This document calculates the advance recovery amount for a construction project. It shows that the current work done is Rs. 14,002,450.23, 90% of the bill of quantities is Rs. 72,265,927.39, and the advance payment was Rs. 13,044,177.25. Based on these numbers, the advance recovery amount is calculated to be Rs. 2,527,476.63.
This document calculates the advance recovery amount for a construction project. It shows that the current work done is Rs. 14,002,450.23, 90% of the bill of quantities is Rs. 72,265,927.39, and the advance payment was Rs. 13,044,177.25. Based on these numbers, the advance recovery amount is calculated to be Rs. 2,527,476.63.
This document calculates the advance recovery amount for a construction project. It shows that the current work done is Rs. 14,002,450.23, 90% of the bill of quantities is Rs. 72,265,927.39, and the advance payment was Rs. 13,044,177.25. Based on these numbers, the advance recovery amount is calculated to be Rs. 2,527,476.63.