Estimate
User Manual
RIB Software AG
Copyright
Copyright
This manual is intended for use as a working document for users of RIB product
families.
The procedures described in this document and the products belonging to them are
the property of RIB Software AG.
We reserve the right to change the information in this document without prior
notice, and the contents pose no obligation to the RIB Software AG. The software
described in this document is provided in conjunction with a licence agreement.
All information is given without warranty. Reproduction or transfer of this document,
or parts of it, is only permitted with the explicit written permission of RIB Software
AG.
With respect to liability for the software described here, please refer to our software
contract conditions.
Copyright RIB Software AG
Published by:
RIB Software AG
Vaihinger Strae 151
70567 Stuttgart-Mhringen
70507 Stuttgart
E-Mail: info@rib-software.com
Imprint: http://www.rib-software.com/impressum
Trademark
RIB iTWO, ARRIBA (Germany only), RIB|EPC, RIBTEC STRATIS,
DIGIMASS, TRIMAS, PONTI and ZEICON are registered trademarks of
RIB Software AG. Other product names mentioned in this documentation may be
owned by other trademark holders and are used only for information purposes.
This product contains software that was developed by the Apache Software
Foundation (http://www.apache.org/).
Estimate
03-2011
Table of Contents
Table of Contents
10
12
1.1
13
1.2
14
1.2.1
15
1.2.2
17
1.3
18
1.3.1
18
1.3.2
19
1.4
Estimate methods
19
1.4.1
19
1.4.2
Column estimate
20
1.4.3
21
1.4.4
22
1.4.5
23
1.5
Bid creation
24
1.6
25
1.7
26
1.7.1
Filter
26
1.7.2
26
1.7.3
32
1.7.4
Disabled flags
37
1.7.5
38
1.7.6
39
1.7.7
WIC estimate
43
1.7.8
Modification functions
45
1.7.9
Generating an estimate
46
1.7.10
47
03-2011
Estimate
Table of Contents
Estimate
1.7.11
Margin
47
1.7.12
48
1.7.13
49
1.7.14
50
1.8
50
1.8.1
Updating quantities
50
1.8.2
51
1.8.3
Assembly details
55
1.8.4
57
1.8.5
59
1.8.6
Backwards calculation
62
1.8.7
Price adjustment
64
1.9
Content Functions
65
1.9.1
65
1.9.2
65
1.10
68
1.10.1
68
1.10.2
68
1.11
68
1.11.1
69
Interface
72
2.1
72
2.1.1
Project properties
72
2.1.2
74
2.2
Estimate document
76
2.2.1
76
2.3
87
2.3.1
88
2.3.2
89
2.3.3
98
03-2011
Table of Contents
2.3.4
100
104
3.1
Create estimate
104
3.2
Open estimate
104
3.3
Close estimate
104
106
4.1
106
4.2
Create lines
106
4.3
106
4.3.1
106
4.3.2
107
4.3.3
107
4.3.4
107
4.3.5
108
4.3.6
Delete lines
108
4.4
108
110
5.1
110
5.2
110
5.3
Active Search
111
5.3.1
111
5.3.2
112
5.4
113
5.4.1
113
5.5
114
5.6
114
5.7
Go to Reference number
115
Copying
116
6.1
116
6.1.1
116
03-2011
Estimate
Table of Contents
6.1.2
117
6.1.3
118
6.1.4
Copy from
118
6.1.5
119
6.2
119
Update estimate
120
121
8.1
121
8.2
121
122
9.1
Editing catalogs
122
9.2
122
10
123
11
125
11.1
125
11.2
125
11.3
126
12
127
13
129
14
Assemblies
130
14.1
Generating an assembly
130
14.2
130
15
Generate
132
15.1
132
15.2
132
15.3
133
16
136
16.1
136
16.2
136
elements
Estimate
03-2011
Table of Contents
16.3
137
17
139
17.1
139
17.2
139
17.3
141
18
143
19
144
19.1
Set/delete flag
144
19.2
Change factors
144
19.3
145
19.4
146
19.5
Update the assignment criteria from the catalog for the estimate
147
element
19.6
Change flag
148
19.7
148
19.8
149
19.9
150
19.10
150
20
152
21
Create bid
154
21.1
154
21.2
154
21.3
155
21.4
156
21.5
156
22
158
22.1
158
23
160
24
161
24.1
161
03-2011
Estimate
Table of Contents
Estimate
24.1.1
Print box
161
24.1.2
Print item/division
163
24.1.3
BoQ Print
164
24.1.4
Print allocation
166
24.1.5
167
24.1.6
167
24.1.7
168
24.1.8
169
24.1.9
169
170
24.2
Reports
170
24.2.1
Reports - Estimate
170
24.2.2
Reports - Controlling
186
24.3
Print Options
188
24.3.1
General
189
24.3.2
190
24.3.3
192
24.3.4
Document
193
24.3.5
193
24.3.6
Checklist settings
194
24.3.7
195
24.3.8
Filter
196
24.3.9
Configuration
198
198
199
207
209
24.3.14 Quantities
210
212
213
03-2011
Table of Contents
215
215
24.3.19 Sorting
216
216
24.3.21 Currency
218
24.3.22 Values
220
24.3.23 Additions
221
Index
03-2011
222
Estimate
Meaning
Safety instructions
must be read. They contain warnings which must not be ignored.
Notes
contain important information such as exceptions or special cases.
Working steps
are instructions that should be followed in the given sequence.
Tips
facilitate your work.
Examples
relate to work steps or serve to clarify relationships.
Troubleshooting
deals with a problem and its solution.
Target (only in training documents and introductions)
defines the next learning target
Exercise (only in training documents and introductions)
shows a practical example for better understanding.
Conclusion (only in training documents and introductions)
provides a short summary of the course content.
10
Estimate
03-2011
Please send any suggestions and wishes regarding our documentation and online
help to the respective hotline.
03-2011
Estimate
11
12
Estimate
03-2011
| Documentation |
03-2011
Estimate
13
Client enquiry
If you receive a "request for handover of a bid" (enquiry) from a client or their
representative, a corresponding project is created.
The process of creating a new project is described in detail in the "The Basics"
documentation.
Bid BoQ
The client may provide the enquiry BoQ either as a file in GAEB format or simply
as a hard copy.
The entry of a BoQ and importing of a BoQ from a data storage medium are
described in detail in the "Enquiry" documentation.
Create bid
Bid totals become available after editing final markups (according to the chosen
method) and activating this allocation for the price calculation. The bid can be
generated, with output being available both as a printed bid and as a file (export to
GAEB).
See also
Requirements for the estimate [ 14]
Bid creation [ 24]
The following minimum requirements must be fulfilled for you to create and edit an
estimate:
There must be at least one BoQ with an item.
There must be a Cost Codes catalog in which at least the major cost codes are
defined. For further information, please refer to the "Catalogs" documentation.
Furthermore, there must be a Currencies catalog containing all currencies that
you would like to use, including their exchange rates. Whenever a project is
14
Estimate
03-2011
created, the master catalog is automatically copied into the current project. No
further work is necessary in this respect if the master catalog is in good working
order.
There must be a Units of Measure catalog containing all units of measure that
you would like to use. Whenever a project is created, the master catalog will be
copied automatically into the current project. No further work is necessary in
this respect if the master catalog is in good working order.
The following further requirements considerably support your work with estimates
and are recommended:
A detailed master cost code calatog, which will be copied into the project.
(Exception: Estimate with DBD estimate data)
A Commodities catalog.
Standard estimates for copying estimates to the current project.
A detailed master assembly catalog, which will be accessed by the current
estimate. (Exception: Estimate with German DBD estimate data)
The Plants catalog in the master project, which is used both in creating the
In the scope of the estimate, you have the following possibilities with regard to the
BoQ:
Create BoQ manually
If you do not have a BoQ file of the client, you have to enter the BoQ. To do
this, you must create a BoQ document under the project alternative. For this,
open the project, select the project alternative and click Start | Modules | BoQ.
(c) RIB Software AG
03-2011
Estimate
15
GC-BoQ
Newly created BoQs with the General Conditions (GC) flag and their divisions are displayed with the
flag [LSUM] (lump sum).
GC-BoQs are always are treated as lump sum BoQs (with revenue =0.00).
The cause for this display can be found in budgeting lump sum elements. (For more information, see
also the "Controlling" documentation).
16
Estimate
03-2011
All subordinate items are automatically Cost Items, i.e. they will only be
referred to for internal analyses.
The subordinate items no longer have a contract price, they have the UR =
negotiation.
In the Execution phase, however, the budget becomes very relevant for the
contractor. For information on this, refer to the "Controlling" documentation.
03-2011
Estimate
17
Levels of the BoQ for which variant factors for labour must be specified
(BoQ or individual divisions).
Fictitious subtotals for the elements with variant factors for labour
18
Estimate
03-2011
Commodity).
03-2011
Estimate
19
In the so-called item estimate, every single detail is created in a separate line, with
specification of a cost code, an assembly, a plant assembly or a German
DATANORM commodity. The columns of the table are subdivided into the following
sections:
Section for Line code, Code and Description
Section for QTO details and Cost details
Section of the Results per unit of measure of the Subitem and the Item
All entries are made in the first two sections. There are no columns for results at
the level of the major cost codes. The DJC per major cost code are only visible in
Totals.
In the item estimate, an item can be divided over any number of subitem levels.
The estimate table itself is divided into lines and columns.
See also
Line types of the estimate in detail [ 100]
20
Estimate
03-2011
03-2011
Estimate
21
You can switch between all three methods at any time. Each type of calculation is processed correctly
in each view. Depending on the setting, the column estimate only allows a reduced view of estimates,
created using individual details. The item estimate allows another (more detailed) view of estimates,
created using the column estimate.
Item
Subitem
Cost Code
Commodity
Assembly
Broken-down assembly
Equipment assembly
Text
Internal text
Detail line
22
Estimate
03-2011
Line type
Computation Detail
Item copy
Reference item
See also
Line types of the estimate in detail [ 100]
Column Type
RN
Subitem
F (flag)
Code (C)
Text (description)
Quantity detail
Quantity
UoM
Factor
Cost/Unit
CUR
C factor (CoC)
Q factor (UoM)
Eff. Quantity
03-2011
Estimate
23
24
Estimate
Column Type
Total quantity
Hrs./UoM subitem
Cost/UoM subitem
Hrs./UoM item
Cost/UoM item
CWT
WC-No.
WIC no.
Disabled
Reserve
Neutr. COR
COR type
UR detail
Surcharge in %
UR item
Item Total
Location
Unassigned
Total/unit
Characteristic 1-10
03-2011
BoQ
2. Printing the bid
For a valid bid, the prices must be copied into the BoQ. This is carried out
automatically once you print the bid.
WARNING
If the CM receives the bid as a file only, you will have to update the prices before exporting the file by
using Actions | Data exchange | Copy values into BoQ. This command copies the UR calculated in the
estimate into the BoQ. The command has the same effect as printing the BoQ, i.e. the UR is copied
into the BoQ.
The calculated UR is valid for items in the estimate, for which the fixed-price flag is not set. This
may change after cost modifications.
If fixed prices were determined in the estimate, they have been copied into the BoQ in advance
by setting this flag.
a) If a division is selected, the URs of all subordinate items will be copied.
b) If a single item is selected, only its own UR will be copied.
For safety reasons, in both cases you will be queried if you would like to copy the prices for the
selected element from the estimate into the BoQ.
See also
Create bid [ 154]
03-2011
Estimate
25
Using Home |
For more information on filters and their definition, refer to the "The Basics"
documentation.
26
Estimate
03-2011
Construction Site. The use of first-level subitems (Numbers 1-9 and A-Z) may very
quickly result in a situation in which the complex structure can no longer be
represented for these, in part very complex, items. This is because only 36 options
(characters) exist for the creation of subitems.
If a CSU consists of more than 36 separate work items, a subdivision of complex
specified work items - exclusively at the first level - will fail for this reason. In this
case, you should use the different levels of the subitems by only carrying out a
rough structuring at the first level and refining it at subsequent levels until the level
of cost details is eventually reached. In this way, an almost unlimited number of
subitems is at your disposal.
If you apply the principle above, you are firstly able to create a very large number
of subitems, and secondly you enable the automatic formation of important
subtotals at the various level, which significantly facilitate the assessment of the
individual results.
See also
Example 3: Complex work items [ 29]
03-2011
Estimate
27
Hours and materials for the concrete can be directly specified as they are
estimated per cbm in any case, i.e. per unit of measure of the item. Hours,
materials and plants for the wall formwork cannot be directly used, however, since
they are not estimated per cbm and the quantity of the formwork per cbm must be
determined first.
In this case, create two subitems which describe the required work items per unit of
measure of the item:
Subitem 1:
Subitem 2:
In the subitem, the estimate is now made per unit of measure of the subitem.
Details in subitem 2 thus relate to 1 m2 wall formwork; the program takes care of
projecting to item level including the "internal" quantity 6.70 m2/cbm.
Thus, detail lines per unit of measure may also refer to the units for which values
gained by experience are available. In the above example, you can evaluate the
estimated costs per square metre of formwork, although not the result for 6.7 m2.
In principle, the estimate of the item appears as follows (for a crew mix of 50,-):
Item 4.37:
360.000 cbm
492,48
Hrs.
Materials
6,26
28
Estimate
03-2011
Plant
155,36
24,12
Subitem 1:
1.000 cbm
Concrete B25
DJC/UoM:
195,00
Hrs.
Materials
0,900
Subitem 2:
6.700 m2
150,00
Wall formwork
DJC/UoM:
44,40
Hrs.
Materials
0,800
Plant
0,80
3,60
With regard to structuring according to the above example, it can be specified more precisely:
a) Subitems below an item are a sub-BoQ for the unit of measure of the item.
It may also be that a subitem is a work item for the quantity total of the item.
See also
Example 3: Complex work items [ 29]
1,600.000 sqm
Subitem 1
0.300 cbm
In this way, the estimate details may refer to the standard unit of measure for
excavations, cbm.
03-2011
Estimate
29
subitem of the 1st level can in turn be subdivided over subitems of the 2nd level,
and these in turn over subitems of the 3rd level, etc.
Here, the same principle always applies:
Subitems below a subitem are a sub-BoQ for the unit of measure of the parent
subitem.
The structure of sub-subitems is also always the same:
No., description, quantity, unit of measure.
The quantity of the subitem is the required quantity per unit of measure of the
parent item.
Example for complex work items
Item 4.121:
Subitem 1:
Foundation
Subitem 11:
Subitem 11:
1.000 m
Subitem 112:
0.125 m
Subitem 12:
0.750 cbm
Subitem 2:
Retaining wall
Subitem 21:
Subitem 211:
3.000 m
Subitem 212:
0.050 m
Subitem 22:
0.300 cbm
In the above example, you obtain work items for foundation and wall per running
metre of retaining wall (1st level), which include work items for formwork per
running metre of retaining wall and concrete 25 (2nd level) as well as for foundation
and wall work items per type of formwork per square metre (3rd level).
The division into subitems is up to you.
Reasons for the selection of the subitems may be:
30
Estimate
03-2011
An appropriate unit of measure of the work item must be available for the
estimate details.
The structure of the estimate must be clear.
Work items that can be evaluated must be created.
Intermediate calculations of the estimate should be available.
"Internal" quantities should be easily adjustable.
The structure should enable an accrual of performances within the item, e.g.
the formwork is already complete but the concrete has not yet been cast.
5000.000 cbm
Subitem 1 lsum
2.000 units
Excavator haulage
Subitem 2:
1.000 cbm
Subitem 3:
1.000 cbm
Removal
The example above allows the estimate of the cost details for transport in Subitem
1. Haulage is considered via the quantity 2.000 The result of Subitem 1 for its
quantity of 2.000 will be automatically allocated to the 5000.000 cbm of the item by
the program. You therefore will not have to divide your details manually by 5,000 to
obtain the value per unit of measure for the item.
In addition, you must be aware of the following information concerning the subitem
type Lump Sum:
It is recommended to use the subitem type Lump Sum only at the first level of
subitems.
03-2011
Estimate
31
The total costs from a subitem of the type Lump Sum will always be allocated
to the AQ (adjusted quantity) of the item.
The AQ was selected as an allocation base, since lump sum costs must be
allocated to the realistic quantity in order to obtain the correct result per unit of
measure. If the BoQ quantities are identical to the AQ quantities, the above rule
has no effect.
Subitems of the type Lump Sum may also be structured using sub-subitems.
Together, they provide the result per unit of measure for the subitem of the type
Lump Sum.
If an installed quantity is reported for a subitem (project phase Execution), then the factor/divisor is
ignored. The IQ quantity of the subitem is already the effective quantity that must be considered for
the analysis of the planned costs.
Hence, for subitems with factors <> 1.000, the effective quantity should be
specified as an IQ quantity. In the example of the excavation for the foundation,
this is therefore not the theoretical quantity but the actual quantity. If the IQ quantity
is reported for the item level, however, the theoretical quantity must be entered.
The IQ quantity in this example of the distribution of the lump-sum advance
performance over three items then is either 0.333 in each item or 1.000 in only one
item and 0.000 in the remaining two items.
If subitems are considered as the reporting level for IQ quantities, it quickly
becomes unclear which quantity should be entered there for the cost side to be
represented correctly.
This means:
With regard to the performance report in the case of the execution, at least the
subitems with Factor/Divisor < > 1.000 that are considered as the reporting level for
32
Estimate
03-2011
IQ quantities should be treated restrictively. The described problem does not arise
if factors/divisors are set in the estimate detail.
Below, you are shown an overview of how to use a factor or divisor in subitems.
The following examples should illustrate how they are used.
1.000 m
0,400
Subitem 2:
1.000 m
0,600
In this case, the subitem quantities can also be set directly to 0.400 or 0.600. In the
above representation, however, the situation is more transparent.
1.000 cbm
1,150
03-2011
Estimate
33
Item 1.10
Factor
Subitem 1
Performance 1
0,80
Subitem 2
Performance 2
0,80
Subitem 3
Performance 3
0,80
Item 1.20
Factor
Subitem 1
Performance 1
0,20
Subitem 2
Performance 2
0,20
Subitem 3
Performance 3
0,20
The factor/divisor of the subitem has an effect on the quantity of the subitem and thus indirectly on the
costs.
34
Estimate
Cost code
Quantity
UR
Factor
Hours
0,800
50,000
1,000
B25
1,000
150,000
1,030
03-2011
When 1.030 is entered as the factor, this concrete loss is taken into account for the
material.
Example: Divisor in the detail line
In an excavation performance, one excavator is operated with one assistant. This unit has an
excavation capacity of 50.00 cbm per hour.
Cost code
Quantity
UR
Divisor
Excavator Hrs.
1,000
122,50
/50,000
Assistant Hrs.
1,000
50,00
/50,000
Both for the excavator and for the assistant, a cost detail per hour has been
created and divided by a performance of 50.000 cbm/h.
The factor/divisor directly influences the quantity of the cost detail and thus indirectly the costs as well.
a cost factor has already been entered in a detail line and you additionally enter a cost factor at
the level of the subitem, then the cost factor is calculated multiple times.
03-2011
Estimate
35
Quantity
1,000
0,200
1,000
0,080
UoM
Factor
m
Hrs.
m
m3
Eff.
Cost/
Quantity
UoM item
1,000
1,000
9,84
1,000
9,84
1,000
1,000
31,34
0,200
6,27
1,000
1,000
2,43
1,000
2,43
1,000
1,000
14,32
0,080
1,15
If you know, for instance, that the price for PVC KG Pipe DN 100 will increase by
5%, you can store a corresponding cost factor now in order to take the increasing
costs into account without affecting the effective quantity.
Provided that you have defined a parameter for the cost increase (e.g. CIPipe with
QTO detail/typical value = 1.05), you can now enter this parameter in the field Cost
factor detail in the corresponding detail line. Alternatively, you could also enter the
value 1.05 directly.
Description
Quantity
1,000
0,200
1,000
0,080
UoM
m
Hrs.
m
Factor
Eff.
Cost/
Quantity
UoM item
1,000
1,000
9,84
1,000
9,96
1,000
1,000
31,34
0,200
6,27
1,050
2,43
1,000
2,55
1,000
14,32
0,080
1,15
1,000
m3
CIPipe
1,000
The total result for the detail line and this subitem is updated depending on the
changed Cost factor.
Factor alternative for the cost factor
In the case of a change using the Factor field (to Quantity), you would have obtained an identical total
result but the value for the Effective quantity would have been changed too.
Description
36
Estimate
Quantity
1,000
0,200
1,000
UoM
m
Hrs.
m
Factor
Eff.
Cost/
Quantity
UoM item
1,000
1,000
9,84
1,000
9,96
1,000
1,000
31,34
0,200
6,27
1,050
1,000
2,43
1,050
2,55
03-2011
Description
Quantity
UoM
0,080
Factor
m3
1,000
1,000
14,32
Eff.
Cost/
Quantity
UoM item
0,080
1,15
See also
Parameters for calculating QTO details [ 39]
See also
Details about item type [ 90]
(c) RIB Software AG
03-2011
Estimate
37
neutralised flag. That way, the details in the project analyses are computationally
no longer active. The characteristic thus has the same effect as the disabled flag of
the subitem (see under 'Disabled flag'). However, it enables the neutralised risk
details to be calculated for information about modifications made in the risk area.
38
Estimate
03-2011
See also
Entering the risk characteristic in the subitems [ 125]
03-2011
Estimate
39
This function can be used to prepare standard items m concrete B25 including
formwork for walls: Define an own subitem for the formwork and a parameter D for
the wall thickness. Note that the parameter or, more precisely, the "characteristic"
has already been defined in the catalog of characteristics and has already been
assigned a value in Parameter in the estimate. In the quantity field of the subitem,
you do not enter a ready formwork quantity/m for a specific wall thickness, but
write the formula 2/D. After copying into an item to be estimated which has a wall
thickness of 0.25 m, for example, enter this value for the parameters. All quantity
fields depending on it are then calculated automatically. That way, you only need to
provide one standard item for all wall thicknesses.
At the level of detail lines, the BoQ item factor can also be used as an item
parameter in the QTO detail in the estimate.
Although the estimate contains a special field for the entry of performance rates or
quantity factors and no parameters need actually be used, this method offers
several advantages.
Special rules apply to parameters for copying detail lines. You can make the default settings for this
via option settings (Estimate - Parameter).
For details on the copy rules, refer to the "System Options and User Options" documentation.
The defined parameters are managed and displayed in a table. Using the context
menu, you can add new lines or delete an existing one.
Parameter definition at project level/project alternative level
Code
Description
UoM
QTO-Detail/Typical Value
A1
Centre-to-centre grid 1
5,00
ADFBOD
2*A1
3,50
5,000
10,000
joints
StFlHeight1
40
Estimate
Value
3,500
03-2011
Description
UoM
Baseplate thickness
QTO-Detail/Typical Value
Value
0,200
0,200
Code
Description
QTO detail
Side formwork
2*D*(2*A1)/(D*(2*A1)^2)
11
Hrs. formwork
2,000
baseplates
423110
Squared timber
0,020
10/10
2
Inserting concrete
S52
1,000
Hrs. concrete
4,000
baseplates
2511252
B25, 290 kg
592050
Concrete pump at
1,000
1,000
50 m3/h
3
Surface finishing
S52
Hrs. concrete
baseplates
0,200
5,000
m2
S32
Quantity
1/D
5,000
2,000
UoM
Factor
m2
1,000
1,000
Hrs.
5,000
m3
10,000
m3
Hrs.
113,80
22,76
55,00
380,00
1,000
/
1,000
m3
1,000
m2
1,000
/
189,50
8,000
m3
Hrs.
Cost/Unit
55,00
150,00
12,00
2,75
40,000
55,00
The quantity of the side formwork at expansion joints of the baseplate was
calculated using two parameters D and A1, where A1 is the standard grid of 5.00 m
and the distance between the expansion joints is (2 * A1). Furthermore, the
quantity of the surface to be finished in m has been calculated using the
parameter D. For example, the estimate of a standard item, in which all the
thicknesses of a normal baseplate are included, could look like this. After calling up
into the project estimate, only the thickness of the baseplate is acquired and the
03-2011
Estimate
41
average distance of the expansion joints. Like this, the quantities which depend on
the parameters of the subitems are automatically generated.
Instead of a directly acquired measurement in the QTO-Detail column, a formula
can also be entered using different parameters, which is illustrated by the example
of the ADFBOD parameter. This parameter could have been used in the above
item example instead of (2*A1).
Please observe the following:
a) If the value of a parameter at the project level that is directly referred to in a QTO detail of the
estimate is changed, then the function Extensions | Data Update | Update Quantities and Cost
Properties window.
If the concrete loss is changed, the detail lines are updated also.
42
Estimate
03-2011
in order to obtain the estimate detail per unit of measure, then a QTO detail with parameters can
be stored for its calculation.
If the value of the parameters is changed then, all details depending on them are updated
automatically.
Both the item and the WIC estimate can be copied from the work item catalogs via
the copy functions (e.g. via <F12> Copy from). This also applies for divisions in the
BoQ, where all associated items including the WIC estimate are copied.
03-2011
Estimate
43
In both cases, the associated estimate is also copied and the WIC ID is stored in
the item.
Delete WIC ID
The function Delete WIC ID is available in the context menu of the estimate table
(only for item estimate). It can be called up for individual WIC sub-items. After
confirmation (the same as for the BoQ), the WIC ID of the sub-item is deleted and
the detail lines can be edited again.
Parameters
If a project parameter is changed, the details in the WIC estimate are also updated.
The search for parameters in detail lines of a WIC estimate works in the same way
as in the PA.
Referenced Costs
In the WIC estimate, derived cost codes can be used, i.e. the Referenced costs
flag can be set in the item/surcharge item.
currencies. Upon data import, the corresponding foreign extensions are created in
the WIC and WIC BoQ.
44
Estimate
03-2011
WARNING
Any existing UPs and UR breakdowns are adopted as local portions.
In the same way as for the PA, the currencies can be entered in the WIC for the
local currency and the foreign currency, and are then automatically adopted by all
subordinate BoQs.
Cost-Code Catalog
With the function Set factors of cost codes to 1.0, the factors in the detail lines of
the WIC estimates are also adjusted.
Misc.
Use the right mouse button to switch from the WIC BoQ to the WIC estimate.
Markups can be calculated in the WIC estimate via the allocation.
03-2011
Estimate
45
Likewise, the total values can also be modified. This is then calculated back
down to the individual cost codes.
WARNING
A change in the project catalog can also have an impact outside the select project/BoQ area. This
applies for:
a) Cost and quantity changes
b) Assembly changes
46
Estimate
03-2011
Cost codes, Commodities ,...) and then be assigned to several target items.
Under 'Brickwork', all items are to be assigned a Labour cost code, the cost code Scaffolding as well
as the commodities Mortar and Bricks in only one work sequence.
See also
Generate estimate from external WBS [ 132]
Generate an estimate inside the BoQ [ 132]
Assigning estimate details (using element copies) [ 133]
1.7.11 Margin
The margin becomes importance from Project phase 2 (contract) onwards.
General definition:
The margin is that portion of the revenue that is available for covering the general
costs after the total job costs have been deducted.
The definition is valid both for the margin of the whole project and for the margins
of individual items. For GC items the margin is always negative since they have no
price and hence no revenue.
The margin of the entire project is required for covering the general and
administration costs of the company. As long as the margin is higher than the
general and administration costs (GA), a profit remains.
03-2011
Estimate
47
The estimate contains planned values, therefore it is only correct to refer to the "projected margin".
During the job estimate in Phase 3 (Execution) with fixed unit rates, the planned costs change along
with the margin.
The so-called "Actual margin" can be calculated from the revenue minus the actual costs.
See also
Margin (tab) [ 85]
48
Estimate
03-2011
Fixed Price flag, which, however, can be deactivated so that the calculated UR
takes effect again. The fixed price itself is still stored in the BoQ, however. Using
the menu command Copy Prices From BoQ, this stored UR can be declared as the
fixed price of the item again. Manually setting the Fixed Price flag in the estimate
has the same effect.
If a division is selected, the URs of all subordinate items are transferred to the estimate as fixed prices
and labelled acorrdingly. If an individual item is selected, only its UR is transferred as a fixed price.
For reasons of security, a query appears asking you whether you want to copy the prices from the
BoQ into the estimate for the selected element.
estimate.
(c) RIB Software AG
03-2011
Estimate
49
In this case, the transfer in the evaluation takes place for the Bidder 0.
50
Estimate
03-2011
In the estimate, the costs of the plants are to be included either directly in certain
items as so-called Operating plants (e.g. the excavator with its costs per hour and
a performance rate of 50 m/h in an excavation item) or as so-called stand-by
plants in an item of the site facilities or the General Conditions (e.g. the cranes and
portakabins etc. with its particular number and stand-by time).
The plant estimate module serves both tasks The basis for the plant estimate is a
Plant catalog, in which the basic data for the estimate is stored:
Stand-by costs as per CPL or free notation
Operation cost, handling cost
Loading, transport, installation
Technical key data
Operating plants are pre-estimated as plant assemblies which are managed in the
plant assembly catalog. It is sufficient that you determine one plant of the plant
catalog and the desired cost component (e.g. time- and use-dependent costs or
non-recurring costs). The estimate of the plant assembly is then generated
automatically. Additional cost components can be added manually. A plant
assembly can be used in different positions of the estimate.
Stand-by plants are compiled in the plant list. After specifying the number, stand-by
time and operating time they are automatically included in these plant lists
(c) RIB Software AG
03-2011
Estimate
51
according to the plant catalog. On the basis of a plant (type), any number of standby plants can be defined, e.g. for several cranes with different stand-by times.
The plant list gives information about:
Costs from stand-by plants
Costs from operating plants that are used in the estimate
Differencse of these costs
Difference costs processed in the estimate
In the plant list, the costs are thus created via the estimate elements operating
plant and stand-by plant, the costs are compared, the differences can be adopted
into the estimate systematically. Thus, the control over the complete inclusion of
the entire plant costs is ensured.
The plant costs are an great portion of the total costs of the construction site. The
bigger a construction project, the greater is the importance of powerful and efficient
plants. Plant costs must be included in the estimate in different ways. The types of
enquiries play an important role but also the considerations with respect to cost
advantages and disadvantages in the case of later quantity changes as well as the
possibilities of performance control during execution.
52
Estimate
03-2011
Non-recurring costs
Loading, transport
Installation
Fees, customs duty etc.
There can be any number of plant assemblies for a plant, e.g. to include different
conditions of application in the energy costs, to evaluate a depreciated plant
differently in the scope of depreciation or to be able to estimate with and without
additional personnel assistance. A plant assembly can be used in any positions of
the work item estimate. That way, the plant costs can be assigned to the work
items or allocation costs very selectively and specifically.
For the time- and use-dependent costs, you can use any of the units of time
Hrs.
Day
Month
with freely selectable conversion factors. All types can be used simultaneously.
The estimate is automatically adjusted when the unit of time is changed.
It is possible to generate all the plant assemblies for an entire range of the plant
catalog with one command. This function enables particularly the master catalog of
the plant assemblies to be structured very rationally.
03-2011
Estimate
53
In the Plant list, all plants are designated as stand-by plants, i.e. even those the
costs of which have already been partially or completely included in the estimate by
using plant assemblies. The estimate has already independently adopted the plant
list as stand-by plants. The stand-by plants are thus used to include the costs of all
plants of the construction site on the basis of their stand-by time, both the time and
use-dependent as well as the non-recurring costs. For example, the latter can only
be included in the estimate by the stand-by plants, i.e. they are not included in the
estimate by plant assemblies.
The plant list compares the total costs from the stand-by plants in each cost code
to the cost components that have already been included via plant assemblies and
forms the difference of the remaining costs that have not yet been included in the
estimate of the work items, e.g.
D + I from stand-by plant
D + I from plant assemblies
152.671,69
42.838,21
---------------------
Difference D + I
109.833,48
Processed difference
109.833,48
These cost differences can be copied to anywhere in the estimate. In the plant list,
a check determines to what extent the differences are included in the estimate.
Each update in plant catalog, plant list and estimate is automatically inherited so
that even new differences are correctly included in the estimate.
WARNING
Complete project plant catalogs and catalogs of the plant assemblies as well as project plant lists can
be copied into other projects. That way, Sample plant lists for certain types of construction projects
can be created and directly copied into ongoing project estimates, where only adjustments are
required then.
54
Estimate
03-2011
With Re-generate plant list the existing contents of the plant list are deleted and a
completely new plant list is generated, in which each plant that has been included
in the estimate via a plant assembly is created as a stand-by plant with the number
1 and a stand-by time of 1 month. To be on the safe side, a query asks you if you
want to delete the plant list. If you answer this message with OK, the plant list is regenerated.
03-2011
Estimate
55
In this special case, you can copy the assembly from the Assemblies catalog
into the item including all the detail lines and adjust it for this case.
In this case, there is no link to the assembly in the catalog.
Belated breakdown of an assembly
You may also start the resolution (copying of all detail lines of the assembly
into the item) at a later date should you only realise later that you must vary the
content of the assembly in an item-specific way. The program always turns a
broken-down assembly into a subitem. The way in which this subitem is
inserted into the existing structure is dependent on the item of the assembly
line:
If the line is not subordinate to a subitem, then a 1st level subitem is
created.
If the line is subordinate to a subitem, then a subitem is created for this
subitem.
If the assembly already had subitems, then these are maintained beneath
the new subitem of the estimate.
Take the following into account:
a) If an assembly which contains a variable is dismantled in an item and if this assembly contains a
variable, the value of which deviates from the value of the same variable in the item, then the
quantity detail is not copied from the assembly to the item, but the result is written in the quantity
field of the detail line, so that the copy of the line in the result still matches the line from the
assembly.
b) The broken-down assembly is no longer an assembly, i.e. the estimate lines of the work items
have lost their reference to the assembly. Any belated modification to the assembly causes no
change to the detail lines of the broken-down assembly in the estimate of the work items.
c) An assembly can only be broken down if the function Break down has been activated for the
assembly in the catalog.
56
Estimate
03-2011
Modifying an assembly
In the Assemblies catalog, some modification functions are available via Start | Actions | Modify
j)
See also
Break down assembly details (at a later date) [ 130]
03-2011
Estimate
57
A labour escalation clause is agreed upon, but the client demands a percentage of the wage
adjustment costs, amounting to 0.5 % of the billing sum. This amount should be calculated into
the GC.
In all above examples, it is required that a particular cost detail can be made in
which the reference value is specified, the respective base value is automatically
determined from the estimate, and a percentage based on this base value can be
specified. In some cases, only a specified portion of the base value should be
taken into consideration, e.g. 40% of the total labour costs.
For these types of tasks, the type of the derived cost code is used.
In the estimate with derived CoC, a detail is created under this special type of cost
codes which refers to a value from another quantity contained in the project
estimate. The computation result of the detail line with the derived CoC hence also
depends on computation results elsewhere in the estimate.
See also
Estimation with referenced costs (derived cost codes) [ 139]
58
Estimate
03-2011
Is only available for derived cost codes of the type not included (in normal items or
surcharge items). If the area to be evaluated contains details that have already
been evaluated with referenced costs, then these are taken into consideration (or
not taken into consideration) according to the defined calculation sequence for
referenced costs.
The result of the partial analysis however is not necessarily exact. Exact values are definitely only
obtained when all referenced values are updated.
This partial analysis can be automated via the system and user options (Estimate -
Estimate Details).
selecting a reference item is available. The program turns the estimate of the
selected item automatically into an assembly and puts this assembly as a detail
into the estimate of the line from which you started the function. At the same time,
the selected item "remembers" that it is a reference item. A modification in these
reference items updates the estimate in all positions that refer to it, i.e. also in the
assembly.
The estimate of the reference item and the estimate of the coupled assembly are
always identical, no matter where you make modifications. A modification in the
assembly or in the reference item updates all "Same-As items" depending on it.
03-2011
Estimate
59
See also
Edit reference item [ 129]
Display Collective WBS [ 127]
item).
Referenced items (B) and the reference items used (R) are displayed. Only
reference items are displayed that have been used in the current estimate.
The Collective BoQ window is called from within the estimate using Advanced |
Specialities | References.
60
Estimate
03-2011
You can jump directly from the Collective BoQ window to a desired destination item (via the Item ...
context menu) and the main window of the estiamte switches to and displays this item.
See also
Display Collective WBS [ 127]
03-2011
Estimate
61
BoQ
Ref. No.
1. 1. 10
B(R)
1. 1. 20
B(R)
1. 1. 30
In this case, the property reference item takes priority and the collective BoQ
appears as follows:
BoQ
Ref. No.
R(B)
1. 1. 30
1. 1. 40
In this special case, the line is marked accordingly with B(R) or R(B).
See also
Display Collective WBS [ 127]
62
Estimate
03-2011
Backwards calculation is only possible with the "Price agreement and backwards calculation" license.
Objective
Using this functionality, existing fixed prices may be calculated in reverse in such a
way that the following formula for price calculation becomes valid again:
DJC + Allocation = UR
In consequence, the fixed price flag can be deleted again and the unit rate
deviation will go back to zero.
This means that the prices become "transparent" again and calculable.
Backwards calculation allows the solution of two different problems:
1. Backwards calculation of items with fixed price, AA or MM to prevent an
occurrence of any deviation of the fixed UR from the estimate UR. In this case,
the backwards calculation must take place based on the active allocation.
2. With respect to change orders, markups that deviate from the markup factors of
the active allocation should be displayed. The following is valid in this case:
Backwards calculation is carried out for items (except surcharge items).
Backwards calculation is carried out based on an allocation containing the
required surcharges.
03-2011
Estimate
63
The prices are calculated on the basis of the active allocation and are
transferred to the BoQ.
The calculation and the allocation selected by the user are copied to a new
project alternative.
The allocation factors are fixed in the new project alternative.
There is no backwards calculation for surcharge items, as they receive their UR
from other items.
Backwards calculation is carried out for all the selected items.
The following is valid:
If necessary, the fixed price flag is deleted.
If necessary, AA is set to 0.
If necessary, MM is set to 0.
If the detail lines are to be modified using random numbers, then a lower limit (LL)
and an upper limit (UL) should be entered for the permitted deviation of the new
value.
The following must be valid for LL = 0.7 and UL = 1.3:
0.7 * Original value <= New value <= 1.3 * Original value
As the detail lines, for example for fixed price items or AA items, have to be
changed by a factor, then it may occur that these limits are not kept to with the
random numbers. An error message is output in the log for items for which the
deviation in a detail line is too great.
When backwards calculation has been carried out for all the selection items, then
the prices for all the items are recalculated on the basis of the selected allocation
and are then transferred to the BoQ.
As the factor and the quantity are rounded to three decimal places and the UR to
two decimal places, then it may occur that in the backwards calculation, there is a
minimal deviation in the UR compared to the original UR.
Therefore, you can specify a maximum permitted percentage deviation for the UR.
If items have a greater UR deviation, then this will be output in the log.
The specification of a maximum permitted percentage deviation only has an impact on the log.
64
Estimate
03-2011
The aim of this is to modify the bid prices in such a way that the same bid price
related to the BoQ quantity is determined, but, based on the AQ quantity, increased
revenue can be expected. The aim of this is that, for items with an AQ quantity less
than that of the BoQ quantity, the handover price is less than the agreed price
(estimate price) and for items with an AQ quantity greater than the BoQ quantity,
the handover price is also greater than the agreed price (estimate price). With this
aim, prices of items which are executed at the beginning of the measure are likely
to be increased, and prices of items executed at the end of the measure are likely
to be reduced. For information, the delta value is also displayed in the dialog box
for the change made.
See also
Modify price adjustment [ 150]
03-2011
Estimate
65
You may control how the program should use DBD estimate data when generating estimates via
system options and user options. For details, refer to the "System Options and User Options"
documentation.
There are two methods available for estimating with the German DBD calculation
details:
1. Estimate of individual items through individual calling up of German DBD
estimate data.
2. Automatic estimate of the whole BoQ or of a selected BoQ area.
The numbers of the text elements automatically form a link to the appropriate
estimate data. The estimate data is copied to the item.
However, it is also possible to access the German DBD estimate data from items
not created using text elements of the German STLB-Bau. In this case, you must
select the relevant elements from the German STLB-Bau manually.
A "mixture" of individual estimate and German DBD estimate data is also possible.
The individual details of the German DBD estimate data must have a connection to
the cost codes, as any cost detail in the estimate must be entered under a cost
code. This connection can be created in two ways:
No cost codes of any kind were defined in the project before estimate work was
commenced
In this case, the cost codes are generated automatically in the catalog upon
transferring of the German DBD estimate data. A cost code structure stored in
the German DBD data is used.
Cost codes are already defined in the project, e.g. the main cost codes
In this case, you must assign the six top-level cost codes of the German DBD
data in the Cost codes catalog to their own cost codes. In this case, the
German DBD cost codes of the lower levels are arranged beneath the cost
codes specified by you for the first level.
Assignment takes place in the opened Cost codes catalog. Click Actions |
66
Estimate
03-2011
See also
Estimate with German DBD estimate details [ 136]
03-2011
Estimate
67
68
Estimate
03-2011
Different reports are available, depending on the object (Project, Project Alternative
or Document) currently selected.
03-2011
Estimate
69
Check estimate
You may perform a check of the estimate. Different checking criteria are
available for selection. In the dialog box Print, the sub-folder Analysis with the
report type Check Report is available in the folder Estimate for this purpose.
Key items
You may carry out an analysis of the key items. In the dialog box Print, the subfolder Analysis with the report type Key Items is available in the folder Estimate
for this purpose.
70
Estimate
03-2011
03-2011
Estimate
71
Interface
2 Interface
2.1 Project and project alternatives
Overview of the estimate-relevant project data and of project alternatives
(properties).
2.1.1.1 Settings
Settings offers both display and settings functions and is subdivided into further
properties.
For a more detailed description of the individual properties, refer to the "Basic Knowledge"
documentation.
If, in addition to this, estimate-relevant aspects or settings need to be taken into account, they are
mentioned here.
72
Estimate
03-2011
Interface
WARNING
You should consider the following:
a) If you have downloaded or distributed the project alternative data by data exchange format, then,
in the change order numbering, there is a limitation of three places and numeric values.
The change order index may not be transmitted by data exchange (Change order 1.1 and
number and Change order index (this applies to the number of decimal places and/or the typical
values), then you will not be able to undo these changes at a later date. This also applies to the
function with change order index.
c) As soon as you have created a BoQ in the project alternative, you cannot reverse a change in the
settings later on here as well. Under certain conditions, you can still delete the BoQ, however,
provided that it is still empty.
Parameters
Here, you can define Parameters or use existing ones (search with <F3> in the
Characteristics catalog) that are only available at the current level (e.g. item level).
Parameter definition
Code
Description
UoM
QTO-
Value
Type
Detail/Typical
Value
L
Length of foundation
1,00
Width of foundation
1,10
Depth of foundation
1,00
Key Figures
Here, you can define Key figures or use existing ones (search with <F3> in the
Characteristics catalog) that are only available at the current level (e.g. item level).
Key figure definition
03-2011
Estimate
73
Interface
Code
Description
BS
Concrete hours
Formwork Index
UoM
Hrs.
QTO-Detail/Typical Value
Value
F(M='AQ";Type="Quantity";CoC="S5+")
10,450
SM_G / SK * 100
17,841
In the item, the system values only calculate their result from the data of the current item.
orders , Client (accessible via Client's representative), Bonds and Bill-to parties.
Submission
74
Estimate
03-2011
Interface
reason at 1.000.
Internally, the revenue is determined as follows:
03-2011
Estimate
75
Interface
The complete change order is evaluated. The values 'Net', 'VAT' and 'Gross' are
always evaluated by default. The following values are displayed:
Change order (entire): total as submitted in the bid
Change order approved: total with valuation factors
(only items with the status approved)
Change order not approved: total with valuation factors
(only items with the status not approved)
Total job costs (net only; all items)
The average valuation factors from the totals of all items are displayed under this
point.
If you enter a factor manually here, then a query appears, in which you are asked
whether you wish all the items of this change order to receive this valuation factor.
WARNING
Please be careful when answering the query with Yes.
Only enter a value here and transfer it if it is required that the valuations of all items are increased.
See also
Project Alternative properties [ 74]
You can obtain information on the estimate document using the associated
properties.
76
Estimate
03-2011
Interface
For information purposes, the time of the last modification and the user who made
it are also displayed.
2.2.1.2 Allocations
(c) RIB Software AG
03-2011
Estimate
77
Interface
The process of creating and editing an allocation is described in detail in the "Allocation"
documentation. Please pay close attention to the descriptions made there before you actually start
working on the allocation methods.
Add
Creates a new allocation.
Open
Opens the the allocation which is selected in Allocation for editing (double-clicking
on one of the displayed allocation definitions opens it as well).
Copy
Copies the selected allocation.
Remove
Deletes the selected allocation.
Properties
Opens the dialog box for editing the properties of the selected allocation.
Print
Opens the Print dialog box to print the selected allocation.
Further information on the allocation can be found in the "Allocation" documentation.
Total Sheet
Starts the additional module "Totals Sheet".
The Total Sheet button is only displayed if you have a licence for this additional module and this
licence is activated.
See also
The BoQ in the estimate [ 15]
78
Estimate
03-2011
Interface
Estimate BoQ
Select the BoQ to which the URB assignment should apply. This assignment is
carried out for each BoQ to be estimated, since the UR breakdown of individual
BoQs may be different.
Assigning UR breakdowns
This table lists all unit rates to which the UR breakdowns can be assigned. For the
assignment, note the definition of the UR breakdowns, which is displayed below
the table.
To assign a UR breakdown, click on the corresponding field. The assignment is
labelled with a . Each line can and must always be assigned to only one UR
breakdown.
a) The number and description of the cost portion are displayed.
b) The cost portions 1 to 6 are always available in the URB assignment and cannot be deleted.
c) The URB assignment is initialised with as many cost portions as were defined in the System
Options (Estimate - Unit Rates) at the time of creation. In case of subsequent system option
modifications, the URB assignments must be adjusted manually.
d) Additional cost portions > 6 can be added and deleted for exceptional cases (import of legacy
data).
e) Stored URB assignments from previous versions can no longer be loaded. An error message
indicates that the URB assignment to be loaded contains an incorrect scheme.
Save/Load
You can save and load a particular assignment of the costs and DCMs on costs for
reutilisation.
03-2011
Estimate
79
Interface
A UR breakdown thus consists of one or more components depending on the assignment. The
total of all UR breakdowns makes up the UR.
Potential problems due to rounding are counteracted by assigning even the rounding differences
specifically to one of the UR breakdowns. Please select a portion here which is usually
associated with values, e.g. Materials.
CoC 1
n1
n2
CoC 2
m1
m2
...
...
...
...
80
Estimate
03-2011
Interface
2.2.1.4 UFS-Sheet
If you have to submit one of the two unified form sheets UFS-Price 1a or UFS-Price
1b with the bid, additional preparatory work is necessary at this point, besides the
preparatory work of assigning cost codes to the cost components of the sheets, in
order to ensure that the form is filled in completely.
The new UFS sheets are shown in accordance with the rules of the awards manual VHB2002. The
allocation to five DJC portions is now possible in the Cost codes catalog.
Both the old and the new UFS sheets are offered for printing.
Markups
Calculate markups via CM
You can select whether the surcharges for social expenditure, non-wage labour
costs and other costs are to be adopted from the calculation of the crew mixes.
However, the prerequisite then is that you have linked all labour cost codes
with some crew mix.
In this case, you must prepare the division of the labour costs into crew mix,
social expenditure, non-wage labour costs and miscellaneous via the catalog of
the wage groups and corresponding crew mixes. The Crew mix B is
permanently assigned to the Crew mix in UFS price; the fixed components
03-2011
Estimate
81
Interface
Social expenditure and Non-wage labour costs in the category group extra
costs are permanently assigned to the corresponding lines of the UFS sheet.
All freely defined labour components from Non-wage labour costs are assigned
to Miscellaneous in the UFS line.
If the UR of the labour cost codes is transferred from the crew mix calculation,
then the relationship to the appropriate crew mix is saved for the CoC. In this
way, the components in the crew mixes can be evaluated with the respective
cost totals of the linked CoCs.
Calculate
You must initiate the calculation of the average markups from all crew mixes using
this button.
If the function Calculate markups via crew CM is activated, the associated fields under Markups are
read-only.
Print
Use this button to start the calculation and the printout. The corresponding reports
are offered for selection.
Enter markups directly
Instead of the calculation of the crew mix markups via the crew mixes and their
link to the labour cost codes, these can also be freely entered here.
Social expenditure in % of the crew mix
Non-wage labour costs in % of the crew mix
Miscellaneous in % of the crew mix
You can access the report for UFS price 1a or 1b either via the button Print or
from the selected or opened document Estimate via the Print icon.
The UFS sheets do not recognise any special influences on the DCMs, such as fixed prices or other
DCMs for optional items. In this context, certain deviations may arise for some values when compared
to the internally valid values. The estimated direct costs and the estimated GC are output as exactly
as possible. In addition, it is ensured that the output bid total agrees exactly with that of the printed bid.
Any "inconsistencies" are then compensated with the printed amounts for GA and R+P, so that the
following is always valid in the UFS sheet:
See also
Printing UFS sheet 2 [ 165]
82
Estimate
03-2011
Interface
The above logic is necessary because the percentages for S, L and Misc. per CM
can be different.
With the above equations any deviations due to manual modifications of URs are
also included in the labour cost code.
2.2.1.5 Rounding
The project-relevant rounding settings for the estimate are displayed here.
You can only influence the display of the number of decimal places with respect to:
Rounding the Factors
Rounding the Detail quantities
Internal accuracy in estimate
You can change the settings for rounding at project level. The property Settings -
03-2011
Estimate
83
Interface
2.2.1.6 Rounding UR
Rounding the UR or UR breakdowns when calculating...
Here, you can define the rounding settings (number of places and rounding
method).
Rounding to
By default, the value 2 is set for the number of places. You can set values from
0 to 5 here.
The following setting options are available:
Places before the decimal point
Places after the decimal point (default setting)
Significant places
Select the desired option here:
Rounding method
Set the desired rounding method here. The following options are available:
Standard (default)
Round up
Round down
Select the desired option here:
Boundary conditions
Value not equal to zero
You can specify as a condition that the rounded value for the UR may not equal
zero. This condition only applies up to the number of decimal places of the unit
rate.
Unit Rate = 2 Decimal places for the BoQ set
Rounding to 0 decimal places
Input or calculation for an UR estimate of 0.03 equals 0.03
The setting Unit Rate = 0 decimal places produces UR = 0, even if the value
thus produced is 0.
Value ranges:
84
Estimate
min. 1
max. 10
min. 0
Significant Places
min. 1
max. 15
03-2011
Interface
See also
UR breakdowns (properties) [ 72]
You can set defaults for updating the margin in the System and User Options
(Estimate - Margin). This concerns:
Transfer prices into the BoQ (in Bid phase only)
Distribute budget between detail lines (in Execution phase only)
Recalculate referenced values
Options
Evaluation with ... - quantity
In this view, you can display the values either for the BoQ quantity or for the
AQ quantity.
CUR
Displays the estimate currency from the basic data of the estimate.
With non-standard items
03-2011
Estimate
85
Interface
Update
If you confirm the query for recalculation with Yes, a query for updating the
referenced values appears. If you answer this with YES, another query will appear
asking whether the calculated prices should be transferred to the BoQ. If you
confirm with Yes, this has no negative consequences at all.
86
Estimate
03-2011
Interface
No.
d) In the BoQ, Yes updates a fixed price not marked with the fixed-price flag in the estimate, while
No causes it to remain at the current level and thus be so included in the calculation of the
revenue and the margin.
e) The bid print does not change any fixed prices of those items that have a fixed-price flag in the
estimate.
f) Cost and revenue shares of cost codes with the characteristic Inhouse work are not included in
the results.
WARNING
You should consider the following:
a) To ensure that your result is up-to-date, you should, if you are not sure, recalculate the margin
although values are already displayed on opening. To do so, click on the Update button.
b) If, however, fixed prices have already been entered into the BoQ before but the fixed price flag is
not set, then it could be that these fixed prices do not correspond to the latest state of the
estimate.
c) If, in such a state, you do not answer with Yes, but select No, then the margin is calculated
according to these "old" fixed prices, meaning that it will be incorrect. You should therefore
confirm with Yes if you are not sure.
Only when you are sure that there are no fixed prices in the BoQ - except for the items with the
fixed-price flag in the estimate - then you can answer No.
No matter whether you have chosen Yes or No, the margin is calculated and shown in updated
form.
03-2011
Estimate
87
Interface
In this table, you can estimate the DJC of the selected item on the basis of
subitem lines and detail lines. These lines can only be created at item level.
See also
Detailed item estimate [ 19]
Column estimate without individual details [ 20]
Column estimate with individual details [ 21]
Directly changing between estimate and BoQ [ 121]
Green colour
Red colour
You can control the colour labelling and the checkmark for items with cost details using the System
and User Options. This representation is only visible if the Estimated items function is activated in
Settings under Estimate.
88
Estimate
03-2011
Interface
See also
Switch between BoQs for estimate and bid [ 25]
Directly changing between estimate and BoQ [ 121]
See also
Directly changing between estimate and BoQ [ 121]
03-2011
Estimate
89
Interface
Bid total
in the Estimate Datatab for the entire estimate (BT)
BoQ totals
in the Estimate data tab at BoQ and division level (UR/IT).
Please observe the following:
a) The default settings under User Options define how the display options are suggested here.
b) The option setting defines on which quantity the total values (estimate data or totals) are based
(General - Totals view). If Calculation based on AQ Quantities in Bid Phase is activated, they are
taken as the basis here; otherwise it would be the BoQ quantities.
Please refer to the "System and User Options" documentation for more details.
See also
Setting the disabled flag in BoQ, division or item [ 125]
90
Estimate
03-2011
Interface
WARNING
Please note the following information:
a) A fixed price that has a fixed price flag in the estimate is not changed when the bid is printed.
When you set the fixed price flag, any prices in the BoQ are overwritten by the fixed price which
has been set in the estimate.
b) A fixed price that is available in the BoQ but has no fixed price flag is not included in the bid print;
the UR which is currently being calculated from the estimate is used instead.
Fixed prices lead to a deficit compared to the normal calculation. However, it makes allocation
possible and thus enables the fixed prices to be balanced with the calculated prices. In this case, the
total of the differences between the calculated UR and the fixed prices is regarded as already included
share of the FM that changes the share still to be allocated and leads to a different DCM.
03-2011
Estimate
91
Interface
that can be compensated for by the allocation. For more information, refer
to Fixed price (item type).
The item with the combined characteristic thus behaves like an item with fixed
price; it only does not generate a share of FMs (GA/RP/AM) of the item total.
Neither an advanced allocation (AA) nor a manual markup (MM) can be
entered in items without markup.
Lump Sum
If a lump sum is generated for an individual item, this function must be
activated. This means that the IT is billed on the basis of the BoQ quantity,
irrespective of which quantity is actually executed. In the bid phase, the
characteristic will hardly play a role; this characteristic only becomes important
in the case of the contract negotiation (phase 2) or the execution phase (phase
3).
You should consider the following:
a) If you have generated lump sums for a division or for the entire BoQ, then the lump sum is
important in the print of the bid. This total is assigned the addition lump sum. The ITs of the
subordinate items are rendered in brackets. Their total does not contribute to the bid total
anymore, but only the lump sum.
b) Starting from phase 2, the following principally applies to lump sum items:
Costs are always calculated with AQ quantities, whereas the revenue is always calculated
with the BoQ quantity, irrespective of whether the BoQ or AQ quantity is specified as the
quantity for analysis.
Fact.
Displays the factor which was entered for this item. This factor is taken into account
for the determination of the estimate result (DJC). If no value has been entered for
the factor in the BoQ, the statement Factor = 1.000 always applies.
The quantity factors are included in all calculations of the estimate, such as
allocation, determination of the margin, total job costs, cost and quantity analyses,
analysis of key items, determination of referenced values, collective BoQ.
Especially in the proof prints, the factor is treated as a quantity factor (is
computationally included in the quantity).
Existing factors are retained during a phase change of the project. Here too, the
total values are determined including the factors.
92
Estimate
03-2011
Interface
Result fields
The following applies to the entry and display:
left column
right column
The results of the cost estimate are displayed at the item level per unit of measure
(left column) and also for the quantity total (right column). Whether the BoQ or AQ
quantity is taken as the basis for the display of the quantity total depends on the
setting of the corresponding option. Entries are possible in individual fields.
DJC
Displays the result of the DJC for the item.
AA (Advanced Allocation)
Advanced allocation is a partial amount of the total GC.
If the GCs have been calculated, then partial amounts of them can specifically
be assigned to particular items in the form of the advanced allocations (AA). AA
is entered either as a value per unit of measure (left column) or as a value
related to the quantity total (right column). The respective different amount is
calculated. The amount can also have a negative sign so that GCs are
extracted from this item by calculation, irrespective of how much was actually
included by allocation. In the latter case, the total of the GCs to be allocated is
increased.
The allocation procedures calculate the total of the amounts that have entered
the items in this way and subtract the total AA from the calculated GC. Only the
remaining amount for GC is included in the allocation then. Items with AA
receive additional GC from the allocation.
WARNING
MM leads to a deficit or increased margin compared to the normal calculation.
MM+URD
MM (Manual Markup)
03-2011
Estimate
93
Interface
URD field.
URD with fixed price
An entered fixed price that deviates from the calculated UR leads to a
difference, which is displayed in the field URD (Unit Rate Difference.
rounded/UoM
80,93817
total
80,94
80.938,17
AA
94
Estimate
03-2011
Interface
GC
7,81609
7,82
7.816,09
FM
9,03721
9,04
9.037,21
URD
0,00000
0,01
1,47
UR/IT
97,79147
97,79
97.790,00
GC (General Conditions)
If area-wide allocation is used, separate direct cost markups (DJCs) for GC and
GA/RP/AM are transferred to the items (for details, see "Allocation"
documentation).
If simple allocation is used, then this field does not contain any value. In this case, a total DCM is
transferred to the items, which leads to the result in the FM field.
a) There is no value if the item has the No Markup characteristic.
b) With value if the item has the Fixed price + no markup characteristic.
FM (Final Markup)
The type of the allocation used determines which DCMs are processed here.
1-step allocation: DCM from GC + GA/RP/AM
2-step allocation: DCM from GA/RP/AM
You should consider the following:
a) There is no value if the item has the No Markup characteristic.
b) With value if the item has the Fixed price + no markup characteristic.
UR = DJC + AA + GC + FM + MM / URD
IT = UR x quantity
Further information on the allocation can be found in the "Allocation"
documentation.
2.3.2.2 Assignment
Here, you make assignments for the selected item.
WC
If the item has been assigned to a work category in the BoQ, the assignment is
displayed here. A modification can only be made in the BoQ (switch with <F9>)
(c) RIB Software AG
03-2011
Estimate
95
Interface
Bill-to parties
If the item has been assigned to a bill-to party in the BoQ, the assignment is
displayed here. A modification can only be made in the BoQ (switch with <F9>)
Location
Here, you can assign a location to the item (search with <F3>). Possible are e.g.:
1 Main building
2 Secondary building
3 Other
WIC
If the item has been generated on the basis of a work item catalog, the WIC no. is
shown here for identification.
CWT-Quantity Flag
This field is connected to the CWT. If the number of hours from the item is to be
included in the total no. of hours of the CWT, but the quantity of the item is not to
be included in the quantity of the CWT, then click in this field. You must know that,
in the analysis of CWTs with a unit of measure, a value Hrs./UoM is also created ,
which corresponds to the quotient of the total of hours divided by the quantity of the
work item. If the unit of measure of the item is not identical to the unit of measure of
the CWT, the program even automatically sets this characteristic by force without
the possibility of removing it later on.
96
Estimate
03-2011
Interface
Classification catalogs
If you have defined classification catalogs and made a corresponding assignment,
up to four classification catalogs are displayed here. For example:
DIN276 new
SAP
Here, you can store a classification each (search with <F3>).
2.3.2.3 Totals
Here, additional analysis results of the item are displayed:
The costs per UoM for each major cost code and their totals (DJC)
The costs for the quantity total of each major cost code and their total (DJC)
The distribution in percent of the costs to the major cost codes.
The number of hours per UoM.
The number of hours for the quantity total.
On which quantity the total values are based depends on the setting in the options
(Estimate - Settings). If the function View with AQ-Quantities is activated there,
they are taken as the basis here; otherwise it would be the BoQ quantities.
03-2011
Estimate
97
Interface
For information purposes, you can also display these contents in a separate window at subitem level
by pressing the function key <F7>.
2.3.2.4 UR Breakdown
Here, the UR breakdowns are displayed according to the defined UR breakdown.
You must have created the following preconditions for this:
1. In the basic BoQ data, you must have defined the UR breakdowns in UR
2.3.2.5 Markups
Here, an overview of the markups listed by their cost codes is given, resulting from
the active allocation.
Edit
If required, you can open the active allocation for editing using this button.
See also
Allocations [ 77]
98
Estimate
03-2011
Interface
The estimate table is based on the BoQ structure. The element selected in the
structure is displayed, and depending on the expanded state, so are the subelements. This means that the table for displaying the elements also takes the filter
of the BoQ structure into consideration. However, this filter is not taken into
consideration when determining the total values
(the filter in the program is a display filter, not a calculation filter!).
a) The estimate summary table is only used to display the values. Editing is not possible.
b) The estimate summary table is not automatically updated for performance reasons. Nor are the
elements displayed in the BoQ tree view synchronised automatically. The update is performed
automatically when the table is opened, after this the update can be performed by pressing the
<F5> key. The table can also be updated via the context menu (Update).
c) When performing an update (<F5>), take into account that further updates may take place
internally, which do not have to be performed every time (determination of referenced values,
etc.).
d) This view is not dependent on the column estimate!
e) Depending on the system option that is set, the BoQ or AQ quantity is displayed.
f) All results are then always calculated using the set quantity. Any number of MCOCs can be
displayed. The table, however, is not dynamic if an estimate is open (i.e. if the MCOCs change,
you must reopen the estimate).
g) Two columns are always displayed for surcharges:
GC and FM
FM contains the total from G&A, R+P and AM. Both columns are filled for a two-step
allocation. The GC column remains empty for a single-step allocation.GC and
FMFMG&AR+PAMGC
03-2011
Estimate
99
Interface
Unit rate
Item total
Currency
a) The values of the hours and MCOC columns are values per unit (therefore also excl. factor).
b) All of the values in the table are displayed in the estimate currency (therefore not in the CUR of
the MCOC, not in the BoQ-CUR). Potential BoQ factors are included in the totals columns.
c) No Austria specifics are taken into consideration for the costs. The costs are not subject to
rounding rules.
d) International projects are not considered either (no division into local and foreign currencies).
e) The IT (item total) is always the IT for the purpose of the estimate. It can deviate from the BoQ-IT
in phase 3 (for lump sums of a parent element). To this end, the overview table is designed for
phase 1 (no display of the revenue in phase 3).
In the following, you get an overview of the line types of the estimate.
Item estimate
Line of the item
Does not exist
Line of the subitems
A subitem line is generated if you enter a number in the Subitem column.
Individual detail
If you do not enter a number for a subitem in the Subitem column, then other
line types are created, the type of which is aligned to your input in Column F
(line flag). Pressing <F3> in this column allows you to display the Line Type
100
Estimate
03-2011
Interface
Flag window, in order to see which flags are available and/or to select the
desired line type.
03-2011
Estimate
101
Interface
To be successful with your estimate work, you should know how the program realises the following
topics:
a) Subitem structure of the estimate
b) Number system of the subitems
c) Numbering of the subitems
See also
Detailed item estimate [ 19]
Column estimate [ 20]
Subitem structure of the estimate [ 26]
Numbering system of the subitems [ 26]
Type
(empty)
CoC detail
Commodity detail
Assembly Summary
Assembly detail
Plant(Equipment) detail
Plant(Equipment)-difference detail
Text line
Computation line
Item copy
Same Item
For all detail lines and assemblies a remark field is available. The report Totel Job
102
Estimate
03-2011
Interface
If you are in a line of a subitem, a subitem of the next lowest level is created. Since the
column estimate only recoognises subitems of the 1st level, the command in the latter case
is actually carried out, but all lines of the subitem of the 1st level are hidden and you only see
the result in the subitem line of the 1st level. Editing the (detail) lines that are no longer
visible is now only possible in the view of the individual estimate.
See also
Create lines [ 106]
03-2011
Estimate
103
Without a BoQ, you can open the estimate but you cannot edit it.
Procedure
1. Create a new project.
2. Open the newly created project for editing.
3. Open the Project Alternatives.
4. Here, you first create or import the BoQ.
5. If necessary, create or import a BoQ for the General Costs.
6. In the Project Alternative, create the estimate document.
7. Open the estimate document for editing.
Create Estimate
1. Select the project alternative under which you want to create an estimate.
2. Click New | Estimate in the context menu or Home | New | Modules | Estimate.
Before you begin with the estimate work, relevant information for the estimate itself
must be stored. This is done by entering the properties of the estimate document.
104
Estimate
03-2011
03-2011
Estimate
105
, Global | System options, you can influence the program behaviour via
Estimate - Settings when creating lines (when using catalog elements and in the
type of result display).
For details on these settings, refer to the "System and User Options"
documentation.
Insert line
The program inserts a new line directly above the line the cursor is in. Alternatively,
you can use the key combination <Ctrl>+<I>.
Append line
The program appends a new line at the end of the estimate. Alternatively, you can
use the key combination <Ctrl>+<N>.
Next subitem
Place the cursor in an existing line.
Depending on the level in which the cursor is placed, the program appends a new
subitem line and labels it with the next higher number of the same level.
Alternatively, you can also use the key combination <Ctrl>+<U>.
See also
Insert subitem at the same level [ 107]
Detail lines of the estimate [ 102]
106
Estimate
03-2011
drag it below the lowest line, if it is to become a subitem of the first level. In the
positions where you want to copy, a plus sign ( ) is displayed.
3. Release the mouse button.
4. Verify the following confirmation query on the subitem.
The subitem is sorted in with its detail lines accordingly.
There are also toolbar buttons for copying and inserting under Home | Edit.
You have the following options for inserting estimate details before subitems, i.e. at
the same level as the subitem and not subordinated to the subitem:
Home | New | Paste on same level
Context menu command Insert At The Same Level
Additional use of the <Shift> key for drag & drop.
See also
Create lines [ 106]
03-2011
Estimate
107
drag it below the lowest line. In the positions where you want to copy, a plus
sign ( ) is displayed.
3. Release the mouse button.
4. Confirm the confirmation query on the cost code detail.
The line is appended as the last line of the subitem or as the last line of the
estimate.
There are also toolbar buttons for copying and inserting under Home | Edit.
108
Estimate
03-2011
You can use the function key <F11> for this purpose. If you recognise in a certain
line that you need exactly the value appearing directly above, simply press <F11>
instead of entering the value.
03-2011
Estimate
109
When searching for a Cost code, the Cost codes window appears. It makes
various functions available via Select or Search.
4. Via Project you can specify where you wish to search for the data. In the
catalog of the Master project or in the catalog of the current project.
In the case of a large catalog in the Master project, you are more likely to find results than in the
catalog of the current project. This is because the latter only contains the cost codes, which you have
reviewed in the project, assuming that you have copied the entire master catalog.
Parameters
Here, you are offered a selection of all defined parameters. Click on the desired
entry and confirm with OK.
110
Estimate
03-2011
In the Type column, you are shown the level at which this parameter was defined:
Type
Level
(empty)
Item
PA
Project Alternative
PRJ
Project
Object Model
Here, you are offered a selection of all system value from the object model.
Click on the desired entry in the Name column and confirm with OK.
Item
Here, you can select from the item-related parameters.
The item factor (from the BoQ) and the quantity parameters for the quantity types
_AQQuantity * 2
03-2011
Estimate
111
112
Estimate
03-2011
Clicking this button, you may define a filter setting for a commodity detail
line if desired. You may activate or deactivate it using the adjacent check
box.
If you activate a filter, the field Contains is switched to inactive.
The Code and the Description are copied into the corresponding fields of the detail
line.
See also
Syntax of the extended selection of catalog elements [ 113]
Extended BoQ selection [ 114]
Code
Meaning
1,2,4
2-
2-5
Range 2 - 5
2-5+
03-2011
Estimate
113
-5
>5
5<
<5
5>
Nothing
+5
5+
See also
Enhanced selection (catalog elements) [ 113]
114
Estimate
| Outline Spec
03-2011
Using this command, you have the option of searching for a certain outline spec
and jumping to this item in the BoQ structure.
1. In the Search dialog box enter the outline spec of the item, or a significant term
in the outline spec.
Activate Find whole word only if you are looking for this word only, and not
for text parts or combinations with other text.
Activate Upper case/lower case if your search should be case-sensitive.
Specify via Up or Down the direction of the search, based on the current
position.
2. Click Find next to start the search.
If the item jumped to is not the desired item, you can continue your search by
clicking this button again.
The most recent search text will be displayed when this function is called again.
If no outline spec is found, the item you are looking for may not be located in the direction of your
search, i.e. before or after the current item. In this case, repeat the search in the opposite direction.
| Reference Number
Using this command, you have the option of jumping to a certain reference number
in the BoQ structure.
1. Enter the desired reference No in the Goto to dialog box.
2. Click OK to carry out the switch to this reference number.
When entering the reference number, you will have to take the structure formating (number of digits)
into account.
03-2011
Estimate
115
Copying
6 Copying
Different functions are available for copying.
In addition, you can also define default settings for copying:
General copy options
, Global | System Options under Estimate in Copy Options
, User Defined | User Options under Estimate in Copy Options
Copy options in the case of detail lines with parameters
, Global | System Options under Estimate in Parameters.
, User Defined | User Options under Estimate in Parameters.
For details on these default settings, refer to the "System and User Options"
documentation.
See also
Copy, move and delete lines [ 106]
Window, the program assumes that you want to copy from the last selected source project.
If you want to change the source project before copying or add a new one, you must select the desired
template in the dropdown list or add a new template via
116
Estimate
03-2011
Copying
2. Click
to a new source project to the list of the projects. The Copy from
Window, the program assumes that you want to copy from the last selected source project.
If you want to change the source project before copying or add a new one, you must select the desired
template in the dropdown list or add a new template via
03-2011
Estimate
117
Copying
drag items onto items in the current estimate document or into the estimate
table, or
drag detail lines into the estimate table.
4. If you have finished the copy process, click View | Screen Configuration |
You can load a saved copy template configuration using this button.
You can save an added copy template in a configuration file using this button.
You can add a copy template using this button. The Copy from dialog box is
displayed for this purpose.
You can delete the selected copy template from the list with this button.
The functionality of this symbol button is also available in the context menu of the
list.
118
Estimate
03-2011
Copying
Structure/Selection list
In the structure the existing projects are displayed, in addition the existing
documents (BoQs, WICs adn estimates) of the selected project or project
alternative.
You can choose the selected document as the copy template by double-clicking or
by clicking OK. Multiple selection is possible.
Filter
You can use this button to display only those projects that have certain properties.
If you work on a BoQ of a client who always bids based on the same BoQ, for
instance, then you can set this client as the filter criterion so that only projects
already used for this client are displayed. If required, you can activate or deactivate
an active filter with the help of the corresponding checkbox.
Option settings for copying
"System and User Options":
03-2011
Estimate
119
Update estimate
7 Update estimate
View | General | Update
The estimate is completely updated.
This function has the following effects:
Updating of quantities and cost factors
Recalculation of referenced values
Updating of the filter (structure)
Display of the sums for the selected element
120
Estimate
03-2011
| Modules | BoQ
Home | Edit |
| Modules | Estimate
Using this commands you can switch directly between the estimate and the BoQ
and vice-versa (alternative: <F9> or BoQ and Estimate respectively in the context
menu).
The switch always takes place at the identical item of the estimate to the BoQ and
vice-versa.
If the cursor is in a box of a detail line, then this remains active on switching, as
long as no other item is highlighted in the BoQ.
If the cursor is placed within a detail line of the estimate, you may switch directly to
editing the catalog object used there.
03-2011
Estimate
121
122
Estimate
03-2011
1. Click View | View Options | Column configuration. The Configuration for the
03-2011
Estimate
123
Irrespective of this column configuration, a quantity column and a cost column can be opened for each
CoC in the estimate table itself.
Depending on the type of cost code, the following will then apply there:
a) Labour cost code
If the selected cost codes do not include all the major cost codes, a column not assigned is
automatically opened in the alternative with individual details, in which the program writes the
cost results from all individual details that do not belong to the concretely defined columns.
124
Estimate
03-2011
from target).
5. In addition, you can activate neutralised cost risk.
In this case, the details of this subitem are not included in the result of the
estimate. The calculated values of the fields Hrs./UoM item and Costs/UoM
item are hidden in the subitem line; they are retained in the detail lines,
however.
Alternatively, you can activate Disabled. In this case, the results of the detail lines are set to zero.
Disabled subitems are not considered in the scope of (standard) evaluations.
See also
Cost details with risk characteristics [ 38]
Item Type.
03-2011
Estimate
125
In this case, the details of this element are not included in the result of the
estimate. The calculated values of the IT field are hidden in the Estimate Data tab,
and in the DJC field, the value zero is displayed for the total values in the BoQ and
division.
1. Select the desired subitem line or one of the associated detail lines in the
estimate table.
2. Click Subitem properties in the context menu (alternative: <Strg>+<E>).
3. Now activateDisabled in Additions.
In this case, the details of this subitem are not included in the result of the estimate.
The calculated values of the fields Hrs./UoM item and Costs/UoM item are set to
zero in the subitem line and in the detail lines.
126
Estimate
03-2011
The columns in the collective BoQ can be set with the help of the stored table configuration.
03-2011
Estimate
127
128
Estimate
03-2011
down reference is only active if "Same item assembly detail" is activated in the
estimate table (line type P). In the Collective BoQ window, it applies to the lines
of the referenced items (flag B). After confirmation, the reference to the
corresponding item is omitted. The detail lines of the reference assembly are
copied into the current item. This item is independent now and has no relation
to the reference item any more. Its estimate can be changed without any
effects on other items.
Open assembly
Using this function, you can change from the reference item directly into the
assembly edit mode of the coupled assembly.
If all the references to an item (reference assembly) are deleted, then this assembly is automatically
flagged as a "normal" assembly.
See also
Reference items (Same-As items) [ 59]
Display Collective WBS [ 127]
03-2011
Estimate
129
Assemblies
14 Assemblies
14.1 Generating an assembly
Enhanced | Specialities | Assemblies | Generate Assembly
Assemblies can be generated from often used or periodic detail lines and stored in
the Assemblies catalogue.
a) Generating is only possible for items as well as surcharge items with details and they must not be
reference items.
b) It is checked before conversion wether the action can be done without loss, if not, a notification is
given.
c) In the Execution phase also the budget of the detail lines is taken.
Generating an assembly
1. Define the source of the assembly by selecting the desired estimate detail
lines.
2. Click Advanced | Assemblies | Generate Assembly. The Generate Assembly
dialog box appears.
3. Expand the Assembly Category structure.
4. Select the desired assembly categorie in structure. If required, you can create a
new (sub-)catogory via the context menu. You must enter a description. The
catogory code is generated automatically.
5. If required, you can edit the assembly code genrated from the category code.
6. The text of the sub item line (in Description) is suggested as description of the
assembly. You can now replace or modify this text.
7. Click OK to generate the assembly.
The assembly is created in the catalog Assembly and the selected estimate detail
lines are replaced by the assembly.
a) If the Assembly-Code value was modified, this code is maintained when changing the
(sub-)category and will no longer be created automatically.
b) In phase Execution the budget of the detail lines is adopted.
130
Estimate
03-2011
Assemblies
vary the content of the assembly in an item-specific way, you may also start the
breaking-down (copying of all detail lines of the assembly into the item) later.
WARNING
A broken-down assembly is no longer an assembly, i.e. the estimate lines of the work items have lost
their reference to the assembly. Any belated modification to the assembly causes no change to the
detail lines of the broken-down assembly in the estimate of the work items.
Details.
A query regarding the insertion of the assembly details is shown.
3. Answer this query with Yes.
The program always turns a broken down assembly into a subitem. The way in
which this subitem is inserted into the existing structure is dependent on the item of
the U line:
If the line is not subordinate to a subitem, then a 1st level subitem is created. If
the line is subordinate to a subitem, then a subitem is created for this subitem.
If the assembly already had subitems, then these are maintained beneath the
new subitem of the estimate.
Take the following into account:
a) If the Break down function is not activated for the assembly in the Assemblies catalog, then the
assembly cannot be broken down.
b) If an assembly which contains a variable is dismantled in an item and if this assembly contains a
variable, the value of which deviates from the value of the same variable in the item, then the
quantity detail is not copied from the assembly to the item, but the result is written in the quantity
field of the detail line, so that the copy of the line in the result still matches the line from the
assembly.
See also
Assembly details [ 55]
03-2011
Estimate
131
Generate
15 Generate
15.1 Generate an estimate inside the BoQ
Actions | Generate | within actual BoQ | Generate from estimated BoQ
If, in the current project, you have already created estimate details for the item(s) to
be generated, you can generate an estimate on the basis of this template.
Generate BoQ
1. In the BoQ structure of the estimate, select the item or the division with the
items to be estimated.
2. Click Actions | Generate | within actual BoQ | Generate from estimated BoQ.
The Generate estimate by retrieval dialog box appears.
3. Click Serach in Source, division.
If you have already generated an estimate, the last selected source is
displayed here.
4. InSelect BoQ level , first define the source in the tree.
5. Then select the BoQ which is available there and which you want to use.
6. Click OK. The source is adopted.
7. Now, define the BoQ area in Target estimate. To do this, you can either enter
the appropriate values or click Search to define them in the BoQ area selection
dialog box.
8. If required, define the desired options settings in Comparison with respect to.
You can further limit them using the corresponding functions, if necessary.
9. In Generate, define the procedure for generation.
To be able to access Replace already existing estimate details, you must first
deactivate Items without any already existing details only.
Specify here also whether the retrieval uses reference items or item copies.
10. When you have made all required settings, click Generate in order to start the
procedure.
The estimate is generated for the selected items.
See also
Generating an estimate [ 46]
132
Estimate
03-2011
Generate
Generate BoQ
1. In the BoQ structure of the estimate, select the item or the division with the
items to be estimated.
2. Click Actions | Generate | from external BoQ | Generate from estimated BoQ.
First, the Generate estimate dialog box appears.
3. Click Search in Source, estimated BoQ. If you have already generated an
estimate, the last selected source project is displayed here.
4. In Estimates source BoQ selection, first define the source project in structure. If
required, you can define a filter for selecting the source project.
5. Then select the BoQ which is available there and which you want to use.
6. Click OK. The dialog box closes and the source project is adopted.
7. Now, define the BoQ area in Target estimate. To do this, you can either enter
the appropriate values or click Search to define them in the BoQ area selection
dialog box.
8. If required, define the desired options settings in Comparison with respect to.
You can further limit them using the corresponding functions, if necessary.
9. In Generate, define the procedure for generation. To be able to access
Replace already existing estimate details, you must first deactivate Items
without any already existing details only.
10. When you have made all required settings, click Generate in order to start the
procedure.
The estimate is generated for the selected items.
See also
Generating an estimate [ 46]
03-2011
Estimate
133
Generate
If, in another project, you have already created estimate details for the item(s) to be
generated, you can generate an estimate on the basis of this template.
you
can delete an existing entry here (and also in the other fields). The Select
Source elements group, the information is displayed that the copies are
generated from a Bid estimate for instance.
7. Now, first define the estimated item to be used as the source. To do this, click
. The Select item dialog box appears.
If required, you can define a filter for selection.
8. Open the the structure down to item level and select the desired source item.
9. Click Copy & Close to copy the item.
10. Then, define the elements to be included:
Cost codes (click
to select)
Commodities (click
Assemblies (click
to select)
to select)
to select)
to select)
For all elements, you can display the dialog box Enhanced Selection for a
complex element selection via the adjacent toolbar icon. Alternatively, you
can search for and select an individual object in the entry field by pressing
<F3>.
11. Finally, define the BoQ area in Target area.
134
Estimate
03-2011
Generate
By pressing <F3> in the dialog box Select item, you can define the
respective values in the fields From and To for an individual BoQ area.
By clicking
, you can also define multiple target areas in the BoQ area
to open the Options dialog box. Make the desired settings regarding
).
14. When you have made all required settings, click Applyin order to start the
procedure.
The estimate is generated for the selected items (target areas).
See also
Distributing estimate details [ 47]
03-2011
Estimate
135
Individual items created with text elements from the German STLBBau
1. Open the estimate.
2. Highlight the item to be estimated.
3. Click Content | External | Germ. DBD estimate details | For currrent item or in
the context menu Germ. DBD estimate details for currrent item.
The elements used to create the text are displayed in the German DBD data
window, which then opens automatically.
4. Click OK to copy the corresponding estimate data under cost codes to the
estimate.
16.2 German DBD estimate item not with German STLBBau text elements
Content | External | Germ. DBD estimate details | for current item
Individual items not with text elements from the German STLB-Bau
1. Open the estimate.
2. Highlight the item to be estimated.
136
Estimate
03-2011
3. Click Content | External | Germ. DBD estimate details | for current item or in
context menu Germ. DBD estimate details for current item.
The work categories are displayed in the German DBD data window, which
then opens automatically.
4. Select the work category.
5. Proceed step-by-step up to the appropriate work item or its text elements.
6. Select the desired entry.
7. Confirm the selection.
The corresponding estimate data under cost codes is copied to the estimate.
In the context menu, you can also find the Modify current German DBD subitem command.
You can use this command to restart access from a highlighted subitem in accordance with the above
descriptions, in order to modify the existing estimate. The existing subitem is replaced completely
according to the new selection.
03-2011
Estimate
137
138
Estimate
03-2011
03-2011
Estimate
139
Code
Description
Quantity
UoM
Factor
Cost/Unit
m
1
Auxiliary labour
1,000
hours
CC
1121
Magaziner
CC
1122
Electrician
CC
1123
Locksmith
CC
1124
Surveyors
30.705,776
30.705,776
30.705,776
30.705,776
PSCH
Hrs.
Hrs.
Hrs.
Hrs.
Hrs./UoM
Cost/UoM
item
item
1,000
67.552,72
1.228,231
67.552,72
0,020
55,00
614,116
33.776,36
0,010
55,00
307,058
16.888,18
0,006
55,00
184,235
10.132,91
0,004
55,00
1222,823
6.755,27
Legend
1
Flag
Derived CoC
Referenced quantity
Estimate detail
140
Estimate
03-2011
2. Click Advanced | Data update | Update referenced values and click Yes in the
query.
Quantity displays the referenced quantity from the reference cost code of
the derived CoC, if the derived CoC is of the type Labour cost code or Cost
0.040, i.e. 4% of the total labour hours are auxiliary labour hours, 96% of the total
labour hours (= valueRED) are production hours. hours.
See also
Estimation with referenced costs (derived cost codes) [ 139]
Estimate with derived cost codes [ 57]
Code
Description
Quantity
UoM
Factor
Costs/Unit
Costs/UoM
Item
Insurance costs
MED 681
1.000
LSUM
1.000
54,158.41
54,158.41
1.000
0.010
5,415,840.52
54,158.41
Insurance costs
Legend
1 Subitem line:
considered results case in this item
2 Estimate detail
3 Referenced costs
03-2011
Estimate
141
Insurance Costs)
The following information is displayed:
By selecting the derived cost code, the program creates the flag MED =
derived. CoC with regard to Total Job Costs
In Quantity of the subitem line (considered results case of item), the value
is 1.000.
In Quantity of detail line (detail of referenced costs), the value is 1.000.
In Factor, the value is (for the time being) 0.000.
In Costs/Unit, the value is (for the time being) 0.000, since the derived CoC
Without Fixed UR has been defined with regards to the Total Job Costs.
2. Click on Advanced | Data Update | Update Referenced Values and confirm the
inquiry with Yes.
In Costs/Unit, the referenced total job costs are displayed as the reference
cost code of the derived CoC.
The value does not change in Quantity, it stays at 1.000.
The value does not change in Factor, it stays at 0.000.
3. Enter the actual insurance costs in Factor. If they represent 1% of the total job
costs, replace the value 0.000 with the factor 0.010.
Referenced costs
In Costs/Unit, the program incorporates the costs of the cost code, which is
identified as the reference cost code for the derived CoC. The prerequisite is
that the derived CoC is Without Fixed UR; otherwise you will find the UR of the
derived CoC.
For the reference parameters Total Job Costs or Tender Total, the respective amount is displayed
here.
See also
Estimation with referenced costs (derived cost codes) [ 139]
Estimate with derived cost codes [ 57]
142
Estimate
03-2011
03-2011
Estimate
143
to change the BoQ area. The Extended BoQ Selection dialog box is
displayed.
If required, you can also select (
) or define (
) a filter.
The following working steps refer to the change of the quantity factor in the
estimate, but they also apply generally for the remaining change functions for
factors.
144
Estimate
03-2011
By default, the currenty marked element in the BoQ structure is adopted for the
) or define (
) a filter.
03-2011
Estimate
145
to change the BoQ Area. The Extended BoQ Selection dialog box is
Click
displayed.
If required, you can also select (
) or define a filter (
).
<F3> or
6. Enter the cost code to be replaced in Replace with. You can search with <F3>
.
or
The following working steps refer to the deletion of a Cost code in the estimate, but
they also apply generally for the remaining deletion functions for estimate
elements.
By default, the currenty marked element in the BoQ structure is adopted for the
to change the BoQ area. The Extended BoQ Selection dialog box is
displayed.
If required, you can also select (
) or define a filter (
).
146
Estimate
03-2011
4. Click Delete Cost Codeif, for example, you want to delete a certain CoC in a
certain range of the estimate.
5. Enter the cost code to be deleted in Elements. In this field, you can search for
an individual cost code with <F3>, or click
Selection dialog box and select from multiple cost codes or particular cost
code ranges.
6. Click Apply to carry out the change.
The following work steps refer to the updating of criteria assignments using
catalogs for a Cost Code in the estimate, but they also apply correspondingly for
the remaining updating functions for estimate elements.
By default, the currenty marked element in the BoQ structure is adopted for the
to change the BoQ area. The Extended BoQ Selection dialog box is
displayed,
If required, you can also select (
) or define (
) a filter.
03-2011
Estimate
147
4. Click Update Cost Code Criteria Assignment from Catalogif, for example, you
want to update a certain assignment in a specific range of the estimate.
5. Activate or deactivate the required settings for updating the criteria assignment
in Options. If required, activate Modify Reference Items in Options, if you also
want to change them. Click
to open the
Enhanced Selection dialog box and select from multiple cost codes or
particular cost code ranges.
7. Click Apply to carry out the change.
See also
Modification functions [ 45]
to change the BoQ Area. The Extended BoQ Selection dialog box is
displayed.
If required, you can also select (
) or define (
) a filter.
148
Estimate
03-2011
By default, the currenty marked element in the BoQ structure is adopted for the
to change the BoQ Area. The Extended BoQ Selection dialog box is
displayed.
If required, you can also select (
) or define (
) a filter.
The following work steps refer to cost or price changes in the estimate.
By default, the currenty marked element in the BoQ structure is adopted for the
to change the BoQ area. The Extended BoQ Selection dialog box is
displayed.
If required, you can also select (
) or define (
)a filter.
03-2011
Estimate
149
to change the BoQ area. The Extended BoQ Selection dialog box is
displayed.
If required, you can also select (
) or define (
) a filter.
150
Estimate
03-2011
Range selection
The range is specified using the BoQ and the ref. number as a from/to range.
Generate
For the generation, you can make settings for prices and quantities.
For the prices, the following are available as base URs for the modification:
Only estimated prices
Only agreed prices
Agreed/estimated prices
Only handover prices
You can use a factor to specify the destination UR for the selected base UR. The
following are available:
Agreed prices
Handover prices
If necessary, you can also specify a factor for the AQ quantity which calculates the
new AQ quantity value on the basis of the BoQ quantity.
For generation, you can also specify that the prices of the generated destination
URs are overwritten and also that a comment is added.
Reset
Besides the generation of target URs, you can also reset already modified
destination URs depending on the selected BoQ range.
Here, you can make the following settings:
Delete agreed prices
Delete handover prices
Reset AQ quantities to BoQ quantities
a) When switching to the execution phase, the AQ quantity is saved as the original AQ quantity (the
same as for the original DJC), so that a comparison can be made between the assumed AQ
quantity in the bid phase and the actual AQ quantity (prognosis quantity) in the execution phase.
b) Discounts in the BoQ are not taken into account.
03-2011
Estimate
151
By default, the currenty marked element in the BoQ structure is adopted for the
BoQ Areas
Clicken
box is displayed. (
You can alternatively search the respective Ref. No. under From or To in
the corresponding entry field by pressing <F3>. The Select item dialog box
appears for selection. In the case of a modification of the BoQ area, you
must update the display under Current amount using the Analyse button.
Cost codes
Select in Cost codes the desired criterion.
By clicking on the adjacent symbol button, the Extended selection dialog
box is displayed. (
search for a corresponding object under From and To, respectively, in the
associated input field using <F3>.
Filter Assignements
By clicking on the adjacent symbol button, the Extended selection dialog
box is displayed. (
search for a corresponding object under From and To, respectively, in the
associated input field using <F3>.
3. Define the desired settings in Modification:
152
Estimate
03-2011
Analysis with
Selcet BQ-Quantity or AQ-Quantity here.
Modify via
Select Cost Factor Detail or QTO-Detail here.
Options
If you click
4. Now click Evaluate to determine the value of the defined selection in Actual
Amount. Displayed are Costs and Hours for the selection and for the whole
estimate.
If you have made a modification in Selection, Filter Assignements or for the
quantity, you should also click Analyse in order to update the values in the
Actual Amount.
5. Now, you can proceed differently:
Entering a percentage for the modification of the current amount for the
selection
Entering a percentage or absolute value for the modification of the total
value
When you quit the entry field, the other fields are updated depending on the
entered value and the value in New changed amount is calculated.
6. If all the settings are correct, click Apply to initiate the DJC modification.
7. Enter a comment in the (protocol) Modify DJC dialog box so that the cause of
the modification can be understood at a later point in time.
8. If you click OK, the DJC modification is applied.
See also
Modification functions [ 45]
Print modifications log [ 169]
03-2011
Estimate
153
Create bid
21 Create bid
You have two options to create a bid:
1. Printing of the bid BoQ
2. Export of the bid BoQ (export to a file)
154
Estimate
03-2011
Create bid
03-2011
Estimate
155
Create bid
156
Estimate
03-2011
Create bid
03-2011
Estimate
157
Original DJCs).
7. Click OK.
The program creates a read-only copy of the existing project alternative and
renames the new estimate document to 'Contract Estimate' (Phase 2) or 'Execution
Estimate' (Phase 3).
158
Estimate
03-2011
Current phase
Here, the current project phase is displayed (Bid or Contract).
Destination phase
In this drop-down list, you can select the desired destination phase.
If the project is in phase 1 (bid), a change to phase 2 (contract) is
suggested. You may also change directly to phase 3 (execution).
If the project is in phase 2, only a change to phase 3 is possible.
AQ-Quantities
If non-standard items have an AQ which is not equal to 0.000, they are included in
the respective previews of the project both with costs and with revenue. Thus, an
assessment has to be made at any phase change concerning the probability of
non-standard items being executed. This assessment takes place - in the same
way as for standard items - via the AQ quantities. Whereas the assessment of the
AQs can only be done individually for standard items, a general assessment is
often possible for the non-standard items, since it is very uncertain - at least initially
- whether they will be executed at all. You will therefore frequently decide during
the phase change that the AQs of the non-standard items should first be generally
set to 0.000. A decision can be made during the phase change so that this does
not have to be done individually in fine detail.
You can set defaults in the System Options in order to decide with which standard
default for treating the AQs of the non-standard items the program is supposed to
carry out the phase change.
For details on these settings, refer to the "The Basics" and "System and User
Options" documentations.
See also
Change project phase [ 158]
03-2011
Estimate
159
160
Estimate
03-2011
Reports
As soon as you have specified a Favourite and/or a User directory in the global
03-2011
Estimate
161
report type to the Favourites folder. This way, you can collect the various
reports that you require regularly in the Favourites folder.
Packages
This folder contains all print packages.
Select the required report type. All further actions then refer to this report type.
Print
You start the printing process.
Cancel
You terminate printing.
Options
Printing Options opened.
Printer
The Windows dialog box for the Printer Settings is opened.
Report Phases
You specify the phase in which the selected reports are available.
This button is only available in the defaults of Print Options. The Print - Defaults
dialog box appears. Select a report and click Defaults. The Print dialog box opens
and makes the Report Phases function available to you.
Layout
You can swap the layouts of all report types very easily. This is very useful if you
would like to swap the provided layouts and use your own layouts which already
have headers and footnotes as well as your own company logo.
This function is only available in the Defaults inPrint Options in the main window.
Preview
You can select whether the data is printed without a print preview or if a print
preview should be shown.
Start values
This setting is useful for printing individual date settings or to print applications after
amendment again.
162
Estimate
03-2011
Date/Time
The input field is set with the current date as default. It is printed in the
document header with the month written out. The time does not appear in the
printout, it is only for information.
Page Numbering
Enter the page number of the first page into the input field.
Both the following functions are only active when a few requirements are fulfilled:
System Options, General | Display | Settings, Extended Filter Options in Print
Item/Division).
If no selection has been made there, or if a non-existant report has been specified, a
corresponding notification will be displayed.
c) If you have also activated Direct Print in the System Options, the screen view is omitted as well.
Print item/division
1. Open the estimate document if it is not already open.
2. Select the desired division/item.
3. >Click Item/Print Division in tn the context menu.
The print result depends on the currently selected entry in the BoQ structure:
Item selected
Only this single item is printed.
Division selected
03-2011
Estimate
163
164
Estimate
03-2011
Eine Besonderheit in den Druckoptionen ist hier, dass Sie entscheiden knnen, ob Nachkommastellen
der Betrge unterdrckt werden sollen.
Print | Print.
The print options themselves correspond to those of the BoQ printout. A filter is set
in the print options settings (in LV3) that takes all the items with this characteristic
into account.
03-2011
Estimate
165
6. Click Print.
This printout is displayed on the screen.
You then initiate the actual output on printer by clicking Application-Button | Print |
Print.
For more detailed information regarding Cover sheet, BoQ1, BoQ2, BoQ3, Sorting and Print range,
refer to the "Enquiry" documentation.
Information on Templates and Format composites can be found in the "Basic Knowledge"
documentation.
See also
UFS-Sheet [ 81]
166
Estimate
03-2011
03-2011
Estimate
167
168
Estimate
03-2011
See also
Sorting [ 216]
Key Item Settings [ 195]
Key items [ 172]
03-2011
Estimate
169
See also
BoQ Areas [ 209]
Check report [ 171]
Document [ 193]
See also
BoQ Areas [ 209]
24.2 Reports
For the estimate document, two report folders are available:
Controlling
Here, analysis reports with respect to CWT and quantity comparison reports
(BoQ quantity, AQ and BQ) are available.
Estimate
Here, various reports for the analysis of estimate-specific data are available
(e.g. analysis, total job costs, proofs).
For all reports, various settings for the printout may be customised via the Print
Options.
170
Estimate
03-2011
Analysis
Commodity analysis
Assembly analysis
UFS sheets VHB2001
UFS sheets VHB2002
Purchase report
Plant assembly analysis
Total job costs
Total job costs, all currencies
Proofs
Price adjustment
Column estimate (report type)
See also
Purchase list (Commodity) [ 173]
Special analysis functions [ 69]
24.2.1.1 Analysis
The sub-folder Analysis provides the following report types:
Margin analysis
Check report
Key items
The individual folders contain reports of the same name.
03-2011
Estimate
171
172
Estimate
03-2011
evaluation list.
See also
Quantities [ 210]
Non-standard Items [ 215]
Catalog object range selection (CWT, evaluations) [ 192]
BoQ Areas [ 209]
Currency [ 218]
Filter [ 196]
03-2011
Estimate
173
evaluation list.
The specifications for the Assembly range are made in the same way as for
specifiying a commodity range.
See also
Quantities [ 210]
BoQ Areas [ 209]
Currency [ 218]
Filter [ 196]
Catalog object range selection (CWT, evaluations) [ 192]
Sheet1b).
In UFS Sheet 2, only the items with the characteristic 'UR Breakdown' will be
output in the form of the BoQ print.
See also the "Settings" documentation.
See also
UFS-Sheet [ 81]
24.2.1.4.1
A crew mix
174
Estimate
03-2011
UFS sheets
G&A, R+P and additional markups can be defined for
No no-markup items
No allocation sections
No allocation alternatives
No lump sums
No discounts
(mixed)
prices during estimate via tender total). The same algorithms are used for the
calculation sheet VHB221 (Determination of prices during estimate via estimate
Crew mix
20.00
Social expenditure as % of CM
98.00
23.82
Miscellaneous as % of CM
2.00
03-2011
Estimate
175
2.1
125,487.87
176
Estimate
03-2011
100.00
100,000.00
AA
0.00
0.00
GC
0.00
0.00
FM
11.11
11,111.11
0.00
-1.11
111.11
111,110.00
MC+URD
UR/IT
The allocation is defined from 8 % G&A and 2 % R+P; which produces 11.1111
with mutual surcharges
The costs and markups are calculated accurately. The UR however must be
rounded to 2 decimal places.
The IT is calculated with the rounded UR * quantity. This produces a rounding
difference of EUR -1.11.
Example 2: Rounding difference through performance factors
DJC
AA
15.00
15,001.50
0.00
0.00
0.0
0.00
0.00
-1.50
15.00
15,000.00
GC
FM
MC+URD
UR/IT
Estimate detail
Quantity
UoM
1.000
m3
03-2011
Factor
Costs/Unit
CUR
Costs/UoM Item
1.000
15.00
EUR
15.00
Estimate
177
Quantity
UoM
1.000
Factor
Costs/Unit
CUR
Costs/UoM Item
6.666
100
EUR
15.00
evaluation list.
The specifications for the Plant assembly range and the Plant list range are made
in the same way as for specifiying a commodity range.
See also
Quantities [ 210]
BoQ Areas [ 209]
Currency [ 218]
178
Estimate
03-2011
Filter [ 196]
Catalog object range selection (CWT, evaluations) [ 192]
03-2011
Estimate
179
Quantities [ 210]
Cost Code Structure [ 198]
Catalog Objects' Range Selection [ 190]
Values [ 220]
Additions [ 221]
Ref. No. Format [ 213]
Currency [ 218]
Item | Print Division, if this has been set as a template in the system options under
Estimate - Print from BoQ Structure.
See also
Bid estimate (list type) [ 179]
180
Estimate
03-2011
See also
Quantities [ 210]
Cost Code Structure [ 198]
Catalog Objects' Range Selection [ 190]
BoQ Areas [ 209]
Currency [ 218]
Filter [ 196]
Total Job Costs [ 179]
List configuation - Total Job Costs [ 199]
03-2011
Estimate
181
1 Code
Description
Total costs in
Costs in
Costs in
Costs in
Costs in
Costs in
Misc.
EUR
EUR
DEM
DKK
CAD
IEP
EUR
2
3
Labour (wage)
Material
Plants
123.456
50.499
234.233
143.000
340.555
210.342
40.000
30.000
Subcontracted
services
Daywork
30.000
54.232
23.500
133.000
45.000
145.544
11.000
12.000
22.033
14.000
23.555
10.000
Misc.
30.000
Total
768.244
10.000
11.000
433.841
94.232
302.044
56.000
26.000
66.588
1,00000
1,95593
7,43280
1,55380
0,787756
1,00000
433.841
48.178
40.637
36.041
33.013
66.588
10
11
Exchange rate
12
Total in EUR
768.244
Columns
Column A
Column B
Column C
Total costs in the selected analysis evaluation (most often project currency)
Column D - H
Column I
Total costs from the currencies 6 to X. These are shown in the same currency as
in column 3.
Exception: there are exactly 6 currencies. If this is the case, the costs in this
currency can be printed directly
182
Estimate
03-2011
Lines
Line 2:
Line 9:
Line 12:
24.2.1.9 Proofs
Different report types are available for the proof of the elements used in the
estimate.
The folder Proofs is structured into sub-folders corresponding to the description of
the report. The following proof reports are available:
Commodity proofs
Assembly proofs
Plant assembly proof
Cost code proof
Parameter proof
Since the print options for the individual proofs are very similar, the estimate-relevant will be discussed
for the commodity proof. This description will then be referenced for all other report types.
evaluation list.
See also
BoQ Areas [ 209]
Currency [ 218]
Filter [ 196]
Quantities [ 210]
Catalog Objects' Range Selection [ 190]
03-2011
Estimate
183
184
Estimate
03-2011
evaluation list.
However, the list only prints out costs as standard; the additional list with the budget placeholders
must be made individually.
See also
Currency [ 218]
Filter [ 196]
BoQ Areas [ 209]
Catalog Objects' Range Selection [ 190]
Quantities [ 210]
evaluation list.
See also
BoQ Areas [ 209]
Filter [ 196]
Catalog Objects' Range Selection [ 190]
Quantities [ 210]
03-2011
Estimate
185
186
Estimate
03-2011
03-2011
Estimate
187
188
Estimate
03-2011
24.3.1 General
03-2011
Estimate
189
This print option is available in conjunction with the following reports in the Controlling - Quantity list
folder:
a) Quantity comparison list BoQ quantity/BQ quantity
b) Quantity comparison list BoQ quantity to AQ quantity
c) Quantity comparison list AQ quantity to IQ quantity
required function.
Activating this function recalculates the margin.
Print subitems
Level with input flag
All the items and subitems are printed.
To level
All the items and subitems up to this input level (reporting level) are printed,
depending on the input level.
The option settings for the subitems are not taken into account in the standard list formats for quantity
comparisons. If you also want to print subitems, then you must meet the following preconditions:
a) Create a new list on the basis of the existing template (copy of the DVL file).
b) Insertion of the appropriate placeholder for the subitem format composites using the "Report
Writer" module.
c) Activate the Subitem quantity list (Contract BoQ) function in Format assemblies of the print
options
d) Assignment of the new template in Templates of the print options.
e) If you wish to use the modified template permanently, then you must save these modifications to
the Print Options.
See also
Quantity report [ 188]
190
Estimate
03-2011
Assembly, Plant assembly, Parameter) refers to different catalogs. The name then corresponds to the
appropriate catalog object for the area selection. For example Commodity range for a range of the
Commodity catalogue.
Code
Input field for the code of the catalog object or the group. If you enter a value and
exit the field by pressing the <Tab> key, then this (existing) code is automatically
transferred to the Selection list.
Browse
This button displays the appropriate dialog box for the selection or search of
catalog element.
If you specify a higher-level catalog element (e.g. CoC) via Find, then this and and its subordinate
elements are transferred to the selection list.
>>
Use this button to transfer the selected element to the Selection list. Any
subordinate elements are not transferred.
All >>
Use this button to transfer the selected element and any subordinate elements to
the Selection list.
<<
This button removes the element selected in the Selection list from the list.
<< All
This button removes all the elements in the Selection list from the list.
Selection
The catalgoue elements to be selected are displayed in this list.
03-2011
Estimate
191
See also
Cost code evaluation (list type) [ 180]
Bid estimate (list type) [ 179]
Purchase list (cost codes) [ 178]
Commodity proof [ 183]
Assembly proofs [ 184]
Plant assembly proof [ 184]
Cost code proof [ 184]
Parameter proof [ 185]
Depending on the selected report type, the selection of the required object (CWT, Commodities,
Assembly, Plant Assembly) refers to different catalogs. The name then corresponds to the
appropriate catalog object for the area selection. For example Commodity range for a range of
the Commodity catalogue.
From
Use this button to apply the selected catalog object as the start of the range.
To
Use this button to apply the selected catalog object as the end of the range. For
information purposes, the description and the code of the selected element are
displayed.
Undo
Use this button to undo any previously made selections.
192
Estimate
03-2011
See also
Job List [ 187]
CWT analysis [ 187]
Commodity evaluation (report type) [ 172]
Assembly Evaluation [ 173]
Plant Assembly Evaluation [ 178]
24.3.4 Document
Here, you can specify the BoQ range and the periods for the quantity comparison
list.
Periods
BP / RP
Use the drop-down lists to specify the start and the end for the desired billing and
reporting periods.
Tree
Here, select the required entry for the start and end of the BoQ range.
From/To (buttons)
Here, transfer the selected entry in the tree for the start and end of the BoQ range.
See also
Quantity report [ 188]
Specify a BoQ range for the check report [ 169]
03-2011
Estimate
193
If you activate this option, all the items will be selected which are less than the
input percentage value. Based on the following calculation:(Revenue -
Stated Amount.
This has nothing to do with "poor", on the contrary: It concerns key margin
items.
Evaluate with
BoQ quantity
AQ quantity
Here, select the quantity to be used as a basis for evaluation.
If there are items with an AQ quantity 0.00, then these are evaluated as items with a poor margin, as
they do not produce a margin on account of their missing quantity.
See also
Sorting [ 216]
Margin analysis [ 171]
194
Estimate
03-2011
Conditions
Here, you can specify according to which criteria your estimate should be
searched. You can specify conditions for:
Items
Subitems
Other details
Here, you can activate or deactivate the appropriate options for the check
report.
See also
Check report [ 171]
Sorting [ 216]
Print check list with a print range definition [ 167]
Print check list [ 167]
Condition
You can choose among the following conditions for the selection:
The n largest BoQ items
If, for example, you enter 5 here, then the five most important items are
selected.
Items, whose prices exceed ... ...
All the items are selected whose IT or TJC exceed the specified amount. The
default currency is the estimate currency.
Items, whose prices exceed ... % portion
All the items are selected whose It or TJC exceed the specified % portion of the
total.
Items, whose price totals exceed ... % portion
The most important items are output, whose IT or TJC totals together reach the
% portion of the total.
03-2011
Estimate
195
Depending on the selection of the Grand total, the text Prices or Price totals for these option buttons
in Costs or Cost totals.
Grand total
Here, you can specify the total type for the selection and weighting and can select
between Bid total and Total job costs. The selection of this division type influences
the text contents for the condition options (Price becomes Costs and vice-versa).
Bid total
If this function is activated, the IT of the items is weighted in a ratio to the bid
total.
Total Job Costs
If this function is selected, the TJC of the items is weighted in a ratio to the total
job costs.
Evaluation Quantity
BoQ quantity
AQ quantity
Select the required base for evaluation quantity.
Non-standard Items
With or without inclusion of the non-standard items.
24.3.8 Filter
196
Estimate
03-2011
This print option is available in conjunction with the reports in the following folders:
a) Estimate folder
Filter file
Here, the loaded filter file is displayed.
Load file
Click this button if you wish to load a filter file. The filter file dialog box appears.
Select the desired filter.
Filter definition
Here, the criteria of the filter are displayed, which you specified during the
definition.
Remove filter
Click here if you want to remove the loaded filters. The filter definition itself is
not deleted.
Edit filter
Click here if you wish to edit the filter definition.
Standard filter
Do not print elements with the flag "Blocked" or "N/A"
If this function is activated, then elements with this flag are not printed.
See also
Commodity evaluation (report type) [ 172]
Purchase list (Commodity) [ 173]
Assembly Evaluation [ 173]
Purchase list (cost codes) [ 178]
Plant Assembly Evaluation [ 178]
03-2011
Estimate
197
24.3.9 Configuration
Here, the current configuration for the column estimate is displayed.
Change
If necessary, you can use this button to define another configuration.
For this, the Column Estimate Configuration dialog box is shown.
See also
Column estimate (list type) [ 186]
Report by structure
Here, select the structure to be used as a basis for the report. Usually, for a bid
estimate this will be the cost code catalog.
Check configuration
If a KOSIV configuration was selected (in the Execution phase), then you can
specify here whether this configuration should be checked.
Suppress lines without values
Lines without values are not transferred to the report by default.
198
Estimate
03-2011
03-2011
Estimate
199
Item Lists
Print area of the individual items.
Division totals
Print range of the appropriate division total within the overall print range of the
items, i.e. the print range for the division total after the last item of a division
and before the first item of the next division. If you deactivate the function Item
Divisions
Print range of the division totals and the BoQ total behind the last item of the last
division. This is thus the print range of a special division summary with the
corresponding BoQ total.
200
Estimate
03-2011
Final analysis
Special summary sheet with the summary of the most important values of the total
estimate.
Totals
The functions in this block (UR/AQ formation, CoC evaluation, Main CoC, CoC
evaluation risks) relate to the print ranges and can be activated or deactivated. This
allows you to control which detailed information is output within the individual print
ranges, i.e. for the appropriate element.
UR/AQ formation
Line range for the appropriate element, which contains the following
information for each UoM (only for the item) and in total:
Budget (only in the Execution project phase)
DJC
AA
GC surcharge
Final surcharge (GA, RP, AM)
MM
URD
UR/IT
Discount
Revenue
CoC evaluation
Line range with cost code evaluation according to the Cost code evaluation (list
type) for the appropriate element. Normally, all the cost codes to which values
are assigned are output. In Cost Code Range, you can make a target selection
of which cost codes are output.
Activation is not necessary, if the CoC are only to be evaluated on the main
CoC level; this list section is selected using the functions in the Main CoC
column.
If the estimate also contains cost details with a risk characteristic, then it is
possible to use the Totals frame to control which values are taken into account
in this section of the evaluation:
Planned + Risks:
The values of the CoC contain all the cost components, i.e. also portions
03-2011
Estimate
201
with risk details. An activated function in the Risk CoC column means that
these portions are output in an additional evaulation section as contained.
Only target costs:
The values of the CoC do not contain any cost components with risk
features. An activated function in the Risk CoC column means that these
portions with risk characteristics are output in an additional evaulation
section as additional.
Main CoC
Line range for the appropriate element, which contains a cost evaluation for
each main cost code. The Main cost codes horizontal or vertical options in the
Totals group control whether the values for each main CoC are printed next to
each other or one above the other. The horizontal arrangement is the spacesaving solution.
If there are cost details with risk characteristics, then the Totals frame controls
which values are taken into account in the main CoC:
Planned + Risks:
The value of the main CoC contains all the cost components; the total of
the main CoC produces the DJC.
Only planned costs:
The value of the main CoC does not contain any cost components with risk
characteristic; the total of the print values of the main CoC does not
produce the indicated DJC..
Risk CoC
Line range with evaluation of the cost codes according to Cost code evaluation
(list type) for the appropriate element from the estimate components which
have a risk characteristic. Please refer to the above explanations under CoC
202
Estimate
03-2011
With the functions, you can activate for which level this division is desired next
to the total values. The item types which are taken into account are dependent
on the appropriate setting in the Totals frame.
See also
Item lists (total job costs) [ 203]
Totals (total job costs) [ 205]
Divisions (Total job costs) [ 207]
Evaluation quantity (total job costs) [ 207]
Cost code evaluation (list type) [ 180]
Summarise to subitem
The detail lines of the estimate are not printed, although the subitems with their
evaluations are. Using the neighbouring button,
settings. The Item Lists - Subitem dialog box appears for this purpose.
Summarise to items
Neither detail lines nor subitems are printed.
for assembly breakdown. The Item Lists - Break down Assemblies dialog box
appears for this purpose.
Internal texts
If this function has been activated, then internal text lines (line flag "I") is printed.
you can make page break settings. The Item Lists - Page
03-2011
Estimate
203
Assemblies
This function is activated by default.
Plant Assemblies
Difference assemblies
Reference item assemblies
This function is activated by default.
204
Estimate
03-2011
03-2011
Estimate
205
In the evaluation according to main cost codes, the individual main CoCs are
written next to each other. This is a space-saving variant and is thus
recommended.
The Totals - Cost code evaluation dialog box appears for this purpose.
See also
Totals - Cost Code Evaluation [ 206]
Evaluation quantity (total job costs) [ 207]
Divisions (Total job costs) [ 207]
Lists/Summaries (Total Job Costs) [ 200]
Item lists (total job costs) [ 203]
206
Estimate
03-2011
See also
Divisions (Total job costs) [ 207]
Totals (total job costs) [ 205]
Item lists (total job costs) [ 203]
Lists/Summaries (Total Job Costs) [ 200]
03-2011
Estimate
207
Price/UR breakdowns
These functions are connected to the functions described previously. They are
deactivated by default. If you activate these functions, then the price/UR
breakdown is applied to the printout.
208
Estimate
03-2011
03-2011
Estimate
209
Tree
Here, you can see the BoQ structure and, by clicking the mouse, you can select
the required entry for the start and end value of the BoQ area. You can define
several different areas.
Here, the selected entry of the estimate is already preallocated in the BoQ
structure.
From/To
Use these two buttons to specify the start and the end of the desired area. The
selected element is transferred to the corresponding table as the start or end value.
Delete
Use this button to delete the start and end value for the selected table line.
210
Estimate
03-2011
24.3.14 Quantities
This print option is available in conjunction with the reports in the following folders:
a) Controlling folder
Evaluation Quantity
Evaluation with BoQ quantity/with AQ quantity/with installed quantities
Select the required base for quantity evaluation.
In conjunction with the installed quantities, the following is also available:
Only elements with reported installed quantities in selected From/To report
period
If this function is activated, then only reported installed quantities are taken
into account according to the report period.
Take 'Suppress in performance analysis' flag from installed/billed quantities
into account
If this function is activated, then quantities with this flag are not taken into
account.
With non-standard items
If this function is activated, then non-standard items are also taken into account
during the quantity evaluation (e.g. for Commodity proof).
03-2011
Estimate
211
In these drop-down lists, you can specify the appropriate start and end values
for the evaluation.
See also
Job List [ 187]
CWT analysis [ 187]
Commodity evaluation (report type) [ 172]
Purchase list (Commodity) [ 173]
Purchase list (cost codes) [ 178]
Assembly Evaluation [ 173]
Plant Assembly Evaluation [ 178]
Bid estimate (list type) [ 179]
Total Job Costs, all Currencies [ 180]
Parameter proof [ 185]
Cost code proof [ 184]
Plant assembly proof [ 184]
Assembly proofs [ 184]
Commodity proof [ 183]
212
Estimate
03-2011
Code:
For placeholder "Q Factor" .. not equal to 1
For placeholder "Co Factor" .. not equal to 1
This option is introduced for space-saving lists, in which the factors themselves
are never output.
Code for quantity factor code for cost factor
A Q or a C is printed, if a factor not equal to 1.000 is stored for the CoC. If
necessary, you can also enter a different abbreviation for the appropriate
code.
03-2011
Estimate
213
Format of Ref. No
Standard
This option displays the reference numbers in the way that you see them on
the screen.
w/ leading Zeros
This option completes all reference numbers with the number zero according to
the defaults of your BoQ in Structure.
Ignore
The reference number is not issued when printing out if you activate this
function.
Items w/o Ref. No. hierarchy
You can activate this function in addition to the two previous options. The
reference numbers of the individual items will not be printed completely in the
print out. Only details of the item are given (e.g. B. 10 instead of 1.1.10), but
below the respective division. The reference numbers are completely printed if
there is no checkmark in the check box.
Replace with user-defined field ...
If you activate this function, the reference numbers of the individual elements
are replaced by the descriptions in User Defined of the BoQ properties.
No entry appears in the Ref. No. column of your printout if you have not assigned any values to the
BoQ elements here.
214
Estimate
03-2011
W/o points
Activate this function if you wish to print out the reference number without the
separator points. The reference number 1.1.10 becomes 1100 if the function is
activated.
Spaces instead of points
Activate this function if you wish to print out the reference number with the
separator points replaced by spaces. The reference number 1.1.10 becomes 1
1 0 0 if the function is activated.
See also
Bid estimate (list type) [ 179]
03-2011
Estimate
215
24.3.19 Sorting
This print option is available in conjunction with the reports in the Analysis folder.
You can use the two lists to specify certain sorting criteria for the analysis.
Available/Selected
These two lists show you the available criteria that have been selected for sorting.
You can move selected entries from one list to another using the buttons between
the two lists. On the right, next to the Selected list, you can modify the ranking
(hierarchy) of the criteria using the two item buttons.
See also
Margin analysis settings [ 193]
Checklist settings [ 194]
Key Item Settings [ 195]
Print check list [ 167]
Print check list with a print range definition [ 167]
Analysis of the key items [ 168]
Print modifications log [ 169]
216
Estimate
03-2011
From. Then, select the end of the print range in the tree and click To. The
reference number is shown alongside for information purposes.
Summarise on
You can choose between the following options for data preparation:
No summary
The lines of all the levels of the estimate are output, i.e. from the detail lines of
the estimate up to the project total.
Divisions
Only the totals on the division, BoQ and entire project levels are output. Items
and their estimate are therefore not printed.
Items
The results on all the levels of the BoQ and the project total are output, but not
the estimate for the items.
Subitems
The detail lines of the estimate are not output, although the results from the
subitems up to the project total are.
Key items
If you activate this function, then only items with this feature are printed with the
selected summary option. This type of evaluation cannot, of course, supply
complete project totals.
Quantity
Evaluation with BoQ quantity
All the calculation results are determined on the basis of the BoQ quantity of
the items.
Evaluation with AQ quantity
All the calculation results are determined on the basis of the AQ quantity of the
items.
Additional options
Page break on changing divisions
03-2011
Estimate
217
If this function is activated, then a page break is inserted after the end of a
division, so that the next division starts on a new page.
With item totals
If this function is activated, then the following results are output on the item
level:
DJC
GCS = Surcharge for GC (only for two-level allocation)
DCM
For one-step allocation = Surcharge for GC, GA, R+P
For two-step allocation = Surcharge for GA, R+P
UR/IT
Item totals are always output for divisions and BoQ. If you deactivate the Item totals function, then only
the detail and subitem lines with their individual results are output for items.
See also
Column estimate (list type) [ 186]
24.3.21 Currency
This print option is available in conjunction with the reports in the following folders:
a) Controlling folder
218
Estimate
03-2011
Estimate currency
Computation results are printed in the estimate currency. (Bid estimate document
selected in the project tree document highlighted in the project structure, Estimate,
Project currency
Computation results are printed in the project currency (project highlighted in the
project structure, Basic Data, Currency field)
Use this function to control the estimate elements for which the currency shall be
taken into account.
If you activate this function, the costs of the commodities are analysed with the
commodity currency.
If the function is deactivated, the commodity costs are analysed with the cost code
currency.
This settings is, of course, only relevant if you have calculated the costs in different currencies. In this
case, there are cost codes or commodities in different units of currency. The starting values of the cost
codes or commodities are always printed in their original currency. "Computation results" deals with
cost code totals, DJCs, surcharges and prices on all the levels of the estimate and the BoQ, which
could be a total result from different units of currency. Such results can only be output in a single
currency. Conversion from the original currency to the selected unit of currency takes place using the
currency rates stored in the units of currency catalog.
See also
Job List [ 187]
03-2011
Estimate
219
24.3.22 Values
This print option is available in conjunction with the reports in the Total Job Costs folder.
Here, various options are available for handling values in the estimate.
General
Here, you can specify how factors for detail lines < > 1 and zero values are
handled.
In addition, you can, if necessary, also determine the assigned companies for
subcontracted services.
If necessary, you can limit this output to the original level.
Planned GC/Planned AM
Here, you can select on which basis the values should be determined.
Update
Here, you can, if necessary, update the margin and related values and transfer the
prices to the BoQ.
Regarding the budget, you can decide whether it should be distributed to the detail
lines or not.
220
Estimate
03-2011
Performance analysis
Here you can select on which base the values should be determined.
See also
Bid estimate (list type) [ 179]
24.3.23 Additions
This print option is available in conjunction with the reports in the Total Job Costs folder.
Using these settings, you can attach additional evaluation lists as well as the
allocation to the main list. For this, you must assign the appropriate cfl file and
activate this evaluation. The following evaluations are available:
Assembly evaluation (*.cfl file)
Plant assembly evaluation (*.cfl file)
Commodity evaluation (*.cfl file)
Allocation (*.cfl file)
The currently selected cfl file is displayed here.
Activate
If you activate this function, then this evaluation or the allocation is attached to the
main list. It is necessary that you have selected an appropriate cfl file.
Browse
If you click the button, then a dialog box is shown in which you can select the .cfl
file. Select the required cfl file and confirm the selection by clicking Open.
Consider the following:
a) No options are polled directly for additional print-outs.
b) You as the user can decide whether the standard list or a limited, company-specific list variant is
to be printed here.
c) If options appear both in the main list (Total job costs) and in the additional list, then the the
options set in the main list will have precedence.
If it was set in the Total job costs list, that the BoQ quantity should be printed, then, in the
additional list, the quantity type set in the clf file is irrelevant. The entire list is printed completely
with the BoQ quantity.
See also
Bid estimate (list type) [ 179]
03-2011
Estimate
221
Index
Index
222
Estimate
03-2011
Index
Bid estimate, 13
Bidder prices
Advantages
Include in estimate, 50
Estimate methods, 21
BoQ
Allocation
Basic data, 16
Active allocation, 78
Budget, 17
For estimate, 78
Disabled flags, 37
Lump sum, 16
Parameters, 39
Assembly
In estimate, 40
Resolve, 56
BoQ structure
As basis of estimate, 88
Estimate, 88
Print, 173
Break down
Backwards calculation
Budget
Objective, 63
BoQ, 17
Division, 17
Based on item
Search for parameter, 111
Basic data
C
Calculate in reverse
Estimate, 77
Fixed prices, 63
Bid, 14
Catalog
Plant assemblies, 51
Export, 155
Labour escalation clause, 17
Print, 154
Print change order bid, 165
General, 18
Summary, 18
Bid BoQ, 14
Bid creation, 25
Change order
(c) RIB Software AG
03-2011
Estimate
223
Index
Internal revenue, 75
Valuation, 75
Valuation factors, 75
Cost Code
Print, 165
Fixed, 19
Client enquiry, 14
Collective BoQ
Print, 185
Reference to reference, 61
Update, 61
Cost estimate
Column estimate, 20
Configuration, 123
Create
Column types
Estimate (overview), 23
Estimate, 104
Columns
Estimate summary, 99
Commodity proof
Print, 183
Compare
Creation
Bid, 25
Crew mix, 83
Configuration
Date
224
Estimate
print, 163
delete
Report Type, 162
Delete
03-2011
Index
BoQ, 17
Disabled flags, 37
Lump sum, 16
Estimate, 57
Print, 163
drucken
Nachtragsbersicht, 164
Partial update, 58
Detail line
Umlage, 166
Copy, 107
Create, 106
Factor/Divisor, 34
Print, 186
Move, 108
estimate
Detail Line
Disabled flags, 37
Estimate
Detailed
Item estimate, 20
Basic data, 77
Deviation
BoQ structure, 88
create, 104
Estimate document properties, 77
Fixed price, 48
For GC in item, 92
Fundamental data, 77
Disabled flag
Of the subitem, 37
Prerequisites, 14
Disabled flags, 37
Of the BoQ, 37
Totals, 97
URB assignment, 79
Division, Item), 37
Using caleandar, 50
Using schedules, 50
Options, 89
Division
Estimate
225
Index
Estimate Data, 89
Factor/Divisor
Detail line, 34
Estimate line
Subitem, 32
Delete, 108
Estimate methods
Advantages, 21
Estimate summary
Columns, 99
Lines, 100
Flag, 48
Show, 98
In the estimate, 48
Fixed prices
Calculate in reverse, 63
G
General conditions (GC), 92
Estimation
139
costs, 141
Generated assemblies, 67
evaluation
Options, 66, 67
Copy prices, 49
Item
Disabled flags, 37
Fixed price, 48
Export
Planned costs, 68
Print, 163
Risk characteristic, 38
Item estimate, 20
Item factor
In the quantity detail, 111
Factor
In subitems, 33
J
Jump to the destination item, 61
226
Estimate
03-2011
Index
key items
Nachtrag
Print, 172
Nachtragsbersicht, 164
Nachtragsbersicht, 164
Net costs, 70
Matrix report, 70, 70
Bid, 17
new
Layout, 162
Line types
Estimate (overview), 22
Line types of the estimate, 100
Lines
Operating plant, 51
Options
BoQ, 16
Division, 16
Lump sum generation for BoQ or division in
project phase 2 or 3, 16
P
Parameter
Scope of validity, 39
Parameters, 73, 73
Manual markup, 92
Margin, 47
Matrix report
Planned costs
Export, 68
Modify
Plant
Customs duty, 53
Move
Fees, 53
Handling cost, 53
Subitem, 107
Installation costs, 53
03-2011
Estimate
227
Index
Loading costs, 53
Bid, 164
Operation cost, 53
Stand-by costs, 53
Transportation costs, 53
Item/division, 163
Plant assemblies, 51
Catalog, 51
Plant catalog, 52
Master, 52
Project, 52
Plant estimate, 51
Project
Settings, 72
Properties
Estimate document, 77
purchase list
Print, 173
Update, 54
Plant time dependent costs, 53
Plants
Costs, 51
Prerequisites, 14
Price adjustment
Modify, 151
Prices
QTO detail
With parameters, 39
Quantities
Update, 51
Quantity detail
Favourites-Reports, 161
Options, 162
System-Reports, 161
Users-Reports, 161
Print, 161
228
Estimate
Quantity parameters
In the quantity detail, 111
03-2011
Index
Reference
S/C prices
Include in estimate, 50
Same-As item, 59
Scope of validity
Reference item, 59
Parameters, 39
Settings
LV-comprehensive, 59
Reference to reference, 61
Projects, 72
Show
Referenced values
Estimate summary, 98
Side computation
Referenced Values
Using parameters, 39
Stand-by plant, 51
References
Start values
Copy, 62
on printing, 162
Report Type
Subitem
Date, 163
Copy, 106
delete, 162
Layout, 162
Disabled flag, 37
Disabled flags, 37
Phases, 162
Factor, 33
Factor/Divisor, 32
Move, 107
Time, 163
Numbering system, 26
Revenue
Risk characteristic, 38
Change order, 75
Risk characteristic
Subitem structure, 26
In project phase 1, 38
Item, 38
Switch
Between BoQs for estimate and bid, 26
Subitem, 38
(c) RIB Software AG
03-2011
Estimate
229
Index
System values
Search for quantity detail (object model), 111
T
Time
print, 163
Time dependent costs, 53
Total job costs
Net costs, 70, 71
Totals
Estimate, 97
U
UFS price 1a and 1b, 81
UFS sheet, 81
Umlage
drucken, 166
Unit rate
Calculation in item, 92
Unit rate difference, 92
Update
Collective BoQ, 61
Plant list, 54
Quantities, 51
Updating the collective BoQ, 61
URB assignment
Estimate, 79
Use dependent costs, 53
V
Valuation factors, 75
230
Estimate