PHYSICAL PROGRESS (Sept - 2010)

Total Percentage
Duration Weigh Actual upto Completed
Sr.no. Description Breakup upto
(Weeks) eage Sept -10
date Activity Total

1 Demolition 6 3% Main Bldg 2% 2.00 3.00 100%


Other 1% 1.00
2 Excavation 6 2% Main Bldg 1.5% 1.50 2.00 100%
others 0.5% 0.50
3 Piling 36 15% Main Bldg(517)11% 11.00
Cafeteria(120)2.75% 2.75 15.00 100%
CMO/Staff (103)1.25% 1.25
4 RCC Below plinth 42 7% Main Bldg 5% 5.00
Cafeteria 1% 1.00 7.00 100%
CMO/Staff 1% 1.00
5 Filling 20 3% Main Bldg 1% 1.00 100%
Cafeteria 1% 1.00 3.00 100% 100%
CMO/Staff 1% 1.00 100%
6 RCC 44 21.5% Main Bldg 15.5% 14.25 92%
Cafeteria 3% 3.00 20.25 100% 94%
CMO/Staff 3% 3.00 100%
7 Antitermite 41 2% Main Bldg 1% 1.00
Cafeteria 0.5% 0.50 2.00 100%
CMO/Staff 0.5% 0.50
8 BBM Internal 52 9% Main Bldg 6% 4.75 79%
Cafeteria 2% 2.00 7.75 100% 86%
CMO/Staff 1% 1.00 100%
9 Plaster Int./ Ext. 56 9% Main Bldg 6% 4.25 71%
Cafeteria 1% 1.00 7.25 100% 81%
CMO/Staff 2% 2.00 100%
10 Water proofing 82 4% Main Bldg 3% 1.75 58%
Cafeteria 0.5% 0.50 2.75 100% 69%
CMO/Staff 0.5% 0.50 100%
Floor/ dado/ false
11 ceil 37 5% Main Bldg 3% 2.15 72%
Cafeteria 1% 1.00 4.15 100% 83%
CMO/Staff 1% 1.00 100%
Plumbing/ Fire
12 Fighting 41 2% Main Bldg 1% 0.30 30%
Cafeteria 0.5% 0.45 1.25 90% 63%
CMO/Staff 0.5% 0.50 100%
Door / window &
13 glaz. 25 3% Main Bldg 2% 0.80 40%
Cafeteria 0.5% 0.50 1.80 100% 60%
CMO/Staff 0.5% 0.50 100%
14 Electrical 95 5% Main Bldg 3% 0.10 3%
Cafeteria 1% 0.70 1.75 70% 35%
CMO/Staff 1% 0.95 95%
15 Painting/ Finishing 19 5% Main Bldg 3% 0.30 10%
Cafeteria 1% 0.85 2.15 85% 43%
CMO/Staff 1% 1.00 100%
16 SWD & Road 10 1.5% SWD 1% 1.00 1.50 100% 100%
Road 0.5% 0.50 100%
Lift/pump/Smoke
17 Det. 16 2% 0.50 0.50 25% 25%
Miecellenous
18 (Compound wall) 4 1% 0.90 0.90 90% 90%
100% 84.00

Anticipated Cumulative physical progress 100.00%

Actual cumulative physical progress 84.00%