Project Status Report

Project Name: Secure Mail system Department: Guide Name: Information Technology Mr. satyendra Singh Team Leader: Ashish Ranjan

Prepared By:
Document Owner(s) Project/Organization Role Coding(50%), Interface designing(25%),Documentation(25%), Testing(40%) Coding(25%), Interface designing(50%),Documentation(25%), Testing(30%) Coding(25%), Interface designing(25%),Documentation(50%), Testing(30%)

Ashish Ranjan

Saurabh Kumar Dipesh Deepak

Department of Information Technology Institute of Engineering and Technology Alwar March 2013

Project Status Report

Project Status Report


Project Name: Secure Mail System Prepared By: Ashish Ranjan Saurabh Kumar Dipesh Deepak Project Overall Status All the designing part of the project is almost complete. Two modules, login modules and mail modules are complete. Coding part of rest of the module is running. Project Summary: The Secure Mail System is meant to keep the security of the mails sent between the users in a LAN .The user can easily encrypt the mail .A user can insert his topic in the LAN to see the views of the other users. The main concern of this project is to improve the efficiency and effectiveness of the whole system. Milestone Deliverables performance reporting over last period Date: 03/09/13 Reporting Period: 09/01/2012 to 05/25/2013

Milestone Deliverables Home Module Designing coding testing

Due Date 12/18/2012 12/25/2012 12/29/2012

% Completed 100% 80% 95%

Deliverable Status [On Schedule] [On Schedule] [Behind Schedule] [On Schedule] [On Schedule] [Behind Schedule] [On Schedule] [Behind Schedule] [Behind Schedule]

Login Module Designing coding testing 01/10/2012 01/14/2012 01/25/2012 100% 100% 95%

Inbox Module Designing Coding Testing 01/29/2013 02/07/2013 02/17/2013 100% 60% 0%

Project Status Report

Draft Module Designing Coding Testing 02/25/2013 03/10/2013 03/20/2013 100% 30% 0% [On Schedule] [On Schedule] [On Schedule] [Ahead of Schedule] [On Schedule] [On Schedule] [Ahead of Schedule] [On Schedule] [On Schedule]

Cryptography Module Designing Coding Testing 03/26/2013 04/03/2013 04/15/2013 95% 0% 0%

Outbox Module Designing Coding Testing 04/16/2013 04/18/2013 04/21/2013 95% 0% 0%

Project Status Report

PROJECT STATUS REPORT APPROVALS

Guide Comments on the Teams performance:

Approved by

Guidse Signature and Date