You are on page 1of 1

HARTMARIN

TOOLS COLLEGE CREEK


SANTA ROSA, CA
INFRASTRUCTURE

ROADS Lin. Ft. Width $/Sq. Ft. Amount


Sidewalk Demo 10.00 5.00 10.00 500.00
Roads 1,000.00 24.00 5.50 132,000.00
New Driveways - 24.00 5.00 -
Sidewalk, curb & gutter 1,000.00 5.00 12.50 62,500.00
Parking Spaces 160.00 10.00 5.50 8,800.00
Total 203,800.00

WATER Lin. Ft. Quan. $/Ln. Ft. Amount


Service 20.00 8.00 100.00 16,000.00
Mains 1,000.00 1.00 100.00 100,000.00
Hydrants 1.00 4.00 5,000.00 20,000.00
Other water work 1.00 8.00 5,000.00 40,000.00
Total 176,000.00

SEWER Lin. Ft. Quan. $/Ln. Ft. Amount


Laterals 20.00 8.00 100.00 16,000.00
Main 1,000.00 1.00 100.00 100,000.00
Pump station - 1.00 50,000.00 -
Other sewer work 1.00 8.00 5,000.00 40,000.00
Total 156,000.00

DRAINAGE Lin. Ft. Quan. $/Ln. Ft. Amount


Units 100.00 8.00 100.00 80,000.00
Site 1,000.00 1.00 100.00 100,000.00
Other drainage work 1.00 - 5,000.00 -
Total 180,000.00

UTILITIES Lin. Ft. Quan. $/Ln. Ft. Amount


Combined utilities 1,000.00 1.00 100.00 100,000.00
PG&E Engineering - 1.00 50,000 -
Other utility work 1.00 8.00 2,500.00 20,000.00
Total 120,000.00

LANDSCAPE Units $/Unit Amount


Front & rear yards 1.00 7.00 25,000.00 175,000.00
Common landscape 1.00 1.00 50,000.00 50,000.00
Terraces 2.00 13,800.00 15.00 414,000.00
Specialty trees 10.00 1.00 1,000.00 10,000.00
Retaining Walls 150.00 5.00 100.00 75,000.00
Fencing 1,000.00 1.00 35.00 35,000.00
Other landscaping work 1.00 9.00 5,000.00 45,000.00
Total 804,000.00