You are on page 1of 94

Developing Capital Excellence

Full report
January 2016

Pre-Decisional - Proprietary and Confidential

Executive summary (1/2)

Diagnostic CU Boulder makes significant investments in capital projects and is exploring ideas and opportunities to
improve efficiency and effectiveness in the execution of these projects

Completed 1900+ Minor and Outlay projects over the past five years routinely fall under budget similar to other
public organizations, accounting for about 18% of total budget value

Completed 30 Major projects (those above $2M), which account for 80%+ of the total spend. Approximately 8 projects
requiring additional spending limit were typically those impacted by accelerated timeline, scope changes, or decision
delays

Interviews with over 40 personnel across all stakeholder groups, review of selected projects, and analysis of available
documentation on processes surfaced opportunities for increased excellence:
a) Capital planning: Right-time commitment of funds in the project planning stage to align with available information
on scope and schedule
b) Contracting methodology: Provide clear guidelines for the project delivery method or contracting terms to
manage owner risk
c) Communication: Proactively manage risks through increased project tracking and clarity in communicating
progress with appropriate stakeholders
d) Project Manager workforce: Enhance PM workforce execution through structured training and onboarding
processes

Recommendations four themes have emerged as opportunities for increasing capital excellence based on the
above diagnostic:

Develop a clear, well-documented, and scalable stage gate process to drive capital investment success
Adopt clear guidelines in contracting strategy to address project risk based on project scope, target cost, expected
delivery schedule, market conditions, and internal capability

Deploy project controls to drive transparency of cost, schedule, and milestones during project execution thus
increasing consistency

Train and retain the Project Manager workforce to ensure best practices adoption and execution in project delivery
1 Budget performance based on initial Vice-chancellor approval limit for projects, not legislative approval
2 Compared to original estimated completion date in program planning
Pre-Decisional - Proprietary and Confidential | 1

Executive summary (2/2)


Implementation CU Boulder has the opportunity to transform its capital program and potentially capture up
to 15% in planned capital spend

In addition to the efficiencies captured, the implementation of the recommendations would bring other
performance and health benefits to CU Boulder including:
Performance: improve pipeline management; ability to attract best contractors; ability to anticipate and
resolve performance issues
Health: improve relationships across stakeholders; increase in morale, accountability and ownership;
heighten value proposition to current and potential workforce

Though current recommendations focus primarily on streamlining project delivery, CU Boulder can engage
in a broader set of available strategies for capital excellence which could potentially result in even higher
savings

Athletics Complex project review reveals that the Athletics Complex faced several challenges in scope and
schedule management due to complex, often unclear, multi-party interactions at an accelerated pace

Scope misalignment between Athletics, designer, and PD&C resulted in ongoing changes and cost
escalations throughout the project lifecycle

High staff turnover both internal and external to PD&C created coordination and communication
challenges given lack of continuity in an already fast-tracked project

In order to prevent future costs, project closeout and quality assurance is an important final step and may
require additional support to supplement capacity of existing team structure

Pre-Decisional - Proprietary and Confidential | 2

Over the past 5 years, CU Boulders capital spend has been


concentrated on Major projects with a valued budget of ~$870M
PRELIMINARY
Number of
projects

Total budget on projects1

Examples
Project size range
Total value

302

Major

Category I
Range $2-$50
Total value $318M

Category II
Range $50-$100
Total value $240M

Category III
Range $100+
Total value $308M

$867M
Range $500K-$1M
Total value $42M

980

Minor

Range $25k-$500K
Total value $91M

$171M

Range $1-$2M
Total value $39M
957

Outlays

Projects over $2M


Athletics Complex
Systems biotechnology
building
Recreation facilities
improvements

Projects between $25k$2M


Food service renovation
Replace boilers, roof
Lab renovation

$8M
Projects under $25k
Sound proofing
Temporary cooling
Fire alarm upgrade

1,967

Total

$1,046M

1 Representative project scale but not exhaustive. Current budget for projects from March 2010 after the implementations of the CP module to September 2015 across all stages of
development from planning (~$30 M) to closed. Budget defined as most recently approved budget in FAMIS as of mid-September 2015
2 Two grants listed as separate projects were merged with their associated projects. Three projects out of the 30 are ESCO with combined project value of USD ~21 M

Source: PD&C, Team analysis

Pre-Decisional - Proprietary and Confidential | 3

Projects requiring additional spending limit were typically impacted


by accelerated timeline, scope changes, or decision delays
PRELIMINARY

NON-EXHAUSTIVE

USD Million

Initial
legislative
spending limit2

Athletics Complex1

142

System Biotech
Projects
impacted
by
significant
scope or
timeline
fluctuations

160

113

Campus Utility1
SEEC1

USD Change in
legislative
spending limit
18

169

75

91

60

56
16

112

53

% Change in
legislative
spending limit

50%
21%
88%

28

37

10

35%

SB Academic Wing1

22

28

28%

Ketchum1

13

23

10

75%

Ekeley Middle Wing

12

14

17%

SPSC - Data room

12

N/A

N/A

N/A

0%

0%

64

64

43

43

EUCLID1 (CASE)
Wilderness1

18

20

14%

IBS

14

16

13%

Bball/ Vball Practice

11

11

2%

Wilderness - Recom

0%

Stad - Video Board

0%

0%

Glenn Miller Ballroom

10%

Hallett Renovation

0%

Atmospheric Lab

0%

GIPF Bldg

(Athletics) 1

Detailed next

12%

JILA

Rec Facilities

Normal
projects

Current
legislative
spending limit3

Observed difference
in performance
between projects
which are pursued
as expected and
those impacted by:
Accelerated
scheduling
Significant or
constant scope
changes
Delayed timing in
decision-making

1 Ongoing project | 2 Initial legislative approval | 3 Current legislative approval

Source: Team Analysis, PD&C

Pre-Decisional - Proprietary and Confidential | 4

Based on 40+ interviews, select project reviews, data analysis, and


focus groups we identified a set of opportunities
Opportunities to increase efficiency and effectiveness

Cross-cutting

Project
execution

Contracting

Design

Capital
Planning

More consistent Program Planning efforts, aligned with paced project schedule to decrease
owner risk
Address backlog in maintenance through improved capital allocation
Enhance integrated portfolio view with clear project prioritization
Rethink approval process to match the release of funds to the maturity level of the project
Augment alignment between PD&C and administration in regards to project budget estimates
and timelines
Continue with recently launched effort for early engagement of Project Manager in project
lifecycle

Emerging themes for


developing excellence

Develop a clear, welldocumented, and scalable


stage gate process to
drive capital investment
success

Adopt clear guidelines in


contracting strategy to
address project risk based
on project scope, target
cost, expected delivery
schedule, market
conditions, and internal
capability

Refine choice in contracting strategy (choice of delivery model, contract type, award process) to
align to scope, project schedule, market conditions, and owner execution capability
Consistently enforce contract terms in the field leading to lower owner risk

Standardize project execution processes


Adopt and enforce tools and as a standardization method
Increase ownership of project controls (i.e., cost and schedule tracking)

Deploy project controls


to drive transparency of
cost, schedule, and
milestones during project
execution thus increasing
consistency

Enhance communication on project progress


Celebrate success
Leverage performance monitoring (e.g., lessons learned at project completion) as source of
insight
Provide training for onboarding new employees and continuous development

Train and retain the


Project Manager
workforce to ensure best
practices adoption and
execution in project
management

Source: Interviews

Pre-Decisional - Proprietary and Confidential | 5

CU Boulder can adapt best practices in capital management across


the four themes to continue to pursue excellence
Emerging theme
Stage-Gate process:
how do projects
move through
A multiple fund and
scope approval
gates through the
lifecycle?

Stage-gate process matches the release of


required funds to the maturity level of project
definition; specifically, it ensures projects do not
progress without an adequate evaluation of the
underlying business case, completion of key
deliverables, and mitigation of critical risks

Clear guidelines on
contracting strategy
to best manage
owner risk

Selecting contracting strategy (delivery model,


contract terms, award process) based on project
specifications (size, cost, delivery schedule,
complexity), market conditions, and internal
capability

Tracking information
on cost, schedule
and milestones for
each project

Project controls dashboards enable PMs and


Project Coordinators to:
Proactively identify issues
Ensure relevant information is at hand to
contribute to the decision making process in a
timely manner

Standardized
processes with
capability building
training to ensure
consistent execution

Establishing standardized methods, training for


PM staff on consistent approaches, and support
from key decision makers which allow PM team
to increase success in delivery of projects

VGI-AAA123-20090508-

Contracting strategy entails defining 3 linked elements


of a project
Key dimensions of contracting strategy

Key questions to be considered


Delivery model (How do I determine optimal contracting scope?)

Should I own the asset or are other ownership structures more


suitable, e.g., lease?

Which project value chain steps should be done internally and which
ones by contractor(s)?

Into how many contracts should the project scope be split?


What is the optimal split of scope between the contractors?

1 Delivery
model

Award process (How do I select my contractors?)

How can the effectiveness of existing award process be enhanced ?


How many and which suppliers/contractors should be invited?
How do we get the suppliers interested?
What is the criteria for evaluation various suppliers?

3 Contract
terms
2 Award
proces
s

Contract terms (How do I ensure most optimal contracting terms?)

What are the key project cost, performance, and schedule risks?
Who is the natural owner of the risks?
What mechanisms exist to transfer or share risk?
How can objectives be aligned between owner and contractor to
ensure an efficient execution through compensation elements such
as incentives, penalties, warranties, etc.?
McKinsey & Company | 3

SJO-AAA123-20110525-

4 Planning and scheduling process

Create/ update
plan

Process step

Users

Progress
measurement

Provide timely,
accurate inputs
Help in identifying
critical milestones

Create WBS
Identify critical
milestones
Create/ update
plan
Publish plan

Customized
analysis

Provide timely,
accurate inputs
Execute recommended focus
actions

Monitor & report


project progress
Recommend
focus actions/
area
Publish report

Identify required
analyses
Provide timely,
accurate inputs

Roles

Printed

Single and
comprehensive
capital investment
framework

W orking Draft - Last Modified 07-Sep-11 6:35:55 PM

Project Managers:
how well is project
D management best
practice followed?

Printed 4/6/2011 4:32:15 PM

Transparency: how
do project controls
C allow for right
information at the
right time?

Description

W orking Draft - Last Modified 9/7/2011 3:32:09 AM

Contracting: how
project delivery and
B contracting methods
are selected

Best practice

Planning
team

Recommend &
perform required
analyses
Publish analysis
report

McKinsey & Company | 5

Pre-Decisional - Proprietary and Confidential | 6

STAGE GATE PROCESS

A Adding stage gates to existing Capital Project Process will focus


University resources and increase control for Major projects
#

Funding gate

From...

Review-only gate

Operations
PD&C Planning Led Process

Project
Initiation/
Concept
Development

Consultant
and
Contractor
Selection

Program
Planning
1

PD&C Project Manager Led Process

Schematic
Design

Design
Development

Construction
Documents

Bidding and
Negotiation

Construction

Close Out

Project Obtains Board Approval and is Funded

Cabinet Review and Authorization

to
PD&C Planning Led Process
Project
Initiation/
Concept
Development

Program
Planning/
Scope
Selection

Is this needed? Is it a
priority?

2a

PD&C Project Manager Led Process

Consultant
and
Contractor
Selection

Schematic
Design

Design
Development

Construction
Documents

2b

Is the best option still viable after scoping?


Freeze Scope. Release full budget.

Develop feasible options. Release seed money.

Bidding and
Negotiation
3

Close Out
5

Is the project ready to begin operation?

Is option still viable given the refined estimate?

Source: PD&C process, Expert interviews, Team Analysis

Start-up/
Commissioning

Construction

Is the project ready to be turned over?

6
Any
outstanding
accounts or
issues?

Pre-Decisional - Proprietary and Confidential | 7

CONTRACTING PROCESS

B Proposed contracting process establishes a consistent risk


based approach to enhance project outcomes
Steps

Select a Delivery Model

Goals

Actions

Who to
involve

Establish a Contracting Strategy


Playbook for optimizing cost/
schedule/quality aligned with
State regulations and CU Boulder
past experience

Understand how alternative


models (bundling, PPP, IPC)
could be utilized to better spread
risks

Understand CU Boulder desired


role (skill building)

Select a Contractor

Integrate Contractor
selection process into
Contracting Strategy
Playbook to best utilize
process to meet cost,
schedule or quality based
outcomes

Determine Contract Terms


and Sign
Transfer project risks to align
objectives between owner and
contractors, not to outsource them
Ensure the terms of the
performance contract are
pragmatic, clear, and
measurable

Develop Contracting Strategy

Integrate contractor

Develop standard language

PD&C
Legal
Procurement
Vice Chancellor
Contractor Rep
Design Team Rep

PD&C
Legal
Procurement
Vice Chancellor
Contractor Rep
Design Team Rep

PD&C
Legal
Procurement
Vice Chancellor

Playbook working group to


explore best delivery options of CU
Boulder projects

selection methods into


Contracting Strategy
Playbook
Formalize Contractor Score
Card

added to State contracts to


provide a fair and equitable
balance of risk on large
Capital Projects

Pre-Decisional - Proprietary and Confidential | 8

TRANSPARENCY

C CU Boulder requires a systematic approach to building


transparency among stakeholders in project delivery
Description

Define key
data and clear
C1 KPIs for
project
delivery

Create an
C2 accessible KPI
dashboard

Provide a
forum for
C3
decision
making

CU Boulder should define Key Performance Indicators (KPIs) at a


project level based on project categories defined (i.e. Major, Minor, and
Outlays) with clear targets across each
An individual should also be identified as a responsible party for
reporting and meeting the KPI target (may be different individuals)
Clear direction and training should be provided on how to calculate and
report the KPI
KPI dashboard should be accessible at multiple levels (e.g. project
level and portfolio level) to the relevant stakeholders
The accessible dashboard can be communicated widely to build
transparency among all stakeholders (e.g. users, administration,
PD&C) and increase project accountability
KPI dashboards can be used as a tool in a regular forum of
stakeholders (e.g. a Project Review Board) to discuss project progress
Project Review Boards will also help resolve issues proactively as it
will:
Enable decision makers to have the right information
Allow PMs to raise concerns at right time

KPI dashboard is designed at both project and portfolio level


Source: Expert interviews, Team Analysis

Pre-Decisional - Proprietary and Confidential | 9

PROJECT MANAGER PERFORMANCE

D
D Project manager performance is the single most influential
driver of construction project profitability
Highest priority
Skills

Project performance is not


correlated with:
Geography
Asset class
Complexity
Customer
Project manager age or tenure
(grey hair)

Source: Interviews, Team analysis

II

III

IV

Mgmt
capabilities
Financial
astuteness

We have found that project


performance is highly correlated
with project manager capabilities

Commercial
orientation

Org
capabilities

We have run an analysis of 10,000


projects, checking the correlation of
project performance with different
factors

High performing PMs excel at these skills

Train
Sustain

1.
1

Optimizing schedule, scope, and cost


dimensions

2
1.

Planning & tracking project performance

3
1.

Managing internal and external teams

4
1.

Understanding financial statements

5
1.

Mitigating project risk

6
1.

Maintaining project lifecycle view

1.
7

Overseeing contractors effectively

8
1.

Mastering contract details

1.
9

Leveraging organization resources

1.
10 Managing client needs (e.g.
change orders)

Pre-Decisional - Proprietary and Confidential | 10

PROJECT MANAGER PERFORMANCE

D A field and forum format ensures appropriate balance between


effort, effectiveness, and reach
ILLUSTRATIVE
Forum
Classroom
setting where
skills are
taught by
experienced
PMs and
standard
setters

Preparation
for forums
Select
participants
Plan
curriculum and
field work

Set expectations
through program
overview
Deliver first series of
workshops
combining activities
and pure lecture
modules
Outline field work
assignments

#1 (1 day)

Celebrate stories of
success from field
work
Establish forum for
PMs to discuss what
worked and what
was challenging
Deliver next set of
lectures and field
work

#2 (1 day)

Train
Sustain

Session sequence
Forum 1 Overseeing contractors
effectively and Mitigating project risk
Forum 2 Planning & tracking project
performance
Forum 3 Managing client needs
Forum 4 Managing internal & external
teams
#4 (1 day)

2016

Q4

Source: Team analysis

Skills

Repeat defined forum format

#3 (1 day)

2015

Field
Practice
application of
lessons and
coaching
sessions to
help PMs
operate with
excellence

Q1

Q2

Field work
(~12 weeks)

Fill out KPIs and use


to have discussions
with management,
clients, and contracts
on the progress and
performance of
projects

Partnering with training provider


can help reduce timeframe
required for field work

Q3

Field work
(~12 weeks)

Provide workshops
for clients on
PD&Cs processes
Perform project
kick-off with client
Use transparency
tools throughout
project

Q4

Field work
(~12 weeks)

Leverage contracting
playbook during
contracting
Create risk
assessments before
project on critical
areas and develop
mitigation plans

Field work
(~12 weeks)

Coach new PMs in


process
Engage with
internal/ external
teams to develop
improved working
processes

Pre-Decisional - Proprietary and Confidential | 11

Applying capital productivity levers can increase CU Boulders


effectiveness and improve its organizational health in the project
delivery functions
Applying capital productivity levers can achieve
substantial efficiency in capital deployment.

in addition to multiple other benefits to


University of Colorado, Boulder

Estimated savings of 15% of the overall capital


spend based on select levers of streamlining
project delivery:
Stage-Gate process: move through multiple
fund and scope approval gates across lifecycle
allocating full funding when with a higher
degree of cost certainty
Contracting: select the project delivery method
and contract terms to match the project goals
and share risks
Transparency: add project controls and
tracking to provide right information at the right
time
Project Managers: spread project
management best practice to create consistent
approach

Grow a transparent and trust-based


relationship across all stakeholders (Board of
Regents, Administration, Planning, Design &
Construction, and Users) involved in project
delivery

Increase morale, accountability, and ownership


of projects in project delivery functions

Better able to attract and retain top talent in the


project delivery functions at CU Boulder

Better able to manage the pipeline of upcoming


projects from an internal resource perspective

Attract best contractors to engage in project


delivery of complex and base projects

Better able to anticipate and resolve project


performance related issues

Estimated savings of 30% based on all capital


levers across project prioritization, streamlining
delivery, and making the most of existing facilities

Maintain and enhance the beauty of the unique


campus architecture in a cost effective manner

Source: Expert interviews, Team Analysis

Pre-Decisional - Proprietary and Confidential | 12

PM
Tools

Transparency

Contracting

Stage gate

CU Boulder has started initiatives that address aspects of the four


recommendation focus areas
Initiative

Description

Involving PM earlier in the


process

Involving PM earlier at project conceptualization instead of


Design Development phase

Leverage technology for


permitting and inspections

Implementing electronic permitting technology to ensure


tracking of permitting and inspection

Engaging contractors with


performance specifications

Investigating use of performance-based specifications to


transfer risk to contractor and design team

Simplifying campus design


formats

Redeveloping campus design standards to more concise


format

Detailing project plans through


Project Charter

Providing an executive summary of Program Plan covering


agreed budget, schedule, and scope, signed by PD&C and
Administration

Creating Key Performance


Indicators dashboard

Developing preliminary set of project KPIs dashboards with


Office of Performance Improvement

Investing in software tools and


solutions

Undergoing an evaluation of software options to be used


across Facilities Management (e.g. developing database for
smaller projects to provide better cost estimates)

Source: CU Boulder Master Plan and Interviews

Pre-Decisional - Proprietary and Confidential | 13

Overall implementation plan


Phase 1: quick wins & critical actions

PRELIMINARY

Phase 2: building excellence

Activity
A. Stage gate process
Share plan and create SG working group
Define stage-gate process for CU
(roles, deliverables, etc @ each gate)
Major projects
Complex Minor and Outlays
Syndicate with key stakeholders
Launch: pilot, adjust, scale to all complex projects
Assess results and define next steps (e.g. extend
to base Minor and Outlays projects)
B. Contracting strategy
Identify CS working group
Create contracting strategy playbook
Syndicate with key stakeholders
Launch: pilot, adjust, scale to all projects
Assess results and define next steps
C. Transparency
Syndicate version 1.0 of transparency
measures (dashboard and PRB)
Implement version 1.0 for all Major projects
Design, pilot, and adjust PRB & dashboard v2.0
Scale v2.0 to all projects
Assess results and define next steps
D. Project Managers
Identify mode for PM trainings (internal/external)
Map needed PM skills (and current state)
Design program (curriculum and format)
Launch field and forum trainings
Define & implement policy to ensure sustainment
(e.g. training refreshers, assessments, etc.)
Assess results of PMs and define next steps
E. PMO for implementation

2015

2016

Oct Nov Dec

Jan

Phase 3: sustaining excellence

Feb Mar

Apr

Phase 4: future considerations

May Jun Jul

Aug Sep Oct

Nov Dec

Implementation of 1.0 continues until v2.0 is scaled to all

Workshop(s) to share recommendations and future plan


Source: Team analysis

Pre-Decisional - Proprietary and Confidential | 14

Appendix

Pre-Decisional - Proprietary and Confidential | 15

Contents

Organization context
Athletics project review
Overall diagnostic
Recommendations
Value at stake
Implementation plan

Pre-Decisional - Proprietary and Confidential | 16

Planning Design & Construction is a ~65 FTE organization within


Facilities Management that manages project delivery for CU Boulder
Department of Facilities Management Planning, Design and Construction
Facilities Management
PD&C

Facilities Planning
(7)

Facilities Engineering (12)

CAD/Document
Management/ CASP (6)

Design &
Construction (37)

Office
Administration (3)

Manages and
directs the
planning and
design of
campus facilities
and grounds
Maintains the
space database
Processes
official requests
for space
Performs space
utilization/needs
analyses

Reviews designs for


compliance with codes,
UCB standards, good
engineering practices
Provides engineering
support to the facilities
maintenance and
operations staff, design
guidance to UCB project
managers, and designoversight of consultants.
Develops and maintains
university standards,
design guidelines, and
construction-requirements
lists in cooperation with
maintenance staff.
Ensures code compliance

Source: CU Boulder organizational chart and PD&C website

Maintains library of
campus site and
building engineering
drawings
Catalogs and
archives campus
project documents
and related materials
Updates achieve
drawings accurately
reflect the campus
and its structures.
Develops and
maintains campus
GIS and maps
database

Provides
administrative,
management and
professional
services required
to facilitate and
accomplish
projects on the
campus
Coordinates the
bidding process
procuring
consulting services
Administers and
maintains
contracts, budgets,
and schedules

Supports
PD&C

Pre-Decisional - Proprietary and Confidential | 17

PD&C uses the following capital construction process for Major


BCPC = Boulder Campus Planning Commission
projects (1/2)
CCHE = Colorado Commission on Higher Ed.
FM = Facilities Management

Project Initiation
and Feasibility

Program Planning

Defines the
basic scope
and likely cost
of the project

Informs the
administration
about the
project

Secures
campus
administration
approval to
proceed with
development
of a program
plan

Outcome:
Approval to
prepare a
Program Plan

Source: Colorado.edu

Defines the
programmatic
requirements for
the designer
Defines limits of
work, including site
and infrastructure
requirements
Builds consensus as to
scope, cost and time
line of the project
Defines the financial
plan and sources of
funds

Outcome:
Campus agreement on
scope of project and a
funding plan identifying
sources of revenue

Approvals

Secures Approval
from Board of
Regents and CCHE

Incorporates project
into larger capital
financial planning of
university and state

Develops support
for the project at all
levels of state
government

Architect Selection

Concept and
Schematic Design

Selects the mostqualified architect


and engineering
firms to do the
project

Confirms and
enhances
program plan
requirements

Encumbers money
to begin the project

Generates
concept for final
building

Contractors are
selected for some
delivery methods

Provides room
by room layout
of spaces

Secures
approval of DRB
and review by
BCPC of
schematic plans

Secures funding for


State-funded project

Outcome:
Authorization to begin
expending money on
a capital construction
project

Outcome:
A design team is
contracted to design
the entire project

Outcome:
Schematic design
is approved and
project budget is
confirmed

Pre-Decisional - Proprietary and Confidential | 18

PD&C uses the following capital construction process for Major


BCPC = Boulder Campus Planning Commission
projects (2/2)
CCHE = Colorado Commission on Higher Ed.
FM = Facilities Management

Design
Development

Develops
detailed room
requirements
Integrates
infrastructure
systems into the
building design

Provides pricing
documents for
contractor

Secures final
DRB approval
and other
entitlements

Outcome:
Design Development is approved
within the
contract budget.

Source: Colorado.edu

Construction
Documents

Translates the design


intent into documents
from which a builder
can construct the
project
Describes the
quantity and quality
of the materials to be
provided by the
contractor
Provides final
estimates of the
project prior to
bidding

Outcome:
A complete set of plans
and specifications is
produced that describes
the design fully.

Bidding &
Negotiation

Initiates
procurement
processes for
all trades
Produces a
final construction price

Construction

Occupancy and
Warranty Period

Contractor constructs the


project

FM ensures that the building


is built per plans and specs
and meets building codes

The building is
occupied by the
users for which it
has been
designed

FM monitors the
project to identify
and correct any
construction
defects

Contracts
with builders
to construct
the project

Outcome:
Final contract
for construction

Outcome:
The project is realized

Outcome:
The building is
accepted and
available to
move in

Pre-Decisional - Proprietary and Confidential | 19

Contents

Organization context
Athletics project review
Overall diagnostic
Recommendations
Value at stake
Implementation plan

Pre-Decisional - Proprietary and Confidential | 20

Athletics Complex has been a challenging program and continues


to be a source of concern for CU Boulder

Original Program Plan called for a phased approach and was envisioned to be
completed August 2016/17
Accelerated timeline and performing all phases concurrently has created additional
stress on delivery model

Internal misunderstanding in early phases between Athletics and PD&C resulted in


ongoing project changes and cost escalations

Lack of team continuity, both internal and external, created hand-off challenges and
eventually coordination and communication challenges

GMP was not executed, despite constant assurance provided by Mortenson and an
agreed upon scope and budget that led to an agreement in GMP
GMP agreement of USD 141 M achieved in April 2015
In May 2015 Mortenson refused to sign

Quality assurance during project closeout is an important final step in Athletics


Complex project in order to prevent future costs and may require additional support
to supplement capacity of existing team structure
Current closeout process is mainly safety focus and user has already discovered
some closeout issues

Source: PD&C, Team analysis

Pre-Decisional - Proprietary and Confidential | 21

Introduction to the Folsom Field Athletic Complex upgrade plan


Athletic Complex project was intended to modernize and
advance CUs facilities among growing talent competition

Phases were intended to help reduce cost and inconvenience of


a full blown construction site but would have taken longer

Phase 1: 4th
Floor Buildout

Phase 2:
Indoor facility,
practice field,
and parking

Last major construction effort in 1991 with addition of Dal Ward


Upgrade to the facilities was an effort to increase recruitment
success of top-performing student athletes which were being
drawn to nearby schools with more advance facilities
Original Program Plan (and original cost) called for a phased
approach with the following phase split:
Phase 1: 4th Floor Build-Out to serve as Olympics Sports
Offices (USD 6.1 M)
Phase 2: Indoor facility, practice fields, site development, and
above ground parking lot (USD 117.9 M)
Phase 3: Dal Ward renovation1 (USD 15.8 M)
Original occupancy date was estimated August 2016/17

Contract was drafted as a Design/Build with a Guaranteed


Maximum Price (GMP) but clause was not executed

Under design/build contract, lead contractor is tasked with


developing designs for the end building and executing on that
design
GMP clause is a clause which sets an upper budgetary limit
which project is expected not to surpass. Costs which exceed that
limit are not to be paid by the client and is an effective risk
mitigation tool
GMP clause was never formally executed by Mortenson
Contract form is ideal for fixed and known project scope,
situations similar Folsom Field Athletic Complex with evolving
scope is not best suited

3
1
2

Phase 3: Dal
Ward

Winners of contract were contractor Mortenson and


architectural engineering firm Populous

Role on
project
Team
Governance
Site
presence

Winning contractor,
led contractor
relationship with CU

Design part of bid


team, essentially
worked for Mortenson

Final decision-maker
for build team

Made recommendations which needed


Mortensons approval

Multiple staff flying in


as needed

Select staff moved to


Boulder, others

1 Includes Space for Olympic Sports teams and their support spaces, training table, and renovated and expanded academic support center
Source: Interviews, Athletic Complex Program Plan

Pre-Decisional - Proprietary and Confidential | 22

Athletics Complex has been impacted by high rates of personnel


turnover both at CU and Mortenson
Lack of continuity has significantly impacted progress of the project
Group

Position

Active period
2013

Athletics
Department
Planning,
Design, &
Construction
Administration

Mortenson

Athletic Director

AD 1

Assistant AD

AAD 1

Campus Architect,
Director of PDC

CA 1

Project Manager
User Rep

2014

2015

Present

AD
AAD 2
CA 2
PM 1

UR 1

PM 2
No replacement

Dir of Project Dev

Dir 1

Dir 2

C&D Liaison

CDL 1

Lead estimator

LE 1 and CDL 2

VP, Gen Manager

VP 1

SR Proj Manager

PM 1

Project Manager

PM 1

Lead Designer

LD 1

Multiple PMs

Populous

Source: Interviews

Pre-Decisional - Proprietary and Confidential | 23

Changes represented a significant upward budgetary push, which


were offset by cost cutting initiatives in other areas of the project
PRELIMINARY

USD millions
Increases driven by twelve significant scope evolutions, but those increases were controlled by three reductions
1
Indoor
Parking1

24

Focus of
changes only
on significant
changes to
scope

Does not
include
required
changes to
schedule,
manpower,
and other
changes
required to
support scope
change

2
IPF2
Track

11

Rooftop
Design

3
5

IPF2
Height
Reduct

-1

5th

Floor
Add-on

0.3

Dal
Ward

-6

Total

12

Footprint

Aud/
Vis

13

10

Rooftop
bridge

0.4

Grounds
Temp

Kitchen

Brand

0.2

IPF2
Sprinklers

Total

0.7

Total

Total

Total

0.2

Total

14

-0

15

16

Tenant
Finish

Value
Eng

-2

DAS
Systems

Total

Total

-2

Total

-2

3
2
1
Feb

Jun

Jul

Apr

Total

Mar

May

Sep

Dec

Jan

2014

2015

1 Separate project but had schedule and cost implications on Athletics Complex 2 IPF = Indoor Practice Field
Source: Interviews

Pre-Decisional - Proprietary and Confidential | 24

Going forward, there are three important considerations for the


Athletics Complex project

1 As of December 2015, the project is 93% of budget (USD 140


M) has been released to Mortenson
2 Current closeout process has strong administrative and safety
focus, no identifiable quality assurance closeout plan is in
place and may require additional support capacity
3 Throughout the project, Mortenson provided constant
assurance to CU personnel that project was on track with
agreed upon budget and timeframe

Source: Interviews, Press Search, Mortenson

Pre-Decisional - Proprietary and Confidential | 25

Contents

Organization context
Athletics project review
Overall diagnostic
Recommendations
Value at stake
Implementation plan

Pre-Decisional - Proprietary and Confidential | 26

Overall capital program diagnostic


Quantitative performance on CU Boulders capital portfolio over the past 5 years shows overruns
and delays for a set of Major projects as well as underruns for Minor and Outlay projects

Major projects (projects above $2M) comprise of 80% of the spend. Approximately 8 projects
requiring additional spending limit were typically those impacted by accelerated timeline, scope
changes, or decision delays

Significant portion of the spend, ~$250M, is still outstanding and provides an opportunity to
improve project delivery in on-going projects

Though market conditions impacted the overall cost of projects since 2009, there is no immediate
impact on attractiveness of CU projects based on bid analyses

More than half (>1000 projects) of all Minor and Outlay projects are completed at 5% or more
under the original target cost, similar to other public agencies

Qualitative analyses and review of select Major projects show that CU Boulders capital program
faces challenges in both strategy and project delivery with the following key opportunities:

Capital planning: Meet target costs by rethinking approval process to match the release of funds to
the maturity level of the project

Contracting methodology: Manage owner risk through clear guidelines on selection project delivery
method or contracting terms

Communication: Manage risks proactively by increasing project tracking and clarity in


communicating progress with appropriate stakeholders

Project Manager workforce: Increase consistency in PM workforce through structured training and
onboarding processes and a decrease in turnover
Pre-Decisional - Proprietary and Confidential | 27

Over the past 5 years, CU Boulders capital spend has been


concentrated on Major projects with a valued budget of ~$870M
PRELIMINARY
Number of
projects

Total budget on projects1

Examples
Project size range
Total value

302

Major

Category I
Range $2-$50
Total value $318M

Category II
Range $50-$100
Total value $240M

Category III
Range $100+
Total value $308M

$867M
Range $500K-$1M
Total value $42M

980

Minor

Range $25k-$500K
Total value $91M

$171M

Range $1-$2M
Total value $39M
957

Outlays

Projects over $2M


Athletics Complex
Systems biotechnology
building
Recreation facilities
improvements

Projects between $25k$2M


Food service renovation
Replace boilers, roof
Lab renovation

$8M
Projects under $25k
Sound proofing
Temporary cooling
Fire alarm upgrade

1,967

Total

$1,046M

1 Representative project scale but not exhaustive. Current budget for projects from March 2010 after the implementations of the CP module to September 2015 across all stages of
development from planning (~$30 M) to closed. Budget defined as most recently approved budget in FAMIS as of mid-September 2015
2 Two grants listed as separate projects were merged with their associated projects. Three projects out of the 30 are ESCO with combined project value of USD ~21 M

Source: PD&C, Team analysis

Pre-Decisional - Proprietary and Confidential | 28

Projects requiring additional spending limit were typically impacted


by accelerated timeline, scope changes, or decision delays
PRELIMINARY

NON-EXHAUSTIVE

USD Million

Initial
legislative
spending limit2

Athletics Complex1

142

System Biotech
Projects
impacted
by
significant
scope or
timeline
fluctuations

160

113

Campus Utility1
SEEC1

USD Change in
legislative
spending limit
18

169

75

91

60

56
16

112

53

% Change in
legislative
spending limit

50%
21%
88%

28

37

10

35%

SB Academic Wing1

22

28

28%

Ketchum1

13

23

10

75%

Ekeley Middle Wing

12

14

17%

SPSC - Data room

12

N/A

N/A

N/A

0%

0%

64

64

43

43

EUCLID1 (CASE)
Wilderness1

18

20

14%

IBS

14

16

13%

Bball/ Vball Practice

11

11

2%

Wilderness - Recom

0%

Stad - Video Board

0%

0%

Glenn Miller Ballroom

10%

Hallett Renovation

0%

Atmospheric Lab

0%

GIPF Bldg

(Athletics) 1

Detailed next

12%

JILA

Rec Facilities

Normal
projects

Current
legislative
spending limit3

Observed difference
in performance
between projects
which are pursued
as expected and
those impacted by:
Accelerated
scheduling
Significant or
constant scope
changes
Delayed timing in
decision-making

1 Ongoing project | 2 Initial legislative approval | 3 Current legislative approval

Source: Team Analysis, PD&C

Pre-Decisional - Proprietary and Confidential | 29

Specific context of building projects reveal important details about


on the dynamic process of design and construction (1/3)
Athletics Complex

System Biotech

Driver for cost change: Accelerated project timeline,


insufficient time for program planning complex project
Additional context
Accelerated timeline provided limited time for
planning efforts to which external consultant was
hired to supplement
Inadequate familiarity/attention to capital process
and requirements by new campus staff
Important changes and decisions were being
made as late as construction

Driver for cost change: Unforeseen construction


escalation in laboratories and need to master plan the
building site for East Campus
Additional context
Efforts were required to master plan the site for
East Campus impacting the budget and schedule
Laboratory facilities required more advanced
features than expected
Additional design fees for LEED certification

Campus Utility

SEEC

Driver for cost change: Delayed approval and new


environmental requirements
Additional context
Original program plan developed in 2007 which
set budget in dollars for that market
Original plan called for $134 M project but
program was only approved for $75 M plan was
reworked
Approved 2011 plan operated in a more expensive
market; student support for continued CoGen

Source: Team Analysis, PD&C

Driver for cost change: Delayed funding, changed


site and program fluctuation
Additional context
Program planning efforts began in 2002 and were
paused, restarted and finalized in 2008
Series of approval delays and program plan
amendments led to the escalation of cost
compared to original budget request
Nature of the building and the market costs
changed significantly from 2008 to 2015

Pre-Decisional - Proprietary and Confidential | 30

Specific context of building projects reveal important details about


on the dynamic process of design and construction (2/3)
JILA

Systems Biotechnology Academic Wing

Driver for cost change: Delayed federal funding and


unforeseen construction needs
Additional context
Original project cost estimated in 2007 but federal
funding was not available until 2009
Unforeseen existing conditions around hazardous
materials were discovered underground (e.g. aged
plant fuel storage tanks)
High sensitivity of research equipment required
advanced vibration-prevention features

Driver for cost change: Delayed funding availability


Additional context
Educational wing of this facility delayed from 2006
to 2015-16 due to the demand for state capital
construction funding and economic hardship
Original cost was completed before the
construction upswing in the Denver area
Increase of cost driven by higher market demand
and inflationary cost which occurred between
2008 and present day

Ketchum

Ekeley

Driver for cost change: Scope significantly evolved


from original capital renewal scope
Additional context
First state funding request was in 1998 which was
only for capital renewal of the building; Circa 1938
building
Appropriated design funds rescinded along with
construction phase funding in 2007-08
2014 funding was granted for a complete overhaul
with an expanded program plan

Source: Team Analysis, PD&C

Driver for cost change: Delayed funding and


inflationary impact of costs
Additional context
Project plan originally scoped in late 1990s
Appropriated design funds rescinded along with
construction funding in 2007-08
Inflationary cost pressures from the original
funding approval impacted the budgetary needs of
the project

Pre-Decisional - Proprietary and Confidential | 31

Specific context of building projects reveal important details about


on the dynamic process of design and construction (3/3)

SPSC Data Room

Driver for cost change: Cost decreased significantly due to

dramatic technological innovation in market


Additional context
Original plan was to develop a facility to hold data servers
to back-up crucial university information
Popularization of online cloud memory capabilities
significantly drove down the need to purchase devices to
support data needs of university
Project costs were dramatically reduced

Source: Team Analysis, PD&C

Pre-Decisional - Proprietary and Confidential | 32

Denver market conditions impact project performance (both


positively and negatively) and need to be accounted for in planning
4,500
6,890

6,985

7,010

7,078

7,000

4,450
6,341

6,384

4,450

4,400

6,500

4,300

5,000
4,500

4,250

4,000

4,150

4,178

Recession
recovery

3,500

Growth
period

3,000

4,092

4,100

Observations:
Denver area market
experienced growth
increase in prices over
the past five years

From June 2009 to July


2010 the compound
aggregated growth rate
was 1.91% for BCI and
3.04% for CCI

Further pricing pressure


may existing due to
scarcity of labor at
subcontracting levels
and increasing project
demands coming online

2,500
2,000

4,050
4,000

CCI

5,500

4,317

4,200

BCI

6,000

4,342

4,350

7,500

1,500

3,975

1,000

3,950

500

3,900

2010

2011

2012

2013

2014

2015

NOTE: The ENR indexes measure how much it costs to purchase the following hypothetical package of goods compared to what it was in the base year. The CCI uses 200 hours of common
labor, multiplied by the 20-city average rate for wages and fringe benefits. The BCI uses 68.38 hours of skilled labor, multiplied by the 20-city wage- fringe average for three trades
bricklayers, carpenters and structural ironworkers. For their materials component, both indexes use 25 cwt of fabricated standard structural steel at the 20-city average price, 1.128 tons of
bulk portland cement priced locally and 1,088 board ft of 2x4 lumber priced locally.

Source: Engineering New Record, Team analysis

Pre-Decisional - Proprietary and Confidential | 33

Analysis of bids reveal CU projects are attractive to general market


Project

Construction
start

Project budget
(USD M)

Total
interested
bidders

13

Total
qualified
bidders

Highest
Lowest Spread
(%)
11%

Second Lowest
Lowest Spread
(%)
3%

IBS

Jun 09

Sys biotech

Sep 09

B/V Ball

Apr 10

11

WLRD Rec

May 10

HLET

May 10

Jila

May 10

East Elect

May 11

Video board

Apr 12

Rec facility

Jun 12

Utility syst

Aug 12

EKLC

Apr 12

Comp data

Aug 13

12%

3%

Atmos lab

Aug 13

12%

1%

MAC

Dec 13

Athletics

Apr 14

GM Ballrm

May 14

GIPF Blg

Sep 14

Ketchum

Jan 15

Wilderness

Mar 15

Ecme Hvac

Sep 15

Euclid

Oct 15

E-wing

Jan

161

1 Expected construction start

Source: PD&C, Team Analysis

143

32%
10%

32

13

0%

14%

6
5

5%

24%

4%

23%

6%

41%

18%

64

10

86

13

14

91

23%

4
14

32

3
10

2
43

13%
23%

2
6
8

6%

40%
3%

6%

11
2

17%

46%

22

25%

10

148

6%

32%

3%
2%

35%

5%

40%
13%

22%
1%
0%

17%

4%
40%

23

No
discernable
trend can be
identified
when
reviewing
past history
of Major bids,
while total
number of
interested
bidders is
trending
lower in 2nd
half of 2015

15%
8

Pre-Decisional - Proprietary and Confidential | 34

Minor and Outlay projects are routinely under budget


Total budget over/underrun USD Millions

Minor projects1
N = 7862

Outlay projects1
N = 6102,3

342

55% of projects
USD 20.2 M
underrun

64% of projects
USD 1.5 M
underrun

214
186

106

5-20

20-50

50+

0.6

3.1

3.1

15

>-20 -20- -5

-5-5

5-20

20-50

50+

Percentage over/under budget


14.7

Underruns in Minor
and Outlay projects
amount to ~$22M,
less than 2% of
overall capital
budget over five
years

Underruns are
expected given low
project values and
lack of knowledge
on existing field
conditions

99

Percentage over/under budget


-0.2

Majority of projects
were under budget
by more than 5%
(55% of Minor and
64% of Outlay)

122

24
-5-5

176

1092

10

>-20 -20- -5

PRELIMINARY

-0.1

0.2

0.5

0.8

1 Includes Substantial Completion, Post Construction, and Closed Representative from March 2010 after the implementations of the CP module to
September 2015
2 Excludes projects with USD 0 spend, Minor = 11 and Outlay = 12
3 Excludes 215 closed projects with a budget of USD 0 but representing USD 890 K of actual spend
Source: PD&C, Team Analysis

Pre-Decisional - Proprietary and Confidential | 35

Among other public organizations, regular underruns for Minor and


Outlays are not uncommon but may constrain user
PRELIMINARY
access to capital
Underrun represents approximately 18% of total
budgeted amount for Outlay and Minor projects1
Outlay

USD Millions
129

-22
2

which is in line with other public organizations


setting budgets for similar projects
Average % budget underrun

Minor

21

107

1
0

Public org 1

14-18%

0
Up to
30%+

Public org 2

120
CU

Budgeted

Underrun

Overrun

Spend

18%

Potential to unlock limited value by tightening


budget estimation processes or employing staged
release of funds during project execution
Lower underruns may allow greater budget to
perform more projects
Performance metrics need to capture user
satisfaction, delivery schedule, and execution cost

1 Includes Substantial Completion, Post Construction, and Closed Representative from March 2010 after the implementations of the CP module to
September 2015
Source: PD&C, Team Analysis, Press search

Pre-Decisional - Proprietary and Confidential | 36

Rapid diagnostic evaluates the effectiveness of CU Boulders


Capital program across the following dimensions
Best practice area

Formal mechanisms for ensuring corporate strategy implementation

Risk/return appetite estimation

Establishing corporate/group level risk and return expectations

Capital headroom calculation

Calculation/simulation of cash generation and investment ability

Portfolio review

Top down review of project portfolios, including improvement


potential

Portfolio allocation

Selecting projects for execution, understanding interactions, risk

Ongoing returns tracking

Evaluating how results match to risk/return appetite

Opportunity Origination

Initial scoping of opportunities and preparation for project success

Business case optimization


and concept selection

Development and testing of concepts against a reference case for


most effective selection

Design, procurement, &


contracting

Detailed project design, planning, and procurement

Construction & Execution

Tactical project execution including scope changes

Comm. & Ramp-up

Startup and handoff to ongoing operating team

Project control

Assessing project outcomes, establishing feedback loops

Organization

Organization structures and standards applied to capital

Mindsets and capabilities

Personnel attitudes and skill sets devoted to capital

Processes and tools

Enabling systems applied to capital budgeting and delivery

Capital Strategy Strategy translation

Portfolio
Strategy

Project
Delivery

Enablers

Description

Source: McKinsey Capital Productivity Practice

Pre-Decisional - Proprietary and Confidential | 37

Rapid diagnostic based on interviews and select project reviews


reveals that strategy as well as project delivery are below
industry average at CU Boulder

PRELIMINARY

Enablers
Project delivery
Opportunity
origination

Concept
selection

Project
definition
and
approval

Project
execution

Project
ramp-up

Project control

Commissioning and
ramp-up

Organization
4.0

Processes and tools


Mindsets and
capabilities

3.0
2.0

Construction and
Execution
Design. procurement.
and contracting
Business case
definition and concept

Strategy translation to
asset base

1.0
0.0

Risk/Return appetite

Industry average = 2-3

Opportunity origination
Ongoing returns
tracking

Capital headroom
calculation

Capital Strategy

Portfolio review
Portfolio allocation

Portfolio Strategy

Source: Based on 40+ interviews with PD&C

Pre-Decisional - Proprietary and Confidential | 38

Based on 40+ interviews, select project reviews, data analysis, and


focus groups we identified a set of opportunities
Opportunities to increase efficiency and effectiveness

Cross-cutting

Project
execution

Contracting

Design

Capital
Planning

More consistent Program Planning efforts, aligned with paced project schedule to decrease
owner risk
Address backlog in maintenance through improved capital allocation
Enhance integrated portfolio view with clear project prioritization
Rethink approval process to match the release of funds to the maturity level of the project
Augment alignment between PD&C and administration in regards to project budget estimates
and timelines
Continue with recently launched effort for early engagement of Project Manager in project
lifecycle

Emerging themes for


developing excellence

Develop a clear, welldocumented, and scalable


stage gate process to
drive capital investment
success

Adopt clear guidelines in


contracting strategy to
address project risk based
on project scope, target
cost, expected delivery
schedule, market
conditions, and internal
capability

Refine choice in contracting strategy (choice of delivery model, contract type, award process) to
align to scope, project schedule, market conditions, and owner execution capability
Consistently enforce contract terms in the field leading to lower owner risk

Standardize project execution processes


Adopt and enforce tools and as a standardization method
Increase ownership of project controls (i.e., cost and schedule tracking)

Deploy project controls


to drive transparency of
cost, schedule, and
milestones during project
execution thus increasing
consistency

Enhance communication on project progress


Celebrate success
Leverage performance monitoring (e.g., lessons learned at project completion) as source of
insight
Provide training for onboarding new employees and continuous development

Train and retain the


Project Manager
workforce to ensure best
practices adoption and
execution in project
management

Source: Interviews

Pre-Decisional - Proprietary and Confidential | 39

Contents

Organization context
Athletics project review
Overall diagnostic
Recommendations
Value at stake
Implementation plan

Pre-Decisional - Proprietary and Confidential | 40

CU Boulder can adapt best practices in capital management across


the four themes to begin developing excellence
Emerging theme
Stage-Gate process:
how do projects
move through
A multiple fund and
scope approval
gates through the
lifecycle?

Stage-gate process matches the release of


required funds to the maturity level of project
definition; specifically, it ensures projects do not
progress without an adequate evaluation of the
underlying business case, completion of key
deliverables, and mitigation of critical risks

Clear guidelines on
contracting strategy
to best manage
owner risk

Selecting contracting strategy (delivery model,


contract terms, award process) based on project
specifications (size, cost, delivery schedule,
complexity), market conditions, and internal
capability

Tracking information
on cost, schedule
and milestones for
each project

Project controls dashboards enable PMs and


Project Coordinators to:
Proactively identify issues
Ensure relevant information is at hand to
contribute to the decision making process in a
timely manner

Standardized
processes with
capability building
training to ensure
consistent execution

Establishing standardized methods, training for


PM staff on consistent approaches, and support
from key decision makers which allow PM team
to increase success in delivery of projects

Source: Interviews, Expert interviews, Team analysis

VGI-AAA123-20090508-

Contracting strategy entails defining 3 linked elements


of a project
Key dimensions of contracting strategy

Key questions to be considered


Delivery model (How do I determine optimal contracting scope?)

Should I own the asset or are other ownership structures more


suitable, e.g., lease?

Which project value chain steps should be done internally and which
ones by contractor(s)?

Into how many contracts should the project scope be split?


What is the optimal split of scope between the contractors?

1 Delivery
model

Award process (How do I select my contractors?)

How can the effectiveness of existing award process be enhanced ?


How many and which suppliers/contractors should be invited?
How do we get the suppliers interested?
What is the criteria for evaluation various suppliers?

3 Contract
terms
2 Award
proces
s

Contract terms (How do I ensure most optimal contracting terms?)

What are the key project cost, performance, and schedule risks?
Who is the natural owner of the risks?
What mechanisms exist to transfer or share risk?
How can objectives be aligned between owner and contractor to
ensure an efficient execution through compensation elements such
as incentives, penalties, warranties, etc.?
McKinsey & Company | 3

SJO-AAA123-20110525-

4 Planning and scheduling process

Create/ update
plan

Process step

Users

Progress
measurement

Provide timely,
accurate inputs
Help in identifying
critical milestones

Create WBS
Identify critical
milestones
Create/ update
plan
Publish plan

Customized
analysis

Provide timely,
accurate inputs
Execute recommended focus
actions

Monitor & report


project progress
Recommend
focus actions/
area
Publish report

Identify required
analyses
Provide timely,
accurate inputs

Roles

Printed

Single and
comprehensive
capital investment
framework

W orking Draft - Last Modified 07-Sep-11 6:35:55 PM

Project Managers:
how well is project
D management best
practice followed?

Printed 4/6/2011 4:32:15 PM

Transparency: how
do project controls
C allow for right
information at the
right time?

Description

W orking Draft - Last Modified 9/7/2011 3:32:09 AM

Contracting: how
project delivery and
B contracting methods
are selected

Best practice

Planning
team

Recommend &
perform required
analyses
Publish analysis
report

McKinsey & Company | 5

Pre-Decisional - Proprietary and Confidential | 41

STAGE GATE PROCESS

A Existing CU Boulder approval process for Major projects does


not match project maturity with funding commitments
# Funding gate

# Review-only gate

Current Process
PD&C Planning Led Process
Project
Initiation/
Concept
Development

Consultant and
Contractor
Selection

Program
Planning
1

PD&C Project Manager Led Process

Schematic
Design

Design
Development

Construction Documents

Bidding
and Negotiation

Construction

Close Out
and
Warranty
Period

2
Project obtains board approval and is funded

Cabinet review and authorization


Observations

Unclear project pipeline prioritization process leads to suboptimal use of resources in developing Program Plans
Consensus must be built across many campus departments to xdevelop a Program Plan which requires considerable investment
of time and effort from the PD&C planning staff
100% of project target cost is established and committed before design is adequately developed
Length of time from project approval at funding gate 2 to project bidding exposes CU Boulder to market conditions as project
estimates no longer reflect the current market conditions
Project Managers enter the process after critical project decisions regarding scope and schedule are made
Continued scope development occurs in the schematic design and design development stage through user input

Source: CU Boulder PD&C website and interviews

Pre-Decisional - Proprietary and Confidential | 42

STAGE GATE PROCESS

A Adding stage gates to existing Capital Project Process will focus


University resources and increase control for Major projects
# Funding gate
From...

# Review-only gate

Operations
PD&C Planning Led Process

Project
Initiation/
Concept
Development

Consultant
and
Contractor
Selection

Program
Planning

PD&C Project Manager Led Process

Schematic
Design

Design
Development

Construction
Documents

Bidding and
Negotiation

Construction

Close Out

2
Project Obtains Board Approval and is Funded

Cabinet Review and Authorization

to

PD&C Planning Led Process


Project
Initiation/
Concept
Development

Program
Planning/
Scope
Selection

Is this needed? Is it a
priority?

2a

PD&C Project Manager Led Process

Consultant
and
Contractor
Selection

Schematic
Design

Design
Development

Construction
Documents

2b

Is the best option still viable after scoping?


Freeze Scope. Release full budget.

Develop feasible options. Release seed money.

Source: Expert interviews, Team analysis

Bidding and
Negotiation

Construction

Start-up/
Commissioning

Close Out

Is the project ready to begin operation?

Is option still viable given the refined estimate?

Is the project ready to be turned over?

6
Any
outstanding
accounts or
issues?

Pre-Decisional - Proprietary and Confidential | 43

STAGE GATE PROCESS

A Proposed process splits the funding gate and provides an


opportunity to develop the design prior to committing total funds
# Funding gate

Consultant and
2a Contractor
Selection

Project Initiation
Program
and Concept
1
Planning
Development
Cabinet Review and
Authorization pre-design

Schematic Design

Select best option or set of


alternatives to further develop

2b

# Review-only gate

Design
Development

Release full project funds with


stronger confidence

Estimate Accuracy1
Percent

Share of total
Percent
30%

>50
50

100% of funding
committed

40

30

25

30
20

20

0.5 10% of
funding
committed

10
0

15

-10
5-15%

-20

10%

10

-30
5%

-40
-50

0.5%
Funding required (percent of total investment cost)

5
2%
Engineering complete

Estimate accuracy

1- Cost estimate accuracy increases (narrows) as design progresses, even as the cost estimate mid-point fluctuates as design progresses.

Source: Expert interviews, Team analysis

Pre-Decisional - Proprietary and Confidential | 44

STAGE GATE PROCESS

A Stage-Gate Process for complex projects at CU Boulder will


help manage resources and provide more financial control (1/2)
Stages

# Funding gate

Project Initiation and 1


Concept Development

Activities

Someone identifies a
project

Options are generated


with order of magnitude
estimates

Program
Planning

2a

A/E and/or
Contractor
Selection

Schematic Design

# Review-only gate

2b

The best option Design Team and/or Contractor Selected


is selected and
funds are
allocated to
complete
preliminary
engineering

either in a temporary (Paid competition/initial


design phase contract) or permanent basis
depending on project and delivery method
selected
Basic engineering is conducted to create a
decision-worthy estimate

Review gate 1

Funding gate 2a

Funding gate 2b

Gate questions:
Is the project need legitimate?
Is it a priority?

Gate questions:
Do feasible options exist that
match the intended purpose?

Gate questions:
Is the best option still viable after
scoping?

Stakeholders:
User
PD&C (Planning)
Vice Chancellor, Administration

Board of Regents (Informed)

Stakeholders:
User
PD&C (Planning and PM)
Vice Chancellor, Administration
CFO
Finance
BCPC (Informed)

Stakeholders:
User
PD&C (PM, Eng., Shops)
Design Team & Contractor
Vice Chancellor, Administration
BCPC
Board of Regents

Final approval authority:


Vice Chancellor

Final approval authority:


CFO

Final approval authority:


Board of Regents

Source: Expert interviews, Team analysis

Pre-Decisional - Proprietary and Confidential | 45

STAGE GATE PROCESS

A Stage-Gate Process comparison for the Wildlife Place project


# Funding gate

Existing Process

Contractor
Selection/Schematic Design

% Design
Complete

0%

5%

Project
Estimate

--

$17.9M

Funding
Required

Program Plan
Funding

100% of project
estimate

Board of
Regents

--

Board approves
full capital spend

Proposed Process

Program
Planning

Program
Planning

Contractor
2a Selection/Schematic Design

% Design
Complete

0%

5%

Project
Estimate

--

$9M - $26.9M
($17.9M)

Funding
Required
Board of
Regents

Program Plan
Funding
--

Source: Expert interviews, Team analysis

$2.2M (12.5%
of Estimate)
Board informed
of design start

Design
Development

# Review-only gate

Construction
Documents

After Funding:
Increase to $22.4M at 100% DD estimate
VE and ESCO engaged, schedule slips
Board of Regents approves additional $2.5M (Total $20.4M)
Additional funding required to achieve project scope

Design
Development

2b

Construction
Documents

30-50%

Project estimate tightens through SD ($19M - $25.8M )


VE to reduce cost, based on need and function, retain quality
$20.2M (mid-point of estimate less $2.2M from Stage 2a
funding gate)

Board of Regents approves capital spend for remaining


unfunded portion of project (~80-90%)
Pre-Decisional - Proprietary and Confidential | 46

STAGE GATE PROCESS

A An internal stage gate working group of stakeholders can


design processes and develop necessary documentation

Detailed next (sample)

Stage Gate documentation: suggested table of contents


Stage Gate
Playbook creation process
Suggested working group:
PD&C (3)
Planning
Representative
Project Manager
Engineering
Vice Chancellor
Potential Participants (at
key intervals):
Users
Legal
Activities:
Conduct a series of
workshops to address
each section of the stage
gate playbook
Review playbook with key
stakeholders to validate
approach

Source: Expert interviews, Team analysis

Stage Gates
Decision and funding gates for:
Base Projects
Complex Projects
Gate 1
Objectives for Gate
Key Deliverables for Gate
By Function
Timeline
Critical Functions of Team
Summary Process Map for Gate
Project Managers Roles in completing
Gate
How to ensure success at Gate 1
Gate 2a
Objectives for Gate
Key Deliverables for Gate
By Function
Critical Functions of Team
Summary Process Map for Gate
Project Managers Roles in completing
Gate
How to ensure success at Gate 2a

Gate 2b
Objectives for Gate
Key Deliverables for Gate
By Function
Timeline
Critical Functions of Team
Summary Process Map for Gate
Project Managers Roles in completing Gate
How to ensure success at Gate 2b
Gates 3-6

Objectives for Gate


Key Deliverables for Gate
By Function
Timeline
Critical Functions of Team
Summary Process Map for Gate
Project Managers Roles in completing Gate
How to ensure success at Gate 2b

Appendix

Alternative Gates for Special Projects


CU Boulder Standard forms

Pre-Decisional - Proprietary and Confidential | 47

STAGE GATE PROCESS

A Stage 1 Project Initiation and Concept Development


Objectives, key deliverables, and critical functions
ILLUSTRATIVE

Objectives

Key deliverables

Select best scope

Explicit reconciliation of variances

alternative that meets


the CU Boulders needs
and objectives

Define all scope


elements to a level
enabling sound decision
making

Define project execution


plan to meet targets as
required

against project requirements

Complete scope identification and


selection of a single option for all scope
elements

Complete draft of a project execution


plan

Initial risk assessment


Cost estimate with an accuracy of

Planner - lead
Users
Engineering
Operations / Shop support
Outside support:
Estimating
Scheduling

50%; and a first estimate at an


operations expenditure budget

Develop an initial schedule through


completion, including resources for
next phase

Source: Expert interviews, Team analysis

Critical functions

Support functions

Finance
Vice Chancellor

Pre-Decisional - Proprietary and Confidential | 48

STAGE GATE PROCESS

A Stage 1 Project Initiation and Concept Development (1/2)


Deliverables by function
ILLUSTRATIVE
Function

PD&C (Planning
and Project
Manager)

Deliverable

Project charter
Issue record of decision for alternative selection
Provide detailed scope
Conduct analysis to facilitate key decision points(e.g., site, execution
strategy)
Develop initial project execution plan (scope / change management plan;
project team and resources; contracting strategy; risk management;
project controls (KPIs); estimate (50%), quality, procurement, testing
and close out, schedule; communication plan; contractor management

Engineering
lead

Evaluate technical alternatives analysis and provide recommendation


Complete basic engineering data requirements (e.g., load requirements,
equipment sizing, energy use, etc.)
Implement optional value improving practices (VIPs):
Types of plant and equipment
Concept optimization
Constructability reviews

Regulatory

Assign code representative, if applicable


Assign environmental representative, if applicable

Source: Expert interviews, Team analysis

Pre-Decisional - Proprietary and Confidential | 49

STAGE GATE PROCESS

A Stage 1 Project Initiation and Concept Development (2/2)


Deliverables by function
ILLUSTRATIVE
Function
Contracting
Strategy
Operations and
Maintenance
Quality
assurance
Finance

Legal

Deliverable

Define delivery method, contract award method, and contract terms

Provide OPEX cost estimate, if applicable


Assign operations representative for next phase, if applicable
Define maintenance requirements, if applicable

Define quality oversight

Review estimate, validate financial view calculation


Input project into the budget

Provide support, as required

Source: Expert interviews, Team analysis

Pre-Decisional - Proprietary and Confidential | 50

STAGE GATE PROCESS

A Stage 1 Project Initiation and Concept Development (1/2)


Summary process map
ILLUSTRATIVE

Form core
project team
Review
business case
Clarify roles and
responsibilities
Identify targets
as per CU
Boulder needs
Review project
charter
Identify
additional
resources
required
Project manager
assigned

Initiate
conceptual
engineering
User
requirements
Preliminary
massing
Assess
infrastructure
requirements

Source: Expert interviews, Team analysis

Identify financial
and logistical
issues

Narrow down
potential sites (if
applicable)

Narrow down
building concept
and potential MEP
systems

Update
conceptual
engineering
Include massing
Process control
strategies

Apply value
improvement
practices
Finalize
programmed
areas
Agree on
standards and
specifications
Conduct
process
simplification
and/or value
engineering
Conduct early
constructability
analysis

Scope and
document the
best option:
Conduct formal
evaluation of
alternatives
including fatal
flaws analysis,
and select best
available option
for application
Document
record of
decision

Pre-Decisional - Proprietary and Confidential | 51

STAGE GATE PROCESS

A Stage 1 Project Initiation and Concept Development (2/2)


Summary process map
ILLUSTRATIVE

Develop
operations and
maintenance
strategies

Decision Gate
Estimate OPEX
Recycle
Proceed to Stage 2a

Conduct
preliminary
equipment
sizing

Finalize and
review scope of
work

Develop Plans
for Completing:
Basic
engineering
Detailed
engineering
Procurement
Construction
Contracting
Project controls

Reconcile
project
objectives

Develop
schedule to
reach Stage
2a and
detailed
milestone
schedule for
execution
phase

Develop
resource
requirements
for Stage 2a

Cancel/postpone
Develop
detailed
risk matrix

Update
Campus project
budget

Issue record of decision


Confirm business objectives, risks
and uncertainties and confirm
compliance with both CU Boulder
and user requirements and
strategies

Prepare
factored
estimate
(50%)

Confirm project objectives,


priorities, trade-offs
Confirm scope to be developed
and compliance with University
objectives
Present cost and schedule

Confirm basic
engineering
requirements
Develop
renderings

Review
engineering
requirements for
permits

Source: Expert interviews, Team analysis

Summarize project execution


strategy and plans
Identify resource requirements for
next phase and through project
completion

Pre-Decisional - Proprietary and Confidential | 52

STAGE GATE PROCESS

A Though the proposed stage-gate process is currently defined


for Major projects, CU Boulder can extend the process to
complex and eventually all Minor and Outlay projects (1/2)
Rough cost of
project

Major
Project
Threshold

2,000,000
Complex
projects
500,000

Base Projects
can continue to
utilize existing
stage gate
process,
potentially adding
key QA/QC steps

Complex and
Major Projects
should use
proposed stage
gate process

Definition of
thresholds should
be agreed
through StageGate working
group

Base
projects
150,000

Low

Med/High
Complexity

Source: Team analysis

Pre-Decisional - Proprietary and Confidential | 53

STAGE GATE PROCESS

A Though the proposed stage-gate process is currently defined


for Major projects, CU Boulder can extend the process to
complex and eventually all Minor and Outlay projects (2/2)
Expansion of stage
gate process
Phase 3
(2 months)

Phase 2
(3 months)

Phase 1
(4.5 months)

All Minor/Outlay Projects:


Applicable processes from
Phases 1 and 2
New processes, etc. with a
focus for streamlining

Develop and Implement Process for


Complex Minor Projects ($0.5M-2M):
Applicable processes from Phase 1
New processes, templates, agendas,
reviews required for Phase 2

Develop and Implement Stage Gate Process


for Major Projects ($2M and over) including:
Pre-work required for each gate
Templates
Agenda for stage gate meetings
Reviews required
Time line of stage gate rollout
Source: Team analysis

Pre-Decisional - Proprietary and Confidential | 54

STAGE GATE PROCESS

A University capital project funding thresholds vary widely but are


typically higher than CU Boulders
USD Millions

Delgated budget threshold


60

Initial
project
approvals
thresholds

Observations

40
2

10

CU Boulder has low approval


thresholds even after
accounting for expected
regional cost variations (e.g.
UC expected $/sqft costs are
1.6-1.8x CU expected costs, but
UC initial approval thresholds
are 10x CU thresholds)

Delegated approval systems


require up-front Board approval
of Long Range Development
Plans and thereafter allow
Campuses to act autonomously
up to a larger cap

Percentage of budget expansion


varies widely, with common aim
to keep projects moving in
uncertain circumstances

Smaller campuses networks


have smaller thresholds

15
5

10

20

Percent of initial cost


30%
25%
Change
approval
thresholds

# of
academic
campuses
Expected $/
sqft1

10%

10%

5%

185-305

185-305

NA

265-395

10

340-490

1 Hard construction costs $/GSF for University buildings in select US cities, Rider Levett Bucknall Quarterly Construction Report, 2nd Quarter 2015
Source: Press Search

Pre-Decisional - Proprietary and Confidential | 55

CU Boulder can adapt best practices in capital management across


the four themes to begin developing excellence
Emerging theme
Stage-Gate process:
how do projects
move through
A multiple fund and
scope approval
gates through the
lifecycle?

Stage-gate process matches the release of


required funds to the maturity level of project
definition; specifically, it ensures projects do not
progress without an adequate evaluation of the
underlying business case, completion of key
deliverables, and mitigation of critical risks

Clear guidelines on
contracting strategy
to best manage
owner risk

Selecting contracting strategy (delivery model,


contract terms, award process) based on project
specifications (size, cost, delivery schedule,
complexity), market conditions, and internal
capability

Tracking information
on cost, schedule
and milestones for
each project

Project controls dashboards enable PMs and


Project Coordinators to:
Proactively identify issues
Ensure relevant information is at hand to
contribute to the decision making process in a
timely manner

Standardized
processes with
capability building
training to ensure
consistent execution

Establishing standardized methods, training for


PM staff on consistent approaches, and support
from key decision makers which allow PM team
to increase success in delivery of projects

Source: Interviews, Expert interviews, Team analysis

VGI-AAA123-20090508-

Contracting strategy entails defining 3 linked elements


of a project
Key dimensions of contracting strategy

Key questions to be considered


Delivery model (How do I determine optimal contracting scope?)

Should I own the asset or are other ownership structures more


suitable, e.g., lease?

Which project value chain steps should be done internally and which
ones by contractor(s)?

Into how many contracts should the project scope be split?


What is the optimal split of scope between the contractors?

1 Delivery
model

Award process (How do I select my contractors?)

How can the effectiveness of existing award process be enhanced ?


How many and which suppliers/contractors should be invited?
How do we get the suppliers interested?
What is the criteria for evaluation various suppliers?

3 Contract
terms
2 Award
proces
s

Contract terms (How do I ensure most optimal contracting terms?)

What are the key project cost, performance, and schedule risks?
Who is the natural owner of the risks?
What mechanisms exist to transfer or share risk?
How can objectives be aligned between owner and contractor to
ensure an efficient execution through compensation elements such
as incentives, penalties, warranties, etc.?
McKinsey & Company | 3

SJO-AAA123-20110525-

4 Planning and scheduling process

Create/ update
plan

Process step

Users

Progress
measurement

Provide timely,
accurate inputs
Help in identifying
critical milestones

Create WBS
Identify critical
milestones
Create/ update
plan
Publish plan

Customized
analysis

Provide timely,
accurate inputs
Execute recommended focus
actions

Monitor & report


project progress
Recommend
focus actions/
area
Publish report

Identify required
analyses
Provide timely,
accurate inputs

Roles

Printed

Single and
comprehensive
capital investment
framework

W orking Draft - Last Modified 07-Sep-11 6:35:55 PM

Project Managers:
how well is project
D management best
practice followed?

Printed 4/6/2011 4:32:15 PM

Transparency: how
do project controls
C allow for right
information at the
right time?

Description

W orking Draft - Last Modified 9/7/2011 3:32:09 AM

Contracting: how
project delivery and
B contracting methods
are selected

Best practice

Planning
team

Recommend &
perform required
analyses
Publish analysis
report

McKinsey & Company | 5

Pre-Decisional - Proprietary and Confidential | 56

CONTRACTING PROCESS

Steps

B Existing process shows opportunity for an integrated


contracting strategy to mitigate and share project risks

Observations

Current tools

Limited range of delivery models


for large capital projects available
to CU Boulder per State
requirements
Inconsistency in application of
delivery models across capital
projects
Lack of institutional experience
in alternative delivery models
(Public Private Partnerships,
Integrated Project Delivery) as not
commonly used for mega projects
Go to strategy is design build or
CM at risk delivery model with a
GMP

State procurement guidance


documents
PD&C staff experience (CU and
previous experience)
PD&C internal discussion to
determine appropriate contact
type

Source: Expert interviews, Team analysis

Determine contract terms


and sign

Select contractor(s)

Select a delivery model

Complex award process due to


state rules and regulations
Competitive bids required
contracts over $20k
Contractor interest is based on
guaranteed payments and
prestigious projects, however
perception of CU Boulder as
challenging client due to
regulation burden

State procurement guidance


PD&C staff experience (CU and
past work experience)
PD&C internal discussion to
determine appropriate contact
type

Cost, performance, schedule, and


disruption to campus operation
are strongly considered, but
unclear how terms are
incorporated into contract terms
CU Boulder is often the natural
owner of risk, with contractors
able to leverage schedule and
change orders to their advantage
State limits the ability to include
incentives in contracts
CU Boulder often not in a
position to enforce contracts
(liquidated damages) due to lack
of authority, tracking, and quality
assurance/quality control
State contracts

Pre-Decisional - Proprietary and Confidential | 57

CONTRACTING PROCESS

B Optimal contracting strategy decisions should aim to maximize


project success within known constraints
Optimal contracting
strategy should aim to
maximize project success

Schedule

Project
Success

while being constrained by three major elements

Project
risks

Cost
Internal
capabilities
Quality/
operation
efficiency
Market
capabilities

Source: Team analysis

How does this project fit into CU Boulders capital


strategy and what are they trying to achieve with it?

How complex is the project? How much experience


does CU Boulder have with this type of project? What
are the associated risks?

What are the risks associated with each step of the


project? Who can manage them best?

What elements of the project can CU Boulder manage


themselves? (skills and availability of resources)?

What can be done better by other parties?

What systems and processes does CU Boulder have


in place to support the contracting strategy?
What are the capabilities of available contractors?
Where can CU Boulder leverage them?
Is the level of competition sufficient to ensure
appropriate negotiation power?

Pre-Decisional - Proprietary and Confidential | 58

CONTRACTING PROCESS

Steps

B Proposed contracting process establishes a consistent risk


based approach to enhance project outcomes

Goals

Who to
involve

Actions

Determine Contract Terms and


Sign

Select a Contractor

Select a Delivery Model

Establish a Contracting Strategy


Playbook for optimizing cost/
schedule/quality aligned with
State regulations and CU Boulder
past experience
Understand how alternative
models (bundling, PPP, IPC)
could be utilized to better spread
risks
Understand CU Boulder desired
role (skill building)

Develop Contracting Strategy


Playbook working group to
explore best delivery options of
CU Boulder projects

PD&C
Legal
Procurement
Vice Chancellor, Administration
Contractor Rep
Design Team Rep

Integrate Contractor selection


process into Contracting
Strategy Playbook to best utilize
process to meet cost, schedule
or quality based outcomes

Transfer project risks to align

objectives between owner


and contractors, not to
outsource them
Ensure the terms of the
performance contract are
pragmatic, clear, and
measurable

Integrate contractor selection


methods into Contracting
Strategy Playbook
Formalize Contractor Score
Card

Develop standard language


added to State contracts to
provide a fair and equitable
balance of risk on large Capital
Projects

PD&C
Legal
Procurement
Vice Chancellor, Administration
Contractor Rep
Design Team Rep

PD&C
Legal
Procurement
Vice Chancellor, Administration

Pre-Decisional - Proprietary and Confidential | 59

CONTRACTING PROCESS

B An internal contracting working group of stakeholders can


develop a Contracting Strategy Playbook
Contracting Strategy Playbook: suggested table of contents
Contracting strategy
playbook creation process

Suggested working
group:
PD&C (3)
Planning
Representative
Project Manager
Engineering
Legal (1)
Procurement Team (1)
Potential Participants (at
key intervals):
Contractor
Representatives
Architect
Representatives
Activities:
Conduct a series of
workshops to address
each section of the
contracting playbook
Review playbook with key
stakeholders to validate
approach

Delivery method
Preferred delivery methods for:
Base Projects
Complex Projects
Delivery methods to maximize:
Cost
Schedule
Quality
Key considerations for delivery methods and
project types:
Operator experience required
Pool of experienced contractors available
Ability of contractor to integrate with others
Ramp-up/Turnover consistency
Single execution voice
Project controls
Contracting risk exposure
Project Managers Roles for each Delivery
Method

Project Managers Role for each


Contractor Selection Method
Contractor Score Card
Contracting terms
Selecting contract terms to maximize:
Cost
Schedule
Quality
Project Managers Role for each
contract type
Appendix
Standard Delivery Models
CU Boulder Contract forms

Contractor selection
Appropriate contractor selection process for:
Base Projects
Complex Projects
Selection process considerations per Delivery
Method
Pre-Decisional - Proprietary and Confidential | 60

CONTRACTING PROCESS

B Contracting strategy playbook example: selecting preferred


contract given decision making posture
ILLUSTRATIVE
Preferred contract form

Type of Project

Nice to have

Must have

Implication to owner

Base

Design-BidBuild (DBB)

Base
Complex

Design-Build
(DB)

Complex

Complex

Construction
Management /
General
Contractor (CM/ Hybrid DB and
CM/GC
GC)

Lowest quality with significant


potential delays and cost overruns

Complex

Provides highest quality project with


minimum or no delay, under budget

Public Private
Partnerships
(PPP)

Rationale

1 Operator
experience

Larger number of contractors has a higher


probability of engaging an experienced
contractor on the project to achieve quality

2 Pool of
experienced people

Larger pool of companies to pull resources


from reduces risk of schedule slippage

3 Ability to integrate
with others

Smaller number of interfaces reduces the


risk of team misalignment affecting schedule
and quality

4 Ramp-up/turnover
consistency

Higher risk of schedule slippage when


multiple contractors are responsible for
commissioning and ramp up

5 Single execution
voice

Lower risk of schedule slippage with a single


company approach to solicitation strategy

6 Project controls

Fewer companies to align on tools reduces


the risk of delays and budget overruns due
to documentation and budget management

Contracting risk
exposure

Late contractor
involvement
could lead to redesigns

Overall score

Most compatible Moderately


with owner
compatible with
strategy
owner strategy

Source: Team analysis

Contractor
driven cost
savings
undermines
quality

Late involvement
from subs leads
to cost and
schedule
overruns

If terms are not


well defined
could lead to
cost, schedule,
quality issues

Lack of CU
Boulder
experience could
lead to cost,
schedule, and
quality issues.

Less compatible Moderately


with higher owner compatible with
risk
owner strategy

Least compatible
with owner
strategy

Pre-Decisional - Proprietary and Confidential | 61

CU Boulder can adapt best practices in capital management across


the four themes to begin developing excellence
Emerging theme
Stage-Gate process:
how do projects
move through
A multiple fund and
scope approval
gates through the
lifecycle?

Stage-gate process matches the release of


required funds to the maturity level of project
definition; specifically, it ensures projects do not
progress without an adequate evaluation of the
underlying business case, completion of key
deliverables, and mitigation of critical risks

Clear guidelines on
contracting strategy
to best manage
owner risk

Selecting contracting strategy (delivery model,


contract terms, award process) based on project
specifications (size, cost, delivery schedule,
complexity), market conditions, and internal
capability

Tracking information
on cost, schedule
and milestones for
each project

Project controls dashboards enable PMs and


Project Coordinators to:
Proactively identify issues
Ensure relevant information is at hand to
contribute to the decision making process in a
timely manner

Standardized
processes with
capability building
training to ensure
consistent execution

Establishing standardized methods, training for


PM staff on consistent approaches, and support
from key decision makers which allow PM team
to increase success in delivery of projects

Source: Interviews, Expert interviews, Team analysis

VGI-AAA123-20090508-

Contracting strategy entails defining 3 linked elements


of a project
Key dimensions of contracting strategy

Key questions to be considered


Delivery model (How do I determine optimal contracting scope?)

Should I own the asset or are other ownership structures more


suitable, e.g., lease?

Which project value chain steps should be done internally and which
ones by contractor(s)?

Into how many contracts should the project scope be split?


What is the optimal split of scope between the contractors?

1 Delivery
model

Award process (How do I select my contractors?)

How can the effectiveness of existing award process be enhanced ?


How many and which suppliers/contractors should be invited?
How do we get the suppliers interested?
What is the criteria for evaluation various suppliers?

3 Contract
terms
2 Award
proces
s

Contract terms (How do I ensure most optimal contracting terms?)

What are the key project cost, performance, and schedule risks?
Who is the natural owner of the risks?
What mechanisms exist to transfer or share risk?
How can objectives be aligned between owner and contractor to
ensure an efficient execution through compensation elements such
as incentives, penalties, warranties, etc.?
McKinsey & Company | 3

SJO-AAA123-20110525-

4 Planning and scheduling process

Create/ update
plan

Process step

Users

Progress
measurement

Provide timely,
accurate inputs
Help in identifying
critical milestones

Create WBS
Identify critical
milestones
Create/ update
plan
Publish plan

Customized
analysis

Provide timely,
accurate inputs
Execute recommended focus
actions

Monitor & report


project progress
Recommend
focus actions/
area
Publish report

Identify required
analyses
Provide timely,
accurate inputs

Roles

Printed

Single and
comprehensive
capital investment
framework

W orking Draft - Last Modified 07-Sep-11 6:35:55 PM

Project Managers:
how well is project
D management best
practice followed?

Printed 4/6/2011 4:32:15 PM

Transparency: how
do project controls
C allow for right
information at the
right time?

Description

W orking Draft - Last Modified 9/7/2011 3:32:09 AM

Contracting: how
project delivery and
B contracting methods
are selected

Best practice

Planning
team

Recommend &
perform required
analyses
Publish analysis
report

McKinsey & Company | 5

Pre-Decisional - Proprietary and Confidential | 62

TRANSPARENCY

C CU Boulder requires a systematic approach to building


transparency among stakeholders in project delivery
Description

Define key
data and clear
C1 KPIs for
project
delivery

Create an
C2 accessible KPI
dashboard

Provide a
forum for
C3
decision
making

CU Boulder should define Key Performance Indicators (KPIs) at a


project level based on project categories defined (i.e. Major, Minor, and
Outlays) with clear targets across each
An individual should also be identified as a responsible party for
reporting and meeting the KPI target (may be different individuals)
Clear direction and training should be provided on how to calculate and
report the KPI
KPI dashboard should be accessible at multiple levels (e.g. project
level and portfolio level) to the relevant stakeholders
The accessible dashboard can be communicated widely to build
transparency among all stakeholders (e.g. users, administration,
PD&C) and increase project accountability
KPI dashboards can be used as a tool in a regular forum of
stakeholders (e.g. a Project Review Board) to discuss project progress
Project Review Boards will also help resolve issues proactively as it
will:
Enable decision makers to have the right information
Allow PMs to raise concerns at right time

KPI dashboard is designed at both project and portfolio level


Source: Team analysis

Pre-Decisional - Proprietary and Confidential | 63

TRANSPARENCY

C1 Defining relevant data and KPIs will help prioritize efforts


in developing a practical dashboard for project delivery

Cost

Major

Schedule

Scope

Quality

Health

Safety

KPI / data

Unit

Where does it live?

Legend:
Who
reports?

EAC at initial approval

$M USD

Board Meetings docs?

Current approval amount

$M USD

Current EAC

Data

KPI

PRELIMINARY

How to report?

Target

Planner

Shared excel?

N/A

Board Meetings docs?

Planner?

Shared excel?

N/A

$M USD

Latest GC update

PM

Shared excel?

N/A

Cost variance (Current EAC/


EAC at initial approval)

Calculated

PM

Shared excel?

<5%

ECD at initial approval

Date

Board Meetings docs?

Planner

Shared excel?

N/A

ECD at contract signing

Date

Contract documents

PM

Shared excel?

N/A

Current ECD

Date

Latest GC update

PM

Shared excel?

N/A

Schedule variance (current


ECD initial ECD)

weeks

Calculated

PM

Shared excel?

<4 weeks

Size at initial approval (new,


renovation split)

Sqft

Board Meetings docs?

Planner

Shared excel?

N/A

Current size (new vs ren)

Sqft

Latest A/E update

PM

Shared excel?

N/A

# of change orders (cumul, new)

N/A

Changes log?

PM

Shared excel?

N/A

# of total RFIs to date:

RFI log

PM

Shared excel?

# of re-inspections:

Inspection log

Permitting?

Shared excel?

As-Built dwg progress

CAD team update?

CAD?

Shared excel?

100%

Team morale
Stakeholder engagement

L,M,H
Days

Survey responses
Meeting minutes

PM
PM

Shared excel?
Shared excel?

High
5

Total # of reportable injuries:

Latest GC update?

PM

Shared excel?

# Lost man-hours due to


injuries:

PM

100%

Note: see definitions for all metrics above


Source: Expert interviews, Team analysis

Pre-Decisional - Proprietary and Confidential | 64

TRANSPARENCY

C2 Simplified dashboards can be used to effectively manage


communication and proactively identify issues (1/2)
Project Review Board: meeting on mm.dd.yyyy
Project name:

Project Manager:

Project description: 1-2 sentences

Comments since last update

Data or KPIs

Past changes in cost with identified drivers


Expected changes in cost (forward looking)

EAC at initial approval: $##


Current approval amount:
EAC at completion:
Cost variance:

Progress on last milestone:


Next milestone:

Key changes since initial approval:


Key changes in scope since last update:

Identify issues faced by / progress made by the inhouse inspection staff

# of total RFIs to date:


# of re-inspections:
As-Built progress:

Safety

Any initiatives or targets by contractor

# of reportable injuries to date:


Lost man-hours due to injuries:

Health

Team wellbeing:
Stakeholder engagement

Survey score:
Number of days beyond regular cadence:

Help needed from leadership: specify actionable help from leadership (PD&C, Administration, or other)
here

Project view: Major

Cost

Schedule

Scope

Quality

Overall

Rating

ECD at initial approval:


ECD at construction contract signing:
Current ECD:
Schedule variance: (-ve if delayed)
Size at initial approval (new, ren.):
Current size (new, ren.):
# of change orders (cumulative, since last update):

Note: see definitions for all metrics above


Source: Expert interviews, Team analysis

Pre-Decisional - Proprietary and Confidential | 65

TRANSPARENCY

C2 Simplified dashboards can be used to effectively manage


communication and proactively identify issues (2/2)

To discuss

Portfolio view

Major

Project Review Board: meeting on mm.dd.yyyy


Stage

Current EAC
In $M USD

Cost (-/+)
In percent

ECD
mm/yy

Schd.(+/-) Overall
In weeks Rating

Project name
Project 1

PM name
PM 1

CON

Projects with cost overrun


<10%

No delay

>20%

0-1 month

>1 month

Minor

10-20%

Projects with schedule overrun

##

##

##

##

##

##

##

Outlays

Portfolio size
In $M USD, # of projects

##

##

##

##

##

##

##

Note: see definitions for all metrics above


Source: Expert interviews, Team analysis

Pre-Decisional - Proprietary and Confidential | 66

TRANSPARENCY

C2

Sample team barometer questionnaire can provide useful insights


to morale and barriers to progress

Introduction page:
Thank you for your participation in this online survey.
The team barometer is a feedback tool used to
monitor team satisfaction. We will discuss the results
every other week as a group, to celebrate successes
and align on actions needed to improve the team's
experience and/or performance.
Time required to complete: 5-10 minutes
Deadline: The survey will open every other Thursday
and will close the following Monday.

Likely scale response options:


Strongly agree
Agree
Somewhat agree
Somewhat disagree
Disagree
Strongly disagree
N/A
If the respondent disagrees with any statement, a
dynamic comment box appears to allow
respondent to enter (optional) additional detail.

Source: Team analysis

Body of survey:
1. I am clear about the objectives and end products of the team.
2. I am excited to be working on the team.
3. I am building new skills on this project.
4. The team has an atmosphere of trust and openness.
5. The team works collaboratively. Together we arrive at better solutions.
6. The team communicates well with one another.
7. Team meetings are engaging.
8. This week, the team created relevant, high-quality content that moves
us toward our objectives.
9. Our work is moving us toward our objectives at an appropriate pace.
10. I am able to maintain a good balance between our work and my
private life on this project.
11. I clearly understand my role on the team.
12. I clearly understand the roles of my fellow team members.
13. I am confident our efforts will ultimately result in significant
improvements to our project and to the business.
What is the team doing well?

What could the team do better in order to have more impact?

Pre-Decisional - Proprietary and Confidential | 67

TRANSPARENCY

C3 A systematic Project Review Board would help address the


communication gaps and leverage KPI dashboards
Potential audience and cadence

Key questions to consider

Lead: Director of PD&C


Chair: CFO
Participants:
CFO
Vice Chancellor of Facilities Management
Director of PD&C
Optional: dial-in/listen in for PMs and

Which stakeholders should be invited

Owners representatives
Distribution: to all PD&C, owners rep, and users
Cadence: minimum monthly

Triggers for discussing a project

At the following defined triggers:


When overall rating is red
At each stage gate
At signing of contract amendments
Requested by leadership
Requested by PD&C Project Manager
Source: Team analysis

to attend the Project Review Board


(from PD&C, Administration, User)?
Who should lead and chair the
Project Review Board meeting?
Who should own the final decision in
the Project Review Board?
Should PMs be invited to listen-in to
the meeting?
What frequency is ideal for Project
Review Board?
Should the KPI dashboards be
distributed to a wider audience? If so,
who?
Who should consolidate and prepare
the dashboard for Project Review
Board discussions?

Pre-Decisional - Proprietary and Confidential | 68

TRANSPARENCY

C3 Key Definitions for the KPI dashboard

Key definitions

EAC (Estimate At Completion): total value of the project (including


contingencies)

ECD (Estimated Completion Date): estimated substantial completion date


Cost variance: current EAC / EAC at initial Board Approval
Schedule variance: (current ECD ECD at initial Board Approval)
Stage: stages defined to be consistent with stage gate process (e.g.
construction, or business case justification)

Overall rating definitions:


Red: high risk to project success with immediate attention from leadership
Yellow: medium risk to project success where mitigation is managed
within PD&C for now
Green: low to no risk to project success

Source: Team analysis

Pre-Decisional - Proprietary and Confidential | 69

CU Boulder can adapt best practices in capital management across


the four themes to begin developing excellence
Emerging theme
Stage-Gate process:
how do projects
move through
A multiple fund and
scope approval
gates through the
lifecycle?

Stage-gate process matches the release of


required funds to the maturity level of project
definition; specifically, it ensures projects do not
progress without an adequate evaluation of the
underlying business case, completion of key
deliverables, and mitigation of critical risks

Clear guidelines on
contracting strategy
to best manage
owner risk

Selecting contracting strategy (delivery model,


contract terms, award process) based on project
specifications (size, cost, delivery schedule,
complexity), market conditions, and internal
capability

Tracking information
on cost, schedule
and milestones for
each project

Project controls dashboards enable PMs and


Project Coordinators to:
Proactively identify issues
Ensure relevant information is at hand to
contribute to the decision making process in a
timely manner

Standardized
processes with
capability building
training to ensure
consistent execution

Establishing standardized methods, training for


PM staff on consistent approaches, and support
from key decision makers which allow PM team
to increase success in delivery of projects

Source: Interviews, Expert interviews, Team analysis

VGI-AAA123-20090508-

Contracting strategy entails defining 3 linked elements


of a project
Key dimensions of contracting strategy

Key questions to be considered


Delivery model (How do I determine optimal contracting scope?)

Should I own the asset or are other ownership structures more


suitable, e.g., lease?

Which project value chain steps should be done internally and which
ones by contractor(s)?

Into how many contracts should the project scope be split?


What is the optimal split of scope between the contractors?

1 Delivery
model

Award process (How do I select my contractors?)

How can the effectiveness of existing award process be enhanced ?


How many and which suppliers/contractors should be invited?
How do we get the suppliers interested?
What is the criteria for evaluation various suppliers?

3 Contract
terms
2 Award
proces
s

Contract terms (How do I ensure most optimal contracting terms?)

What are the key project cost, performance, and schedule risks?
Who is the natural owner of the risks?
What mechanisms exist to transfer or share risk?
How can objectives be aligned between owner and contractor to
ensure an efficient execution through compensation elements such
as incentives, penalties, warranties, etc.?
McKinsey & Company | 3

SJO-AAA123-20110525-

4 Planning and scheduling process

Create/ update
plan

Process step

Users

Progress
measurement

Provide timely,
accurate inputs
Help in identifying
critical milestones

Create WBS
Identify critical
milestones
Create/ update
plan
Publish plan

Customized
analysis

Provide timely,
accurate inputs
Execute recommended focus
actions

Monitor & report


project progress
Recommend
focus actions/
area
Publish report

Identify required
analyses
Provide timely,
accurate inputs

Roles

Printed

Single and
comprehensive
capital investment
framework

W orking Draft - Last Modified 07-Sep-11 6:35:55 PM

Project Managers:
how well is project
D management best
practice followed?

Printed 4/6/2011 4:32:15 PM

Transparency: how
do project controls
C allow for right
information at the
right time?

Description

W orking Draft - Last Modified 9/7/2011 3:32:09 AM

Contracting: how
project delivery and
B contracting methods
are selected

Best practice

Planning
team

Recommend &
perform required
analyses
Publish analysis
report

McKinsey & Company | 5

Pre-Decisional - Proprietary and Confidential | 70

PROJECT MANAGER PERFORMANCE

D Project Manager capability building design focused on three


crucial questions which influenced skill selection & delivery
design

1 What are important skills to be a successful PM and


which should we focus on?
2 What format should we use to train PMs on those
important skills?
3 What do we need to do to make the benefit of those
important skills sustainable?

Source: Team analysis

Pre-Decisional - Proprietary and Confidential | 71

PROJECT MANAGER PERFORMANCE

D Project manager performance is the single most influential


driver of construction project profitability
Highest priority
Skills

Project performance is not


correlated with:
Geography
Asset class
Complexity
Customer
Project manager age or tenure
(grey hair)

Source: Interviews, Team analysis

II

III

IV

Mgmt
capabilities
Financial
astuteness

We have found that project


performance is highly correlated
with project manager capabilities

Commercial
orientation

Org
capabilities

We have run an analysis of 10,000


projects, checking the correlation of
project performance with different
factors

High performing PMs excel at these skills

Train
Sustain

1.
1

Optimizing schedule, scope, and cost


dimensions

2
1.

Planning & tracking project performance

3
1.

Managing internal and external teams

4
1.

Understanding financial statements

5
1.

Mitigating project risk

6
1.

Maintaining project lifecycle view

1.
7

Overseeing contractors effectively

8
1.

Mastering contract details

1.
9

Leveraging organization resources

1.
10 Managing client needs (e.g.
change orders)

Pre-Decisional - Proprietary and Confidential | 72

PROJECT MANAGER PERFORMANCE

D Clear understanding of exceptional performance is required


before PM training can begin
PM capability

Planning & tracking


project performance

Managing internal &


external teams

Mitigating project
risk

Overseeing
7 contractors
effectively

10

Managing client
needs

Skills

Definition of exceptional performance behavior

Train

Monitoring project progress, ensuring stage gate milestones are achieved in an


acceptable timeframe and at an appropriate quality level
Raising timeline and budget obstacles to project timelines well in advance of
occurrence

Sustain

Communicating project updates and important milestones in a regular and


timely manner
Engaging with partnering organizations to improve project delivery methodology
for joint activities
Leveraging owners representative more to navigate clients context
Identifying and assessing risk factors at project start and reviewing risk
evolution regularly
Creating mitigation plans to successfully resolve project challenges and including
appropriate internal and external personnel
Establishing clear performance metrics and communication standards
Maintaining independent budget tracking documents to provide adequate
project control
Ensuring project delivery and quality is aligned with contract terms
Ensuring client understanding of PD&Cs processes and providing sufficient
clarity on project lifecycle
Managing clients input and needs into project delivery while ensuring budgetary
tradeoffs
Providing regular progress updates focusing on budget and project milestones
To be matched against needs of CU Boulder PMs
Examples are general best practice

Source: Team analysis, Expert interviews

Pre-Decisional - Proprietary and Confidential | 73

PROJECT MANAGER PERFORMANCE

ILLUSTRATIVE

NON-EXHAUSTIVE
D Overview of potential capability modules topics and
support tools which may be considered to improve skills
Skills

Planning

Workshoip module topics

Planning & tracking


project performance

Planning through uncertainty


an approach to planning
under various uncertainties

Understanding market
trends to strengthen plan
scenario assumptions

Capturing lessons from


performing post-mortem
plan analysis

Identifying project support


needs and staffing project for
excellence

Developing legally savvy


contracts a primer to
engaging legal resources

Bringing the best of CU


Boulder to a project
navigating CU Boulders
resources

Identifying potential risk


areas in your upcoming
project

Shifting risks and owning


risks: risk management
approach to contracting

Seeing the smoke signs


developing mitigation
plans and stopping risks
before they start

Developing a view of
contractors performance
before the RFP is released

Setting the tone starting


projects on the right foot
with contractors

Ensuring quality with


commissioning,
developing plans to
minimize after-build costs

Educating clients/ users to


construction and PD&Cs
approach to building

Partnering with client to


ensure client-specific
needs are met while
constructing excellence

Creating clarity to project


progress
Managing client needs
throughout project lifecycle

Project cost modeling


spreadsheets
Stage gate forms

Contracting playbook

Project pipeline
management
Stage gate approval process

Mitigating project
risk

Managing client
needs

Support tools

Tools

Processes

Source: Team Analysis

Train
Sustain

Managing internal &


external teams

Overseeing
contractors
effectively

Design & construction

Contracting

Contracting process to
align with playbook

Project KPI dashboard

Project review board

Tools &
processes
required
not
exhaustive

Pre-Decisional - Proprietary and Confidential | 74

PROJECT MANAGER PERFORMANCE

D Training models for skill-building span across three levels of


involvement
Skills
Train
Sustain

SEE

DO

Providing information

Role-modeling work

in classroom settings
covering specific
skills and leveraging
knowledge experts
and practitioners to
spread best-practices

alongside employee
in an effort to create
experiential learning
to develop and
spread skills among
workforce

Source: Team analysis

TEACH

Developing PMs into


skill and content
masters, then
enlisting their support
in teaching fellow
PMs how to develop
and apply new skills

Pre-Decisional - Proprietary and Confidential | 75

PROJECT MANAGER PERFORMANCE

D Sustainable capability building and maintenance requires a


clear process supported with updated policies
Skills
Train
Sustain

Train new
Project
Managers

Train select
Project
Managers
Review
display
of mastery
and
provide
next
level
training

Ensure
standard
baseline
understanding
of department
approach to
building and
individual
capabilities
are achieved

Offer existing Project Managers


should have access to two
types of training:
Initial: first time introduction
to capability or process
Maintenance: refresher or
rebuilding existing
knowledge

Source: Team Analysis

Provide
Project
Managers
opportunities to
display
abilities
through
project
execution

Sustain policy
and procedures
change

Determine next step of Project Managers


training journey either furthering a new
capability or practicing an existing capability

Train
Field and
Forum
approach

Sustained
capability building
will require
policy and
procedures to
support the
ongoing training
needs of both
new and existing
PMs

Provide sufficient
opportunity for
Project Manager to
demonstrate
mastery of capability
or understanding of
department policy

Pre-Decisional - Proprietary and Confidential | 76

PROJECT MANAGER PERFORMANCE

D A field and forum format ensures appropriate balance between


ILLUSTRATIVE
effort, effectiveness, and reach
Forum
Classroom
setting where
skills are
taught by
experienced
PMs and
standard
setters

Preparation
for forums
Select
participants
Plan
curriculum and
field work

Set expectations
through program
overview
Deliver first series of
workshops
combining activities
and pure lecture
modules
Outline field work
assignments

#1 (1 day)

Celebrate stories of
success from field
work
Establish forum for
PMs to discuss what
worked and what
was challenging
Deliver next set of
lectures and field
work

#2 (1 day)

Train

Repeat defined forum format

Sustain

Session sequence
Forum 1 Overseeing contractors
effectively and Mitigating project risk
Forum 2 Planning & tracking project
performance
Forum 3 Managing client needs
Forum 4 Managing internal & external
teams
#4 (1 day)

2016

Q4

Q1

Q2

Field work
(~12 weeks)

Fill out KPIs and use


to have discussions
with management,
clients, and contracts
on the progress and
performance of
projects

Partnering with training provider


can help reduce timeframe
required for field work

Source: Team analysis

#3 (1 day)

2015

Field
Practice
application of
lessons and
coaching
sessions to
help PMs
operate with
excellence

Skills

Q3

Field work
(~12 weeks)

Provide workshops
for clients on
PD&Cs processes
Perform project
kick-off with client
Use transparency
tools throughout
project

Q4

Field work
(~12 weeks)

Leverage contracting
playbook during
contracting
Create risk
assessments before
project on critical
areas and develop
mitigation plans

Field work
(~12 weeks)

Coach new PMs in


process
Engage with
internal/ external
teams to develop
improved working
processes

Pre-Decisional - Proprietary and Confidential | 77

PROJECT MANAGER PERFORMANCE

D Retaining strong PMs can be supported through empowerment,


training, and fostering a culture of sharing best practices
PRELIMINARY

Empower the PMs


to provide
authentic
authority to match
responsibility

Provide support
to PMs through
before, during,
and after project
duration

Create a culture
of exchange
where best ideas
are raised up

Source: Interviews, Team analysis

Communicating clearly PMs role to stakeholders with


reinforcement from top levels of CU Boulder

Creating the machine that perpetuates the holistic


apprenticeship program, ensures curriculums are up-to-date
and provides certification to qualified project managers

Developing tools that are simple, relevant, practical and usable

Skills
Train
Sustain

Designing and implementing rigorous performance


measurement on projects

Supporting PMs in all stages of project


Before e.g. training, estimating, planning, and agreeing
scope
During e.g. cost tracking, client management, change order
management
After e.g. project closeout focused on quality assurance

Fostering culture of exchanging ideas between PMs and


institutionalizing best ideas across all teams to reduce
variability experienced by clients and to increase ownership
and adherence to process by PMs

Pre-Decisional - Proprietary and Confidential | 78

PROJECT MANAGER PERFORMANCE

D Alternatively, CU Boulder can consider partnering with external


professional PM firms for high-value, complex projects
Category

Cost

Benefits

Considerations

Team size flexibility based on upcoming

Direct costs of project management on per

pipeline of projects
Low performing external PM firms more
easily replaced with less impact to
organization

Project deliverable likely quality higher

Project
delivery

due to fewer constraints and higher


specialization
Focus less spread across multiple
domains (e.g. capital, non-capital,
maintenance)

Control of project is external which may


increase decision and reaction time

State administrative requirements

Institutional
knowledge

Risk

project increases
Overhead cost to oversee program
increases

remain, no benefit provided from external


PM firms
Priorities mismatch may occur with
external firms
Learning curve to operate within CU
organization may result in inefficiencies,
especially in non-repeatable projects

Processes and policies used in external

Building-specific knowledge and expertise

Execution risk of project management

Misalignment of incentives if partnering

contracting organizations can be


incorporated into CU

can be reduced by shifting performancerelated activities externally


Quality assurance of extern firms provides
an independent review of work
performed

Source: Team analysis, Expert interviews

from performing project management will


dissipate over time

firm seeks to maximize one-time profit from


project
Reduced oversight into actions and
behaviors of external firms employees and
partners
Firm-specific risk may arise if external firm
goes through bankruptcy, strategic sale, key
individuals leave, or other business
continuity risks

Important
considerations

Initial project
selection important
for signaling
considerations to
PD&C staff
Ideal project
would be highly
complex and
atypical of
PD&Cs
projects

Benefits will be
actualized by PD&C
staff, not
administration so
complete buy-in at
all levels of CU
organization
required

High degree of
clarity required for
what activities
external PM should
perform compared
to internal activities

Pre-Decisional - Proprietary and Confidential | 79

PM
Tools

Transparency

Contracting

Stage gate

CU Boulder has started initiatives that address aspects of the four


recommendation focus areas
Initiative

Description

Involving PM earlier in the


process

Involving PM earlier at project conceptualization instead of


Design Development phase

Leverage technology for


permitting and inspections

Implementing electronic permitting technology to ensure


tracking of permitting and inspection

Engaging contractors with


performance specifications

Investigating use of performance-based specifications to


transfer risk to contractor and design team

Simplifying campus design


formats

Redeveloping campus design standards to more concise


format

Detailing project plans through


Project Charter

Providing an executive summary of Program Plan covering


agreed budget, schedule, and scope, signed by PD&C and
Administration

Creating Key Performance


Indicators dashboard

Developing preliminary set of project KPIs dashboards with


Office of Performance Improvement

Investing in software tools and


solutions

Undergoing an evaluation of software options to be used


across Facilities Management (e.g. developing database for
smaller projects to provide better cost estimates)

Source: CU Boulder Master Plan and Interviews

Pre-Decisional - Proprietary and Confidential | 80

Contents

Organization context
Athletics project review
Overall diagnostic
Recommendations
Value at stake
Implementation plan

Pre-Decisional - Proprietary and Confidential | 81

Though current recommendations focus on streamlining project


delivery, CU Boulder can engage in a broader set of available
strategies for capital excellence to address its spend
900-1,100

Suggested efforts

Full set of available strategies4


CU has the opportunity to engage in the
full set of capital excellence strategies to
address its upcoming project portfolio:

Future Capital
Projects
(2015-2020)1

550-650

Current capital
projects unspent
budget1

250

Minor3
Capital Outlay3

170

PRELIMINARY

Improving project section / optimizing


portfolio: use precise selection criteria
that ensure proposed projects meet
specific goals; develop sophisticated
evaluation methods to determine costs and
benefits; and prioritize projects at a system
level, using transparent, fact-based
decision making
Streamlining project delivery: improve
cost and schedule performance of projects
via targeted efforts including investing
heavily in early stages of projects;
improving project controls; and
harmonizing processes across multiple
agencies
Making the most of existing facilities:
leverage current capacity by boosting
asset utilization, optimizing maintenance
planning, and expanding the use of
demand-management measures

Applying suggested capital


management best practice within
streamlining project delivery
will already begin developing
excellence at CU Boulder:

Stage-Gate process: move


through multiple fund and scope
approval gates across lifecycle
allocating full funding when with
a higher degree of cost certainty
Contracting: select the project
delivery method and contract
terms to match the project goals
and share risks
Transparency: add project
controls and tracking to provide
right information at the right
time
Project Managers: spread
project management best
practice to create consistent
approach

Current portfolio
1 Future capital projects includes CAMP (2014) and all projects not completed on the 20 year Proposed Capital Projects List (2011); Current capital projects unspent budget includes projects
in planning, deisgn, pre-construction, and construction phase with unspent budget | 2 17% average project budget overrun per Major project performance based on PD&C FAMIS system
data | 3 Minor and Capital Outlay numbers are sum totals from 2010-2015 taken from the PD&C FAMIS system and assumed to be consistent for 2015-2020
4 Infrastructure productivity: How to save $1 trillion a year, McKinsey Global Institute, Jan13

Source: PD&C, Team analysis

Pre-Decisional - Proprietary and Confidential | 82

Applying capital productivity levers can increase CU Boulders


effectiveness and improve its organizational health in the project
delivery functions
Applying capital productivity levers can achieve
substantial efficiency in capital deployment.

in addition to multiple other benefits to


University of Colorado, Boulder

Grow a transparent and trust-based relationship


across all stakeholders (Board of Regents,
Administration, Planning, Design & Construction,
and Users) involved in project delivery

Increase morale, accountability, and ownership


of projects in project delivery functions

Better able to attract and retain top talent in the


project delivery functions at CU Boulder

Better able to manage the pipeline of upcoming


projects from an internal resource perspective

Attract best contractors to engage in project


delivery of complex and base projects

Better able to anticipate and resolve project


performance related issues

Maintain and enhance the beauty of the unique


campus architecture in a cost effective manner

Estimated savings of 15% of the overall capital


spend based on select levers of streamlining
project delivery:
Stage-Gate process: move through multiple
fund and scope approval gates across lifecycle
allocating full funding when with a higher degree
of cost certainty
Contracting: select the project delivery method
and contract terms to match the project goals
and share risks
Transparency: add project controls and
tracking to provide right information at the right
time
Project Managers: spread project
management best practice to create consistent
approach
Estimated savings of 30% based on all capital
levers across project prioritization, streamlining
delivery, and making the most of existing facilities

Source: Team analysis

Pre-Decisional - Proprietary and Confidential | 83

Contents

Organization context
Athletics project review
Overall diagnostic
Recommendations
Value at stake
Implementation plan

Pre-Decisional - Proprietary and Confidential | 84

For each of the recommendations, there is a phased approach that


leads to excellence
Phase 4: Future
considerations

Map of phased overall implementation plan

Phase 3: Sustaining
excellence

Phase 2: Building
excellence

Phase 1: Quick wins


and critical actions

Set the foundation


for future success
and create
momentum through
quick wins

Source: Team analysis

Build foundational
processes and
capabilities
Pilot new
processes and
adjust based on
results before
scaling to all
projects

Scale new
processes to all
applicable project
types and project
delivery functions
Distribute and onboard personnel
on required
documentation
and tools to help
follow the new
processes

Assess progress
and take
comprehensive
stock of
achievements and
next steps
Evaluate results
and consider more
fundamental
changes
Re-evaluate
organization
strategy at later
stage based on
evolving needs

Pre-Decisional - Proprietary and Confidential | 85

Overall implementation plan


Phase 1: quick wins & critical actions

PRELIMINARY

Phase 2: building excellence

Activity
A. Stage gate process
Share plan and create SG working group
Define stage-gate process for CU
(roles, deliverables, etc @ each gate)
Major projects
Complex Minor and Outlays
Syndicate with key stakeholders
Launch: pilot, adjust, scale to all complex projects
Assess results and define next steps (e.g. extend
to base Minor and Outlays projects)
B. Contracting strategy
Identify CS working group
Create contracting strategy playbook
Syndicate with key stakeholders
Launch: pilot, adjust, scale to all projects
Assess results and define next steps
C. Transparency
Syndicate version 1.0 of transparency
measures (dashboard and PRB)
Implement version 1.0 for all Major projects
Design, pilot, and adjust PRB & dashboard v2.0
Scale v2.0 to all projects
Assess results and define next steps
D. Project Managers
Identify mode for PM trainings (internal/external)
Map needed PM skills (and current state)
Design program (curriculum and format)
Launch field and forum trainings
Define & implement policy to ensure sustainment
(e.g. training refreshers, assessments, etc.)
Assess results of PMs and define next steps

2015

2016

Oct Nov Dec

Jan

Phase 3: sustaining excellence

Feb Mar

Apr

May Jun Jul

Phase 4: future considerations

Aug Sep Oct

Nov Dec

Implementation of 1.0 continues until v2.0 is scaled to all

Workshop(s) to share recommendations and future plan


Source: Team analysis

Pre-Decisional - Proprietary and Confidential | 86

STAGE GATE PROCESS


PRELIMINARY

A Stage Gate Implementation Plan


2015
Activity

Oct Nov

2016
Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

A. Stage gate process


Establish Stage Gate Focus
Group to revise current Planning
Process
CU Boulder Funding Review Boards:
Establish an internal Review Board and Procedures
to evaluate need for Projects (Stage 1, prior Stage 2b,
and optional Stage 3)
Clarify Campus Priorities:
Review 10 year campus master plan and 2030 plan
to determine Capital Project prioritize over next 2 years
Funding Analysis:
Determine 2 year project pipeline and estimate
Stage 2a funding requirements
Define Base vs Complex project type
Determine if funding comes from CU Boulder or
from initial Board of Regents approval
CU Boulder Policy and Process:
Focus on Construction QA/QC Procedure (optional Stages
4 and 5) and Close Out Procedure (optional Stage 6) to
maximize quality and timely accounting closure
Develop Stage Gate Playbook:
Focused on pre-work required for each gate, templates,
agenda for stage gate meetings, Reviews required.
Launch New Stage Gate Process
Playbook and Process Rollout:
Rollout to PD&C Team and larger user group
Trial Playbook and Process:
Utilize Playbook on two new projects
Constant Improvement:
Provide feedback after each use at each gate
Source: Team analysis

Pre-Decisional - Proprietary and Confidential | 87

STAGE GATE PROCESS


PRELIMINARY

A Stage Gate Implementation Plan


2015 2016
Activity

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

A. Stage gate process


Establish Stage Gate Working Group:
defines stage gate process for CU
(roles, deliverables, etc at each gate
Clarify Campus Priorities and Funding Needs:
Review 10 year campus master plan and 2030 plan
to determine Capital Project prioritize over next 2 years
CU Boulder Funding Review Boards:
Establish an internal Review Board and Procedures
to evaluate

Define Base vs Complex project type

Determine if funding comes from CU Boulder or


from initial Board of Regents approval
CU Boulder Policy and Process:
Focus on Construction QA/QC Procedure (Stages
4 and 5) and Close Out Procedure (Stage 6) to
maximize quality and timely accounting closure
Develop Stage Gate Playbook for Major Projects
Develop Stage Gate Playbook for Complex
Minor and Outlay Projects
Launch New Stage Gate Process:
Pilot, adjust, scale to all complex projects
Asses results and define next steps
(e.g. extend to base Minor and Outlay projects)
Source: Team analysis

Pre-Decisional - Proprietary and Confidential | 88

CONTRACTING PROCESS
PRELIMINARY

B Contracting Implementation Plan


2016
Activity

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

A. Contracting process
Establish Contracting Strategy Playbook Working Group to
develop preferred delivery methods for complex projects
Create Contracting Strategy Playbook:
Delivery Methods:
Evaluate delivery methods that match a mix of project goals.
Evaluate against State requirements
Contractor Selection Methods:
Determine contractor selection methods against selected
delivery methods and State requirements.
Contract Language:
Develop standard contract language to match Delivery
methods, risk division, and mix of project goals.
Evaluate against State requirements.
Syndicate with key stakeholders
Launch New Contracting Strategy Playbook
Pilot and Adjust:
Educate PD&C Team and larger user group
(Legal, etc) to new tools and processes moving forward
Scale to all projects:
Assess results and define next steps

Source: Team analysis

Pre-Decisional - Proprietary and Confidential | 89

TRANSPARENCY

C Transparency implementation plan


2015
Activity

Oct

PRELIMINARY

2016
Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Review Project Review Board format

With Administration
With PD&C leadership
With (select) PMs
Any other stakeholders

Pilot & scale v1.0

Identify PMs and projects to pilot


transparency measures v1.0

Conduct at least 2 pilot PRB meetings


and iterate over the format

Scale v1.0 to all Major projects and


Capital PMs

Scale v1.0 to all Minor and Outlays

Design and scale v2.0

Identify technological solutions to


automate and scale the data collected
for Project Review Board

Design version transparency 2.0 for


all projects

Pilot transparency v2.0 with select


Major, Minor, and Outlays project

Adjust v2.0 per feedback from pilot


Scale to entire capital program
(including Minors and Outlays)

Source: Team analysis

Pre-Decisional - Proprietary and Confidential | 90

PROJECT MANAGER PERFORMANCE

D Preparation for module deliver must happen well in advance of


Ongoing support provided
actual workshop modules
through fieldwork
Activity
A. Develop new PM
training modules
Confirm necessary
PM skills and
definition of excellence
Select first batch
of PM trainees, confirm
in participation
Create workshop
module content
Review module content
with internal and external
PMs and experts
Revise module content
based on senior PM review
B. Train new PMs on
identified skills

Dec

Jan

Feb

Mar

Apr

May

Workshop series 1
Workshop series 2
Workshop series 3
Workshop series 4
C. Sustain program through
policy and procedure page
Identify skill development
needs of PMs
Provide workshop
to develop skills
Source: Team analysis

Workshops completed on a quarterly


basis on Field and Forum approach

Perform quarterly
Perform as needed
Pre-Decisional - Proprietary and Confidential | 91

The Steering Committee would support change management efforts


and resolve any obstacles

Members involved

Session objectives

Cadence

Core team members, every


meeting
CFO
Interim Vice Chancellor,
Administration
Interim Assistant Vice
Chancellor, Administration
Director, PD&C
TBD

Track progress on various

Initial set-up (Months 1-3)

initiatives
Guide teams on critical
decision points
Provide support in
obstacle resolution
Celebrate success and
provide change
momentum

Every 2 weeks during


months 1-3 while work
streams kick off

Steady state (Months 3+)


Monthly until with option
to adjust cadence as
needed

Supporting experts, as
needed
PD&C Change Agents
Initiative Champions
PMs, Planners
Others

Source: Team analysis

Pre-Decisional - Proprietary and Confidential | 92

Immediate next steps for CU Boulder

Agree on a timeline for

implementation among relevant


stakeholders (PD&C, Administration,
etc.)

Establish a leadership task force to


oversee the implementation

Communicate the findings and plan


widely with all impacted organizations

Begin to identify champions for each


of the recommendation

Pre-Decisional - Proprietary and Confidential | 93

You might also like