You are on page 1of 3

REVIEW ( 5-Jun- 13 )

1. What is the SPT for dense sand?


Options: 0-20 / 20-40 / > 100.
JUM: 20-40.
2. How to calculate a continuous T beam ?
Supported at various points
Simply supported
Flanged section
Rectangular section.
JUM : flanged section.
3. What is Degree of curve? JUM : 100 feet chord angle .
4. For how cross sections are used ? JUM : for cut and fill quantities.
5. What is the perception and reaction time for calculating the sight distance?
1 second
2.5 s
3.5 s
None of the above .
JUM : 1 second.
6. If a work, if the property decides to make a change in scope, what is the procedure to
do ?
Change order
Modification
....
JUM : Change order .
7. For why steel is preferred as reinforcement in concrete?
Because it is inexpensive and resistant
Because it is easily accessible
Because it adheres well to concrete
Because it has the same coefficient of expansion of the concrete.
JUM : because it adheres well to concrete.
8. What is concrete density ? JUM : 2.4 .
9. Right or false? What factors influence the compressive strength of concrete?
Resistance is inversely proportional to the water-cement ratio
The resistance is proportional to the cement content

Cracks on the surface due to excessive water content


All others are true.
JUM : all others are true.
10. On relation to the use of air-entraining agents in concrete, which of the following
statements are true:
Improve the workability
Improving long-term durability
Makes a less dense mixture
...
JUM : all the above are true.
11.Rellenar the gap : The immediate ______________ are Necessary to Develop the
Following tasks in a breaking down of a project .
Critical activities
predecessor activities
successor activities
Burst activities
None of the above is correct.
JUM : Predecessor activities.
12. What of the following statements are false for a Work package:
Allocating resources must
It should designate a Work manager.
It should set deadlines "definitive "
None of the above is false .
JUM : You should set a timetable definitive .
13.On Work breakdown structure relative to project which of the following statements are
false ? .
Breaks up the project in a " top-down " .
It breaks down the draft as "down -top "
Used to handle large projects.
JUM : used to handle large projects.
14. What is a logical sequence of activities?
1,2,3,4
3,2,4,1
2,4,3,1 .
JUM : 1,2,3,4 .
15. What is the logical sequence of a concrete ?
JUM: formwork (framework) > pouring ( pouring ) > curing ( curing ) > stripping .

16. Problem influence lines. Vocabulary: shear stress .


17. Problem a lattice.
18. Problem: "If in a plane I measure 7 " "(inches ) and is 1/62.500 scale , what is the
distance between the two points in miles ? " JUM : 7, 25 miles.
19. Lacing system. Doubt: Is an articulated structure?.
20. In a beam which points of stress due to the time and bearing is equal to 0 ?
In the neutral light center .
In the top center fiber light.
At lower fiber support.
In the neutral support .
JUM : the neutral center and the neutral light support .
21. Problem of a cross section of concrete. What is the moment of resistance?