You are on page 1of 1

RHP.

qxd:Layout 1 1/19/09 1:15 PM Page 220

RHP MECHANICAL SYSTEMS – WESTERN DAIRIES

RHP Mechanical completed the Western Dairies project in


Yerington, Nev., on a fast-tracked schedule of 16 months.

RHP Sets The Standard


RHP Mechanical Systems says its innovative design for Western Dairies – the first milk processing plant
of its kind in the United States – will be a template for similar facilities across the country.

S oftware, such as 3-D and Auto/CAD technologies


allowed RHP Mechanical to successfully complete its
portion of the new $78 million Western Dairies facility
in Yerington, Nev., says Guy Lutz, senior project manager and
lead estimator. The 86,000-square-foot facility was completed
which took more than 18,000 hours in 16 months. The
company also constructed all conveyors and specialty
stainless supports.
The facility contains more than 6.5 miles of piping,
which allows it to process 860,000 gallons of milk per
on a fast-track schedule of 16 months. month. It also has the capability to process more than one
To accomplish a project that was the first of its kind, RHP kind of milk at a time using 10 percent less labor than tra-
Mechanical Systems completed coordination, fitting and ditional milk processing plants.
design of internal mechanical systems requiring extensive Due to its inventive design, the piping layout and coordi-
use of 3-D computer-aided technology. The design process nation completed by RHP for Western Dairies is now
took more than 1,370 hours of work by RHP in order to being used as a template for other milk processing plants
interface with all mechanical and processing equipment. across the country.
Lutz says the company has used this technology on other
projects, but nothing of this magnitude. Overcoming Challenges
RHP Mechanical Systems – “The biggest thing was to make sure every- RHP encountered several challenges during construction.
Western Dairies thing fit,” he says. “We wanted to have clash For example, work had to be completed in 16 months, an
www.rhpinc.net
Total project cost: $78 million protection and, if needed, we’d find an accelerated schedule because of the scope and magnitude
Location: Yerington, Nev. alternative way of running things.” of the project. The company had to work six 10-hour days
Scope: Milk processing plant RHP’s scope of the project was to per week for the duration of that time. “Due to the commit-
Guy Lutz, senior project man-
ager: “The biggest thing was to inventory, set and install all the mechani- ment with the supermarkets, contractors had to get the
make sure everything fit.” cal and processing equipment on-site, project done by a certain date,” Lutz says.

220 ■ WWW.CONSTRUCTION-TODAY.COM ■ FEBRUARY 2009

You might also like