CNG HO X HI CH NGHA VIT NAM C LP T DO HNH PHC Lai Chu, ngy 22 thng 07 nm 2011
3. i din nh thu thi cng: Cng ty c phn xy dng cng trnh ngm Trung Vit
vy gng hm thi cng rt yu dn n bin hm m rng hn so vi h s thit k (tp bn v N0 109-06-05-02-1) 2. Bin php x l n v thi cng tip tc khoan o hm v kt hp vi TVGS, BQLDA theo di cht tnh hnh a cht gng o. Nu a cht yu hn th phi tin hnh dng thm v I15 vi bc chng l 1m v an vi thp 12, a b = 20 20cm nhm m bo an ton thi cng IV. Kt lun Cc bn cng thng nht cc ni dung nu trn. Ton b khi lng pht sinh s c cn b BQLDA v TVGS xc nhn lm cn c nghim thu thanh ton sau ny. Yu cu Cng ty c phn xy dng cng trnh ngm Trung Vit khn trng trin khai thc hin ngay cc cng vic pht sinh nu trn, sm hon thnh v bn giao trin khai cc cng vic tip theo. Bin bn c lp thnh 07 bn, mi bn tham gia gi mt bn c gi tr nh nhau lm c s thc hin.
N V THI CNG T VN GIM ST BQLDA T MNG KIM II