Professional Documents
Culture Documents
ABC by 2010
UDOT goals
Accelerated Bridge Construction
Standard practice by 2010
ABC Phase 1
Early implementation of ABC
Workshops held
Precast Concrete Elements
Prefabricated Components
Modular Construction
Large Prefab. Components
Brought all stakeholders together Identified what was needed Prioritized needs Looked at several specific pilot projects
ABC Phase 1
Results of Phase 1 work
Several key standards were developed
Precast Full Depth Deck Panels Manual on Self Propelled Modular Transporters (SPMTs) Development of specifications and manuals for each Several pilot projects initiated and built
Precast Superstructures
Crane, Sliding, and SPMT
ABC By 2010
ABC By 2010
Voided Slabs
Voided Slabs
Precast Substructure
Precast Substructure
ABC By 2010
Precast Substructure
Precast Substructure
ABC By 2010
ABC By 2010
ABC Phase 2
Standardized the remainder of prefabricated element types Developed details for:
Precast substructures
Piers, Abutments, walls, culverts
Developed Specifications and Manuals Workshops were held for industry input
ABC Phase 2
Other work completed in Phase 2
Reviewed computer monitoring data from first round of SPMT bridge moves Refined Phase 1 work based on lessons learned in construction
Deck Panel standards and specifications SPMT Manuals
Connections with Grouted Splice Couplers Emulates a reinforcing steel lap splice Used in precast parking garages and stadiums and bridges New seismic research coming
ABC By 2010
Connections with Grouted Splice Couplers Installation video on Youtube Search Georgia Bridge Pier
ABC By 2010
ABC By 2010
Stage 1
1.
Drive Piles
Stage 2
Stage 3
1. 2. 3.
Place footings over pile and set to grade and alignment (day 1) Cast concrete in voids around piles (day 1) Cast concrete between footings if required (day 2)
1. 2. 3. 4. 5.
Install pier wall panels. (day 4) Connect to footing via grouted splice couplers (day 4) Fill voids with concrete to within 3 feet of top (day 5) Install rebar cage in top of voids extending 2 feet above (day 5) Joints between may be grouted or left dry
Stage 4
Final Construction
1. 2.
3.
Install pier cap, set to grade (day 6) Pour concrete through ports to fill voids and make connection (day 7) Install precast beam seats (day 7)
ABC By 2010
Box Culverts
Precast boxes, aprons, and walls
Tolerances
Tolerance details developed for all critical elements Based on PCI Tolerance manual
MNL-135-00
Tolerance Details
Splice couplers Columns
Tolerance Details
10
ABC By 2010
11
ABC By 2010
Erect Girders
12
ABC By 2010
Charged with review of data and recommendations for future SPMT bridge moves Used computer monitoring data from 2008 Typical 2 Span Bridge
Dynamic Strain
Lifting Strain
Typical Data
13
ABC By 2010
3d Analysis is needed to estimate lifting stresses if a flexible carrying beam is used Recommended future gaging locations
Lessons Learned
Study of Performance of ABC Bridges Bridge Types Studied
Full Depth Deck Panels with welded tie connections (6) Full Depth Deck Panels with Post-Tensioning (2) Precast Parapets integral with deck (5) SPMT Bridge Moves (9) Precast Abutments (2) Precast Piers (2)
Neg. DL moment on girder May be a problem with prestressed girders Light weight concrete could help Little or no deck cracking Deck is pre-compressed in final condition
Neg. DL moment on composite section Significant deck cracking is possible Light weight concrete could help
Lessons Learned
Project locations
Milepost 200 on Route 6 not shown
Lessons Learned
Purpose of the study
Investigate the performance of each component type What is performing well and what is not Not intended to critique past designs
Most of these bridges were designed prior to development of standards Many were designed as short term fixes prior to full replacement in the near future (10-25 years)
14
ABC By 2010
Lessons Learned
Welded Tie Connections
Joint Leakage is widespread Shear transfer is still working Composite connection is good
Lessons Learned
Welded Tie Connections
Lessons Learned
Welded Tie Connections Welded Tie Connections
Lessons Learned
Lessons Learned
Post Tensioned Connections
3 span continuous bridge
Lessons Learned
Post Tensioned Connections
No Joint Leakage Even in negative moment areas
15
ABC By 2010
Project Information
Curved structure (straight beams) 6 Span bridge with continuous spans Single lane Prestressed transversely and post tensioned longitudinally Details similar to UDOT 42 Day construction
No construction problems
Built in 1991
Lessons Learned
Precast parapets integral with precast decks
Most are good Problem with panels cast with 2 parapets
No transverse adjustment during installation
Asphalt wearing surface with waterproofing membrane In service for 15 years Excellent condition
16
ABC By 2010
Lessons Learned
Precast Abutments
Few have been built
Lessons Learned
Horizontal joints (Lego bridges) None built to new standards yet There were significant fit-up problems on one bridge
Can be resolved with appropriate casting tolerances
Performing well
Lessons Learned
Precast Piers
Few have been built
One is similar
Lessons Learned
None built to new standards yet Construction went well Performing well
Lessons Learned
Lessons Learned
SPMT Bridge Moves
Deck cracking is common Exceptions:
Bridges cast while supported at lift points Lightweight Concrete Deck
17
ABC By 2010
Lessons Learned
Lessons Learned
Lessons Learned
Cast-in-place closure pours
Some have significant shrinkage cracks
Restraint of adjacent panels Some leakage through cracks
Lessons Learned
Lessons Learned
Lessons Learned
Shear Connector Pockets
Several have minor leakage around pockets (not all)
Shrinkage of Grout Blind pockets should alleviate this
18
ABC By 2010
Lessons Learned
Recommendations
Lessons Learned
Full Depth Deck Panels
Eliminate welded tie detail Always use post-tensioning Use blind pocket detail for shear connectors New Standards address these recommendations
Lessons Learned
Recommendations
Precast integral parapets
Do not use 2 per panel
Use a longitudinal closure pour in deck to allow for adjustment in the field Cast one or both in the field behind temp. barriers
Lessons Learned
Recommendations
Precast Abutments and Piers
Use vertical joints in abutment stems and wall stems
Allows for easier fit-up in the field
No problems noted with pier construction New Standards address these recommendations
Lessons Learned
SPMT Moves
TAC Committee work verifies issues found in the field
Pick bridges closer to ends If possible, support girders at lift points during deck casting Investigate the use of lightweight concrete to reduce deck and girder stresses New SPMT Manual will address these recommendations
Lessons Learned
Other general recommendations
Overlays
Consider thicker overlay with a quality waterproofing membrane
European and East Coast Systems CME recommendation, not UDOT policy
Closure Pours
Use a better high early strength concrete mix
Shrinkage compensating mixes NY State mix is being investigated
19
ABC By 2010
Decrease MOT
Reduce User Costs and impact to society
Lightweight Concrete
SPMT Decks (minimize deck cracking) Substructure Elements (reduce shipping and handling costs)
Questions?
This presentation will be posted on the UDOT website
Testing data
20
ABC By 2010
Testing data
21