You are on page 1of 17

SHA TIN HEIGHTS TUNNEL : A REVIEW OF FACTORS AFFECTING EXCAVATION CYCLE TIMES

J. K. Murfitt(1), Cameron Chin(2), Billy Siu(3), C. H. Chan(4) Abstract Excavation progress for the Sha Tin Heights Tunnel was constrained by a combination of adjacent sensitive features, noise regulations, access restrictions, weather, construction equipment, blasting technology and programme. This Paper presents and discusses how the blast, mucking out, temporary support and excavation cycles were monitored during the course of the Works. Various proposals, both put forward and implemented, to minimise cycle times and increase excavation advance rates within the framework of the external constraints are also discussed.

INTRODUCTION The Sha Tin Heights Tunnel (SHT) is a twin bored 19m span and 11m high road tunnel of around 1km in length, excavated mainly through coarse-grained granite, with occasional basalt dykes. One portal drive (south portal, southbound tunnel) was excavated through approximately 50m of soft and mixed ground before encountering rock with a design 6m cover over the tunnel crown, with the remaining three portals commencing in Grade III rock. A number of possible faults along the proposed route were identified at tender stage. One of these was observed during the tunnel excavation. Excavation progress in any drill and blast tunnel is dependent on a number of interrelated factors, some of which have a greater impact on progress than the others. Some of these factors are variable (e.g. charge weight) and some fixed (e.g. the surrounding geology), but all of the factors combine to define the eventual rates of advance. Measures were put into place at the SHT to review some of these factors as works progressed, with those identified as having the greatest impact, and those with the greatest scope for improvement of progress being afforded the closest attention during construction. Assuming that the size of the excavation, the surrounding geology and topography remains fixed, those factors identified as having the greatest scope for review on the SHT can be separated into the following broad categories : i. ii. Working cycle times. This includes the number and type of elements in an excavation cycle and the resources required for minimising the time required for each cycle. Allowable working hours using machinery, to comply with statutory noise regulations. Working hours were agreed in consultation with the Environmental Protection Department (EPD). Efficiency of blasting. This category includes blasting technology, use of bulk emulsion versus cartridge emulsion charges, possible use of electronic detonators to cover larger face area with lower vibrations and more efficient blast patterns, blast vibration attenuation laws, and burden.

iii.

_____________________________________________________________________________________________ 1 2

Resident Engineer (Geotechnical), Maunsell Consultants Asia Ltd. Blasting Engineer, China State-China Railways Joint Venture. 3 Assistant Resident Engineer (Geotechnical), Maunsell Consultants Asia Ltd. 4 Project Engineer, Civil Engineering and Development Department, HKSAR.

iv.

Vibration limits on sensitive receivers. This includes the applicability and accuracy of both the parameters, and the approaches themselves, used to derive Peak Particle Velocity limits (PPVs) for sensitive receivers, such as slopes. A study of PPV limits for one particular slope is discussed.

Within each of the above categories there are in turn various approaches and methods of achieving the greatest efficiency in performing the works, in terms of progress. This Paper discusses examples from within each of the above four categories and presents monitoring results of working cycles and progress achieved. SITE CONSTRAINTS FOR TUNNEL EXCAVATION Site constraints were identified prior to tunnel commencement and categorized to determine their impact on the excavation. The following is a broad outline of site constraints on the SHT Project : Site Constraint 1 : Vibration Limits of Adjacent Sensitive Receivers When conducting any excavation works by blasting in Hong Kong, particularly in urban areas, most of the site constraints arise due to sensitive receivers adjacent to the blast zone. Flyrock, vibration, airblast, noise and fumes during blasting may individually, or in combination, cause adverse effects to public safety, and may cause human discomfort, cracking or in severe cases, structural distress. Vibration limits for blasting currently set by commercial and residential building owners and by utility companies in Hong Kong are normally stated as single peak particle velocity (PPV) vibration levels, with no frequency component. In the case of Water Services Department (WSD) structures, both vibration and amplitude limits are defined by the WSD. The main sensitive receivers for blast vibrations are shown in Fig. 1 below. The sensitive receivers that are shown limited the allowable charge weights per delay that were able to be used in the excavation cycle, in turn limiting the advance for each blast. Most of the vibration limits of these features were fixed by owners and utility companies, however, as the slopes were assessed separately, there was scope for review of the PPV limits by revisiting the models used in the initial assessments. A more detailed discussion of the reassessment of these slopes is presented below. Slopes along Tai Po Road presented one of the major controls over allowable charge weights per delay. The crown of two approximately 3 to 3.2m span WSD water tunnels were located less than 18m below the SHT invert level. In accordance with WSDs requirements, a zone within 60m plan distance of each tunnel was designated as a WSD Special Protection Zone. These zones reduced charge weights to a minimum approaching the WSD Tunnels, due to concerns over vibration (causing rockfalls or leakage) and tunnel deformation. Figure 2 below plots charge weight and pull length along the northbound tunnel alignment and shows a marked drop in allowable charge weights around the WSD Tunnels. Pull length is the length the face advances per round i.e. face advance after each blast.

Site Constraints / Site Geology


Fault Zone
Luk Hop Village Shell Petrol Station CLP Pylon

Woodcrest Hill

Keng Hau Road Residential WSD TUNNELS and Water Treatment Plant

Garden Villa Slopes and Utilities along Tai Po Road

Figure 1 : Excavation Progress Constraints


Charge Weight & Pull Length vs Chainage (All Full Face, Pilot and Enlargement Blasts for North Bound Tunnel)
6 6

5 Charge Weight (kg/delay)

0 1100

1200

1300

1400

1500

1600 Chainage

1700

1800

1900

2000

0 2100

Breakthrough of Full Face and Pilot Tunnel WSD Tunnel 2 T1N - 23% Pilot - Charge Weight T1S - 58% Enlargement - Charge Weight T1S - 77% Enlargement - Charge Weight T1N - 42% Pilot - Pull Length T1N - 77% Enlargement - Pull Length T1S- FF- Pull Length

WSD Tunnel 1 T1S - FF- Charge Weight T1N - 42% Pilot - Charge Weight T1N - 77% Enlargement - Charge Weight T1N - 23% Pilot - Pull Length T1S - 58% Enlargement - Pull Length T1S - 77% Enlargement - Pull Length

Figure 2 : Variation of Charge Weight and Pull Length along Tunnel Alignment Site Constraint 2 : Noise No blasting was conducted (nor permitted) at night time as the noise generated by the detonation of explosives may have caused discomfort to the residents of the properties in close proximity to the blasting zone (e.g. Garden Villa and the Shatin Heights residential complex), and had the potential to panic road users.

Pull Length (m)

One of the major activities in the blasting cycle, mucking out, is also the most time consuming one. Working hours for mucking out were limited by the Noise Control Ordinance (NCO). As such, no mucking out was permitted after 19:00hrs on normal working days. Site Constraint 3 : Temporary Access Roads (TAR) Tunnel spoil material removed after blasting was either transported off-site immediately or stored in the temporary stockpile near the portal areas prior to the removal off site via the temporary access roads (TARs) at the South Portal (TAR1) and North Portal (TAR3). Owing to the high traffic flow of Tai Po Road, which was the designated exit point of both TARs, a large number of dump trucks were used during the excavation cycle, with truck movements along TAR1 reaching a peak of 40 trucks/hr. The high traffic flows along Tai Po Road placed restrictions on the maximum combined numbers of trucks able to use TAR1 and TAR3 simultaneously. Site Constraint 4 : Drill Length, Drilling & Blasting Plant and Equipment The drill length was dependent on the maximum allowable charge weight per delay. This resulted in a drill length of, on average, 1000mm plus the length of the charge column which ensures the explosive is placed an adequate depth beyond the free face. This provides appropriate confinement for efficient blasting and ensures adequate stemming-plug depth can be provided. Drill lengths varied from 0.5m to 4.1m and were dependent on the allowable charge weight per delay. While allowable charge weights per delay permitted longer drill lengths at some sections of the tunnel, the maximum length drilled was 4.1m due to two factors : i. limitations of the tunnel drill rigs : A single drill rod was able to drill 4.1m and longer lengths could be drilled if necessary, but would have required adding new drill rod by hand, as this process could only be automated for single drillholes, not for a full blast pattern. To drill deeper a jumbo with longer feeds would be required. The feeds on the large 3-boom Jumbos used were 14 (4.3m) long and the 2-arm Jumbo 18 (5.5m). These feeds were used with the hydraulic rock drill COP1838 which has the most effective output power for blasthole drilling. The full 165m2 face with a typical 238 drill holes could be drilled within the cycle times tabulated in Figure 5, with automatic positioning of the boomer arm, however a change of drill rod would mean a considerably increased drilling cycle, possibly extending the cycle to the next day, delaying the blast. It was thus determined, even at chainages where charge weights would have allowed a longer pull length, to maintain the drill length at 4.1m. The concept of extension of drill rod is suitable for surface vertical drilling but not tunnelling. The automatic extension rod system used on a surface drill rig, for vertical holes, would be too heavy for a Jumbo feed which is cantilever supported. It is also dangerous to extend the drill rod alongside the other 2 operating booms on a three boom jumbo. For safety reasons, the Jumbo has sensors near the booms and the booms stop automatically if an object or person comes close to the booms during operation. This means all 3 booms stop during extension of the drill rods. ii. mucking out and support cycle : Restrictions on noise levels meant that even had a longer pull been designed, the resultant size of the muckpile would have required a longer mucking out and support cycle period. In order to avoid unnecessary stockpiling and double-handling of the spoil, haulage of the excavated rock off-site was performed by trucks only during times permitted by the Environmental Protection Department. This limited the total volume of spoil able to be hauled offsite during the mucking out operation, hence longer drill lengths were not considered an advantage to the overall drill and blast cycle.

In addition to the tunnel drill rigs the efficiency and periods of downtime, for maintenance purposes, of other tunnel plant (excavators and loaders) and equipment (e.g. the shotcreting rig) controlled the blasting cycle. Site Constraint 5 : Explosive Delivery and Capacity of Site Magazine A site magazine was approved by the CEDD Mines Division (representing the Commissioner of Mines) to be built on site under the SHT project. This magazine had a maximum capacity to store 800kg of cartridge explosives and 200 kg of other DG-Cat I accessories such as detonators and detonating cords. With a maximum charge weight of 3.8kg/delay x approximately 213 holes/face (1 delay/hole) = approximately 850kg/blast, the capacity of the site magazine was insufficient for 4 blasts per day during the peak period of the project. Daily explosive deliveries by the Mines Division were thus required to supplement explosive supply. The daily explosive delivery also affects the blasting cycle, as the timing of delivery is partially dependent on CEDD Mines Division and is also subject to both weather and supplyroute constraints. Site Constraint 6 : Adverse Weather Delivery of explosives is not recommended when a thunder storm warning or a tropical cyclone warning signal. No 3 or higher is in force. The numbers of blasts affected by adverse weather is shown in Figure 3 below.

Blast Affected By Adverse Weather


40 35 30 Number of Blast 25 20 15 10 5 0 Jun-04 Aug-04 Oct-04 Dec-04 Date Feb-05 Apr-05 Jun-05 No. of Blasts Affected by Adverse Weather Cumulative

Figure 3 : Blasts Affected by Adverse Weather Site Constraint 7 : Program An additional site constraint governing the tunnel excavation method was the key-date for possession of areas of site. For the two temporary access roads, TAR1 at the South Portal and TAR3 at the North Portal, the site area required to construct TAR1 was available at the commencement of the Contract while the site area required for TAR3 was only available 4 months after Contract commencement.

Apart from normal key dates for completing the tunnel lining for handover to third parties for electrical and mechanical (E&M) installations, the early removal date of TAR1 required a tunnel breakthrough on or before the TAR1 removal date, so that explosive delivery from the magazine at the south and in particular stockpiled spoil removal could continue unimpeded through the northern access. Considering the removal date of TAR1 and the earliest start date to construct TAR3 was later than that for TAR1, the Contractor proposed, and implemented, pilot tunnel excavations from the North Portal to meet up with the full face drive extending from the South, followed by enlargement of the pilot tunnel from both north and south ends of the pilot drive. The tunnelling sequence is shown in Fig. 4, with the extent of the pilot tunnels shown at the right hand side of the figure.

Figure 4 : Tunnelling Sequence

TUNNELLING CYCLE The sequence of a normal drill and blast cycle is listed below : Profile survey and setting out : Surveyors will check the tunnel profile and set out the alignment prior to any construction works. Probing : Probing is carried out to ensure probed material is always 20m in advance of the tunnel face. When water inflow from probe holes exceeds the specified limits, grouting will be conducted in advance of the excavation. The maximum pull lengths for blasts in the SHT are approximately 5m. Charging and blasting : The blasting engineer will design blasting patterns for every blast, which are checked and certified by the independent blasting consultant (IBC). Charging by the shotfirers will be carried out after the completion of blast hole drilling. After blasting, the tunnel ventilator will be switched on to provide fresh air inside the tunnel. Mucking out and scaling : Mucking out and scaling will be carried out by loader and hydraulic breaker respectively. Upon completion of mucking, loose rock at the exposed tunnel face will be scaled off by a hydraulic breaker.

Face Mapping, Surveying and Installation of Temporary Support : The Contractors geotechnical engineers will inspect and map the exposed tunnel face in order to determine the support class and the corresponding temporary support measures. After the completion of their inspection, the survey team will check the profile and the miners will prepare the installation of temporary support, if any. Face mapping sheets and all subsequent temporary support that is required are certified by an independent checking engineer (ICE). Vibration and Convergence Monitoring : Vibrations resulting from each blasting operation will be recorded after each blast and the results will be checked by the blasting engineer. Convergence monitoring pins will be installed when the rock class is determined to be lower than Class 5 (for the SHT Tunnels) in accordance with Bartons Q system. The inspection procedures are implemented by the Contractors Geotechnical Engineers, and the results of the inspections are checked by the Consultants Geotechnical Engineers, following the completion of mucking out and scaling, in the sequence listed below : Inspect the excavated roof, wall and tunnel face; Inform the tunnel staff to continue further scaling if deemed necessary; Inform the tunnel staff to install rock bolts at the required locations if deemed necessary; Collect information for the determination of the Q-value; and Design temporary support required, such as pattern rock bolts and thickness of shotcrete, as per the mapping record sheets. Before the commencement of the subsequent drilling and charging cycle, a visual inspection will be carried out by the Geotechnical Engineers to verify if further scaling is required. The General Foreman and Shotfirer also visually check the excavated face for any loose material or blocks that require either support, or scaling.
Total Length of the tunnel Chainage Tunnel From To Explosive Usage Bulk Emulsion Length (m) 32mm Cartridge (Packaged) Emulsion 905 860 25mm Cartridge (Packaged) Emulsion Tunnel Face Area Weight (Kg) 84650 123418 Totals (kg) Totals (t)

Northbound Southbound

1136.4 1134.7 m

2041.22 1994.38

9597 Full Face

217665
2 2

218

166 m Approx 38~70 m Approx mm mm 7600 27 160 m3 m mm

1765 Total Length = Total Volume Rock Excavated: 161675 Northbound Tunnel 158581 Southbound Tunnel Cross-passages (CP2-CP10) Average Powder Factor =

Temporary Support No. of Bars: Dowel Type No. Swellex 4367 Resin Anchored 2393 Totals 6760 Length of Softground support: Tunnel Northbound South Portal Southbound Northbound North Portal Southbound Totals

Volume of shotcrete applied: Tunnel Periphery Length Approx. Calc. Average Shotcrete Thickness No. of Drillholes for Full Face Blasts 2 Drill Length: Max: 286 Approx. bars/m 0.14 Min: 213 Max: 4.1m 2 Average: 250 Min: 0.5m Approx. m /bar 7 Average: 2.3m Tunnel Soft Ground Support Length (m) Totals (m) UC/Lattice Girders 38 Northbound North Portal 74 Southbound 36 25.5 Northbound South Portal 35 9 Southbound 109 (m) Totals

m Approx. 3 m Approx. 2125 0.89

Pilot Average overbreak after smoothing: 286 Northbound 297 Southbound m 3 kg/m
3

No. of UC Girders 17 6 6 11 40

No. of Lattice 0 0 44 35 79

Table 1: Tunnel Excavation Summary

Drill and blast excavation was carried out throughout the rock formation except for excavations through weak zones and the soft ground at the portals, where mechanical excavation methods were employed. Before excavation, monitoring instruments such as ground settlement markers, extensometers, tell-tales and piezometers were installed at the required locations on existing slopes, buildings, private and commercial facilities, utility installations and roadways). Initial readings were then recorded and checked by surveyors and the Contractors geotechnical engineers. In weak ground, and in defined areas, such as the WSD Zone, convergence markers were installed in the tunnel periphery. Details of the total length of the tunnels, total explosive used, rock excavated, shotcrete and other support applied, and number of rock bolts installed, are presented in Table 1 above.

MONITORING OF PROGRESS Tunnel progress was monitored against the Contractors programme using activity durations recorded from the works activities in the excavation cycle. These activities are : a. b. c. d. charge hole drilling; charging and blasting; mucking out and scaling; and face mapping, surveying and temporary support installation.

A summary of the resultant average excavation cycle times for each of the full face and pilot face area is presented in Figure 5 below. Figures 6 show the weekly advance rates achieved.

Figure 5 : Summary of Cycle Times for Various Blast Faces (Full Face = 165m2 approx.)

Advance (m)

Advance (m) 10 15 20 25 0 5
20 25 30

10

15

13-Oct-03 3-Nov-03 24-Nov-03 15-Dec-03 5-Jan-04 26-Jan-04 16-Feb-04 8-Mar-04 29-Mar-04 19-Apr-04 10-May-04 31-May-04 21-Jun-04 12-Jul-04 2-Aug-04 23-Aug-04 13-Sep-04 4-Oct-04 25-Oct-04 15-Nov-04 6-Dec-04 27-Dec-04 17-Jan-05 7-Feb-05 28-Feb-05 21-Mar-05 11-Apr-05 2-May-05 23-May-05 13-Jun-05 30-Jun-05

Northbound Tunnel advancing from South to North Portal

Southbound Tunnel advancing from South to North Portal

13-Oct-03 3-Nov-03 24-Nov-03 15-Dec-03 5-Jan-04 26-Jan-04 16-Feb-04 8-Mar-04 29-Mar-04 19-Apr-04 10-May-04 31-May-04 21-Jun-04 12-Jul-04 2-Aug-04 23-Aug-04 13-Sep-04 4-Oct-04 25-Oct-04 15-Nov-04 6-Dec-04 27-Dec-04 17-Jan-05 7-Feb-05 28-Feb-05 21-Mar-05 11-Apr-05 2-May-05 23-May-05 13-Jun-05 30-Jun-05

0 Cum. Advance (m)

100

200

300

400

500

600

700

800

100

200

Figure 6 : Full Face (or Equivalent Full advance where appropriate) Weekly Advance Rate Monitoring.
Cum. Advance (m) 300 400 500 600 700 800

Note that for comparison with full face advance rates, at locations where a pilot, benching or enlargement drive was conducted, the percentage face area (compared to a full face tunnel) multiplied by the actual advance was used to calculate equivalent full-face drive progress.

Figure 7 graphically presents the typical relationship between pull length and charge weight per delay for the Shatin Heights Tunnel. Plotting pull length versus the charge weights per delay used permitted an assessment of future progress to be made, as charge weights per delay were already known at each chainage interval along the alignment based on the Contractors blast assessment report.
Pull Length VS Charge Weight for All Pilot Tunnel Blasts
6 All Pilot Tunnel Blasts 5 Log. (All Pilot Tunnel Blasts) Pull Length (m) 4 3 2 1 0 0 0.5 1 1.5 2 2.5 Charge Weight (kg/delay) 3 3.5 4 y = 0.8963Ln(x) + 2.1664 R2 = 0.7613

Pull Length VS Charge Weight for All Full Face Blasts


6 5 Pull Length (m) 4 3 2 1 0 0 0.5 1 1.5 2 2.5 Charge Weight (kg/delay) 3 3.5 4 y = 1.2896Ln(x) + 2.2131 R2 = 0.6261 All Full Face Blasts Log. (All Full Face Blasts)

Pull Length VS Charge Weight for All Enlargement Blasts


6 All Enlargement Blasts 5 Pull Length (m) Log. (All Enlargement Blasts) 4 3 2 1 0 0 0.5 1 1.5 2 2.5 Charge Weight (kg/delay) 3 3.5 4 y = 0.965Ln(x) + 2.5931 R2 = 0.6504

Figure 7 : Typical Relationship between Advance Pull Length and Charge Weight for Shatin Heights Tunnel

PRIMARY FACTORS AFFECTING EXCAVATION PROGRESS Each of the following factors affecting progress were reviewed to determine opportunities for improving excavation progress : i. ii. iii. iv. working cycle times allowable working hours using machinery efficiency of blasting vibration limits on sensitive receivers

WORKING CYCLE TIMES Working cycle times may be affected by down time of plant and equipment, supply of explosives and detonators, delays due to misfires, weather and weak zones within the tunnel. Down Time of Plant and Equipment To minimise the down time of the plant and equipment, the Contractor provided sufficient spare plant, spare parts for the plant and an effective service team to maintain the plant and equipment. In conjunction with the monitoring of cycle times and constant updates of the predictions for advance as a function of charge weight as shown above, machine in-service and maintenance schedules were prepared, and additional plant brought into service for large blasts in particular, where increased mucking out and shotcreting times added significantly to the cycle. During tunnelling, with the exception of a single event of a shotcreting machine breakdown causing disruption to one blast cycle, no stoppages were caused by down time of plant and equipment. Supply of Explosives and Detonators At the peak period of the tunnelling works, the capacity of the site magazine was insufficient to conduct 4 blasts per day. As a result a daily explosive delivery was arranged with the CEDD Mines Division. The reassessment of 2 slopes (as discussed below) also increased the allowable charge weight along chainages affected by those features. This had the advantage of not only permitting more rapid advance due to the larger charge weights per delay, but also had the added advantage of opening up a longer tunnel section where bulk emulsion explosives could be used. Supply of bulk emulsion explosives are not affected by the capacity of the site magazine. Bulk emulsion explosives were used where charge weights more than 2.5kg/delay could be used. An emulsion depot was built on site by the explosive supplier. Bulk emulsion has the advantage that while it is a lower class Dangerous Goods (DG7, flammable) material it is not classed as an explosive until gassed at the nozzle, and larger quantities could be stored on site than in the magazine. The management of the explosives supply was crucial. The blasting engineer performed a daily review of the blast designs and the explosive balance in the site magazine, to prevent both lack of explosives or overloading, the latter which was not permitted. Delays due to misfires Misfires may be caused by : a) b) poor connection or crimping of plain detonators; damage of detonating cords or detonators;

c) d)

poor wiring; or cutting off of detonating cords due to rock fragments from the surface detonators immediately after initiation.

If a misfire occurs, the blasting site shall be closed for at least 30 minutes (Dangerous Goods (General) Regulations, Chapter 295B, Regulation 57). The shot firer will then carry out a detailed inspection and checking procedure to identify the area where the misfire occurred and determine the most appropriate method of reconnection prior to re-firing. The whole procedure to review a single misfire can take up to 2 hours subject to the difficulties of reconnection. During the project, one case of misfire was reported due to damaged detonating cords. The blasting cycle was delayed by one day due to this incident. To reduce the chance of a misfire, the Contractor used the Surefire system for initiation, which is generally accepted as a more reliable and safer initiating system than traditional electric detonating systems or those which use plain detonators (initiated by safety fuse). The Surefire system sends a pyrotechnically initiated shock wave down a NONEL shock tube, which in turn sets off the NONEL initiating detonator. All components downstream of the Surefire device are thus non-electric, and unaffected by stray currents. Traditional electric detonating systems send a current down electrical wires to an electric initiating detonator, which can then subsequently be used to set off NONEL shock tubes leading to NONEL detonators. All components downstream of the electric detonator up to and including the initiating detonator are thus electric and may be initiated by stray currents. Electric initiating systems must also undergo rigorous circuit checks, which are time-consuming and can thus affect blasting cycle times. Stoppages caused by the problem of explosives supply during tunnel excavation were thus able to be kept to a minimum.

Plate 1 : Surefire (Left); Electric Blasting Machine (Right) Weak Zones within Tunnel Excavation Apart from soft ground at the south portal (Southbound Tunnel), pre-tender site investigation including two horizontal drill holes providing ground investigation data for the full tunnel length showed several faults or weak zones could be expected, one of which was actually encountered during excavation. The slow advance rates at the south portal in soft ground can be seen in Figure 6 above, resulting in an average advance rate of just 2m/week,

due to requirements for application of both ribs and shotcrete. There is a significant difference between the advance rates in soft ground and hard rock (approximately 10.5m/week). The weak faulted zones away from the Portal were probed extensively prior to advancement for strength and particularly groundwater inflow determination. Mechanical breaking was used to remove spoil. Although the material was of sufficient strength that no ribs were required, with ground support being supplied by shotcrete alone, but it has considerably slowed down the progress. Most of the tunnel length was dry, even at the weak zones, providing ideal tunnelling conditions, with maximum recorded water inflows of less than 3.2l/min. Figure 8 shows mapped Q value versus tunnel chainage, which gives an indication of the rock mass quality encountered. With one exception, a weak zone, the primary factor which determined tunnel advance was allowable charge weight per delay, not rock quality.
Q-Value vs. Tunnel Chainage
100

Mapped Q Value

10 1 0.1 0.01 0.001 1134

Weak Zone

1234

1334

1434

1534

1634

1734

1834

1934

2034

2134

Mapped Q - Northbound Tunnel T1

Tunnel Chainage

Mapped Q - Southbound Tunnel T2

Figure 8 : Mapped Q value vs. Tunnel Chainage

NOISE LIMITS - PUBLIC COMPLAINTS Blasting operations are always sensitive works with regards to the public and residents who live in the vicinity of a blast site. The concerns are not only flyrock, excessive vibration, noise and airblast, but also the blast fumes that may contribute to discomfort amongst residents or road users. With the support from the CEDD, the Resident Site Staff (RSS) and the Contractors blasting team, the Contractor created good communication channels with the public, with site personnel providing details of what could be expected during blasting. The blasting was carried out with the general support of residents in the surrounding area. This resulted in the actual numbers of complaints that were received being relatively few. Three cases of minor cracking were reported in residences. However, an examination of the available blast timing versus dates upon which cracking observations were made, vibration levels, distance, type and direction of cracks observed and review of settlement results all indicated that the blasting was extremely unlikely to have been the cause of the incidents. No structural damage was recorded. The tunnelling works were never stopped due to public complaints or complaints by EPD, WSD or CEDD Mines Division.

EFFICIENCY OF BLASTING METHODS AND TECHNOLOGY Several proposals were put forward to improve advance rates as follows : A joint proposal was put forward to the CEDD Mines Division by the Contractor, Client and Consultant to use bulk emulsion explosives with charge weights less than 2.5kg, with weight-trials to test the accuracy of the computer controlled delivery pump performed at Shek O Quarry. The reduced limit would not only have helped with explosives delivery and storage, but also theoretical improved coupling of explosive to charge hole walls could have helped in reducing vibration levels. The theoretical reduction in vibration levels was reviewed by plotting vibrations due to both explosive types at weights just below and just above 2.5kg/delay, at similar scaled distances. However, this was not considered a sufficiently reliable review as no direct comparison with cartridge (packaged) explosive weights were possible and many other factors such as sensitive receiver locations were considered to have biased the data. The vibration review however showed little difference in the resultant vibration levels. Unfortunately, due to CEDD Mines Division concern over the suitability of the SHT site for trials of this type, and the sensitivity of adjacent receivers at this site, the proposal for use of a lowered bulk emulsion charge weight below 2.5kg/delay was not accepted by the CEDD Mines Division. An informal proposal was also put forward to the CEDD Mines Division by the Contractor for the possible use of electronic detonators in place of NONEL detonators. Electronic detonators provide superior accuracy in delay timing, which reduces overlapping blast shock wave pulses, theoretically reducing vibration levels (Hoshino et al. 2000; Zhang et al. 2004). Added advantages include improved fragmentation and preservation of the integrity of the insitu rock mass (Grobler 2003). A further advantage of electronic detonators is that the higher number of delays available than conventional non-electric (NONEL) delays would have permitted a full face to be blasted in one shot, for very low allowable charge weights. Low allowable charge weights (e.g. 0.066kg/delay as used at the Northbound Tunnel) results in a blast design with close blasthole spacing (low burden), which, with the limited NONEL delays available restricts the blast to a small portion of the face. The 0.066kg/delay blasts e.g. required three separate blasts to advance the entire face a distance of just 500mm. Due to the length of time required for testing and approval of new blasting equipment coupled with the cost of electronic detonators, the Contractors proposal to use electronic detonators was not pursued further. An internal review of blast vibration attenuation laws was conducted to determine if some of the more sensitive close-in blasts, which generally result in low allowable charge weights per delay, more closely followed cube-root scaling (Lucca 2003; Yang et al. 2000) than square-root scaling (Dowding 1996). A more appropriate scaling law, if justified, may have permitted higher allowable charge weights per delay, subject to CEDD Mines Division approval. However the results of the internal review indicated that while cube root scaling may have been appropriate at the portal areas, there was insufficient evidence to justify its use throughout the tunnel, due to the dynamic nature of the location of the advancing face with respect to the location of the sensitive receivers.

VIBRATION LIMITS ON SENSITIVE RECEIVERS Reassessment of Slopes A significant constraint on blast progress was due to the nearby slopes. There are many of them and they presented the greatest challenge due to the initially low assessed critical peak particle velocity (PPVc) limits. Current guidelines for determining peak particle velocities published by the GEO are presented in GEO Report 15, Wong and Pang (1991)

and the GEO Report 15 approach was adopted for initial review of the limiting PPVc on these slopes. GEO Report 15 adopts relatively conservative assumptions (as acknowledged in the report) with dynamic response analysis of slopes conducted at limiting equilibrium, assuming a pseudo-static response mechanism. A transfer function is used to determine resultant soil surface motions as a function of bedrock input motion, with values of the transfer function increasing towards what is termed (Kramer 1996) as the fundamental frequency of the soil deposit, but also falling off as frequency increases further. The fundamental (first natural) frequency of the soil deposit is determined from the geometry and properties of the material, which are also subject to damping. The second, third and fourth natural frequencies are also included in GEO Report 15. Conservative lower bound input frequency levels of 30Hz are commonly adopted, and were used in this case, although these can be adjusted and were also reviewed, and the report methodology also assumes infinite durations of input motions. The duration of input motions from blasting are considered as commonly being of considerably shorter durations than earthquake input motions. The limiting PPVc in GEO Report 15 applies to bedrock input motion PPV below the slope. However on many soil slopes, particularly fill slopes, bedrock motion can be difficult to measure directly unless boreholes are drilled through the feature down to bedrock and inborehole transducers are employed, or outcrops (not boulders) are identified on sites for instrumentation. Bedrock input motions below softer or weaker deposits commonly result in amplified displacements at ground surface (Dowding 1996), although as Kramer (1996) observes, higher frequency (short wavelength) motions may cause portions of a slope above the failure surface to be moving in opposite directions. As time constraints did not permit a more rigorous analysis of the failure mechanisms involved, the underlying assumptions for the original subsurface profile were revisited, based on borehole information and a comprehensive site inspection. The pre and post-contract assumed subsurface profiles for one particular slope are presented in Figures 8a and 8b below. Wong and Pang (1991) observed that the calculation for the critical PPVc had several levels of conservatism in the assumptions. However, they also noted the dynamic slope factor of safety (Fd) should not be allowed to drop below unity, in particular for saprolitic soils which exhibit a large post-peak drop in shear strength, to ensure any slope would not be stressed beyond the failure point. Given the slope was located immediately above a busy main road (Tai Po Rd) a dynamic factor of safety Fd of unity (1.0) was thus chosen as the basis for estimation of the acceleration factor . As a result of the ground profile review, the acceleration factor (the factor which would theoretically cause the slope to fail in a pseudo-static slope stability analysis model) was increased from 0.075 to 0.095. This small change, in conjunction with the appropriate subsurface model, yielded a critical PPV of 13mm/s (which is higher that the PPV of 8mm/s initially adopted in the design). This resulted in an over 2-fold increase in allowable charge weight, pushing it up above 2.5kg/delay, where bulk emulsion could be used. In revisiting the slope profile, the most important factor in increasing the acceleration factor was the presence of the HDG layer in the subsurface profile, immediately above rockhead.

165

Blasting Assessment Feature No: 7SW-D/C9 Scale 1:400 2m GWT


Tai Po Road <------|<------------------ 7SW-D/C9 -------------------------------------->|<Natu

155

S2 S3 S1

Description: Colluvium Unit Weight: 19 Cohesion: 4 Phi: 36

145

135

FOS S1: 1.091 S2: 1.090 S3: 1.091 =0

FOS = 1.0

= 0.075 S2: 0.951


S3: 0.951 = 0.075

FOS S1: 0.952

Description: CDG Unit Weight: 19 Cohesion: 5 Phi: 40

125
Description: Bedrock

115
1,2,3

20 kPa

105 0 10 20 30 40 50 60 70 80 90

Figure 9a : Original Assumed Subsurface and Groundwater Profile


165

Blasting Assessment Feature No: 7SW-D/C9 Scale 1:400 2m GWT


Tai Po Road <------|<------------------ 7SW-D/C9 -------------------------------------->|<Natu

155

S2 S3 S1

Description: Colluvium Unit Weight: 19 Cohesion: 4 Phi: 36

145

FOS = 1.0
FOS = S1: 1.091 S2: 1.090 S3: 1.091 =0

0.095 0.952 S1:


S2: 0.951 S3: 0.951 = 0.075

FOS

135

Description: CDG Unit Weight: 19 Cohesion: 5 Phi: 40

125
Description: Bedrock

115
1,2,3

20 kPa

105 0 10 20 30 40 50 60 70 80 90

Figure 9b : Revised Assumed Subsurface and Groundwater Profile (HDG shown shaded) For the initial PPVc of 8mm/s, the limiting charge weight (~Ch.1550) was1.38kg/delay (max.). After additional ground investigation (GI) with a revision of ground profile and GWL information : Final PPVc = 13mm/s Charge Weight = 3.10kg/delay (max.) Charge Weight Ratio Increase = 1 : 2.2

Assumed frequency in analysis= 30Hz Actual measured frequency: Surface vibrograph 30-85 Hz In-hole vibrograph 85-170 Hz

(In-hole to Surface).

CONCLUSIONS The continuous monitoring of all the elements of the excavation cycle, reviews of areas where additional resources were needed, reviews of site constraints and joint efforts amongst the Client, the Engineer and the Contractor to not just accept the constraints, but pro-actively seek solutions to overcome them, all resulted in timely completion of the tunnel excavation of Sha Tin Heights Tunnel. Acknowledgements The support of the CEDD of the HKSAR throughout the works and in preparation of this paper is gratefully acknowledged. References Dowding, C. H. (1996). Construction Vibrations. Prentice Hall, Upper Saddle River. Grobler, H. P. (2003). Using electronic detonators to improve all-round blasting performances, Fragblast, 7(1), 1-12. Hoshino, T., Mogi, G., & Shaoquan, K. (2000). Optimum delay interval design in delay blasting, Fragblast, 4(2), 139-148 Kramer, S. L. (1996). Geotechnical Earthquake Engineering. Prentice Hall, Upper Saddle River, N.J. Lucca, F. J. (2003). Effective Blast Design & Optimization. Terra Dinamica L.L.C. Wong, H. N. and Pang, P. L. R. (1991). Assessment of Stability of Slopes Subjected to Blasting Vibration. GEO Report 15, Geotechnical Engineering Office, Civil Engineering Department, HKSAR. Yang, N., Zhang, Z., & Liu, H. (2000). The vibration characteristics of a tunnel induced by adjacent blasting. Proc., of the 1st World Conference on Explosives & Blasting Technique, Munich, Germany. Zhang, Z. X., Lindqvist. P. A., Naarttijrvi, T., & Wikstrm, K. (2004). A feasibility study on controlling ground vibrations caused by blasts in Malmberget underground mine, Fragblast, 8(1), 3-21.

You might also like