Serial No.

Date / Day
Weather
A - Outstanding Works
B - Defects

DAILY REPORT:MASTER DEFECT PUNCHLIST AND AS BUILT DRAWING UPDATING


005
PERSON AT SITE: VANISHA, AKHILASH AND TAUFIK
19th April 2016
SUNNY
PLANNED
TODAY
1
Liased with Miss Poh - no major outstanding works.
_
1 Inspected DEMIN STATION AND CHEMICAL LAB with En.Mar'e

PIC

Continue updating Master defect Punchlist


TAUFIK

2 Liased with Miss Poh to update Master Defect Punchlist to


eliminate possible repitition in defect list.

C - As-Built Drawings

To complete updating Master Defect Punchlist for Pipes


and Trenches, Concreting Works and Effluent Water
Pipelines, Oily Water Pipelines, Sewage before
proceeding to other location.

AKHILASH

1 UPDATED AS BUILT DRAWING(2016/4077) IN :( COMMENT SHEET, DRAWING LIST AND COVER)


VANISHA