BSC6810 System Commissioning

www.huawei.com

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Foreword

The commissioning is performed after the hardware installation The commissioning ensures the RNC works properly as designed RNC commissioning procedure

Commissioning RNC hardware Commissioning software loading Verifying all interfaces Verifying RNC services Integrating the RNC into M2000

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page2

References

RNC Commissioning Guide

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page3

Objectives

Upon completion of this course, you will be able to:

Describe the procedure of RNC commissioning Perform the steps in RNC commissioning

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page4

Contents
1. Introduction to RNC Commissioning 2. Procedure of RNC Commissioning

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page5

Introduction to RNC Commissioning

Definition of RNC Commissioning

The commissioning of equipment, RNC loading, interfaces, and services after hardware installation To ensures that the RNC works as designed

RNC Commissioning Prerequisites

Passing hardware installation acceptance and powering-on test At least one NodeB and one set of CN equipment available

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page6

Introduction to RNC Commissioning

RNC Commissioning Preparations

BAM and LMT application software are ready License file is ready MML command script for initial configuration is ready

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page7

Contents
1. Introduction to RNC commissioning 2. Procedure of RNC commissioning

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page8

Contents
2.

Procedure of RNC commissioning


2.1 Commissioning RNC Equipment

2.2 Verifying interfaces (Iub, Iu-CS, Iu-PS, Iur) 2.3 Handling Alarms During RNC Commissioning 2.4 Verifying RNC Services 2.5 Integrating the RNC into the M2000 2.6 Creating RNC Scheduled Tasks 2.7 Checking RNC Commissioning Results

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page9

Procedure of RNC commissioning

Commissioning RNC Equipment

Step 1 Commissioning BAM

Install the BAM application in the active workspace Check the operation of the BAM application

Step 2 Commissioning LMT

Install LMT application Connect LMT to the BAM Start the local maintenance terminal

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page10

Procedure of RNC commissioning

Commissioning RNC Equipment

Step 3 Loading RNC software and data file

Generating RNC data file


Clear the data in the BAM database (RST DATA) Generate the data file in offline state (SET OFFLINE & FMT DATA)

MML Configuration command Configuration console

Configuration Management module Reset to load

Format

DB

*.dat

FAM board

BAM
Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved. Page11

Procedure of RNC commissioning

Commissioning RNC Equipment

Step 3 Loading RNC software and data file

Setting RNC loading parameter (SET LODCTRL ) Loading RNC


Reset RNC (RST SYS) The boards automatically load software and data file from the BAM Start the loading progress window to monitor the loading process

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page12

Procedure of RNC Commissioning

Commissioning RNC Equipment

Step 4 Verifying the license

Save the license in BAM Active Workspace Installation Directory\FTP\License

Activate the license (ACT LICENSE) Check the license consistency between host and BAM (CMP LICENSE)

Display the configuration of license (DSP LICENSE)

Step 5 Verifying Switchover Between Active and Standby Boards (SWP BRD)

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page13

Procedure of RNC Commissioning Iu-PS, Iur) Verifying interfaces (Iub, Iu-CS,

The protocol structure of terrestrial interfaces


Control Plane Application Protocol
User Plane

Radio Network Layer

User Data

Transport Network User Plane

Transport Network Control Plane ALCAP

Transport Network User Plane

Transport Network Layer

Signaling Bearer

Signaling Bearer

Data Bearer

Physical Layer

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page14

Procedure of RNC Commissioning

Verifying interfaces (Iub, Iu-CS, Iu-PS, Iur)

Check the status of different objects Verifying Iub interface

Checking physical link (DSP E1T1, DSP ETHPORT) Checking control plane (DSP SAALLNK, DSP SCTPLNK, DSP IUBCP)

Checking user plane (DSP AAL2PATH, DSP IPPATH)

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page15

Procedure of RNC Commissioning

Verifying interfaces

Verifying Iub interface

Checking management plane


To be sure NodeB can be operated at remote end

Checking cell status (DSP CELL)

Verifying Iu-CS, Iu-PS and Iur interfaces

The procedures and commands are similar with those in Iub interface

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page16

Procedure of RNC Commissioning

Handling Alarms During RNC Commissioning

Clearing the alarms if something wrong happen

Verifying RNC Services

To be sure RNC can provide services defined in license file

Basic services
Voice service, CS stream service, PS service, mobility management, and OM management

Feature services
Inter-system handover, HSDPA service, HSUPA service, MBMS service, and location service

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page17

Procedure of RNC Commissioning


Integrating the RNC into the M2000 Creating RNC Scheduled Tasks (back up tasks) Checking RNC Commissioning Results
iManagerTM M2000

DCN

Copyright 2007 Huawei Technologies Co., Ltd. All rights reserved.

Page18