You are on page 1of 13

ET CDMA Phases II

ZTE Engineering

Quality Check Manual for

BTS Site

Date: 05/10/2009

Version 1.1

1 / 13
ET CDMA Phases II

Catalog
1 Checking of Design .............................................................................................................................................. 3
2 Site Environment .................................................................................................................................................. 3
2.1 Sealed Room for equipment ..................................................................................................................... 3
2.2 Site Safety................................................................................................................................................. 3
2.3 Site clean................................................................................................................................................... 3
2.4 Spare parts neaten ..................................................................................................................................... 4
2.5 Detection devices ...................................................................................................................................... 4
2.6 Site safeguard ........................................................................................................................................... 5
3 Civil work and grounding system and of the new site .......................................................................................... 5
3.1 Civil work ................................................................................................................................................. 5
3.2 Tower foot................................................................................................................................................. 5
3.3 Earthing net and grounding system .......................................................................................................... 5
4 Tower, generator, solar, shelter installation .......................................................................................................... 6
4.1 Installation accord with the design ........................................................................................................... 6
4.2 Tower anchor bolt ..................................................................................................................................... 6
4.3 Shelter body .............................................................................................................................................. 6
4.4 Cable tray.................................................................................................................................................. 7
4.5 Support bracket for the external Air Conditioner ..................................................................................... 7
4.6 Generator or solar installation .................................................................................................................. 8
5 Lightning Protection and Grounding .................................................................................................................... 8
5.1 Feeder grounding ...................................................................................................................................... 8
5.2 Grounding cables Connect ........................................................................................................................ 9
5.3 Outdoor anticorrosion ............................................................................................................................... 9
5.4 RF lightning arrester ............................................................................................................................... 11
6 BTS Installation and wiring ................................................................................................................................12
6.1 Equipment installation reliable ...............................................................................................................12
6.2 Cable routing ..........................................................................................................................................12
6.3 Power cables ...........................................................................................................................................12
6.4 BTS device .............................................................................................................................................12
6.5 Label .......................................................................................................................................................12
6.6 Antenna ...................................................................................................................................................13
6.7 VSWR .....................................................................................................................................................13

2 / 13
ET CDMA Phases II

1 Checking of Design
There are design documents, and the installation is accord with the design documents.
2 Site Environment

2.1 Sealed Room for equipment


The doors and windows of the new shelter, the cable-through feeder window and holes
leading outside, should be sealed properly. The holes leading outside of the outdoor site should
be sealed properly, so as to keep water, dust, mice and insects from entering the room.

Sealed properly

2.2 Site Safety


There are no any flammable, explosive, corrosive, or heat producing object (such as paint,
gasoline, and stove) in the site room.
2.3 Site clean
The room and the floor are cleaned when the site installation finished.

3 / 13
ET CDMA Phases II

2.4 Spare parts neaten


Spare parts, construction materials and other items should be neatly stacked .The sundries
irrelevant to operation, like cartons or remnant cables or wastes should be removed or packed
up.

2.5 Detection devices


There should be early fire detection devices,such as smog detector, temperature detector,in
the equipment area. There should be fire extinguishers around.

4 / 13
ET CDMA Phases II

2.6 Site safeguard


The ground must be even, there should be wall or fence around the site to protect. This is
ETC's responsibility.
3 Civil work and grounding system and of the new site

3.1 Civil work


The civil work and the concrete intensity should conform to the engineering design. This is
ETC's responsibility.
3.2 Tower foot
The tower-foot should be encapsulated with cement and mortar without surface defects. This
is ETC's responsibility.

Tower foot should be encapsulated with


cement and mortar without surface defects

3.3 Earthing net and grounding system


Earthing net and grounding system construction should conform to the engineering design.
5 / 13
ET CDMA Phases II
This is ETC's responsibility. The cross joints between tower-foot and earth lead are welded
properly without any loose or shaking.
4 Tower, generator, solar, shelter installation

4.1 Installation accord with the design


The tower,generator, solar and shelter installation should conform to the design.
4.2 Tower anchor bolt
The anchor bolt above the foundation should be treated with anticorrosion and theft proof.

4.3 Shelter body


The shelter body should be installed properly and firmly on the groundwork without any
deformation.

6 / 13
ET CDMA Phases II

4.4 Cable tray


The cable tray should be connected well, firmly.

4.5 Support bracket for the external Air Conditioner


The support bracket for the external AC (air conditioner) part should be installed properly and
firmly.

7 / 13
ET CDMA Phases II

4.6 Generator or solar installation


All the bolts and nuts of the generator or solar must be fixed firmly without any loosening.

the blot of solar


fixed firmly

5 Lightning Protection and Grounding

5.1 Feeder grounding


The feeder should be grounded in an applicable way at the following three points: at the
tower platform, in between the tower and the outdoor cable tray, 1m away from the feeder
window outside.
If the tower is over 60m high, the feeder should be grounded once more at the center of the
tower.
If the feeder is laid on the building roof, the feeder should be grounded at the following three
points: 1m away from the antenna pole, 1m away from the roof platform, and 1m away from the
entrance to the equipment room.

8 / 13
ET CDMA Phases II

5.2 Grounding cables Connect


Copper lugs should be used for the ends of the grounding cables. The surface between the
lugs and the grounding bar should be attached tightness.

If the bolts are


not enough, two
grounding cables
can share one
bolt.

5.3 Outdoor anticorrosion


All the outdoor grounding bars and joints are treated with anticorrosion and rust-proof.

9 / 13
ET CDMA Phases II

anticorrosion

anticorrosion

10 / 13
ET CDMA Phases II

anticorrosion

5.4 RF lightning arrester


The grounding cables of RF lightning arrester must be connected reliably to the outdoor
grounding bar.

To outdoor
grounding bar

11 / 13
ET CDMA Phases II

6 BTS Installation and wiring

6.1 Equipment installation reliable


Equipment installation must fix to the ground and the fixing method should be reliable.
6.2 Cable routing
The routing of power cable, signal cables and GND cable should be straight and with proper
addition at the bends..

6.3 Power cables


The copper lugs of the power cable must have a protective casing or wrapped. The power
cable should be without any joint in between, and the insulating layer should be intact and
sound.
6.4 BTS device
There are no sundries in the BTS Cabinet.

6.5 Label
The labels must be uniform and printed clear. The tail of these straps should be in the same
direction.
12 / 13
ET CDMA Phases II

6.6 Antenna
The antenna model, azimuth and suspension height should conform to the design.
The antennas, feeders, grounding cables shall be installed properly and firmly.
6.7 VSWR
The measured standing wave ratio should be smaller than 1.5. It is required to provide the
corresponding VSWR value and the VSWR test diagram.

13 / 13