
Leak/Damaged Bulkhead

2702

Leak (Sealant of Precast)

2714+15
2808
3112+14+15
3006

Leak/Damage Laminated
flooring
Missing Window Handle (Right)

Leak/Damaged Bulkhead

3414+15

3428+29

Leak/Damaged Laminated
flooring
Leak/Damaged Laminated
flooring
Scratches of kitchen Cabinet
door
Leak/Damaged Kit. Cab

3614+15

Leak/Damaged Bulkhead

3424

3807

Waiting for
delivery
Ongoing
rectification
Keys @ Owner
Keys @ Owner
Waiting for
delivery
Re-sealant of
PRECAST
Under
Observation
Re-sealant of
PRECAST
Under
Observation

Leak/Damaged Laminated
flooring
Uneven countertop

3116+17

3416+17

Remarks

Leak/Damaged Laminated
flooring

MASTERPIECE ASIA PROPERTIES INC.

Keys @ Owner
Under
Observation
Under
Observation

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

3914+15
4007
4014/15

Leak/Damaged Laminated
flooring
Leak/Damaged Laminated
flooring
Leak/Damaged Bulkhead

4016+17+18

Leak/Damaged Bulkhead

4110+11+12

Leak/Damaged Laminated
flooring
Leak/Damaged Bulkhead

4114
4116+17
4206

Leak/Damaged Bulkhead

4214+15

Leak/Damaged ceiling @ Living


Area
Ongoing List of Owner
Rectification
Leak/Damaged ceiling @ Living
Area
Leak/Damaged bulkhead

4216+17

Leak & Missing Handle

4207
4211

4218

4225

Leak/Damaged
Area
Leak/Damaged
Area
Leak/Damaged
Area
Leak/Damaged
flooring
Leak/Damaged
flooring
Leak/Damaged

4226

Leak/Damaged Bulkhead

4219
4220
4223
4224

Under
Observation

Under
Observation

Waiting for
delivery
Under
Observation
Under
Observation
Under
Observation

Ongoing
rectification
Ongoing
rectification

ceiling @ Living
ceiling @ Living
ceiling @ Living
Laminated
Laminated
Bulkhead

MASTERPIECE ASIA PROPERTIES INC.

Keys @ Owner

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

3. PROJECT TURNOVER FILES


AND RELEVANT INFORMATION
PROJECT DIRECTORY
Consultants
NAME OF
COMPANY/
CONTACT
PERSON
OWNER:
MASTERPIECE
ASIA PROPERTIES
INC. (MAPI)
A. Jose R.
Tresvalles, Jr.
B. Phillip A.
Lanuza

POSITION

Project Manager
Project Architect

ADDRESS

TELEPHON
E NO.

4F
Worldwide
Corporate
Center,
Shaw Blvd.,
Mandaluyon
g City

MASTERPIECE ASIA PROPERTIES INC.

FAX NO./
EMAIL
ADDRESS

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

ARCHITECT:
ALBERT S. YU &
ASSOCIATES
(ASYA)
A. Albert S. Yu
B. Alan Ranera
C.
STRUCTURAL:
SY
A. Jose Sy
B. Alex Ty
C. Lawrence Uy

LANDSCAPE:
E.A. AURELIO
A. Alex Ty

ELECTRICAL:
MAR A .ALIX &
PARTNERS
A. Mar A. Alix
B. Stephen
Napenas
MECHANICAL:
D.L. LAGMAN
ENGINEERING
A.
Domingo
Lagman
PLUMBING/
SANITARY:
F.L.FIGUEROA
& ASSOCIATES
A.
FL Figueroa
B.
Rodney
Constantino
LIFT
CONSULTANT:
MEINHARDT
PHILS., INC.
(MPI)
A. Ferdinand
Naniong
B. Vegchell
Acuna
FAADE
CONSULTANT:
MEINHARDT
FAADE

Principal

Associate
Project
Coordinator

Principal

Principal
Project
Coordinator

Principal

Principal
Project
Coordinator

Principal

Faade

Units 504 to
507, Pryce
Center
Condo. Corp.
1179 C.
Roces Ave.,
cor. Bagtikan
st., Makati
City
Unit 5A
Benjamin 1
Bldg. 62 Sgt.
Esguerra Ave.
cor. M.
Ignacia Q.C.
2430
Singalong St.,
Malate,
Manila
Unit 408
West Trader
Center,
Condominium
, 132 West
Ave. Q.C.
# 670 Cavo F.
Sanchez,
Mandaluyong
City
25/F Chattam
House 116
Valero cor.
Rufino St.
Salcedo
Village,
Makati City
25/F Chattam
House 116
Valero cor.
Rufino St.

896-9704
896-9705

896-9760
arominsy@inf
o.
com.ph/
arominsy@
gmail.com

929-0206

410-5401
e.augelio@
yahoo.com

523-1473
521-6083

521-6083
maralix_b77
@
yahoo.com

374-4046

371-9847
dllagmaneng
@
yahoo.com.p
h

531-7721
532-4640

719-4811
flfigueroa111
@
yahoo.com

887-1391

887-1172
mpi@meinhar
dt.
com.ph

887-1391

887-1172

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

TECHNOLOGY
(MFT)
A. Jaime Tandoc
B. Pedro Elumba
I.D.
CONSULTANT:
ASUNSCION
BERENGUER
A. Isabel
Asuncion
B. Ronnel
Dolores

Consultant

Principal
Project
Coordinator

Salcedo
Village,
Makati City

2/F Timog
Bldg. 28 E.
Lopez Ave.,
Quezon City

Jtandoc
@meinhardt.
com.ph

725-8747
loc 109

71-9871

Contractors
NAME OF
COMPANY/
CONTACT
PERSON
GENERAL
CONTRACTOR:
WILL DECENA
&
ASSOCIATES
INC.
A. Wilfredo L.
Decena
B. Bernardo L.
Decena
C. Jesus
Caburian

POSITION

ADDRESS

CONTACT NO.

3F & 4F Rose Building,


West Avenue, Quezon
City
CEO
Area Manager
Project-In-Charge

WILL DECENA & ASSOCIATES INC.S SUB-CONTRACTORS (LABOR):


SCOPE OF
WORK
CAST IN PLACE:

NAME OF
COMPANY
JMN

CONTACT PERSON

CONTACT NO.

Jerry Alquisar
+639328793363

EJJM TRADING
MASONRY
WORKS:

DSO

Eldren Joel Fabia

+639228674396

Danilo Ortega
+639391351378

RICHARD
PELICANO
EMROD

Richard Pelicano
+639471875811
Edentor Rodriguez

MASTERPIECE ASIA PROPERTIES INC.

+639174388712

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

CIPRIA
ENTERPRISES
JEM NICE
BUILDERS
DEMOLIITION
OF BEAM:
CEILING
WORKS:

Eugene Cipria
+639255888687
Ronelo Dumaguing

+639985394697

FLEXICORE
HASMED

Nestor Enriquez

JOSELITO
SALEN

Joselito Salen

TILING WORKS:

CIPRIA
ENTERPRISES

Eugene Cipria

FABRICATION &
INSTALLATION
OF TUBULAR
LOUVER AND
BILLBOARD
FRAMING:

AE FLORESCA
STEEL WORKS

Amador Floresca

+639217393332
+639182381674

+639255888687

+639474377146
WILL DECENA & ASSOCIATES INC.S SUB-CONTRACTORS (LABOR &
MATERIALS):
SOIL
JULANT PEST
Arman Muros
POISONING:
CONTROL
SYSTEM
+639294161142
REBAR & FORM EFJ
Edwin Garpin
WORKS:
CONSTRUCTIO
N
+639238378425
FORMWORKS:
AJINCO
EXTERIOR
DROP WALL
PARTITION:

MACRO AIR

INSTALLATION
OF CANOPY:

MACCEGON

CANOPY
FRAMING:

VICTORY
BUILDERS

Ariel Santos
+639175510097
Corie Tobias
+639176060902
Ferdie Olanga
+639985322328

ROOFING
WORKS:

PUYAT STEEL

MICHAEL
SUMAGAYSAY

A. Arnold
Guevarra
B. Joyce Catague
Michael Momar
Sumagaysay

MASTERPIECE ASIA PROPERTIES INC.

+639228669463
+639154999763

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

+639205636716
SKYLIGHT
ROOFING:

K-PLAST

Andy Waniwan

ACP
INSTALLATION:

CT-BOND

Jefferson Mase

FIRE
PROTECTION
WORKS:

GREENMASTER

MECHANICAL
WORKS:

PAGS

STAINLESS
RAILINGS:

BUILDCRAFT

GLASS
RAILING:

SUPER ART

Ronnie Gonida

WATERPROOFI
NG WORKS:

CONCRETE
SOLUTIONS

Rey Marin

EIFS &
WATERPROOFI
NG WORKS:

PIONEER

Herman Acotanza

PAINTING
WORKS:

GLOBAL
DESIGN

Alex Davel

PRECAST
WORKS:

NABB

TOILET
PARTITION:

GS GO BROS.

+639228139450
+639234412908
Shirley Perez
+639227869877
Resty Ganotisi
+639337181797
Michael Santiago
+639328589636
+639334149251

+639224395756

+639175505508
+639178331473
Angel Barcial
+639064661211
Bhel Tayag
+639178082902

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

PROJECT FACT SHEET


PROJECT NAME:

Starmall Prima Daang Hari

PROJECT LOCATION:

Daang Hari Corner Molino Blvd., Bacoor, Cavite

OWNER:

Masterpiece Asia Properties Inc.

Contact Persons:
Business Address:

Jose R. Tresvalles, Jr.


4th Floor, Worldwide Corporate Center, Shaw Blvd.,

Telephone No. :
Fax No.:

Mandaluyong City
(02) ?
(02) ?

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

CONSULTANTS:
Architect:
Structural Engineer:
Mechanical Engineer:
Sanitary/ Plumbing Engineer:
Electrical/ Lighting Engineer:
Fire Protection Engineer:
Landscape Architect:
Site Development:
CONTRACTORS:
General Contractor:
Sub-Contractors
Bored Piling Works:
Formworks:
Rebarworks:
Cast in Place:
Masonry Works:

Albert S. Yu & Associates


A.C. Ong Consulting Inc.
Domingo L. Lagman Engineers
A.C. Ong Consulting Inc.
A.C. Ong Consulting Inc.
A.C. Ong Consulting Inc.
?
Ma. Luisa B. Bricia
Will Decena & Associates Inc.

Ajinco / EFJ Consruction


EFJ Construction
EJJM Trading
DSO
Richard Pelicano
Emrod
Cipria Enterprises
Jem Nice Builders
Pre-Cast Cladding:
NABB
EIFS
Pioneer
Metal Door:
City Shutter
Drywall Partition & Ceiling Works:
Joselito Salen / AE Floresca
Tiling Works:
Cipria Enterprises
Tubular Louver & Billboard Framing: AE Floresca
Plumbing/ Sanitary:
Greenmaster Builders Inc.
Fire Protection:
Greenmaster Builders Inc.
Waterproofing:
Concrete Solution / Pioneer
Painting:
Global Design (Phase 1)
Mechanical:
Pacific Airconditioning and General Inc.
Aluminum Composite Panel:
CT Bond
Toilet Partition:
GS Go Bros.
Glass Railing:
Super Art
Stainless Railing:
Buildcraft
Skylight Roofing:
K-Plast
Roofing Works:
Michael Sumagaysay / Puyat Steel
Installation of Canopy:
Maccegon
Canopy Framing:
Victory Builders
Exterior Dropwall Partition:
Macro Air
Thermal Insulation:
?
Interior Fit-Out
?
Trade Contractors
Elevators & Escalatorrs:
KPI Elevators
Electrical:
Phases
Fire Detection/Alarm System:
?
Auxiliary System:
?

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

PERMITS/ LICENSES SECURED (NO. AND DATE ISSUED):


License Name
Permit/ License No.
Barangay Clearance:
4748
HLURB - License to Sell:
22028
ATO-Height Clearance:
DENR-EMB:
DPWH-BUILDING PERMIT:
Civil/ Structural:
Electrical:
Mechanical:

Sanitary/ Plumbing:
DPWH - Excavation&
Ground Preparation:
Occupancy Permit:
Sidewalk Construction
Permit
GENERAL DATA:
Lot Area:
Floor Area
Phase 1
Lower Ground Floor:
Ground Floor :
Roof Deck:
Phase 2
Ground Floor :
Second Floor:
Roof Deck:
Parking Slots
Phase 1 Parking:
Phase 2 Parking:
Number of Tenants
Phase 1:
Phase 2:
Number of floors
Height of Building:
Floor to Floor Height:
Capacity of Cistern (Domestic):

Date
03 Oct 2007
09 Mar 2009

I-140-07
ECC 2007-09-28-082-220

03 Jul 2007
28 Oct 2007

C12-07-1746
EP-C-12-2007-7054-8028
EP-C-2008-10-15098-16427
0712001348 (Fire-Protection)
0712001349 (ACU/Vent)
081000131337
0912001323 (1 Standby Gen-Set)
1003000184 (1,350 kg.PE #1)
1003000189 (1,350 kg. PE#2)
1003000207 (1,350 kg.PE #3)
1003000198 (1,600 kg.PE #4)
CS1207-0975
RC-08-10-0952

13 Dec 2007
13 Dec 2007
18 Nov 2008
12 Dec 2007
12 Dec 2007
18 Nov 2008
20 Jan 2010
01 Mar 2010
01 Mar 2010
04 Mar 2010
03 Mar 2010
13 Dec 2007
18 Nov 2008

E05-08-0737
OP0712-0529

21 May 2008
04 Jul 2012

TS11-11-1512

08 Nov 2011

37,079.39 square meters


13,316.25 square meters
12,291.93 square meters
12,062.17 square meters
3,287.80 square meters
2,785.23 square meters
2,790.96 square meters
146 slots
56 slots
13 slots
16 (17 for Cyber Zone) slots

158 meters/ 518.37 ft.


3.10 meters
100,000 gallon/ tank

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Capacity of Cistern
(Fire Protection):
Sewage Treatment Plant
Strength of Concrete Used
Columns:
Slab & beam:
Slab on grade:
PROJECT BRIEF:
Masonry Works
CHB Laying:
Plastering/Skim coat:
Metal Doors & Frames
Pipe Chase Enclosure:
Fire Exit Doors:
Electrical Room:
ACU Secret Door:
Garbage Room:
Transformer Room:
Generator Set:
Machine Room:
PLDT Room:
Doors & Hardwares
D15 (Main Door):
D15A (Main Door):
Bedroom Door:
T&B Door (Swing Type):
T&B Door (Sliding):
Maids T&B (Acrylic):
Tiles
Residential (Living Area) (600x600):
T&B (Wall & Floor) (600x600):
Balcony Tiles (300x300):
Hallway /Elevator Lobbies (600x600):
Natural Stones
Travertine Wall Cladding:
Travertine Wall Accent:
Bush hammered Flooring:
Windows & Glazing
Operable Windows:
Fixed Windows:
AGD Door:
Laminated Flooring
Floor Planks:
Baseboard:
T-Profile:
End Profile:
Reducer:

100,000 gallon/ tank


350 m3/ day
9,000 psi
6,500 psi
3,000 psi

46,644.98 square meters


93,289.96 square meters
468 sets
72 sets
72 sets
144 sets
1 set (roll-up door)
2 sets
1 set
1 set
1 set
98 sets
819 sets
419 sets
909 sets
70 sets
12 sets
19,239.00 square meters
11,523.62 square meters
282.10 square meters
3,636.56 square meters
63.070 square meters
7.856 square meters
93.00 square meters
2722 sets
1778 sets
104 sets
4877.30 square meters
6,491.78 linear meters
446.20 linear meters
29.37 linear meters
68.14 linear meters

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Plumbing Fixtures
Kitchen Sink (Round):
Kitchen Sink (Rectangle):
Kitchen Faucet:
Kitchen Sink P-Trap
Angle Valve w/ Hose (KS)
Water Closet
Lavatory
Lavatory Faucet:
Angle Valve w/ Hose (Lavatory)
Angle Valve w/ Hose (WC)
Water Heater
Telephone Shower
Shower Faucet
Towel Holder
Soap Holder
Tissue Holder
Shower Enclosure
Gypsum Board
Ordinary 12mm thick
Moisture Resistant 12mm thick
Ficemboard 12mm thick
Manhole Covers
Elevator
Passenger:
Service:
Electrical
Main distribution Normal Power:
Main Distribution Emergency Power:
Sub-distribution:
Lighting Fixtures
Fluorescent (T5):
Pin Lights:
Wall Lights (Entry):
Wall lights (Exit):
Incandescent (CFL):
Wiring Devices
Convenience Outlets (wall):
Floor-Mounted C.O.
Convenience Switches:
Wire and Cables:
IMC
PVC
Boxes:
Fire Protection
Fire Pump (Cap: 750 GPM)
Jockey Pump (Cap: 40 GPM)
Sprinkler Heads
Standpipe
Fire hose Cabinet

733.00 sets
176.00 sets
909 sets
909 sets
909 sets
960 sets
954 sets
954 sets
960 sets
960 sets
929 sets
949 sets
949 sets
949 sets
949 sets
949 sets
949 sets
19,120 square meters
6,681.04 square meters
5,294 square meters
2,382 sets
3 (1,350 kg.)
1 (1,600 kg.)
380 400V
380 400V
Line 1 to Neutral / Ground
3,477 pcs.
926 pcs.
211 pcs.
85 pcs.
5,823 pcs.
4,392 sets
2 sets
3,983 sets
581,505 linear meters
4,585 linear meters
61,552 linear meters
35,497 set
1 set
1 set
6,082 pcs.
300.8 linear meters
84 sets

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

Piping System
Fire Extinguisher
AFFE WFE (50 lbs)
CO2 PFE (15 lbs)
ABC PFE (15 lbs)
Dry Chemical (10 lbs)

20,692
6 pcs.
8 pcs.
2 pcs.
84 pcs.

ROCES TOWER RESIDENTIAL UNITS: TYPICAL COLOR SCHEME


SCHEME 1
AREA

COLOR

WALL COLOR

KITCHEN/ DINING/ LIVING

LILY WHITE

WALL COLOR

BEDROOM

DAISY CREAM

FLOOR

BEDROOM

CHERRY

CABINET

KITCHEN

SILVER

AREA

COLOR

WALL COLOR

KITCHEN/ DINING/ LIVING

DAISY CREAM

WALL COLOR

BEDROOM

SKYLINE

FLOOR

BEDROOM

HIMALAYAN OAK

CABINET

KITCHEN

BEECHWOOD

AREA

COLOR

WALL COLOR

KITCHEN/ DINING/ LIVING

INNER CALM

WALL COLOR

BEDROOM

SKYLINE

FLOOR

BEDROOM

HIMALAYAN OAK

CABINET

KITCHEN

CHERRY

SCHEME 2

SCHEME 3

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

SCHEME 4
AREA

COLOR

WALL COLOR

KITCHEN/ DINING/ LIVING

OFF WHITE

WALL COLOR

BEDROOM

LILY WHITE

FLOOR

BEDROOM

SNOW WHITE

CABINET

KITCHEN

ROYAL BLUE

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

MASTERPIECE ASIA PROPERTIES INC.

STARMALL PRIMA DAANG HARI


Daang Hari Corner Molino Blvd., Bacoor, Cavite

MASTERPIECE ASIA PROPERTIES INC.

You might also like