Work shall be carried out by the party as per the detail working drawings to be
issued to them by EPI in phases. They may visit the site and see layout of the
buildings and ascertain themselves with the approach to the work site etc.
Party shall carry out the works as per Indian safety regulation.
Excavation shall be carried out in all kinds of soil, (soft and hard),
boulder studded seal etc. Excavated pit shall be always kept dry by
pumping out of sub-soil / rain water during construction. In case of
acidic soil, acid pumps shall be used otherwise normal dewatering pump
shall be used. During excavation all underground / over ground facilities
like bables, pipes etc. to be protected with due care. Nearby existing
facilities, foundation must be retained, in case of damage the same shall
be rectified by the Party.
1.1.. During excavation shoring work shall be provided and proper slope to be
kept during cutting. Necessary site plan shall be provided by EPI. If good
soil at designed depth is not found then further excavation shall be done
to reach at strong foundation level.
1.2 After completion of foundation, back filling shall be done with good
excavation earth in layer of 150 mm and well-compacted remmed,
watered before next layer is laid.
1.3 Surplus excavation earth shall be dumped at allotted place within a lead
of 1 KM inside plant.
2 Concrete :
2.1 Plain cement concrete (PCC) grade as per BOQ shall be used at base of
foundation for column, tie beam at ground level, Equipment foundation,
base of trench, brick foundation, underground pipe.
2.5 All coarse & fine aggregate shall conform to IS:383-1970. Fine aggregate
shall be of approved river bed and coarse aggregate shall be of approved
black trap-stone.
3 D. P. C :
4 Reinforcement :
4.1 Reinforcing (R/F) bars shall be either cold twisted deformed (CTD) or
thermo mechanically treated (TMT) as per IS:1786-1985. The same will
be supplied by EPI
4.2 R/F shall be made free from mill scales, rust grease or oil before
concreting.
4.3 Cover to R/F shall be provided by use of cement sand mortar block (1:4).
5 Shuttering :
5.1 Shuttering work shall conform to IS:456-2000. This shall preferably be
made of steel/Wooden Batton/Plyboard. Maximum use of ply/wooden
shuttering shall be 3(Three) times.
7 Brickwork :
9 Flooring :
9.1 For building top of floor will be IPSS with 40 mm thick M-15 concrete
cast in panels(1M/1M) having 2 mm thick alluminium metal strip,
divider. Floor should be free from cracks & crevices.
Acid resistant non-slippery flooring for all areas handling with acid shall
be provided.
On the above primer, mastic compound shall be laid as per IS:9510. The
specific gravity of mastic shall be 2 and penetration at 25 deg.C
(100gm/5mm) shall be 1. the liner thickness shall be 15 mm. Test
certificate for the above work shall be submitted to EPI’s Client
9.3.3Tiles :
10.1 Process building shall have adequate nos of wooden doors. The doors
shall be wooden single or double leaf. Door frame shall be of teak wood
and shutters shall be of teak wood. All wood shall be well seasoned by a
suitable process and suitable preservative treatment shall be given on it
panel shall be 40 mm thick and frame 125 mm x 75 mm, shutter shall
be 20 mm thick. Paints will be supplied by EPI.
10.2 All windows shall be of wooden frame with glazing as per IS standard. All
glazing shall be made of 6 mm thick wired glass panes. Paints will be
supplied by EPI.
10.3 Wherever utility / non-explosive buildings require steel doors this shall
be made of MS steels fixed on angle frames and bracings. Airtight steel
doors in motor / control room shall be provided.
(iii). Chajjas of adequate size with side drops and front drops shall be
provided to the windows and front door opening to stop rain beat hitting
the fittings.
(iv). Cast Iron/PVC rain water pipes shall be provided for all buildings,
wherever required. The rain water pipes shall have grating at top and
shoe at the bottom. The joints shall be jointed with clamp and cement or
mortar. The arrangement should be such that there should be free of
rain water through pipes.
12 Paintings
(i..) Steel Structures, after erection shall be clear off rust and scale and given
2 coats of red oxide zinc chromate primer finished by 2 coats of
Synthetic enamel. Equipments shall be given red oxide primer finished
by Synthetic enamel.
(ii).. All walls of buildings shall be given two coats of colour washes on the
external surface and two coats of lead free paint on internal surface and
ceiling.
(iii.) Red oxide zinc chromate primer will be in the scope of the Party. EPI will
supply the Paint.
All the materials for foundation bolts, nuts insert shall conform to
IS:1363 (Latest)
14 Drains :
15 Pathway / Gantry :
(i). From the main roads all the buildings will be connected by pathway /
gantry 3.0 M (minimum) width. However, the width will be fixed as per
layout and width will be maximum of 4.5 M.
(ii). Over the compacted earth there will be 150 mm hardcore of broken
stone. There will 100 mm thick RCC laid over stone. Also 80 mm thick
stone kerbs, RCC kerbs either side of the pathway / gantry shall be laid
with suitable gap for draining of rain water.
(iii). All pathway / gantry near the buildings shall be leveled. All pathways
shall be constructed first up to WBM level and RCC at the top shall be
laid after erection / movement of heavy machineries for entry in to the
building is over.
16 Water Supply :
(i). Water supply lines within the battery limit up to the individual building
and inside the building as per requirement shall be planned. The water
mains shall however be designed keeping in view the ultimate
requirements of the plant. The supply system shall be designed by laying
suitable pipe lines considering the present requirement and supply shall
be taken from a point one meter outside the battery limit. Supply line for
drinking water requirements for employees shall also be considered. The
pipe connections for the water supply for process water, fire fighting and
drinking water will be available at one metre outside the battery limit for
connection by the Party.
18 Anti-Termite Treatment :
(iii). All construction materials including cement & steel have to be arranged
by the Party themselves.