HARTMARIN TOOLS COLLEGE CREEK SANTA ROSA, CA INFRASTRUCTURE ROADS Sidewalk Demo Roads New Driveways Sidewalk, curb and gutter Parking Spaces Lin. Ft. Width 5.
HARTMARIN TOOLS COLLEGE CREEK SANTA ROSA, CA INFRASTRUCTURE ROADS Sidewalk Demo Roads New Driveways Sidewalk, curb and gutter Parking Spaces Lin. Ft. Width 5.
HARTMARIN TOOLS COLLEGE CREEK SANTA ROSA, CA INFRASTRUCTURE ROADS Sidewalk Demo Roads New Driveways Sidewalk, curb and gutter Parking Spaces Lin. Ft. Width 5.
Service 20.00 8.00 100.00 16,000.00 Mains 1,000.00 1.00 100.00 100,000.00 Hydrants 1.00 4.00 5,000.00 20,000.00 Other water work 1.00 8.00 5,000.00 40,000.00 Total 176,000.00
SEWER Lin. Ft. Quan. $/Ln. Ft. Amount
Laterals 20.00 8.00 100.00 16,000.00 Main 1,000.00 1.00 100.00 100,000.00 Pump station - 1.00 50,000.00 - Other sewer work 1.00 8.00 5,000.00 40,000.00 Total 156,000.00
DRAINAGE Lin. Ft. Quan. $/Ln. Ft. Amount
Units 100.00 8.00 100.00 80,000.00 Site 1,000.00 1.00 100.00 100,000.00 Other drainage work 1.00 - 5,000.00 - Total 180,000.00
UTILITIES Lin. Ft. Quan. $/Ln. Ft. Amount
Combined utilities 1,000.00 1.00 100.00 100,000.00 PG&E Engineering - 1.00 50,000 - Other utility work 1.00 8.00 2,500.00 20,000.00 Total 120,000.00
LANDSCAPE Units $/Unit Amount
Front & rear yards 1.00 7.00 25,000.00 175,000.00 Common landscape 1.00 1.00 50,000.00 50,000.00 Terraces 2.00 13,800.00 15.00 414,000.00 Specialty trees 10.00 1.00 1,000.00 10,000.00 Retaining Walls 150.00 5.00 100.00 75,000.00 Fencing 1,000.00 1.00 35.00 35,000.00 Other landscaping work 1.00 9.00 5,000.00 45,000.00 Total 804,000.00