You are on page 1of 37

Interconnection Facilities Study

For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.


Executive Summary

This Facilities Study is conducted for the 50 MW Negros PH Solar Inc.s Solar Power Project in
Brgy. Felisa, Mansilingan, Bacolod City, Negros Occidental. This study aims to identify the
necessary connection equipment to connect the proposed power plant to the grid. The connection
configuration presented in this study is based on the connection requirement of NGCP as
documented in the System Impact Study for the project.
The connection arrangement is compliant with the requirements of the Philippine Grid Code and
other applicable regulatory issuances. The proposed project will connect to the grid through a 69
kV transmission facility approximately 1 km in length. The connection will be a tapped
connection along the existing 69 kV transmission line owned by NGCP. Power generated from
the proposed power plant will be delivered to CENECO, NOCECO and to the grid through NGCPs
Bacolod Substation.
After a series of discussion, it was agreed with the local NGCP that no switching substation will
be installed at the tapping point. Aerial disconnect switch will be installed next to the tapping point
and another one on the tapping pole isolating the CENECO/NONECO line.
In compliance with the requirement of ERC Resolution 16 series of 2011, the power plants
disconnection means will be the existing feeder breaker and corresponding disconnect switches
at Bacolod Substation. Included in this study are the telecommunication and protection equipment
needed in by the power plant. From the results of the System Impact Study, no other
improvements or additions will be required for the transmission network beyond the connection
point.
The following are the results of the FS:
1. No issue on the proposed connection scheme as this is to be owned by the developer
following provisions of the Section 9 of the Electric Power Industry Reform Act of 2001;
2. Negros PH will follow NGCPs Open Access Policy requirements and procedures;

1|Page

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

3. Negros PH will consider the protection arrangement as required by NGCP, as the Grid
Owner;

4. Telecommunication and SCADA equipment will be advanced following the prescription of


the Energy Regulatory Commission under NGCPs Draft Determination;
5. Protection equipment shall be provided, owned, operated and maintained by NGCP and
NPHSI at their respective sides; and

6. Technical specifications for equipment that are related to the interconnection facility and
interfacing of plant to NGCPs system as SO shall be in accordance with applicable ERC
issuances (e.g. Philippine Grid Code) as well as NGCPs standards. Proponent is even
willing to procure the accredited equipment manufacturers in ensure compliances.
It is considered that the assistance of NGCP, which plays critical roles as Transmission Provider,
System Operator and Metering Provider, is crucial to ensure the timely completion and successful
commissioning of the project.

2|Page

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant
1.0

Negros PH Solar Inc.

Introduction
1.1

Project Background
Negros PH Solar Inc is developing a solar project in Negros island in a land totalling
to 150 hectares. Many of the landowners are prominent local business people with
good reputation. NPHSI aims to secure approximately 280 hectares to build a 200
MW solar in the future.

The interconnection is via the Bacolod San Enrique 69 KV line which remains a
subtransmission asset. Following previous case precedents, the line has to be filed
for reclassification with the Energy Regulatory Commission.

Initially, this FS is only focused on 50 MW on Site 1 at Felisa given the tight


schedule set by the Department of Energy on the Feed-in Tariff:

3|Page

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

1.2

Negros PH Solar Inc.

Scope/Purposes

This Facilities Study applies the findings in the SIS in identifying the necessary equipment
for the connection of the proposed project to the transmission system.

Specifically the study presents the following:


-

Substation equipment specification

Transmission Line requirements

Identify the appropriate telecommunication and protection facility

The proposed layout of the solar farm is shown below. Note that the layout is for the full
development. This study will not give emphasis on plants specification.
Initial development based on the System Impact Study (re-run) will be redesigned such
that it will optimize the utilization of the area with aimed to put it closer to the tapping point
for immediate completion.
It must be emphasized however that the FS does not cover the plants configuration and
specifications including its high-voltage equipment such as inverter transformer and stepup transformers including the switching equipment at the plant switchyard. The FS covers
starting the coordination of protection of the plants connection line to NGCPs system
4|Page

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

including the SCADA and Telecom equipment which are all Grid assets pursuant to Article
4.3 of the Philippine Grid Code.

1.3

Description of Connection Facility

The scope of this facility study includes only the interconnection equipment needed to
connect the proposed generation plant to the grid. Included thus in this report are the
facilities and equipment from the generating plant takeoff substation up to the tapping
point.
The receiving substation will be NGCPs Bacolod Substation. The feeder circuit breaker
and its associated disconnect switches will serve as the disconnecting means for the
project in compliance with the requirements of ERC Resolution 16 Series of 2011. The
control of these equipment is at NGCPs Bacolod Substation.

The connecting 69kV transmission line is designed to utilize steel/concrete poles which
are selected for this application to minimize the overall cost of the line in addition to the
5|Page

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

benefits of ease of transportation and installation. The 69kV transmission line will connect
at the existing Bacolod San Enrique 69kV line as illustrated below. The location of the
solar take-off substation to the existing line is about <100meters.

Figure 1. Proposed Interconnection Scheme


Protection, telecommunication and SCADA system between the receiving substation
and takeoff substations will also be included. Also included are the upgrades and/or
additional equipment at the NGCP Bacolod Substation.

As shown above, a DS shall be installed at the tap-connection along with fault indicator.
Functional testing of the Fault Clearance System shall be undertaken at field with NGCP
witnessing the testing to be conducted.

1.4

Results of the System Impact Study

The results of the SIS has to be outlined herein.

Noting the known congestion in the Negros grid specifically the limitation to export
power to Cebu, with Panay alredy exporting with the completion of 2x135 MW
Palm Concepcion plant and Panay Energy Development Corporation Unit 3 (150
MW), the projects recommendation is to implement the project into two-stage, i.e.,
50 MW at the 69 KV connection and the second phase is contingent to the
completion of the Negros-Cebu 230 KV Upgrading Project which is unlikely to
complete within the 4th Regulatory Period (2016-2020).

The conclusion of the study indicated the that Phase 1 (50 MW) has no significant
impact to the reliability, stability and operating characterirest of the Visayas Power
transmission system. The conclusion indicated that the power plant could be
6|Page

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

safely and reliably integrated to the Visayas grid, Phase 2 can only be implemented
by the Negros-Panay 230 KV Project.

In agreement with NGCP, the technical assessment has to be conducted and it will
be discussed further in succeeding section.

In order to aid in determining the appropriateness of the equipment related to the


interconnection to NGCPs system, relevant information have to be considered in
the FS.

7|Page

i.

Demand

ii.

Capacity Additions Considered

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

iii.

BUS

STATION

Short Circuit Level at Bacolod

KV

VISAYAS GRID FORECAST FAULT LEVEL


Generator Impedance Used Subtransient (Xd")
(As of June 30, 2015)
MAXIMUM FAULT
THEVENIN IMPEDANCE, Ohm
CURRENT, Amp
PHASE

37500
35500

BACOLOD SS
BACOLOD_69KV

Negros PH Solar Inc.

138
69

4,034
6,578

GROUND
4,464
9,007

Z1_R

Z1_X

Z2_R

Z2_X

Z0_R

Z0_X

3.47768
0.98017

21.54910
7.88087

3.70430
1.03798

21.97810
7.99257

2.42858
0.29642

16.16490
3.00741

Note: Z1- Positive Sequence, Z2 - Negative Sequence, Z0 - Zero Sequence


VISAYAS GRID FORECAST FAULT LEVEL
Generator Impedance Used Subtransient (Xd")
(Projected 2016)
BUS

STATION

KV

MAXIMUM FAULT
CURRENT, Amp
PHASE

37500
35500

BACOLOD SS
BACOLOD_69KV

138
69

5,202
9,408

GROUND
5,701
12,512

THEVENIN IMPEDANCE, Ohm


Z1_R

Z1_X

Z2_R

Z2_X

Z0_R

Z0_X

2.33511
0.62706

14.7341
4.80683

2.57988
0.68234

14.4069
4.75931

1.62274
0.20064

11.8726
2.03129

Note: Z1- Positive Sequence, Z2 - Negative Sequence, Z0 - Zero Sequence

iv.

8|Page

Transmission Expansion Considered

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

v.

Negros PH Solar Inc.

Technical Assessment

Results of the SIS shall be discussed in the attachment to be provided in the final
appendix.

2.0

Objective
Following the requirements prescribed under Module B15 of the Open Access
Transmission Service (OATS) Rules, the purpose of the facility study is to determine
the details of the connection scheme and specifications of the equipment to be used
to conform with the requirement of NGCP and in accordance with the provisions of
the Philippine Grid Code as amended in 2007, The Renewable Energy Act otherwise
known as RA 9513 and RA 9136 (EPIRA).

The primary objective of the Interconnection Facilities Study is to determine the


interconnection scheme to the transmission system. It intends to identify the major
9|Page

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

equipment related to interconnection and the necessary secondary devices which are
crucial infrastructures related to the role of NGCP as System Operation.

3.0

Connection Configuration
Anticipating the approval of the new PGC, it is considered safe that in the selection of
connection scheme it will be better to adopt the definition in amendment no. 2, which
states as quoted below:
GCR 4.4.1 Requirements Relating to the Connection Point

GCR 4.4.1.1 The Generators Equipment shall be connected to the Grid or to


the Distribution System at the voltage level(s) agreed to by the Grid Operator
or the Distributor and the Generator based on Grid Impact Studies.

GCR 4.4.1.2 The Connection Point shall be controlled by a circuit breaker that
is capable of interrupting the maximum short circuit current at the point of
connection.

GCR 4.4.1.3 Disconnect switches shall also be provided and arranged to


isolate the circuit breaker for maintenance purposes.

In the layout below, it already considered that mandatory requirements set by the PGC.

10 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

Figure 2: Basic layout of the substation


While the corresponding plan is:

Figure 3: Basic plan of the substation

4.0

Asset Boundary
In accordance with the Resolution 16 Series of 2011issued by the Energy Regulatory
Commission (ERC) dated 6 July 2011 Section 4.2 Connection Assets for Generation
Customers of Transmission Provider, 3rd

paragraph, A generation company

may develop and own or operate a dedicated point-to-point limited facilities


provided,that such facilities are required only for the purpose of connecting

to

the transmission system, and are used solely by the generating facility subject to prior
authorization by the

ERC and following the convention in Annex C of said

resolution, the asset boundary between NPHSI and NGCP shall be at the at the tapping
point at San Enrique 69 KV line as illustrated below:

Following requirements at the tapping point, below are the illustration of the tapping point
but will be subject to the approval of NGCP prior to the construction stage.

11 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

Figure 4: Illustration of asset boundary

12 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

Figure 5: Details of the tap-connection


NPHSI shall execute the Fixed Asset Boundary Document as one of the attachments
of the Transmission Service Agreement.
The document will precisely show the Connection Point and shall specify the following:
a. Equipment and ownership
b. Accountable Managers
c. Safety Rules and procedures during Local Safety Instruction and the Safety
Coordination of any other persons for safety
d. Operational procedures and the responsible party for operation and control
e. Maintenance agreement and the responsible party for undertaking the
maintenance
f.

5.0

Any agreement pertaining to emergency situation

Receiving Substation Facility Requirements


The existing Bacolod Substation 69kV switchyard will be maintained as is. The
tapped connection will not require modifications at the switchyard. Only
communication facility via optical groundwire will be installed at this substation.

13 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

5.1.1

Negros PH Solar Inc.

General Technical Requirements

The electrical equipment shall be designed in such a way as to bear without


damage and permanent deformation the consequences of over voltage of internal
or atmospheric origin and each electrical component can withstand the maximum
stresses under fault conditions.

Outdoor installations shall be protected against solar radiation by means of


adequate covers, where required, with non-deteriorating material.

All equipment shall be designed to be insensitive to any signals emitted by wireless


communication equipment.

All metallic frames shall be securely connected to the general earthing system in
compliance with accepted standards.

The center line spacing and clearances above ground level of the conductors
shall be as shown in the detailed design drawings.

The minimum clearance between live metal parts and ground shall be 837.5 mm.
while, the minimum clearance between live metal parts of two phases shall be 1500
mm. The practical distance between phase center lines shall be 1500 mm. and the
minimum height of live conductors above ground shall be 3000 mm, however, the
upper edge of an earthed insulator support shall have a height of, at least, 2300 mm.
above the ground level.

Creepage distance of equipment bushing, insulator strings, station post insulators


and rigid support insulators shall be equal or greater than the resultant of the 21
mm/KV multiplied by the maximum nominal voltage . Outdoor equipment shall
be painted with RAL 7035 color, while indoor equipment (including inside cubicle)
shall be painted with RAL 7032 color.

Phase indication plates with color and code letters, which shall be luminous
and made of weather resistant materials, shall be provided on the substation steel
structures to indicate the phases of bus, incoming lines and transformer feeders
and shall be as follows: Phase A is Red and code is A; Phase B is Yellow and
code is B; and Phase C is Blue and code is C.
14 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

Outdoor and indoor equipment and panels shall be labeled in accordance with the
Site and Equipment Identification and Labeling (SElL) standard of NGCP as
mandated by the Grid Code. NGCP, therefore, must provide guidance to
the developer on the appropriate nomenclature of the major devices
interphasing with NGCPs System Operation.

5.1.2

Codes and Standards

All engineering, fabrication, construction/erection, startup and testing provided


by the Contractor shall be in accordance with applicable codes and standards,
regulations and guides. The applicable codes, standards and regulations will
consist of the substation requirements as the basis, and also include those for the
Contractor's nation as follows:

1) Philippine Standards and Codes


2) United States Standards and Codes (IEEE/ANSI/NEMA/NFPA etc.)
3) International Electro-technical Commission (IEC)
4) DIN (German)
5) BS (British standard)
6) JIS (Japanese Industrial Standard)
7) CNS (China National Standard)

5.2

Power Transformer

The Power Transformer i s rated 50/65 MVA (ONAN/ONAF), 13.2/69 kV,


60Hz, and capable of changing its tap ratio by+/- ten percent (10%), with
a step size of 1.25%. The HV bushings of the Power Transformer shall be
of the resin paper impregnated and non-draw lead type. Aside from the
insulation, polarization index, oil dielectric, polarity and ratio tests that are
required by NGCP to be conducted on the power transformer prior to
connection, other routine tests specified under the applicable ANSI/IEEE
standard

and

the

manufacturer's standard test regime shall also be

conducted on the power transformer.

The cooling medium shall be oil and its temperature of cooling air shall not
15 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

exceed 40C. Cooler shall be transformer mounted and should be radiator fin
type. Monitoring and control system shall be interfaced at the Substation
Control System.

Transformer shall be equipped with On-load Tap Changer (OLTC) and should
be oil-immersed. Taps shall be 0.625% by 8 taps. The motor of the OLTC
shall be sourced by 400 VAC, 3-phase at 60 Hz.

5.3

Power Circuit Breaker

The power circuit breakers (PCB) shall be of the S F 6 a n d outdoor type. It


shall be rated at least 69 kV, 60 Hz, with continuous current rating at 60
Hz of at least 2000A rms, with interrupting time of no longer than 50 ms.
and shall be capable of interrupting successfully its rated interrupting current
of at least 4 0 kA rms, for its entire operational life. It shall be capable of
withstanding all system lightning impulse and switching over voltages
less than or equal to its Basic Impulse Level (BIL) or switching surge
withstand capability. Generally, the PCB shall meet or exceed all rated
values listed in applicable ANSI or IEC standards. The PCB shall be
designed to have the capability of permitting, at least, two complete
closing-opening operations and to withstand swells caused by ground faults.
Each PCB shall be equipped with an operation counter.

Multiple-pole or single-pole tripping devices shall be protected against


accidental operation and conveniently located for manual tripping or local
operation of the PCB. The tripping mechanism shall have two (2) electrically
independent trip coils (circuits) per pole.

PCBs capable of single-pole actuation shall be provided with a phase


discrepancy monitoring and control system for synchronized closing and
opening operation of individual poles.

The PCB shall be capable of switching out line faults (regardless of the
distance

between

the circuit breakers

and

faults),

no-load

lines,

transformers on no-load and reactive loads without causing re-striking when

16 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

switching.

The PCB

shall

be equipped

with

enough

auxiliary

contacts

to

accommodate the required status and alarm indications, plus additional


convertible eight (8) types A and B contacts each. The operating status
and other parameters of the PCB shall be monitored/interfaced with the
Substation Automation System (SACS).

The technical data sheets of the PCB are shown in subsequent Annex.

5.4

Disconnect and Earthing Swtich

Disconnect Switches (DS) shall be provided and arranged so as to isolate


the PCB during maitneannce. The switching device shall be station class,
outdoor, 3phase, two column horizontal center break type and rated 60 Hz,
69 kV, 2000 A rms and have a short-time withstand capability of at least
4 4 kA rms.

The switching device shall be three pole construction, horizontal mode of


contact separation with reference to the mounting plane, and equipped with
an earthing switch.

The switching device shall withstand and operate without malfunction with
simultaneously acting forces from connection at terminals and short circuit.
The safety factor against break of an insulator shall be at least 1.25 times
the simultaneously acting forces plus operating forces.

The DS shall have the capability of being either motor-operated or manual


through remote, local or manual mode.

The DS shall be equipped with enough auxiliary contacts to accommodate


the required status and alarm indications, plus additional convertible eight
(8) types A and B contacts each.

The operating status of the DS shall be monitored/interfaced with the


SACS,
17 | P a g e

whenever applicable. It shall be equipped with key interlocks,

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

position indicator (both mechanical and light) and damping device.

The switching device shall be electrically interlocked with the associated


circuit breaker to prevent the possibility of making or breaking load current.

To prevent

maloperation,

the operating

mechanism

of disconnect

switches and earthing switches shall be interlocked relative to each other


such that when the main disconnect switch is in "closed" position, the
earthing switch cannot be closed and vice versa. Said interlocking
arrangements shall be effective both in local and in remote operation.

The technical data sheets of the Disconnect/Earthing Switch can be seen


in the Annexes.

5.5

Current Transformer (for statistical meter and protection purposes)

Current Transformers (CT) shall be provided for all PCBs. The CTs shall
be single pole. For outdoor installations, the CT's insulation medium shall
be oil. While, for indoor installations, the CT's insulation medium shall be
SF6 gas.

Current Transformers shall be rated at 69 kV, 60Hz. Its current ratio (with
secondary taps) shall be 2 0 00/1500/1000/500:5A. The CTs shall have 4
cores (i.e., 1 core for metering with accuracy class of 0.2 and 3 cores
for relaying with 5P20 accuracy class) per IEC standards. Rated burden
is 30 VA for metering and 100 VA for protection.

The short-time current thermal rating of the CTs shall be at least 4 0 kA


rms while the rated short-time mechanical is 100 KA rms. The cores shall be
designed and built in such a way that no reciprocal electromagnetic
influence or influence from external fields can occur.

The CT shall have adequate output to meet double the total burden
of the equipment connected to it. It shall also have sufficient thermal,
voltage, over-current performance, internal resistance and accuracy for
the satisfactory operation of the equipment connected to its secondary
18 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

circuit. CT shall withstand the mechanical and thermal stresses caused by


short circuits.

CTs provided for protective purposes shall have over current and saturation
factors not less than those corresponding to the design short circuit level of
the system.

The technical data sheets of the CT (not for billing purposes) are shown in the
Annexes.
5.6

Potential Device

PT shall be of the inductive type, with a marked ratio of 600/345:1 and its
rated secondary voltage shall be 115 VL_J66.4 VL-G It shall be of the
accuracy IEC Class 0.3. The burden rating shall be at least 12.5 VA which
can handle the total burden of the cables and all connected devices at the
PT/VT secondary circuit. It shall have three (3) secondary cores/windings,
both, preferably of metering class accuracy. It shall be tested and certified on
ratio accuracy, phase deviation and insulation integrity.

For its rated insulation, the lightning impulse withstand voltage is 350 KV peak
while power frequency withstand voltage is 140 KV rms dry.

The technical data sheets of the Voltage Transformer can be seen in Annex
M, while the test reports of the VTs are shown in the Annexes.

5.7

Surge Arrester

Each arrester shall be station class, outdoor type, metal oxide (i.e., ZnO)
and gapless type with surge counter. Material of insulator can be composite
type.

The surge arrester at the high voltage (69 kV) side shall be rated for
nominal system voltage of 69 kV, while that of the low voltage side shall
be 13.2 kV. The arrester shall be rated 60 Hz, and its Duty Cycle Voltage
rating shall be 60 kV rms, nominal discharge current of 10 kA and the
19 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Lightning

Negros PH Solar Inc.

Impulse Withstand

Voltage capability of its post insulator

housing, for outdoor installations, shall be 325 kV.

The arrester assembly shall consist of an arrester unit, line terminal,


earth terminal, insulating base, cyclometer type discharge counter with
integral

continuous

AC

leakage/internal

current

indicator.

Outdoor

installations shall have a supporting structure.

Remote indication of discharge counter registers shall be provided and


interfaced with the SACS, if applicable.

The arrester housing shall have either a hollow insulator with gas filling
(tube design) or directly molded housing material on the MO-blocks caged
by FRP rods ("caged design"). Insulator material shall be either porcelain or
silicon rubber.

The unit shall be hermetically sealed, moisture free. For hollow insulators
(tube design), a pressure relief device is required to limit the internal
pressure so as to prevent explosion or violent shattering of the housing
during short circuit current conditions. For outdoor installations, the arresters
shall be vertically mounted on a horizontal surface.

For outdoor installations, each arrester shall be furnished complete with a


non-corroding clamp type ground connector suitable for copper stranded
conductor.

The arrester supporting structure shall be provided with a

grounding pad. Each grounding pad shall be flat and shall be provided with
a non-corroding clamp type connector suitable for, at least, 100 sq.mm. sized
annealed, stranded PVC insulated copper ground conductor. The grounding
pad shall be located about 400 mm above finished ground level.
5.8

Substation Automation Control System

The Substation may be equipped with a microprocessor-based Substation


Automation Control System (SACS) to perform control and monitoring
tasks for all the major and critical equipment in the substation. The SACS
consists of the operator workstations, data highway, process controllers,
20 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

engineering workstation, servers, gateways, GPS Time, and all necessary


peripherals. The SACS shall be equipped with at least three (3) data
communication ports to satisfy NGCP Supervisory Control and Data
Acquisition (SCADA) requirements. In the event that the substation is not
equipped with a SACS or the number of data communication ports of the
SACS be insufficient to satisfy the SCADA requirement, a Remote Terminal
Unit (RTU), with, at least, three (3) data communication ports shall be
provided by NGCP and shall be connected to the DNP 3.0-configured data
communication port of the SACS, if applicable.
communication

ports

shall

use

the

DNP

Said
3.0

three

(3)

data

data communication

protocol to communicate with the Back-up NationaV Regional Control Center


(BNIRCC) in Cebu; the Back-up Regional Control Center (BRCC) in Mandaue,
also in Cebu; and, the Area Control Center (ACC) in Iloilo.

The SACSIRTU shall be equipped with sufficient digital and analog inputs
and control outputs to monitor and control all necessary parameters of the
various plant and substation equipment, with enough spare input, output and
control modules.

The SACSIRTU shall display, aside from the important substation diagrams
and parameters, the single-line diagram of the major substation equipment,
including the out-going lines, together with their identification names
conforming to NGCP's Site and Equipment Identification and Labeling (SElL)
Standard.

The SACS/RTU shall monitor and communicate the following substation


equipment parameters to the above said NGCP Control Centers:

1) Each Power
Transformer

21 | P a g e

MW

MVAR

MVA

Current, A (each phase)

Voltage, kV (each phase)

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Pressure Relief Alarm

Transformer Differential Relay Alarm

Negros PH Solar Inc.

Buchholz Relay Alarm

Overcurrent Relay Alarm

High Winding Temperature Alarm

Lock-out Alarm

2)

Each High Voltage Bus

Voltage

Frequency

Bus differential relay alaRm

3)

6.0

Power Circuit beaker

Status (open, close)

Spring charge alarm

BFR alarm

Auto-reclaose Operation

Open/Close Control Operation

Transmission Line

6.1

Steel Structure

The structures are made from concrete and designed for 69 kV. The structures are
designed for outdoor, tropical, salt and dust laden and heavily contaminated
atmospheric conditions.

The structures are designed to consider the weight of porcelain insulator strings and
the length of composite insulator strings so that in any maintenance work requiring
replacement of insulator string assembly, both types of insulator assembly can
be used without any restrictions
6.2

Conductor

The conductors to be used at the high voltage (69 kV) shall be 336.4 MCM
ACSR (Linnet), while the line hardware to be used shall be appropriate for said size
of cable.
22 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

The conductor and wire data are as follows:


Particular
Size and type
Stranding
Outside diameter
Area
Weight
Breaking strength
6.3

Data
ACSR/AS 336.4 MCMC Linnet
26/7
18.26mm
198.21 sq.mm.
0.6553 kg/m
6,110 kgs.

Optical Pilot Ground Wire


The Optical Pilot Ground Wire (OPGW) shall be 1550 nm, single-mode, 36core fiber based on ITU-T G.652D.

6.4

Conductor Clearances
The Philippine Electrical Code Part II sets safety clearances from ground,
structure and vegetation. Values below are the minimum vertical clearances:

Crossing over at 50C no wind final sag


Track rails of railroad
Public streets and highways
Rural roads
Cultivated fields, area accessible only to
pedestrian along roads in rural areas
All other types of obstruction
6.5

6.6

Clearance in meter
11.5
10
8.5
7.5
Refer to PEC Part II

Pole Design Criteria

Footing resistance is 10 ohms

Design wind velocity is 270 kph

Wind pressure on poles will be in accordance with NESC Rule 252B2

Wind pressure on wires will be in accordance with NESC Rule 250C

Pole Setting

Pole will be direct buried and below will be followed:


Pole height (in feet)
50
55
60
65
23 | P a g e

Depth of setting (in feet)


On rock
On Earth
4.5
6.5
5.0
7.0
5.5
7.5
6.0
8.0

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.


70

6.7

6.5

8.5

Insulator

Porcelain or polymer insulator can be used: suspension or post type. For


porcelain appropriate mechanical and electrical rating shall be used. For the
polymer insulator, appropriate specified mechanical load and routine tests load
rating shall be used.

Electrical Parameters:

Nominal system voltage 69 KV rms

Maximum system line-to-ground voltage 41.8 KV rms

Maximum peak line-to-ground voltage 59.1 KV rms

Leakage Distance Requirements

Assumed ESDD 0.01 0.04 mg/sq.mm.

Pollution severity medium (moderately polluted area to be


considered)

Leakage distance 20mm/KV

Impulse Overvoltage Requirements

6.8

Assumed peak impulse current 40 KA

Pole footing resistance - 10 ohm

Impulse withstand 400 KV

Line Hardwares

All line hardwares to be used shall be compatible with all the associated lien
materials to be supplied.

6.9

Pole Resistance

Resistance measurement will be conducted to ensure that all poles to be built


are properly grounded. Pole footing earth resistance shall not exceed 10 ohms

24 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

otherwise ground rods or counterpoise shall be installed to meet the required


earth resistance.

7.0

Take-off Substation
The proposed power plant takeoff substation will located within NPSI-Felisa Solar
Power facilities The following switchyard equipment not including generatorrelated
facilities, will be installed at the substation:

a. One (1) set of power transformer, 50/65MVA, 13.8/69kV


b. One (1) set power circuit breakers, 69 kV, 40 kA
c. Two (2) sets disconnect switches, 69 kV, 2000A
d. One (1) set current transformer, 69 kV, 2000:5A
e. One (1) set voltage transformer, 69 kV, 350/600:1
f.

Two (2) sets surge arrester, 60 kV

The tapping connection shall be installed with Disconnect Switch and Line Fault
Indicator as shown in earlier drawings (Figure No. 5).

Excluding generatorrelated equipment, the following auxiliary power system facilities


will be installed at the control building:

a. 400/230 Vdc Distribution Board


b. 125 Vdc Battery, Charger, and Distribution System
c. 48 Vdc Battery, Charger, and Distribution System
d. 240 Vac UPS System

Switchyard conductors to be used shall be 850 mm2 THAL. OHGW shall be 7/8
Aluminum Clad.

Below is the indicative layout of the substation

25 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

Figure 6: Illustrations of Plan and Layout

Naming conventions of all equipment will follow the GMCs mandated use of Standard
Equipment Identification and Labelling (SEIL).

The proponent shall follow the

prescribed naming to be suggested by NGCP.

8.0

Protection, Control and Monitoring Requirement


Protection relay, control and monitoring equipment should be provided for the take
off substation and the new transmission line. These protection schemes were
designed consistent with the requirements of NGCPs Network Protection Philosophy.
For the takeoff substation, the following protection, control, monitoring and
communication equipment should be provided:

a. Protection Main1 and Main 2


b. Transformer Protection Main 1
c. Network Disturbance Monitoring Equipment
d. Control Switchboard
e. Fiber Optic Terminal Equipment

26 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

Protection equipment at Bacolod Substation will be asis.


Communication between the receiving and the takeoff substations to provide for
exchange of remote control signal, alarm status, metering data, relay communications
requirements, and voice link shall be implemented through OPGW.

Metering CT and PT will be provided by the Project Proponent while revenue meters
may be supplied by NGCP as metering service provider and will be installed at the
takeoff substation.

Technical Data sheet are provided in the Annexes.

9.0

Communication and SCADA Requirements

Section 4.6.1 Communication System for Monitoring and Control of Chapter 4 Grid
Connection Requirements, a communication system shall be established so that Grid
Owner, the System Operator and the Users can communicate with one another as
well as exchange data signals for monitoring and controlling the Grid during normal
and emergency condition. On the other hand, Section 4.6.2 SCADA System for
Monitoring and Control, the Grid Owner shall provide a Remote Terminal Unit (RTU)
for interconnection of the System Operator's Control Center to serve as telemetry
equipment for monitoring real time information and controlling the Equipment at
the User System.

The Communication and SCADA shall be provided to communicate the proposed


50 MW solar project is described in the succeeding article.

Technical Data sheet are provided in the Annexes.


10.0

Revenue Metering

NPHSI has not decided on what metering agreement it will enter with NGCP.
Nevertheless, NPHSI will be guided with the following NGCP standards for the
Revenue Metering as described in succeeding paragraph.

In accordance with Section 8.2.1 Metering Equipment of Chapter 8 of PGC, the


27 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

Metering E quipment at the Connection point shall consist

of:

a. Instrument Transformers;
b. Lightning Protections;
c. Revenue Class Meters;
d. Integrating pulse recorder(s) and time source;
e. All interconnecting wires and associated devices;
f.

Data communication devices; and

g. Mounting structures and ground wires for instrument transformers

The technical requirements and the e quipment specifications shall be in


accordance with NGCP's Standard Specifications as described below:

A. MINIMUM TECHNICAL REQUIREMENTS FOR THE GRID METERING


FACILITIES:

1.

Blondel's Theorem Compliance. The metering circuit for a 3-phase


4- wire Y connection of the Customer circuit, shall be 3-Eiement.
For a 3- Phase 3-Wire Delta connection, the metering circuit shall be
Delta- connected 2 Element.

For the 3-Eiement, 4-Wire Y metering circuit, the Neutral Point of the
Potential and Current Transformer Secondaries are to be grounded
at a single point to the system ground mat through the grounding
connection at the meter enclosure.

2.

Exclusive Use of Instrument Transformers for Revenue Metering.


To safeguard the security of the metering facility, and to prevent the
simultaneous loss of metering and other functions in case of
instrument transformer failure, the Potential and Current Transformers
shall be exclusively

used for revenue metering. The use of the

instrument transformers for both revenue metering applications


and

substation protection is not allowed, even with separate

cores/windings.
28 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

3.

Negros PH Solar Inc.

Voltage or Potential Transformers (VT or PT)

a.

Type: Inductive type

b.

Secondary Voltage: 115VAC for 34KV and above, 120VAC


for lower voltages

c.

Accuracy Class: ANSI Class 0.3/IEC Class 0.2 or better

d.

Burden Rating: Must be at least 100% higher than the total


burden of the cables and all connected devices at the PT
secondary circuit.

e.

Secondary Cores/Windings: Preferably 2, both of which are


metering class

f.

Factory Test

Report(s): Test Reports of

Ratio Accuracy,

Phase Deviation, and Insulation Integrity

4.

Current Transformers (CT)

a.

Type: Inductive-type

b.

Secondary Current: 0-5A

Primary Current Range: 1.25 - 1.5 x the expected Full Load


Current. For a CT with multiple ratios, the change of tapping
shall be at the secondary side.

d.

Accuracy Class: For Loads: ANSI Class 0.3/IEC Class 0.2 or


Better

For Generators: ANSI Class 0.15/IEC Class 0.2s or Better

e.

Burden Rating: Must be at least 100% higher than the total


burden of the cables and all connected devices at the CT

29 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

secondary circuit.

f.

Secondary Cores/Windings: Preferably 2, both of which are


metering class

g.

Factory Test Report(s):

Test Reports of Ratio Accuracy,

Phase Deviation, and Insulation Integrity. For multiple-ratio


CT's, they shall be factory-tested for accuracy and phase
deviation at all current ratios.

5.

Lightning/Surge

Arresters.

Lightning/surge

arresters

of

appropriate electrical ratings for the application shall be installed at


the line side of the instrument transformers.

6.

Metal

Meter

Security

Enclosure. A steel or aluminum security

enclosure for the main and alternate meter which can be secured by
padlocks and security seals shall be provided. The enclosure shall be
provided with a glass viewing window for visual observation/reading
of meter registers.

7.

Instrument Transformer Secondary Cables. The cables shall be


stranded and with a minimum size of No.12 AWG, and whose
resistance shall not cause the burden of the metering circuit to
exceed 50% of the rated burden of the instrument transformers at
a maximum length of 15 meters from the instrument transformer
secondary terminal to the metal enclosure.

All Instrument Transformer Secondaries are to be cabled through


the Meter Enclosure, including unused instrument transformer
secondaries.

8.

Rigid Steel Conduits for Instrument Transformer Secondaries,


routed directly to the Meter Security Enclosure without any marshalling
box or conduit openings. Only metering circuit cables must be
contained in the conduits.

30 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

9.

Negros PH Solar Inc.

Copper Grounding Cable.

Cable

connecting the

Transformer

Instrument

size is 4/0 Minimum


housings,

for

grounded

secondaries and the Meter Enclosure to the Substation Ground Mat.

10.

Billing Meter(s). The revenue-class meter(s) shall conform with


functional requirements and specifications prescribed under the
Philippine Grid Code and the WESM Metering Manual.

11.

Meter Test Block. A 10-pole switch assembly where the instrument


transformer secondary cables terminate and where the meter is
connected for the purpose of isolating the meter from service and
providing a means of injecting test currents and voltages into the meter
when the meter is to undergo accuracy tests.

11.0

Project Bill of Materials

Below is the preliminary requirements of primary devices and accessories at Felisa:


NPSI-Felisa Solar Take-off S/S
ITEM
NO.

QUANTIT
Y

UNIT

GENERATOR STEP-UP TRANSFORMER, 13.8/69kV,


50/65MVA, 3f, ONAN/ONAF, complete with oil, all
appurtenances, accessories, on-load tap changing
mechanism,and other required accessories, supporting
structures, anchor bolts, foundations, etc.

set

POWER CIRCUIT BREAKER, 69kV, 40kA, 2000A, live


tank type, suitable for 3 pole operation, complete with all
the required accessories, supporting structures, anchor
bolts, foundations, etc.

set

A.

31 | P a g e

DESCRIPTION

HV SWITCHYARD EQUIPMENT

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

DISCONNECT SWICTH, 69kV, 40kA, 2000A, without


Earthing Switch, pedestal mounted, complete with all the
required accessories, anchor bolts, foundations, etc.

sets

CURRENT TRANSFORMER, 69kV, 4-core with 1


metering (Cl 0.2 30VA) and 3 relaying (5P20 100VA),
multi-ratio (2000/1500/1000/800/500:5) complete with all
the required accessories, supporting structures, anchor
bolts, foundations, etc.

each

VOLTAGE TRANSFORMER, 69kV, 600/350:1, inductive


type, two secondary winding, 20VA, complete with all the
required accessories, supporting structures, anchor bolts,
foundations, etc.

each

SURGE ARRESTER, 60kV, Metal Oxide, gapless,


complete with all the required accessories, supporting
structures, anchor bolts, foundations, etc.

each

COMBINED CT/VT, 69kV, for billing, CT: 2 metering core


(Cl 0.2S 20VA) 300/150:5 and PT: two secondary winding
(Cl 0.2 50VA) 350:1, complete with all the required
accessories, supporting structures, anchor bolts,
foundations, etc.

each

SUBSTATION STEEL STRUCTURES for 69kV hotdipped galvanized complete with mounting bolts and
accessories in accordance with the technical data sheets
and drawings

lot

STATION INSULATORS for 69kV, string and post (bus


support), complete with all the required accessories,
protection against electrolytic corrosion, grading shields,
etc.in accordance with the technical data sheets and
drawings

lot

10

BUS CONDUCTOR AND HARDWARE for 69kV


consisting of conductors, hardwares, connectors, fittings,
clamps, etc. in accordance with the technical data sheets
and drawings

lot

11

STATION SERVICE TRANSFORMER, 3-phase,


complete with all the required accessories, anchor bolts,
foundations, etc. in accordance with the drawings.
a. 75kVA, 13.8kV/400V complete with fuse cutout and
lightning arrester

set

b. 75kVA, 13.2kV/400V complete with fuse cutout and


lightning arrester

set

a. 400/230 VAC Auxiliary Board

lot

b. 125 VDC Auxiliary Board

lot

c. 48 VDC Auxiliary Board

lot

12

32 | P a g e

Negros PH Solar Inc.

AUXILIARY POWER SUPPLY SYSTEM, complete with


all the required accessories, intruments, relays, etc. in
accordance with the drawings.

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

13

STORAGE BATTERIES, complete with all the required


accessories, support rack, etc. in accordance with the
technical data sheets and drawings
a. 125 VDC Battery Bank

sets

b. 48 VDC Battery Bank

sets

a. 125 VDC Battery Charger/Rectifier

sets

b. 48 VDC Battery Charger/Rectifier

sets

15

UPS POWER SUPPLY SYSTEM, complete with all the


required accessories, intruments, relays, etc. in
accordance with the technical data sheets and drawings

set

16

DIESEL GENERATOR SET, 60 kW, 400V, 0.8 p.f., 60Hz,


complete with all the required accessories, intruments,
relays, etc.

set

17

CABLES, provided with filler and binder tapes,


termination kits and accessories, etc. in accordance with
the requirements of the technical data sheets.

lot

a. XLPE Power Cable, 15kV Insulation

lot

b. Power Cable, 600 V Insulation

lot

c. Control and instrumentation Cable, 600V Insulation,


shielded

lot

18

CONDUITS AND CABLE TRAY SYSTEM, various sizes,


including, supports, fittings and accessories in
accordance with the technical data sheets and drawings

lot

19

GROUNDING SYSTEM for the Substation including


OHGW, air terminals, connectors, fittings, hard-drawn
copper conductors, ground rods, mold, powder for
exothermic connections, molds, flint guns, etc.in
accordance with the technical data sheets and drawings

lot

20

LIGHTING SYSTEM, complete with lighting fixtures,


lamps, lamp posts with ground terminals including
foundation if required, conductor, conduits, switches,
boxes, etc., for the switchyard, roadways, perimeter and
control building and other indoor establishmentin
accordance with the technical data sheets and drawings

lot

14

33 | P a g e

Negros PH Solar Inc.

BATTERY CHARGER/RECTIFIER, 125 and 48VDC,


complete with all the required accessories, intruments,
relays, etc. in accordance with the technical data sheets
and drawings

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

21

Negros PH Solar Inc.

CONTROL
BUILDING,
complete
design
and
construction of single-storey building. Reinforced
concrete/steel structure and pre-painted long span
roofing, roof slab canopy complete with the required
architectural/civil/structural/sanitary/
electrical/mechanical to complete to complete the scope
of works for the building in accordance with drawings

lot

QUANTIT
Y

UNIT

TRANSMISSION LINE comprising of steel poles, pole


dressing, guying and supports, conductors, insulator
from the take-off substation to the designated tapping
point including reconfiguration of existing NGCP Pole
(designated tapping point)

km.

LOAD BREAK SWITCH, 630A, 20kA, 69kV, complete


with all the required mounting accessories

sets

QUANTIT
Y

UNIT

set

The transmission connection asset is:

TRANSMISSION LINE
ITEM
NO.

A.

DESCRIPTION

69kV TRANSMISSION LINE

The secondary devices are summarized as follows:

NPSI-Felisa Solar Take-Off S/S


ITEM
NO.
A.

SUBSTATION PROTECTION SYSTEM


1

B.

C.

34 | P a g e

DESCRIPTION

13.8/69kV Transformer Protection System, numerical,


transformer differential protection
LINE PROTECTION SYSTEM

69kV Line Protection System (Main 1 - line distance


protection)

set

69kV Line Protection System (Main 2 - directional


phase and ground overcurrent protection)

set

SUBSTATION MONITORING SYSTEM

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

D.

Network Disturbance Monitoring Equipment fully


compatible with NGCP Master Station complete with
accessories and necessary interface devices (DI: 96 &
AI: 32)

Negros PH Solar Inc.

lot

SUBSTATION CONTROL SYSTEM


1

Main Control Switchboard complete with mimic


diagram, meters etc.

lot

Remote Terminal Unit complete with interface


equipment, I/O modules, etc.

lot

Fiber Optic Terminal Equipment, complete with optical


distribution frame (ODF), access multiplexers,
indicators, pigtails, patchcords and other
appurtenances

lot

Fiber Optic Approach Cable, 36 fibers, 1550nm, single


mode

lot

E.

FIBER OPTIC COMMUNICATION SYSTEM

No consideration yet on the civil works and additional electrical works that may only
be determined during the detailed engineering design. Variation works may be
expected depending on actual site conditions.

12.0

Project Cost and Assumptions

Assumption in deriving the project cost is based on accuracy of 10% and already
considered the applicable taxes and contingencies equivalent to same assumptions.
Applicable taxes already considered the applicability of RA 9513 to the proponent.

Acquisition of right-of-way of the line and site, for purposes of this facilities study, are
already excluded including the engineering activities. Interest during construction is
likewise considered for purposes of this interconnection study.

Exchange rates considered is 1US$ to PhP 45.

35 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

For NGCP substation, considering that the existing facilities (Bacolod-San Enrique)
will be used as the interconnection facility, it is assumed that there will be no primary
devices upgrading at the side of NGCPs substation

13.0

Recommendation

The interconnection scheme (configuration and the line), its associated primary
devices and secondary devices (protection arrangement, telecommunication and
SCADA) and metering are presented based on initial assessment and analysis.
However, there are still needed coordination with NGCP as Grid Owner, System
Operator and Wholesale Metering Service Provider on the following:

1. Submission of major equipment and specifications related to interconnection to


conform with the requirements of NGCP. This does not cover however the plants
equipment and specifications including the transformers related to the conversion
from DC to AC and stepping-up to the voltage agreed upon with NGCP;
2. Electrical diagrams and drawings covering the grid assets (i.e., SCADA and
Telecom equipment) shall be approved by NGCP;
3. Procurement of brand acceptable to NGCP will be pursued particularly the
protective equipment;
4. The secondary devices (i.e., SCADA and Telecom equipment) which are all grid
assets per Grid Code will be funded but manufacturers drawings shall be approved
by NGCP;
5. Protection equipment shall be provided, owned, operated and maintained by
NGCP and NPHSI at their respective sides but the latter may consider of engaging
the maintenance services of NGCP;
6. Protection setting shall be consistent with the prescribed settings of NGCP to
coordinate with its current protection scheme; and
36 | P a g e

Interconnection Facilities Study


For Felisa 50 MW Solar Power Plant

Negros PH Solar Inc.

7. NPHSI shall coordinate closely with NGCP for the commissioning and testing of
the solar plants following NGCPs Open Access Policy, Grid Code, OATS Rules
and ERC Resolution No. 7-2014 on the testing of VRE as outline below, the PGC
Minimum Requirements for Large PVS (>20MW):

37 | P a g e

Specific Requirements

Large PVS

2.1 Generating unit


power output
2.2 Frequency withstand
capability
2.3 Reactive Power
capability
2.4 Performance during
network disturbances
2.5 Voltage Control
system
2.6 Active Power Control
system
2.7 Power Quality
4.1 Information
Exchange/SCADA Test

Laboratory
Test

Field Test

Certification

You might also like