Removal of existing cyclone fence (left side if you are facing the entrance door of the tank farm)
Positive isolation of liquid and vapor line of tank 3 from the present connection, degassing of
pipeline if needed.
Removal/ uplift of tank 3 (1000AG) from the pedestal
Installation of new 1 x 2000AG tank to where the 1 x 1000AG tank was uplifted
Modification of concrete tank pedestal (as discussed during the site pre-bid).
Modification of the concrete step ladder (as discussed during the site pre-bid).
Note: There were 3x1000AG LPG tank existing in the present location and there should be no downtime
on the customer side during tank upgrading. Therefore tank uplift should be one at a time. There should
be NO HOT WORKS inside the tank farm.