Client: Puma Energy Vietnam Limited

Project: Bitumen storage and Distribution Terminal Project


at Tam Hiep IZ, Quang Nam Province, Vietnam

WELDING REPAIR PROCEDURE

CONTRACTOR:
MK Bui Nguyen Construction JSC
No.631 Binh Gia Street, Thang Nhat Ward,
Vung Tau City, Vietnam
CONSULTANT:
Tebodin Vietnam Co., Ltd.
6th Floor, Quy Hanh Building
165 Ba Trieu, Le Dai Hanh Ward,
Hai Ba Trung District, Hanoi
Vietnam
Author: Dinh TV
- Telephone:

always close

April 11, 2016


Document number: 7721005
Revision: 00

MK Buinguyen Vietnam Co., Ltd.


Procurement Plan for EPC Service
Document number: 7721005
Revision: 00
April 11, 2016
Page 2 / 6

00

11th April, 16

Welding Repair Procedure

TV Dinh

Rev.

Date

Description

Author

Checked by

Copyright MK Bui Nguyen Construction JSC


All rights reserved. No part of this publication may be reproduced or transmitted in any form or by any means
without permission of the publisher.

MK Buinguyen Vietnam Co., Ltd.


Procurement Plan for EPC Service
Document number: 7721005
Revision: 00
April 11, 2016
Page 3 / 6

Table of contents
1.0
2.0
3.0
4.0
5.0
5.1
6.0
7.0

PURPOSE
SCOPE
REFERENCES
DEFINITIONS
PROCEDURE
WELDS REPAIR
RECORD
APPENDIX

4
4
4
4
5
5
6
6

Attachments

Revision

Date

Drawings

Revision

Date

MK Buinguyen Vietnam Co., Ltd.


Procurement Plan for EPC Service
Document number: 7721005
Revision: 00
April 11, 2016
Page 4 / 6

1.0

PURPOSE
This procedure is established to provide proper control of repair welding activities to ensure all
welding production comply with Client specification, quality standard and industry practices.

2.0

SCOPE
This procedure is applicable for repair weld defects of structure, piping and tank fabrication work.

3.0

4.0

REFERENCES
AWS.D1.1

American Welding Society Structural Steel Code

ASME IX

Qualification standard for Welding and Brazing

ASME B31.3

Process Piping

API 650

Welded Steel Tanks for Oil Storage

2680001

Piping Material Specification

2181001

Specification for API 650 tanks

DEFINITIONS
COMPANY

Puma Energy Vietnam Limited

CONTRACTOR

MK Bui Nguyen Construction JSC

MPI

Magnetic Particle Testing

WPS

Welding Procedure Specification

HAZ

Heat Affected Zone

Full thickness repair

Excavation and re-welding of fill/cap or cap pass only

Partial Thickness repair

Excavation and re-welding of the whole weld i.e.; removal of root


pass up to the capping passes

MK Buinguyen Vietnam Co., Ltd.


Procurement Plan for EPC Service
Document number: 7721005
Revision: 00
April 11, 2016
Page 5 / 6

5.0

PROCEDURE

5.1

WELDS REPAIR
5.1.1

Refer to the NDT reports for the location, size, depth and orientation of the defect. Location
of defective areas shall be clearly marked on the joint.

5.1.2

Re-welding of the defective areas. Preheat temperature shall be 50C above preheat used in
performing the original or 150C whichever is higher weld as specified by the approved
repair WPS. Preheat is not applicable for Stainless steel and Duplex steel. Preheat shall be
maintained throughout the excavation and re-welding operation.

5.1.3

Excavation shall extend at least 25 mm (50 mm for cracks) beyond the extremities of the
defect and in the case of partial thickness repair; the depth of excavation shall extend at
least 3 mm beyond the reported depth.

5.1.4

When a defect is identified as a crack, the repair shall not be done until the casue of the
crack has been established and investigated. A notification shall be provided and repair may
only commence once appropriate repair method is approved by COMPANY. The gouging
shall be carried out in two stages. The first shall commence one inch before the beginning of
the defect location progressing to the midpoint of the weld. The second stage shall
commence one inch from the other end and progressing to the same midpoint. This will
ensure that the crack is contained and propagation is prevented.

5.1.5

Excavation of the repair area may be done by grinding or air carbon arc gouging to remove
the defect. When air carbon arc gouging is used it shall be followed by grinding to remove
the residual carbon prior to welding. The excavated cavity shall have a groove preparation
approximating the requirement of the applicable WPS. A mimic of the excavated area shall
be performed for this purpose and to ensure that the defect is removed.

5.1.6

Carry out visual inspection of the gouged area and perform depth checks using profile
gauge, pit gauge, welding gauge or other appropriate means to verify that the proper
gouging depth is reached.

5.1.7

Perform MPI or DPI on the excavated area to ascertain complete removal of defect prior to
re-welding

5.1.8

When full thickness repair is to be made it shall be performed in the same manner as
described above except that the gouging depth shall be at through thickness. For a double
sided joint repair, the one side shall be excavated and re-welded first prior to repairing the
other side.

MK Buinguyen Vietnam Co., Ltd.


Procurement Plan for EPC Service
Document number: 7721005
Revision: 00
April 11, 2016
Page 6 / 6

5.1.9

Only a maximum of two (2) repairs shall be attempted on any weldment at the same location
unless approved otherwise by Company.

5.1.11

All activities during the repair operation shall be monitored by a dedicated QA/QC Inspector
and overseen by the Welding Foreman/Leader. Company to be notified prior to the start of
the any major repair activities.

5.1.12

All repairs and subsequent NDT test after repair shall be the same manner as that of the
original weld. Perform visual inspection, NDT in accordance with the original requirements.
NDT shall be carried out after repaired area has cooled down to ambient temperature after
completion of weld repair. For welds of project material type I, II, VI, & VII NDT shall be
carried out after 48 hours of completion of weld repair.

5.1.13

Minor weld defects such as: Overlap, Excessive convexity, undercut, weld spatter, etc shall
be removed by grinding, chipping or brushing.

5.1.14
5.1.15
6.0

Contractor shall inform Company at least 4 hours in advance of major repair activities.
All repair for piping shall be recorded.

RECORD
Reports including. MPI, RT (whichever applicable)
All reports shall be verified by Company representative and must be kept by CONTRACTOR for
Final Documentation.

7.0

APPENDIX
APPENDIX 1 WELD REPAIR REQUEST