You are on page 1of 89

PROJECT IMPLEMENTATION

STATUS REPORT
OF
CENTRAL SECTOR PROJECTS
Costing ` 150 Crores & above
(July-September, 2010)

HPCL-Mumbai Refinery

Government of India
Ministry of Statistics and Programme Implementation
Infrastructure and Project Monitoring Division
Sardar Patel Bhavan, Sansad Marg
New Delhi-110001
Website: www.mospi.gov.in
www.cspm.gov.in

PROJECT IMPLEMENTATION
STATUS REPORT
OF
CENTRAL SECTOR PROJECTS
Costing ` 150 Crores & above
((JJuullyy--SSeepptteem
mbbeerr,, 22001100))

Government of India
Ministry of Statistics and Programme Implementation
Infrastructure and Project Monitoring Division
Sardar Patel Bhavan, Sansad Marg
New Delhi-110001
Website: www.mospi.gov.in

CONTENTS
Pages
FOREWORD

ABBREVIATIONS USED IN THE REPORT

HIGHLIGHTS

INTRODUCTION

7-8

PART-I

9-32

OVERVIEW

Appendix-I -

List of completed projects during


July 2010 to September 2010

Appendix-II-

List of the Additional Delay projects


(as on 30-09-10).

Appendix-III-

Major factors for delay

Appendix-IV-

Summary of the Central Sector Projects


in States/UTs (as on 30-09-10)

Appendix-V-

Summary of the Mega Central Sector Projects


in States/UTs (as on 30-09-10)

Appendix-VI-

List of delayed Central Sector Projects


(as on 30-09-10)

Appendix-VII-

Summary of Central Sector Projects due for


completion in current financial year (2010-11)
(as on 30-09-10)

FOREWORD
The Quarterly Project Implementation Status Report on Central Sector Projects (each
costing Rs.150 Crores and above) for the quarter July-September, 2010 covers 606 projects. It
provides information on 143 mega projects (each costing Rs.1,000 Crores and above), 463 major
projects (each costing between Rs.150 Crores and Rs. 1000 Crores) The anticipated cost of these
606 projects is Rs 7,41,428.63 Crores. The total expenditure till 31-09-2010 was Rs 3,20,808.36 Crores
which is 43.27 % of the total estimated cost. Against an approved outlay of Rs. 80,245.01 Crores for
2010-11, the expenditure incurred till September, 2010 is Rs 38,072.09 Crores. The outlay for the
projects of Road Transport & Highways and Telecom sectors has not been reported by the
authorities. However, the expenditure in these sectors has been taken into account (Table 5 of the
overview). At the beginning of the year 2010-11, 293 projects were scheduled for completion
during the year. By the end of the 2nd quarter, another 36 projects were added for completion by
March, 2011. Overall, 49 projects have been commissioned during 2010-2011. Part I of the Report
gives an overview of implementation of projects during the quarter. Part II gives a sectoral analysis
and the status of individual projects.
2.
Out of a total of 606 Projects on our monitor, there are 103 projects without approved
completion schedules. 103 projects do not have anticipated dates of completion (DOC). The major
chunk of these projects i.e. 61 are in the Railways sector. Sector-wise details of the projects showing
status with respect to original and latest schedules, for the quarter ending September 2010 is given
below:-

Sector wise Implementation Status of Project with reference to original and latest schedule

Sector/ Month

Ahead
Original
Latest

On Schedule
Original
Latest

Delayed
Original
Latest

(Number of Projects)

Without DOC
Original
Latest

Atomic Energy

Civil Aviation

Coal

21

39

20

Fertilisers

Mines

Steel

12

12

Petroleum

36

42

35

30

Power

38

38

38

38

Health & Family Welfare

Railways

40

33

30

36

61

61
15

Road Transport & Highways

116

116

15

Shipping & Ports

12

11

Telecommunications

43

42

Urban Development

Water Resources

Total:

16

12

165

184

316

300

103

103

3.
Time and cost overruns have been a major problem affecting the central sector projects. The
analysis shows that 208 projects have accounted for a cost over run of Rs. 1,40,644.40 Crores i.e.
81.30 % with respect to their original sanctioned cost during the July-September, 2010 quarter.
However the position improves in case of anticipated/latest completion schedule and shows that
1

167 Projects accounts for a cost overrun of Rs 87,906.00 Crores i.e. 61.8% during the period JulySeptember, 2010. The analysis further shows that 84 Projects suffer from both time and cost
overrun during the period. (Table-6,7,8 of the overview).
4. The following chart depicts the number of projects on schedule and delayed with respect to the
total projects. There is an increase of 3.27 % in terms of percentage of delayed projects with respect
to their original schedule as compared to June, 2010. In absolute terms there is a decrease in the
number of projects on schedule as compared to that of in June, 2010. 123 Projects have reported
additional delays as compared to the position in the Previous Quarter ending June 2010. There have
been slippages in the range of 1-60 months in respect of projects relating to the additional delayed
projects in the Atomic Energy(1), Coal(3), Fertilisers(4), Petroleum(14), Power(18), Railways(5),
Road Transport and Highways(53), Shipping & Ports(2), Steel(5), Telecommunications(17) and
Urban Development(1). List of projects showing Additional Delayed Projects with respect to
original schedule compared to Last Quarter i.e. June 2010 is enclosed as Appendix 2.

No. of projects

1200
1000

800
600
400
200

232370
108
234 401
148
239 414
123
458
215
112
418
222
88
211 469
120
174 462
131
454
144
135
540
213
148
568
211
152
674
263
185
742
265
245
882
301
343
909
243381
925
445
211
1005
250 481
600
306
168
316 606
165

Projects on schedule and Delayed (excluding projects without Date of


Commisioning) with reference to total number of projects

Total Project
Delayed
Projects
Projects on
schedule

Sep,2010

June,2010

Mar,2010

Mar,2009

Mar,2008

Mar; 2007

Mar, 2006

Mar, 2005

Mar, 2004

Mar, 2003

Mar, 2002

Mar, 2001

Mar, 2000

Mar, 1999

Mar, 1998

Mar, 1997

Mar, 1996

Mar, 1995

Years

The chart below gives the trend of percentage of projects delayed. The increase during AprilSeptember 2010 is due to exclusion of projects between Rs. 20 150 crore which have lesser
delays than larger projects.

Trend of projects running behind schedule w.r.t original schedule


70.00 62.22

62.70
58.22
58.3557.73
53.11
46.94
44.99

60.00
50.00

48.1147.86 52.10
41.91

39.44 37.1539.0238.80
37.66
34.13
31.72

40.00
30.00
20.00
10.00

Year(s)
2

Sep,10

Mar,10

Mar, 09

Mar,08

Mar-07

Mar-06

Mar-05

Mar-04

Mar-03

Mar-02

Mar-01

Mar-2000

Mar-99

Mar-98

Mar-97

Mar-96

Mar-95

Mar-94

0.00
Mar-1993

Percentage of projects

5.

6. There has been a continuous decline in the extent of time and cost overruns which can be
attributed to closer monitoring and system improvements by the Ministries concerned, with the
active support of this Ministry. An analysis of cost overruns in the last 20 years with respect to the
originally approved cost shows that the cost overrun has declined from 61.6% in March, 1991 to
12.06% till March, 2008. There is an upward trend from March, 2008 to 14.72 % in March 2010
and it has reached to 21.1% in September 2010 mainly due to exclusion of projects costing to Rs.
20 -150 crores from the monitoring system as these had lower cost overrun compared to major
projects above Rs. 150 crores. The increase is also due to steep rise in prices of cement and steel in
2006-07 followed by recent international on recession. The chart below gives the trend of cost
overruns (with reference to originally approved cost).

% of cost overrun

Trend of Cost Overrun w.r.t Original cost


70 61.6
56.857.5
53.9
60
51.4
46.9 45
50
40

Overall %
cost overun

40.9
37.3
36 36
26

30
20

21.1
22.322.4
13.45
17.717.4
14.51
12.06 14.72

10
Sep 2010

Mar 2010

Mar 2009

Mar 2008

Mar 2007

Mar 2006

Mar 2005

Mar 2004

Mar 2003

Mar 2002

Mar 2001

Mar 2000

Mar 1999

Mar 1998

Mar 1997

Mar 1996

Mar 1995

Mar 1994

Mar 1993

Mar 1992

Mar 1991

Years

7.
While the cost overruns due to general inflation cannot be avoided, the escalation on
account of delays can be minimized. The institution of Standing Committees in each Ministry to
review the time and cost overruns in projects and to fix responsibility, thereof, has to be made more
effective. It is hoped that through focused attention and constant monitoring and efficient
facilitation in resolving the problems by the Ministry of Statistics and Programme Implementation
and by the administrative Ministries/Departments, the declining trend in time and cost overruns in
project implementation can be accelerated. Closer monitoring by Ministries would be necessary to
ensure timely completion of projects scheduled for 2010-2011

(Pankaj Jain)
Additional Secretary to the Government of India
Ministry of Statistics and Programme Implementation

Abbreviations used in the report


AAI
AERB
AIBP
AIR
APW
ATU
BHEL
BHPV
BLU
BOLT
BPST
CCEA
CCU
CDS
CDU
CEA
CEC
CHP
CLW
CMPDI
COS
CPP
CRIS
CRL
CSL
CTU
DAE
DB
DCME
DGMS
DHDS
DOC
DOT
DVC
ECL
EIL
EMP
EOT
ESP
FCCU
FE
FOIS
FPU
GAIL
GC
GDS
GIS
GT
GTPP
HCU
HEC
HEMM
HEP
HPCL
HRT
HSCL
HVDC
IAAI
ICT
IDC
IFFCO
IMG
IOC
IPCL

Airport Authority of India


Atomic Energy Regulatory Board
Accelerated Irrigation Benefit Programme
All India Radio
Active Process Water
Atomic Treating Unit
Bharat Heavy Electricals Ltd.
Bharat Heavy Plates & Vessel Ltd.
Boiler Light Up
Build , Operate, Lease & Transfer
Bureau of Parliamentary Studies & Training
Cabinet Committee on Economic Affairs
Catalytic Cracking Unit
Crude Distribution System
Crude Distillation Unit
Central Electricity Authority
Central Empowered Committee
Coal Handling Plant
Chittaranjan Locomotive Works
Central Mine Planning & Design Institute
Committee of Secretaries
Captive Power Plant
Centre for Railway Information System
Cochin Refinery Ltd.
Cochin Shipyard Ltd.
Crude Topping Unit
Department of Atomic Energy
Dumb Barges
Digital Circuit Multiplexiing Equipment
Director General Mines Safety
Diesel Hydro Desulphurisation project
Date of Commissioning
Department of Telecommunication
Damodar Valley Corporation
Eastern Coalfields Ltd.
Engineers India Ltd.
Enivronment Management Plan
Electrical Overhead travelling crane
Electrostatic Precipitator
Fluidised catalytic Cracker Unit
Foreign Exchange
Freight Generation Information System
Feed Preparation Unit
Gas Authority of India Ltd.
Gauge Conversion
Gateway Digital Switch
Gas Insulated Station
Gas Turbine
Gas Turbine Power Plant
Hydro- cracker Unit
Heavy Engineering Corporation
Heavy Equipment & Mining Machinery
Hydro Electric Project
Hindustan Petrochemicals Ltd.
Head Race Tunnel
Hindustan Steel Construction Ltd.
High Voltage Direct Current
International Airport Authority of India
Inter Connecting Transformer
Interest During construction
Indian Farmer Fertilizer Co-operative
Inter Ministrial Group
Indian Oil Corporation
Indian Petrochemicals Ltd.

KV
L&T

Kilo Volts.
Larsen & Toubro

LEP

Life Extension Program

LOI
LPG
LSTK
MAMC
MFL
MGCL
MIS
MMSCMD
MMT
MOE&F
MT
MTY
MU
MW
NALCO
NBCC
NCL
NEC
NEEPCO
NFL
NH
NHPC
NIRE
NIT
NJPC
NLC
NMDC
NPC
NRL
OB
OC
OECF
ONGC
OPGC
P&M
PERT
PHT
PIB
PSLW
QRC
RAPP
RCE
RCF
ROB
ROH
RTU
SAIL
SCI
SDH
SG
SP
ST
STPS
SSS
SUR
SWSU
TBM
TG
TPA
TPS
TPY
UG
ULDCS
VDU
WHRB

Letter of Intent
Liquified Petroleum Gas
Lump sum Turnkey contract
Minning & Allied Machinery Copn.
Madras Fertilizer Ltd.
Madras Gas Cracker Complex
Management Information System
Million Metric Standard Cubic Meter day
Million Metric Tonnes
Ministry of Environment & Forest
Metric Tonnes
Metric Tonne per year
Million Unit
Mega Watts
National Aluminium Company
National Building Construction Copn.
Northern coalfields Ltd
North East Council
North-Eastern Electric Power Corporation
National Fertilizer Ltd.
National Highway
National Hydro-Electric Power Corporation
National Institute of Renewable Energy
Notice Inviting Tender
Nathpa Jhakri Power Corpn.
Neyveli Lignite Corpn.
National Mineral Development Corpn.
Nuclear Power Corporation
Numaligarh Refinery Ltd.
Over burden
Opencast
Overseas Economic Co-operation Fund
Oil & Natural Gas Commission
Orissa Power Generation Corporation
Plant & Machinery
Project Evaluation & Review Technique
Primary Heat Transport
Public Investment Board
Powered Support Longwall
Quick Roll Changer
Rajasthan Atomic Power Plant
Revised Cost Estimates
Railway Coach Factory
Road Over bridge
Regular Overhauling
Remote Terminal Unit
Steel Authority of India Ltd.
Shipping Corporation of India
Synchronous Digital Hierarchy
Steam Generator
Self Propelled
Steam Turbine
Super Thermal Power Station
Sardar Swaran Singh
Sulphur Recovery Unit
Sour Water Stripping Unit
Tunnel Boring Machine
Turbo Generator
Tonnes Per Annum
Thermal Power Station
Tonnes per year
Under Ground
Unified Load Despatch & Communication Scheme
Vaccum Distillation Unit
Waste Heat Recovery Boiler

HIGHLIGHTS
Total number of projects on the monitor
Total Original estimated cost of these projects
Total latest approved cost of these projects
Total anticipated cost of these projects
Total Expenditure
Overall percentage cost overrun with respect to original estimates
Overall percentage cost overrun with respect to latest sanctioned estimates
Total number of projects showing cost overrun w.r.t original approved cost
Total number of projects showing time overrun w.r.t original Schedule
Percentage cost overrun in 313 delayed Projects
No. of projects due for commisioning during the year
No. of projects completed during the year
Total Cost ofthe completed projects

606
612254.28 Crore
660174.16 Crore
741428.63 Crore
320808.36 Crore
21.10%
12.31%
208
313 (Ranging from 1 to 225 months)
22.91%
329
49
Rs. 42,101 Crore
Rs.
Rs.
Rs.
Rs.

INTRODUCTION

1.
The Ministry of Statistics and Programme Implementation (MOSPI) is the apex-level central
monitoring organisation of the Government of India for Central Sector Projects costing Rs.150
Crores and above.
2.
As the apex institution for monitoring, the Ministry of Statistics and Programme
Implementation has initiated several measures to improve the systems and procedures relating to
project formulation, implementation and monitoring. The Infrastructure and Project Monitoring
Division (IPMD) of the MOSPI has strengthened the institution of the MOU system through
introduction of project milestones, adoption of network-based monitoring, extensive training of
project managers, prioritization of projects with reference to available resources and several other
project-based interventions. A host of other measures like amendments to the Land Acquisition
Act, development of a Standard Rehabilitation Package, On-line Computerised Monitoring System
(OCMS), etc. are under progress, by other Ministries and this Ministry.
3.
Time and cost overruns in projects in an environment of uncertainties, inadequate funding,
delay in land acquisition, law and order problems, general escalation in costs, and high cost of
capital cannot be eliminated altogether; but these can be controlled by suitable measures. The
measures highlighted above have definitely brought about improvements in the project
implementation scenario. A study carried out by the Ministry shows that the cost overruns in
projects with respect to original costs have come down from 62% in March, 1991 to 21.1% in
September 2010
4.
The MOSPI has been monitoring projects of different sectors of the economy. A two-tier
system of monitoring is adopted. While all projects are monitored on quarterly basis, the major
projects (costing between Rs.150 Crores and Rs.1000 Crores) and mega projects (costing over
Rs.1000 Crores) are monitored on a monthly basis. Based on the computerised data base and
comments furnished by the project authorities/administrative Ministries and in-house analysis, the
Infrastructure and Project Monitoring Division (IPMD) of the Ministry prepares Monthly Flash
Reports in respect of the major and mega projects. On the directions of the Prime Ministers Office
a special report is being prepared for the Prime Ministers Office on Projects costing Rs. 1000
Crores and above from the quarter ending June, 2009 bringing out major problems in
implementation. The Quarterly Status Report is brought out in respect of all projects costing Rs.
150 Crores and above. The present report presents a macro analysis of the projects in 15 sectors on
the monitor of the MOSPI during the period July-September 2010
5. General Improvements in Project Management.
5.1
Being the central monitoring agency of the Government of India, IPMD of MOSPI has been
able to document problems faced by project authorities in different sectors. Suggestions, from time
to time, and various remedial measures to be adopted for better implementation of projects have
also been given in various fora. The Division is engaged in examining the causes of time and cost
overruns in projects and identifying bottlenecks during implementation. It also examines specific
projects to fix responsibility for overruns. The Division has been creating awareness for bringing in
qualitative change in the system of project management and implementation, by organizing
workshops and seminars for the North Eastern States and newly created States.
5.2
The IPMD is assisting the Parliamentary Standing Committee of Finance and Committee of
Secretaries to bring second stage reforms of extant procedures and approvals of projects.

6.

Past Management Initiatives and System Improvements

6.1
The status of implementation of projects is continuously reviewed by officers of the
Ministry of Statistics and Programme Implementation, Planning Commission, Cabinet Secretariat
and the Prime Ministers Office. Particular attention has been paid to major factors, like delay in
land acquisition, fund constraints, delay in award of contracts and civil works, supply of equipment,
etc. Efforts have also been made to identify system deficiencies relating to project formulation,
functioning of Empowered Committees, Contract Management System and Arbitration.
Accordingly, some policy issues have been identified to minimise delays. Some of the recent
management initiatives being followed up by the MOSPI are:
6.2.1 Amendments to the Land Acquisition Act: Ministry of Rural Development after detailed
consultation with the Central and State Governments, got the Amendment Bill to the Land
Acquisition Act introduced to the Lok Sabha in December, 2007. Ministry of Rural Development
also got the National Policy on Resettlement notified on 31st October, 2007. A bill in this regard
was also introduced in the Lok Sabha in December, 2007. Both the Bills are under evaluation of the
Standing Committee of the Ministry of Rural Development.
6.2.2 Standardisation of the Contract Management System: The Policy issues relating to
standardisation of contract documents have been examined by the MOSPI, particularly in the light
of constraints in award of contracts, reasons for failure of contracts, poor contract management, etc..
The Standard Contract Management System consisting of (i) Standard Contract Clauses and (ii)
Standard General conditions of contract approved as guidelines for adoption at the National level
have already been released. Efforts are being made to remove other weaknesses in the Contract
Management System in India. Efforts are also being made to improve institutional arrangements for
efficient management of arbitration.
6.2.3 Standing Committees: The institution of Standing Committees in each Ministry to review
the time and cost overruns in projects and to fix responsibility thereto has been made more effective
by introducing a system of furnishing an Action Taken Report (ATR) on the recommendations of
these Committees while recommending proposals for Revised Cost Estimates for approval of the
PIB/CCEA. Submission of ATR is mandatory for Revised Cost Estimates (RCE) approval by
PIB/CCEA.
6.2.4 Reforming Extant Procedures for Project Formulation, Implementation and
Monitoring: The Ministry carried out a detailed study on the various types of clearances (103
types), analysed their relevance in the present environment and made the findings available to a
High Level Committee headed by Shri V. Govindrajan. The ministry assisted the Committee to
bring out its report in two volumes on Extant Procedures for Project Formulation, Appraisal,
Implementation and Monitoring. These recommendations were accepted by the Government.
7.

The macro analysis of 606 Projects under implementation as on 30-09-2010 is given in Part-I.

8.

Part-II of the Report gives sector-wise status of each project.

PART-I
PROJECT IMPLEMENTATION STATUS
(July-September, 2010)
OVERVIEW
1. The report presents an overview of the projects under implementation, indicating sector-wise
analysis of time/cost overruns, with respect to approved schedules and incremental time/cost overruns reported during the quarter July-September, 2010. The overview also includes factors for
delay, gestation period, fund requirement, etc. and analysis of projects due for commissioning and
those actually commissioned.

2. During the year 2010-2011, in all 49 projects have been completed. The list of these 49 projects
is enclosed and may be seen as Appendix-I. As on 01-04-2010, 293 projects were expected to be
completed in various sectors during the year 2010-2011. In addition, 36 more projects were added
for completion during the Quarter under reference i:e June-September-2010. Overall, 44 projects
have been completed during the Quarter under reference i:e June-September-2010.
3. As on 30.09.2010 there were 606 projects involving an anticipated cost of Rs 7,41,428.63 Crores
on the monitor of MOSPI. The classification of these Projects into Mega (costing Rs.1000 Crores.
and above), Major (costing between Rs.100 Crores and Rs.1000 Crores.), categories is given in
Table-1 set out below: The 143 mega (includes 9 completed during the quarter in reference) and
463 major projects involve an anticipated cost of Rs 7,41,428.63 Crores. The expenditure incurred
on 606 Mega and Major projects is Rs. 3,20,808.36 Crores..
TABLE-1

Classification of projects in Mega, Major and Medium

( All sums of money in crore of rupees)

During
No.

Qtr.

Mega Projects
Major Projects

143
463

Investment
556902.01
184526.62

Total

606

741428.63

2010-2011
% of total
75.11
24.89

Exp. till Qtr.


221106.9
99701.46

Original Cost
452652.43
159601.85

100.00

320808.36

612254.28

4. The graphic presentation of the classification of the projects is depicted below in the
Chart, The 143 mega (134 ongoing and 9 completed) Projects accounted for about 75% of
the total anticipated cost whereas 463 major Projects share only 25% of the anticipated
cost.

CHART-I
NUMBER OF PROJECTS

Expenditure in Rs. crore

% OF TOTAL COST

143
26%

99701.46

221106.9
463

74%

MEGA

MAJOR

5. Table-2 presents sector-wise break-up of the projects on the monitoring system at the end
of July-September, 2010. The graphic presentation of the frequency distribution of projects
among various sectors as on 30.09.2010 is shown in chart-2.

10

Frequency distribution of projects at the end of

S.
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Name of the
sector
Atomic Energy
Civil Aviation
Coal
Fertilisers
Mines
Steel
Petroleum
Power
Health &
Family Welfare
Railways
Road Transport
& Highways
Shipping &
Ports
Telecommunic
ations
Urban
Development
Water
Resources
Total

No of
Mega
Projects
4
2
8
3
1
6
43
43
0

Anticipated
Cost
(RS.
CRORE)
23,236.29
3,215.51
17,623.16
4,065.66
4,401.76
60,291.00
171,463.04
169,525.59
0.00

20
0

2nd Quarter

21,982.29
3,215.51
13,329.34
4,065.66
4,091.51
39,671.00
149,167.95
163,474.71
0.00

No of
Major
Projects
0
7
37
3
0
14
40
42
1

Anticipated
Cost
(RS.
CRORE)
0.00
2,131.89
12,606.81
1,251.75
0.00
5,223.79
19,040.50
18,529.03
443.15

54,263.58
0.00

21,232.80
0.00

116
135

53,627.28
42,136.98

29,878.94
41,863.55

13,074.37

12,756.07

17

7,166.70

6,901.74

4,051.69

4,051.69

51

22,368.74

22,244.53

30,503.36

15,071.00

0.00

0.00

1,187.00

542.90

0.00

0.00

143

556902.01

452652.43

463

184526.62

159601.85

Original
Cost

11

Original
Cost
0.00
2,131.89
12,135.03
1,251.75
0.00
4,526.03
21,146.00
17,451.21
71.18

CHART-II
FREQUENCY DISTRIBUTION OF PROJECTS
AT THE END OF 2nd QTR. (2010-2011)
150

300
280
260

200
180
160
140
120

50

100

NO. OF PROJECTS

220
100

80
60
40
20

Water Resources

Urban Development

Telecommunications

Shipping & Ports

Railways

Health & Family


Welfare

Power

Petroleum

Steel

Mines

Total Cost (Rs. Crore)

Road Transport &


Highways

Total Projects

Fertilisers

Coal

0
Civil Aviation

0
Atomic Energy

INVESTMENT IN RS.'000 CRORES

240

6. In September, 2010 there were 606 projects on the monitoring system of the Ministry.
During Second Quarter 20 new projects were added for monitoring and 14 projects were
dropped from monitoring due to their completion and other reasons. During First quarter
47 new projects were added for monitoring and 6 projects were dropped from the monitor
due to their completion and other reasons. During the last financial year (2009-10) a total
of 97 projects were completed. Sector wise numbers of projects dropped and added during
the quarter are given in table-3 below.

12

TABLE-3
Summary of Projects Added/Dropped

Summary of projects added/dropped, in the 2nd quarter (2010-2011)


Sr.
No.

Name of the
Sector

QR. II
No. of projects
6/10

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Added

Dropped

9/10

Atomic Energy
Civil Aviation
Coal
Fertilisers
Mines
Steel
Petroleum
Power
Health & Family Welfare
Railways
Road Transport & Highways
Shipping & Ports
Telecommunications
Urban Development
Water Resources

4
8
39
6
1
22
80
85
1
135
135
22
59
2
1

0
1
6
0
0
0
9
1
0
1
0
2
0
0
0

0
0
0
0
0
2
6
1
0
0
0
0
5
0
0

4
9
45
6
1
20
83
85
1
136
135
24
54
2
1

Total

600

20

14

606

13

7. The details of 134 mega projects under the monitoring system as on 30.09.2010 are as given
in table-4 below:TABLE-4A

(Sep,2010)

Date of
Commissioning
Delay
w.r.t.
Date of
Approval

S.No Project
1

Cost

Anticipated
Cost

Original /
Revised

Cumm.
Original Milestones
Achieved/
Expendi- Original / Antici(in
Total
ture
Revised pated months)
6

10

10/2009
09/2007

12/2010

39(R1)

04/2011

Atomic Energy
1 KAIGA 3 and 4 UNITS (NPCIL) [020100041]NPCIL,Karnataka

05/2001

4,213.00
-

3,282.00

2,572.00

2 URANIUM ORE MINE & PROCESSING


PLANT AT TUMMALAPALL [N02000007]UCIL,Andhra Pradesh

09/2007

1,106.29
-

1,106.29

778.60

3 PROTOTYPE FAST BREEDER


REACTOR (BHAVINI, 500 MWE) [020100044]BHAVNI,Tamil Nadu

09/2003

3,492.00
-

5,677.00

2,592.29

09/2010
-

09/2011

12(O)

8/80

4 KUDANKULAM APP (NPCIL) [020100040]NPCIL,Tamil Nadu

12/2001

13,171.00
-

13,171.00

13,150.00

12/2008
-

12/2011

36(O)

61/119

21,982.29
-

23,236.29

19,092.89

Total

71/75
0/1

140/275

Civil Aviation
5 D/O KAMARAJ DOMESTIC TER-PH-II &
EXP. ANNA INT. TE(K1) [N04000038]AAI,Tamil Nadu

08/2008

1,273.00
-

1,273.00

594.84

01/2011
-

01/2011

0(O)

0/0

6 C/O INTEGRATED PASSENGER TER.


BULD. NSCBI AIRPORT [N04000037]AAI,West Bengal

08/2008

1,942.51
-

1,942.51

860.83

05/2011
-

08/2011

3(O)

0/0

3,215.51
-

3,215.51

1,455.67

Total

0/0

Coal
7 BARSINGSAR TPS (2X125MW) (NLC) [060100089]NLC,Rajasthan

12/2004

1,114.18
1,626.09

1,626.09

1,488.75

06/2009
-

10/2010

16(O)

59/26

8 TPS-II EXPANSION (1470MW TO


1970MW) (NLC) [060100087]NLC,Tamil Nadu

10/2004

2,030.78
2,453.57

2,453.57

2,025.08

06/2009
-

06/2011

24(O)

41/24

9 TUTICORIN THERMAL POWER


PROJECT - [N06000047]NLC,Tamil
Nadu

05/2008

4,904.54
-

4,904.54

1,071.67

08/2012
-

08/2012

0(O)

0/0

10 KUSMUNDA
EXPN.OCP(SECL)(10MTY) [N06000008]SECL,Chhatisgarh

06/2006

737.65
1,188.31

1,188.31

554.36

03/2011
03/2013

03/2013

0(R3)

0/4

11 GEVRA EXPANSION OCP (SECL) (25


MTY) - [060100093]SECL,Chhatisgarh

07/2005

1,667.55
2,675.67

2,675.67

1,011.42

03/2010
03/2014

03/2014

0(R3)

3/7

12 DIPKA EXPANSION OCP (SECL) (20


MTY) - [060100094]SECL,Chhatisgarh

07/2005

1,268.53
1,943.66

1,943.66

887.83

03/2010
03/2014

03/2014

0(R3)

2/6

14

(Sep,2010)

Date of
Commissioning
Delay
w.r.t.
Date of
Approval

S.No Project
1

2
13 AMLOHRI EPR (NCL) (6 MTY) [N06000010]NCL,Madhya pradesh

3
05/2006

Total

Anticipated
Cost

Original /
Revised

Cost
4

Original Milestones
Cumm.
Achieved/
Expendi- Original / Antici(in
Total
ture
Revised pated months)
6

1,352.04
1,143.54

1,143.54

32.03

13,075.27
-

15,935.38

7,071.14

03/2014
03/2016

03/2016

10

0(R3)

1/1
106/68

Fertilisers
14 NANGAL - AMMONIA PLANT
FEEDSTOCK PROJECT [N08000006]NFL,Punjab

01/2010

1,478.63
-

1,478.63

43.41

12/2012

0/8

15 PANIPAT - AMMONIA PLANT


FEEDSTOCK CHANGEOVER PROJE [N08000004]NFL,Haryana

01/2010

1,292.84
-

1,292.84

46.98

01/2013

0/5

16 BATHINDA - AMMONIA PLANT


FEEDSTOCK CHANGEOVER PROJ [N08000005]NFL,Punjab

01/2010

1,294.19
-

1,294.19

42.93

01/2013

0/5

4,065.66
-

4,065.66

133.32

4,091.51
4,401.76

4,401.76

3,856.50

4,091.51
-

4,401.76

3,856.50

Total

0/18

Mines
17 SECOND PHASE EXPANSION OF
CAPTIVE ALUMINIUM,SMELTER AND
POWE - [100100054]NALCO,Orissa

10/2004

Total

12/2008
01/2011

03/2011

2(R3)

116/110

116/110

Steel
18 EXPANSION OF SALEM STEEL PLANT
- [N12000050]SAIL,Tamil Nadu

01/2008

1,902.00
-

1,902.00

1,694.98

06/2011
-

10/2010

-8(O)

2/6

19 EXPANSION OF RINL/VSP FROM 3


MTPY-6.3 MTPY OF LIQUID STEEL [120100067]RINL,Andhra Pradesh

10/2005

8,692.00
-

12,228.00

7,323.00

10/2009
-

06/2011

20(O)

4/126

20 EXPANSION OF IISCO STEEL PLANT [N12000051]SAIL,West Bengal

02/2008

14,443.00
-

14,443.00

8,898.53

06/2011
-

06/2011

0(O)

0/6

21 EXPANSION OF BOKARO STEEL


PLANT - [N12000055]SAIL,Jharkhandd

01/2008

3,316.00
6,325.00

6,325.00

1,313.20

12/2011
12/2011

12/2011

0(R3)

0/7

22 EXPENSION OF ROURKELA STEEL


PLANT - [N12000056]SAIL,Orissa

09/2008

6,133.00
-

8,128.00

2,506.34

02/2011
-

03/2013

25(O)

0/0

23 EXPANSION OF BHILAI STEEL PLANT


- [N12000057]SAIL,Chhatisgarh

09/2008

5,185.00
17,265.00

17,265.00

1,488.41

03/2013
03/2013

03/2013

0(R3)

0/8

39,671.00
-

60,291.00

23,224.46

Total

6/153

Petroleum
24 INST. OF FACILITIES FOR
IMPROVEMENT IN DIESEL QUALITY
(IOCL) - [160100289]IOCL,West Bengal

11/2005

1,876.00
2,869.00

3,155.00

2,747.34

04/2009
12/2009

02/2010

2(R1)

41/36

25 C2-C3 AND LPG RECOVERY FROM


LNG, DAHEJ (ONGC) [160100168]ONGC,Gujarat

12/2003

900.92
-

1,493.49

726.23

06/2006
07/2010

10/2010

3(R3)

0/2

26 EXPANSION OF PANIPAT REFINERY


FROM 12 TO 15 MMTPA [N16000017]IOCL,Haryana

06/2005

806.00
-

1,096.23

809.69

03/2008
12/2009

10/2010

10(R1)

18/66

27 VIJAPUR DADRI-BAWANA PIPE LINE


PROJECT - [N16000048]GAIL,Multi
State

11/2007

5,595.31
4,262.00

3,700.00

3,260.61

11/2009
04/2010

10/2010

6(R3)

0/0

15

(Sep,2010)

Date of
Commissioning
Delay
w.r.t.
Date of
Approval

S.No Project
1

Anticipated
Cost

Original /
Revised

Cost
4

Original Milestones
Cumm.
Achieved/
Expendi- Original / Antici(in
Total
ture
Revised pated months)
7

28 CAPACITY EXP. CUM


MODERNISATION PH-II [N16000080]BPCL,Kerala

09/2009

2,591.80
3,941.41

3,941.41

2,864.54

12/2009
-

10/2010

10(O)

0/0

29 RESIDUE UPGRADATION AND


MS/HSD QUALITY IMPROVEMENT [N16000021]IOCL,Gujarat

01/2007

5,693.00
6,898.00

6,898.00

5,735.33

01/2010
06/2010

11/2010

5(R3)

0/0

30 MSQ UPGRADATION PROJECT AT


BARAUNI REFINERY [N16000038]IOCL,Bihar

04/2008

1,492.00
-

1,505.24

1,069.91

04/2010
-

11/2010

7(O)

0/0

31 DIESEL HYDRO TREATMENT


PROJECT,BRPL DHALIGAON [N16000009]BRPL,Assam

06/2006

1,431.91
1,646.39

1,676.00

1,438.72

09/2009
-

12/2010

15(O)

0/0

32 IOR GELEKI (ONGCL) [160100216]ONGC,Assam

09/2001

390.09
834.90

1,200.00

1,125.49

03/2007
03/2011

03/2011

0(R3)

6/6

33 DEVELOPMENT OF C-SERIES FIELDS


- [N16000023]ONGC,Maharashtra

08/2006

3,195.16
-

2,800.00

2,520.63

12/2008
12/2008

03/2011

27(R3)

0/0

34 HEERA AND SOUTH HEERA REDEVELOPMENT PROJECT [N16000024]ONGC,Maharashtra

09/2006

2,305.30
-

2,305.30

2,061.15

06/2010
06/2010

03/2011

9(R3)

0/0

35 BAWANA NANGAL PIPE LINE


PROJECT - [N16000050]GAIL,Multi
State

07/2011

1,816.07
1,816.07

1,816.07

349.25

04/2011

04/2011

0(R3)

0/1

36 DAHEJ-VIJAYPUR PIPE LINE


PROJECT(PHASE-II) [N16000052]GAIL,Multi State

11/2007

4,429.38
4,403.00

2,800.00

1,697.61

10/2011
04/2011

04/2011

0(R3)

0/2

37 COMPRESSOR STATIONS (VIJAYPUR


AND JHABUA) PHASE-I [N16000053]GAIL,Multi State

11/2007

1,512.00
1,434.00

1,434.00

644.05

04/2011
04/2011

04/2011

0(R3)

0/2

38 COMPRESSOR STATIONS (KAILARAS


&CHAINSA) - [N16000054]GAIL,Multi
State

11/2007

1,061.93
1,167.00

1,167.00

26.77

04/2011
04/2011

04/2011

0(R3)

0/2

39 INTEGRATED DEV OF G1 and GS-15


(ONGCL) - [160100231]ONGC,Multi
State

04/2003

429.82
2,218.01

2,218.01

1,234.69

03/2005
05/2011

05/2011

0(R3)

0/0

40 DIESEL HYDROTREATOR PROJECT


AT VISAKH REFINERY [N16000068]HPCL,Andhra Pradesh

03/2009

3,597.00
-

3,597.00

146.54

09/2011
-

09/2011

0(O)

0/0

41 DIESEL HYDROTREATOR PROJECT


AT MUMBAI REFINERY [N16000069]HPCL,Maharashtra

03/2009

3,284.00
-

3,284.00

109.26

09/2011
-

09/2011

0(O)

0/0

42 ADDITIONAL DEV. OF D-1 FIELD [N16000086]ONGC,Multi State

01/2010

2,163.64
-

2,163.64

110.39

12/2011
-

12/2011

0(O)

0/0

43 Additional Development of D-1 Field [N16000097]ONGC,Multi State

01/2010

2,163.64
-

2,163.64

110.39

12/2011
-

12/2011

0(O)

0/0

44 JAGDISHPUR-HALDIA PIPELINE
PROJECT PHASE-I [N16000072]GAIL,Multi State

07/2009

7,596.18
-

6,652.22

01/2013
-

03/2012

-10(O)

0/0

45 DHABOL-BANGALORE PIPELINE
PROJECT PHASE-I [N16000073]GAIL,Multi State

06/2009

4,543.43
4,508.38

4,508.38

10.46

03/2012
-

03/2012

0(O)

11/10

46 Integrated offshore crude Oil handling


facilities at Paradip [N16000090]IOCL,Maharashtra

12/2009

1,492.33
-

1,492.33

22.57

06/2012
-

03/2012

-3(O)

0/0

47 Assam gas Cracker project [N16000106]BCPL,Assam

04/2006

5,460.61
-

5,460.61

04/2012

48 CONSTRUCTION OF NEW PROCESS


COMPLEX MHN [N16000030]ONGC,Maharashtra

01/2007

2,853.29
-

6,326.40

1,269.57

05/2010
-

05/2012

16

10

24(O)

0/2
0/0

(Sep,2010)

Date of
Commissioning
Delay
w.r.t.
Date of
Approval

S.No Project
1

Anticipated
Cost

Original /
Revised

Cost

49 DEVELOPMENT OF B-22 CLUSTER


FIELDS [N16000032]ONGC,Maharashtra

01/2007

1,552.63
2,920.82

2,920.82

164.51

02/2009
09/2010

05/2012

20(R1)

0/0

50 DEVELOPMENT OF B-46 CLUSTER


FIELD [N16000046]ONGC,Maharashtra

06/2007

1,436.21
-

1,436.21

07/2010
-

05/2012

22(O)

0/0

51 DEVELOPMENT OF B-193 CLUSTER


FIELDS [N16000033]ONGC,Maharashtra

06/2007

3,248.78
5,633.44

5,633.44

45.51

03/2010
08/2010

06/2012

22(R1)

0/0

52 MUMBAI HIGH NORTH


DEVELOPMENT PHASE-II [N16000060]ONGC,Maharashtra

01/2009

6,855.93
-

6,855.93

931.54

09/2012
-

09/2012

0(O)

0/0

53 Paradip-Raipur-Sambalpur Ranchi
Pipeline [N16000088]IOCL,Maharashtra

08/2009

1,793.00
-

1,793.00

16.31

09/2012
-

09/2012

0(O)

0/0

54 PARADIP REFINERY PROJECT [N16000058]IOCL,Orissa

02/2009

29,777.00
-

29,777.00

4,256.49

11/2012

0/103

55 De-bottlenecking of SMPL [N16000089]IOCL,Maharashtra

12/2009

1,584.00
-

1,584.00

1.55

12/2012

0/0

56 ADDITIONAL GAS PROCESSING


UNITS AT URAN [N16000064]ONGC,Maharashtra

10/2008

1,797.35
-

1,797.35

9.78

12/2011
-

01/2013

13(O)

0/0

57 Fluidized catalytic cracking unit(FCCU)


revamp - [N16000107]IOCL,Uttar
Pradesh

07/2010

1,000.00
-

1,000.00

7.93

01/2013
-

01/2013

0(O)

0/0

58 MUMBAI HIGH SOUTH


REDEVELOPMENT PH-2 [N16000039]ONGC,Maharashtra

06/2007

1,252.75
8,813.41

8,813.41

5,208.06

06/2009
03/2013

03/2013

0(R3)

0/0

59 ASSAM RENEWAL PROJECT FOR


GROUP A - [N16000061]ONGC,Assam

03/2009

2,465.15
-

2,378.86

211.94

03/2013
-

03/2013

0(O)

0/0

60 Development of Cluster-7 Fields [N16000104]ONGC,Multi State

03/2010

3,241.03
-

3,241.03

03/2013
-

03/2013

0(O)

0/0

61 Development of WO-16 Cluster Fields [N16000105]ONGC,Multi State

06/2010

2,523.00
-

2,523.00

01/2014
-

01/2014

0(O)

0/0

127,207.64
-

144,608.02

40,944.81

Total

Original Milestones
Cumm.
Achieved/
Expendi- Original / Antici(in
Total
ture
Revised pated months)
6

10

76/232

Power
62 National Capital Thermal Power Project
Stage-II - [N18000013]NTPC,Uttar
Pradesh

10/2006

5,135.33
-

5,135.33

10/2010
-

10/2010

0(O)

12/40

63 KORBA STPP STAGE-III [N18000011]NTPC,Madhya pradesh

08/2006

2,448.50
-

2,448.49

2,059.00

02/2010
-

11/2010

9(O)

5/24

64 URI H.E.P STAGE -II (NHPC) [180100251]NHPC,J & K

08/2005

1,729.29
-

1,724.79

1,211.77

11/2009
-

02/2011

15(O)

0/0

65 Farakka STPP Stage-III [N18000016]NTPC,West Bengal

07/2006

2,570.44
-

2,570.44

1,766.00

08/2010
-

02/2011

6(O)

13/26

66 TRANSMISSION SY. ASSOCIATED


WITH BARH GENER. PROJECT(P.GR.)
- [180100260]PGCIL,Bihar

12/2005

3,779.46
-

3,725.13

3,409.04

09/2009
-

03/2011

18(O)

15/30

67 WESTERN REGION STRENGTHENING


SCHEME-II [N18000022]PGCIL,Rajasthan

07/2006

5,221.23
-

4,978.56

2,585.00

07/2010
-

03/2011

8(O)

3/20

68 SIMHADRI STPP STAGE -II (NTPC) [N18000032]NTPC,Andhra Pradesh

08/2007

5,103.39
-

5,038.53

3,284.00

05/2011
-

05/2011

0(O)

0/0

69 PARBATI H.E.P. STAGE -III (NHPC) [180100250]NHPC,Himachal Pr.

10/2005

2,304.56
-

2,304.52

1,123.71

10/2010
-

06/2011

8(O)

0/0

70 CHAMERA,STAGE-III (NHPC) [180100241]NHPC,Himachal Pr.

08/2005

1,405.63
-

1,405.63

1,285.03

08/2010
-

08/2011

12(O)

0/0

17

(Sep,2010)

Date of
Commissioning
Delay
w.r.t.
Date of
Approval

S.No Project
1

Anticipated
Cost

Original /
Revised

Cost
4

Original Milestones
Cumm.
Achieved/
Expendi- Original / Antici(in
Total
ture
Revised pated months)
7

71 KOLDAM HEP (NTPC) [180100211]NTPC,Himachal Pr.

10/2002

4,527.15
-

4,527.15

3,315.00

04/2009
-

12/2011

32(O)

19/41

72 SIPAT STPP STAGE - I (NTPC) [180100229]NTPC,Chhatisgarh

12/2003

8,323.39
-

8,323.39

6,993.00

12/2009
-

12/2011

24(O)

33/56

73 765 KV SYSTEM FOR CENTRAL PART


OF NORTHERN GRID PA [N18000068]PGCIL,Multi State

02/2009

1,347.32
-

1,347.32

436.80

02/2012
-

02/2012

0(O)

0/0

74 KOTESHWAR HEP(THDC) [180100184]THDCL,Uttaranchal

04/2000

1,301.56
-

2,398.39

2,001.82

04/2005
-

03/2012

83(O)

2/22

75 KUNADANKULAM-APP TRANS.
SYSTEM (PGCIL) [180100258]PGCIL,Tamil Nadu

05/2005

1,779.29
-

2,159.07

1,608.50

11/2008
-

03/2012

40(O)

25/38

76 BONGAIGAON THERMAL POWER


PROJECT (NTPC) [N18000041]NTPC,Assam

01/2008

4,375.35
-

4,375.35

1,422.00

07/2011
-

03/2012

8(O)

0/0

77 765KV System for central part of


Northern Region Grid [N18000079]PGCIL,Multi State

11/2009

1,075.12
-

1,075.12

88.84

05/2012
-

05/2012

0(O)

0/0

78 765KV System for Central part of


Northern Region G [N18000078]PGCIL,Multi State

07/2009

1,736.36
-

1,736.36

06/2012
-

06/2012

0(O)

0/0

79 TEESTA LOW DAM HEP, STAGE-IV


(NHPC) - [180100243]NHPC,West
Bengal

09/2005

1,061.38
-

1,061.38

799.39

09/2009
-

08/2012

35(O)

0/0

80 SUPPLIMENTARY TRANSMISSION
ASSOCIATED WITH DVC AND [N18000065]PGCIL,Multi State

08/2008

2,360.95
-

2,360.95

1,260.40

08/2012
-

08/2012

0(O)

0/0

81 765 KV POOLING STATION &


NETWORK WITH DVC AND MAIT [N18000069]PGCIL,Multi State

08/2008

7,075.33
-

7,075.33

2,433.20

08/2012
-

08/2012

0(O)

0/0

82 System Strengthening in NR for SASAN


& MUNDRA (UMPP) [N18000081]PGCIL,Multi State

12/2009

1,216.83
-

1,216.83

99.04

08/2012
-

08/2012

0(O)

0/0

83 MOUDA STPP (NTPC) [N18000048]NTPC,Maharashtra

11/2007

5,459.28
-

6,010.89

1,431.00

02/2012
08/2012

10/2012

2(R3)

0/0

84 TR. SYSTEM ASSOCIATED WITH


MUNDRA ULTRA MEGA POWER [N18000061]PGCIL,Multi State

10/2008

4,824.12
-

4,824.12

800.41

10/2012
-

10/2012

0(O)

0/0

85 Transmission System of Vindhuachal -IV


& Rihand -I - [N18000076]PGCIL,Multi
State

03/2010

4,672.99
-

4,672.99

11.89

11/2012
-

11/2012

0(O)

0/0

86 LOHARINAG-PAL HEP(4X150MW) [N18000005]NTPC,Uttaranchal

06/2006

2,895.10
-

2,895.10

552.33

11/2011
-

12/2012

13(O)

6/34

87 TRANSMISSION SYSTEM
ASSOCIATED WITH SASAN ULTRA
ME - [N18000046]PGCIL,Multi State

12/2008

7,031.88
-

7,031.88

1,277.30

12/2012
-

12/2012

0(O)

0/0

88 VINDHYACHAL STTP STAGE-IV


(NTPC) - [N18000072]NTPC,Madhya
pradesh

01/2009

5,915.00
-

5,915.00

1,019.00

11/2012
-

12/2012

1(O)

0/0

89 RIHAND STTP STAGE-III (2X500MW)


(NTPC) - [N18000073]NTPC,Uttar
Pradesh

01/2009

6,230.81
-

6,230.81

873.00

11/2012
-

12/2012

1(O)

0/0

90 Trans. System associated with


PALLATANA GBPP & BPT [N18000080]PGCIL,Multi State

02/2010

2,144.00
-

2,144.00

69.78

12/2012
-

12/2012

0(O)

0/0

91 Transmission System for phase-1


generation project [N18000087]PGCIL,Orissa

09/2010

2,074.86
-

2,074.86

02/2013
-

02/2013

0(O)

0/0

92 PARBATI HEP (NHPC) II [180100210]NHPC,Himachal Pr.

09/2002

3,919.59
-

3,919.59

2,903.19

09/2009
-

03/2013

42(O)

1/20

18

10

(Sep,2010)

Date of
Commissioning
Delay
w.r.t.
Date of
Approval

S.No Project
1

Anticipated
Cost

Original /
Revised

Cost

93 Tapovan-Vishnugad HEP (4x130MW)


(NTPC) - [N18000014]NTPC,Uttaranchal

11/2006

2,978.48
-

2,978.48

912.00

03/2013
-

03/2013

0(O)

5/31

94 KAMENG HYDROELECTRIC PROJECT


(NEEPCO) [180100239]NEEPCO,Arunachal Pr.

12/2004

2,496.90
-

2,496.90

1,229.44

05/2013
05/2013

05/2013

0(R3)

77/49

95 NORTH- EAST NORTH WESTERN


INTERCONNECTOR I PROJECT [N18000066]PGCIL,Multi State

02/2009

11,130.19
-

11,130.19

1,353.80

08/2013
-

08/2013

0(O)

0/0

96 RAMPUR HEP(412 MW) [N18000024]SJVNL,Himachal Pr.

01/2007

2,047.03
-

2,047.03

952.75

01/2012
-

09/2013

20(O)

2/10

97 BARH STPP STAGE -II (NTPC) [N18000047]NTPC,Bihar

02/2008

7,341.04
-

7,341.04

1,105.00

08/2013
-

10/2013

2(O)

0/0

98 LOWER SUBANSIRI H.E.P (NHPC) [180100221]NHPC,Arunachal Pr.

09/2003

6,285.33
-

7,451.99

4,181.57

09/2010
-

12/2013

39(O)

2/11

99 BARH STPP(3X660MW) NTPC [180100242]NTPC,Bihar

12/2003

8,692.97
-

8,692.97

5,057.00

11/2010
-

09/2014

46(O)

15/51

100 Transm System for development of


Pooling stn. in N [N18000077]PGCIL,West Bengal

04/2010

4,404.57
-

4,404.57

01/2015
-

01/2015

0(O)

0/0

101 TEHRI PUMPED STORAGE


PLANT(1000MW) [N18000010]THDCL,Uttaranchal

07/2006

1,657.00
-

3,124.76

249.07

07/2010
-

03/2015

56(O)

0/0

102 VISHNUGAD PIPALKOTI HYDRO


ELECTRIC PROJECT [N18000042]THDCL,Uttaranchal

08/2008

2,491.58
-

2,491.58

122.73

07/2014
-

03/2015

8(O)

0/8

103 KISHANGANGA HEP [N18000031]NHPC,J & K

07/2007

2,238.67
-

3,642.04

472.88

07/2014
-

01/2016

18(O)

0/0

104 SEWA- II H.E.P (NHPC) [180100220]NHPC,J & K

09/2003

665.46
-

1,016.74

961.39

09/2007
-

163,474.71
-

169,525.59

62,717.07

Total

Original Milestones
Cumm.
Achieved/
Expendi- Original / Antici(in
Total
ture
Revised pated months)
6

10

8/36
243/547

Railways
105 MUMBAI URBAN TRANSPORT
PROJECT PHASE-I, MTP [N22000093]MRTP,Maharashtra

04/2003

3,125.20
-

4,103.20

3,866.40

12/2010

0/1

106 CONV.OF 1500V DC TRACTION TO 25


KV AC,WR [220100233]RE,Maharashtra

07/1996

273.67
1,160.52

1,800.00

501.49

12/2012

0/0

107 CHANDIGARH-LUDHIANA(NEW BG
LINE),NR - [220100241](NR),Punjab

07/1997

248.44
576.27

1,103.47

679.18

12/2012

0/0

108 PATNA GANGA BRIDGE (NL), ECR [220100308]ECR,Bihar

04/2001

624.47
-

1,480.71

445.84

10/2007
-

12/2012

109 QUILON-TIRUNELVELI-TENKASIVIRUDHUNAGAR(SR)(GC) [220100263]SR,Multi State

03/1998

280.00
-

1,029.00

597.31

03/2013

0/0

110 RANGIA-MURKONGSELEK, (GC)


NEFR - [220100315]NEFR,Multi State

01/2004

912.70
912.70

1,556.23

295.30

03/2013

0/0

111 BRAHAMAPUTRA BRIDGE AT


BOGIBIL & LINK LINES,NEFR [220100201]NEFR,Assam

04/1996

1,000.00
1,500.00

3,230.02

1,920.25

04/2008
12/2011

03/2014

27(R1)

0/0

112 NEW MAYNAGURI TO JOGIGHOPA


VIA CHANGRABANDHA (NL), [220100266]NEFR,Multi State

02/2000

733.00
-

1,655.80

520.84

12/2008
-

03/2014

63(O)

0/0

113 BHAIRABI SAIRONG, NEFR [N22000100]NL,Mizoram

04/2008

619.34
-

2,429.41

1.61

04/2014
-

03/2014

-1(O)

0/0

114 MUMBAI URBAN TRANSPORT


PROJECT PHASE-II, MTP [N22000092]MRTP,Maharashtra

04/2008

5,300.00
-

5,300.00

128.02

03/2014
-

03/2015

12(O)

0/0

19

62(O)

0/0

(Sep,2010)

Date of
Commissioning
Delay
w.r.t.
Date of
Approval

S.No Project
1

Anticipated
Cost

Original /
Revised

Cost

115 SEVOK RANGPO, NEFR [N22000102]LD,Sikkim

04/2008

1,339.48
-

3,380.57

2.56

12/2015
-

12/2015

0(O)

0/0

116 JIRIBAM TO IMPHAL


(TUPUI)(NL)(NEFR) [220100288]NEFR,Multi State

04/2003

727.56
727.53

3,123.52

237.63

03/2011
-

03/2016

60(O)

0/0

117 UDHAMPUR-SRINAGAR-BARAMULLA
(NL),NR - [220100133](NR),J & K

03/1995

2,500.00
8,000.00

11,270.00

6,481.16

03/2001
-

12/2017

201(O)

0/0

118 AHMEDNAGAR-PARLI VAIJNATH(NL)


CR - [220100181]CR,Maharashtra

02/1997

353.08
-

1,010.00

67.32

0/0

119 KANPUR-KASGANJMATHURA(GC),NER [220100197]NER,Uttar Pradesh

03/1997

395.00
1,062.36

1,548.95

1,101.82

0/0

120 KODERMA-RANCHI VIA


BARKAKHANA (NL),ECR [220100222]ECR,Jharkhandd

03/1999

491.19
-

1,099.20

711.79

07/2005
-

0/0

121 BANGLORE - SATYAMANGALAM


(NL)(SWR) [220100274]SWR,Karnataka

02/1999

138.00
-

1,300.00

0.29

0/0

122 RAMGANJMUNDI-BHOPAL (NL),WCR [220100314]WCR,Madhya pradesh

04/2001

727.13
727.13

1,225.00

148.10

0/0

123 TOLLYGANJ-GARIA with extension to


Dum Dum-Naopara [220100268]MRTP,West Bengal

03/2000

907.69
1,032.76

5,608.50

2,664.44

12/2006
08/2010

0/0

20,695.95
-

53,253.58

20,371.35

Total

Original Milestones
Cumm.
Achieved/
Expendi- Original / Antici(in
Total
ture
Revised pated months)
6

10

0/1

Shipping & Ports


124 SETHUSAMUDRAM SHIP CHANNEL
PROJECT - [250100175]PORT
TRUST,Tamil Nadu

06/2005

2,427.40
-

2,427.40

819.11

10/2008
-

11/2010

25(O)

0/0

125 C/O Berthing and Allied Facilities off


tekra near - [N25000037]PORT
TRUST,Gujarat

04/2005

882.00
-

1,140.00

0.16

02/2011
-

02/2011

0(O)

0/0

126 ACQUISITION OF 6 NOS. 60470 DWT


LR-I PRODUCT TANKE [N25000029]SHIPP.,Maharashtra

10/2006

1,658.59
-

1,658.59

1,332.47

07/2010
-

03/2011

8(O)

0/0

127 ACQUISITION OF 4 NOS. OF 115000


DWT CRUDE OIL CARR [N25000032]SHIPP.,Maharashtra

08/2008

1,108.12
-

1,168.42

569.26

04/2011
-

12/2011

8(O)

0/0

128 ACQUISITION OF 6 NOS. OF 57000


DWT HANDYMAX BULK C [N25000033]SHIPP.,Maharashtra

11/2007

1,061.96
-

1,061.96

219.98

03/2012
-

01/2012

-2(O)

0/0

129 SETTING UP OF LNG


REGASIFICATION TERMINAL AT
PUTHU - [N25000048]PORT
TRUST,Kerala

03/2009

3,500.00
-

3,500.00

01/2012
-

01/2012

0(O)

0/0

10,638.07
-

10,956.37

2,940.98

Total

0/0

Telecommunications
130 Execution of telecom network
requirement of defence [N26000065]BSNL,Multi State

05/2006

1,077.00
-

1,077.00

841.00

03/2009
-

09/2010

18(O)

0/0

131 GSM EQUIPMENT OF 3125K


LINES(2G) AND 625K LINES(3 [N26000043]BSNL,Maharashtra

09/2008

1,799.94
-

1,799.94

214.38

09/2009
-

11/2010

14(O)

0/0

2,876.94
-

2,876.94

1,055.38

Total

20

0/0

(Sep,2010)

Date of
Commissioning
Delay
w.r.t.
Date of
Approval

S.No Project
1

Cost

Anticipated
Cost

Original /
Revised

Original Milestones
Cumm.
Achieved/
Expendi- Original / Antici(in
Total
ture
Revised pated months)
6

10

Urban Development
132 DELHI MRTS PHASE-II PROJECT [280100002]DMRC,Delhi

08/2005

8,676.00
8,605.36

18,894.36

15,839.63

06/2010
-

10/2010

4(O)

0/8

133 BANGALORE METRO RAIL PROJECT


- [N28000008]MRTP,Karnataka

05/2006

6,395.00
-

11,609.00

2,954.59

12/2011
-

03/2013

15(O)

6/6

15,071.00
-

30,503.36

18,794.22

542.90
-

1,187.00

35.49

542.90
-

1,187.00

35.49

0/0

426,608.45

524,056.46

201,693.28

693/1418

Total

6/14

Water Resources
134 PAGLADIYA DAM PROJECT [300100001]MoWR,Assam
Total

Grand Total

01/2001

12/2007
-

12/2012

60(O)

0/0

The details of 9 mega projects that were completed in the current financial year (2010-11) as on
30.09.2010 are as given in table-4B below:TABLE-4B

Month wise List of Completed Project Costing


Rs.

1000 Crore and above during

2010-2011
Original Date
Of

Cumulative
Expenditure

Commissioning

(Rs. Crore)

Project
Sl. No.

Original Cost
(Rs. Crore)

Name

June,2010
Petroleum
1

1,635.00

CLEAN FUELS PROJECT AT VISAKH


REFINERY(HPCL)(HINDUSTAN PETROLEUM CORPORATION
LIMITED) - [160100281]
September,2010
Coal

21

05/2006

2,095.36

Month wise List of Completed Project Costing


Rs.

1000 Crore and above during

2010-2011
Original Date
Of

Cumulative
Expenditure

Commissioning

(Rs. Crore)

Project
Sl. No.

Original Cost
(Rs. Crore)

Name

BARSINGSAR MINE 2.10 MTPA LIGNITE (NLC)(NEYVELI


LIGNITE CORPORATION) - [060100090]

PANIPAT NAPHTA CRACKER PROJECT(INDIAN OIL


CORPORATION LIMITED) - [160100292]
LUBE OIL BASE STOCK QUALITY UPGRADATION AT MUMBAI
REFINERY(HINDUSTAN PETROLEUM CORPORATION LIMITED)
- [N16000026]
MSQ UPGRADATION PROJECT AT PANIPAT REFINERY(INDIAN
OIL CORPORATION LIMITED) - [N16000035]

254.07

06/2009

1,687.78

14,439.00

11/2009

12,054.37

638.90

04/2009

796.21

1,131.00

12/2009

750.71

536.85

03/2003

1,005.50

2,118.00

11/2004

.00

1,174.75

03/2006

371.41

Petroleum

4
5

Railways
6

NEW JALPAIGURI-NEW BONGAIGAON (GC),NEFR(NORTH


EAST FRONTIER RAILWAY) - [220100224]
Shipping & Ports

DEV. & OPRATION OF AN INTERNATIONAL CONTAINER


TRA(PORT TRUST) - [N25000046]
Telecommunications

GSM EXPANSION PH.IV (B) (BSNL) MAHARASHTRA(BHARAT


SANCHAR NIGAM LIMITED) - [260100095]

22

8. Table-5 below presents an analysis of investments and expenditure in projects under

implementation in each of the 15 sectors. The graphic presentation of the analysis of planned
investment and balance expenditure of the projects is shown in Chart-3.
TABLE-5

Analysis of planned and balance expenditure (Sector wise)


S.
No.

Sector
Outlays
(Rs. Cr.)
Number
of
projects

Original
Cost

Now anti
cipated

Cum.
Exp. (Rs.
Cr.)

Exp. upto
the
End of Qtr.

Balance
expenditure
2010-2011

cost
of project
1.

Atomic Energy

21,982.29

(Rs. Cr)
23,236.29

18,370.75

4,865.54

610.00

2.

Civil Aviation

5,347.40

5,347.40

1,553.55

3,793.85

1,133.11

2,522.61

3.

Coal

45

25,464.37

30,229.97

9,557.38

20,672.59

2,560.00

11,811.18

4.

Fertilisers

5,317.41

5,317.41

18.29

5,299.12

503.57

161.98

5.

Mines

4,091.51

4,401.76

3,648.00

753.76

484.00

3,856.50

6.

Steel

20

44,197.03

65,514.79

19,214.29

46,300.50

8,569.00

25,595.76

7.

Petroleum

83

170,313.95

190,503.54

54,249.82

136,253.72

24,339.71

64,935.52

8.

Power

85

180,925.92

188,054.62

67,070.11

120,984.51

28,109.91

70,486.99

9.

Health & Family Welfare

71.18

443.15

477.33

-34.18

67.85

547.78

10.

Railways

136

51,111.74

107,890.86

45,700.36

62,190.50

5,170.93

48,575.45

11.

Road Transport & Highways

135

41,863.55

42,136.98

36,690.42

5,446.56

0.00

40,620.42

12.

Shipping & Ports

24

19,657.81

20,241.07

3,547.96

16,693.11

4,905.46

5,104.50

13.

Telecommunications

54

26,296.22

26,420.43

6,930.11

19,490.32

0.00

8,667.07

14.

Urban Development

15,071.00

30,503.36

15,987.26

14,516.10

3,791.47

18,794.22

15.

Water Resources

542.90

1,187.00

35.49

1,151.51

0.00

35.49

741428.63

283051.12

458,377.51

80,245.01

320808.36

Total

606

612254.28

* Outlays for Road Transport & Highways, Water Resources, and Telecommunications sectors are not reported.

23

19,092.89

CHART-III

160000
140000

120,984.51

136,253.72

SECTOR-WISE ANALYSIS OF PLANNED INVESTMENT AND BALANCE


EXPENDITURE

1,151.51

35.49

Water Resources

18,794.22

14,516.10

Urban Development

19,490.32

8,667.07

Telecommunications

16,693.11

5,104.50

Shipping & Ports

40,620.42

Road Transport &


Highways

5,446.56

62,190.50

Railways

547.78

-34.18

Cum Exp upto


End Of Qtr.

48,575.45

70,486.99

Power

3,856.50

753.76

64,935.52

Petroleum

Steel

Health & Family


Welfare

BAL..EXP.

Mines

5,299.12

161.98

Fertilisers

3,793.85

2,522.61

20,672.59

Coal

-20000

SECTOR

20000

Civil Aviation

4,865.54

40000

19,092.89

60000

11,811.18

80000

25,595.76

46,300.50

100000

Atomic Energy

(Rs. CRORES)

120000

9. Out of 606 projects, 16 projects are ahead of schedule, 168 are on schedule, 313 projects are delayed
with respect to the original schedule. 103 projects were approved without original date of
commissioning and for 103 projects the anticipated date of commissioning has not been firmed up. An
analysis of cost and time -overruns of all the 606 projects with respect to the original approved
sanctions is presented in Table-6 and 6(A) below:

24

TABLE-6

Extent of Cost Overrun in Projects with respect to Original Schedule (As on 30.09.2010)
Extent of cost overrun in projects with respect to original schedule
S.No.

Sector

No. of
Projects

Total cost (Rs. Cr.)

Projects with cost overrun


Original

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Atomic Energy
Civil Aviation
Coal
Fertilisers
Mines
Steel
Petroleum
Power
Health & Family Welfare
Railways
Road Transport & Highways
Shipping & Ports
Telecommunications
Urban Development
Water Resources
Total

Anticipated
cost

Cost
overrun
(%)

No
.

Original
cost

Anticipated
cost

% Incr
Base

4
9
45
6
1
20
83
85
1
136
135
24
54
2
1

21,982.3
5,347.4
25,464.4
5,317.4
4,091.5
44,197.0
170,314.0
180,925.9
71.2
51,111.7
41,863.6
19,657.8
26,296.2
15,071.0
542.9

23,236.3
5,347.4
30,230.0
5,317.4
4,401.8
65,514.8
190,503.5
188,054.6
443.2
107,890.9
42,137.0
20,241.1
26,420.4
30,503.4
1,187.0

5.7
0.0
18.7
0.0
7.6
48.2
11.9
3.9
522.6
111.1
0.7
3.0
0.5
102.4
118.6

1
0
14
0
1
12
25
15
1
116
5
6
9
2
1

3,492.0
0.0
9,381.1
0.0
4,091.5
25,323.7
44,284.4
23,656.5
71.2
38,270.2
1,221.8
3,242.6
4,378.5
15,071.0
542.9

5,677.0
0.0
14,842.9
0.0
4,401.8
46,753.4
72,736.4
31,263.6
443.2
95,101.3
1,677.5
3,924.5
5,159.9
30,503.4
1,187.0

62.6
0.0
58.2
0.0
7.6
84.6
64.2
32.2
522.6
148.5
37.3
21.0
17.8
102.4
118.6

606

612,254.3

741,428.6

21.1

208

173,027.3

313,671.7

81.3

25

TABLE-6A

Extent of the Time Overrun in Projects with respect to Original Schedule (As on 30.09.2010)
Extent of the time overrun in projects with respect to original schedule
S.No
.

Sector

No. of
Projects

Total cost (Rs. Cr.)

Projects with time overrun


Original

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Atomic Energy
Civil Aviation
Coal
Fertilisers
Mines
Steel
Petroleum
Power
Health & Family Welfare
Railways
Road Transport & Highways
Shipping & Ports
Telecommunications
Urban Development
Water Resources
Total

Anticipated
cost

4
9
45
6
1
20
83
85
1
136
135
24
54
2
1

21,982.3
5,347.4
25,464.4
5,317.4
4,091.5
44,197.0
170,314.0
180,925.9
71.2
51,111.7
41,863.6
19,657.8
26,296.2
15,071.0
542.9

23,236.3
5,347.4
30,230.0
5,317.4
4,401.8
65,514.8
190,503.5
188,054.6
443.2
107,890.9
42,137.0
20,241.1
26,420.4
30,503.4
1,187.0

Cost
overrun
(%)
5.7
0.0
18.7
0.0
7.6
48.2
11.9
3.9
522.6
111.1
0.7
3.0
0.5
102.4
118.6

606

612,254.3

741,428.6

21.1

26

No.

313

3
3
20
0
1
12
32
38
0
30
116
12
43
2
1

Original
cost

Anticipated
cost

Range
(Months)

20,876.0
2,690.9
13,971.6
0.0
4,091.5
18,385.9
42,895.5
101,750.3
0.0
18,511.3
33,407.9
9,887.5
21,169.0
15,071.0
542.9

22,130.0
2,690.9
18,015.1
0.0
4,401.8
24,219.7
59,880.3
107,504.9
0.0
37,054.7
33,681.3
10,098.8
21,356.3
30,503.4
1,187.0

12 - 36
2- 6
8 - 64
27 - 27
6 - 25
2 - 74
1 - 83
3 - 225
3 - 90
3 - 71
1 - 69
4 - 15
60 - 60

303,251.2

372,724.1

10. An analysis of cost and time over-run of all the 606 projects on the monitoring system with
respect to the latest schedule and cost approved by the Government is given in Table-7 and 7(A)
respectively. The graphic presentation of the sector-wise anticipated cost vis-a-vis approved cost
of delayed projects at the end of September, 2010 is shown in Chart-4.

TABLE-7

Extent of cost overrun in projects with respect to latest schedule


S.No.

Sector

No. of
projects

Total cost (Rs. Cr.)

Projects with cost overrun


Latest
approved

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Atomic Energy
Civil Aviation
Coal
Fertilisers
Mines
Steel
Petroleum
Power
Health & Family Welfare
Railways
Road Transport &
Highways
Shipping & Ports
Telecommunications
Urban Development
Water Resources
Total

Anticipated
cost

Cost
overrun
(%)

No .

Latest
approved

Anticipated
cost

%
Increase
Base

4
9
45
6
1
20
83
85
1
136
135

21,982.3
5,347.4
30,190.7
5,317.4
4,401.8
59,739.0
184,276.2
181,845.0
422.6
62,942.4
41,863.6

23,236.3
5,347.4
30,230.0
5,317.4
4,401.8
65,514.8
190,503.5
188,054.6
443.2
107,890.9
42,137.0

5.7
0.0
0.1
0.0
0.0
9.7
3.4
3.4
4.9
71.4
0.7

1
0
1
0
0
7
15
14
1
109
5

3,492.0
0.0
158.6
0.0
0.0
15,999.0
28,386.7
23,568.4
422.6
47,329.3
1,221.8

5,677.0
0.0
198.6
0.0
0.0
21,886.8
38,719.6
30,315.6
443.2
92,323.8
1,677.5

62.6
0.0
25.2
0.0
0.0
36.8
36.4
28.6
4.9
95.1
37.3

24
54
2
1

19,756.3
26,546.2
15,000.4
542.9

20,241.1
26,420.4
30,503.4
1,187.0

2.5
-0.5
103.4
118.6

5
6
2
1

3,087.8
3,006.6
15,000.4
542.9

3,671.1
3,518.4
30,503.4
1,187.0

18.9
17.0
103.4
118.6

606

660,174.2

741,428.6

12.3

167

142,216.0

230,122.0

61.8

27

TABLE-7(A)

Extent of time overrun in projects with respect to latest schedule


Sector

No. of
projects

Total cost (Rs. Cr.)

Projects with time overrun


Latest
approved

Atomic Energy
Civil Aviation
Coal
Fertilisers
Mines
Steel
Petroleum
Power
Health & Family Welfare
Railways
Road Transport & Highways
Shipping & Ports
Telecommunications
Urban Development
Water Resources
Total

Cost
overrun
(%)

No .

Latest
approved

Anticipated
cost

4
9
45
6
1
20
83
85
1
136
135
24
54
2
1

21,982.3
5,347.4
30,190.7
5,317.4
4,401.8
59,739.0
184,276.2
181,845.0
422.6
62,942.4
41,863.6
19,756.3
26,546.2
15,000.4
542.9

23,236.3
5,347.4
30,230.0
5,317.4
4,401.8
65,514.8
190,503.5
188,054.6
443.2
107,890.9
42,137.0
20,241.1
26,420.4
30,503.4
1,187.0

5.7
0.0
0.1
0.0
0.0
9.7
3.4
3.4
4.9
71.4
0.7
2.5
-0.5
103.4
118.6

3
3
5
0
1
12
30
38
0
36
116
11
42
2
1

20,876.0
2,690.9
6,226.7
0.0
4,401.8
18,405.9
49,175.5
101,750.3
0.0
26,848.5
33,407.9
7,868.0
21,238.4
15,000.4
542.9

22,130.0
2,690.9
6,226.7
0.0
4,401.8
24,219.7
54,207.9
107,504.9
0.0
39,540.0
33,681.3
7,980.8
21,175.7
30,503.4
1,187.0

606

660,174.2

741,428.6

12.3

300

308,433.2

355,450.0

Range
(Months)
12-39
2-6
12-64
2-2
6-25
3-60
1-83
2-225
3-90
3-61
1-69
4-15
60-60

CHART-IV

28

15,000.40
30,503.40
Urban Development

542.9
1,187.00

26,546.20
26,420.40
Telecommunications

Water Resources

19,756.30
20,241.10

41,863.60
42,137.00
Road Transport &
Highways

62,942.40
107,890.90
Health & Family 422.6
443.2
Welfare

Mines

Anticipated Cost

Shipping & Ports

Latest Approved Cost

Fertilisers

Coal

Civil Aviation

Atomic Energy

0.00

Railways

181,845.00
188,054.60
Power

4,401.80
4,401.80

5,317.40
5,317.40

30,190.70
30,230.00

50,000.00

5,347.40
5,347.40

100,000.00

21,982.30
23,236.30

150,000.00

59,739.00
65,514.80

200,000.00

184,276.20
190,503.50

250,000.00

Petroleum

SECTORWISE LATEST APPROVED V/s ANTICIPATED COST OF


PROJECTS AT THE END OF 2nd QUARTER OF 2010-2011

COST IN Rs. CRORE

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Anticipated
cost

Steel

S.No

11. There are 85 projects reporting both time and cost overrun to the extent of 70.20% from the original cost and
time overrun ranging from 2 to 225 months. The sector wise details and extent of time overrun and cost overrun
are given in Table-8 below.

TABLE-8

Extent of time & cost overrun in projects with respect to original schedule
S No.

Sector

No. of
projects

Total Cost (Rs. Cr.)


Original

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Atomic Energy
Civil Aviation
Coal
Fertilisers
Mines
Steel
Petroleum
Power
Health & Family Welfare
Railways
Road Transport & Highways
Shipping & Ports
Telecommunications
Urban Development
Water Resources
Total

4
9
45
6
1
20
83
85
1
136
135
24
54
2
1

21,982.29
5,347.40
25,464.37
5,317.41
4,091.51
44,197.03
170,313.95
180,925.92
71.18
51,111.74
41,863.55
19,657.81
26,296.22
15,071.00
542.90

Anticipated
Cost
23,236.29
5,347.40
30,229.97
5,317.41
4,401.76
65,514.79
190,503.54
188,054.62
443.15
107,890.86
42,136.98
20,241.07
26,420.43
30,503.36
1,187.00

606

612254.28

741428.63

Projects with time & cost overrun

Cost
overrun(%)
5.70
0.00
18.71
0.00
7.58
48.23
11.85
3.94
522.58
111.09
0.65
2.97
0.47
102.40
118.64

No.

Original

1
0
8
0
1
7
16
10
0
22
5
3
9
2
1

3,492.00
0.00
7,863.96
0.00
4,091.51
16,319.50
26,332.69
20,983.57
0.00
9,980.87
1,221.78
1,508.63
4,378.45
15,071.00
542.90

Anticipated
cost
5,677.00
0.00
12,602.98
0.00
4,401.76
22,153.33
49,513.08
27,140.52
0.00
28,524.30
1,677.51
1,719.95
5,159.90
30,503.36
1,187.00

21.10

85

111786.86

190260.69

Range
(Months)
12- 12
0- 0
8- 48
0- 0
27- 27
6- 25
7- 74
8- 83
0- 0
12- 225
25- 72
8- 42
10- 58
4- 15
60- 60

12. The analysis of various factors for time and cost overruns shows that further delay is taking
place with respect to the latest revised schedules even in those projects, which have already been
delayed with reference to their original schedule. The main factors and the number of projects in
various sectors, the progress of which are being affected adversely are summarized in AppendixIII (It may be noted that the projects affected by more than one factor appear under more than one
head).
13.

Reasons for Time and Cost Overruns


The factors, which cause delays and the number of projects affected by them, are as follows:

Sl.No. Factors
1.
2.
3.

4.
5.
6.

No. of Projects

20 (16 projects are of Railways, 2 Coal and 2 projects in Health& Family


welfare sector)
Land Acquisition 47 (39 Railways, 5 Coal, 1 in Power, 1 Health & Family welfare, 1
Problems
Petroleum sector)
Slow Progress in 46 (44 in Railways, 1 Coal, 1 Steel sector)
Works other than
Civil Works
Law and order
4 (1 in Railways ,1 Health& Family welfare and 2 in Coal sector)

Fund Constraints

Delay in Supply of 5 (2 Coal, 1 Steel and 2 in Railways sector)


Equipment
Environmental
7 (7 in Coal sector).
clearance
29

7.

Others

52 (These includes the problems of technology selection, award of


contract, delay in civil work, geo-mining, court cases, inadequate
infrastructure, bad weather and Govt. clearance)

In addition, the following reasons have also been contributing to time and cost overruns:

Reasons for Time Overruns:


(i)
(ii)

Lack of supporting infrastructure facilities,


Delay in finalization of detailed engineering plans, release of drawings and delay in
availability of fronts,
(iii) Changes in scope/delay in finalization of the scope,
(iv) Industrial relations and law & order problems,
(v) Delay and uncertainty in feedstock supply,
(vi) Pre-commissioning teething troubles,
(vii) Technology problems, and
(viii) Geological surprises.
Reasons for Cost Overruns

(i) Time overruns,


(ii) Changes in rates of foreign exchange and statutory duties,
(iii) High cost of environmental safeguards and rehabilitation measures,
(iv) Higher cost of land acquisition,
(v) Change in the scope of the project,
(vi) Higher prices being quoted by the bidders in certain areas,
(vii) Under-estimation of original cost, and
(viii) General price rise.

PROJECTS REQUIRING EXAMINATION OF THE REVISED COST ESTIMATE


14. It may be noted that as many as 167 (43 Mega, 124 Major) of the 606 projects on the
monitoring system require review/sanction of the cost estimates as their anticipated costs have
gone up over and above the latest approved cost. It may also be noted from the Table below that
in 131 (13 Mega, 118 Major) projects, the actual expenditure up to September, 2010 had already
exceeded the latest sanctioned cost. The exercise for the review of cost is required for 167
projects and in the case of 131 projects RCE needs to be approved by PIB/CCEA. The sector-wise
picture is presented in Table-9 in the following page: -

30

TABLE-9
(As on 30.09.2010)

Sector-wise distribution of projects requiring review/sanctions of RCE


(No. of projects)
S. No.

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Sector

Atomic Energy
Civil Aviation
Coal
Fertilisers
Mines
Steel
Petroleum
Power
Health & Family Welfare
Railways
Road Transport & Highways
Shipping & Ports
Telecommunications
Urban Development
Water Resources

Total
no. of
projects

Mega

Total

Major
Medium

Approved cost
less than

Approved cost
less than

Approved cost
less than

Approved cost
less than

NAC

Exp

NAC

Exp

NAC

Exp

NAC

Exp

4
9
45
6
1
20
83
85
1
136
135
24
54
2
1

1
0
0
0
0
2
9
7
0
19
0
2
0
2
1

0
0
0
0
0
0
2
2
0
8
0
0
0
1
0

0
0
1
0
0
5
6
7
1
90
5
3
6
0
0

0
0
2
0
0
0
4
1
1
48
59
1
2
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

1
0
1
0
0
7
15
14
1
109
5
5
6
2
1

0
0
2
0
0
0
6
3
1
56
59
1
2
1
0

606

43

13

124

118

167

131

Total

15. It may be seen that a number of projects, require review of the sanctioned cost. In the case of
Railways and Hydro Electric based Power projects, costs of projects are arrived on the basis of
rough parameters. Revisions of costs and schedules are necessary to arrive at correct capital costs
and viability analysis.
Constraints of data used in the Report
16. The list of projects included in the Report is not exhaustive. Only those projects, which are
reported by the Companies/Departments, are included in the Report. In many such cases data has
been taken from the Annual Plan Reports or draft of MOUs sent to the Ministry for comments.
This has also been brought to the notice of some administrative departments so that they may
advise companies to send complete and regular details on projects approved by their Boards.
Projects, which are sanctioned recently by the Government where the execution work has not yet
started, would be included in subsequent reports.

17. The project-wise outlay of all the projects covered in the Report is not the same as approved
by the Planning Commission projects with a capital cost between Rs.20 crore and Rs.50 crore.
The outlays for such projects are generally fixed by the Company depending upon the availability
of resources. The expenditure figures shown against each project are provisional and at times do
not include the re-appropriation of funds within the projects. The committed expenditure for a
31

particular project is not covered. The ratio of expenditure commitment for various activities as
against the total cost of the project gives the extent to which progress is made towards its
implementation.
18. The project authorities are not furnishing complete and accurate data in time. This is one of
the main reasons for delay in bringing out the Status Report. Some of the project authorities are
not reporting the exact status of progress of the projects for a considerable time and these are
corrected in the report as and when the details are made available by them. In most of the projects
the physical progress of the project is not reported. The same parameters without change for
several quarters continuously, is being reported.

32

List of projects completed in 2010-2011 as on 30-09-2010


(All sums of money in crores of rupees

Project
(District)
(State)

Date of
commissioning
Original
( Revised)

Cost
Approved
Original
(Revised)

Cumulative
expenditure

Completed
During

Sector Coal
NLC
1 BARSINGSAR MINE 2.10 MTPA
LIGNITE (NLC)
Bikaner
Rajasthan

06/2009

254.07
1687.78

1687.78

Qtr. 2 of 2010-2011

12/2009
03/2010

405.82

354.93

Qtr. 2 of 2010-2011

01/2010

390
230

188.43

Qtr. 1 of 2010-2011

12/2009

490.71
639.11

590.52

Qtr. 2 of 2010-2011

09/2009

967.77

416.9

Qtr. 2 of 2010-2011

643.46

726.45

Qtr. 2 of 2010-2011

Sector Petroleum
BPCL
2 BINA KOTA PIPE LINE PROJECT
Multi State
3 SHORT TERM LOW COST MUMBAI
REFINERY
Maharashtra
4 BINA DESPATCH TERMINAL
Madhya pradesh

GAIL
5 CHAINSA-JHAJJAR PIPE LINE
PROJECT
Haryana

HPCL
6 SINGLE POINT MOORING PROJECT
AT VISAKHAPATNAM
Andhra Pradesh
7 CLEAN FUELS PROJECT AT VISAKH
REFINERY(HPCL)
Visakhapat.
Andhra Pradesh

05/2006

1635

2095.36

Qtr. 1 of 2010-2011

8 LUBE OIL BASE STOCK QUALITY


UPGRADATION AT MUMBAI REFINERY

04/2009

638.9
1030

796.21

Qtr. 2 of 2010-2011

12/2009

1131

750.71

Qtr. 2 of 2010-2011

12/2009

348

186.58

Qtr. 2 of 2010-2011

06/2008

250.66

350.96

Qtr. 2 of 2010-2011

Maharashtra

IOCL
9 MSQ UPGRADATION PROJECT AT
PANIPAT REFINERY
Haryana
10 INST. OF FCC GASOLINE DESULPHUN
UNIT AT MATHURA REFINERY
Uttar Pradesh
11 DADRI- PANIPAT R-LNG SPUR
PIPELINE
Haryana

List of projects completed in 2010-2011 as on 30-09-2010


(All sums of money in crores of rupees

Project
(District)
(State)

Date of
commissioning
Original
( Revised)

Cost
Approved
Original
(Revised)

Cumulative
expenditure

Completed
During

Sector Petroleum
12 NAPHTHA CRACKER & DOWNSTREAM
POLYMER PROJECT AT PANIPAT
Panipat
Haryana

12138

12054.37

Qtr. 2 of 2010-2011

267

72.99

Qtr. 2 of 2010-2011

05/2010

289.6

198.16

Qtr. 2 of 2010-2011

03/2003

536.85

1005.5

Qtr. 2 of 2010-2011

03/2009
07/2010

86.44

201.79

Qtr. 2 of 2010-2011

12/1999
03/2008

105.22

283.49

Qtr. 2 of 2010-2011

223

586.85

Qtr. 2 of 2010-2011

09/2009
11/2009

13 Construction of Tank and Blending


Facility at Vadinar
Gujarat

ONGC
14 BARGE BUMPER-BOAT LANDINGRISER PROTECTOR PROJECT PH-II
Maharashtra

Sector Railways
NEFR
15 NEW JALPAIGURI-NEW BONGAIGAON
(GC),NEFR
Jalpaiguri
Multi State

NL
16 ABOHAR- FAZILKA, NR, NL
Punjab

RVNL
17 HOSPET-GUNTAKAL(LD),SCR
Multi State
18 TAHANJAVUR-VILLUPURAM GAUGE
CONVERSION (G.C)(SR)
(Sr)
Tamil Nadu

11/2008

19 AJMER-PHULERA-RINGUS-REWARI
(G.C.)(NWR)(RVNL)

03/2008
08/2008

352
716.64

616.44

Qtr. 2 of 2010-2011

04/2008

276

360

Qtr. 2 of 2010-2011

04/2008

310

392.26

Qtr. 2 of 2010-2011

Rajasthan

Sector Road Transport &


Highways
NHAI
20 PURNEA-FORBESGANJ (BR-1) PHASEII, KM.309 TO 268, NH-57
Bihar
21 PURNEA-FORBESGANJ (BR-2) PHASEII, KM.268 TO 230, NH-57
Bihar

List of projects completed in 2010-2011 as on 30-09-2010


(All sums of money in crores of rupees

Project
(District)
(State)

Date of
commissioning
Original
( Revised)

Cost
Approved
Original
(Revised)

Cumulative
expenditure

Completed
During

Sector Road Transport &


Highways
22 MADURAI -KANNIAKUMARI SEC. (NS42/TN) NH-7, KM.120 TO KM.160

03/2008

507.49

342.8

Qtr. 2 of 2010-2011

11/2009

360.42

478.4

Qtr. 2 of 2010-2011

07/2008

450

876.61

Qtr. 2 of 2010-2011

05/2009

320

636.1

Qtr. 2 of 2010-2011

26 WAINGANGA BRIDGE -CHHATISGARH- 09/2010


MAHARASHTRA

424

298.4

Qtr. 2 of 2010-2011

12/2008

469.8

665.8

Qtr. 2 of 2010-2011

03/2009

556

568.5

Qtr. 2 of 2010-2011

29 ALLAHABAD BYPASS (KM.198KM.242.708) GQ, NH-2


Allahabad
Uttar Pradesh

05/2007

534.39

716.15

Qtr. 2 of 2010-2011

30 ALLAHABAD BYPASS (KM.158-KM.198)


GQ, NH-2
Allahabad
Uttar Pradesh

12/2006

440.93

641.4

Qtr. 2 of 2010-2011

31 TRICHY BYPASS END TO


TOVARAMKURCHI (NH-45B)(NHAI)

08/2008

261

286.3

Qtr. 2 of 2010-2011

03/2010

546.83

667.8

Qtr. 2 of 2010-2011

03/2009

402.8

453.7

Qtr. 2 of 2010-2011

Tamil Nadu
23 MAHARASHTRA/AP BORDER TO
ISLAM NAGAR,(NS-2/BOT/AP-6),NH-7
Andhra Pradesh
24 ELEVATED HIGHWAY FROM SILK
BOARD JUNCTION TO ELECTRONIC
CITY JUNCTION
Karnataka
25 PADALUR-TRICHY, NH-45
Tamil Nadu

Multi State
27 SALEM TO KERALA BORDER
SEC(TN6), KM.203.96 NH7 TO KM 53
NH47
Tamil Nadu
28 DHULE-PIMPALGAON, NH-3, KM.380
TOKM. 265
Maharashtra

Tamil Nadu
32 ISLAM NAGAR TO KADTAL
Andhra Pradesh
33 AP/KARNATKA BORDER-NANDI HILL
CROSSING AND DEVANHALLI TO
MEENU KUNLE VILLAGE,NH-7
Karnataka

List of projects completed in 2010-2011 as on 30-09-2010


(All sums of money in crores of rupees

Project
(District)
(State)

Date of
commissioning
Original
( Revised)

Cost
Approved
Original
(Revised)

Cumulative
expenditure

Completed
During

Sector Road Transport &


Highways
34 TOVARAMKURCHI-MADURAI,NH45B
(NHAI)

08/2008

263

317.74

Qtr. 2 of 2010-2011

03/2005

467.93

453.64

Qtr. 2 of 2010-2011

03/2005

399.75

424.96

Qtr. 2 of 2010-2011

07/2004

372.4

406.05

Qtr. 2 of 2010-2011

11/2004

2118

Qtr. 2 of 2010-2011

39 ACQUISITION OF TWO NOS.OF 470000 03/2010


DWT MR TANKERS

411.32

406.28

Qtr. 2 of 2010-2011

08/2009

248.94

164.48

Qtr. 1 of 2010-2011

09/2009

416.5
436.54

305.14

Qtr. 2 of 2010-2011

12/2008

409.21

470.24

Qtr. 2 of 2010-2011

Tamil Nadu
35 VARANASI-MOHANIA (GQ) KM.317-329
AND KM.0-KM.65 (NH-2)
Multi State
36 GORHAR-BARWA ADDA (GQ) KM.320KM.398.75 (NH-2)
Jharkhandd
37 FATEHPUR-KHAGA (GQ) KM.38KM.115 (NH-2)
Uttar Pradesh

Sector Shipping & Ports


PORT TRUST
38 DEV. & OPRATION OF AN
INTERNATIONAL CONTAINER
TRANSHIPMENT TERMINAL
Kerala

SHIPP.

Maharashtra

Sector Steel
SAIL
40 REBUILDING OF COKE OVEN BATTRY
NO.-4 STEEL PLANT(SAIL)
Orissa
41 REBUILIDING OF COKE OVEN
BATTERY-10
West Bengal

Sector Telecommunications
BSNL
42 GSM EQUIPMENT OF 1006280 LINES
IN TAMILNADU PH-4.5
Tamil Nadu

List of projects completed in 2010-2011 as on 30-09-2010


(All sums of money in crores of rupees

Project
(District)
(State)

Date of
commissioning
Original
( Revised)

Cost
Approved
Original
(Revised)

Cumulative
expenditure

Completed
During

Sector Telecommunications
43 COMMISSIONING OF GSM
EQUIPMENT OF 650K LINES (PH-IV++)

364.52

51.44

Qtr. 2 of 2010-2011

03/2006

1174.75

371.41

Qtr. 2 of 2010-2011

12/2004

279.97

136.24

Qtr. 2 of 2010-2011

12/2008
12/2009

168.33

175.77

Qtr. 1 of 2010-2011

12/2009

463.61

106.13

Qtr. 1 of 2010-2011

10/2007

741.77

151.37

Qtr. 2 of 2010-2011

12/2009

180.53

25.97

Qtr. 2 of 2010-2011

Maharashtra
44 GSM EXPANSION PH.IV (B) (BSNL)
MAHARASHTRA
Maharashtra

DOT
45 NATIONAL RADIO SPECTRUM
MANAGEMENTand MONIT. SY. IN WPC
(DOT)
Delhi

MTNL
46 EXPANSION OF 750K GSM LINES
Delhi
47 DELHI EXP. OF 1250K LINES OF 2G/3G
GSM LINES
Delhi
48 EXP. OF 750K GSM LINES OF 2.5 GSM
AND VALIDATION EQUPT. WCDMA
Delhi
49 EXPANSION OF EXISTING 2G&3G
GSM N/W BY 750 KPE NO 9920/05-06
Delhi

List Of Additional Delayed Projects


(As on 30-09-2010)

Atomic Energy
NUCLEAR POWER CORPORATION OF INDIA LIMITED

SN
1

Project Name
KUDANKULAM APP (NPCIL)

DOA
12/2001

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
13,171.00
12/2008
13,171.00
6/2011
12/2011

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
490.10
3/2014
490.10
3/2016
3/2017

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
746.04
3/2012
437.34
3/2013
3/2015

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
1,667.55
3/2010
2,675.67
3/2012
3/2014

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
1,294.19
1/2013
1,294.19
10/2012
1/2013

Add Delay
(in Mon)

Coal
MAHANADI COAL FIELDS LIMITED

SN
2

Project Name
BHUBANESWARI OCP

DOA
12/2007

12

NORTHERN COAL FIELDS LIMITED

SN
3

Project Name
BLOCK-B OCP NCL (3.5 MTY)

DOA
6/2006

24

SOUTH-EASTERN COAL FIELDS LIMITED

SN
4

Project Name
GEVRA EXPANSION OCP (SECL) (25 MTY)

DOA
7/2005

24

Fertilisers
NATIONAL FERTILISER LIMITED

SN
5

Project Name
BATHINDA - AMMONIA PLANT FEEDSTOCK
CHANGEOVER PROJECT

DOA
1/2010

List Of Additional Delayed Projects


(As on 30-09-2010)

NANGAL - AMMONIA PLANT FEEDSTOCK


PROJECT

1/2010

1,478.63
1,478.63

PANIPAT - AMMONIA PLANT FEEDSTOCK


CHANGEOVER PROJECT

1/2010

1,292.84
1,292.84

12/2012
10/2012
12/2012
1/2013
10/2012
1/2013

RASHTRIYA CHEMICAL & FERTILISER LIMITED

SN
8

Project Name

DOA

THAL AMMONIA REVAMP PROJECT

1/2009

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
488.75
/
3/2011
488.75
11/2011

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
12/2009
2,591.80
9/2010
3,941.41
10/2010

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
9/2009
1,431.91
10/2010
1,676.00
12/2010
12/2009
293.60
9/2010
293.60
10/2010

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
6/2011
540.92
5/2011
540.92
6/2011
4/2011
1,512.00
10/2010
1,434.00
4/2011

Add Delay
(in Mon)

Petroleum
BHARAT PETROLEUM CORPORATION LIMITED

SN
9

Project Name
CAPACITY
II

EXP. CUM MODERNISATION PH-

DOA
9/2009

BONGAIGAON REFINERY PETROLEUM LIMITED

SN

Project Name

DOA

10

DIESEL HYDRO TREATMENT PROJECT,BRPL


DHALIGAON

6/2006

11

MSQ IMPROVMENT PROJECT

4/2008

GAS AUTHORITY OF INDIA LIMITED

SN

Project Name

DOA

12

BNPL SPURLINE (UTTRANCHAL & PUNJAB)

12/2009

13

COMPRESSOR STATIONS (VIJAYPUR AND


JHABUA) PHASE-I & II

11/2007

List Of Additional Delayed Projects


(As on 30-09-2010)

14

SULTANPUR NEEMRANA PIPE LINE PROJECT


(Spurline to CJPL)

11/2007

396.13
396.13

15

VIJAPUR DADRI-BAWANA PIPE LINE


PROJECT

11/2007

5,595.31
3,700.00

10/2009
9/2010
11/2010
11/2009
8/2010
10/2010

HINDUSTAN PETROLEUM CORPORATION LIMITED

SN

Project Name

DOA

16

CONSTRUCTION OF NEW TERMINAL AT


ENNORE CHENNAI

1/2008

17

INSTALLATION OF FCCV AT MUMBAI


REFINERY

3/2007

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
224.00
12/2010
224.00
12/2010
2/2011
900.47
9/2009
900.47
10/2010
11/2010

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
1,492.00
4/2010
10/2010
1,505.24
11/2010
356.00
2/2010
9/2010
300.00
11/2010
372.00
2/2010
9/2010
325.00
10/2010
5,693.00
1/2010
6,898.00
10/2010
11/2010

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
1,797.35
12/2011
1,797.35
11/2012
1/2013

Add Delay
(in Mon)

INDIAN OIL CORPORATION LIMITED

SN

Project Name

DOA

18

MSQ UPGRADATION PROJECT AT BARAUNI


REFINERY

4/2008

19

MSQ UPGRADATION PROJECT AT DIGBOI


REFINERY

4/2008

20

MSQ UPGRADATION PROJECT AT GUWAHATI


REFINERY

4/2008

21

RESIDUE UPGRADATION AND MS/HSD


QUALITY IMPROVEMENT PROJECT AT GUJRAT

1/2007

OIL & NATURAL GAS CORPORATION LIMITED

SN
22

Project Name
ADDITIONAL GAS PROCESSING UNITS AT
URAN

DOA
10/2008

Power
NATIONAL HYDRO-ELECTRIC POWER CORPORATION

List Of Additional Delayed Projects


(As on 30-09-2010)

SN

Project Name

DOA

23

CHAMERA,STAGE-III (NHPC)

8/2005

24

EST. OF 400/220 KV GIS POOLING


STATION NEAR CHAMERA-II HEP

9/2007

25

LOWER SUBANSIRI

9/2003

26

NIMOO BAZGO HYDROELECTRIC PROJECT


(NHPC)

8/2006

27

TEESTA LOW DAM HEP, STAGE-IV

9/2005

H.E.P (NHPC)

(NHPC)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
1,405.63
8/2010
12/2010
1,405.63
8/2011
262.10
9/2010
9/2010
262.10
12/2010
6,285.33
9/2010
12/2012
7,451.99
12/2013
611.01
8/2010
12/2010
611.02
7/2011
9/2009
1,061.38
8/2011
1,061.38
8/2012

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
8/2013
7,341.04
8/2013
7,341.04
10/2013
11/2010
8,692.97
4/2014
8,692.97
9/2014
2/2010
2,448.50
10/2010
2,448.49
11/2010
11/2012
6,230.81
11/2012
6,230.81
12/2012
11/2012
5,915.00
11/2012
5,915.00
12/2012

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
11/2008
1,779.29
9/2011
2,159.07
3/2012

Add Delay
(in Mon)

12

12

NATIONAL THERMAL POWER CORPORATION

SN

Project Name

DOA

28

BARH STPP STAGE -II (NTPC)

29

BARH STPP(3X660MW) NTPC

30

KORBA STPP STAGE-III

8/2006

31

RIHAND STTP STAGE-III (2X500MW)


(NTPC)

1/2009

32

VINDHYACHAL STTP STAGE-IV (NTPC)

1/2009

2/2008

12/2003

POWER GRID CORPORATION OF INDIA LIMITED

SN
33

Project Name
KUNADANKULAM-APP TRANS. SYSTEM
(PGCIL)

DOA
5/2005

List Of Additional Delayed Projects


(As on 30-09-2010)

34

TR. SYSTEM FOR STARTUP POWER TO DVC &


MAITHON RB GEN. PROJ.

35

TRANSMISSION SY. ASSOCIATED WITH BARH 12/2005


GENER. PROJECT(P.GR.)

36

WESTERN REGION STREGTHENING SCHEME-VI

2/2008

340.72
340.72

37

WESTERN REGION STRENGHTENING SCHEMEIX

4/2008

230.89
230.89

4/2008

290.49
299.08
3,779.46
3,725.13

4/2010
9/2010
12/2010
9/2009
12/2010
3/2011
11/2010
11/2010
12/2010
1/2011
1/2011
2/2011

SATLUJ JAL VIDYUT NIGAM LIMITED

SN
38

Project Name
RAMPUR HEP(412 MW)

DOA
1/2007

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
2,047.03
1/2012
3/2012
2,047.03
9/2013

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
4/2005
1,301.56
12/2010
2,398.39
3/2012
7/2010
1,657.00
12/2014
3,124.76
3/2015

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
726.96
/
810.78
2/2011
3/2012

Add Delay
(in Mon)

Cost
Original
Anticipated

Add Delay
(in Mon)

18

TEHRI HYDRO DEVELOPMENT CORPORATION LIMITED

SN

Project Name

DOA

39

KOTESHWAR HEP(THDC)

4/2000

40

TEHRI PUMPED STORAGE PLANT(1000MW)

7/2006

15

Railways
EAST CENTRAL RAILWAYS

SN
41

Project Name
TALCHER-BIMALAGARH(NL)(ECOR)

DOA
4/2005

13

LINE DOUBLING

SN

Project Name

DOA

DOC Original
Anti Old
Anti

List Of Additional Delayed Projects


(As on 30-09-2010)

42

UTRATIA-ZAFRABAD, NR (LINE DOUBLING)

4/2006

325.00
369.90

3/2010
12/2011
12/2012

12

METROPOLITAN RAPID TRANSPORT PROJECTS

SN
43

Project Name

DOA

MUMBAI URBAN TRANSPORT PROJECT PHASEII, MTP

4/2008

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
5,300.00
3/2014
5,300.00
3/2014
3/2015

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
248.44
/
1,103.47
12/2011
12/2012
190.81
/
234.45
3/2012
12/2012

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
348.16
9/2007
348.16
2/2011
6/2013
367.49
3/2005
367.49
12/2010
4/2011
205.88
6/2010
205.88
8/2010
10/2010
212.00
10/2008
212.00
10/2010
12/2010
445.00
7/2010
445.00
8/2010
10/2010

Add Delay
(in Mon)

12

NORTHERN RAILWAY

SN

Project Name

DOA

44

CHANDIGARH-LUDHIANA(NEW BG
LINE),NR

7/1997

45

JIND-SONEPAT (NL),NR

1/2004

12

Road Transport & Highways


NATIONAL HIGHWAYS AUTHORITY OF INDIA

SN

Project Name

DOA

46

AGRA-BYPASS(NS-1/UP-1), NH-2,3

47

AGRA-SHIKOHABAD (GQ) KM.199.66KM.250.50 (NH-2)

4/2000

48

AMRITSAR-WAGHA BORDER

6/2008

49

AYODHYA-LUCKNOW (LMNHP-3),NH-28,
KM.135.000 TO KM.93.075

50

BANGALORE-NEELAMANGLALA NH-4

12/2003

12/2003

3/2005

28

List Of Additional Delayed Projects


(As on 30-09-2010)

51

BARA TO ORAI, NH-2, 25

12/2003

465.00
465.00

52

CHENNAI BYPASS (NHAI) OTHERS, NH-45,


4 AND 5

12/2003

480.00
480.00

53

COCHIN PORT, NH-47 (PORT


CONNECTIVITY) KMS 348 - KMS 358

4/2000

106.00
193.00

54

DARBHANGA-MUZAFFARPUR, NH-57 (NHAI)

12/2003

305.00
305.00

55

FORBESGANJ TO SIMRAHI (NH-57)(NHAI)

12/2003

332.94
332.94

56

GAGODHAR-GARAMORE(PK-IV,NH15) KM 245
TO 281.3 AND 308 TO 254

12/2003

412.78
479.54

57

GANJAM-ICCHAPURUM,NH-5(NHAI)

4/2000

263.27
263.27

58

GORAKHPUR BYPASS, NH-28, PHASE-II


EAST-WEST CORRIDOR

12/2003

600.24
600.24

59

GORAKHPUR-AYODHYA (LMNHP-4),NH-28,
KM.164.00 TO KM.135.00

12/2003

205.00
205.00

60

GORAKHPUR-AYODHYA (LMNHP-5),NH-28,
KM.208.00 TO KM.164.00

12/2003

227.00
227.00

61

GWALIOR BYPSS, NH-75,3

12/2003

300.93
300.93

62

GWALIOR-JHANSI, NH-75

12/2003

604.00
604.00

63

HALDIA PORT
41)

4/2000

273.00
522.00

64

HARANGAJO TO MAIBANG, NH-54

12/2003

196.00
196.00

65

HARANGAJO TO MAIBANG,km 164.08190.587 NH-54

12/2003

212.00
212.00

(PORT CONNECTIVITY) (NH-

4/2009
12/2010
3/2011
11/2007
8/2010
11/2010
8/2006
8/2010
10/2010
6/2008
12/2010
11/2011
9/2008
3/2011
6/2011
11/2007
6/2010
12/2010
2/2004
6/2010
4/2011
10/2009
3/2011
6/2011
10/2008
10/2010
12/2010
10/2008
3/2011
6/2011
10/2009
10/2010
1/2011
12/2009
12/2010
3/2011
3/2005
9/2010
3/2011
7/2009
12/2012
12/2013
9/2007
12/2012
12/2013

11

10

12

12

List Of Additional Delayed Projects


(As on 30-09-2010)

66

HARIHAR-CHITRADURGA (GQ) KM.284KM.207 (NH-4)

4/2000

318.00
207.56

67

HAVERI-HARIHAR (GQ) KM.340-KM.284


(NH-4)

4/2000

241.00
196.65

68

HYDERABAD-BANGALORE SEC.(NS CORR.PHII)[KM 293.4-336]

12/2003

239.19
239.19

69

HYDERABAD-BANGALORE SEC.(NS CORR.PHII)[KM 376-418]

12/2003

205.92
205.92

70

HYDERABAD-BANGALORE SEC.(NS CORR.PHII)[KM 418-463.16]

12/2003

243.64
243.64

71

JALANDAR-AMRITSAR, KM.407/100 TO
KM.456/100, NH-1

3/2005

263.00
263.00

72

JHANSI TO LALITPUR, NH-25,26

12/2003

355.06
355.06

73

JHANSI TO LALITPUR, NH-26

12/2003

276.09
276.09

74

KASIA TO GORAKHPUR (NH-28)(NHAI)

12/2003

242.00
242.00

75

KOTA BYPASS,RJ-4, NH-76 (NHAI)

12/2003

275.00
250.39

76

KURALI-KIRATPUR, NH-21

3/2005

309.00
309.00

77

LAKHNADON TO MP/MH BORDER (NS1/BOT/MP-2), NH-7

12/2003

263.17
263.17

78

LALITPUR TO SAGAR KM 132 TO KM 187,


NH-26 (NHAI)

12/2003

225.00
225.00

79

LANKA TO DABOKA (NH-54)(NHAI)

12/2003

225.00
225.00

80

MADURAI -KANIAKUMARI SECTION (NS41/TN) NH-7,KM.80 TO KM.120

12/2003

323.36
323.36

8/2004
9/2010
12/2010
8/2004
7/2010
12/2010
9/2009
9/2010
10/2010
8/2009
8/2010
10/2010
8/2009
8/2010
10/2010
2/2009
8/2010
10/2010
9/2009
9/2010
3/2011
9/2009
9/2010
3/2011
12/2008
12/2010
5/2011
10/2008
9/2010
12/2010
6/2010
10/2010
3/2011
9/2009
9/2010
10/2010
10/2008
12/2010
3/2011
6/2008
8/2010
3/2011
3/2008
8/2010
12/2010

List Of Additional Delayed Projects


(As on 30-09-2010)

81

MADURAI-ARUPKOTTAI-TUTICORIN,
KM.138.8 TO KM.264.5, NH-45 B

82

MAIBANG TO LUNDING (AS-24),


KM.111.000 TO KM.126.450

3/2005

629.00
629.00

12/2003

155.04
155.04

83

MAIBANG TO LUNDING (AS-25), KM.83.400 12/2003


TO KM.111.000

199.81
199.81

84

MAIBANG TO LUNDING (AS-26), KM.60.500 12/2003


TO KM.83.400, NH-54

167.64
167.64

85

NAGAON

12/2003

230.00
230.00

86

NEW MANGALORE PORT NH-17 AND 48

4/2000

196.50
196.50

87

NH CONNECTIVITY TO ICTT VALLARPADAEU


NH - SH

3/2005

557.00
557.00

88

ORAI TO JHANSI (UP-4),NH-25,


KM.170.0 TO KM.104.0

12/2003

451.97
451.97

89

ORAI TO JHANSI (UP-5),NH-25,


KM.220.0 TO KM.170.0

12/2003

340.68
340.68

90

PONDICHERY - TINDIVANAU NH-66

3/2005

285.00
285.00

91

RINGBUNDS TO JHAJHANPUR (BR-6)

12/2003

340.00
340.00

92

SAGAR - RAJMARG CHORAHA,KM 211 TO KM


255, NH-26 (NHAI)

12/2003

203.43
203.43

93

SAGAR BY PASS,KM 187 TO KM 211 , NH26 (NHAI)

12/2003

151.30
151.30

94

SALEM - U / UNDRUPET(BOT -1/TN-06) NH


-68

3/2005

941.00
941.00

95

SITAPUR-LUCKNOW

3/2005

322.00
322.00

BYPASS (NH-37)(NHAI)

11/2010
9/2010
11/2010
11/2008
12/2012
12/2013
4/2009
12/2010
12/2013
11/2008
12/2010
12/2013
6/2008
9/2010
12/2010
6/2008
8/2010
12/2010
2/2010
12/2010
10/2011
4/2008
10/2010
3/2011
3/2008
12/2010
3/2011
7/2010
10/2010
1/2011
6/2008
12/2010
3/2011
10/2008
12/2010
12/2011
10/2008
3/2011
11/2011
1/2011
1/2011
6/2011
6/2009
12/2010
3/2011

12

36

36

10

12

List Of Additional Delayed Projects


(As on 30-09-2010)

96

TRICHY - KORUR NH-67

97

UP/BIHAR BORDER TO KASIA (NH28)(NHAI)

98

ZIRAKPUR(HARYANA) -PARWANOO(HIMACHAL
PRADESH)

3/2005

516.00
516.00

12/2003

227.00
227.00

2/2008

295.00
295.00

7/2010
12/2010
6/2011
12/2008
12/2010
6/2011
8/2010
12/2010
5/2011

Shipping & Ports


PORT TRUST

SN
99

Project Name
DEEPENING OF CHEENEL AT PARADIP PORT

DOA
12/2005

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
6/2007
154.84
253.36
9/2010
12/2010

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
11/2010
586.58
586.58
11/2010
3/2011

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
6/2011
1,902.00
1,902.00
8/2010
10/2010
6/2009
302.70
302.70
8/2010
10/2010
1/2010
172.78
172.78
11/2010
2/2011

Add Delay
(in Mon)

SHIPPING crp. of india

SN
100

Project Name
ACQUISITION OF 2 NOS. OF 105000 DWT
LR-II TANKERS

DOA
8/2007

Steel
STEEL AUTHORITY OF INDIA LIMITED (SAIL)

SN

Project Name

DOA

101

EXPANSION OF SALEM STEEL PLANT

1/2008

102

INSTALLATION OF 700 TPD OXYGEN PLANT,


ROURKELA

7/2007

103

REBUILDING OF COKE OVEN BATTERY NO-6


(BSP)

7/2008

List Of Additional Delayed Projects


(As on 30-09-2010)

104

Rebuilding of coke oven battery No.1


& 2 (Bokaro Steel Plant)

10/2007

500.90
500.90

105

SIMULTANEOUS BLOWING OF BOF CONVERTER


OF SMS-II

1/2008

197.66
197.66

4/2010
4/2011
7/2011
11/2009
8/2010
10/2010

Telecommunications
BHARAT SANCHAR NIGAM LIMITED

SN

Project Name

DOA

106

GSM equipment of 1100000Lines (2G)


UP East Phase V.2 Telecom Circle

9/2009

107

GSM equipment of 1500000Lines (2G)


264700lines 3(G)Andhra Pradesh Phase
V.1 Telecom Circle

1/2009

108

GSM equipment of 1625000Lines (2G)


325000 lines 3(G) MP Phase V.1
Telecom Circle

11/2009

109

GSM equipment of 1700000Lines (2G)


234100 lines 3(G)Karnataka Phase
V.1 Telecom Circle

10/2008

110

GSM equipment of 1867000Lines (2G)


383000 lines 3(G) GujaratPhase V.1
Telecom Circle

8/2008

111

GSM equipment of 1900000Lines (2G)


335500lines 3(G)kerala Phase V.1
Telecom Circle

1/2009

112

GSM equipment of 1900000Lines (2G)


401700 lines 3(G)Tamil Nadu Phase
V.1 Telecom Circle

1/2009

113

GSM equipment of 2,00,000Lines (2G)


Rajasthan ( Phase V.2) Telecom Circle

9/2009

114

GSM equipment of 200000Lines (2G)


UP(West)Phase V.2 Telecom Circle

115

GSM equipment of 375000Lines (2G)


75000lines 3(G) Kolkatta Phase V.1
Telecom Circle

6/2008

116

GSM equipment of 614000Lines (2G)


150000lines 3(G) Chennai TD Phase
V.1 Telecom Circle

1/2009

10/2008

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
9/2010
624.75
8/2010
624.75
11/2010
1/2010
922.91
8/2010
922.91
12/2010
11/2010
916.70
8/2010
916.70
11/2010
10/2009
677.75
9/2010
719.70
12/2010
8/2009
868.00
9/2010
868.00
12/2010
1/2010
848.70
9/2010
848.70
11/2010
1/2010
760.20
8/2010
810.37
11/2010
9/2010
577.35
8/2010
577.35
9/2010
10/2009
336.84
8/2010
336.84
11/2010
6/2009
170.23
8/2010
167.20
12/2010
1/2010
315.19
8/2010
315.19
12/2010

Add Delay
(in Mon)
3

List Of Additional Delayed Projects


(As on 30-09-2010)

117

GSM equipment of 799000Lines (2G)


101000 lines 3(G) JharkhandPhase V.1
Telecom Circle

3/2008

328.13
392.44

118

GSM equipment of 849862Lines (2G)


150138 lines 3(G) West Bengal Phase
V.1 Telecom Circle

2/2008

584.33
584.33

119

GSM equipment of 900000Lines (2G)


PunjabPhase V.2 Telecom Circle

9/2008

241.49
241.49

120

GSM equipment of 945000Lines (2G)


225000lines 3(G) Bihar Phase V.1
Telecom Circle

10/2007

366.00
529.32

121

GSM equipment of 975000Lines (2G)


325000 lines 3(G) UP East Phase V.1
Telecom Circle

2/2009

625.53
625.53

3/2009
8/2010
10/2010
2/2009
8/2010
10/2010
9/2009
9/2010
11/2010
10/2008
8/2010
12/2010
2/2010
8/2010
11/2010

MAHANAGAR TELEPHONE NIGAM LIMITED

SN
122

Project Name
Expn of existing 2G & 3G GSM N/W by
750k

DOA
10/2008

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
6/2010
180.53
180.53
9/2010
12/2010

Add Delay
(in Mon)

Cost
DOC Original
Original
Anti Old
Anticipated
Anti
6/2010
8,676.00
18,894.36
9/2010
10/2010

Add Delay
(in Mon)

Urban Development
DELHI METRO RAIL CORPORATION

SN
123

Project Name
DELHI MRTS PHASE-II PROJECT

DOA
8/2005

Major Factors For Delay


Sr.
No.

Sector

Fund
Constraints

Land
Acquisition

Environment
Clearance

Slow
Progress

Delay in
Supply of
Equipments

Law &
Order

Others*

0
2

0
0

1 Atomic Energy

2 Civil Aviation

3 Coal

4 Fertilisers

5 Financ

6 Health & Family Welfare

0
0

7 Heavy Industry

8 Information &
Broadcasting
9 Information technology

10 Mines

11 Petrochemicals

0
0

12 Petroleum

13 Power

0
0

2
0

32

0
1

0
0

14 Railways

16

39

44

15 Road Transport &


Highways
16 Shipping & Ports

17 Steel

18 Telecommunications

19 Urban Development

20 Water Resources

0
0

21 mobile sector

20

47

46

52

* Includes Technology selection and agreement, Award of contract,Delay in civil works and government
clearance, Geomining, Court case, Inadequate Infrastructure and bad whether.

Summary of Central Sector Projects in Various States/UTs


(Status of projects as on

Sr
N.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29

State Name
Andhra Pradesh
Arunachal Pr.
Assam
Bihar
Chhatisgarh
Delhi
Goa
Gujarat
Haryana
Himachal Pr.
J & K
Jharkhandd
Karnataka
Kerala
Madhya pradesh
Maharashtra
Manipur
Meghalaya
Mizoram
Multi State
Orissa
Punjab
Rajasthan
Sikkim
Tamil Nadu
Tripura
Uttar Pradesh
Uttaranchal
West Bengal

TOTAL

No of
Projects
35
4
40
31
17
3
1
20
11
8
9
21
18
11
26
48
1
1
2
94
26
11
10
2
32
3
39
8
21
553

Cost
Original
28652.64
9512.22
23365.64
29643.83
20642.28
9413.76
204.73
13416.98
4780.87
15381.72
8963.30
9761.89
15490.06
9511.93
19323.72
62200.88
578.62
71.18
988.06
114175.36
49676.93
5532.97
8832.80
1603.77
39822.61
1522.39
24151.87
11951.31
30305.35
569479.67

30.9.2010 )
(Rs.Crores)
Cost
Anticipated Expenditure
35503.31
10683.36
28500.60
32782.54
35617.35
19612.53
204.73
16549.86
5449.61
15463.96
19472.26
14698.51
22957.00
11042.22
19588.25
81510.29
578.62
443.15
3343.04
118035.43
53626.70
6388.00
9560.86
3644.86
45724.94
1724.82
26070.62
14505.03
37720.77
691003.22

17316.17
5617.91
10486.29
17210.34
12597.26
16104.48
5.97
9800.34
2288.28
10102.42
10575.70
4975.65
10595.15
5713.50
6748.41
27039.48
28.33
547.78
218.40
28842.20
13626.52
2781.33
5753.32
2.56
31755.38
156.65
10554.54
3989.84
20485.93
285920.13

SN
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25

NO OF
COST
COST
EXPENDITURE
STATE NAME
PROJECTS ORIGINAL ANTICIPATED CUMM
Andhra Pradesh
4
18498.68
22473.82
3089.09
Arunachal Pr.
2
8782.23
9948.89
3312.04
Assam
7
15666.01
17766.09
2906.99
Bihar
5
21929.94
22786.22
5866.21
Chhatisgarh
5
17182.12
17182.12
6960.19
Delhi
1
8676.00
8676.00
4870.33
Gujarat
3
7475.92
8257.49
1860.27
Haryana
2
2098.84
2352.84
325.02
Himachal Pr.
5
14203.96
13761.84
6233.22
J&K
4
7133.42
15710.53
6305.36
Jharkhandd
2
3807.19
4961.00
603.77
Karnataka
3
10746.00
10578.62
2272.29
Kerala
2
6091.80
7441.41
0.00
Madhya pradesh
4
10442.67
10441.58
1172.88
Maharashtra
20
49505.24
48928.05
2871.94
Mizoram
1
619.34
619.34
0.00
Multi State
29
87213.78
89031.84
2243.44
Orissa
5
43568.70
43568.70
2637.68
Punjab
3
3021.26
3359.90
460.62
Rajasthan
2
6335.41
6847.32
1354.49
Sikkim
1
1339.48
1339.48
0.00
Tamil Nadu
8
30980.01
31520.16
15579.86
Uttar Pradesh
4
12761.14
13027.86
2415.25
Uttaranchal
5
11323.72
11324.32
2061.45
West Bengal
7
27205.59
28581.66
4614.71
TOTAL
134
426608.45
450487.08
80017.10

List of Delayed Projects in qr-2 ,2010-2011


SN

9
10

11

12
13

14

PROJECT NAME
Andhra Pradesh
Railways

DOA

DOC
ORIGINAL
ANTICIPATED COST

ANTICIPATED EXPENDITURE
COST
CUMM

RAICHUR-GUNTAKAL(DL)(SCR)
Road Transport & Highways
HYDERABAD-BANGALORE
SEC.(NS CORR.PH-II)[KM 211251]
HYDERABAD-BANGALORE
SEC.(NS CORR.PH-II)[KM 418463.16]
HYDERABAD-BANGALORE
SEC.(NS CORR.PH-II)[KM 336376]
HYDERABAD-BANGALORE
SEC.(NS CORR.PH-II)[KM 376418]
HYDERABAD-BANGALORE
SEC.(NS CORR.PH-II)[KM 251293.4],N
HYDERABAD-BANGALORE
SEC.(NS CORR.PH-II)[KM 293.4336]
Shipping & Ports
Mechanization of coal handling
facilities to 200000 DWT Vessels
on DBFOT basis
Steel
COKE OVEN BATTERY NO. 4
PHASE-II
Augmentation of Iron Ore Storage
in RMHP
EXPANSION OF RINL/VSP
FROM 3 MTPY-6.3 MTPY OF
LIQUID STEEL (RINL)
67.5 MW TG-5 AUX. S'TEM
EMERGENCY POWER
REQUIREMENT EXP. UNIT
330 TPH BOILER-6 AND
AUXILIARY SYSTEM
Telecommunications
GSM equipment of 1500000Lines
(2G) 264700lines 3(G)Andhra
Pradesh Phase V.1 Telecom
Circle
Arunachal Pr.
Power

04/2003

12/2010

136.62

221.90

124.14

12/2003

10/2010

194.80

194.80

174.00

12/2003

10/2010

243.64

243.64

254.70

12/2003

10/2010

243.38

243.38

261.40

12/2003

10/2010

205.92

205.92

204.40

12/2003

10/2010

208.46

208.46

193.70

12/2003

10/2010

239.19

239.19

224.50

02/2010

11/2012

444.10

444.10

0.00

08/2007

06/2011

108.00

168.95

12.00

05/2008

12/2011

480.00

480.84

4.04

10/2005

06/2011

8692.00

12228.00

7323.00

07/2007

01/2011

230.00

358.00

114.32

07/2007

08/2010

260.00

353.00

188.89

01/2009

12/2010

922.91

922.91

266.06

SN
15

16
17
18
19
20

21

22

23
24
25
26
27
28
29
30
31
32

33

34

DOA

DOC
ORIGINAL
ANTICIPATED COST

09/2003

12/2013

6285.33

7451.99

4181.57

04/2008
09/2001

10/2010
03/2011

293.60
390.09

293.60
1200.00

0.00
1125.49

09/2001
09/2001

03/2011
03/2011

345.10
113.90

600.00
219.22

542.47
183.10

06/2006

12/2010

1431.91

1676.00

1438.72

01/2008

03/2012

4375.35

4375.35

1422.00

04/1996

03/2014

1000.00

3230.02

1920.25

12/2003

12/2012

217.61

217.61

75.75

12/2003

12/2013

212.00

212.00

35.04

GUWAHATI TO NALBARI (AS-5) 12/2003


DHARAMTUL TO SONAPUR (AS19)
12/2003
NALBARI TO BIJNI (AS-8)
12/2003
NALBARI T BIJNI (AS-7)
12/2003
DAKOBA TO NAGAON (NH36)(NHAI)
12/2003
LANKA TO DABOKA (NH54)(NHAI)
12/2003
NALBARI TO BIJNI (AS-6)
12/2003
NAGAON BYPASS (NH37)(NHAI)
12/2003

03/2012

198.16

198.16

137.80

12/2011
01/2011
12/2011

200.00
200.00
208.00

200.00
200.00
208.00

150.20
186.80
163.80

10/2011

225.00

225.00

203.40

03/2011
03/2011

225.00
225.00

225.00
225.00

201.60
144.50

12/2010

230.00

230.00

289.00

12/2003

12/2011

237.80

237.80

119.60

12/2003

12/2011

230.00

230.00

132.90

03/2011

280.00

280.00

139.40

12/2013

199.81

199.81

28.39

12/2013

167.64

167.64

39.49

PROJECT NAME
LOWER SUBANSIRI H.E.P
(NHPC)
Assam
Petroleum
MSQ IMPROVMENT PROJECT
IOR GELEKI (ONGCL)
IOR LAKWA - LAKHMANI
(ONGCL)
IOR, RUDRASAGAR (ONGCL)
DIESEL HYDRO TREATMENT
PROJECT,BRPL DHALIGAON
Power
BONGAIGAON THERMAL
POWER PROJECT (NTPC)
Railways
BRAHAMAPUTRA BRIDGE AT
BOGIBIL AND LINK
LINES,NEFR
Road Transport & Highways
BRAHMPUTRA BRIDGE,NH NO31
HARANGAJO TO MAIBANG,km
164.08-190.587 NH-54

BIJNI TO ASSAM /WB.BORDER


(NH-31.C)(2)(NHAI)
BIJNI TO ASSAM/WB BORDER
PH.II, KM.30.00 TO 0.00, NH-31
C

36

HARANGAJO TO MAIBANG (AS23), KM.126.450 TO KM.140.700 12/2003


MAIBANG TO LUNDING (AS-25),
KM.83.400 TO KM.111.000
12/2003

37

MAIBANG TO LUNDING (AS-26),


KM.60.500 TO KM.83.400, NH-54 12/2003

35

ANTICIPATED EXPENDITURE
COST
CUMM

SN

38
39
40
41
42
43
44
45
46

47
48

49
50

51
52

53
54
55

56
57
58
59

PROJECT NAME

DOA

MAIBANG TO LUNDING (AS-24),


KM.111.000 TO KM.126.450
12/2003
MAIBANG TO LUNDING (AS-27),
KM.40.000 TO KM.60.500
12/2003
SILCHAR-UDARBAND (PH.II) HN54, KM.309 TO KM.275
12/2003
DHARAMTUL TO SONAPUR,KM
205-183 (AS-20)
12/2003
GUWHATI TO NALBARI (AS-4)
12/2003
BIJNI TO ASSAM WB BORDER
(NH-31.C)(1)(NHAI)
12/2003
SONAPUR TO GUWAHTI (AS-3)
NAGAON TO DHARAMTUL (AS2)
HARANGAJO TO MAIBANG, NH54
Telecommunications
Assam Telecom Circle, Phase-V.I,
2G & 3G
Water Resources
PAGLADIYA DAM PROJECT
Bihar
Petroleum
MSQ UPGRADATION PROJECT
AT BARAUNI REFINERY
Power
BARH STPP STAGE -II (NTPC)
TRANSMISSION SY.
ASSOCIATED WITH BARH
GENER. PROJECT(P.GR.)
BARH STPP(3X660MW) NTPC
Railways
SITAMARHI-RAXAULNARKATIAGANJ (GC)
RAIL-CUM-ROAD BRIDGE AT
MUNGER (NL), ECR
PATNA GANGA BRIDGE (NL),
ECR
Road Transport & Highways
RINGBUNDS TO JHAJHANPUR
(BR-6)
DARBHANGA-MUZAFFARPUR,
NH-57 (NHAI)
JHAJHARPUR TO DARBANGA
(BR-7)
FORBESGANJ TO SIMRAHI (NH57)(NHAI)

DOC
ORIGINAL
ANTICIPATED COST

ANTICIPATED EXPENDITURE
COST
CUMM

12/2013

155.04

155.04

28.27

04/2011

200.00

200.00

63.10

03/2011

157.47

154.57

137.80

06/2011
03/2012

160.00
175.96

160.00
175.96

85.57
95.16

12/2011

195.00

195.00

125.40

12/2003

03/2011

245.00

245.00

245.90

12/2003

12/2011

264.72

264.72

189.00

12/2003

12/2013

196.00

196.00

25.11

06/2007

12/2010

336.81

336.81

105.16

01/2001

12/2012

542.90

1187.00

35.49

04/2008

11/2010

1492.00

1505.24

1069.91

02/2008

10/2013

7341.04

7341.04

1105.00

12/2005
12/2003

03/2011
09/2014

3779.46
8692.97

3725.13
8692.97

3409.04
5057.00

04/1997

03/2012

501.69

501.69

45.90

04/2002

12/2012

921.00

981.00

340.69

04/2001

12/2012

624.47

1480.71

445.84

12/2003

03/2011

340.00

340.00

485.10

12/2003

11/2011

305.00

305.00

462.00

12/2003

12/2011

340.00

340.00

344.90

12/2003

06/2011

332.94

332.94

219.90

SN

60

61

62

63

64

65

66
67

68
69
70
71
72
73

74

75

76
77

PROJECT NAME
DOA
KOSI BRIDGE INCLUDING
APPROACHES AND GUIDE
BOND AND AFFLUX-BOND (BR5)
12/2003
MEHSI TO KOTWA (LMNHP-II),
PH.II, KM.480 TO KM.440, NH-28 12/2003
MUZZAFFARPUR TO MEHSI
(LMNHP-12), KM.520 TO 480, NH28
12/2003
KOTWA TO DEWAPUR(10
LMNHP),NH-28 PHASE-II,
KM.440 TO KM.402
12/2003
PURNEA-GOYAKOTA SEC.(EW)
(NS AND EW-PH-I) KM.419KM.447, NH-31
04/2000
DARBHANGAMUZAFFARPUR(KM 30 TO KM
0), NH-57 (NHAI)
12/2003
Telecommunications
GSM equipment of 945000Lines
(2G) 225000lines 3(G) Bihar
Phase V.1 Telecom Circle
10/2007
BIHAR TELECOM CIRCLE
PHASE-V.1, 2G &3G
04/2007
Chhatisgarh
Coal
MANIKPUR OC EXPANTION
11/2009
DIPKA EXPANSION OCP (SECL)
(20 MTY)
07/2005
GEVRA EXPANSION OCP
(SECL) (25 MTY)
07/2005
KUSMUNDA
EXPN.OCP(SECL)(10MTY)
06/2006
PELMA OC
07/2008
Power
SIPAT STPP STAGE - I (NTPC) 12/2003
Railways
SALKA ROAD -ANUPNAGAR
LINE DOUBLING
09/2006
Road Transport & Highways
AURANG-RAIPUR, NH-6, KM.232
TO KM.281
03/2005
Delhi
Telecommunications
EXP. OF 750K GSM LINES OF
2.5 GSM AND VALIDATION
EQUPT. WCDMA
02/2007
CONVERGENT BILLING AND
CRM-MTNL(DELHI)
12/2005

DOC
ORIGINAL
ANTICIPATED COST

ANTICIPATED EXPENDITURE
COST
CUMM

06/2011

418.04

418.04

252.70

03/2011

239.00

239.00

265.10

03/2011

275.00

275.00

292.40

03/2011

240.00

240.00

202.50

12/2010

205.73

205.73

244.30

12/2010

291.80

291.80

425.50

12/2010

366.00

529.32

202.66

10/2010

366.00

529.32

202.66

03/2014

321.42

321.50

211.81

03/2014

1268.53

1943.66

887.83

03/2014

1667.55

2675.67

1011.42

03/2013
03/2015

737.65
448.32

1188.31
448.32

554.36
0.00

12/2011

8323.39

8323.39

6993.00

03/2012

324.90

324.90

116.94

12/2010

190.00

190.00

221.70

09/2010

741.77

278.16

151.37

03/2011

249.00

229.41

66.20

DOA

DOC
ORIGINAL
ANTICIPATED COST

ANTICIPATED EXPENDITURE
COST
CUMM

08/2000

09/2010

279.97

172.04

136.24

10/2008

09/2010

180.53

180.53

25.97

08/2005

10/2010

8676.00

18894.36

15839.63

81

PROJECT NAME
NATIONAL RADIO SPECTRUM
MANAGEMENTand MONIT. SY.
IN WPC (DOT)
EXPANSION OF EXISTING
2G&3G GSM N/W BY 750 KPE
NO 9920/05-06
Urban Development
DELHI MRTS PHASE-II
PROJECT
Gujarat
Petroleum
C2-C3 AND LPG RECOVERY
FROM LNG, DAHEJ (ONGC)

12/2003

10/2010

900.92

1493.49

726.23

82

ADDITIONAL GAS PROCESSING


FACILITI AT HAZIRA
02/2008

07/2012

370.11

370.11

8.53

02/2009

12/2011

349.00

349.00

114.41

02/2008

12/2010

340.72

340.72

147.53

04/2005

10/2010

148.61

227.52

241.13

12/2003

12/2010

412.78

479.54

424.60

01/2002

01/2011

165.00

165.00

107.58

08/2008

12/2010

868.00

868.00

274.30

06/2005

10/2010

806.00

1096.23

809.69

04/2008

12/2010

290.49

299.08

301.86

01/2004

02/2011

149.38

475.16

405.65

SN

78

79

80

83

84

85

86

87

88

89

90
91

BRANCH PIPELINE FROM KSPL


VIRAMGAON TO KANDLA
Power
WESTERN REGION
STREGTHENING SCHEME-VI
Railways
PRATAPNAGAR-CHOTA
UDAIPUR (GC) (WR)
Road Transport & Highways
GAGODHAR-GARAMORE(PKIV,NH15) KM 245 TO 281.3 AND
308 TO 254
Shipping & Ports
ESTABLISHMENT OF VESSEL
TRAFFIC SERVICES IN GULF
OF KUTCH
Telecommunications
GSM equipment of 1867000Lines
(2G) 383000 lines 3(G)
GujaratPhase V.1 Telecom Circle
Haryana
Petroleum
EXPANSION OF PANIPAT
REFINERY FROM 12 TO 15
MMTPA
Power
TR. SYSTEM FOR STARTUP
POWER TO DVC & MAITHON
RB GEN. PROJ.
Railways
REWARI-ROHTAK (NL),NR
Road Transport & Highways

SN
92

93

94
95
96
97
98

99
100

101
102
103

104

105

106

107
108

109
110

111

DOA

DOC
ORIGINAL
ANTICIPATED COST

04/2007

05/2011

486.00

486.00

287.00

07/2006

06/2011

557.24

639.52

377.38

12/2005

12/2012

358.42

358.42

6.57

10/2005
08/2005
09/2002
10/2002

06/2011
08/2011
03/2013
12/2011

2304.56
1405.63
3919.59
4527.15

2304.52
1405.63
3919.59
4527.15

1123.71
1285.03
2903.19
3315.00

09/2007
01/2007

12/2010
09/2013

262.10
2047.03

262.10
2047.03

138.79
952.75

08/2006
08/2005
07/2007

07/2011
02/2011
01/2016

611.01
1729.29
2238.67

611.02
1724.79
3642.04

512.92
1211.77
472.88

03/1995

12/2017

2500.00

11270.00

6481.16

12/2003

12/2010

166.27

166.27

105.30

12/2003

12/2010

193.09

193.09

140.30

04/2006
07/2006

03/2012
03/2013

471.66
469.78

341.63
706.40

101.85
16.23

02/1999

11/2010

180.73

358.00

322.19

RANCHI-LOHARDAGA(GC),SER 04/1997
Road Transport & Highways
GORHAR-BARWA ADDA (GQ)
KM.320-KM.398.75 (NH-2)
04/2000
Steel

03/2011

193.78

456.45

247.29

10/2010

399.75

399.75

424.96

PROJECT NAME
DELHI/ HARYANA BORDER TO
ROHTAK
Himachal Pr.
Power
TRANSMISSION SYSTEM
ASSOCIATED WITH PARBATI-III
HEP
TRANSMISSION SYSTEM
ASSOCIATED WITH PARBATI =
II HEP
PARBATI H.E.P. STAGE -III
(NHPC)
CHAMERA,STAGE-III (NHPC)
PARBATI HEP (NHPC) II
KOLDAM HEP (NTPC)
EST. OF 400/220 KV GIS
POOLING STATION NEAR
CHAMERA-II HEP
RAMPUR HEP(412 MW)
J&K
Power
NIMOO BAZGO
HYDROELECTRIC PROJECT
(NHPC)
URI H.E.P STAGE -II (NHPC)
KISHANGANGA HEP
Railways
UDHAMPUR-SRINAGARBARAMULLA (NL),NR
Road Transport & Highways
VIJAYAPUR TO PATHANKOT
(NS-35/J AND K) NH-1A KM.50
TO KM.80
VIJAYAPUR TO PATHANKOT (J
AND K) NH-1A KM.16.35 TO
KM.50.00
Jharkhandd
Coal
ASHOK EXPN.OCP -CCL (6.5
MTY)
MAGADH OC (CCL)
Railways
DEOGHAR-DUMKA NEW BG
LINE (DOUBL.)(ER)

ANTICIPATED EXPENDITURE
COST
CUMM

SN
112
113

114

115

116

117
118
119
120
121

122

123

124

125
126

127

128

PROJECT NAME
Rebuilding of coke oven battery
No.1 & 2 (Bokaro Steel Plant)
REBUILDING OF COKE OVEN
BATTERY NO-6 (BSP)
UPGRADATION OF BLAST
FURNANCE NO.2(BOKARO
STEEL PLANT)
Telecommunications
GSM equipment of 799000Lines
(2G) 101000 lines 3(G)
JharkhandPhase V.1 Telecom
Circle
Karnataka
Atomic Energy
KAIGA 3 & 4 UNITS (NPCIL)
Road Transport & Highways
HARIHAR-CHITRADURGA (GQ)
KM.284-KM.207 (NH-4)
BANGALORE-NEELAMANGLALA
NH-4
NEW MANGALORE PORT NH-17
AND 48
HAVERI-HARIHAR (GQ) KM.340KM.284 (NH-4)
BANGLORE - HOSKOTE
MUDBOGAL SECTION NH-4
NEELAMANGALAR JUNCTION
ON NH-4 SMITH NH-48 TO
DEVIHALLI
Telecommunications
GSM equipment of 1700000Lines
(2G) 234100 lines 3(G)Karnataka
Phase V.1 Telecom Circle
Urban Development
BANGALORE METRO RAIL
PROJECT
Kerala
Petroleum
CAPACITY EXPANSION AND
MODERNISATION OF KOCHI
REFINERY
CAPACITY EXP. CUM
MODERNISATION PH-II
Road Transport & Highways
NH CONNECTIVITY TO ICTT
VALLARPADAEU NH - SH
COCHIN PORT, NH-47 (PORT
CONNECTIVITY) KMS 348 - KMS
358

DOA

DOC
ORIGINAL
ANTICIPATED COST

ANTICIPATED EXPENDITURE
COST
CUMM

10/2007

07/2011

500.90

500.90

216.39

07/2008

02/2011

172.78

172.78

108.46

10/2007

07/2010

892.32

892.32

616.57

03/2008

10/2010

328.13

392.44

149.92

05/2001

12/2010

4213.00

3282.00

2572.00

04/2000

12/2010

318.00

207.56

110.72

03/2005

10/2010

445.00

445.00

802.00

04/2000

12/2010

196.50

196.50

196.10

04/2000

12/2010

241.00

196.65

99.15

03/2005

10/2010

565.00

565.00

881.00

03/2005

03/2011

441.00

441.00

632.80

10/2008

12/2010

677.75

719.70

294.44

05/2006

03/2013

6395.00

11609.00

2954.59

04/2006

09/2010

2591.80

3941.41

1793.00

09/2009

10/2010

2591.80

3941.41

2864.54

03/2005

10/2011

557.00

557.00

914.50

04/2000

10/2010

106.00

193.00

141.70

SN
129

130
131

132

133
134
135
136
137
138

139

140
141

142

143
144
145

146

147
148

PROJECT NAME
THRISSUR TO ANGAMALI (NH47)
Shipping & Ports
DEV. & OPRATION OF AN
INTERNATIONAL CONTAINER
TRANSHIPMENT TERMINAL
RAIL CONNECTIVITY TO ICTT
AT VALLARPADAM
Telecommunications
GSM equipment of 1900000Lines
(2G) 335500lines 3(G)kerala
Phase V.1 Telecom Circle
Madhya pradesh
Coal
Batura OC
AMLOHRI EPR (NCL) (6 MTY)
KRISHNASHILA (NCL) (4MTY)
BLOCK-B OCP NCL (3.5 MTY)
Power
KORBA STPP STAGE-III
VINDHYACHAL STTP STAGE-IV
(NTPC)
Railways
BHOPAL BINA 3D LINE
DOUBLING
Road Transport & Highways
RAJMARG CHORAHA TO
LAKHNANDON,KM 297 TO KM
351, NH-26 (NHAI)
GWALIOR BYPSS, NH-75,3
LAKHNAADON TO MP/MH
BORDER,KM 596.75-653.22 (NS1/BOT/MP-2),NH7
LAKHNADON TO MP/MH
BORDER (NS-1/BOT/MP-2), NH7
KALGHAT-MP/MAHARASHTRA
BORDER KM 16.6-84.70
LALITPUR TO SAGAR, NH-26
(NHAI)
SAGAR - RAJMARG
CHORAHA,KM 211 TO KM 255,
NH-26 (NHAI)
RAJMARG CHORAHA TO
LAKHNANDON,KM 351 TO KM
405.7, NH-26 (NHA
LALITPUR TO SAGAR KM 132
TO KM 187, NH-26 (NHAI)

DOA

DOC
ORIGINAL
ANTICIPATED COST

ANTICIPATED EXPENDITURE
COST
CUMM

12/2003

12/2010

312.50

312.50

477.00

11/2004

10/2010

2118.00

2118.00

0.00

03/2007

12/2010

245.67

298.17

297.86

01/2009

11/2010

848.70

848.70

438.75

09/2008
05/2006
05/2006
06/2006

03/2015
03/2016
03/2013
03/2015

203.82
1352.04
789.88
746.04

203.82
1143.54
741.56
437.34

0.00
32.03
136.37
136.70

08/2006

11/2010

2448.50

2448.49

2059.00

01/2009

12/2012

5915.00

5915.00

1019.00

09/2007

12/2012

687.20

687.20

125.24

12/2003
12/2003

06/2011
01/2011

251.03
300.93

251.03
300.93

205.60
232.10

12/2003

12/2010

407.60

407.60

182.00

12/2003

10/2010

263.17

263.17

232.50

11/2008

05/2011

549.00

549.00

641.80

12/2003

03/2011

198.00

198.00

132.10

12/2003

12/2011

203.43

203.43

138.60

12/2003

06/2011

229.91

229.91

150.30

12/2003

03/2011

225.00

225.00

205.30

SN

149

150

151
152
153
154

155
156
157
158

159
160
161
162
163
164
165
166

167

168
169

PROJECT NAME
SAGAR - RAJMARG
CHORAHA,KM 255-297, NH-26
(NHAI)
Telecommunications
GSM EQUIPMENT OF 1625K
LINES(2G) & 325K LINES IN M.P
PH-V.I
Maharashtra
Petroleum
INSTALLATION OF FCCV AT
MUMBAI REFINERY
HEERA RECONSTRUCTION
ADDITIONAL GAS PROCESSING
UNITS AT URAN
HEERA AND SOUTH HEERA REDEVELOPMENT PROJECT
LUBE OIL BASE STOCK
QUALITY UPGRADATION AT
MUMBAI REFINERY
DEVELOPMENT OF B-22
CLUSTER FIELDS
DEVELOPMENT OF B-193
CLUSTER FIELDS
CONSTRUCTION OF NEW
PROCESS COMPLEX MHN
OFFSHORE GRID
INTERCONNECTIVITY
PROJECT IN MUMBAI HIGH
MUMBAI HIGH SOUTH
REDEVELOPMENT PH-2
DEVELOPMENT OF C-SERIES
FIELDS
REVAMPING OF WIN
PLATFORM AT MH ASSET
MNW-NF BRIDGE PROJECT
DEVELOPMENT OF B-46
CLUSTER FIELD
Power
MOUDA STPP (NTPC)
WESTERN REGION
STRENGTHENING SCHEME-V
Railways
MUMBAI URBAN TRANSPORT
PROJECT PHASE-II, MTP
BELAPUR-SEAWOOD-URAN
ELECTRIF-IED DOUBLE
LINE(MTP)
AMRAVATI-NARKHER NL(CR)
Road Transport & Highways

DOA

DOC
ORIGINAL
ANTICIPATED COST

ANTICIPATED EXPENDITURE
COST
CUMM

12/2003

12/2010

206.96

206.96

281.90

06/2008

09/2010

908.30

916.70

151.70

03/2007
05/2008

11/2010
04/2011

900.47
706.70

900.47
706.70

679.84
456.65

10/2008

01/2013

1797.35

1797.35

9.78

09/2006

03/2011

2305.30

2305.30

2061.15

10/2006

07/2010

638.90

1030.00

796.21

01/2007

05/2012

1552.63

2920.82

164.51

06/2007

06/2012

3248.78

5633.44

45.51

01/2007

05/2012

2853.29

6326.40

1269.57

01/2007

03/2012

740.02

740.02

411.41

06/2007

03/2013

1252.75

8813.41

5208.06

08/2006

03/2011

3195.16

2800.00

2520.63

05/2008
05/2008

05/2011
05/2011

333.40
175.21

330.40
162.12

0.39
0.00

06/2007

05/2012

1436.21

1436.21

0.00

11/2007

10/2012

5459.28

6010.89

1431.00

12/2007

03/2011

477.69

477.69

313.87

04/2008

03/2015

5300.00

5300.00

128.02

03/1996
06/1994

12/2010
03/2011

401.81
120.90

495.44
488.76

155.05
355.55

DOA

DOC
ORIGINAL
ANTICIPATED COST

03/2005

12/2010

168.00

168.00

305.42

03/2005

01/2011

579.00

579.00

678.70

08/2008

12/2011

1108.12

1168.42

569.26

08/2007

03/2011

586.58

586.58

475.09

06/2011

290.85

290.85

72.59

175

Acquisition of two nos. of 120 B.P 04/2009


Acquisition of Two nos. of 3060
DWT
04/2009

12/2011

277.03

277.03

55.41

176

ACQUISITION OF 6 NOS. 60470


DWT LR-I PRODUCT TANKERS 10/2006

03/2011

1658.59

1658.59

1332.47

12/2006

09/2010

411.32

411.32

406.28

10/2008

12/2010

180.53

180.53

40.92

09/2008

11/2010

1799.94

1799.94

214.38

07/2005

09/2010

1174.75

1174.75

371.41

01/2006

12/2010

247.00

247.00

73.73

06/2009

12/2012

3032.00

348.00

7.27

04/2003

05/2011

429.82

2218.01

1234.69

11/2007

11/2010

396.13

396.13

185.56

07/2007

07/2010

405.82

405.82

354.93

11/2007

10/2010

5595.31

3700.00

3260.61

02/2009

02/2012

353.57

353.57

139.59

12/2007

12/2010

227.52

227.52

115.88

SN
170
171

172
173
174

177

178

179
180
181

182
183

184
185
186

187
188

PROJECT NAME
NAGPUR-KONDHALI,NH6(NHAI)
GONDE-VADAPE(THANE), NH-3,
KM.440/000 TO KM.539/500
Shipping & Ports
ACQUISITION OF 4 NOS. OF
115000 DWT CRUDE OIL
CARRIERS
ACQUISITION OF 2 NOS. OF
105000 DWT LR-II TANKERS

ACQUISITION OF TWO NOS.OF


470000 DWT MR TANKERS
Telecommunications
Expn of existing 2G & 3G GSM
N/W by 750k
GSM EQUIPMENT OF 3125K
LINES(2G) AND 625K LINES(3G)
PH-5.1
GSM EXPANSION PH.IV (B)
(BSNL) MAHARASHTRA
CONVERGENT BILLING AND
CRM(MUMBAI)
Multi State
Petroleum
KOCHI-KANJIRKOD
BANGALORE-MANGALORE
PIPELINE PROJECT PHASE-I
INTEGRATED DEV OF G1 and
GS-15 (ONGCL)
SULTANPUR NEEMRANA PIPE
LINE PROJECT (Spurline to
CJPL)
BINA KOTA PIPE LINE PROJECT
VIJAPUR DADRI-BAWANA PIPE
LINE PROJECT
Power
TR. SYSTEM ASSOCIATED
WITH TUTICORIN JV TPS
EASTERN REGION
STRENGTHENING SCHEME-II

ANTICIPATED EXPENDITURE
COST
CUMM

SN
189

190

191
192
193
194

195
196
197

198

199
200

201

202
203
204
205

206
207
208
209

PROJECT NAME
WESTERN REGION
STRENGHTENING SCHEME-IX
EAST-WEST TRANSNISSION
CORRIDOR STRENGTHNING
SCHEME
Railways
PALWAL-BHUTESWAR 3RD
LINE DOUBLING(NCR)(RVNL)
GUNA-ETAWAH(NCR), NL
NEW JALPAIGURI-NEW
BONGAIGAON (GC),NEFR
JIRIBAM TO IMPHAL
(TUPUI)(NL)(NEFR)
NEW MAYNAGURI TO
JOGIGHOPA VIA
CHANGRABANDHA (NL),NEFR
HOSPET-GUNTAKAL(LD),SCR
LALITPUR-SATNA-REWASINGRULI NL, (NCR)
Road Transport & Highways
DHOLPUR - MORENA SECTION
(INCLUDING CHAMBOL
BRIDGE) NH-3
ZIRAKPUR(HARYANA) PARWANOO(HIMACHAL
PRADESH)
GWALIOR-JHANSI, NH-75
VARANASI-MOHANIA (GQ)
KM.317-329 AND KM.0-KM.65
(NH-2)
Telecommunications
ERP implementation in BSNL on
Turnkey basis
PROJ.III OF NIB-II OF
MESSAGING STORAGE
Procurement of 10G (40 chl)
DWDM equipment
Procurement of 2.5G DWDM
equipment
Procurement of 10G 40 CHL (12
chi equipped) DWDM equipment
(SDCA level)
Procurement of STM-1 SDH
equipment
Procurement of STM-16 MADM
equipment
Procurement of STM-16 ADM
equipment

DOA

DOC
ORIGINAL
ANTICIPATED COST

ANTICIPATED EXPENDITURE
COST
CUMM

04/2008

02/2011

230.89

230.89

41.57

06/2006

12/2010

803.70

803.76

612.68

04/2005
04/1985

03/2011
12/2012

240.00
158.77

329.70
540.96

268.75
479.30

11/1998

09/2010

536.85

1010.00

1005.50

04/2003

03/2016

727.56

3123.52

237.63

02/2000
03/1996

03/2014
09/2010

733.00
105.22

1655.80
268.00

520.84
283.49

09/1998

03/2011

925.00

925.00

472.80

12/2003

03/2011

232.45

232.45

123.00

02/2008
12/2003

05/2011
03/2011

295.00
604.00

295.00
604.00

475.80
257.40

04/2000

10/2010

467.93

467.93

453.64

10/2009

11/2010

384.00

384.00

12.64

11/2003

10/2010

250.00

425.51

109.31

08/2006

12/2010

590.10

590.10

0.00

08/2006

12/2010

424.00

424.00

0.00

12/2007

12/2010

545.50

545.50

0.00

02/2007

12/2010

154.03

154.03

0.00

03/2008

12/2010

355.92

355.92

0.00

02/2007

12/2010

477.00

477.00

0.00

SN

210

211
212
213

214
215
216
217
218

219

220

221
222

223

224
225
226

227

228

PROJECT NAME
DOA
Implementation of FTTH, the state
of the art access
network.Procurement of gpon
equipmant
12/2007
Implementation of FTTH, the state
of the art Access
Network,procurement of gepon
equipment
12/2007
Procurement of DXC equipment
02/2008
NIB-II PROJECT RURAL
BROADBAND
12/2007
Orissa
Coal
BHUBANESWARI OCP
12/2007
GOPAL PRASAD OCP
02/2008
TALABIRA OCP
03/2008
BALRAM OCP EXTENSION
12/2007
KULDA OCP (MAHANADI
COALFIELDS LTD.)
01/2005
Mines
SECOND PHASE EXPANSION
OF NALCO
MINE,REFINERY,SMELTER AND
CAPTIVE POWER PLANT
10/2004
Road Transport & Highways
GANJAM-ICCHAPURUM,NH5(NHAI)
04/2000
BALASORE BHADRAK
(REVIVED) KM 136.5 - 199.14 NH5
04/2000
SUNAKHALA-GANJAM (GQ)
KM.338-KM.284 (NH-5)
04/2000
Shipping & Ports
DEEPENING OF CHEENEL AT
PARADIP PORT
12/2005
Steel
SIMULTANEOUS BLOWING OF
BOF CONVERTER OF SMS-II
EXPENSION OF ROURKELA
STEEL PLANT
INSTALLATION OF 700 TPD
OXYGEN PLANT, ROURKELA
Telecommunications
GSM EQUIPMENT OF 700K
LINES(2G) AND 150K LINES(3G)
PH-5.1
Punjab
Railways
ABOHAR- FAZILKA, NR, NL

DOC
ORIGINAL
ANTICIPATED COST

ANTICIPATED EXPENDITURE
COST
CUMM

10/2010

952.88

952.88

0.00

10/2010
11/2010

152.65
229.00

152.65
229.00

0.00
0.00

09/2010

312.86

353.00

234.24

03/2017
03/2015
03/2016
03/2011

490.10
395.87
447.72
172.08

490.10
395.87
447.72
172.08

58.77
24.33
6.04
485.97

03/2012

302.96

302.96

64.16

03/2011

4091.51

4401.76

3856.50

04/2011

263.27

263.27

220.42

12/2010

228.70

228.70

88.78

10/2011

225.00

225.00

0.00

12/2010

154.84

253.36

221.58

01/2008

10/2010

197.66

197.66

128.68

09/2008

03/2013

6133.00

8128.00

2506.34

07/2007

10/2010

302.70

302.70

242.30

11/2007

10/2010

277.34

277.34

293.29

09/2001

09/2010

86.44

209.57

201.79

SN

PROJECT NAME
Road Transport & Highways

229
230

PATHANKOT BHOGPUR NH-1A 12/2003


AMRITSAR-WAGHA BORDER
06/2008
JALANDAR-AMRITSAR,
KM.407/100 TO KM.456/100, NH1
03/2005
PATHANKOT- BHOGPUR, KM.26KM.70, NH-1A
12/2003
KURALI-KIRATPUR, NH-21
03/2005
Telecommunications
GSM equipment of 900000Lines
(2G) PunjabPhase V.2 Telecom
Circle
09/2008
GSM EQUIPMENT OF 390K
LINES(2G) AND 130K LINES(3G)
PH-5.1
02/2008
Rajasthan
Coal
BARSINGSAR MINE 2.10 MTPA
LIGNITE (NLC)
12/2004
BARSINGSAR TPS (2X125MW)
(NLC)
12/2004
Power
WESTERN REGION
STRENGTHENING SCHEME-II
07/2006
Railways
AJMER-PHULERA-RINGUSREWARI (G.C.)(NWR)(RVNL)
04/2005
Road Transport & Highways
CHAMBAL BRIDGE, NH-76 (RJ5)
12/2003
KOTA BYPASS,RJ-4, NH-76
(NHAI)
12/2003
Telecommunications
GSM EQUIPMENT OF 900K
LINES(2G) AND 300K
LINES(3G)PH-5
06/2007
Tamil Nadu
Atomic Energy

231
232
233

234

235

236
237

238

239

240
241

242

243
244

245

DOA

PROTOTYPE FAST BREEDER


REACTOR (BHAVINI, 500 MWE) 09/2003
KUDANKULAM APP (NPCIL)
12/2001
Civil Aviation
CONSTRACTION OF RCC/PRE
STRESSD CONCRETE BRIDGE
ACROSS THE ADYAR AT
CHENNAI AIRPORT(k3)
06/2009

DOC
ORIGINAL
ANTICIPATED COST

ANTICIPATED EXPENDITURE
COST
CUMM

08/2012
10/2010

229.00
205.88

229.00
205.88

47.42
214.90

10/2010

263.00

263.00

420.80

12/2010
03/2011

284.00
309.00

284.00
309.00

299.10
485.20

11/2010

241.49

241.49

89.66

11/2010

373.94

373.94

176.33

09/2010

254.07

1687.78

1687.78

10/2010

1114.18

1626.09

1488.75

03/2011

5221.23

4978.56

2585.00

09/2010

352.00

718.30

616.44

03/2012

275.00

281.31

177.32

12/2010

275.00

250.39

253.20

10/2010

601.49

601.49

474.24

09/2011
12/2011

3492.00
13171.00

5677.00
13171.00

2592.29
13150.00

11/2010

213.35

213.35

153.05

SN

246

247

248

249

250
251
252

253
254
255
256
257

258

259

260
261

262
263

PROJECT NAME
DOA
D/O OF TERMINAL BLDG. AND
PAVEMENT WORKS AT
CHENNAI AIRPORT
01/2008
Coal
TPS-II EXPANSION (1470MW TO
1970MW) (NLC)
10/2004
Petroleum
CONSTRUCTION OF NEW
TERMINAL AT ENNORE
CHENNAI
01/2008
Power
KUNADANKULAM-APP TRANS.
SYSTEM (PGCIL)
05/2005
Road Transport & Highways
IMPROVEMENT OF ACCESS OF
GQ WITHIN CHENNAI
CITY(NHAI) OTHERS
12/2003
SALEM - U / UNDRUPET(BOT 1/TN-06) NH -68
03/2005
THANJAUR-TRICHY,NH67(NHAI)
03/2005
MADURAI -KANIAKUMARI
SECTION (NS-41/TN) NH7,KM.80 TO KM.120
12/2003
CHENNAI BYPASS (NHAI)
OTHERS, NH-45, 4 AND 5
12/2003
TRICHY - KORUR NH-67
03/2005
TRICHY - DINDIGUAL NH-45
03/2005
PONDICHERY - TINDIVANAU NH66
03/2005
Shipping & Ports
SETHUSAMUDRAM SHIP
CHANNEL PROJECT
06/2005
Telecommunications
GSM equipment of 614000Lines
(2G) 150000lines 3(G) Chennai
TD Phase V.1 Telecom Circle
01/2009
GSM equipment of 1900000Lines
(2G) 401700 lines 3(G)Tamil Nadu
Phase V.1 Telecom Circle
GSM EQUIPMENT OF 1006280
LINES IN TAMILNADU PH-4.5
Uttar Pradesh
Power
RIHAND STTP STAGE-III
(2X500MW) (NTPC)
EASTERN REGION
STRENGTHENING SCHEME-I
Railways

DOC
ORIGINAL
ANTICIPATED COST

ANTICIPATED EXPENDITURE
COST
CUMM

12/2010

535.00

535.00

331.80

06/2011

2030.78

2453.57

2025.08

02/2011

224.00

224.00

132.52

03/2012

1779.29

2159.07

1608.50

12/2010

210.00

210.00

653.80

06/2011

941.00

941.00

598.50

12/2010

280.00

280.00

573.00

12/2010

323.36

323.36

189.90

11/2010
06/2011
01/2011

480.00
516.00
576.00

480.00
516.00
576.00

837.90
452.20
340.00

01/2011

285.00

285.00

240.00

11/2010

2427.40

2427.40

819.11

12/2010

315.19

315.19

106.18

01/2009

11/2010

760.20

810.37

720.67

06/2008

09/2010

409.21

483.54

470.24

01/2009

12/2012

6230.81

6230.81

873.00

10/2006

12/2010

975.96

894.26

616.13

SN
264
265
266

267
268
269

270
271
272

273

274
275
276
277

278

279
280
281

282

283

284

DOA

DOC
ORIGINAL
ANTICIPATED COST

04/2006

12/2012

325.00

369.90

88.21

04/2003

12/2010

230.73

399.50

267.19

04/1999

03/2011

108.00

214.09

152.40

12/2003

05/2011

242.00

242.00

328.50

12/2003

06/2013

348.16

348.16

108.90

12/2003

06/2011

227.00

227.00

306.80

12/2003

12/2010

275.00

275.00

284.00

04/2000

04/2011

367.49

367.49

453.68

12/2003

03/2011

451.97

451.97

502.00

12/2003

12/2010

205.00

205.00

312.40

12/2003

10/2010

239.00

239.00

389.90

JHANSI TO LALITPUR, NH-25,26 12/2003


JHANSI TO LALITPUR, NH-26
12/2003
BARA TO ORAI, NH-2, 25
12/2003
GORAKHPUR BYPASS, NH-28,
PHASE-II EAST-WEST
CORRIDOR
12/2003
MEERUT-MUZAFFARNAGAR,
NH-58 PHASE-III, KM.52.25 TO
KM.131.00
03/2005
SITAPUR-LUCKNOW
03/2005
JHANSI BYPASS (UP-3), KM.104KM.91, NH-25
12/2003
GANGA BRIDGE TO RAMDEVI
CROSSING PH.II NH-25, KM.7580.06
12/2003

03/2011
03/2011
03/2011

355.06
276.09
465.00

355.06
276.09
465.00

243.50
184.60
33.65

06/2011

600.24

600.24

524.20

03/2011
03/2011

359.00
322.00

359.00
322.00

570.30
275.40

03/2011

158.06

158.06

157.80

06/2011

155.00

201.66

61.17

10/2010

217.00

217.00

310.30

06/2011

227.00

227.00

0.00

PROJECT NAME
UTRATIA-ZAFRABAD, NR (LINE
DOUBLING)
ALIGARH-GAZIABAD 3RD LINE
DOUBLING (RVNL)
AGRA-ETAWAH VIA FATEBAD
AND BAD (NL) NCR
Road Transport & Highways
KASIA TO GORAKHPUR (NH28)(NHAI)
AGRA-BYPASS(NS-1/UP-1), NH2,3
UP/BIHAR BORDER TO KASIA
(NH-28)(NHAI)
GARHMUKTESHWARMURADABAD (NHAI) OTHERS
KM.93-149.25, NH-24
AGRA-SHIKOHABAD (GQ)
KM.199.66-KM.250.50 (NH-2)
ORAI TO JHANSI (UP-4),NH-25,
KM.170.0 TO KM.104.0
GORAKHPUR-AYODHYA
(LMNHP-4),NH-28, KM.164.00 TO
KM.135.00
GORAKHPUR-AYODHYA
(LMNHP-6),NH-28, KM.251.70 TO
KM.208.00

AYODHYA - LUCKNOW (LMNHPII) KM.93.075 TO KM.45, NH-28 12/2003


GORAKHPUR-AYODHYA
(LMNHP-5),NH-28, KM.208.00 TO
KM.164.00
12/2003

ANTICIPATED EXPENDITURE
COST
CUMM

SN

285
286
287
288

289
290

291

292

293

294

295
296
297
298
299

300

301
302
303

PROJECT NAME
AYODHYA-LUCKNOW (LMNHP3),NH-28, KM.135.000 TO
KM.93.075
ORAI TO JHANSI (UP-5),NH-25,
KM.220.0 TO KM.170.0
FATEHPUR-KHAGA (GQ) KM.38KM.115 (NH-2)
HAPUR-GARHMUKTESWAR
(OTHERS) KM.58-93, NH-24
AYODHYA - LUCKNOW (LMNHPI) NH-28, KM.45 TO KM.8.250,
NH-28
SAGAR BY PASS,KM 187 TO KM
211 , NH-26 (NHAI)
Telecommunications
GSM equipment of 1100000Lines
(2G) UP East Phase V.2
Telecom Circle
GSM EQUIPMENT-480K
LINES(2G) & 220K LINES(3G) IN
UP(W)-PH-V.I
GSM equipment of 200000Lines
(2G) UP(West)Phase V.2
Telecom Circle
GSM equipment of 975000Lines
(2G) 325000 lines 3(G) UP East
Phase V.1 Telecom Circle
Uttaranchal
Power
KOTESHWAR HEP(THDC)
TEHRI PUMPED STORAGE
PLANT(1000MW)
KOTESWAR TRANSMISSION
SYSTEM (PGCIL)
VISHNUGAD PIPALKOTI HYDRO
ELECTRIC PROJECT
LOHARINAG-PAL
HEP(4X150MW)
West Bengal
Civil Aviation

DOA

DOC
ORIGINAL
ANTICIPATED COST

12/2003

12/2010

212.00

212.00

330.60

12/2003

03/2011

340.68

340.68

300.70

04/2000

10/2010

372.40

372.40

406.05

03/2005

06/2011

220.00

220.00

168.80

12/2003

10/2010

193.00

193.00

284.10

12/2003

11/2011

151.30

151.30

130.00

09/2009

11/2010

624.75

624.75

75.25

05/2007

11/2010

335.91

335.91

169.43

10/2008

11/2010

336.84

336.84

22.26

02/2009

11/2010

625.53

625.53

242.56

04/2000

03/2012

1301.56

2398.39

2001.82

07/2006

03/2015

1657.00

3124.76

249.07

06/2006

11/2010

260.34

241.27

151.56

08/2008

03/2015

2491.58

2491.58

122.73

06/2006

12/2012

2895.10

2895.10

552.33

08/2011

1942.51

1942.51

860.83

03/2015

287.18

287.17

0.00

02/2011

2570.44

2570.44

1766.00

08/2012

1061.38

1061.38

799.39

C/O INTEGRATED PASSENGER


TER. BULD. NSCBI AIRPORT
08/2008
Coal
JHANJRA LONGWAL UG PHASE
II
11/2006
Power
Farakka STPP Stage-III
07/2006
TEESTA LOW DAM HEP, STAGEIV (NHPC)
09/2005

ANTICIPATED EXPENDITURE
COST
CUMM

SN
304
305
306

307
308
309

310

311

312
313

DOA

DOC
ORIGINAL
ANTICIPATED COST

03/1984

04/2012

293.97

293.97

313.13

BARDHAMAN-KATWA, ER (GC) 04/2007


PANSPURA-KHARAGPUR 3D
LINE
09/2007
Road Transport & Highways

03/2011

245.15

245.15

59.41

11/2011

252.50

252.50

93.70

SILIGURI TO ISLAMPUR (WB-7)


HALDIA PORT (PORT
CONNECTIVITY) (NH-41)
ASSAM/WB BORDER TO
GAIRKATTA (WB-1)
Steel
REBUILIDING OF COKE OVEN
BATTERY-10
Telecommunications

12/2003

12/2010

225.00

225.00

169.80

04/2000

03/2011

273.00

522.00

333.40

12/2003

12/2010

221.82

221.82

186.30

03/2007

08/2010

416.50

436.54

305.14

10/2010

584.33

584.33

377.08

12/2010

170.23

167.20

127.42

10/2010

208.50

208.50

146.00

PROJECT NAME
Railways
TAMLUK DIGHA

GSM equipment of 849862Lines


(2G) 150138 lines 3(G) West
Bengal Phase V.1 Telecom Circle 02/2008
GSM equipment of 375000Lines
(2G) 75000lines 3(G) Kolkatta
Phase V.1 Telecom Circle
06/2008
KOLKATA TELECOM DISTRICT
PH-4
09/2006

ANTICIPATED EXPENDITURE
COST
CUMM

List of Projects due for commissioning in 2009-10

S.no State/Sector/Proect Title


Andhra Pradesh
PETROLEUM
CLEAN FUELS PROJECT AT VISAKH
1 REFINERY(HPCL)
SINGLE POINT MOORING PROJECT AT
2 VISAKHAPATNAM
RAILWAYS
GOOTY- RENIGUNTA PATCH
3 DOUBLING PH-II (DL) (SCR)
4 RAICHUR-GUNTAKAL(DL)(SCR)
5 RENIGUNTA-GUNTAKAL(RE)
ROAD TRANSPORT & HIGHWAYS
HYDERABAD-BANGALORE SEC.(NS
6 CORR.PH-II)[KM 211-251]
HYDERABAD-BANGALORE SEC.(NS
7 CORR.PH-II)[KM 251-293.4],N
HYDERABAD-BANGALORE SEC.(NS
8 CORR.PH-II)[KM 293.4-336]
HYDERABAD-BANGALORE SEC.(NS
9 CORR.PH-II)[KM 336-376]
HYDERABAD-BANGALORE SEC.(NS
10 CORR.PH-II)[KM 376-418]
HYDERABAD-BANGALORE SEC.(NS
11 CORR.PH-II)[KM 418-463.16]
12 ISLAM NAGAR TO KADTAL
MAHARASHTRA/AP BORDER TO ISLAM
13 NAGAR,(NS-2/BOT/AP-6),NH-7
STEEL
330 TPH BOILER-6 AND AUXILIARY
14 SYSTEM
67.5 MW TG-5 AUX. S'TEM
EMERGENCY POWER REQUIREMENT
15 EXP. UNIT
16 AIR SEPARATION PLANT (ASU-4)
BAILADILA IRON ORE DEPOSIT17 II(B)(NMDC)
18 BILADILLA IRON ORE DEPOSITE-11B
19 POWER PLANT-I
TELECOMMUNICATIONS
GSM EQUIPMENT OF 1500000LINES
(2G) 264700LINES 3(G)ANDHRA
PRADESH PHASE V.1 TELECOM
20 CIRCLE
Assam
PETROLEUM

DOA

Original
Cost

Original
Date
Anticipate Of
d
Commissi
Cost
oning

Anticipate
d Date
Of
Commissi
oning

05/2006

02/2009

643.46

N.A.

N.A.

304.50
136.62
168.34

306.00
221.90
296.20

N.A.
12/2007
04/2003

03/2011
12/2010
N.A.

12/2003

194.80

194.80

08/2009

10/2010

12/2003

208.46

208.46

08/2009

10/2010

12/2003

239.19

239.19

09/2009

10/2010

12/2003

243.38

243.38

09/2008

10/2010

12/2003

205.92

205.92

08/2009

10/2010

12/2003
12/2003

243.64
546.83

243.64
546.83

08/2009
03/2010

10/2010
N.A.

12/2003

360.42

360.42

11/2009

N.A.

07/2007

260.00

319.89

02/2010

08/2010

07/2007
03/2008

230.00
96.00

358.19
161.00

02/2010
06/2010

01/2011
N.A.

01/2003
01/2009
09/2007

295.89
295.89
462.00

607.17
295.89
465.00

N.A.
06/2010
12/2009

N.A.
10/2009
N.A.

01/2009

922.91

922.91

01/2010

12/2010

04/2003

1,635.00

2,508.00

11/2008

643.46

05/2002
04/2003
06/2000

S.no State/Sector/Proect Title


DIESEL HYDRO TREATMENT
21 PROJECT,BRPL DHALIGAON
22 IOR GELEKI (ONGCL)
23 IOR LAKWA - LAKHMANI (ONGCL)
24 IOR, RUDRASAGAR (ONGCL)
25 MSQ IMPROVMENT PROJECT
MSQ UPGRADATION PROJECT AT
26 DIGBOI REFINERY
MSQ UPGRADATION PROJECT AT
27 GUWAHATI REFINERY
ROAD TRANSPORT & HIGHWAYS
BIJNI TO ASSAM WB BORDER (NH28 31.C)(1)(NHAI)
29 BRAHMPUTRA BRIDGE,NH NO-31
30 DAKOBA TO NAGAON (NH-36)(NHAI)
31 DHARAMTUL TO SONAPUR (AS-19)
DHARAMTUL TO SONAPUR,KM 205-183
32 (AS-20)
33 GUWAHATI TO NALBARI (AS-5)
HARANGAJO TO MAIBANG (AS-23),
34 KM.126.450 TO KM.140.700
HARANGAJO TO MAIBANG,KM 164.0835 190.587 NH-54
36 LANKA TO DABOKA (NH-54)(NHAI)
MAIBANG TO LUNDING (AS-24),
37 KM.111.000 TO KM.126.450
MAIBANG TO LUNDING (AS-25),
38 KM.83.400 TO KM.111.000
MAIBANG TO LUNDING (AS-26),
39 KM.60.500 TO KM.83.400, NH-54
MAIBANG TO LUNDING (AS-27),
40 KM.40.000 TO KM.60.500
41 NAGAON BYPASS (NH-37)(NHAI)
42 NAGAON TO DHARAMTUL (AS-2)
43 NALBARI T BIJNI (AS-7)
44 NALBARI TO BIJNI (AS-6)
45 NALBARI TO BIJNI (AS-8)
SILCHAR-UDARBAND (PH.II) HN-54,
46 KM.309 TO KM.275
47 SONAPUR TO GUWAHTI (AS-3)
TELECOMMUNICATIONS
ASSAM TELECOM CIRCLE, PHASE-V.I,
48 2G & 3G
Bihar
PETROLEUM

DOA

Original
Cost

Original
Date
Anticipate Of
d
Commissi
Cost
oning

Anticipate
d Date
Of
Commissi
oning

09/2009
03/2007
03/2007
03/2006
12/2009

12/2010
03/2011
03/2011
03/2011
10/2010

300.00

N.A.

11/2010

372.00

325.00

N.A.

10/2010

12/2003
12/2003
12/2003
12/2003

195.00
217.61
225.00
200.00

195.00
217.61
225.00
200.00

06/2008
04/2010
06/2008
06/2008

12/2011
12/2012
10/2011
12/2011

12/2003
12/2003

160.00
198.16

160.00
198.16

05/2008
04/2008

06/2011
03/2012

12/2003

280.00

280.00

02/2009

03/2011

12/2003
12/2003

212.00
225.00

212.00
225.00

09/2007
06/2008

12/2013
03/2011

12/2003

155.04

155.04

11/2008

12/2013

12/2003

199.81

199.81

04/2009

12/2013

12/2003

167.64

167.64

11/2008

12/2013

12/2003
12/2003
12/2003
12/2003
12/2003
12/2003

200.00
230.00
264.72
208.00
225.00
200.00

200.00
230.00
264.72
208.00
225.00
200.00

04/2009
06/2008
06/2008
04/2008
06/2008
06/2008

04/2011
12/2010
12/2011
12/2011
03/2011
01/2011

12/2003
12/2003

157.47
245.00

154.57
245.00

09/2007
03/2008

03/2011
03/2011

06/2007

336.81

174.36

01/2009

12/2010

06/2006
09/2001
09/2001
09/2001
04/2008

1,431.91
390.09
345.10
113.90
293.60

1,675.72
834.90
429.38
219.22
293.60

04/2008

356.00

04/2008

S.no State/Sector/Proect Title


INTEGRATED SUGAR, ETHANOL,
COGEN POWER PLANT AT SUGAULI
49 AND LAURIYA
MSQ UPGRADATION PROJECT AT
50 BARAUNI REFINERY
POWER

51

52
53
54

55
56
57

58
59
60
61
62
63

64

65

66

67

DOA

Anticipate
d Date
Of
Commissi
oning

06/2009

613.54

727.88

12/2010

12/2010

04/2008

1,492.00

1,492.00

04/2010

11/2010

3,779.46

3,779.46

09/2009

03/2011

470.09

881.19

N.A.

N.A.

114.01
100.00

169.94
214.43

N.A.
N.A.

03/2011
02/2011

291.80

291.80

06/2008

12/2010

305.00

305.00

06/2008

11/2011

332.94

332.94

09/2008

06/2011

12/2003

240.00

240.00

10/2008

03/2011

12/2003

239.00

239.00

07/2005

03/2011

12/2003

275.00

275.00

07/2005

03/2011

12/2003

310.00

310.00

04/2008

N.A.

04/2000
12/2003

205.73
340.00

205.73
340.00

07/2004
06/2008

12/2010
03/2011

04/2007

366.00

366.00

09/2009

10/2010

10/2007

366.00

529.32

10/2008

12/2010

04/1997

151.52

273.00

N.A.

03/2011

03/2005

190.00

190.00

01/2009

12/2010

TRANSMISSION SY. ASSOCIATED


WITH BARH GENER. PROJECT(P.GR.) 12/2005
RAILWAYS
CHHAPRA-SETTING UP OF WHEEL
MANUFACTURING PLANT
03/2005
MANSI-PURNIA (EXTENSION OF MANSISAHARSA) GAN ECR
04/1996
MUZAFFARPUR-SITAMARHI(NL),ECR
03/1997
ROAD TRANSPORT & HIGHWAYS
DARBHANGA-MUZAFFARPUR(KM 30
TO KM 0), NH-57 (NHAI)
12/2003
DARBHANGA-MUZAFFARPUR, NH-57
(NHAI)
12/2003
FORBESGANJ TO SIMRAHI (NH57)(NHAI)
12/2003
KOTWA TO DEWAPUR(10 LMNHP),NH28 PHASE-II, KM.440 TO KM.402
MEHSI TO KOTWA (LMNHP-II), PH.II,
KM.480 TO KM.440, NH-28
MUZZAFFARPUR TO MEHSI (LMNHP12), KM.520 TO 480, NH-28
PURNEA-FORBESGANJ (BR-2) PHASEII, KM.268 TO 230, NH-57
PURNEA-GOYAKOTA SEC.(EW) (NS
AND EW-PH-I) KM.419-KM.447, NH-31
RINGBUNDS TO JHAJHANPUR (BR-6)
TELECOMMUNICATIONS
BIHAR TELECOM CIRCLE PHASE-V.1,
2G &3G
GSM EQUIPMENT OF 945000LINES
(2G) 225000LINES 3(G) BIHAR PHASE
V.1 TELECOM CIRCLE
Chhatisgarh
RAILWAYS
BILASPUR-URKURA (DL)
ROAD TRANSPORT & HIGHWAYS
AURANG-RAIPUR, NH-6, KM.232 TO
KM.281

Original
Cost

Original
Date
Anticipate Of
d
Commissi
Cost
oning

S.no State/Sector/Proect Title


END OF DURG BYPASSCHHATISGARH/MAHARASHTRA
68 BORDER
Delhi
TELECOMMUNICATIONS
CONVERGENT BILLING AND CRM69 MTNL(DELHI)
DELHI EXP. OF 1250K LINES OF 2G/3G
70 GSM LINES

71
72
73

74
75
76

77

78
79
80

81

82

83
84

85

EXP. OF 750K GSM LINES OF 2.5 GSM


AND VALIDATION EQUPT. WCDMA
EXPANSION OF 750K GSM LINES
EXPANSION OF EXISTING 2G&3G GSM
N/W BY 750 KPE NO 9920/05-06
NATIONAL RADIO SPECTRUM
MANAGEMENTAND MONIT. SY. IN WPC
(DOT)
PROVISION OF DATA NETWORK FOR
CWG DELHI
URBAN DEVELOPMENT
DELHI MRTS PHASE-II PROJECT
Gujarat
CIVIL AVIATION
CONSTRUCTION OF NEW
INTERNATIONAL TERMINAL BLDG. AT
SVPI AIRPORT, AHMEDABAD
PETROLEUM
C2-C3 AND LPG RECOVERY FROM
LNG, DAHEJ (ONGC)
CONSTRUCTION OF TANK AND
BLENDING FACILITY AT VADINAR
NORTH TAPTI GAS FIELD DEV.
RESIDUE UPGRADATION AND MS/HSD
QUALITY IMPROVEMENT PROJECT AT
GUJRAT
POWER
WESTERN REGION STREGTHENING
SCHEME-VI
RAILWAYS
BHARUCH-SAMNI-DAHEJ GAUGE
CONVERSIN
PRATAPNAGAR-CHOTA UDAIPUR (GC)
(WR)
RAJKOT-VERAVAL (GC) AND
WANSJALIYA-JETALSAR GC AND
VERAVAL SOMNATH NL(WR)

DOA

Original
Cost

Original
Date
Anticipate Of
d
Commissi
Cost
oning

Anticipate
d Date
Of
Commissi
oning

01/2008

464.00

464.00

01/2011

01/2011

12/2005

249.00

229.41

02/2007

03/2011

02/2007

463.61

463.61

12/2009

03/2010

02/2007
10/2006

741.77
168.33

278.16
278.16

10/2007
12/2008

09/2010
12/2008

10/2008

180.53

180.53

12/2009

09/2010

08/2000

279.97

172.04

12/2004

09/2010

11/2009

488.76

488.76

10/2010

10/2010

08/2005

8,676.00

8,676.00

06/2010

10/2010

02/2007

290.92

290.92

N.A.

N.A.

12/2003

900.92

1,493.49

06/2006

10/2010

02/2009
07/2008

267.00
589.70

267.00
589.70

N.A.
03/2011

08/2011
03/2011

01/2007

5,693.00

5,882.00

N.A.

11/2010

02/2008

340.72

340.72

11/2010

12/2010

09/2005

200.80

200.80

N.A.

12/2010

04/2005

148.61

227.52

03/2008

10/2010

04/1992

112.53

464.50

03/1996

N.A.

S.no State/Sector/Proect Title


86 RAJPIPLA-ANKELASHWAR, WR (GC)
ROAD TRANSPORT & HIGHWAYS

87

88
89

90

91

92

93
94
95
96
97

GAGODHAR-GARAMORE(PK-IV,NH15)
KM 245 TO 281.3 AND 308 TO 254
SHIPPING & PORTS
C/O BERTHING AND ALLIED
FACILITIES OFF TEKRA NEAR TUNA
CONSTRUCTION OF 13 & 14 CARGO
BERTH AT KANDLA

Anticipate
d Date
Of
Commissi
oning
03/2011

12/2003

412.78

479.54

11/2007

12/2010

04/2005

882.00

882.00

02/2011

02/2011

12/2005

702.00

702.00

03/2011

03/2011

01/2002

165.00

165.00

12/2005

01/2011

08/2008

868.00

868.00

08/2009

12/2010

01/2009

488.75

488.75

N.A.

11/2011

11/2007

967.77

571.64

09/2009

03/2010

06/2005

250.66

389.00

06/2008

N.A.

06/2005

806.00

1,060.00

03/2008

10/2010

JHAJJAR HISSAR PIPE LINE PROJECT 11/2007


MSQ UPGRADATION PROJECT AT
PANIPAT REFINERY
01/2008

281.07

281.07

10/2010

10/2010

1,131.00

1,131.00

12/2009

N.A.

12,138.00 14,439.00 09/2009

N.A.

ESTABLISHMENT OF VESSEL TRAFFIC


SERVICES IN GULF OF KUTCH
TELECOMMUNICATIONS
GSM EQUIPMENT OF 1867000LINES
(2G) 383000 LINES 3(G)
GUJARATPHASE V.1 TELECOM
CIRCLE
Haryana
FERTILISERS
THAL AMMONIA REVAMP PROJECT
PETROLEUM
CHAINSA-JHAJJAR PIPE LINE
PROJECT
DADRI- PANIPAT R-LNG SPUR
PIPELINE
EXPANSION OF PANIPAT REFINERY
FROM 12 TO 15 MMTPA

NAPHTHA CRACKER & DOWNSTREAM


POLYMER PROJECT AT PANIPAT
POWER
NORTHERN REGION SYSTEM
99 STRENGHTENING SCHEME-XII
TR. SYSTEM FOR STARTUP POWER
100 TO DVC & MAITHON RB GEN. PROJ.
RAILWAYS
101 REWARI-ROHTAK (NL),NR
ROAD TRANSPORT & HIGHWAYS
DELHI/ HARYANA BORDER TO
102 ROHTAK
TELECOMMUNICATIONS
98

DOA
04/2006

Original
Date
Anticipate Of
Original d
Commissi
Cost
Cost
oning
196.97
196.97 03/2011

04/2006

02/2008

261.55

261.55

11/2010

10/2010

04/2008

290.49

290.49

04/2010

12/2010

01/2004

149.38

456.75

02/2010

02/2011

04/2007

486.00

486.00

05/2010

05/2011

S.no State/Sector/Proect Title


GSM EQUIPMENT OF 216650
103 LINES(2G) PH-5.1
GSM EQUIPMENT OF 4,50,000 LINES
(2G) HARYANA (PHASE V.2) TELECOM
104 CIRCLE
Himachal Pr.
POWER
105 CHAMERA,STAGE-III (NHPC)
EST. OF 400/220 KV GIS POOLING
106 STATION NEAR CHAMERA-II HEP
J&K
POWER
CHUTAK HYDRO-ELECTRIC PROJECT
107 (NHPC)
NIMOO BAZGO HYDROELECTRIC
108 PROJECT (NHPC)
109 SEWA- II H.E.P (NHPC)
110 URI H.E.P STAGE -II (NHPC)
ROAD TRANSPORT & HIGHWAYS
VIJAYAPUR TO PATHANKOT (J AND K)
111 NH-1A KM.16.35 TO KM.50.00
VIJAYAPUR TO PATHANKOT (NS-35/J
112 AND K) NH-1A KM.50 TO KM.80
Jharkhandd
COAL
113 CHURI BENTI UG
RAILWAYS
DEOGHAR-DUMKA NEW BG LINE
114 (DOUBL.)(ER)
115 KODERMA GIRIDH (NL), ECR
116 RANCHI-LOHARDAGA(GC),SER
ROAD TRANSPORT & HIGHWAYS
GORHAR-BARWA ADDA (GQ) KM.320117 KM.398.75 (NH-2)
STEEL
REBUILDING OF COKE OVEN BATTERY
118 NO-6 (BSP)

DOA

Original
Cost

Original
Date
Anticipate Of
d
Commissi
Cost
oning

Anticipate
d Date
Of
Commissi
oning

01/2008

192.48

192.48

03/2009

N.A.

09/2008

216.54

216.54

09/2009

08/2010

08/2005

1,405.63

1,532.52

08/2010

08/2011

09/2007

262.10

262.10

09/2010

12/2010

08/2006

621.26

747.10

02/2011

02/2011

08/2006
09/2003
08/2005

611.01
665.46
1,729.29

723.99
849.98
1,351.88

08/2010
09/2007
11/2009

07/2011
N.A.
02/2011

12/2003

193.09

193.09

03/2008

12/2010

12/2003

166.27

166.27

03/2008

12/2010

06/2007

163.51

163.51

03/2011

03/2011

02/1999
04/1996
04/1997

180.73
371.36
193.78

335.00
371.36
449.83

12/2006
N.A.
06/2004

11/2010
03/2011
03/2011

04/2000

399.75

399.75

03/2005

10/2010

07/2008

172.78

191.00

01/2010

02/2011

892.32

892.32

08/2009

07/2010

328.13

328.13

03/2009

10/2010

UPGRADATION OF BLAST FURNANCE


119 NO.2(BOKARO STEEL PLANT)
10/2007
TELECOMMUNICATIONS
GSM EQUIPMENT OF 799000LINES
(2G) 101000 LINES 3(G)
JHARKHANDPHASE V.1 TELECOM
120 CIRCLE
03/2008
Karnataka
ATOMIC ENERGY

S.no State/Sector/Proect Title


121 KAIGA 3 & 4 UNITS (NPCIL)
POWER
KAIGA 3 AND 4 TRANSMISSION
122 SYSTEM (PGCIL)
RAILWAYS
123 KOTTUR-HARIHAR(NL),(SWR)
124 SHIMOGA-TALAGUPPA (SWR), GC
ROAD TRANSPORT & HIGHWAYS
AP/KARNATKA BORDER-NANDI HILL
CROSSING AND DEVANHALLI TO
125 MEENU KUNLE VILLAGE,NH-7

DOA
05/2001

126 BANGALORE-NEELAMANGLALA NH-4


BANGLORE - HOSKOTE MUDBOGAL
127 SECTION NH-4
ELEVATED HIGHWAY FROM SILK
BOARD JUNCTION TO ELECTRONIC
128 CITY JUNCTION
HARIHAR-CHITRADURGA (GQ) KM.284129 KM.207 (NH-4)
HAVERI-HARIHAR (GQ) KM.340-KM.284
130 (NH-4)
NEELAMANGALAR JUNCTION ON NH-4
131 SMITH NH-48 TO DEVIHALLI
NEW MANGALORE PORT NH-17 AND
132 48
SHIPPING & PORTS
OPERATION, MANAG. & MAINT. OF
MULTI USER-JETTY FOR COAL
133 HANDELLING
TELECOMMUNICATIONS
GSM EQUIPMENT OF 1700000LINES
(2G) 234100 LINES 3(G)KARNATAKA
134 PHASE V.1 TELECOM CIRCLE
Kerala
PETROLEUM
CAPACITY EXP. CUM
135 MODERNISATION PH-II
CAPACITY EXPANSION AND
136 MODERNISATION OF KOCHI REFINERY
ROAD TRANSPORT & HIGHWAYS
COCHIN PORT, NH-47 (PORT
137 CONNECTIVITY) KMS 348 - KMS 358
NH CONNECTIVITY TO ICTT
138 VALLARPADAEU NH - SH
139 THRISSUR TO ANGAMALI (NH-47)

Original
Date
Anticipate Of
Original d
Commissi
Cost
Cost
oning
4,213.00 3,282.00 10/2009

Anticipate
d Date
Of
Commissi
oning
12/2010

12/2007

N.A.

281.20
158.95

N.A.
N.A.

09/2010
02/2011

402.80

402.80

03/2009

N.A.

03/2005

445.00

445.00

07/2010

10/2010

03/2005

565.00

565.00

07/2010

10/2010

03/2005

450.00

450.00

07/2008

N.A.

04/2000

318.00

207.56

08/2004

12/2010

04/2000

241.00

196.65

08/2004

12/2010

03/2005

441.00

441.00

07/2010

03/2011

04/2000

196.50

196.50

06/2008

12/2010

06/2006

230.00

230.00

12/2010

12/2010

10/2008

677.75

677.75

10/2009

12/2010

09/2009

2,591.80

3,941.41

12/2009

10/2010

04/2006

2,591.80

3,941.41

09/2009

09/2010

04/2000

106.00

193.00

08/2006

10/2010

03/2005
12/2003

557.00
312.50

557.00
312.50

02/2010
03/2009

10/2011
12/2010

03/2005

596.45

1,007.16

04/1995
12/1992

65.94
46.00

12/2003

S.no State/Sector/Proect Title


SHIPPING & PORTS
DEV. & OPRATION OF AN
INTERNATIONAL CONTAINER
140 TRANSHIPMENT TERMINAL
RAIL CONNECTIVITY TO ICTT AT
141 VALLARPADAM
TELECOMMUNICATIONS
GSM EQUIPMENT OF 1900000LINES
(2G) 335500LINES 3(G)KERALA PHASE
142 V.1 TELECOM CIRCLE
Madhya pradesh
PETROLEUM
BINA
DESPATCH TERMINAL
143
POWER
144 KORBA STPP STAGE-III
ROAD TRANSPORT & HIGHWAYS
145 GWALIOR BYPSS, NH-75,3
LAKHNAADON TO MP/MH BORDER,KM
146 596.75-653.22 (NS-1/BOT/MP-2),NH7
LAKHNADON TO MP/MH BORDER (NS147 1/BOT/MP-2), NH-7
LALITPUR TO SAGAR KM 132 TO KM
148 187, NH-26 (NHAI)
149 LALITPUR TO SAGAR, NH-26 (NHAI)
SAGAR - RAJMARG CHORAHA,KM 211
150 TO KM 255, NH-26 (NHAI)
SAGAR - RAJMARG CHORAHA,KM 255151 297, NH-26 (NHAI)
TELECOMMUNICATIONS
GSM EQUIPMENT OF 1625000LINES
(2G) 325000 LINES 3(G) MP PHASE V.1
152 TELECOM CIRCLE

DOA

Anticipate
d Date
Of
Commissi
oning

11/2004

2,118.00

2,118.00

11/2004

10/2010

03/2007

245.67

298.17

04/2009

12/2010

01/2009

848.70

848.70

01/2010

11/2010

05/2007

490.71

639.11

12/2009

N.A.

08/2006

2,448.50

2,448.49

02/2010

11/2010

12/2003

300.93

300.93

10/2009

01/2011

12/2003

407.60

407.60

06/2010

12/2010

12/2003

263.17

263.17

09/2009

10/2010

12/2003
12/2003

225.00
198.00

225.00
198.00

10/2008
11/2008

03/2011
03/2011

12/2003

203.43

203.43

10/2008

12/2011

12/2003

206.96

206.96

10/2008

12/2010

11/2009

916.70

916.70

11/2010

11/2010

908.30

908.30

08/2009

09/2010

289.60

289.60

05/2010

05/2010

08/2006

3,195.16

1,800.00

12/2008

03/2011

09/2006
05/2008

2,305.30
706.70

1,339.25
706.70

06/2010
04/2010

03/2011
04/2011

03/2007

900.47

900.47

09/2009

11/2010

GSM EQUIPMENT OF 1625K LINES(2G)


153 & 325K LINES IN M.P PH-V.I
06/2008
Maharashtra
PETROLEUM
BARGE BUMPER-BOAT LANDING154 RISER PROTECTOR PROJECT PH-II
05/2008
155 DEVELOPMENT OF C-SERIES FIELDS
HEERA AND SOUTH HEERA RE156 DEVELOPMENT PROJECT
157 HEERA RECONSTRUCTION
INSTALLATION OF FCCV AT MUMBAI
158 REFINERY

Original
Cost

Original
Date
Anticipate Of
d
Commissi
Cost
oning

S.no State/Sector/Proect Title


LUBE OIL BASE STOCK QUALITY
UPGRADATION AT MUMBAI REFINERY
MNW-NF BRIDGE PROJECT
REFRIGERAPED LPG STORAGE AT
JNPT
SHORT TERM LOW COST MUMBAI
REFINERY
POWER
WESTERN REGION STRENGTHENING
SCHEME-V
RAILWAYS
AMRAVATI-NARKHER NL(CR)
BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP)
CONV.OF 1500V DC TRACTION TO 25
KV AC,WR
MUMBAI URBAN TRANSPORT
PROJECT PHASE-I, MTP
ROAD TRANSPORT & HIGHWAYS
DHULE-PIMPALGAON, NH-3, KM.380
TOKM. 265
GONDE-VADAPE(THANE), NH-3,
KM.440/000 TO KM.539/500
NAGPUR-KONDHALI,NH-6(NHAI)
SHIPPING & PORTS
ACQUISITION OF 2 NOS. OF 105000
DWT LR-II TANKERS
ACQUISITION OF 6 NOS. 60470 DWT
LR-I PRODUCT TANKERS
ACQUISITION OF TWO NOS.OF 470000
DWT MR TANKERS
CONST. & DEV. OF 2 OFFSHORE
CONTAINER BERTHS & TERMINAL
TELECOMMUNICATIONS

DOA

Original
Cost

Original
Date
Anticipate Of
d
Commissi
Cost
oning

Anticipate
d Date
Of
Commissi
oning

10/2006
05/2008

638.90
175.21

1,030.00
175.21

04/2009
03/2009

07/2010
05/2011

06/2008

304.40

304.40

12/2010

12/2010

12/2006

390.00

230.00

01/2010

01/2010

12/2007

477.69

477.69

09/2010

03/2011

06/1994

120.90

284.27

06/1999

03/2011

03/1996

401.81

495.44

03/2004

12/2010

07/1996

273.67

1,160.52

N.A.

12/2012

04/2003

3,125.20

4,174.00

N.A.

12/2010

03/2005

556.00

556.00

03/2009

N.A.

03/2005
03/2005

579.00
168.00

579.00
168.00

04/2009
12/2008

01/2011
12/2010

08/2007

586.58

586.58

11/2010

03/2011

10/2006

1,658.59

1,658.59

07/2010

03/2011

12/2006

411.32

411.32

03/2010

09/2010

11/2007

366.00

1,228.00

12/2010

12/2010

11/2006

364.52

364.52

N.A.

09/2010

01/2006

247.00

247.00

02/2007

12/2010

06/2006

231.38

231.38

10/2007

N.A.

10/2008

180.53

180.53

06/2010

12/2010

GSM EQUIPMENT OF 3125K LINES(2G)


179 AND 625K LINES(3G) PH-5.1
09/2008

1,799.94

1,799.94

09/2009

11/2010

159
160
161
162

163
164
165
166
167

168
169
170

171
172
173
174

COMMISSIONING OF GSM
175 EQUIPMENT OF 650K LINES (PH-IV++)
CONVERGENT BILLING AND
176 CRM(MUMBAI)
EXPANSION OF EXISTING 750K GSM
177 NETWORK PE NO. 9920/05-06
EXPN OF EXISTING 2G & 3G GSM N/W
178 BY 750K

S.no State/Sector/Proect Title


GSM EXPANSION PH.IV (B) (BSNL)
180 MAHARASHTRA
Multi State
PETROLEUM

DOA

Original
Cost

Original
Date
Anticipate Of
d
Commissi
Cost
oning

Anticipate
d Date
Of
Commissi
oning

07/2005

1,174.75

1,174.75

03/2006

09/2010

181 BAWANA NANGAL PIPE LINE PROJECT 07/2011


182 BINA KOTA PIPE LINE PROJECT
07/2007

1,816.07
405.82

1,816.07
405.82

N.A.
12/2009

04/2011
07/2010

11/2007

1,512.00

975.00

04/2011

04/2011

11/2007

4,429.38

4,429.38

10/2011

04/2011

07/2009

238.68

238.68

N.A.

01/2012

01/2010

589.70

755.56

03/2011

03/2011

11/2007

396.13

396.13

10/2009

11/2010

11/2007

5,595.31

3,760.00

11/2009

10/2010

12/2007

227.52

227.52

06/2010

12/2010

06/2006

803.70

803.76

06/2009

12/2010

07/2008

525.14

525.14

07/2011

10/2010

12/2007

417.76

417.76

12/2010

10/2010

04/2008

297.37

297.37

07/2011

12/2010

02/2009

353.57

353.57

07/2010

02/2012

04/2008

230.89

230.89

01/2011

02/2011

12/2006
04/2005
03/1996
09/2001

170.00
200.73
105.22
100.00

255.96
230.03
268.00
586.69

N.A.
N.A.
12/1999
N.A.

03/2011
03/2011
09/2010
12/2010

09/1998

925.00

925.00

05/2008

03/2011

11/1998

536.85

960.48

03/2003

09/2010

COMPRESSOR STATIONS (VIJAYPUR


183 AND JHABUA) PHASE-I & II
DAHEJ-VIJAYPUR PIPE LINE
184 PROJECT(PHASE-II)
KARANPUR MORADABAD-KASHIPURRUDRAPUR PIPELINE PROJECT
185 PHASE-I
NORTH TAPTI GAS FIELD
186 DEVELOPMENT
SULTANPUR NEEMRANA PIPE LINE
187 PROJECT (SPURLINE TO CJPL)
VIJAPUR DADRI-BAWANA PIPE LINE
188 PROJECT
POWER
EASTERN REGION STRENGTHENING
189 SCHEME-II
EAST-WEST TRANSNISSION
190 CORRIDOR STRENGTHNING SCHEME
NORTHERN REGION SYSTEM
191 STRENGHTENING SCHEME-IX
NORTHERN REGION SYSTEM
192 STRENGTHENING-XI
TR. SYSTEM ASSOCIATED WITH
193 CHAMERA III HEP
TR. SYSTEM ASSOCIATED WITH
194 TUTICORIN JV TPS
WESTERN REGION STRENGHTENING
195 SCHEME-IX
RAILWAYS
ALUABARI ROAD SILIGURI JANCTION
196 VIA GALGALIA, NEFR
197 HATHUA-BHATNI (N L) (NER)
198 HOSPET-GUNTAKAL(LD),SCR
199 KATIHAR - JOGBANI (GC)(NEFR)
LALITPUR-SATNA-REWA-SINGRULI
200 NL, (NCR)
NEW JALPAIGURI-NEW BONGAIGAON
201 (GC),NEFR

S.no State/Sector/Proect Title


PALWAL-BHUTESWAR 3RD LINE
202 DOUBLING(NCR)(RVNL)
203 VIRAMGAM-BHILDI(WR),GC
ROAD TRANSPORT & HIGHWAYS
DHOLPUR - MORENA SECTION
204 (INCLUDING CHAMBOL BRIDGE) NH-3
205 GWALIOR-JHANSI, NH-75
VARANASI-MOHANIA (GQ) KM.317-329
206 AND KM.0-KM.65 (NH-2)
WAINGANGA BRIDGE -CHHATISGARH207 MAHARASHTRA
ZIRAKPUR(HARYANA) 208 PARWANOO(HIMACHAL PRADESH)
TELECOMMUNICATIONS
ERP IMPLEMENTATION IN BSNL ON
209 TURNKEY BASIS
EXECUTION OF TELECOM NETWORK
210 REQUIREMENT OF DEFENCE FORCES
IMPLEMENTATION OF FTTH, THE
STATE OF THE ART ACCESS
NETWORK,PROCUREMENT OF GEPON
211 EQUIPMENT
IMPLEMENTATION OF FTTH, THE
STATE OF THE ART ACCESS
NETWORK.PROCUREMENT OF GPON
212 EQUIPMANT
213 NIB-II PROJECT RURAL BROADBAND
PROCUREMENT OF 10G (40 CHL)
214 DWDM EQUIPMENT
PROCUREMENT OF 10G 40 CHL (12
CHI EQUIPPED) DWDM EQUIPMENT
215 (SDCA LEVEL)
PROCUREMENT OF 2.5G DWDM
216 EQUIPMENT
217 PROCUREMENT OF 24 F OF CABLE.
218 PROCUREMENT OF DXC EQUIPMENT
PROCUREMENT OF STM-1 SDH
219 EQUIPMENT
PROCUREMENT OF STM-16 ADM
220 EQUIPMENT
PROCUREMENT OF STM-16 MADM
221 EQUIPMENT
PROJ.III OF NIB-II OF MESSAGING
222 STORAGE
Orissa

DOA

Original
Cost

Original
Date
Anticipate Of
d
Commissi
Cost
oning

Anticipate
d Date
Of
Commissi
oning

04/2005
04/1990

240.00
155.66

330.00
119.75

03/2009
N.A.

03/2011
03/2011

12/2003
12/2003

232.45
604.00

232.45
604.00

09/2010
12/2009

03/2011
03/2011

04/2000

467.93

467.93

03/2005

10/2010

03/2008

424.00

424.00

09/2010

09/2010

02/2008

295.00

295.00

08/2010

05/2011

10/2009

384.00

384.00

10/2010

11/2010

05/2006

1,077.00

1,077.00

03/2009

N.A.

12/2007

152.65

152.65

03/2010

10/2010

12/2007
12/2007

952.88
312.86

952.88
312.86

03/2010
02/2008

10/2010
09/2010

08/2006

590.10

590.10

03/2009

12/2010

12/2007

545.50

545.50

03/2010

12/2010

08/2006
02/2008

424.00
199.00

424.00
136.00

03/2009
03/2010

12/2010
11/2010

02/2008

229.00

229.00

03/2010

11/2010

02/2007

154.03

154.03

03/2010

12/2010

02/2007

477.00

477.00

03/2010

12/2010

03/2008

355.92

355.92

03/2010

12/2010

11/2003

250.00

300.00

12/2005

10/2010

S.no State/Sector/Proect Title


DOA
COAL
223 BALRAM OCP EXTENSION
12/2007
MINES
SECOND PHASE EXPANSION OF
NALCO MINE,REFINERY,SMELTER AND
224 CAPTIVE POWER PLANT
10/2004
RAILWAYS
KHURDA ROAD - BARANG 3RD LINE
225 (DL) (ECOR)
04/2000
226 KHURDA ROAD-BOLANGIR(NL)ECOR
04/1994
227 RAJATGARH-BARANG(LD),ECOR
04/1999
228 SUKINDA ROAD - ANGUL (NL)(ECOR)
04/1998
TALCHER-BIMALAGARH(NL)(ECOR)
229
04/2005
ROAD TRANSPORT & HIGHWAYS
BALASORE BHADRAK (REVIVED) KM
230 136.5 - 199.14 NH-5
04/2000
231 GANJAM-ICCHAPURUM,NH-5(NHAI)
04/2000
SHIPPING & PORTS
DEEPENING OF CHEENEL AT PARADIP
232 PORT
12/2005
STEEL
INSTALLATION OF 700 TPD OXYGEN
233 PLANT, ROURKELA
07/2007
REBUILDING OF COKE OVEN BATTRY
234 NO.-4 STEEL PLANT(SAIL)
05/2007
SIMULTANEOUS BLOWING OF BOF
235 CONVERTER OF SMS-II
01/2008
TELECOMMUNICATIONS
GSM EQUIPMENT OF 700K LINES(2G)
236 AND 150K LINES(3G) PH-5.1
Punjab
PETROLEUM
GURU GOVIND SINGH REFINARY
237 PRODUCTS EVACUATION PROJECT
RAILWAYS
238 ABOHAR- FAZILKA, NR, NL
ROAD TRANSPORT & HIGHWAYS
239 AMRITSAR-WAGHA BORDER
JALANDAR-AMRITSAR, KM.407/100 TO
240 KM.456/100, NH-1
241 KURALI-KIRATPUR, NH-21
PATHANKOT- BHOGPUR, KM.26-KM.70,
242 NH-1A
TELECOMMUNICATIONS

Original
Cost

Original
Date
Anticipate Of
d
Commissi
Cost
oning

Anticipate
d Date
Of
Commissi
oning

172.08

172.08

03/2009

03/2011

4,091.51

4,091.51

12/2008

03/2011

133.41
355.38
166.16
183.23
726.96

207.00
1,000.00
240.00
638.00
810.78

N.A.
N.A.
N.A.
02/2015
N.A.

12/2010
03/2011
12/2010
11/2010
03/2012

228.70
263.27

228.70
263.27

02/2004
02/2004

12/2010
04/2011

154.84

253.36

06/2007

12/2010

302.70

302.70

06/2009

10/2010

248.94

248.94

08/2009

08/2009

197.66

197.66

11/2009

10/2010

11/2007

277.34

277.34

03/2009

10/2010

01/2009

605.40

605.40

12/2010

12/2010

09/2001

86.44

205.00

03/2009

09/2010

06/2008

205.88

205.88

06/2010

10/2010

03/2005
03/2005

263.00
309.00

263.00
309.00

02/2009
06/2010

10/2010
03/2011

12/2003

284.00

284.00

05/2008

12/2010

S.no State/Sector/Proect Title

243

244

245
246

247

248
249
250
251

252
253

254

255
256

257

258

259

GSM EQUIPMENT OF 390K LINES(2G)


AND 130K LINES(3G) PH-5.1
GSM EQUIPMENT OF 900000LINES
(2G) PUNJABPHASE V.2 TELECOM
CIRCLE
Rajasthan
COAL
BARSINGSAR MINE 2.10 MTPA LIGNITE
(NLC)
BARSINGSAR TPS (2X125MW) (NLC)
POWER
WESTERN REGION STRENGTHENING
SCHEME-II
RAILWAYS
AJMER-PHULERA-RINGUS-REWARI
(G.C.)(NWR)(RVNL)
SRIGANGANAGAR-SARUPSAR (GC),
NWR
ROAD TRANSPORT & HIGHWAYS
CHAMBAL BRIDGE, NH-76 (RJ-5)
KOTA BYPASS,RJ-4, NH-76 (NHAI)
TELECOMMUNICATIONS
GSM EQUIPMENT OF 2,00,000LINES
(2G) RAJASTHAN ( PHASE V.2)
TELECOM CIRCLE
GSM EQUIPMENT OF 900K LINES(2G)
AND 300K LINES(3G)PH-5
Tamil Nadu
ATOMIC ENERGY
KUDANKULAM APP (NPCIL)
CIVIL AVIATION
CONSTRACTION OF RCC/PRE
STRESSD CONCRETE BRIDGE
ACROSS THE ADYAR AT CHENNAI
AIRPORT(K3)
D/O KAMARAJ DOMESTIC TER-PH-II &
EXP. ANNA INT. TER BLDG(K1)
D/O OF TERMINAL BLDG. AND
PAVEMENT WORKS AT CHENNAI
AIRPORT
EXTENSION OF SECONDARY
RUNWAY, CONSTRUCTION OF TAXI
TRACKS AT CHENNAI AIRPORT(K2)
PETROLEUM
CONSTRUCTION OF NEW TERMINAL
AT ENNORE CHENNAI

DOA

Original
Cost

Original
Date
Anticipate Of
d
Commissi
Cost
oning

Anticipate
d Date
Of
Commissi
oning

02/2008

373.94

373.94

12/2008

11/2010

09/2008

241.49

241.49

09/2009

11/2010

12/2004
12/2004

254.07
1,114.18

254.07
1,626.09

06/2009
06/2009

09/2010
10/2010

07/2006

5,221.23

5,221.23

07/2010

03/2011

04/2005

352.00

716.60

03/2008

09/2010

04/1997

143.92

168.80

N.A.

03/2011

12/2003
12/2003

275.00
275.00

281.31
250.39

02/2010
10/2008

03/2012
12/2010

09/2009

577.35

577.35

09/2010

09/2010

06/2007

601.49

601.49

12/2008

10/2010

13,171.00 13,171.00 12/2008

12/2011

12/2001

06/2009

213.35

213.35

09/2010

11/2010

08/2008

1,273.00

1,273.00

01/2011

01/2011

01/2008

535.00

535.00

06/2010

12/2010

08/2008

230.00

230.00

01/2011

01/2011

01/2008

224.00

224.00

12/2010

02/2011

S.no State/Sector/Proect Title


DOA
RAILWAYS
TAHANJAVUR-VILLUPURAM GAUGE
260 CONVERSION (G.C)(SR)
10/2001
ROAD TRANSPORT & HIGHWAYS
CHENNAI BYPASS (NHAI) OTHERS, NH261 45, 4 AND 5
12/2003

Anticipate
d Date
Of
Commissi
oning

223.00

356.90

N.A.

09/2010

480.00

480.00

11/2007

11/2010

210.00

210.00

04/2007

12/2010

323.36

323.36

03/2008

12/2010

507.49

507.49

03/2008

N.A.

629.00
320.00
285.00

629.00
320.00
285.00

11/2010
05/2009
07/2010

11/2010
N.A.
01/2011

941.00
280.00

941.00
280.00

01/2011
06/2009

06/2011
12/2010

263.00
576.00
516.00

263.00
576.00
516.00

08/2008
07/2010
07/2010

N.A.
01/2011
06/2011

261.00

261.00

08/2008

N.A.

2,427.40

2,427.40

10/2008

11/2010

01/2008

1,902.00

1,902.00

06/2011

10/2010

06/2008

409.21

409.21

12/2008

09/2010

01/2009

760.20

810.37

01/2010

11/2010

01/2009

315.19

315.19

01/2010

12/2010

07/2009

199.57

199.57

N.A.

01/2011

IMPROVEMENT OF ACCESS OF GQ
262 WITHIN CHENNAI CITY(NHAI) OTHERS 12/2003
MADURAI -KANIAKUMARI SECTION (NS263 41/TN) NH-7,KM.80 TO KM.120
12/2003
MADURAI -KANNIAKUMARI SEC. (NS264 42/TN) NH-7, KM.120 TO KM.160
12/2003
MADURAI-ARUPKOTTAI-TUTICORIN,
265 KM.138.8 TO KM.264.5, NH-45 B
03/2005
266 PADALUR-TRICHY, NH-45
03/2005
267 PONDICHERY - TINDIVANAU NH-66
03/2005
SALEM - U / UNDRUPET(BOT -1/TN-06)
268 NH -68
03/2005
269 THANJAUR-TRICHY,NH-67(NHAI)
03/2005
TOVARAMKURCHI-MADURAI,NH45B
270 (NHAI)
04/2000
271 TRICHY - DINDIGUAL NH-45
03/2005
TRICHY
KORUR
NH-67
272
03/2005
TRICHY BYPASS END TO
273 TOVARAMKURCHI (NH-45B)(NHAI)
03/2005
SHIPPING & PORTS
SETHUSAMUDRAM SHIP CHANNEL
274 PROJECT
06/2005
STEEL
275 EXPANSION OF SALEM STEEL PLANT
TELECOMMUNICATIONS
GSM EQUIPMENT OF 1006280 LINES IN
276 TAMILNADU PH-4.5
GSM EQUIPMENT OF 1900000LINES
(2G) 401700 LINES 3(G)TAMIL NADU
277 PHASE V.1 TELECOM CIRCLE
GSM EQUIPMENT OF 614000LINES
(2G) 150000LINES 3(G) CHENNAI TD
278 PHASE V.1 TELECOM CIRCLE
Uttar Pradesh
PETROLEUM
CAPACITY AUGMENTATION OF AGRA&
279 FEROZABAD REGION

Original
Cost

Original
Date
Anticipate Of
d
Commissi
Cost
oning

S.no State/Sector/Proect Title

280

281
282
283

284
285

286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301

DOA

INST. OF FCC GASOLINE DESULPHUN


UNIT AT MATHURA REFINERY
01/2008
POWER
EASTERN REGION STRENGTHENING
SCHEME-I
10/2006
NATIONAL CAPITAL THERMAL POWER
PROJECT STAGE-II
10/2006
NORTHERN REGION SYSTEM
STRENGTHENING SCHEME-X
12/2007
RAILWAYS
AGRA-ETAWAH VIA FATEBAD AND
BAD (NL) NCR
04/1999
ALIGARH-GAZIABAD 3RD LINE
DOUBLING (RVNL)
04/2003
ELECTRIFICATION OF KHURJAMEERUT-SAHARANPUR & G'BADMEERUT
02/2008
ELECTRIFICATION OF MORADABADROZA
03/2006
ROAD TRANSPORT & HIGHWAYS
AGRA-BYPASS(NS-1/UP-1), NH-2,3
12/2003
AGRA-SHIKOHABAD (GQ) KM.199.66KM.250.50 (NH-2)
04/2000
ALLAHABAD BYPASS (KM.158-KM.198)
GQ, NH-2
04/2000
ALLAHABAD BYPASS (KM.198KM.242.708) GQ, NH-2
04/2000
AYODHYA - LUCKNOW (LMNHP-I) NH28, KM.45 TO KM.8.250, NH-28
12/2003
AYODHYA - LUCKNOW (LMNHP-II)
KM.93.075 TO KM.45, NH-28
12/2003
AYODHYA-LUCKNOW (LMNHP-3),NH28, KM.135.000 TO KM.93.075
12/2003
BARA TO ORAI, NH-2, 25
12/2003
FATEHPUR-KHAGA (GQ) KM.38-KM.115
(NH-2)
04/2000
GARHMUKTESHWAR-MURADABAD
(NHAI) OTHERS KM.93-149.25, NH-24
12/2003
GORAKHPUR BYPASS, NH-28, PHASEII EAST-WEST CORRIDOR
12/2003
GORAKHPUR-AYODHYA (LMNHP-4),NH28, KM.164.00 TO KM.135.00
12/2003
GORAKHPUR-AYODHYA (LMNHP-5),NH28, KM.208.00 TO KM.164.00
12/2003
GORAKHPUR-AYODHYA (LMNHP-6),NH28, KM.251.70 TO KM.208.00
12/2003

Original
Cost

Original
Date
Anticipate Of
d
Commissi
Cost
oning

Anticipate
d Date
Of
Commissi
oning

348.00

348.00

12/2009

N.A.

975.96

975.96

10/2009

12/2010

5,135.33

5,135.33

10/2010

10/2010

408.36

408.36

12/2010

10/2010

108.00

214.09

12/2009

03/2011

230.73

399.50

03/2009

12/2010

171.10

171.10

03/2011

03/2011

258.35

258.35

03/2011

03/2011

348.16

348.16

09/2007

06/2013

367.49

367.49

03/2005

04/2011

440.93

440.93

12/2006

N.A.

534.39

534.39

05/2007

N.A.

193.00

193.00

10/2008

10/2010

217.00

217.00

10/2008

10/2010

212.00
465.00

212.00
465.00

10/2008
04/2009

12/2010
03/2011

372.40

372.40

07/2004

10/2010

275.00

275.00

09/2007

12/2010

600.24

600.24

10/2009

06/2011

205.00

205.00

10/2008

12/2010

227.00

227.00

10/2008

06/2011

239.00

239.00

10/2008

10/2010

S.no State/Sector/Proect Title


JHANSI BYPASS (UP-3), KM.104-KM.91,
302 NH-25
303 JHANSI TO LALITPUR, NH-25,26
304 JHANSI TO LALITPUR, NH-26
305 KASIA TO GORAKHPUR (NH-28)(NHAI)
MEERUT-MUZAFFARNAGAR, NH-58
306 PHASE-III, KM.52.25 TO KM.131.00
ORAI TO JHANSI (UP-4),NH-25,
307 KM.170.0 TO KM.104.0
ORAI TO JHANSI (UP-5),NH-25,
308 KM.220.0 TO KM.170.0
SAGAR BY PASS,KM 187 TO KM 211 ,
309 NH-26 (NHAI)
310 SITAPUR-LUCKNOW
UP/BIHAR BORDER TO KASIA (NH311 28)(NHAI)
TELECOMMUNICATIONS
GSM EQUIPMENT OF 1100000LINES
(2G) UP EAST PHASE V.2 TELECOM
312 CIRCLE
GSM EQUIPMENT OF 200000LINES
(2G) UP(WEST)PHASE V.2 TELECOM
313 CIRCLE
GSM EQUIPMENT OF 975000LINES
(2G) 325000 LINES 3(G) UP EAST
314 PHASE V.1 TELECOM CIRCLE
GSM EQUIPMENT-480K LINES(2G) &
315 220K LINES(3G) IN UP(W)-PH-V.I
Uttaranchal
POWER
316 KOTESHWAR HEP(THDC)
KOTESWAR TRANSMISSION SYSTEM
317 (PGCIL)
West Bengal
POWER
318 FARAKKA STPP STAGE-III
TESSTA LOW DAM - III
HYDROELECTRIC POWER PROJECT
319 (NHPC)
RAILWAYS
320 BARDHAMAN-KATWA, ER (GC)
TARAKESWAR - BISHNUPUR NEW BG
321 LINE (NL), ER
TOLLYGANJ-GARIA WITH EXTENSION
TO DUM DUM-NAOPARA AND
322 NOAPARA-NSCB AIRPORT(MTP)

DOA

Original
Cost

Original
Date
Anticipate Of
d
Commissi
Cost
oning

Anticipate
d Date
Of
Commissi
oning

12/2003
12/2003
12/2003

158.06
355.06
276.09

158.06
355.06
276.09

08/2005
09/2009
09/2009

03/2011
03/2011
03/2011

12/2003

242.00

242.00

12/2008

05/2011

03/2005

359.00

359.00

03/2009

03/2011

12/2003

451.97

451.97

04/2008

03/2011

12/2003

340.68

340.68

03/2008

03/2011

12/2003
03/2005

151.30
322.00

151.30
322.00

10/2008
06/2009

11/2011
03/2011

12/2003

227.00

227.00

12/2008

06/2011

09/2009

624.75

624.75

09/2010

11/2010

10/2008

336.84

336.84

10/2009

11/2010

02/2009

625.53

625.53

02/2010

11/2010

05/2007

335.91

335.91

03/2009

11/2010

04/2000

1,301.56

1,301.56

04/2005

03/2012

06/2006

260.34

266.61

06/2008

11/2010

07/2006

2,570.44

2,570.44

08/2010

02/2011

10/2003

768.92

1,073.29

03/2007

12/2009

04/2007

245.15

245.15

12/2010

03/2011

04/2000

157.96

567.00

N.A.

N.A.

03/2000

907.69

1,032.76

12/2006

N.A.

S.no State/Sector/Proect Title


ROAD TRANSPORT & HIGHWAYS
ASSAM/WB BORDER TO GAIRKATTA
323 (WB-1)
HALDIA PORT (PORT CONNECTIVITY)
324 (NH-41)
325 SILIGURI TO ISLAMPUR (WB-7)
STEEL
REBUILIDING OF COKE OVEN
326 BATTERY-10
TELECOMMUNICATIONS
GSM EQUIPMENT OF 375000LINES
(2G) 75000LINES 3(G) KOLKATTA
327 PHASE V.1 TELECOM CIRCLE

DOA

Original
Cost

Original
Date
Anticipate Of
d
Commissi
Cost
oning

Anticipate
d Date
Of
Commissi
oning

12/2003

221.82

221.82

11/2008

12/2010

04/2000
12/2003

273.00
225.00

522.00
225.00

03/2005
07/2008

03/2011
12/2010

03/2007

416.50

436.59

09/2009

08/2010

06/2008

170.23

167.20

06/2009

12/2010

GSM EQUIPMENT OF 849862LINES


(2G) 150138 LINES 3(G) WEST BENGAL
328 PHASE V.1 TELECOM CIRCLE
02/2008
329 KOLKATA TELECOM DISTRICT PH-4
09/2006

584.33
208.50

584.33
208.50

02/2009
09/2008

10/2010
10/2010

You might also like