BILL OF MATERIALS /COST ESTIMATE

Item no. Description Quantity Unit Unit Cost Amount


I. MOBILIZATION
1. EARTHFILL 40 cu.m 500 20,000

II. MASONRY WORKS

1.CEMENT(PORTLAND) 512 bags 193 98,816


2.SAND 34 cu.m 400 13,600
3.GRAVEL 21 cu.m 800 16,800
4.CHB(10x20x40) 4,126 pcs. 7 28,882

III. REINFORCEMENTS

1.STEEL BARS
6m-12mm dia. 50 pcs. 172 8600
7.5m-12mm dia. 15 pcs. 225 3375
9m-12mm dia. 8 pcs. 268 2144
10.5m-12mm dia. 90 pcs. 310 27900
12m-12mm dia. 6 pcs. 354 2124

7.5m-10mm dia. 202 pcs. 164 33128


12m-10mm dia. 18 pcs. 256 4608

2.#16 GI WIRES 23 kgs. 75 1,725

IV. FORMWORKS/SCAFOLDS

1.PLYWOOD
1.2 X 2.4 m 49 pcs. 360 17,640

2. 2" X 2" 2305 bd.ft. 39 89,895

3. 2" X 3" 752 bd.ft. 39 29,328

V. TRUSSES

6m.-2" X 2" x 1/4" 27 pcs. 475 12,825


ANGLE BAR

VI. ROOFING

1.RIB TYPE
PRE PAINTED
1.1. 4.0 m long 16 sheets 332 5,312
1.2. 5.0 m long 30 sheets 350 10,500

2. PLAIN GI SHEET 8 pcs. 285 2,280

3.PLYWOOD
1/4" X 4" X 8" 21 pcs. 385 8,085

VII. TILE SETTING

1. 8" X 8" 127 pcs. 13 1,651

2. 8" X 12" 378 pcs. 21.25 8,032.50

3. MORTAR 3 bags 60 180


4. WHITE CEMENT 14 kgs. 25 350

VIII. FIXTURES

LAVATORY 2 sets 3,500 7,000

T & B PACKAGE 2 sets 4,200 8,400

KITCHEN SINK 1 set 656 656

FAUCET 2 sets 260 560

SHOWER/VALVE 2 sets 385 770

FLOOR DRAIN 2 sets 65 130

IX. DOORS
6 sets 3800 11,400

X. WINDOWS

1.8m x 1.2m 1 set 3600 3600


1.2m x 1.1m 4 sets 2700 10800
o.6m x 0.6m 2 sets 1600 3200

XI. ELECTRICAL 51,169.65

XII. PLUMBING 30,701.79

XIII. PAINTING

1. BOYSEN FLAT LATEX 12 gallons 475 5,700

2.BOYSEN GLOSS LATEX 10 gallons 540 5,400

3.FOR FINAL COATING 9 gallons 650 5,850

4.NEUTRALIZER 5 liters 90 450

EXCLUDING:plumbing, fence, gate, screen and landscaping


COST OF MATERIALS 593,567.94
LABOR COST 237,427.18