Professional Documents
Culture Documents
Full report
January 2016
Diagnostic CU Boulder makes significant investments in capital projects and is exploring ideas and opportunities to
improve efficiency and effectiveness in the execution of these projects
Completed 1900+ Minor and Outlay projects over the past five years routinely fall under budget similar to other
public organizations, accounting for about 18% of total budget value
Completed 30 Major projects (those above $2M), which account for 80%+ of the total spend. Approximately 8 projects
requiring additional spending limit were typically those impacted by accelerated timeline, scope changes, or decision
delays
Interviews with over 40 personnel across all stakeholder groups, review of selected projects, and analysis of available
documentation on processes surfaced opportunities for increased excellence:
a) Capital planning: Right-time commitment of funds in the project planning stage to align with available information
on scope and schedule
b) Contracting methodology: Provide clear guidelines for the project delivery method or contracting terms to
manage owner risk
c) Communication: Proactively manage risks through increased project tracking and clarity in communicating
progress with appropriate stakeholders
d) Project Manager workforce: Enhance PM workforce execution through structured training and onboarding
processes
Recommendations four themes have emerged as opportunities for increasing capital excellence based on the
above diagnostic:
Develop a clear, well-documented, and scalable stage gate process to drive capital investment success
Adopt clear guidelines in contracting strategy to address project risk based on project scope, target cost, expected
delivery schedule, market conditions, and internal capability
Deploy project controls to drive transparency of cost, schedule, and milestones during project execution thus
increasing consistency
Train and retain the Project Manager workforce to ensure best practices adoption and execution in project delivery
1 Budget performance based on initial Vice-chancellor approval limit for projects, not legislative approval
2 Compared to original estimated completion date in program planning
Pre-Decisional - Proprietary and Confidential | 1
In addition to the efficiencies captured, the implementation of the recommendations would bring other
performance and health benefits to CU Boulder including:
Performance: improve pipeline management; ability to attract best contractors; ability to anticipate and
resolve performance issues
Health: improve relationships across stakeholders; increase in morale, accountability and ownership;
heighten value proposition to current and potential workforce
Though current recommendations focus primarily on streamlining project delivery, CU Boulder can engage
in a broader set of available strategies for capital excellence which could potentially result in even higher
savings
Athletics Complex project review reveals that the Athletics Complex faced several challenges in scope and
schedule management due to complex, often unclear, multi-party interactions at an accelerated pace
Scope misalignment between Athletics, designer, and PD&C resulted in ongoing changes and cost
escalations throughout the project lifecycle
High staff turnover both internal and external to PD&C created coordination and communication
challenges given lack of continuity in an already fast-tracked project
In order to prevent future costs, project closeout and quality assurance is an important final step and may
require additional support to supplement capacity of existing team structure
Examples
Project size range
Total value
302
Major
Category I
Range $2-$50
Total value $318M
Category II
Range $50-$100
Total value $240M
Category III
Range $100+
Total value $308M
$867M
Range $500K-$1M
Total value $42M
980
Minor
Range $25k-$500K
Total value $91M
$171M
Range $1-$2M
Total value $39M
957
Outlays
$8M
Projects under $25k
Sound proofing
Temporary cooling
Fire alarm upgrade
1,967
Total
$1,046M
1 Representative project scale but not exhaustive. Current budget for projects from March 2010 after the implementations of the CP module to September 2015 across all stages of
development from planning (~$30 M) to closed. Budget defined as most recently approved budget in FAMIS as of mid-September 2015
2 Two grants listed as separate projects were merged with their associated projects. Three projects out of the 30 are ESCO with combined project value of USD ~21 M
NON-EXHAUSTIVE
USD Million
Initial
legislative
spending limit2
Athletics Complex1
142
System Biotech
Projects
impacted
by
significant
scope or
timeline
fluctuations
160
113
Campus Utility1
SEEC1
USD Change in
legislative
spending limit
18
169
75
91
60
56
16
112
53
% Change in
legislative
spending limit
50%
21%
88%
28
37
10
35%
SB Academic Wing1
22
28
28%
Ketchum1
13
23
10
75%
12
14
17%
12
N/A
N/A
N/A
0%
0%
64
64
43
43
EUCLID1 (CASE)
Wilderness1
18
20
14%
IBS
14
16
13%
11
11
2%
Wilderness - Recom
0%
0%
0%
10%
Hallett Renovation
0%
Atmospheric Lab
0%
GIPF Bldg
(Athletics) 1
Detailed next
12%
JILA
Rec Facilities
Normal
projects
Current
legislative
spending limit3
Observed difference
in performance
between projects
which are pursued
as expected and
those impacted by:
Accelerated
scheduling
Significant or
constant scope
changes
Delayed timing in
decision-making
Cross-cutting
Project
execution
Contracting
Design
Capital
Planning
More consistent Program Planning efforts, aligned with paced project schedule to decrease
owner risk
Address backlog in maintenance through improved capital allocation
Enhance integrated portfolio view with clear project prioritization
Rethink approval process to match the release of funds to the maturity level of the project
Augment alignment between PD&C and administration in regards to project budget estimates
and timelines
Continue with recently launched effort for early engagement of Project Manager in project
lifecycle
Refine choice in contracting strategy (choice of delivery model, contract type, award process) to
align to scope, project schedule, market conditions, and owner execution capability
Consistently enforce contract terms in the field leading to lower owner risk
Source: Interviews
Clear guidelines on
contracting strategy
to best manage
owner risk
Tracking information
on cost, schedule
and milestones for
each project
Standardized
processes with
capability building
training to ensure
consistent execution
VGI-AAA123-20090508-
Which project value chain steps should be done internally and which
ones by contractor(s)?
1 Delivery
model
3 Contract
terms
2 Award
proces
s
What are the key project cost, performance, and schedule risks?
Who is the natural owner of the risks?
What mechanisms exist to transfer or share risk?
How can objectives be aligned between owner and contractor to
ensure an efficient execution through compensation elements such
as incentives, penalties, warranties, etc.?
McKinsey & Company | 3
SJO-AAA123-20110525-
Create/ update
plan
Process step
Users
Progress
measurement
Provide timely,
accurate inputs
Help in identifying
critical milestones
Create WBS
Identify critical
milestones
Create/ update
plan
Publish plan
Customized
analysis
Provide timely,
accurate inputs
Execute recommended focus
actions
Identify required
analyses
Provide timely,
accurate inputs
Roles
Printed
Single and
comprehensive
capital investment
framework
Project Managers:
how well is project
D management best
practice followed?
Transparency: how
do project controls
C allow for right
information at the
right time?
Description
Contracting: how
project delivery and
B contracting methods
are selected
Best practice
Planning
team
Recommend &
perform required
analyses
Publish analysis
report
Funding gate
From...
Review-only gate
Operations
PD&C Planning Led Process
Project
Initiation/
Concept
Development
Consultant
and
Contractor
Selection
Program
Planning
1
Schematic
Design
Design
Development
Construction
Documents
Bidding and
Negotiation
Construction
Close Out
to
PD&C Planning Led Process
Project
Initiation/
Concept
Development
Program
Planning/
Scope
Selection
Is this needed? Is it a
priority?
2a
Consultant
and
Contractor
Selection
Schematic
Design
Design
Development
Construction
Documents
2b
Bidding and
Negotiation
3
Close Out
5
Start-up/
Commissioning
Construction
6
Any
outstanding
accounts or
issues?
CONTRACTING PROCESS
Goals
Actions
Who to
involve
Select a Contractor
Integrate Contractor
selection process into
Contracting Strategy
Playbook to best utilize
process to meet cost,
schedule or quality based
outcomes
Integrate contractor
PD&C
Legal
Procurement
Vice Chancellor
Contractor Rep
Design Team Rep
PD&C
Legal
Procurement
Vice Chancellor
Contractor Rep
Design Team Rep
PD&C
Legal
Procurement
Vice Chancellor
TRANSPARENCY
Define key
data and clear
C1 KPIs for
project
delivery
Create an
C2 accessible KPI
dashboard
Provide a
forum for
C3
decision
making
D
D Project manager performance is the single most influential
driver of construction project profitability
Highest priority
Skills
II
III
IV
Mgmt
capabilities
Financial
astuteness
Commercial
orientation
Org
capabilities
Train
Sustain
1.
1
2
1.
3
1.
4
1.
5
1.
6
1.
1.
7
8
1.
1.
9
1.
10 Managing client needs (e.g.
change orders)
Preparation
for forums
Select
participants
Plan
curriculum and
field work
Set expectations
through program
overview
Deliver first series of
workshops
combining activities
and pure lecture
modules
Outline field work
assignments
#1 (1 day)
Celebrate stories of
success from field
work
Establish forum for
PMs to discuss what
worked and what
was challenging
Deliver next set of
lectures and field
work
#2 (1 day)
Train
Sustain
Session sequence
Forum 1 Overseeing contractors
effectively and Mitigating project risk
Forum 2 Planning & tracking project
performance
Forum 3 Managing client needs
Forum 4 Managing internal & external
teams
#4 (1 day)
2016
Q4
Skills
#3 (1 day)
2015
Field
Practice
application of
lessons and
coaching
sessions to
help PMs
operate with
excellence
Q1
Q2
Field work
(~12 weeks)
Q3
Field work
(~12 weeks)
Provide workshops
for clients on
PD&Cs processes
Perform project
kick-off with client
Use transparency
tools throughout
project
Q4
Field work
(~12 weeks)
Leverage contracting
playbook during
contracting
Create risk
assessments before
project on critical
areas and develop
mitigation plans
Field work
(~12 weeks)
PM
Tools
Transparency
Contracting
Stage gate
Description
PRELIMINARY
Activity
A. Stage gate process
Share plan and create SG working group
Define stage-gate process for CU
(roles, deliverables, etc @ each gate)
Major projects
Complex Minor and Outlays
Syndicate with key stakeholders
Launch: pilot, adjust, scale to all complex projects
Assess results and define next steps (e.g. extend
to base Minor and Outlays projects)
B. Contracting strategy
Identify CS working group
Create contracting strategy playbook
Syndicate with key stakeholders
Launch: pilot, adjust, scale to all projects
Assess results and define next steps
C. Transparency
Syndicate version 1.0 of transparency
measures (dashboard and PRB)
Implement version 1.0 for all Major projects
Design, pilot, and adjust PRB & dashboard v2.0
Scale v2.0 to all projects
Assess results and define next steps
D. Project Managers
Identify mode for PM trainings (internal/external)
Map needed PM skills (and current state)
Design program (curriculum and format)
Launch field and forum trainings
Define & implement policy to ensure sustainment
(e.g. training refreshers, assessments, etc.)
Assess results of PMs and define next steps
E. PMO for implementation
2015
2016
Jan
Feb Mar
Apr
Nov Dec
Appendix
Contents
Organization context
Athletics project review
Overall diagnostic
Recommendations
Value at stake
Implementation plan
Facilities Planning
(7)
CAD/Document
Management/ CASP (6)
Design &
Construction (37)
Office
Administration (3)
Manages and
directs the
planning and
design of
campus facilities
and grounds
Maintains the
space database
Processes
official requests
for space
Performs space
utilization/needs
analyses
Maintains library of
campus site and
building engineering
drawings
Catalogs and
archives campus
project documents
and related materials
Updates achieve
drawings accurately
reflect the campus
and its structures.
Develops and
maintains campus
GIS and maps
database
Provides
administrative,
management and
professional
services required
to facilitate and
accomplish
projects on the
campus
Coordinates the
bidding process
procuring
consulting services
Administers and
maintains
contracts, budgets,
and schedules
Supports
PD&C
Project Initiation
and Feasibility
Program Planning
Defines the
basic scope
and likely cost
of the project
Informs the
administration
about the
project
Secures
campus
administration
approval to
proceed with
development
of a program
plan
Outcome:
Approval to
prepare a
Program Plan
Source: Colorado.edu
Defines the
programmatic
requirements for
the designer
Defines limits of
work, including site
and infrastructure
requirements
Builds consensus as to
scope, cost and time
line of the project
Defines the financial
plan and sources of
funds
Outcome:
Campus agreement on
scope of project and a
funding plan identifying
sources of revenue
Approvals
Secures Approval
from Board of
Regents and CCHE
Incorporates project
into larger capital
financial planning of
university and state
Develops support
for the project at all
levels of state
government
Architect Selection
Concept and
Schematic Design
Confirms and
enhances
program plan
requirements
Encumbers money
to begin the project
Generates
concept for final
building
Contractors are
selected for some
delivery methods
Provides room
by room layout
of spaces
Secures
approval of DRB
and review by
BCPC of
schematic plans
Outcome:
Authorization to begin
expending money on
a capital construction
project
Outcome:
A design team is
contracted to design
the entire project
Outcome:
Schematic design
is approved and
project budget is
confirmed
Design
Development
Develops
detailed room
requirements
Integrates
infrastructure
systems into the
building design
Provides pricing
documents for
contractor
Secures final
DRB approval
and other
entitlements
Outcome:
Design Development is approved
within the
contract budget.
Source: Colorado.edu
Construction
Documents
Outcome:
A complete set of plans
and specifications is
produced that describes
the design fully.
Bidding &
Negotiation
Initiates
procurement
processes for
all trades
Produces a
final construction price
Construction
Occupancy and
Warranty Period
The building is
occupied by the
users for which it
has been
designed
FM monitors the
project to identify
and correct any
construction
defects
Contracts
with builders
to construct
the project
Outcome:
Final contract
for construction
Outcome:
The project is realized
Outcome:
The building is
accepted and
available to
move in
Contents
Organization context
Athletics project review
Overall diagnostic
Recommendations
Value at stake
Implementation plan
Original Program Plan called for a phased approach and was envisioned to be
completed August 2016/17
Accelerated timeline and performing all phases concurrently has created additional
stress on delivery model
Lack of team continuity, both internal and external, created hand-off challenges and
eventually coordination and communication challenges
GMP was not executed, despite constant assurance provided by Mortenson and an
agreed upon scope and budget that led to an agreement in GMP
GMP agreement of USD 141 M achieved in April 2015
In May 2015 Mortenson refused to sign
Phase 1: 4th
Floor Buildout
Phase 2:
Indoor facility,
practice field,
and parking
3
1
2
Phase 3: Dal
Ward
Role on
project
Team
Governance
Site
presence
Winning contractor,
led contractor
relationship with CU
Final decision-maker
for build team
1 Includes Space for Olympic Sports teams and their support spaces, training table, and renovated and expanded academic support center
Source: Interviews, Athletic Complex Program Plan
Position
Active period
2013
Athletics
Department
Planning,
Design, &
Construction
Administration
Mortenson
Athletic Director
AD 1
Assistant AD
AAD 1
Campus Architect,
Director of PDC
CA 1
Project Manager
User Rep
2014
2015
Present
AD
AAD 2
CA 2
PM 1
UR 1
PM 2
No replacement
Dir 1
Dir 2
C&D Liaison
CDL 1
Lead estimator
LE 1 and CDL 2
VP 1
SR Proj Manager
PM 1
Project Manager
PM 1
Lead Designer
LD 1
Multiple PMs
Populous
Source: Interviews
USD millions
Increases driven by twelve significant scope evolutions, but those increases were controlled by three reductions
1
Indoor
Parking1
24
Focus of
changes only
on significant
changes to
scope
Does not
include
required
changes to
schedule,
manpower,
and other
changes
required to
support scope
change
2
IPF2
Track
11
Rooftop
Design
3
5
IPF2
Height
Reduct
-1
5th
Floor
Add-on
0.3
Dal
Ward
-6
Total
12
Footprint
Aud/
Vis
13
10
Rooftop
bridge
0.4
Grounds
Temp
Kitchen
Brand
0.2
IPF2
Sprinklers
Total
0.7
Total
Total
Total
0.2
Total
14
-0
15
16
Tenant
Finish
Value
Eng
-2
DAS
Systems
Total
Total
-2
Total
-2
3
2
1
Feb
Jun
Jul
Apr
Total
Mar
May
Sep
Dec
Jan
2014
2015
1 Separate project but had schedule and cost implications on Athletics Complex 2 IPF = Indoor Practice Field
Source: Interviews
Contents
Organization context
Athletics project review
Overall diagnostic
Recommendations
Value at stake
Implementation plan
Major projects (projects above $2M) comprise of 80% of the spend. Approximately 8 projects
requiring additional spending limit were typically those impacted by accelerated timeline, scope
changes, or decision delays
Significant portion of the spend, ~$250M, is still outstanding and provides an opportunity to
improve project delivery in on-going projects
Though market conditions impacted the overall cost of projects since 2009, there is no immediate
impact on attractiveness of CU projects based on bid analyses
More than half (>1000 projects) of all Minor and Outlay projects are completed at 5% or more
under the original target cost, similar to other public agencies
Qualitative analyses and review of select Major projects show that CU Boulders capital program
faces challenges in both strategy and project delivery with the following key opportunities:
Capital planning: Meet target costs by rethinking approval process to match the release of funds to
the maturity level of the project
Contracting methodology: Manage owner risk through clear guidelines on selection project delivery
method or contracting terms
Project Manager workforce: Increase consistency in PM workforce through structured training and
onboarding processes and a decrease in turnover
Pre-Decisional - Proprietary and Confidential | 27
Examples
Project size range
Total value
302
Major
Category I
Range $2-$50
Total value $318M
Category II
Range $50-$100
Total value $240M
Category III
Range $100+
Total value $308M
$867M
Range $500K-$1M
Total value $42M
980
Minor
Range $25k-$500K
Total value $91M
$171M
Range $1-$2M
Total value $39M
957
Outlays
$8M
Projects under $25k
Sound proofing
Temporary cooling
Fire alarm upgrade
1,967
Total
$1,046M
1 Representative project scale but not exhaustive. Current budget for projects from March 2010 after the implementations of the CP module to September 2015 across all stages of
development from planning (~$30 M) to closed. Budget defined as most recently approved budget in FAMIS as of mid-September 2015
2 Two grants listed as separate projects were merged with their associated projects. Three projects out of the 30 are ESCO with combined project value of USD ~21 M
NON-EXHAUSTIVE
USD Million
Initial
legislative
spending limit2
Athletics Complex1
142
System Biotech
Projects
impacted
by
significant
scope or
timeline
fluctuations
160
113
Campus Utility1
SEEC1
USD Change in
legislative
spending limit
18
169
75
91
60
56
16
112
53
% Change in
legislative
spending limit
50%
21%
88%
28
37
10
35%
SB Academic Wing1
22
28
28%
Ketchum1
13
23
10
75%
12
14
17%
12
N/A
N/A
N/A
0%
0%
64
64
43
43
EUCLID1 (CASE)
Wilderness1
18
20
14%
IBS
14
16
13%
11
11
2%
Wilderness - Recom
0%
0%
0%
10%
Hallett Renovation
0%
Atmospheric Lab
0%
GIPF Bldg
(Athletics) 1
Detailed next
12%
JILA
Rec Facilities
Normal
projects
Current
legislative
spending limit3
Observed difference
in performance
between projects
which are pursued
as expected and
those impacted by:
Accelerated
scheduling
Significant or
constant scope
changes
Delayed timing in
decision-making
System Biotech
Campus Utility
SEEC
Ketchum
Ekeley
6,985
7,010
7,078
7,000
4,450
6,341
6,384
4,450
4,400
6,500
4,300
5,000
4,500
4,250
4,000
4,150
4,178
Recession
recovery
3,500
Growth
period
3,000
4,092
4,100
Observations:
Denver area market
experienced growth
increase in prices over
the past five years
2,500
2,000
4,050
4,000
CCI
5,500
4,317
4,200
BCI
6,000
4,342
4,350
7,500
1,500
3,975
1,000
3,950
500
3,900
2010
2011
2012
2013
2014
2015
NOTE: The ENR indexes measure how much it costs to purchase the following hypothetical package of goods compared to what it was in the base year. The CCI uses 200 hours of common
labor, multiplied by the 20-city average rate for wages and fringe benefits. The BCI uses 68.38 hours of skilled labor, multiplied by the 20-city wage- fringe average for three trades
bricklayers, carpenters and structural ironworkers. For their materials component, both indexes use 25 cwt of fabricated standard structural steel at the 20-city average price, 1.128 tons of
bulk portland cement priced locally and 1,088 board ft of 2x4 lumber priced locally.
Construction
start
Project budget
(USD M)
Total
interested
bidders
13
Total
qualified
bidders
Highest
Lowest Spread
(%)
11%
Second Lowest
Lowest Spread
(%)
3%
IBS
Jun 09
Sys biotech
Sep 09
B/V Ball
Apr 10
11
WLRD Rec
May 10
HLET
May 10
Jila
May 10
East Elect
May 11
Video board
Apr 12
Rec facility
Jun 12
Utility syst
Aug 12
EKLC
Apr 12
Comp data
Aug 13
12%
3%
Atmos lab
Aug 13
12%
1%
MAC
Dec 13
Athletics
Apr 14
GM Ballrm
May 14
GIPF Blg
Sep 14
Ketchum
Jan 15
Wilderness
Mar 15
Ecme Hvac
Sep 15
Euclid
Oct 15
E-wing
Jan
161
143
32%
10%
32
13
0%
14%
6
5
5%
24%
4%
23%
6%
41%
18%
64
10
86
13
14
91
23%
4
14
32
3
10
2
43
13%
23%
2
6
8
6%
40%
3%
6%
11
2
17%
46%
22
25%
10
148
6%
32%
3%
2%
35%
5%
40%
13%
22%
1%
0%
17%
4%
40%
23
No
discernable
trend can be
identified
when
reviewing
past history
of Major bids,
while total
number of
interested
bidders is
trending
lower in 2nd
half of 2015
15%
8
Minor projects1
N = 7862
Outlay projects1
N = 6102,3
342
55% of projects
USD 20.2 M
underrun
64% of projects
USD 1.5 M
underrun
214
186
106
5-20
20-50
50+
0.6
3.1
3.1
15
>-20 -20- -5
-5-5
5-20
20-50
50+
Underruns in Minor
and Outlay projects
amount to ~$22M,
less than 2% of
overall capital
budget over five
years
Underruns are
expected given low
project values and
lack of knowledge
on existing field
conditions
99
Majority of projects
were under budget
by more than 5%
(55% of Minor and
64% of Outlay)
122
24
-5-5
176
1092
10
>-20 -20- -5
PRELIMINARY
-0.1
0.2
0.5
0.8
1 Includes Substantial Completion, Post Construction, and Closed Representative from March 2010 after the implementations of the CP module to
September 2015
2 Excludes projects with USD 0 spend, Minor = 11 and Outlay = 12
3 Excludes 215 closed projects with a budget of USD 0 but representing USD 890 K of actual spend
Source: PD&C, Team Analysis
USD Millions
129
-22
2
Minor
21
107
1
0
Public org 1
14-18%
0
Up to
30%+
Public org 2
120
CU
Budgeted
Underrun
Overrun
Spend
18%
1 Includes Substantial Completion, Post Construction, and Closed Representative from March 2010 after the implementations of the CP module to
September 2015
Source: PD&C, Team Analysis, Press search
Portfolio review
Portfolio allocation
Opportunity Origination
Project control
Organization
Portfolio
Strategy
Project
Delivery
Enablers
Description
PRELIMINARY
Enablers
Project delivery
Opportunity
origination
Concept
selection
Project
definition
and
approval
Project
execution
Project
ramp-up
Project control
Commissioning and
ramp-up
Organization
4.0
3.0
2.0
Construction and
Execution
Design. procurement.
and contracting
Business case
definition and concept
Strategy translation to
asset base
1.0
0.0
Risk/Return appetite
Opportunity origination
Ongoing returns
tracking
Capital headroom
calculation
Capital Strategy
Portfolio review
Portfolio allocation
Portfolio Strategy
Cross-cutting
Project
execution
Contracting
Design
Capital
Planning
More consistent Program Planning efforts, aligned with paced project schedule to decrease
owner risk
Address backlog in maintenance through improved capital allocation
Enhance integrated portfolio view with clear project prioritization
Rethink approval process to match the release of funds to the maturity level of the project
Augment alignment between PD&C and administration in regards to project budget estimates
and timelines
Continue with recently launched effort for early engagement of Project Manager in project
lifecycle
Refine choice in contracting strategy (choice of delivery model, contract type, award process) to
align to scope, project schedule, market conditions, and owner execution capability
Consistently enforce contract terms in the field leading to lower owner risk
Source: Interviews
Contents
Organization context
Athletics project review
Overall diagnostic
Recommendations
Value at stake
Implementation plan
Clear guidelines on
contracting strategy
to best manage
owner risk
Tracking information
on cost, schedule
and milestones for
each project
Standardized
processes with
capability building
training to ensure
consistent execution
VGI-AAA123-20090508-
Which project value chain steps should be done internally and which
ones by contractor(s)?
1 Delivery
model
3 Contract
terms
2 Award
proces
s
What are the key project cost, performance, and schedule risks?
Who is the natural owner of the risks?
What mechanisms exist to transfer or share risk?
How can objectives be aligned between owner and contractor to
ensure an efficient execution through compensation elements such
as incentives, penalties, warranties, etc.?
McKinsey & Company | 3
SJO-AAA123-20110525-
Create/ update
plan
Process step
Users
Progress
measurement
Provide timely,
accurate inputs
Help in identifying
critical milestones
Create WBS
Identify critical
milestones
Create/ update
plan
Publish plan
Customized
analysis
Provide timely,
accurate inputs
Execute recommended focus
actions
Identify required
analyses
Provide timely,
accurate inputs
Roles
Printed
Single and
comprehensive
capital investment
framework
Project Managers:
how well is project
D management best
practice followed?
Transparency: how
do project controls
C allow for right
information at the
right time?
Description
Contracting: how
project delivery and
B contracting methods
are selected
Best practice
Planning
team
Recommend &
perform required
analyses
Publish analysis
report
# Review-only gate
Current Process
PD&C Planning Led Process
Project
Initiation/
Concept
Development
Consultant and
Contractor
Selection
Program
Planning
1
Schematic
Design
Design
Development
Construction Documents
Bidding
and Negotiation
Construction
Close Out
and
Warranty
Period
2
Project obtains board approval and is funded
Unclear project pipeline prioritization process leads to suboptimal use of resources in developing Program Plans
Consensus must be built across many campus departments to xdevelop a Program Plan which requires considerable investment
of time and effort from the PD&C planning staff
100% of project target cost is established and committed before design is adequately developed
Length of time from project approval at funding gate 2 to project bidding exposes CU Boulder to market conditions as project
estimates no longer reflect the current market conditions
Project Managers enter the process after critical project decisions regarding scope and schedule are made
Continued scope development occurs in the schematic design and design development stage through user input
# Review-only gate
Operations
PD&C Planning Led Process
Project
Initiation/
Concept
Development
Consultant
and
Contractor
Selection
Program
Planning
Schematic
Design
Design
Development
Construction
Documents
Bidding and
Negotiation
Construction
Close Out
2
Project Obtains Board Approval and is Funded
to
Program
Planning/
Scope
Selection
Is this needed? Is it a
priority?
2a
Consultant
and
Contractor
Selection
Schematic
Design
Design
Development
Construction
Documents
2b
Bidding and
Negotiation
Construction
Start-up/
Commissioning
Close Out
6
Any
outstanding
accounts or
issues?
Consultant and
2a Contractor
Selection
Project Initiation
Program
and Concept
1
Planning
Development
Cabinet Review and
Authorization pre-design
Schematic Design
2b
# Review-only gate
Design
Development
Estimate Accuracy1
Percent
Share of total
Percent
30%
>50
50
100% of funding
committed
40
30
25
30
20
20
0.5 10% of
funding
committed
10
0
15
-10
5-15%
-20
10%
10
-30
5%
-40
-50
0.5%
Funding required (percent of total investment cost)
5
2%
Engineering complete
Estimate accuracy
1- Cost estimate accuracy increases (narrows) as design progresses, even as the cost estimate mid-point fluctuates as design progresses.
# Funding gate
Activities
Someone identifies a
project
Program
Planning
2a
A/E and/or
Contractor
Selection
Schematic Design
# Review-only gate
2b
Review gate 1
Funding gate 2a
Funding gate 2b
Gate questions:
Is the project need legitimate?
Is it a priority?
Gate questions:
Do feasible options exist that
match the intended purpose?
Gate questions:
Is the best option still viable after
scoping?
Stakeholders:
User
PD&C (Planning)
Vice Chancellor, Administration
Stakeholders:
User
PD&C (Planning and PM)
Vice Chancellor, Administration
CFO
Finance
BCPC (Informed)
Stakeholders:
User
PD&C (PM, Eng., Shops)
Design Team & Contractor
Vice Chancellor, Administration
BCPC
Board of Regents
Existing Process
Contractor
Selection/Schematic Design
% Design
Complete
0%
5%
Project
Estimate
--
$17.9M
Funding
Required
Program Plan
Funding
100% of project
estimate
Board of
Regents
--
Board approves
full capital spend
Proposed Process
Program
Planning
Program
Planning
Contractor
2a Selection/Schematic Design
% Design
Complete
0%
5%
Project
Estimate
--
$9M - $26.9M
($17.9M)
Funding
Required
Board of
Regents
Program Plan
Funding
--
$2.2M (12.5%
of Estimate)
Board informed
of design start
Design
Development
# Review-only gate
Construction
Documents
After Funding:
Increase to $22.4M at 100% DD estimate
VE and ESCO engaged, schedule slips
Board of Regents approves additional $2.5M (Total $20.4M)
Additional funding required to achieve project scope
Design
Development
2b
Construction
Documents
30-50%
Stage Gates
Decision and funding gates for:
Base Projects
Complex Projects
Gate 1
Objectives for Gate
Key Deliverables for Gate
By Function
Timeline
Critical Functions of Team
Summary Process Map for Gate
Project Managers Roles in completing
Gate
How to ensure success at Gate 1
Gate 2a
Objectives for Gate
Key Deliverables for Gate
By Function
Critical Functions of Team
Summary Process Map for Gate
Project Managers Roles in completing
Gate
How to ensure success at Gate 2a
Gate 2b
Objectives for Gate
Key Deliverables for Gate
By Function
Timeline
Critical Functions of Team
Summary Process Map for Gate
Project Managers Roles in completing Gate
How to ensure success at Gate 2b
Gates 3-6
Appendix
Objectives
Key deliverables
Planner - lead
Users
Engineering
Operations / Shop support
Outside support:
Estimating
Scheduling
Critical functions
Support functions
Finance
Vice Chancellor
PD&C (Planning
and Project
Manager)
Deliverable
Project charter
Issue record of decision for alternative selection
Provide detailed scope
Conduct analysis to facilitate key decision points(e.g., site, execution
strategy)
Develop initial project execution plan (scope / change management plan;
project team and resources; contracting strategy; risk management;
project controls (KPIs); estimate (50%), quality, procurement, testing
and close out, schedule; communication plan; contractor management
Engineering
lead
Regulatory
Legal
Deliverable
Form core
project team
Review
business case
Clarify roles and
responsibilities
Identify targets
as per CU
Boulder needs
Review project
charter
Identify
additional
resources
required
Project manager
assigned
Initiate
conceptual
engineering
User
requirements
Preliminary
massing
Assess
infrastructure
requirements
Identify financial
and logistical
issues
Narrow down
potential sites (if
applicable)
Narrow down
building concept
and potential MEP
systems
Update
conceptual
engineering
Include massing
Process control
strategies
Apply value
improvement
practices
Finalize
programmed
areas
Agree on
standards and
specifications
Conduct
process
simplification
and/or value
engineering
Conduct early
constructability
analysis
Scope and
document the
best option:
Conduct formal
evaluation of
alternatives
including fatal
flaws analysis,
and select best
available option
for application
Document
record of
decision
Develop
operations and
maintenance
strategies
Decision Gate
Estimate OPEX
Recycle
Proceed to Stage 2a
Conduct
preliminary
equipment
sizing
Finalize and
review scope of
work
Develop Plans
for Completing:
Basic
engineering
Detailed
engineering
Procurement
Construction
Contracting
Project controls
Reconcile
project
objectives
Develop
schedule to
reach Stage
2a and
detailed
milestone
schedule for
execution
phase
Develop
resource
requirements
for Stage 2a
Cancel/postpone
Develop
detailed
risk matrix
Update
Campus project
budget
Prepare
factored
estimate
(50%)
Confirm basic
engineering
requirements
Develop
renderings
Review
engineering
requirements for
permits
Major
Project
Threshold
2,000,000
Complex
projects
500,000
Base Projects
can continue to
utilize existing
stage gate
process,
potentially adding
key QA/QC steps
Complex and
Major Projects
should use
proposed stage
gate process
Definition of
thresholds should
be agreed
through StageGate working
group
Base
projects
150,000
Low
Med/High
Complexity
Phase 2
(3 months)
Phase 1
(4.5 months)
Initial
project
approvals
thresholds
Observations
40
2
10
15
5
10
20
# of
academic
campuses
Expected $/
sqft1
10%
10%
5%
185-305
185-305
NA
265-395
10
340-490
1 Hard construction costs $/GSF for University buildings in select US cities, Rider Levett Bucknall Quarterly Construction Report, 2nd Quarter 2015
Source: Press Search
Clear guidelines on
contracting strategy
to best manage
owner risk
Tracking information
on cost, schedule
and milestones for
each project
Standardized
processes with
capability building
training to ensure
consistent execution
VGI-AAA123-20090508-
Which project value chain steps should be done internally and which
ones by contractor(s)?
1 Delivery
model
3 Contract
terms
2 Award
proces
s
What are the key project cost, performance, and schedule risks?
Who is the natural owner of the risks?
What mechanisms exist to transfer or share risk?
How can objectives be aligned between owner and contractor to
ensure an efficient execution through compensation elements such
as incentives, penalties, warranties, etc.?
McKinsey & Company | 3
SJO-AAA123-20110525-
Create/ update
plan
Process step
Users
Progress
measurement
Provide timely,
accurate inputs
Help in identifying
critical milestones
Create WBS
Identify critical
milestones
Create/ update
plan
Publish plan
Customized
analysis
Provide timely,
accurate inputs
Execute recommended focus
actions
Identify required
analyses
Provide timely,
accurate inputs
Roles
Printed
Single and
comprehensive
capital investment
framework
Project Managers:
how well is project
D management best
practice followed?
Transparency: how
do project controls
C allow for right
information at the
right time?
Description
Contracting: how
project delivery and
B contracting methods
are selected
Best practice
Planning
team
Recommend &
perform required
analyses
Publish analysis
report
CONTRACTING PROCESS
Steps
Observations
Current tools
Select contractor(s)
CONTRACTING PROCESS
Schedule
Project
Success
Project
risks
Cost
Internal
capabilities
Quality/
operation
efficiency
Market
capabilities
CONTRACTING PROCESS
Steps
Goals
Who to
involve
Actions
Select a Contractor
PD&C
Legal
Procurement
Vice Chancellor, Administration
Contractor Rep
Design Team Rep
PD&C
Legal
Procurement
Vice Chancellor, Administration
Contractor Rep
Design Team Rep
PD&C
Legal
Procurement
Vice Chancellor, Administration
CONTRACTING PROCESS
Suggested working
group:
PD&C (3)
Planning
Representative
Project Manager
Engineering
Legal (1)
Procurement Team (1)
Potential Participants (at
key intervals):
Contractor
Representatives
Architect
Representatives
Activities:
Conduct a series of
workshops to address
each section of the
contracting playbook
Review playbook with key
stakeholders to validate
approach
Delivery method
Preferred delivery methods for:
Base Projects
Complex Projects
Delivery methods to maximize:
Cost
Schedule
Quality
Key considerations for delivery methods and
project types:
Operator experience required
Pool of experienced contractors available
Ability of contractor to integrate with others
Ramp-up/Turnover consistency
Single execution voice
Project controls
Contracting risk exposure
Project Managers Roles for each Delivery
Method
Contractor selection
Appropriate contractor selection process for:
Base Projects
Complex Projects
Selection process considerations per Delivery
Method
Pre-Decisional - Proprietary and Confidential | 60
CONTRACTING PROCESS
Type of Project
Nice to have
Must have
Implication to owner
Base
Design-BidBuild (DBB)
Base
Complex
Design-Build
(DB)
Complex
Complex
Construction
Management /
General
Contractor (CM/ Hybrid DB and
CM/GC
GC)
Complex
Public Private
Partnerships
(PPP)
Rationale
1 Operator
experience
2 Pool of
experienced people
3 Ability to integrate
with others
4 Ramp-up/turnover
consistency
5 Single execution
voice
6 Project controls
Contracting risk
exposure
Late contractor
involvement
could lead to redesigns
Overall score
Contractor
driven cost
savings
undermines
quality
Late involvement
from subs leads
to cost and
schedule
overruns
Lack of CU
Boulder
experience could
lead to cost,
schedule, and
quality issues.
Least compatible
with owner
strategy
Clear guidelines on
contracting strategy
to best manage
owner risk
Tracking information
on cost, schedule
and milestones for
each project
Standardized
processes with
capability building
training to ensure
consistent execution
VGI-AAA123-20090508-
Which project value chain steps should be done internally and which
ones by contractor(s)?
1 Delivery
model
3 Contract
terms
2 Award
proces
s
What are the key project cost, performance, and schedule risks?
Who is the natural owner of the risks?
What mechanisms exist to transfer or share risk?
How can objectives be aligned between owner and contractor to
ensure an efficient execution through compensation elements such
as incentives, penalties, warranties, etc.?
McKinsey & Company | 3
SJO-AAA123-20110525-
Create/ update
plan
Process step
Users
Progress
measurement
Provide timely,
accurate inputs
Help in identifying
critical milestones
Create WBS
Identify critical
milestones
Create/ update
plan
Publish plan
Customized
analysis
Provide timely,
accurate inputs
Execute recommended focus
actions
Identify required
analyses
Provide timely,
accurate inputs
Roles
Printed
Single and
comprehensive
capital investment
framework
Project Managers:
how well is project
D management best
practice followed?
Transparency: how
do project controls
C allow for right
information at the
right time?
Description
Contracting: how
project delivery and
B contracting methods
are selected
Best practice
Planning
team
Recommend &
perform required
analyses
Publish analysis
report
TRANSPARENCY
Define key
data and clear
C1 KPIs for
project
delivery
Create an
C2 accessible KPI
dashboard
Provide a
forum for
C3
decision
making
TRANSPARENCY
Cost
Major
Schedule
Scope
Quality
Health
Safety
KPI / data
Unit
Legend:
Who
reports?
$M USD
$M USD
Current EAC
Data
KPI
PRELIMINARY
How to report?
Target
Planner
Shared excel?
N/A
Planner?
Shared excel?
N/A
$M USD
Latest GC update
PM
Shared excel?
N/A
Calculated
PM
Shared excel?
<5%
Date
Planner
Shared excel?
N/A
Date
Contract documents
PM
Shared excel?
N/A
Current ECD
Date
Latest GC update
PM
Shared excel?
N/A
weeks
Calculated
PM
Shared excel?
<4 weeks
Sqft
Planner
Shared excel?
N/A
Sqft
PM
Shared excel?
N/A
N/A
Changes log?
PM
Shared excel?
N/A
RFI log
PM
Shared excel?
# of re-inspections:
Inspection log
Permitting?
Shared excel?
CAD?
Shared excel?
100%
Team morale
Stakeholder engagement
L,M,H
Days
Survey responses
Meeting minutes
PM
PM
Shared excel?
Shared excel?
High
5
Latest GC update?
PM
Shared excel?
PM
100%
TRANSPARENCY
Project Manager:
Data or KPIs
Safety
Health
Team wellbeing:
Stakeholder engagement
Survey score:
Number of days beyond regular cadence:
Help needed from leadership: specify actionable help from leadership (PD&C, Administration, or other)
here
Cost
Schedule
Scope
Quality
Overall
Rating
TRANSPARENCY
To discuss
Portfolio view
Major
Current EAC
In $M USD
Cost (-/+)
In percent
ECD
mm/yy
Schd.(+/-) Overall
In weeks Rating
Project name
Project 1
PM name
PM 1
CON
No delay
>20%
0-1 month
>1 month
Minor
10-20%
##
##
##
##
##
##
##
Outlays
Portfolio size
In $M USD, # of projects
##
##
##
##
##
##
##
TRANSPARENCY
C2
Introduction page:
Thank you for your participation in this online survey.
The team barometer is a feedback tool used to
monitor team satisfaction. We will discuss the results
every other week as a group, to celebrate successes
and align on actions needed to improve the team's
experience and/or performance.
Time required to complete: 5-10 minutes
Deadline: The survey will open every other Thursday
and will close the following Monday.
Body of survey:
1. I am clear about the objectives and end products of the team.
2. I am excited to be working on the team.
3. I am building new skills on this project.
4. The team has an atmosphere of trust and openness.
5. The team works collaboratively. Together we arrive at better solutions.
6. The team communicates well with one another.
7. Team meetings are engaging.
8. This week, the team created relevant, high-quality content that moves
us toward our objectives.
9. Our work is moving us toward our objectives at an appropriate pace.
10. I am able to maintain a good balance between our work and my
private life on this project.
11. I clearly understand my role on the team.
12. I clearly understand the roles of my fellow team members.
13. I am confident our efforts will ultimately result in significant
improvements to our project and to the business.
What is the team doing well?
TRANSPARENCY
Owners representatives
Distribution: to all PD&C, owners rep, and users
Cadence: minimum monthly
TRANSPARENCY
Key definitions
Clear guidelines on
contracting strategy
to best manage
owner risk
Tracking information
on cost, schedule
and milestones for
each project
Standardized
processes with
capability building
training to ensure
consistent execution
VGI-AAA123-20090508-
Which project value chain steps should be done internally and which
ones by contractor(s)?
1 Delivery
model
3 Contract
terms
2 Award
proces
s
What are the key project cost, performance, and schedule risks?
Who is the natural owner of the risks?
What mechanisms exist to transfer or share risk?
How can objectives be aligned between owner and contractor to
ensure an efficient execution through compensation elements such
as incentives, penalties, warranties, etc.?
McKinsey & Company | 3
SJO-AAA123-20110525-
Create/ update
plan
Process step
Users
Progress
measurement
Provide timely,
accurate inputs
Help in identifying
critical milestones
Create WBS
Identify critical
milestones
Create/ update
plan
Publish plan
Customized
analysis
Provide timely,
accurate inputs
Execute recommended focus
actions
Identify required
analyses
Provide timely,
accurate inputs
Roles
Printed
Single and
comprehensive
capital investment
framework
Project Managers:
how well is project
D management best
practice followed?
Transparency: how
do project controls
C allow for right
information at the
right time?
Description
Contracting: how
project delivery and
B contracting methods
are selected
Best practice
Planning
team
Recommend &
perform required
analyses
Publish analysis
report
II
III
IV
Mgmt
capabilities
Financial
astuteness
Commercial
orientation
Org
capabilities
Train
Sustain
1.
1
2
1.
3
1.
4
1.
5
1.
6
1.
1.
7
8
1.
1.
9
1.
10 Managing client needs (e.g.
change orders)
Mitigating project
risk
Overseeing
7 contractors
effectively
10
Managing client
needs
Skills
Train
Sustain
ILLUSTRATIVE
NON-EXHAUSTIVE
D Overview of potential capability modules topics and
support tools which may be considered to improve skills
Skills
Planning
Understanding market
trends to strengthen plan
scenario assumptions
Developing a view of
contractors performance
before the RFP is released
Contracting playbook
Project pipeline
management
Stage gate approval process
Mitigating project
risk
Managing client
needs
Support tools
Tools
Processes
Train
Sustain
Overseeing
contractors
effectively
Contracting
Contracting process to
align with playbook
Tools &
processes
required
not
exhaustive
SEE
DO
Providing information
Role-modeling work
in classroom settings
covering specific
skills and leveraging
knowledge experts
and practitioners to
spread best-practices
alongside employee
in an effort to create
experiential learning
to develop and
spread skills among
workforce
TEACH
Train new
Project
Managers
Train select
Project
Managers
Review
display
of mastery
and
provide
next
level
training
Ensure
standard
baseline
understanding
of department
approach to
building and
individual
capabilities
are achieved
Provide
Project
Managers
opportunities to
display
abilities
through
project
execution
Sustain policy
and procedures
change
Train
Field and
Forum
approach
Sustained
capability building
will require
policy and
procedures to
support the
ongoing training
needs of both
new and existing
PMs
Provide sufficient
opportunity for
Project Manager to
demonstrate
mastery of capability
or understanding of
department policy
Preparation
for forums
Select
participants
Plan
curriculum and
field work
Set expectations
through program
overview
Deliver first series of
workshops
combining activities
and pure lecture
modules
Outline field work
assignments
#1 (1 day)
Celebrate stories of
success from field
work
Establish forum for
PMs to discuss what
worked and what
was challenging
Deliver next set of
lectures and field
work
#2 (1 day)
Train
Sustain
Session sequence
Forum 1 Overseeing contractors
effectively and Mitigating project risk
Forum 2 Planning & tracking project
performance
Forum 3 Managing client needs
Forum 4 Managing internal & external
teams
#4 (1 day)
2016
Q4
Q1
Q2
Field work
(~12 weeks)
#3 (1 day)
2015
Field
Practice
application of
lessons and
coaching
sessions to
help PMs
operate with
excellence
Skills
Q3
Field work
(~12 weeks)
Provide workshops
for clients on
PD&Cs processes
Perform project
kick-off with client
Use transparency
tools throughout
project
Q4
Field work
(~12 weeks)
Leverage contracting
playbook during
contracting
Create risk
assessments before
project on critical
areas and develop
mitigation plans
Field work
(~12 weeks)
Provide support
to PMs through
before, during,
and after project
duration
Create a culture
of exchange
where best ideas
are raised up
Skills
Train
Sustain
Cost
Benefits
Considerations
pipeline of projects
Low performing external PM firms more
easily replaced with less impact to
organization
Project
delivery
Institutional
knowledge
Risk
project increases
Overhead cost to oversee program
increases
Important
considerations
Initial project
selection important
for signaling
considerations to
PD&C staff
Ideal project
would be highly
complex and
atypical of
PD&Cs
projects
Benefits will be
actualized by PD&C
staff, not
administration so
complete buy-in at
all levels of CU
organization
required
High degree of
clarity required for
what activities
external PM should
perform compared
to internal activities
PM
Tools
Transparency
Contracting
Stage gate
Description
Contents
Organization context
Athletics project review
Overall diagnostic
Recommendations
Value at stake
Implementation plan
Suggested efforts
Future Capital
Projects
(2015-2020)1
550-650
Current capital
projects unspent
budget1
250
Minor3
Capital Outlay3
170
PRELIMINARY
Current portfolio
1 Future capital projects includes CAMP (2014) and all projects not completed on the 20 year Proposed Capital Projects List (2011); Current capital projects unspent budget includes projects
in planning, deisgn, pre-construction, and construction phase with unspent budget | 2 17% average project budget overrun per Major project performance based on PD&C FAMIS system
data | 3 Minor and Capital Outlay numbers are sum totals from 2010-2015 taken from the PD&C FAMIS system and assumed to be consistent for 2015-2020
4 Infrastructure productivity: How to save $1 trillion a year, McKinsey Global Institute, Jan13
Contents
Organization context
Athletics project review
Overall diagnostic
Recommendations
Value at stake
Implementation plan
Phase 3: Sustaining
excellence
Phase 2: Building
excellence
Build foundational
processes and
capabilities
Pilot new
processes and
adjust based on
results before
scaling to all
projects
Scale new
processes to all
applicable project
types and project
delivery functions
Distribute and onboard personnel
on required
documentation
and tools to help
follow the new
processes
Assess progress
and take
comprehensive
stock of
achievements and
next steps
Evaluate results
and consider more
fundamental
changes
Re-evaluate
organization
strategy at later
stage based on
evolving needs
PRELIMINARY
Activity
A. Stage gate process
Share plan and create SG working group
Define stage-gate process for CU
(roles, deliverables, etc @ each gate)
Major projects
Complex Minor and Outlays
Syndicate with key stakeholders
Launch: pilot, adjust, scale to all complex projects
Assess results and define next steps (e.g. extend
to base Minor and Outlays projects)
B. Contracting strategy
Identify CS working group
Create contracting strategy playbook
Syndicate with key stakeholders
Launch: pilot, adjust, scale to all projects
Assess results and define next steps
C. Transparency
Syndicate version 1.0 of transparency
measures (dashboard and PRB)
Implement version 1.0 for all Major projects
Design, pilot, and adjust PRB & dashboard v2.0
Scale v2.0 to all projects
Assess results and define next steps
D. Project Managers
Identify mode for PM trainings (internal/external)
Map needed PM skills (and current state)
Design program (curriculum and format)
Launch field and forum trainings
Define & implement policy to ensure sustainment
(e.g. training refreshers, assessments, etc.)
Assess results of PMs and define next steps
2015
2016
Jan
Feb Mar
Apr
Nov Dec
Oct Nov
2016
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
CONTRACTING PROCESS
PRELIMINARY
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
A. Contracting process
Establish Contracting Strategy Playbook Working Group to
develop preferred delivery methods for complex projects
Create Contracting Strategy Playbook:
Delivery Methods:
Evaluate delivery methods that match a mix of project goals.
Evaluate against State requirements
Contractor Selection Methods:
Determine contractor selection methods against selected
delivery methods and State requirements.
Contract Language:
Develop standard contract language to match Delivery
methods, risk division, and mix of project goals.
Evaluate against State requirements.
Syndicate with key stakeholders
Launch New Contracting Strategy Playbook
Pilot and Adjust:
Educate PD&C Team and larger user group
(Legal, etc) to new tools and processes moving forward
Scale to all projects:
Assess results and define next steps
TRANSPARENCY
Oct
PRELIMINARY
2016
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
With Administration
With PD&C leadership
With (select) PMs
Any other stakeholders
Dec
Jan
Feb
Mar
Apr
May
Workshop series 1
Workshop series 2
Workshop series 3
Workshop series 4
C. Sustain program through
policy and procedure page
Identify skill development
needs of PMs
Provide workshop
to develop skills
Source: Team analysis
Perform quarterly
Perform as needed
Pre-Decisional - Proprietary and Confidential | 91
Members involved
Session objectives
Cadence
initiatives
Guide teams on critical
decision points
Provide support in
obstacle resolution
Celebrate success and
provide change
momentum
Supporting experts, as
needed
PD&C Change Agents
Initiative Champions
PMs, Planners
Others