NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.

18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

PROJECT: TECHNOMEIJI FACTORY

WEEKLY REPORT
(Week No.xx from xxxx , 2012 xxxx , 2012)
-----------------------------------------------------------------------------------------------------------------

Reported by xxxx Site Manager Sent to: Mr. xxxx xxxx the Emplyer Mr. xxxx xxxx the H/Q CM company Mr. xxxx xxxx- the Contractor

CONTENTS
WORK PROGRESS Work in this week: CONSTRUCTION: Installing wall cladding of factory 80% completed. Fabrication steel structure at work shop 100% completed.. Plastering for factory 95% completed. Infrastructure piping works 85% completed. Brick wall for office area 100% completed. Plastering for office area 90% completed. Brick wall for transformer 70% completed. Crush stone 0x4 for ground floor of factory 100% completed. Crush stone 0x4 for ground floor of factory 5% completed. Putty work for office area 10% completed. M & E: Welding and painting pipe for Fire Fighting 70% completed Installing system pipe Fire Fighting 70% completed Drill hole, installation of hanging rod 50% completed. II. Quality control ID 1 2 3 Task name Concrete Rebar Materials Situation Take concrete sample Take sample for tensile test & bending test Take sample for material testing (sand, stone 1x2, cement, brick) Supervisor inspects all work, every day. Consultants request Remark

Inspection

+ Request the contractor to add more 02 strengthen plate for steel column of factory 01 at the drill holes + Request the contractor to add screw for wall cladding
1/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

2/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

Wall appears some crack

Request the contractor adjust wall purlin, repaint & clean metal sheet of wall before installing wall cladding

3/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

Request the contractor repair bracing beam on the top of the rolling door grid X5-X6/1Y8

4/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

Request contractor touch up painting and clear for steel structure

5/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

To add some nuts & connection bolt for bracing beam and purlin

6/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

Insulation air bubble is broken

III. Safety and environmental ID STT Task name Situation Schedule Remark

1 2

Safety Cleaning work

No Safety

Inform in Next week

IV. Weather TUE


11 12 1 10 9 8 7 5 2 3 4 10 9 8 7 5

WED
11 12 1 2 3 4 10 9 8

THU
11 12 1 2 3 4 7 5 10 9 8 7

FRI
11 12 1 2 3 4 5 10 9 8

SAT
11 12 1 2 3 4 7 5 10 9 8 7

SUN
11 12 1 2 3 4 5 10 9 8 7

MON
11 12 1 2 3 4 5

xxx Off day

xxx

xxx

xxx xxx MARCH 2012 Rainy chart

xxx Raining

xxx

Note: Red day is non-working day


7/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

Plan of next week Civil works * Factory + Fabrication of steel frame at workshop: 100% + Lower soil and sub-grading / 100% + Plastering for factory / 100% + Infrastructure piping / 100%. + Concrete for man hole bottom / 100%. + Crush stone base course for ground slab of factory 02 / 100% completed. + Installing wall cladding of factory 02 & factory 03 / 80% completed. + Crush stone base course for ground slab of factory 03: 50% completed. * Office + Putty on wall / 100% completed. + Brick wall / 100% completed. + Compacted soil for ground slab / 100% completed. + Plastering for office area / 100% completed. * Transformer + Concrete for roof floor / 100% completed. + Brick wall / 100% completed. * Motor cycle parking + Lower soil & subgrading / 100% completed. + Installing anchor bolt & casting concrete for column / * M&E (cng tc lp t): + Welding and paiting pipe fire fighting/ PCC: 100%. + Installation the pipe for Fire Fighting / 100%. + Drill hole, installing of hanging rod / 100%

Man Power Tue (xx) 1 3 1 1 55 61 Wed (xx) 1 3 1 1 50 56 Thu (xx) 1 3 1 1 65 71 xxx-xxx Fri (xx) 1 3 1 1 65 71 Sat (xx) 1 3 1 1 50 56 Sun (xx) 1 3 1 1 12 18 Mon (xx) 1 3 1 1 60 66

No. 1 2 3 4 6 7

Title Site manager Site Eng. Surveyor Staff Foreman Worker Total

8/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

Equipments: MACHINE AND EQUIPMENT REPORT xxxx xxxx Fri Sat (xx) (xx) 1 1 1 1 1 1 1 1 0 1 1 1 2 3 1 0 14 1 1 0 1 1 1 2 3 1 0 14

No. Title 1 Bulldozer 2 Truck 3 Excavator 4 5 6 7 8 9 10 11 12 13 14 Grader Theodolite Water pump Bar cropper Roller Bending machine Vibrator Road roller Backfill compactor Crane Total

Tue (xx) 1 0 1 1 1 0 1 1 1 2 3 1 0 13

Wed (xx) 1 1 1 1 1 0 1 1 1 2 3 1 0 14

Thu (xx) 1 1 1 1 1 0 1 1 1 2 3 1 0 14

Sun (xx) 1 0 1 1 1 0 1 1 1 2 3 1 0 13

Mon (xx) 1 0 1 1 1 0 1 1 1 2 3 1 0 13

V. Tracking progress: Please see attached work tracking. VI. Others: - Request the contractor to speech up office finishing work -Request the contractor to submit detail connection for purlin grid X3 with office area, the drawing brick wall grid X1/2Y1-2Y3 - Request the contractor to deliver structure frame to site - Construction work at site is very slow, next week plan of the contractor was delayed in particular : plaster for office area, putty work, concrete of ground slab of factory 02, install anchor bolt for bike park, compacting ground slab of office area. -Request the contractor to improve and to overcome to catch schedule. Site pictures

9/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

Brick wall & plastering for office area

Putty work

10/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

Waterproof & cement mortar work of office roof slab

Leveling for ground slab of office area

Installing support of roof frame of forklift way

11/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

Installing wall cladding for factory 02 & factory 03

Compaction crush stone 0x4 for ground slab of the factory 02

12/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

Checking level of stone 0x4 of factory 02

Checking level of ground base of factory 03

Testing field density of factory 02 & factory 03

13/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

Constructing crush stone 0x4 for ground slab of the factory 03

Fabrication structure frame

14/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

Tensile & bending testing of wire mesh

TRANSFORMER

Installing steel bar, formwork for roof floor

Checking slump of concrete

15/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

Casting concrete for roof floor

Getting concrete sample MOTORCYCLE PARKING

Backfilling for foundation

16/17

NEW CC CONSTRUCTION CONSULTANTS Co., Ltd.


18B Road N.02 Lu Gia Resident Area- Dist 11- HCMC Tel: 08-8641262 Email: cttvxdcc@hcm.vnn.vn fax: 08-8641258

M&E:

Installing pipe Fire Fighting

17/17