cementing Program

shoe Depth
(m)
surface casing

Mud Density
(ppg)

TOC (m)

650

9.1

Intermediate
casing

2500

10

1500

Production casing

4100

12

2150

production liner

4750

15.8

3750

Lead
Slurry
(ppg)

Tail Slurry
(ppg)
Remark
single slurry to
surface

10

Hole size Casing


Float collar
(inch)
size (Inch) depth (m)
23

18 5/8

12.8

15.8

17 1/2

13 3/8

12.8

15.8

12 1/4

9 5/8

5 1/2

8 1/2

17

Single slurry to
liner hanger

Excess
(%)

10

General Data
Casing size
Casing ID
Hole size
Annular capacity
Casing Capacity

5 1/2 inch
4.548 inch
7 inch
0.0182144939 barrel/feet
0.0200935535 barrel/feet

Volume of Lead
slurry

0 barrel

Length of tail slurry


(m)
Volume of Tail Slurry
Length of Lead
Slurry (m)
Excess
Total Volume
A

well description
Depth (m)
0
650
2500
4100
4750

0
0
0
0
0

grade

650

8.6
9
10.8
13.8

Fracture Pressure
(ppg)
12
15
17.1
17.6

Casing data
Shoe depth (m)

Pore pressure
(ppg)

Angle

Fluid Sequence
Component
Spacer
Lead Slurry
Tail Slurry
Mud
Mud
Mud
Mud

K-55

flow rate

Pumping Calculations

weight (ppf)
106

volume

burst pressure
(psi)
1140

stage time

Flowrate

velocity

Centralizer Placement

Mud displacement calculations

Reynold number

Mud weight (ppg)


9.1
10
12
15.8

Collapse pressure
(psi)
2740

cumm volume

Thread
BTC

comments
Pressure Test Lines
Pump Spacer Ahead
Drop Bottom Plug
Pump Slurry
Drop Top Plug
Start displacement by mud
Slowdown to bump the plug

Cementing Program
GENERAL DATA
Input data
CSD
Hole size
Casing OD
Casing ID
slurry excess volume
Lead slurry length
Tail slurry length
Shoe track
PRESSURE DATA
Pore pressure
Fracture Pressure
BHST

1756 m
14.126 inch
9.625 inch
8.681 inch
0%
756 m
200 m
24.7 m
8.3 ppg
11 ppg
88 DegC

Casing Internal Capacity


Annular Capacity
Lead slurry volume
Tail slurry volume (Hole)
Tail slurry volume (casing)
Total slurry volume

0.07321 bbl/feet
0.10385 bbl/feet
257.593 bbl
68.1464 bbl
5.93278 bbl
331.673 bbl

Previous String
MD (m)
OD (inches)
weight (ppfID (Inches)
475
13.375
68
12.415
Casing
MD (m)
OD (inch)
1756
A

Joint (m) Weight (ppfID (inch) Grade


9.625
11.9
47
8.681 N-80

FLUID SEQUENCE
original mud
Displacement volume
Total volume
TOC

Name
Spacer

volume (bbl)

9.8 ppg
415.8473 bbl
741.5872 bbl
800 m
Annular
length
Top
50 837.0249

Density

Collapse (pBurst (psi) Thread


4760
6870 BTC

GPF

Severity Rating
1 Minor
2 Minor
3 Minor
4 Minor
5 Moderate
6 Moderate

7 Moderate
8 Moderate
9 Severe
10 Severe

Hole size
(inch)

Casing size
(inch)
20
18 5/8
16
13 3/8
12 1/4
9 5/8
8 1/2
5 1/2

Tail slurry
length (m)
I section
II section
III section
IV section

0
150
150

Length of
Casing Setting
cement
Depth (m)
TOC (m)
column (m)
MPR
650
0
650 2590
2500
1500
1000 2087
4100
2150
1950 4070
4750
3750
1000 1826

OBP
MPR
1/5 221.7956
11
1/3 1578.161
1
1/3 3197.269
1
3/7 1253.998
1

Severity
2/3 severe
1/3 minor
2/7 minor
4/9 minor

Fracture
Tail slurry
Lead slurry
Lead slurry
Mud
Mud
pressure
density (ppg) length (m)
density (ppg) length
weight
OBP
(ppg)
0
650
10
0
9.1 1108.978
12
15.8
850
12.8
1500
10 4819.789
15
15.8
2000
12.8
1950
12 8764.338
17.1
0
1000
17
3750
15.8 13009.17
17.6

Fracture
pressure
(psi)
Margin
1330.774 221.7956
6397.95 1578.161
11961.61 3197.269
14263.16 1253.998