You are on page 1of 332

d Site: 0 Computer Code No. : Item No.

: FDAPL/WP/VIII/3 Description : Box type W/P to RCC raft, walls Location : Pune W1 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Providing box type waterproofing treatment to RCC raft, wall, footings, columns, beams in basement by fixing rough shahabad stone slabs of about 25 mm thickness in C:M. 1:3 with waterproofing layer in between shahabad stone and slab bottom/ wall surfaces well pointed with cement plaster mixed with waterproofing compound carefully well pressed and cured. The said treatment shall be carried out at the hands of approved waterproofing agency. Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Shahabad stone with 5% wastage d) Waterproofing compound 2 Labours : Masons for laying tiles & finishing Unskilled labour Centering & Shuttering Nil Quantity 1.28 0.04 1.05 0.60 Unit Bags Cum Sqm. Kg. Rate per 245.00 1060.00 82.50 40.00 Amount 313.60 42.40 86.63 24.00

0.15 0.30

No. No.

150.00 80.00

22.50 24.00

Others 0.00 TOTAL (A) 0.00 0.00 513.13 10.26 2.57 0.00 525.95 78.89 604.85

5 6 7 8

Tools & Plants Charges Water charges Electricity Charges Over head & Profit

2.00% 0.50% 0.00% 15.00%

on total (A) on total (A) on total (A) TOTAL (B) on total (B) TOTAL

Say Rs. Prepared by :

605 /- Per

per sqm

Name : _________________________________

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/WP/VIII/2 Description : Brickbat water proofing for toilets Location : Pune W2 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Cum

Providing & laying brick bat coba of required thickness in C:M. 1:4 over the specified area including rubbing and cleaning the base formwork if necessary giving proper slope compacting and curing etc. complete, (in sunk portion of toilets) including providing and fixing 1" dia GI water escape pipe etc. complete. Sr.No. 1 Particulars Quantity Assuming the thickness of 200mm Materials : a) Cement 0.63 b) Sand 0.07 c) Brickbats 0.16 d) Waterproofing compound 0.63 e) 1" dia. GI pipe 0.30 Unit Rate per Amount

Bags Cum Cum Kg. Rmt.

245.00 1060.00 250.00 40.00 89.00

154.35 74.20 40.00 25.20 26.70

Labours : Laying of brickbats & finishing Mason Helper

0.50 0.50

No. No.

200.00 80.00

100.00 40.00

Others Lift

1.00

Cum

17.75

17.75

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit Costing for 0.2 cum 15.00% on total (B) TOTAL

478.20 9.56 2.39 0.00 490.16 73.52 563.68

Say Rs. Prepared by : Name : _________________________________

2,818 /- Per

per Cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/WP/VIII/1 Description : Location : Pune W3 Default Date : Revised on Date : Unit : Brickbat water proofing for terrace

Jan 0, 00 14-08-06 per sqm

Providing and laying cement bonded waterproofing treatment using brick bats fixed in concrete 1:2:4 in required slope and finishing top with neat cement punning, marking lines at 300 mm c/c including providing and mixing waterproofing compound ( work to be carried out at the hands of approved nominated sub contractors) including curing, testing against watertightness Sr.No. 1 a) Cement b) Sand c) Metal d) Brickbats e) Waterproofing compound 2 Labours : Laying of brickbats & finishing Mason Helper 0.40 0.03 0.03 0.08 0.43 Bags Cum Cum Cum Kg. 245.00 1060.00 340.00 250.00 40.00 98.74 31.80 10.20 20.00 17.20 Particulars Quantity Assuming 1 sqm. Of area with 115 thk. Coba Unit Rate per Amount

0.40 0.40

No. No.

200.00 80.00

80.00 32.00

Others Lift

0.12

Cum

17.75

2.04

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A)

291.98 5.84 1.46 0.00

TOTAL (B) 7 Over head & Profit 15.00% on total (B) TOTAL

299.28 44.89 344.17

Say Rs. Prepared by : Name : _________________________________

344 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : 35 Description : Location : Pune W4 Default Date : Revision on Date : Unit : Chemical w/p for terrace, toilets

Jan 0, 00 14-08-06 per sqm

Providing and applying approved waterproofing chemical as per manufacturer's specifications to terrace slab, toilet bottoms and sides, balconies etc wherever required with all labour and material Sr.No. Particulars 1 Materials : Rate given by water proofing agency Quantity Unit Rate per Amount

1.00

Sqm

275.00

275.00

Labours :

Centering & Shuttering Nil

Others

TOTAL (A) 5 6 Tools & Plants Charges Water charges 2.00% 0.50% on total (A) on total (A)

275.00 5.50 1.38

Electricity Charges

1.00%

on total (A) TOTAL (B)

2.75 284.63 42.69 327.32

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

327 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/PAINT/IX/1 Description : Location : 0 W3 Default Date : Revised on Date : Unit : White wash

Jan 0, 00 14-08-06 per sqm

Providing and applying white wash to walls and ceilings , to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, including scaffolding of required type, all labour and material complete. Sr.No. 1 Particulars Assuming 10sqm of area Materials : a) Slaked Lime b) Ultramarine blue c) Glue d) Sodium chloride Labours : For 10 sqm. Area , labour required = (0.085+0.035) for first coat & (0.07+.035)*2 for two coat Lime washer Helper 3 Others 0.23 0.11 No. No. 100.00 80.00 22.50 8.40 Quantity Unit Rate per Amount

2.80 7.00 8.00 365.00

Kg. Gram Gram Gram

1.50 0.11 0.05 0.01

4.20 0.80 0.39 3.65

TOTAL (A)

39.95

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit For 10 sqm costing = 63/15.00% on total (B) TOTAL

39.95 0.80 0.20 0.00 40.94 6.14 47.09

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/PAINT/IX/2 Description :

5 /- Per

per sqm

Sign: ________________

Location : 0 W3 Default Date : Revised on Date : Unit : Dry distemper

Jan 0, 00 14-08-06 per sqm

Providing and applying dry distemper of approved make, colour and shade to walls and ceilings , to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, including scaffolding of required type, all labour and material complete. Sr.No. 1 Particulars Assuming 10sqm of area Materials : a) Dry distemper b) Glue d) Putty Quantity Unit Rate per Amount

1.35 80.00 0.20

Kg. Gram Kg.

67.00 0.05 40.95

90.45 3.91 8.19

Labours : For 10 sqm. Area , labour required = (0.22+0.05) for first coat & (0.145+.04) for second coat Painter Helper 0.37 0.09 No. No. 150.00 80.00 54.75 7.20

Others

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit For 10 sqm costing = 290/15.00% on total (B) TOTAL

164.50 3.29 0.82 0.00 168.61 25.29 193.90

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/PAINT/IX/3 Description :

19 /- Per

per sqm

Sign: ________________

Location : 0 W3 Default Date : Revised on Date : Unit : Oil bound distemper

Jan 0, 00 14-08-06 per sqm

Providing and applying oil bound distemper of approved make,colour and shade to walls and ceilings , to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks, putty filling, rubbing etc including scaffolding of required type, all labour and material complete. Sr.No. 1 Particulars Assuming 10sqm of area Materials : a) OBD b) Primer c) Glue d) Whitning e) Putty Labours : For 10 sqm. Area , labour required = (0.275+0.06) for first coat & (0.22+.05) for second coat Quantity Unit Rate per Amount

1.50 0.85 80.00 1.00 0.20

Kg. lts. Gram Kg. Kg.

90.00 60.90 0.05 20.00 40.95

135.00 51.77 3.91 20.00 8.19

Painter Helper 3 Others

0.50 0.11

No. No.

150.00 80.00

74.25 8.80

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit For 10 sqm costing = 371.5/Say Rs. Prepared by : Name : _________________________________ 15.00% on total (B) TOTAL 36 /- Per per sqm

301.91 6.04 1.51 0.00 309.46 46.42 355.88

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/PAINT/IX/4 Description : Location : 0 W3 Default Date : Revised on Date : Unit : Synthetic enamel paint

Jan 0, 00 14-08-06 per sqm

Providing and applying synthetic enamel paint of approved make,colour and shade to walls and ceilings , to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks, putty filling, rubbing etc including scaffolding of required type, all labour and material complete. Sr.No. Particulars Quantity Unit Rate per Amount Assuming 10sqm of area 1 Materials : a) Synthetic enamel 1.50 Kg. 141.75 212.63 b) Primer 0.85 lts. 60.90 51.77 c) Glue 80.00 Gram 0.05 3.91 d) Whitning 1.00 Kg. 20.00 20.00 e) Putty 0.20 Kg. 40.95 8.19 2 Labours :

For 10 sqm. Area , labour required = (0.295+0.09) for first coat & (0.265+.06) for second coat Painter Helper 3 Others 0.56 0.15 No. No. 150.00 80.00 84.00 12.00

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit For 10 sqm costing = 482.95/15.00% on total (B) TOTAL

392.49 7.85 1.96 0.00 402.30 60.34 462.64

Say Rs. Prepared by : Name : _________________________________

46 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/PAINT/IX/6 Description : Location : 0 W3 Default Date : Revised on Date : Unit : Lustre paint

Jan 0, 00 14-08-06 per sqm

Providing and applying lustre paint of approved make,colour and shade to walls and ceilings , to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks, putty filling, rubbing etc including scaffolding of required type, all labour and material complete. Sr.No. 1 Particulars Assuming 10sqm of area Materials : a) Luster paint b) Primer c) Glue Quantity Unit Rate per Amount

1.50 0.85 80.00

Ltr. lts. Gram

218.75 60.90 0.05

328.13 51.77 3.91

d) Whitning e) Putty 2 Labours : For 10 sqm. Area , labour required = (0.4+0.15) for first coat & (0.375+.12) for second coat Painter Helper 3 Others

1.00 0.30

Kg. Kg.

20.00 40.95

20.00 12.29

0.85 0.30

No. No.

150.00 80.00

127.88 23.76

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit For 10 sqm costing = 623.93/15.00% on total (B) TOTAL

567.72 11.35 2.84 0.00 581.91 87.29 669.20

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/PAINT/IX/7 Description :

67 /- Per

per sqm

Sign: ________________

Location : 0 W3 Default Date : Revised on Date : Unit : Cement paint

Jan 0, 00 14-08-06 per sqm

Providing and applying cement paint of approved make,colour and shade to walls and wherever required to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks, putty filling, rubbing , curing etc including scaffolding of required type, all labour and material complete. Sr.No. Particulars Quantity Unit Rate per Amount Assuming 10sqm of area 1 Materials :

a) Cement paint b) Putty 2 Labours : For 10 sqm. Area , labour required = (0.25+0.15) for first coat & (0.2+.1) for second coat Painter Helper Unskilled Others

4.00 0.15

Kg. Kg.

49.35 40.95

197.40 6.14

0.45 0.25 0.20

No. No. No.

150.00 80.00 80.00

67.50 20.00 16.00

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit For 10 sqm costing = 377.82/15.00% on total (B) TOTAL

307.04 6.14 1.54 0.00 314.72 47.21 361.93

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/PAINT/IX/8 Description :

36 /- Per

per sqm

Sign: ________________

Location : 0 W3 Default Date : Revised on Date : Unit : Sandtex paint

Jan 0, 00 14-08-06 per sqm

Providing and applying sandtex paint of approved make,colour and shade to walls and wherever required to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks, putty filling, rubbing , curing etc including scaffolding of required type, all labour and material complete. Sr.No. Particulars Quantity Unit Rate per Amount Assuming 10sqm of area 1 Materials :

a) Sandtex paint b) Cement paint c) Putty 2 Labours : For 10 sqm. Area , labour required = (0.3+0.1) for first coat & (0.25+.1) for second coat Painter Helper Unskilled Others

4.50 1.50 0.20

Kg. Kg. Kg.

86.36 49.35 40.95

388.63 74.03 8.19

0.65 0.20 0.20

No. No. No.

150.00 80.00 80.00

97.50 16.00 16.00

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit For 10 sqm costing = 761.5/15.00% on total (B) TOTAL

600.35 12.01 3.00 0.00 615.35 92.30 707.66

Say Rs. Prepared by : Name : _________________________________

71 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/PAINT/IX/9 Description : Location : 0 W3 Default Date : Revised on Date : Unit : Antifungal paint

Jan 0, 00 14-08-06 per sqm

Providing and applying anti fungal paint of approved make,colour and shade to walls to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks, putty filling, rubbing , curing etc including scaffolding of required type, all labour and material complete. Sr.No. Particulars Quantity Unit Rate per Amount

Assuming 10sqm of area Materials : a) Antifungal paint b) Cement paint c) Putty Labours : For 10 sqm. Area , labour required = (0.3+0.1) for first coat & (0.25+.1) for second coat Painter Helper Unskilled Others

4.50 1.50 0.20

Kg. Kg. Kg.

123.38 49.35 40.95

555.19 74.03 8.19

0.65 0.30 0.20

No. No. No.

150.00 80.00 80.00

97.50 24.00 16.00

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit For 10 sqm costing = 953.22/Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/PAINT/IX/5 Description : Location : 0 W3 Default Date : Revised on Date : Unit : Plastic emulsion paint 15.00% on total (B) TOTAL 91 /- Per per sqm

774.90 15.50 3.87 0.00 794.28 119.14 913.42

Sign: ________________

Jan 0, 00 14-08-06 per sqm

Providing and applying plastic emulsion paint of approved make,colour and shade to walls and ceilings , to concrete / brick /block/ stone surfaces including preparing the surface by cleaning, filling the cracks, putty filling, rubbing etc including scaffolding of required type, all labour and material complete. Sr.No. Particulars Quantity Unit Rate per Amount

Assuming 10sqm of area Materials : a) Plastic emulsion paint b) Primer c) Glue d) Whitning e) Putty Labours : For 10 sqm. Area , labour required = (0.425+0.25) for first coat & (0.375+.15) for second coat Painter Helper

1.75 0.85 80.00 1.25 0.40

Kg. lts. Gram Kg. Kg.

205.15 60.90 0.05 20.00 40.95

359.01 51.77 3.91 25.00 16.38

0.80 0.40

No. No.

150.00 80.00

120.00 32.00

Others

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit For 10 sqm costing = 553.7/15.00% on total (B) TOTAL

608.06 12.16 3.04 0.00 623.27 93.49 716.75

Say Rs. Prepared by : Name : _________________________________

72 /- Per

per sqm

Sign: ________________

0.38 0.0152 1.2768

refer page 109 & 75

17.7

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/ROOF/X/1 Description : Ac trafford 6mm thk.sheets Location : 0 B1 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Sqm.

Providing and fixing in position AC sheet roofing with 6mm thick Trafford sheets at all required levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material.

Sr.No. 1

Particulars Quantity Assuming area of 15 x 4 = 60 sqm. Materials : a) AC trafford sheets 72.77 (adding 100mm for side laps & 200mm for end lap & 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk. 0.30 64.00 0.30

Unit

Rate per

Amount

Sqm.

149.10

10849.26

Kg. Nos. Kg.

32.00 6.30 47.25

9.60 403.20 14.18

Labours : For fixing the sheets Others Nil

60.00

Sqm.

35.00

2100.00

0.00

0.00

0.00

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit Costing for 60 sqm. area 15.00% on total (B) TOTAL

13376.24 267.52 0.00 66.88 13710.64 2056.60 15767.24

Say Rs.

263 /- Per

per Sqm.

Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/ROOF/X/2 Description : Ac 6mm thk.ridges Location : 0 B1 Default Date : Revised on Date : Unit : Sign: ________________

Jan 0, 00 14-08-06 per Rmt.

Providing and fixing in positional AC ridges as required including all fixing accessories complete Sr.No. Particulars 1 Materials : a) AC ridges (adding 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk. 2 Labours : For fixing the sheets Others Nil 0.00 0.00 0.00 Quantity 1.05 Unit Rmt. Rate per 94.50 Amount 99.23

0.02 2.00 0.02

Kg. Nos. Kg.

32.00 6.30 47.25

0.64 12.60 0.95

1.00

Rmt

25.00

25.00

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit 15.00% on total (B) TOTAL

138.41 2.77 0.00 0.69 141.87 21.28 163.15

Say Rs. Prepared by :

163 /- Per

per Rmt.

Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/ROOF/X/3 Description :

Sign: ________________

Location : 0 B1 Default Date : Revised on Date : Unit : Ac trafford 6mm thk.sheets cladding

Jan 0, 00 14-08-06 per Sqm.

Providing and fixing in position AC sheet roofing with 6mm thick Trafford sheets at all required levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material. For Cladding, flashing etc. Sr.No. 1 Particulars Quantity Assuming area of 15 x 4 = 60 sqm. Materials : a) AC trafford sheets 69.30 (adding 100mm for side laps & 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk. 2 Labours : For fixing the sheets Others Nil 0.00 0.00 0.00 0.30 48.00 0.30 Unit Rate per Amount

Sqm.

149.10

10332.63

Kg. Nos. Kg.

32.00 6.30 47.25

9.60 302.40 14.18

1.00

Sqm.

42.00

42.00

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit Costing for 60 sqm. area 15.00% on total (B) TOTAL

10700.81 214.02 0.00 53.50 10968.33 1645.25 12613.57

Say Rs.

210 /- Per

per Sqm.

Prepared by : Name : _________________________________ Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/ROOF/X/4 Description : Ac gutter Location : 0 B1 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Rmt.

Providing and fixing in required slope AC gutter including fixing with MS flat brackets at 600 mm c/c of required size, filling the joints with polysulphide sealants etc with all labour and material and testing against watertightness. (MS bracket to be measured & paid separately) Sr.No. Particulars 1 Materials : a) AC Gutter (adding 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk. 2 Labours : For fixing the sheets Others Nil 0.00 0.00 0.00 Quantity 1.05 Unit Rmt. Rate per 105.00 Amount 110.25

0.02 2.00 0.02

Kg. Nos. Kg.

32.00 6.30 47.25

0.64 12.60 0.95

1.00

Rmt

25.00

25.00

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit 15.00% on total (B) TOTAL

149.44 2.99 0.00 0.75 153.17 22.98 176.15

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/ROOF/X/5 Description : MS precoated sheets

176 /- Per

per Rmt.

Sign: ________________

Location : 0 B1 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Sqm.

Providing and fixing in position MS precoated sheet roofing of 0.55 mm thickness of ISPAT or any other equivalent make at all required levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material. Sr.No. 1 Particulars Quantity Assuming area of 15 x 5.6 = 84 sqm. Materials : a) MS precoated sheets 97.74 0.55mm (adding 70mm for side laps & 200mm for end lap & 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk. 2 Labours : For fixing the sheets Others Nil 0.00 0.00 0.00 0.38 80.00 0.38 Unit Rate per Amount

Sqm.

319.00

31180.50

Kg. Nos. Kg.

32.00 6.30 47.25

12.00 504.00 17.72

84.00

Sqm.

72.80

6115.20

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit 15.00% on total (B)

37829.41 756.59 0.00 189.15 38775.15 5816.27

Costing for 84 sqm. area

TOTAL

44591.42

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/ROOF/X/2 Description : MS precoated ridges

531 /- Per

per Sqm.

Sign: ________________

Location : 0 B1 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Rmt.

Providing and fixing in position MS precoated ridges as required including all fixing accessories complete Sr.No. Particulars 1 Materials : a) MS precoated ridges (adding 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk. 2 Labours : For fixing the sheets Others Nil 0.00 0.00 TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit 15.00% on total (B) TOTAL 0.00 259.76 5.20 0.00 1.30 266.25 39.94 306.19 Quantity 1.05 Unit Rmt. Rate per 181.50 Amount 190.58

0.02 2.00 0.02

Kg. Nos. Kg.

32.00 6.30 47.25

0.64 12.60 0.95

1.00

Rmt

55.00

55.00

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/ROOF/X/3 Description :

306 /- Per

per Rmt.

Sign: ________________

Location : 0 B1 Default Date : Revised on Date : Unit : MS precoated .55mm thk.sheets cladding

Jan 0, 00 14-08-06 per Sqm.

Providing and fixing in position MS precoated sheet roofing of 0.55 mm thickness of ISPAT or any other equivalent make at all required levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material. For Cladding Sr.No. 1 Particulars Quantity Assuming area of 15 x 2 = 30 sqm. Materials : a) MS precoated sheets 33.71 0.55mm (adding 70mm for side laps & 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk. 2 Labours : For fixing the sheets Others Nil 0.00 0.00 TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit 15.00% on total (B) 0.00 13952.13 279.04 0.00 69.76 14300.93 2145.14 0.23 48.00 0.23 Unit Rate per Amount

Sqm.

319.00

10751.90

Kg. Nos. Kg.

32.00 6.30 47.25

7.20 302.40 10.63

32.00

Sqm.

90.00

2880.00

Costing for 32 sqm. area

TOTAL

16446.07

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/ROOF/X/4 Description : MS precoated gutter

514 /- Per

per Sqm.

Sign: ________________

Location : 0 B1 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Rmt.

Providing and fixing in required slope precoated sheet gutter including fixing with MS flat brackets at 600 mm c/c of required size, filling the joints with polysulphide sealants etc with all labour and material and testing against watertightness. (MS bracket to be measured & paid separately) Sr.No. Particulars 1 Materials : a) MS precoated Gutter (adding 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk. 2 Labours : For fixing the sheets Others Nil 0.00 0.00 0.00 Quantity 1.05 Unit Rmt. Rate per 216.15 Amount 226.96

0.02 2.00 0.02

Kg. Nos. Kg.

32.00 6.30 47.25

0.64 12.60 0.95

1.00

Rmt

90.00

90.00

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit 15.00% on total (B)

331.14 6.62 0.00 1.66 339.42 50.91

TOTAL

390.33

Say Rs. Prepared by : Name : _________________________________

390 /- Per

per Rmt.

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/ROOF/X/5 Description : Alluminium sheets Location : 0 B1 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Sqm.

Providing and fixing in position aluminium sheet roofing with 0.6 mm thick sheets at all required levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material.

Sr.No. 1

Particulars Quantity Assuming area of 15 x 5.6 = 84 sqm. Materials : a) MS precoated sheets 97.74 0.55mm (adding 70mm for side laps & 200mm for end lap & 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk. 0.38 80.00 0.38

Unit

Rate per

Amount

Sqm.

415.80

40642.16

Kg. Nos. Kg.

32.00 6.30 47.25

12.00 504.00 17.72

Labours : For fixing the sheets

84.00

Sqm.

72.80

6115.20

Centering & Shuttering Nil

Others Nil 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit Costing for 84 sqm. area 15.00% on total (B) TOTAL

47291.08 945.82 0.00 236.46 48473.36 7271.00 55744.36

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/ROOF/X/10 Description : Alluminium ridges

664 /- Per

per Sqm.

Sign: ________________

Location : 0 B1 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Rmt.

Providing and fixing in position aluminium ridges as required including all fixing accessories complete

Sr.No. Particulars 1 Materials :

Quantity

Unit

Rate per

Amount

a) MS precoated ridges (adding 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk.

1.05

Rmt.

236.50

248.33

0.02 2.00 0.02

Kg. Nos. Kg.

32.00 6.30 47.25

0.64 12.60 0.95

Labours : For fixing the sheets

1.00

Rmt

55.00

55.00

Centering & Shuttering Nil

Others Nil 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

317.51 6.35 0.00 1.59 325.45 48.82 374.26

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. :

374 /- Per

per Rmt.

Sign: ________________

Location : 0 B1 Default Date :

Jan 0, 00

Revised on Date : Item No. : FDAPL/ROOF/X/11 Description : Alluminium sheets cladding Unit :

14-08-06 per Sqm.

Providing and fixing in position aluminium sheet roofing with 0.6 mm thick sheets at all required levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material. For cladding

Sr.No. 1

Particulars Quantity Assuming area of 15 x 2 = 30 sqm. Materials : a) MS precoated sheets 33.71 0.55mm (adding 70mm for side laps & 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk. 0.23 48.00 0.23

Unit

Rate per

Amount

Sqm.

415.80

14014.54

Kg. Nos. Kg.

32.00 6.30 47.25

7.20 302.40 10.63

Labours : For fixing the sheets

32.00

Sqm.

90.00

2880.00

Centering & Shuttering Nil

Others Nil 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A)

17214.77 344.30 0.00 86.07

TOTAL (B) 8 Over head & Profit Costing for 30 sqm. area 15.00% on total (B) TOTAL

17645.14 2646.77 20291.91

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/ROOF/X/12 Description : Alluminium gutter

676 /- Per

per Sqm.

Sign: ________________

Location : 0 B1 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Rmt.

Providing and fixing in required slope aluminium gutter including fixing with MS flat brackets at 600 mm c/c of required size, filling the joints with polysulphide sealants etc with all labour and material and testing against watertightness. (MS bracket to be measured & paid separately)

Sr.No. Particulars 1 Materials : a) MS precoated Gutter (adding 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk.

Quantity 1.05

Unit Rmt.

Rate per 302.50

Amount 317.63

0.02 2.00 0.02

Kg. Nos. Kg.

32.00 6.30 47.25

0.64 12.60 0.95

Labours : For fixing the sheets

1.00

Rmt

90.00

90.00

Centering & Shuttering Nil

Others Nil 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

421.81 8.44 0.00 2.11 432.36 64.85 497.21

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/ROOF/X/13 Description : FRP sheets

497 /- Per

per Rmt.

Sign: ________________

Location : 0 B1 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Sqm.

Providing and fixing in position FRP sheet of 1.5 mm thick of Finoram or any other approved make at all required levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material.

Sr.No. 1

Particulars Quantity Assuming area of 15 x 5.6 = 84 sqm. Materials :

Unit

Rate per

Amount

a) FRP sheets 1.5mm (adding 70mm for side laps & 200mm for end lap & 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk.

97.74

Sqm.

423.50

41394.80

0.38 80.00 0.38

Kg. Nos. Kg.

32.00 6.30 47.25

12.00 504.00 17.72

Labours : For fixing the sheets

84.00

Sqm.

72.80

6115.20

Centering & Shuttering Nil

Others Nil 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit Costing for 84 sqm. area 15.00% on total (B) TOTAL

48043.71 960.87 0.00 240.22 49244.81 7386.72 56631.53

Say Rs. Prepared by : Name : _________________________________ Rate analysis

674 /- Per

per Sqm.

Sign: ________________

Site:

0 Computer Code No. : Item No. : FDAPL/ROOF/X/14 Description :

Location : 0 B1 Default Date : Revised on Date : Unit : FRP ridges

Jan 0, 00 14-08-06 per Rmt.

Providing and fixing in position FRP ridges as required including all fixing accessories complete

Sr.No. Particulars 1 Materials : a) MS precoated ridges (adding 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk.

Quantity 1.05

Unit Rmt.

Rate per 154.00

Amount 161.70

0.02 2.00 0.02

Kg. Nos. Kg.

32.00 6.30 47.25

0.64 12.60 0.95

Labours : For fixing the sheets

1.00

Rmt

48.05

48.05

Centering & Shuttering Nil

Others Nil 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B)

223.93 4.48 0.00 1.12 229.53

TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

229.53 34.43 263.96

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/ROOF/X/15 Description : FRP sheets cladding

264 /- Per

per Rmt.

Sign: ________________

Location : 0 B1 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Sqm.

Providing and fixing in position FRP sheet roofing with 1.5 mm thick sheets at all required levels including fixing with 'J' hooks, bitumen washers,etc complete with all labour and material. For cladding

Sr.No. 1

Particulars Quantity Assuming area of 15 x 2 = 30 sqm. Materials : a) MS precoated sheets 33.71 0.55mm (adding 70mm for side laps & 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk. 0.23 48.00 0.23

Unit

Rate per

Amount

Sqm.

423.50

14274.07

Kg. Nos. Kg.

32.00 6.30 47.25

7.20 302.40 10.63

Labours : For fixing the sheets

32.00

Sqm.

90.00

2880.00

Centering & Shuttering Nil

Others Nil 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit Costing for 30 sqm. area 15.00% on total (B) TOTAL

17474.30 349.49 0.00 87.37 17911.16 2686.67 20597.83

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/ROOF/X/16 Description : FRP gutter

687 /- Per

per Sqm.

Sign: ________________

Location : 0 B1 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Rmt.

Providing and fixing in required slope FRP gutter including fixing with MS flat brackets at 600 mm c/c of required size, filling the joints with polysulphide sealants etc with all labour and material and testing against watertightness. (MS bracket to be measured & paid separately)

Sr.No.

Particulars

Quantity

Unit

Rate per

Amount

Materials : a) MS precoated Gutter (adding 5% for wastage) b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk. e) Polysulphide sealant

1.05

Rmt.

209.00

219.45

0.02 2.00 0.02 0.03

Kg. Nos. Kg. Kg.

32.00 6.30 47.25 500.00

0.64 12.60 0.95 12.50

Labours : For fixing the sheets

1.00

Rmt

105.00

105.00

Centering & Shuttering Nil

Others Nil 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

351.14 7.02 0.00 1.76 359.91 53.99 413.90

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Location : 0

414 /- Per

per Rmt.

Sign: ________________

Computer Code No. : Item No. : FDAPL/ROOF/X/13 Description :

B1

Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Sqm.

Polycarbonate sheets

Providing and fixing in position polycarbonate sheet roof as per detail design and drawing with minimum thickness of sheet as 2 mm of Lexan or any other approved make including making the joints waterproof with all labour and material and accessories to complete the work.

Sr.No. 1

Particulars Quantity Assuming area of 15 x 5.6 = 84 sqm. Materials : a) Polycabonate sheets 2mm add 5% for wastage b) Bitumen washers 3mm thk. c) J hooks & nuts d) GI flat washer 2mm thk. 0.38 80.00 0.38 88.20

Unit

Rate per

Amount

Sqm.

1500.00

132300.00

Kg. Nos. Kg.

32.00 6.30 47.25

12.00 504.00 17.72

Labours : For fixing the sheets

84.00

Sqm.

72.80

6115.20

Centering & Shuttering Nil

Others Nil 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A)

138948.92 2778.98 0.00 694.74

TOTAL (B) 8 Over head & Profit Costing for 84 sqm. area 15.00% on total (B) TOTAL

142422.64 21363.40 163786.04

Say Rs.

1,950 /- Per

per Sqm.

16.5 4.2 1.21275 72.765 (sheets in row + 1) x no. of purlins 64 hooks

1100

1100

1014 950 0.921818182 0.863636

sheet width = 1.07m, length = 3.2 15*2*1.07*2.9*1.05 97.7445 (sheets in row + 1) x no. of purlins area of sheets = 15*2*2.9*1.07 = 93.09 93.09 Purlin spacing = 1.2m (sheets in row + 1) x no. of purlins 80 hooks

sheets required = 15*1.07*2*1.05 33.705

150.72 4.71 1.536 122.88

7.7

15.4

347908.2

160650

3080 757 73920 97.64861 2587777 2601726.8 538200 6075612 30378.06 15.4 1972.601299 9863.006494

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/2 Description : Location : F1 Pune Default Date : Revised on Date : Unit : Grey Mosaic Tile Flooring of 25cm x 25cm Jan 0, 00 14-08-06 per sqm

Providing,laying and fixing marble mosaic tiles in grey cement on C.M. 1:6 bed including filling the joins with coloured cement slurry of matching colour including polishing, washing, cleaning with dilute acid, waxing etc. complete. Size of tile 25 cm x 25 cm

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Mosaic tile ( as approved) d) White/ coloured cement 2 Labours : a) for fixing & joint grouting b) for polishing (including 3 coats)

Quantity 0.16 0.03 1.05 0.01

Unit Bags Cum Sqm Bags

Rate per 245.00 1060.00 150.00 150.00

Amount 39.20 31.80 157.50 1.50

1.00 1.00

Sqm Sqm

32.00 20.00

32.00 20.00

Centering & Shuttering Nil Others Nil 0.00 0.00 TOTAL (A) 0.00 282.00 5.64 1.41 1.41 290.46 43.57 334.03

5 6 7

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.50% 0.50%

on total (A) on total (A) on total (A) TOTAL (B)

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

334 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/2 Description : Grey Mosaic Tile Flooring of 30x30 Location : F1 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Providing,laying and fixing marble mosaic tiles in grey cement on C.M. 1:6 bed including filling the joins with coloured cement slurry of matching colour including polishing, washing, cleaning with dilute acid, waxing etc. complete. Size of tile 30 cm x 30cm

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Mosaic tile ( as approved) d) White/ coloured cement 2 Labours : a) For fixing & joint grouting b) for polishing (including 3 coats) Centering & Shuttering Nil Others Nil

Quantity 0.16 0.05 1.05 0.01

Unit Bags Cum Sqm Bags

Rate per 245.00 1060.00 220.00 150.00

Amount 39.20 53.00 231.00 1.50

1.00 1.00

Sqm Sqm

32.00 20.00

32.00 20.00

0.00

0.00 TOTAL (A)

0.00 376.70 7.53 1.88 1.88 388.00 58.20 446.20

5 6 7

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.50% 0.50%

on total (A) on total (A) on total (A) TOTAL (B)

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by :

446 /- Per

per sqm

Name : _________________________________

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/2 Description : White Mosaic Tile Flooring of 25x25 Location : F1 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Providing & laying mosaic tile flooring of 20 to 25 mm thk. & size 25x25cm of White colour in required positions & set in a bed of 1:6 cement mortor including neat cement float, filling the joint with appropriate coloured cement slurry, curing, polishing etc. complete

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Mosaic tile ( as approved) d) White/ coloured cement 2 Labours : a) For fixing & joint grouting b) for polishing (including 3 coats) Centering & Shuttering Nil Others Nil

Quantity 0.16 0.03 1.05 0.55

Unit Bags Cum Sqm Kg

Rate per 245.00 1060.00 244.00 30.00

Amount 39.20 31.80 256.20 16.50

1.00 1.00

Sqm Sqm

32.00 20.00

32.00 20.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

395.70 7.91 1.98 1.98 407.57 61.14 468.71

Say Rs.

469 /- Per

per sqm

Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/2 Description : White Mosaic Tile Flooring of 30 x 30 Location : F1 0 Default Date : Revised on Date : Unit : Sign: ________________

Jan 0, 00 14-08-06 per sqm

Providing,laying and fixing marble mosaic tiles in white cement on C.M. 1:6 bed including filling the joins with coloured cement slurry of matching colour including polishing, washing, cleaning with dilute acid, waxing etc. complete. Size of tile 30 cm x 30 cm

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Mosaic tile ( as approved) d) White/ coloured cement 2 Labours : a) For fixing & joint grouting b) for polishing (including 3 coats) Centering & Shuttering Nil Others Nil

Quantity 0.16 0.05 1.05 0.55

Unit Bags Cum Sqm Kg

Rate per 245.00 1060.00 350.00 30.00

Amount 39.20 53.00 367.50 16.50

1.00 1.00

Sqm Sqm

32.00 20.00

32.00 20.00

0.00

0.00 TOTAL (A)

0.00 528.20 10.56 2.64 2.64 544.05 81.61 625.65

5 6 7

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.50% 0.50%

on total (A) on total (A) on total (A) TOTAL (B)

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

626 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/22 Description : Location : F2 Pune Default Date : Revised on Date : Unit : Grey Mosaic Tile Skirting of 125 mm ht. Jan 0, 00 14-08-06 per rmt

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including fixing with C:M 1:4 backing filling the joints with cement slurry, polishing, cleaning complete - gray mosaic tile skirting 125 mm high

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Mosaic tile skirting(as approved)

Quantity 0.02 0.01 1.05

Unit Bags Cum. rmt

Rate per 245.00 1060.00 23.00

Amount 4.90 10.60 24.15

Labours : a) For fixing & joint grouting b) for polishing (including 3 coats)

1.00 1.00

rmt rmt

10.00 9.00

10.00 9.00

3 4

Centering & Shuttering Nil Others Nil

0.00

0.00

0.00

TOTAL (A) 5 6 Tools & Plants Charges Water charges 2.00% 0.50% on total (A) on total (A)

58.65 1.17 0.29

Electricity Charges

0.50%

on total (A) TOTAL (B)

0.29 60.41 9.06 69.47

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

69 /- Per

per rmt

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/23 Description : Location : F2 0 Default Date : Revised on Date : Unit : Grey Mosaic Tile Skirting of 150 mm ht.

Jan 0, 00 14-08-06 per rmt

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including fixing with C:M 1:4 backing, polishing, cleaning, curing etc complete - gray mosaic tile skirting 150 mm high Sr.No. Particulars 1 Materials : a) Cement b) Mosaic tile skirting(as approved) c) Mosaic tile skirting(as approved) 2 Labours : a) For fixing & joint grouting b) for polishing (including 3 coats) Centering & Shuttering Nil Others Nil 0.00 0.00 0.00 Quantity 0.02 0.01 1.05 Unit Bags Cum rmt Rate per 245.00 1060.00 32.00 Amount 4.90 10.60 33.60

1.00 1.00

rmt rmt

10.00 9.00

10.00 9.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/24 Description : Location : F2 0 Default Date : Revised on Date : Unit : White Mosaic Tile Skirting of 125 mm ht. Sign: ________________ 81 /- Per per rmt

68.10 1.36 0.34 0.34 70.14 10.52 80.66

Jan 0, 00 14-08-06 per rmt

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including fixing with C:M 1:4 backing, filling the joints with cement slurry,polishing, cleaning curing etc complete white mosaic tile skirting 125 mm high

Sr.No. Particulars 1 Materials : a) Cement b) Sand b) Mosaic tile skirting(as approved) c) White/ coloured cement 2 Labours : a) For fixing & joint grouting b) for polishing (including 3 coats) Centering & Shuttering Nil

Quantity 0.02 0.01 1.05 0.25

Unit Bags cum. rmt Kg

Rate per 245.00 1060.00 30.00 30.00

Amount 4.90 10.60 31.50 7.50

1.00 1.00

rmt rmt

10.00 9.00

10.00 9.00

Others Nil 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

73.50 1.47 0.37 0.37 75.71 11.36 87.06

Say Rs. Prepared by : Name : _________________________________

87 /- Per

per rmt

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/25 Description : Location : F2 0 Default Date : Revised on Date : Unit : White Mosaic Tile Skirting of 150 mm ht.

Jan 0, 00 14-08-06 per rmt

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including fixing with C:M 1:4 backing,filling the joints with cement slurry, cleaning complete - white mosaic tile skirting 150 mm high

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Mosaic tile skirting(as approved) d) White/ coloured cement 2 Labours : a) For fixing & joint grouting

Quantity 0.02 0.01 1.05 0.25

Unit Bags Cum rmt Kg

Rate per 245.00 1060.00 45.00 30.00

Amount 4.90 10.60 47.25 7.50

1.00

rmt

10.00

10.00

b) for polishing (including 3 coats) 3 4 Centering & Shuttering Nil Others Nil

1.00

rmt

9.00

9.00

0.00

0.00 TOTAL (A)

0.00 89.25 1.79 0.45 0.45 91.93 13.79 105.72

5 6 7

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.50% 0.50%

on total (A) on total (A) on total (A) TOTAL (B)

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

106 /- Per

per rmt

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/1 Description : P/L IPS 50mm thk. Location : F1 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Provding and laying in position IPS flooring 50mm thick in proportion of 1:2:4 laid in proper line and level including finishing the top surface with cement punning, curing, cleaning etc complete with all labour and material.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal 12mm

Quantity 0.22 0.02 0.05

Unit Bags Cum Cum

Rate per 245.00 1060.00 340.00

Amount 53.90 23.85 15.30

Labours : a) for pouring b) for finishing c) for shuttering Centering & Shuttering Nil Others Nil

1.00 1.00 1.00 1.00

Sqm Sqm Sqm Sqm

16.00 23.00 10.56 4.00

16.00 23.00 10.56 4.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

146.61 2.93 0.73 0.73 151.01 22.65 173.66

Say Rs. Prepared by : Name : _________________________________

174 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : 29 Description : Ceramic Tile Flooring Location : F3 Pune Default Date : Revised on Date : Unit : Jan 0, 00 14-08-06 per sqm

Providing and laying ceramic tiles of approved quality of approved colour, size & thickness for flooring in required position laid on a bed 30mm thk.in 1:6 cement mortor including cement float filling joints with white/colour cement slurry cleaning curing etc. complete as shown in detailed drawing or as directed by architect incharge. Sr.No. Particulars 1 Materials : a) Cement b) Sand Quantity 0.16 0.05 Unit Bags Cum Rate per 245.00 1060.00 Amount 39.20 53.00

c) Ceramic tile (as approved) d) white cement 2 Labours : for flooring including fixing, cleaning & curing etc. complete Centering & Shuttering Providing good Specified material/ material / erection & dismantling

1.05 0.55

Sqm Kg

380.00 30.00

399.00 16.50

1.00 0.00

Sqm

75.00 0.00

75.00 0.00

Others 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL Say Rs. Prepared by : Name : _________________________________ Sign: ________________ 690 /- Per per sqm

582.70 11.65 2.91 2.91 600.18 90.03 690.21

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/6 Description : Marble Flooring Location : F4 Pune Default Date : Revised on Date : Unit : Jan 0, 00 14-08-06 per sqm

Providing, laying and fixing in position marble slabs for flooring in plain or diamond pattern or as required including fixing in CM 1:4, cutting if necessary filling joints in white cement slurry curing, polishing, cleaning etc. complete

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Marble (including 5% wastage) d) White cement 2 Labours : a) for fixing & joint grouting b) for polishing Centering & Shuttering Nil Others Nil

Quantity 0.22 0.04 1.05 0.22

Unit Bags Cum Sqm Kg

Rate per 245.00 1060.00 860.00 30.00

Amount 53.90 42.40 903.00 6.60

1.00 1.00

Sqm Sqm

100.00 129.00

100.00 129.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

1234.90 24.70 6.17 6.17 1271.95 190.79 1462.74

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/35 Description : Marble Skirting Location : F4

1,463 /- Per

per sqm

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Rmt.

Providing and fixing in position dado of tiles / stone as per requirement, including fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete -marble stone

Sr.No. Particulars 1 Materials : a) Cement b) Marble (including 10% wastage) c) White cement d) Sand 2 Labours : a) for fixing & joint grouting b) for polishing Centering & Shuttering Nil Others Nil

Quantity 0.22 1.10 1.00 0.01

Unit Bags Sqm Kg Cum

Rate per 245.00 860.00 30.00 1060.00

Amount 53.90 946.00 30.00 10.60

1.00 1.00

Sqm Sqm

110.00 148.35

110.00 148.35

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit Costing per Sqm. 15.00% on total (B) TOTAL

1298.85 25.98 6.49 6.49 1337.82 200.67 1538.49

Say Rs. Prepared by : Name : _________________________________

154 /- Per

per Rmt.

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/7 Description : Kota Flooring Location : F4 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Providing, laying and fixing in required position machine cut machine polished Kotah stone flooring of required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.

Providing, laying and fixing in required position machine cut machine polished Kotah stone flooring of required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Kota (including 5% wastage) d) White cement 2 Labours : a) for fixing & polishing Centering & Shuttering Nil Others Nil

Quantity 0.22 0.04 1.05 0.35

Unit Bags Cum Sqm Kg

Rate per 245.00 1060.00 290.52 30.00

Amount 53.90 42.40 305.05 10.50

1.00

Sqm

100.00

100.00

3 4

0.00

0.00 TOTAL (A)

0.00 511.85 10.24 2.56 2.56 527.20 79.08 606.28

5 6 7 8

Tools & Plants Charges Water charges Electricity Charges Over head & Profit

2.00% 0.50% 0.50% 15.00%

on total (A) on total (A) on total (A) TOTAL (B) on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/27 Description : Kota Skirting Location : F4

606 /- Per

per sqm

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Rmt.

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including fixing with C:M 1:4 backing, filling the joints with cement slurry, polishing, cleaning , curing etc complete - kotah stone 100 mm height

fixing with C:M 1:4 backing, filling the joints with cement slurry, polishing, cleaning , curing etc complete - kotah stone 100 mm height

Sr.No. Particulars 1 Materials : a) Cement b) Kota (including 15% wastage) c) White / coloured cement d) Sand

Quantity 0.34 1.15 1.10 0.01

Unit Bags Sqm Kg Cum

Rate per 245.00 290.52 30.00 1060.00

Amount 83.30 334.10 33.00 10.60

Labours : a) for fixing & polishing

1.00

Sqm

121.00

121.00

3 4

Centering & Shuttering Nil Others Nil

0.00

0.00 TOTAL (A)

0.00 582.00 11.64 2.91 2.91 599.46 89.92 689.38

5 6 7 8

Tools & Plants Charges Water charges Electricity Charges Over head & Profit Costing per sqm

2.00% 0.50% 0.50% 15.00%

on total (A) on total (A) on total (A) TOTAL (B) on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

69 /- Per

per Rmt.

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/9 Description : Tandoor Flooring Location : F4 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Providing, laying and fixing in required position machine cut machine polished Tandur stone flooring of required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.

Providing, laying and fixing in required position machine cut machine polished Tandur stone flooring of required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Tandoor (including 5% wastage) d) White cement 2 Labours : a) for fixing & polishing Centering & Shuttering Nil Others Nil

Quantity 0.22 0.04 1.05 0.35

Unit Bags Cum Sqm Kg

Rate per 245.00 1060.00 291.00 30.00

Amount 53.90 42.40 305.55 10.50

1.00

Sqm

86.00

86.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

498.35 9.97 2.49 2.49 513.30 77.00 590.30

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/29 Description : Tandoor Skirting Location : F4

590 /- Per

per sqm

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Rmt

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning , curing etc complete - tandur stone 100 mm height

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning , curing etc complete - tandur stone 100 mm height

Sr.No. Particulars 1 Materials : a) Cement b) Tandoor (including 15% wastage) c) White / coloured cement d) Sand 2 Labours : a) for fixing & polishing Centering & Shuttering Nil Others Nil

Quantity 0.34 1.15 0.35 0.01

Unit Bags Sqm Kg Cum

Rate per 245.00 291.00 30.00 1060.00

Amount 83.30 334.65 10.50 10.60

1.00

Sqm

94.60

94.60

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit Costing for each Sqm 15.00% on total (B) TOTAL

533.65 10.67 2.67 2.67 549.66 82.45 632.11

Say Rs. Prepared by : Name : _________________________________

63 /- Per

per Rmt

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/8 Location : F4 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Description :

Granite Flooring

Providing, laying and fixing in position granite stone for flooring in plain or diamond pattern or as required including fixing in CM 1:4, cutting if necessary filling joints in white cement slurry curing, polishing, cleaning etc. complete Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Granite (including 5% wastage) d) White / coloured cement 2 Labours : a) For fixing Centering & Shuttering Nil Others Nil Quantity 0.22 0.04 1.05 0.35 Unit Bags Cum Sqm Kg Rate per 245.00 1060.00 1695.00 30.00 Amount 53.90 42.40 1779.75 10.50

1.00

Sqm

172.00

172.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

2058.55 41.17 10.29 10.29 2120.31 318.05 2438.35

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/28 Location : F4

2,438 /- Per

per sqm

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Rmt.

Description :

Granite Skirting

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including fixing with C:M 1:4 backing, filling the joints with white cement, cleaning, curing etc complete - granite stone / tile 100 mm height

Sr.No. Particulars 1 Materials : a) Cement b) Granite (including 15% wastage) c) White cement d) Sand

Quantity 0.34 1.15 0.35 0.01

Unit Bags Sqm Kg Cum

Rate per 245.00 1695.00 30.00 1060.00

Amount 83.30 1949.25 10.50 10.60

Labours : a) for fixing & polishing Centering & Shuttering Nil Others Nil

1.00

Sqm

215.00

215.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit Costing for each Ssqm 15.00% on total (B) TOTAL

2268.65 45.37 11.34 11.34 2336.71 350.51 2687.22

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Location : F4

269 /- Per

per Rmt.

Sign: ________________

0 Default Date : Revised on Date :

Jan 0, 00 14-08-06

Item No. : FDAPL/FLOOR/VI/11 Description : Rough Shahabad flooring

Unit :

per sqm

Providing, laying and fixing in required position machine cut rough shahabad stone flooring of required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Rough shahabad (including 5% wastage) d) White / coloured cement 2 Labours : a) For fixing Centering & Shuttering Nil Others Nil

Quantity 0.22 0.04 1.05 0.35

Unit Bags Cum Sqm Kg

Rate per 245.00 1060.00 75.00 3.00

Amount 53.90 42.40 78.75 1.05

1.00

Sqm

65.00

65.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

241.10 4.82 1.21 1.21 248.33 37.25 285.58

Say Rs. Prepared by : Name : _________________________________

286 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Location : F4 0 Default Date :

Jan 0, 00

Revised on Date : Item No. : FDAPL/FLOOR/VI/10 Description : Polished Shahabad flooring Unit :

14-08-06 per sqm

Providing, laying and fixing in required position machine cut machine polished shahabad stone flooring of required size in plain or diamond pattern or as directed on a cement mortar bedding of 1:4 including cement float ,filling joints with slurry curing rubbing, polishing and cleaning complete.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Polished shahabad (including 5% wastege) d) White / coloured cement 2 Labours : a) For fixing Centering & Shuttering Nil Others Nil

Quantity 0.22 0.04 1.05 0.35

Unit Bags Cum Sqm Kg

Rate per 245.00 1060.00 110.00 30.00

Amount 53.90 42.40 115.50 10.50

1.00

Sqm

80.00

80.00

3 4

0.00 0.00 0.00

0.00 0.00 0.00

0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

302.30 6.05 1.51 1.51 311.37 46.71 358.07

Say Rs. Prepared by : Name : _________________________________

358 /- Per

per sqm

Sign: ________________

Rate analysis

Site:

0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/13 Description :

Location : F4

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Ceramic tiles flooring

Providing and fixing in position ceramic tile of various sizes such as 200 x 200 mm, 300 x 300 mm, 200 x 300 etc of approved make, color and shade on C:M 1:6 bedding including filling the joints with neat cement slurry of matching colour, including cutting the tiles to required size, curing, cleaning etc complete. Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Ceramic tiles(including 5% wastage) d) White / coloured cement 2 Labours : a) For fixing Centering & Shuttering Nil Others Nil Quantity 0.22 0.03 1.05 0.25 Unit Bags Cum Sqm Kg Rate per 245.00 1060.00 380.00 30.00 Amount 53.90 34.45 399.00 7.50

1.00

Sqm

75.00

75.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

569.85 11.40 2.85 2.85 586.95 88.04 674.99

Say Rs. Prepared by : Name : _________________________________

675 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/13 Description : Ceramic tiles Dado Location : F4 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete - ceramic tiles of approved make and type and given height.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Ceramic tiles(including 10% wastage) d) White / coloured cement 2 Labours : a) For fixing Centering & Shuttering Nil Others Nil

Quantity 0.28 0.03 1.10 0.30

Unit Bags Cum Sqm Kg

Rate per 245.00 1060.00 380.00 30.00

Amount 68.60 26.50 418.00 9.00

1.00

Sqm

90.00

90.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

612.10 12.24 3.06 3.06 630.46 94.57 725.03

Say Rs. Prepared by :

725 /- Per

per sqm

Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/33 Description : Ceramic tiles Skirting Location : F4

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Rmt

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete - ceramic tiles of approved make and type and colour 100 mm height

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Ceramic tiles(including 10% wastege) d) White / coloured cement 2 Labours : a) For fixing Centering & Shuttering Nil Others Nil

Quantity 0.28 0.02 1.07 1.00

Unit Bags Cum Sqm Kg

Rate per 245.00 1060.00 380.00 30.00

Amount 68.60 15.90 406.60 30.00

1.00

Sqm

80.00

80.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit Costing per Sqm. 15.00% on total (B) TOTAL

601.10 12.02 3.01 3.01 619.13 92.87 712.00

Say Rs.

71 /- Per

per Rmt

Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/14 Description : Vitrified tiles flooring Location : F4 0 Default Date : Revised on Date : Unit : Sign: ________________

Jan 0, 00 14-08-06 per sqm

Providing and fixing in position vitrified tile flooring of approved make,size and shade on bed of cement mortar 1:6 in required line and level, filling the joints with white cement, cleaning etc complete.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Vetrified tiles(including 5% wastage) d) White / coloured cement 2 Labours : a) For fixing Centering & Shuttering Nil Others Nil

Quantity 0.20 0.03 1.05 0.25

Unit Bags Cum Sqm Kg

Rate per 245.00 1060.00 800.00 30.00

Amount 49.00 26.50 840.00 7.50

1.00

Sqm

80.00

80.00

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

1003.00 20.06 5.02 5.02 1033.09 154.96 1188.05

Say Rs. Prepared by : Name : _________________________________

1,188 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : 30 Description : Vitrified tiles Dado Location : F4 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Providing and fixing in position vitrified tile flooring of approved make,size and shade in required line and level, filling the joints with white cement, cleaning etc complete.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Vetrified tiles(including 10% wastage) d) White / coloured cement 2 Labours : a) For fixing Centering & Shuttering Nil Others Nil

Quantity 0.28 0.02 1.10 0.30

Unit Bags Cum Sqm Kg

Rate per 245.00 1060.00 800.00 0.00

Amount 68.60 21.20 880.00 0.00

1.00

Sqm

96.00

96.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B)

1065.80 21.32 5.33 5.33 1097.77 164.67

TOTAL

1262.44

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : 30 Description : Vitrified tiles Skirting Location : F4

1,262 /- Per

per sqm

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Rmt.

Providing and fixing in position skirting of tiles as per requirement, flush to the plaster surface including fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, curing etc complete -polished vitrified tile 100 mm height

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Vetrified tiles(including 10% wastage) d) White / coloured cement 2 Labours : a) For fixing Centering & Shuttering Nil Others Nil

Quantity 0.28 0.02 1.07 0.30

Unit Bags Cum Sqm Kg

Rate per 245.00 1060.00 800.00 30.00

Amount 68.60 15.90 856.00 9.00

1.00

Sqm

85.00

85.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B)

1034.50 20.69 5.17 5.17 1065.54 159.83

Costing per sqm

TOTAL

1225.37

Say Rs. Prepared by : Name : _________________________________

1,225 /- Per

per Rmt.

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/16 Description : Designer tiles flooring Location : F4 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Providing and fixing in position interlocking type designer tiles of approved make, colour and shade, over bed of 1:6 mortar in proper line and level including finishing, compaction, filling joints cleaning etc complete.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Designer tiles(including 5% wastage)

Quantity 0.18 0.04 1.05

Unit Bags Cum Sqm

Rate per 245.00 1060.00 430.40

Amount 44.10 41.34 451.92

Labours : a) For fixing Centering & Shuttering Nil Others Nil

1.00

Sqm

60.00

60.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B)

597.36 11.95 2.99 2.99 615.28

TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

615.28 92.29 707.57

Say Rs. Prepared by : Name : _________________________________

708 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/17 Description : Paving blocks flooring (regular) Location : F4 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Providing and fixing in position interlocking type designer tiles of approved make, colour and shade, on bed of sand in proper line and level including compaction, filling joints with sand and surface vibrating etc complete. ( of strength M20 - 65 mm thick)

Sr.No. Particulars 1 Materials : a) Sand b) Paver blocks (including 5% wastege) 2 Labours : a) For fixing Centering & Shuttering Nil Others Nil

Quantity

Unit

Rate per

Amount

0.05 1.05

Cum Sqm

1060.00 242.10

53.00 254.21

1.00

Sqm

30.00

30.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A)

337.21 6.74 1.69 1.69

TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

347.32 52.10 399.42

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/18 Description : Location : F4

399 /- Per

per sqm

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Paving blocks heavy duty (M40 & above)

Providing and fixing in position interlocking type designer tiles of approved make, colour and shade, on bed of sand in proper line and level including compaction, filling joints with sand and surface vibrating etc complete. ( of strength M40 - 65 mm thick)

Sr.No. Particulars 1 Materials : a) Sand b) Paver blocks (including 5% wastage)

Quantity

Unit

Rate per

Amount

0.05 1.05

Cum Sqm

1060.00 386.00

53.00 405.30

Labours : a) For fixing

1.00

Sqm

30.00

30.00

3 4

Centering & Shuttering Nil Others Nil

0.00

0.00

0.00

TOTAL (A) 5 Tools & Plants Charges 2.00% on total (A)

488.30 9.77

6 7

Water charges Electricity Charges

0.50% 0.50%

on total (A) on total (A) TOTAL (B)

2.44 2.44 502.95 75.44 578.39

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

578 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/19 Description : Chequered tiles flooring Location : F4 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Providing and laying chequered tiles in required position in proper line and level, on bed of C:M 1:6 including filling the joints with neat cement slurry, cleaning, curing etc complete.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Chequered tiles(including 5% wastage)

Quantity 0.21 0.04 1.05

Unit Bags Cum Sqm

Rate per 245.00 1060.00 102.00

Amount 51.45 41.34 107.10

Labours : a) For fixing

1.00

Sqm

60.00

60.00

3 4

Centering & Shuttering Nil Others Nil

0.00

0.00

0.00

TOTAL (A)

259.89

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

259.89 5.20 1.30 1.30 267.69 40.15 307.84

Say Rs. Prepared by : Name : _________________________________

308 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/42 Description : Kota for steps Location : F4 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing,edge polishing, curing nosing etc complete -kotah stone

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Kota steps (including 5% wastege)

Quantity 0.28 0.04 1.05

Unit Bags Cum Sqm

Rate per 245.00 620.00 250.00

Amount 68.60 24.80 262.50

Labours : a) for fixing & polishing Centering & Shuttering Nil Others Nil

1.00

Sqm

400.00

400.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

755.90 15.12 3.78 3.78 778.58 116.79 895.36

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/40 Description : Marble for steps Location : F4

895 /- Per

per sqm

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Rmt

Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing, edge polishing, nosing,curing etc complete -marble stone

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Marble steps (including 5% wastage) d) White cement 2 Labours : a) for fixing & polishing Centering & Shuttering Nil Others

Quantity 0.28 0.04 1.05 0.35

Unit Bags Cum Sqm Kg

Rate per 245.00 1060.00 1032.00 30.00

Amount 68.60 42.40 1083.60 10.50

1.00

Sqm

167.70

167.70

3 4

Nil

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit Costing per sqm 15.00% on total (B) TOTAL

1372.80 27.46 6.86 6.86 1413.98 212.10 1626.08

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/41 Description : Granite for steps Location : F4

163 /- Per

per Rmt

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Rmt

Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M 1:4 backing, filling the joints with cement slurry,cleaning,polishing,edge polishing,nosing, curing etc complete -granite stone of approved colour

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Granite steps (including 5% wastage) d) White cement 2 Labours : a) for fixing & polishing Centering & Shuttering Nil

Quantity 0.28 0.04 1.05 1.00

Unit Bags Cum Sqm Kg

Rate per 245.00 1060.00 2118.75 30.00

Amount 68.60 42.40 2224.69 30.00

1.00

Sqm

223.60

223.60

Others Nil 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit Costing per sqm. 15.00% on total (B) TOTAL

2589.29 51.79 12.95 12.95 2666.97 400.04 3067.01

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/43 Description : Tandoor for steps Location : F4

307 /- Per

per Rmt

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Providing and fixing in position treads and risers of stone as per requirement, including fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, polishing,edge polishing,nosing, curing etc complete -tandur stone Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Tandoor steps (including 5% wastage) d) White cement 2 Labours : a) for fixing & polishing Centering & Shuttering Nil Quantity 0.22 0.04 1.05 0.35 Unit Bags Cum Sqm Kg Rate per 245.00 1060.00 378.30 30.00 Amount 53.90 42.40 397.22 10.50

1.00

Sqm

111.80

111.80

Others Nil 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit costing per sqm. 15.00% on total (B) TOTAL

615.82 12.32 3.08 3.08 634.29 95.14 729.43

Say Rs. Prepared by : Name : _________________________________

73 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/50 Location : F4 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Description : Kota for sill & Jams Providing and fixing in position window sills and jambs of stone as per requirement, including fixing with C:M 1:4 bedding, filling the joints with cement slurry, cleaning, polishing,edge polishing, curing nosing etc complete -kotah stone Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Kota sill (including 10% wastege) d) White cement 2 Labours : a) for fixing & polishing Centering & Shuttering Nil Others Quantity 0.20 0.02 1.10 1.00 Unit Bags Cum Sqm Kg Rate per 245.00 1060.00 290.52 30.00 Amount 49.00 21.20 319.57 30.00

1.00

Sqm

132.00

132.00

3 4

Nil

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

551.77 11.04 2.76 2.76 568.33 85.25 653.57

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/48 Location : F4

654 /- Per

per sqm

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Description : Marble for Sills & jams Providing and fixing in position window sills and jambs of stone as per requirement, including fixing with C:M 1:4 bedding, filling the joints with cement slurry, cleaning, polishing, edge polishing, nosing,curing etc complete -marble stone Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Marble sill (including 10% wastage) d) White cement Quantity 0.20 0.02 1.10 1.00 Unit Bags Cum Sqm Kg Rate per 245.00 1060.00 860.00 30.00 Amount 49.00 21.20 946.00 30.00

Labours : a) for fixing & polishing

1.00

Sqm

132.00

132.00

Centering & Shuttering Nil

Others Nil 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

1178.20 23.56 5.89 5.89 1213.55 182.03 1395.58

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/49 Location : F4

1,396 /- Per

per sqm

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Description : Granite for sills & Jams Providing and fixing in position window sills and jambs stone as per requirement, including fixing with C:M 1:4bedding, filling the joints with cement slurry,cleaning,polishing,edge polishing,nosing, curing etc complete -granite stone of approved colour Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Granite sill (including 10% wastage) d) White cement 2 Labours : a) for fixing & polishing Centering & Shuttering Nil Quantity 0.28 0.04 1.10 1.00 Unit Bags Cum Sqm Kg Rate per 245.00 1060.00 1695.00 30.00 Amount 68.60 42.40 1864.50 30.00

1.00

Sqm

258.00

258.00

Others Nil 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

2263.50 45.27 11.32 11.32 2331.41 349.71 2681.12

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/51 Location : F4

2,681 /- Per

per sqm

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Description : Tandoor for sills & jams Providing and fixing in position window sills and jambs of stone as per requirement, including fixing with C:M 1:4 bedding, filling the joints with cement slurry, cleaning, polishing,edge polishing,nosing, curing etc complete -tandur stone Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Tandoor sill (including 10% wastege) d) White cement 2 Labours : a) for fixing & polishing Quantity 0.20 0.02 1.10 0.35 Unit Bags Cum Sqm Kg Rate per 245.00 1060.00 291.00 30.00 Amount 49.00 21.20 320.10 10.50

1.00

Sqm

113.52

113.52

Centering & Shuttering Nil

Others Nil 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

514.32 10.29 2.57 2.57 529.75 79.46 609.21

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/56 Location : F4

609 /- Per

per sqm

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 Rmt.

Description : Granite Kitchen otta Providing, making and erecting in position kitchen platform with following specifications. Width of platform 2'3" and height 30" top Sr.No. Particulars Quantity Considering the size of 3.0m x.75m 1 Materials : a) Cement 2.55 b) Sand 0.03 c) Granite (including 10% 3.71 wastage) d) Kaddappa (with 10% wastage) e) White / colour cement 2 Labours : a) for fixing of Kadappa & granite 2.25 Sqm 1506.00 3388.50 3.82 0.35 Unit Rate per Amount

Bags Cum Sqm Sqm Kg

245.00 1060.00 1695.00 220.00 30.00

624.75 31.80 6293.54 840.40 10.50

(considering labour rate @ 105/per rft length I.e = 105/- per 0.75 sft. Rate per sqm = (105/.75)*10.76 = Rs. 1506 b) For moulding & edge polishing c) For Cutout making for sink fixing 3 Others Nil

4.42 1.00

Rmt. No.

246.00 400.00

1087.32 400.00

0.00

0.00 TOTAL (A)

0.00 12676.81 253.54 63.38 63.38 13057.11 1958.57 15015.68 Rmt.

5 6 7

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.50% 0.50%

on total (A) on total (A) on total (A) TOTAL (B)

Over head & Profit Total costing for 3 Rmt.

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

5,005 /- Per

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/57 Location : F4 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 Rmt.

Description : Marble Kitchen otta Providing, making and erecting in position kitchen platform with following specifications. Width of platform 2'3" and height 30" top- Marble stone Sr.No. Particulars Quantity Considering the size of 3.0m x.75m 1 Materials : a) Cement 2.55 b) Sand 0.03 c) Marble (including 10% 3.71 wastage) d) Kaddappa (with 10% wastage) 3.82 Unit Rate per Amount

Bags Cum Sqm Sqm

245.00 1060.00 860.00 220.00

624.75 31.80 3193.18 840.40

e) White / colour cement 2 Labours : a) for fixing of Kadappa & Marble (considering labour rate @ 80/per rft length I.e = 80/- per 0.75 sft. Rate per sqm = (80/.75)*10.76 = Rs. 1147 b) For edge polishing c) For Cutout making for sink fixing 3 Others Nil

0.35

Kg

30.00

10.50

2.25

Sqm

1147.00

2580.75

4.57 1.00

Rmt. No.

196.80 400.00

900.00 400.00

0.00

0.00 TOTAL (A)

0.00 8581.38 171.63 42.91 42.91 8838.82 1325.82 10164.64 Rmt.

4 5 6

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.50% 0.50%

on total (A) on total (A) on total (A) TOTAL (B)

Over head & Profit Total costing for 3 Rmt.

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/58 Location : F4

3,388 /- Per

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 Rmt.

Description : Kadappa Kitchen otta Providing, making and erecting in position kitchen platform with following specifications. Width of platform 2'3" and height 30" top- Kadappa stone Sr.No. Particulars Quantity Considering the size of 3.0m x.75m 1 Materials : a) Cement 2.55 b) Sand 0.03 c) Top & shelf kadappa (including 3.80 10% wastage) Unit Rate per Amount

Bags Cum Sqm

245.00 1060.00 258.00

624.75 31.80 980.40

d) Kaddappa Verticals & Facia (with 10% wastage) e) White / colour cement 2 Labours : a) for fixing of Kadappa (considering labour rate @ 60/per rft length I.e = 60/- per 0.75 sft. Rate per sqm = (60/.75)*10.76 = Rs. 717 b) For moulding & edge polishing c) For Cutout making for sink fixing Others Nil

1.60 0.35

Sqm Kg

220.00 30.00

352.00 10.50

2.25

Sqm

860.00

1935.00

4.57 1.00

Rmt. No.

82.00 250.00

375.00 250.00

0.00

0.00 TOTAL (A)

0.00 4559.45 91.19 22.80 22.80 4696.23 704.44 5400.67 Rmt.

4 5 6

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.50% 0.50%

on total (A) on total (A) on total (A) TOTAL (B)

Over head & Profit Total costing for 3 Rmt.

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

1,800 /- Per

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/FLOOR/VI/43 Description : Designer tiles for steps Location : F4 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Providing and fixing in position treads and risers of designer tiles as per requirement, including fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, etc complete -

Providing and fixing in position treads and risers of designer tiles as per requirement, including fixing with C:M 1:4 backing, filling the joints with cement slurry, cleaning, etc complete -

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Designer Tiles (including 5% wastage) d) White cement 2 Labours : a) for fixing & polishing Centering & Shuttering Nil Others Nil

Quantity 0.22 0.04 1.05 0.35

Unit Bags Cum Sqm Kg

Rate per 240.00 620.00 780.00 30.00

Amount 52.80 24.80 819.00 10.50

1.00

Sqm

300.00

300.00

3 4

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges -3.00% -0.50% -0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit costing per sqm. 15.00% on total (B) TOTAL

1207.10 -36.21 -6.04 -6.04 1158.82 173.82 1332.64

Say Rs. Prepared by : Name : _________________________________

1,333 /- Per

per sqm

Rs 320/- per step


Sign: ________________

0.2 mason 0.5 labour

0.01

0.344 0.86 137.6

0.2 0.5 0.2 0.35

40 28 68

0.2 0.5

40 40

0.2 0.4

40 32

0.25 0.45 90

50 36

0.15 0.3

30 24

0.4 0.8

80 64 144 158.4

65.20

0.9 0.45

180 36

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/MAS/IV/2 Description : UCR In plinth Location : B1 Pune Default Date : Revised on Date : Unit : Jan 0, 00 14-08-06 per cum

Providing & constructing UCR masonry II sort in cement mortar 1:6 for foundation steps, platforms etc.below plinth including curing , weepholes if required, including specials such as corners, quions, headers, through stones etc. dewatering if required, racking out joints 10 mm deep etc. complete.

Sr.No. Particulars 1 Materials : a) Rubble b) Cement c) Sand

Quantity 1.25 1.57 0.40

Unit cum Bags cum

Rate per 500.00 240.00 1060.00

Amount 625.00 376.80 424.00

Labours : for U.C.R. masonry works

1.00

cum

250.00

250.00

Centering & Shuttering Nil

Others Nil 0.00 0.00 0.00

5 6 7 8

Tools & Plants Charges Water charges Electricity Charges Over head & Profit

2.00% 0.50% 0.50% 15.00%

on total (A) on total (A) on total (A) on total (B)

TOTAL (A)

1675.80 33.52 8.38 8.38 1726.07 258.91 1984.99

TOTAL (B) TOTAL

Say Rs. Prepared by :

1,985 /- Per

per cum

Name : _________________________________

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/MAS/IV/3 Description : Location : B1 0 Default Date : Revised on Date : Unit : Uncoursed rubble masonry in superstructure

14-08-06 per cum

Providing & constructing UCR masonry II sort in cement mortar 1:6 for foundation for compound wall, steps, pillars , platforms etc. and wherever required including scaffolding, curing , weepholes if required, including specials such as corners, quions, headers through stones etc. dewatering if required, racking out joints 10 mm deep etc. complete.

Sr.No. Particulars 1 Materials : a) Rubble b) Cement c) Sand

Quantity 1.25 1.57 0.40

Unit cum Bags cum

Rate per 500.00 245.00 1060.00

Amount 625.00 384.65 424.00

Labours : for U.C.R. masonry works

1.00

cum

252.00

252.00

Centering & Shuttering Nil

Others Scaffolding 1.00 Cum 20.00 20.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

1705.65 34.11 8.53 8.53 1756.82 263.52 2020.34

Say Rs.

2,020 /- Per

per cum

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/MAS/IV/1 Description : Location : B1 0 Default Date : Revised on Date : Unit : Brick masonary 35cm thk. Below plinth

14-08-06 per cum

Providing & constructing general BB masonry 350 mm (13.5") or above in thickness in C.M. 1:4 in plinth for steps, or any where as required including racking out joints 1.5 cm deep including scaffolding, curing etc. complete.

Sr.No. Particulars 1 Materials : a) Bricks b) Cement c) Sand

Quantity 500.00 1.70 0.26

Unit Nos. Bags cum

Rate per 2.25 245.00 1060.00

Amount 1125.00 416.50 275.60

Labours : for brick masonry works

1.00

cum

164.00

164.00

Centering & Shuttering Nil Others Nil 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

1981.10 39.62 9.91 0.00 2030.63 304.59 2335.22

Say Rs.

2,335 /- Per

per cum

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/MAS/IV/4 Description : Location : B1 0 Default Date : Revised on Date : Unit : Brick work 35cm thk. In superstructure

Jan 0, 00 14-08-06 per cum

Providing & constructing general BB masonry 350 mm (13.5") or above in thickness in C.M. 1:4 in superstructure at all levels wherever required including raking out joints 1.5 cm deep including scaffolding, curing etc. complete.

Sr.No. Particulars 1 Materials : a) Bricks b) Cement c) Sand

Quantity 500.00 1.70 0.30

Unit Nos. Bags cum

Rate per 2.25 245.00 1060.00

Amount 1125.00 416.50 318.00

Labours : for brick masonry works

1.00

cum

164.00

164.00

Centering & Shuttering Nil

Others Add for scaffolding & sand screening etc.

1.00

cum

45.60

45.60

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B)

2069.10 41.38 10.35 0.00 2120.83 318.12

TOTAL

2438.95

Say Rs.

2,439 /- Per

per cum

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/MAS/IV/5 Description : Plinth Masonry 23cm thk Location : B2 Pune Default Date : Revised on Date : Unit : Jan 0, 00 14-08-06 per cum

Providing & constructing BB masonry of 23 cm thk in 1:4 C.M for walls,etc below plinth wherever required including raking out joints 1.5 cm deep including scaffolding, curing etc. complete.

Sr.No. Particulars 1 Materials : a) Bricks b) Cement c) Sand

Quantity 500.00 0.90 0.05

Unit No Bags cum

Rate per 3.00 210.00 850.00

Amount 1500.00 189.00 42.50

Labours : for Brick masonry works

1.00

sqm

38.00

38.00

Others Nil 0.00 0.00 0.00

5 6 7

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.50% 0.00%

on total (A) on total (A) on total (A)

TOTAL (A)

1769.50 35.39 8.85 0.00 1813.74

TOTAL (B)

Over head & Profit

15.00%

on total (B)

TOTAL (B) TOTAL

1813.74 272.06 2085.80

Say Rs. Prepared by : Name : _________________________________

2,086 /- Per

per cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/MAS/IV/6 Description : BBM 23cm thk in superstructure Location : B2 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per cum

Providing & constructing BB masonry of 23 cm thk in 1:4 C.M for walls in superstructure at all levers wherever required including raking out joints 1.5 cm deep including scaffolding, curing etc. complete.

Sr.No. Particulars 1 Materials : a) Bricks b) Cement c) Sand

Quantity 500.00 0.90 0.05

Unit No Bags cum

Rate per 3.00 245.00 1060.00

Amount 1500.00 220.50 53.00

Labours : for Brick masonry works

1.00

sqm

42.00

42.00

Others Scaffolding / sand screening etc.

1.00

sqm.

9.80

9.80

TOTAL (A)

1825.30

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

1825.30 36.51 9.13 0.00 1870.93 280.64 2151.57

Say Rs. Prepared by : Name : _________________________________

2,152 /- Per

per cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/MAS/IV/8 Description : P/F 15cm thk. Brick Wall (C.M. 1:4) Location : B3 Pune Default Date : Revised on Date : Unit : Jan 0, 00 14-08-06 per sqm

Providing & constructing 6" thk, brick masonry using 'Thoklas' bricks in C.M. 1:4, at all levels wherever required including raking out joints, scaffolding, curing etc,. All complete.

Sr.No. Particulars 1 Materials : a) Thokla Bricks (15cm thk.) b) Cement c) Sand

Quantity 48.00 0.26 0.04

Unit No Bags Cum

Rate per 4.00 245.00 1060.00

Amount 192.00 63.70 42.40

Labours : for Brick masonry works

1.00

Sqm

46.00

46.00

Centering & Shuttering Nil

Others Scaffolding / sand screening etc.

0.00

8.23

0.00

5 6 7 8

Tools & Plants Charges Water charges Electricity Charges Over head & Profit

2.00% 0.50% 0.00% 15.00%

on total (A) on total (A) on total (A) on total (B)

TOTAL (A)

344.10 6.88 1.72 0.00 352.70 52.91 405.61

TOTAL (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

406 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/MAS/IV/7 Description : P/F 10cm thk. Brick Wall (C.M. 1:4) Location : B4 Pune Default Date : Revised on Date : Unit : Jan 0, 00 14-08-06 per sqm

Providing & constructing bricks on edges or half brick masonry at all levels in 1:4 C.M. with 8 cm thick 1:2:4 p.c.c. patli using 2 Nos. of dia 6 mm at every one meter height, including scaffolding, curing, racking out joints to receive plaster etc. complete. If length of wall exceeds4 .25 m then 4"x4.5" x ht, concrete mullion with 10 mm diameter 4 No. reinforcement is to be provided as stiffner at every 2 meter. ( Concrete and reinforcement will be paid in items of Columns and reinforcement respectively)

Sr.No. Particulars 1 Materials : a) Bricks b) Cement c) Sand

Quantity 58.00 0.17 0.03

Unit No Bags Cum

Rate per 3.00 245.00 1060.00

Amount 174.00 41.65 26.50

Labours : for Brick masonry works

1.00

Sqm

41.50

41.50

Centering & Shuttering Nil Others Scaffolding / sand screening etc.

1.00

Sqm.

7.70

7.70

5 6 7 8

Tools & Plants Charges Water charges Electricity Charges Over head & Profit

2.00% 0.50% 0.00% 15.00%

on total (A) on total (A) on total (A) on total (B)

TOTAL (A)

291.35 5.83 1.46 0.00 298.63 44.80 343.43

TOTAL (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

343 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/MAS/IV/9 Description : Coursed rubble masonary Location : B1 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per cum

Providing & constructing coursed rubble masonry II sort in cement mortar 1:6 for foundation steps, platforms etc.at all required levels including curing, scaffolding if required, weepholes if required, including specials such as corners, quions, headers through stones etc. dewatering if required, raking out joints 10 mm deep etc. complete.

Sr.No. Particulars 1 Materials : a) Rubble b) Cement c) Sand

Quantity 1.25 1.75 0.31

Unit cum Bags cum

Rate per 500.00 245.00 1060.00

Amount 625.00 428.75 332.84

Labours : For coursed rubble masonary

1.00

cum

253.22

253.22

Centering & Shuttering Nil

Others Scaffolding & sand screening

1.00

Cum.

29.71

29.71

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

1669.53 33.39 8.35 0.00 1711.27 256.69 1967.96

Say Rs. Prepared by : Name : _________________________________

1,968 /- Per

per cum

Sign: ________________

Rate analysis Site: Computer Code No. : Item No. : FDAPL/MAS/IV/11 Description : 150mm thk. C.C. Solid block masonry Location : B5

Default Date : Revised on Date : Unit :

14-08-06 per sqm

Providing & constructing 150 mm thick solid concrete block masonry in C.M. 1:4 including cutting if required, curing, scafflolding, raking out joints etc. complete..

Sr.No. Particulars 1 Materials : a) Concrete blocks

Quantity 18.00

Unit No

Rate per 16.00

Amount 288.00

b) Cement c) Sand

0.15 0.04

Bags Cum

245.00 1060.00

36.02 42.40

Labours : for C.C.block masonry works

1.00

Sqm

8.23

8.23

Centering & Shuttering Nil Others Scaffolding / sand screening etc.

1.00

Job

8.23

8.23

TOTAL (A) 5 6 7 8 Tools & Plants Charges Water charges Electricity Charges Over head & Profit 2.00% 0.50% 0.00% 15.00% on total (A) on total (A) on total (A) TOTAL (B) on total (B) TOTAL

382.88 7.66 1.91 0.00 392.45 58.87 451.31

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/MAS/IV/12 Description : Location : B5

451 /- Per

per sqm

Sign: ________________

Pune Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

200mm thk. C.C. Solid block masonry

Providing & constructing 200 mm thick solid concrete block masonry in C.M. 1:4 including cutting if required, curing, scafflolding, raking out joints etc. complete..

Sr.No. Particulars 1 Materials : a) Concrete blocks b) Cement

Quantity 12.00 0.11

Unit No Bags

Rate per 34.00 245.00

Amount 408.00 26.95

c) Sand

0.05

Cum

1060.00

53.00

Labours : for C.C.block masonry works

1.00

Sqm

25.30

25.30

Centering & Shuttering Nil Others Scaffolding / sand screening etc.

1.00 0.00

Job

8.76 0.00

8.76 0.00

5 6 7 8

Tools & Plants Charges Water charges Electricity Charges Over head & Profit

2.00% 0.50% 0.00% 15.00%

on total (A) on total (A) on total (A) on total (B)

TOTAL (A)

522.01 10.44 2.61 0.00 535.06 80.26 615.32

TOTAL (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

615 /- Per

per sqm

Sign: ________________

Rate analysis Site: Computer Code No. : Item No. : 22 / Description : 100mm thk. Siporex block masonry Location : B5

Default Date : Revised on Date : Unit :

14-08-06 per sqm

Providing 100mm thk siporex blocks of size 0.1 x 0.1 x 0.2 with c.m. 1:6,in super structure including striking joints, taking out joints and scaffolding, curing etc. complete.

Sr.No. Particulars 1 Materials : a)Siporex blocks

Quantity 24.00

Unit No

Rate per 60.00

Amount 1440.00

b) Cement c) Sand

0.15 0.04

Bags Cum

245.00 1060.00

36.02 42.40

Labours : for 100mm Siporex block masonry works

1.00

Sqm

25.30

25.30

Centering & Shuttering Nil Others Scaffolding / sand screening etc.

1.00

Sqm

7.70

7.70

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

1551.42 31.03 7.76 0.00 1590.20 238.53 1828.73

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: #REF! Computer Code No. : Item No. : 22 / Description : Location : B5

1,829 /- Per

per sqm

Sign: ________________

#REF! Default Date : Revised on Date : Unit :

#REF! 14-08-06 per sqm

150mm thk. Siporex block masonry

Providing 150mm thk siporex blocks of size 0.15 x 0.15 x 0.3 with c.m. 1:6,in super structure including striking joints, taking out joints and scaffolding, curing etc. complete.

Sr.No. Particulars 1 Materials : a)Siporex blocks b) Cement c) Sand

Quantity 24.00 0.15 0.04 0.00 0.00 0.00

Unit No Bags Cum

Rate per 0.00 245.00 1060.00 0.00 0.00 0.00

Amount 0.00 36.02 42.40 0.00 0.00 0.00

Labours : for 100mm Siporex block masonry works

1.00

Sqm

28.06

28.06

Centering & Shuttering Nil

Others Scaffolding / sand screening etc.

1.00

Sqm

8.23

8.23

TOTAL (A) 5 6 7 8 Tools & Plants Charges Water charges Electricity Charges Over head & Profit 2.00% 0.50% 0.00% 15.00% on total (A) on total (A) on total (A) TOTAL (B) on total (B) TOTAL

114.71 2.29 0.57 0.00 117.57 17.64 135.21

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : 22 / III 7 Description : Location : B5

135 /- Per

per sqm

Sign: ________________

0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

200mm thk. Siporex block masonry

Providing 200mm thk Siporex blocks of size 0.2x0.2x0.4 with c.m. 1:6,in super structure including striking joints, taking out joints and scaffolding, curing etc. complete.

Sr.No. Particulars 1 Materials : a)Siporex blocks b) Cement c) Sand

Quantity 13.00 0.11 0.05

Unit No Bags Cum

Rate per 0.00 245.00 1060.00

Amount 0.00 26.95 53.00

Labours : for 100mm Siporex block masonry works

1.00

Sqm

28.06

28.06

Centering & Shuttering Nil

Others Scaffolding / sand screening etc.

1.00

Sqm

8.76

8.76

TOTAL (A) 5 6 7 8 Tools & Plants Charges Water charges Electricity Charges Over head & Profit 2.00% 0.50% 0.00% 15.00% on total (A) on total (A) on total (A) TOTAL (B) on total (B) TOTAL

116.77 2.34 0.58 0.00 119.69 17.95 137.64

Say Rs. Prepared by : Name : _________________________________

138 /- Per

per sqm

Sign: ________________

2.631579 #REF!

0.304 1.7024

0.304 0.0608 1.7024 0.391552 0.04864 0.051072

WELCOME TO RATE ANALYSIS


Enter the data in yellow cells.
a) Site Name : b) Default date : c) For MKS system click d) Tools & Plants & fixed Charges : e) Water Charges : f) Electricity Charges : g) PROFIT ( Over heads+ Profit) :
MKS

Location : Pune Revision on date :

For FPS system click 5.00% 1.00% 1.00% 10.00%


(Over head)

FPS

+ +

5.00%
( Profit )

= =

15.00%
(TOTAL)

Instructions Enter Data

Uneditable text Clickable links

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/PCC/II/3 Description : P.C.C. (1 :2:4 ) Location : C1 Pune Default Date : Revised on Date : Unit : Jan 0, 00 14-08-06 per cum

Providing & laying PCC 1:2:4 using metal 40 mm & 20 mm size in equal parts including, spreading, levelling, ramming, curing,formwork etc. all complete.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal (1.5") d) Metal ( 3/4)" 2 Labours : a)Mixing & Pouring b)Levelling & finishing c) Shuttering

Quantity 6.20 0.47 0.48 0.48

Unit Bags cum cum cum

Rate per 245.00 1060.00 575.00 500.00

Amount 1519.00 498.20 276.00 240.00

1.00 1.00 1.00

cum cum cum

120.00 7.50 57.50

120.00 7.50 57.50

Centering & Shuttering Providing good Specified material/ Errection & dismantling Others Mixer & Vibrator

1.00

cum

80.00

80.00

1.00

cum

25.00

25.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

2823.20 56.46 0.28 0.00 2879.95 431.99 3311.94

Say Rs.

3,312 /- Per

per cum

Prepared by : Name : _________________________________ Sign: ________________

Rate analysis
Site: 0 Computer Code No. : Item No. : FDAPL/PCC/II/1 Description : Location : C1 0 Default Date : Revised on Date : Unit : Jan 0, 00 14-08-06 per cum

P.C.C. (1 : 5 : 10 )

Providing & laying PCC 1:5:10 using metal 40 mm & 20 mm size in equal parts including, spreading, levelling, ramming, curing,formwork etc. all complete.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal (1.5") d) Metal ( 3/4)"

Quantity 2.74 0.49 0.48 0.48

Unit Bags cum cum cum

Rate per 245.00 1060.00 575.00 500.00

Amount 671.30 519.40 276.00 240.00

Labours : a)Mixing & Pouring b)Levelling & finishing c) Shuttering

1.00 1.00 1.00

cum cum cum

120.00 7.50 57.50

120.00 7.50 57.50

Centering & Shuttering Providing good Specified material/ Errection & dismantling Others Mixer & Vibrator

1.00

cum

80.00

80.00

1.00

cum

24.75

24.75

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B)

1996.45 39.93 0.20 0.00 2036.58 305.49

TOTAL

2342.07

Say Rs. Prepared by : Name : _________________________________

2,342 /- Per

per cum

Sign: ________________

Rate analysis
Site: 0 Computer Code No. : Item No. : FDAPL/PCC/II/2 Description : P.C.C. (1 : 4: 8 ) Location : C2 Pune Default Date : Revised on Date : Unit : Jan 0, 00 14-08-06 per cum

Providing & laying PCC 1:4:8 using metal 40 mm & 20 mm size in equal parts including, spreading, levelling, ramming, curing,formwork etc. all complete.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal (1") d) Metal ( 3/4)" 2 Labours : for a)Mixing & Pouring b)Levelling & finishing c) Shuttering

Quantity 3.40 0.48 0.48 0.48

Unit Bags cum cum cum

Rate per 245.00 1060.00 575.00 500.00

Amount 833.00 508.80 276.00 240.00

1.00 1.00 1.00

cum cum cum

120.00 7.50 57.50

120.00 7.50 57.50

Centering & Shuttering Providing good Specified material/ erection & dismantling Others Mixer & Vibrator

1.00

cum

80.00

80.00

4 1.00 cum 24.75 24.75

TOTAL (A)

2147.55

5 6 7

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.50% 0.50%

on total (A) on total (A) on total (A) TOTAL (B)

42.95 10.74 10.74 2211.98 331.80 2543.77

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

2,544 /- Per

per cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/PCC/II/6 Description : Location : C2 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per cum

Plum concrete with P.C.C. (1 : 4: 8 )

Providing and laying plum concrete of 1:4:8 mix using stone of size not more than 230 mm in size and proportion of plum to concrete @ 35:65 including curing, formwork if required, etc complete.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal (1.5") d) Metal ( 1)" e) Rubble 2 Labours : for a)Mixing & Pouring b)Levelling & finishing c) Shuttering Centering & Shuttering Providing good Specified material/ erection & dismantling Others

Quantity 2.21 0.31 0.31 0.31 0.46

Unit Bags cum cum cum cum

Rate per 240.00 1060.00 575.00 500.00 500.00

Amount 530.40 330.72 179.40 156.00 227.50

1.00 1.00 1.00

cum cum cum

275.00 7.50 57.50

275.00 7.50 57.50

1.00

cum

80.00

80.00

Mixer & Vibrator

1.00

cum

24.75

24.75

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

1868.77 37.38 9.34 9.34 1924.83 288.72 2213.56

Say Rs. Prepared by : Name : _________________________________

2,214 /- Per

per cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/1 Description : Location : C4 Pune Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per cum

C.C. M20 for Footing, raft

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For Footings, pedastals, raft,pilecaps.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" 2 Labours : a) Mixing & Pouring (concreting) b)Levelling & finishing c) Shuttering Centering & Shuttering

Quantity 7.77 0.45 0.60 0.25

Unit Bags cum cum cum

Rate per 210.00 850.00 500.00 340.00

Amount 1631.70 382.50 300.00 85.00

1.00 1.00 1.00

cum cum cum

107.20 16.50 86.25

107.20 16.50 86.25

Providing good Specified material for erection & dismantling 4 Others Mixer & Vibrator

1.00

cum

136.20

136.20

1.00

cum

24.75

24.75

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

2770.10 55.40 13.85 13.85 2853.20 427.98 3281.18

Say Rs. Prepared by : Name : _________________________________

3,281 /- Per

per cum

Sign: ________________

Rate analysis Site: Computer Code No. : Item No. : FDAPL/RCC/III/2 Description : Location : C6

Default Date : Revised on Date : Unit :

14-08-06 per cum

C.C. M20 for Columns below plinth

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For Columns upto plinth Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" Quantity 7.77 0.45 0.60 0.25 Unit Bags cum cum cum Rate per 245.00 1060.00 500.00 340.00 Amount 1903.65 477.00 300.00 85.00

Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering

1.00 1.00 1.00

cum cum cum

144.00 0.00 287.50

144.00 0.00 287.50

Centering & Shuttering Providing good Specified material/ Fixing & removing

1.00

cum

820.00

820.00

Others Mixer & Vibrator

1.00

cum

24.75

24.75

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

4041.90 80.84 20.21 20.21 4163.16 624.47 4787.63

Say Rs. Prepared by : Name : _________________________________

4,788 /- Per

per cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/3 Description : Location : C6 Pune Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per cum

C.C. M20 for superstructure Columns

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For Columns at all levels Sr.No. Particulars Quantity Unit Rate per Amount

Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering Centering & Shuttering Providing good Specified material/ erection & dismantling Others Mixer & Vibrator

7.77 0.45 0.60 0.25

Bags cum cum cum

245.00 1060.00 500.00 340.00

1903.65 477.00 300.00 85.00

1.00 1.00 1.00

cum cum cum

176.00 0.00 359.38

176.00 0.00 359.38

1.00

cum

1040.00

1040.00

1.00

cum

24.75

24.75

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

4365.78 87.32 21.83 21.83 4496.75 674.51 5171.26

Say Rs. Prepared by : Name : _________________________________

5,171 /- Per

per cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/5 Description : Location : C8 Pune Default Date : Revised on Date : Unit :

14-08-06 per cum

C.C. M20 for floor Beams

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For Floor beams

finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For Floor beams Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" 2 Labours : a) Mixing & Pouring (Concreting) b) Levelling & finishing c) Shuttering Centering & Shuttering Providing good Specified material/ Fixing & removing Others Mixer & Vibrator Lift Quantity 7.77 0.45 0.60 0.25 Unit Bags cum cum cum Rate per 245.00 1060.00 500.00 340.00 Amount 1903.65 477.00 300.00 85.00

1.00 1.00 1.00

cum cum cum

176.00 15.00 480.13

176.00 15.00 480.13

1.00

cum

992.25

992.25

1.00 1.00

cum cum

24.75 17.75

24.75 17.75

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

4471.53 89.43 22.36 22.36 4605.67 690.85 5296.52

Say Rs. Prepared by : Name : _________________________________

5,297 /- Per

per cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/9 Description : Location : C10 Pune Default Date : Revised on Date : Unit :

14-08-06 per cum

C.C. M20 for slab

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For Floor slabs Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" 2 Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering Quantity 6.80 0.45 0.60 0.25 Unit Bags cum cum cum Rate per 245.00 1060.00 500.00 340.00 Amount 1666.00 477.00 300.00 85.00

1.00 1.00 1.00

cum cum cum

160.00 15.00 310.50

160.00 15.00 310.50

Centering & Shuttering Providing good Specified material/ Fixing & removing Others Mixer & Vibrator Lift

1.00

cum

682.50

682.50

1.00 1.00

cum cum

24.75 17.75

24.75 17.75

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

3738.50 74.77 18.69 18.69 3850.66 577.60 4428.25

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Location : C11

4,428 /- Per

per cum

Sign: ________________

Pune Default Date :

Jan 0, 00

Item No. : FDAPL/RCC/III/19 Description :

Revised on Date : Unit : C.C. M20 for Staircase

14-08-06 per cum

Providing & casting M 200 for RCC staircase upto 17 cm riser 30 cm tread & 20 cm th waist slab but excluding parapet as per detailed drawing & design at all levels with all leads & lift or as directed including formwork, centering, scaffolding, machine mixing, & mixing , laying, levelling, vibrating and finishing rough and broken surfaces with C.M. 1:2 including curing etc. complete (excluding steel reinforcement) Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" 2 Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering Quantity 7.77 0.60 0.65 0.20 Unit Bags cum cum cum Rate per 245.00 1060.00 500.00 340.00 Amount 1903.65 636.00 325.00 68.00

1.00 1.00 1.00 0.00

cum cum cum

190.00 17.50 621.00 0.00

190.00 17.50 621.00 0.00

Centering & Shuttering Providing good Specified material/ Fixing & removing Others Mixer & Vibrator Lift

1.00

cum

800.00

800.00

1.00 1.00

cum cum

24.75 17.75

24.75 17.75

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

4603.65 92.07 23.02 0.00 4718.74 707.81 5426.55

Say Rs. Prepared by : Name : _________________________________

5,427 /- Per

per cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/17 Description : Location : Pune Default Date : Revised on Date : Unit : Jan 0, 00 14-08-06 per cum

RCC M20 for Pardi, fins

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For pardis,parapets and fins Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" 2 Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering Quantity 7.77 0.60 0.65 0.20 Unit Bags cum cum cum Rate per 245.00 1060.00 500.00 340.00 Amount 1903.65 636.00 325.00 68.00

Centering & Shuttering Providing good Specified material/ Fixing & removing Others Mixer & Vibrator Lifts

1.00 1.00 1.00 0.00 0.00 0.00 1.00

cum cum cum 0 cum

225.00 7.50 575.00 0.00 0.00 0.00 1520.00

225.00 7.50 575.00 0.00 0.00 0.00 1520.00

1.00 1.00

cum cum

24.75 17.75 TOTAL (A)

24.75 17.75 5302.65 106.05 26.51 26.51325 5461.73 819.26 6280.99

5 6 7

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.50% 0.50%

on total (A) on total (A) on total (A) TOTAL (B)

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by :

6,281 /- Per

per cum

Name : _________________________________

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/4 Description : Location : C8 0 Default Date : Revised on Date : Unit :

14-08-06 per cum

C.C. M20 for Plinth Beams

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For Plinth beams Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" 2 Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering Quantity 7.77 0.45 0.60 0.25 Unit Bags cum cum cum Rate per 245.00 1060.00 500.00 340.00 Amount 1903.65 477.00 300.00 85.00

1.00 1.00 1.00

cum cum cum

176.00 10.50 359.38

176.00 10.50 359.38

Centering & Shuttering Providing good Specified material/ erection & dismantling Others Mixer & Vibrator

1.00

cum

750.00

750.00

1.00

cum

24.75

24.75

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B)

4086.28 81.73 20.43 20.43 4208.86

Over head & Profit

15.00%

on total (B) TOTAL

631.33 4840.19

Say Rs. Prepared by : Name : _________________________________

4,840 /- Per

per cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/7&16 Description : Location : C8 0 Default Date : Revised on Date : Unit :

Jan 1, 00 per cum

C.C. M20 for lintels & chajjas

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For lintels & chajja Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" 2 Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering Quantity 7.77 0.45 0.60 0.25 Unit Bags cum cum cum Rate per 245.00 1060.00 500.00 340.00 Amount 1903.65 477.00 300.00 85.00

1.00 1.00 1.00

cum cum cum

240.00 10.50 575.00

240.00 10.50 575.00

Centering & Shuttering Providing good Specified material/ erection & dismantling Others Mixer & Vibrator Lift

1.00

cum

996.00

996.00

1.00 1.00

cum cum

24.75 17.75 TOTAL (A)

24.75 17.75 4629.65 92.59

Tools & Plants Charges

2.00%

on total (A)

6 7

Water charges Electricity Charges

0.50% 0.50%

on total (A) on total (A) TOTAL (B)

23.15 23.15 4768.54 715.28 5483.82

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

5,484 /- Per

per cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/6 Description : Location : C8 0 Default Date : Revised on Date : Unit :

14-08-06 per cum

C.C. M20 for grid Beams

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For Grid beams Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" 2 Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering Quantity 7.77 0.45 0.60 0.25 Unit Bags cum cum cum Rate per 245.00 1060.00 500.00 340.00 Amount 1903.65 477.00 300.00 85.00

1.00 1.00 1.00

cum cum cum

240.00 10.50 575.00

240.00 10.50 575.00

Centering & Shuttering Providing good Specified material/ Fixing & removing

1.00

cum

1344.00

1344.00

Others Mixer & Vibrator Lift

1.00 1.00

cum cum

24.75 17.75

24.75 17.75

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

4977.65 99.55 24.89 24.89 5126.98 769.05 5896.03

Say Rs. Prepared by : Name : _________________________________

5,896 /- Per

per cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/8 Description : Location : C8 0 Default Date : Revised on Date : Unit :

14-08-06 per cum

C.C. M20 for RCC walls

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For lift & Basement walls Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" 2 Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering Quantity 7.77 0.45 0.60 0.25 Unit Bags cum cum cum Rate per 245.00 1060.00 500.00 340.00 Amount 1903.65 477.00 300.00 85.00

1.00 1.00 1.00

cum cum cum

176.00 0.00 460.00

176.00 0.00 460.00

Centering & Shuttering Providing good Specified material/ Fixing & removing Others Mixer & Vibrator Lift

1.00

cum

776.00

776.00

1.00 1.00

cum cum

24.75 17.75 TOTAL (A)

24.75 17.75 4220.15 84.40 21.10 21.10 4346.75 652.01 4998.77

5 6 7

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.50% 0.50%

on total (A) on total (A) on total (A) TOTAL (B)

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

4,999 /- Per

per cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/15 Description : Location : C11 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per cum

M20 for folded Steps upto 150mm thk.

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For folded staircase slabs Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" Quantity 7.77 0.45 0.60 0.25 Unit Bags cum cum cum Rate per 245.00 1060.00 500.00 340.00 Amount 1903.65 477.00 300.00 85.00

Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering

1.00 1.00 1.00

cum cum cum

240.00 37.50 931.50

240.00 37.50 931.50

Centering & Shuttering Providing good Specified material/ Fixing & removing Others Mixer & Vibrator Lift

1.00

cum

1224.00

1224.00

1.00 1.00

cum cum

24.75 17.75 TOTAL (A)

24.75 17.75 5241.15 104.82 26.21 26.21 5398.38 809.76 6208.14

5 6 7

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.50% 0.50%

on total (A) on total (A) on total (A) TOTAL (B)

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

6,208 /- Per

per cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/28 Description : Location : C11 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 Rmt.

P/F PVC sleeves 40mm dia. in concrete

Providing & fixing in corrent position.line, level 40 mm dia Finolex or equivalent PVC pipe in RCC members such as columns, beams, slabs, paradi, chajjas etc. including fixing / typing with binding wire & M.S. rod to secure in position during concrete including all lifts etc. complete.

Sr.No. Particulars 1 Materials : a) PVC pipe b) Binding wire 2 Labours : a) Cutting & fixing sleeves

Quantity 1.00 0.20

Unit Rmt. Kg.

Rate per 51.75 40.00

Amount 51.75 8.00

1.00 0.00

Rmt.

55.90 0.00

55.90 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

115.65 2.31 0.00 0.00 117.96 17.69 135.66

Say Rs. Prepared by : Name : _________________________________

136 /- Per

Rmt.

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/12 Description : Location : C11 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per cum

M20 for sloping slabs

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For sloping slabs Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" Quantity 7.77 0.45 0.60 0.25 Unit Bags cum cum cum Rate per 245.00 1060.00 500.00 340.00 Amount 1903.65 477.00 300.00 85.00

Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering Centering & Shuttering Providing good Specified material/ Fixing & removing Others Mixer & Vibrator Lift

1.00 1.00 1.00

cum cum cum

200.00 19.50 412.97

200.00 19.50 412.97

1.00

cum

682.50

682.50

1.00 1.00

cum cum

24.75 17.75 TOTAL (A)

24.75 17.75 4123.12 82.46 20.62 20.62 4246.81 637.02 4883.83

5 6 7

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.50% 0.50%

on total (A) on total (A) on total (A) TOTAL (B)

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

4,884 /- Per

per cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/11 Description : Location : C11 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per cum

M20 for cantilever slabs upto 2.0m span

Providing & laying M 200 (as per design mix) for RCC work (without plaster) using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For cantilever slabs Sr.No. Particulars 1 Materials : a) Cement b) Sand Quantity 7.77 0.45 Unit Bags cum Rate per 245.00 1060.00 Amount 1903.65 477.00

c) Metal ( 3/4)" d) Metal ( 1/2)" 2 Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering

0.60 0.25

cum cum

500.00 340.00

300.00 85.00

1.00 1.00 1.00

cum cum cum

160.00 10.50 363.29

160.00 10.50 363.29

Centering & Shuttering Providing good Specified material/ Fixing & removing Others Mixer & Vibrator Lift

1.00

cum

892.50

892.50

1.00 1.00

cum cum

24.75 17.75

24.75 17.75

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

4234.44 84.69 21.17 21.17 4361.47 654.22 5015.69

Say Rs. Prepared by : Name : _________________________________

5,016 /- Per

per cum

Sign: ________________

Site:

0 Computer Code No. : Item No. : FDAPL/RCC/III/19 Description :

Rate analysis Location : 0 C11 Default Date : Revised on Date : Unit : M20 for Copings & sills

Jan 0, 00 14-08-06 per cum

Providing and laying in situ C.C. M-20 of trap metal for R.C.C.work of Copings & sills as per detailed drawings and design or as directed including centering formwork, compacting using vibrator, curing and roughening the surface if special finish is to be provided etc. complete. (excluding reinforcement & fitter work).

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" 2 Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering

Quantity 7.77 0.45 0.60 0.25

Unit Bags cum cum cum

Rate per 245.00 1060.00 500.00 340.00

Amount 1903.65 477.00 300.00 85.00

1.00 1.00 1.00

cum cum cum

212.80 66.00 621.00

212.80 66.00 621.00

Centering & Shuttering Providing good Specified material/ Fixing & removing Others Mixer & Vibrator Lift

1.00

cum

1220.00

1220.00

1.00 1.00

cum cum

24.75 17.75

24.75 17.75

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

4927.95 98.56 24.64 24.64 5075.79 761.37 5837.16

Say Rs. Prepared by : Name : _________________________________

5,837 /- Per

per cum

Sign: ________________

E/O for providing M25 grade concrete instead of M20 grade Cement consumption for M20 grade = 7.77 bags Cement consumption for M25 grade = 7.77 bags Difference in cement consumption = Basic rate difference = x 150 = Total rate difference including OH/profit etc. = Say Rs. = E/O for providing M30 grade concrete instead of M20 grade Cement consumption for M20 grade = 7.77 bags

Cement consumption for M25 grade = 7.77 bags Difference in cement consumption = Basic rate difference = x 150 = Total rate difference including OH/profit etc. = Say Rs. = E/O for providing M35 grade concrete instead of M20 grade Cement consumption for M20 grade = 7.77 bags Cement consumption for M25 grade = 7.77 bags Difference in cement consumption = Basic rate difference = x 150 = Total rate difference including OH/profit etc. = Say Rs. = E/O for providing M40 grade concrete instead of M20 grade Cement consumption for M20 grade = 7.77 bags Cement consumption for M25 grade = 7.77 bags Difference in cement consumption = Basic rate difference = x 150 = Total rate difference including OH/profit etc. = Say Rs. =

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/29 Description : Location : C11 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 Rmt.

Welding of bars to existing reinforcement

Welding the reinforcement bars to existing steel or as per the requirement including finishing the welding work neatly, all labour and material etc complete. Sr.No. Particulars 1 Materials : a) Welding rods For one Rmt. Of welding (Assuming that average 6 nos of 16mm dia. Bars are welded for one end of beam) Welding rods used are of 4mm & ESAB / Advani make 2 Labours : a)Welder b)Helper One welder can do about 30rmt. Of welding Quantity 5.00 Unit No. Rate per 2.34 Amount 11.70

0.03 0.03

No. No.

150.00 100.00

4.50 3.00

Scaffolding If required for welding at heights Assuming the area of scaffolding to be 1.2m x1.2m

15.49

Sft.

0.75

11.62

Others Hire charges of welding machine Assuming the hire charges rate of 250 /-for 8 hrs.

0.25

Hr.

31.25

7.81

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 10.00% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

38.63 0.77 0.00 3.86 43.27 6.49 49.76

Say Rs. Prepared by : Name : _________________________________

50 /- Per

Rmt.

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/30 Description : Location : C11 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Providing shalitex board expansion joint

Providing & fixing shalitex board expansion joint of 25mm thickness for beams, columns & slab

Sr.No. Particulars 1 Materials : a) Shalitex board

Quantity 1.00

Unit Sqm.

Rate per 800.00

Amount 800.00

Add for wastage @ 5%

0.05

Sqm.

800.00

40.00

Labours : a)carpenter b)Helper One pair of carp/helper can do about 2 columns as given below. Assuming the size of column to be 450x230 & joint on 450mm face, Ht. Of col.of about 3m. Area = 3 x 0.45 = 1.35 sqm.

0.37 0.37

No. No.

150.00 100.00

55.50 37.00

Others

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

932.50 18.65 0.00 4.66 955.81 143.37 1099.18

Say Rs. Prepared by : Name : _________________________________

1,099 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/9 Description : Location : C10 0 Default Date : Revised on Date : Unit :

14-08-06 per cum

C.C. M20 for precast slab of 50 mm thick slab

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" 2 Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering

Quantity 0.10 0.03 0.04 0.02

Unit Bags cum cum cum

Rate per 215.00 850.00 425.00 450.00

Amount 21.50 25.50 17.85 7.88

0.07 0.07 0.07

cum cum cum

212.00 66.00 621.00

14.84 4.62 43.47

Centering & Shuttering Providing good Specified material/ Fixing & removing Others Mixer & Vibrator Lift

0.07

cum

1220.00

85.40

1.00 1.00

cum cum

24.75 17.75

24.75 17.75

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges -3.00% -0.50% -0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 0.00% on total (B) TOTAL

263.56 -7.91 -1.32 -1.32 253.01 0.00 253.01

Say Rs. Prepared by : Name : _________________________________

253 /- Per

per cum

OR Rs 15/ sqm Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/8 Location : C8 0 Default Date : Revised on Date : Unit :

14-08-06 per cum

Description :

C.C. M50 for RCC walls

Providing & laying M 50 (as per design mix) for RCC work (without plaster) using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For lift & Basement walls

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" 2 Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering Centering & Shuttering Providing good Specified material/ Fixing & removing Others Mixer & Vibrator Lift

Quantity 9.65 0.85 0.70 0.50

Unit Bags cum cum cum

Rate per 210.00 1060.00 550.00 550.00

Amount 2026.50 901.00 385.00 275.00

1.00 1.00 1.00

cum cum cum

185.00 0.00 486.00

185.00 0.00 486.00

1.00

cum

776.00

776.00

1.00 1.00

cum cum

24.75 17.75 TOTAL (A)

24.75 17.75 5077.00 -152.31 -25.39 -25.39 4873.92 731.09 5605.01

5 6 7

Tools & Plants Charges Water charges Electricity Charges

-3.00% -0.50% -0.50%

on total (A) on total (A) on total (A) TOTAL (B)

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

5,605 /- Per

per cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/8 Description : Location : C8 0 Default Date : Revised on Date : Unit :

14-08-06 per cum

C.C. M30 for Concrete Road

Providing & laying M 30 (as per design mix) for Road work using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" 2 Labours : a) Mixing & Pouring (Concreting) b)Levelling & finishing c) Shuttering Centering & Shuttering Providing good Specified material/ Fixing & removing Others Mixer & Vibrator Lift

Quantity 7.50 0.85 0.70 0.50

Unit Bags cum cum cum

Rate per 210.00 1060.00 550.00 550.00

Amount 1575.00 901.00 385.00 275.00

1.00 1.00 1.00

cum cum cum

185.00 0.00 150.00

185.00 0.00 150.00

1.00

cum

365.00

365.00

1.00 1.00

cum cum

24.75 17.75 TOTAL (A)

24.75 17.75 3878.50 -116.36 -19.39 -19.39 3723.36 558.50 4281.86

5 6 7

Tools & Plants Charges Water charges Electricity Charges

-3.00% -0.50% -0.50%

on total (A) on total (A) on total (A) TOTAL (B)

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs.

4,282 /- Per

per cum

Prepared by : Name : _________________________________ Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/2 Description : Location : C4 0 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per cum

C.C. M30 for Footing, raft

Providing & laying M 300 (as per design mix) for RCC work (without plaster) using machine crushed metal of approved quality and grading, of size 20 mm to 12 mm in required proportions at all lead & lift including centering formwork, scaffolding, machine mixing, laying, levelling, vibrating curing etc, finishing rough broken surfaces with 1:2 c.m. etc. as per drawings and design etc. complete (excluding mild steel/tor steel reinforcement) .---For Footings, pedastals, raft,pilecaps.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Metal ( 3/4)" d) Metal ( 1/2)" 2 Labours : a) Mixing & Pouring (concreting) b)Levelling & finishing c) Shuttering Centering & Shuttering Providing good Specified material for erection & dismantling Others Mixer & Vibrator

Quantity 8.50 0.45 0.60 0.25

Unit Bags cum cum cum

Rate per 210.00 850.00 500.00 550.00

Amount 1785.00 382.50 300.00 137.50

1.00 1.00 1.00

cum cum cum

107.20 16.50 86.25

107.20 16.50 86.25

1.00

cum

136.20

136.20

1.00

cum

24.75

24.75

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

2975.90 59.52 14.88 14.88 3065.18 459.78 3524.95

Say Rs. Prepared by : Name : _________________________________

3,525 /- Per

per cum

Sign: ________________

2.21 0.312 0.624 0.312 0.455

0.276364 7.738182 7.970327

16.5 86.25

250 31.25 0.792 24.8 36 3.217503 2.284427 79.6332 56.53958 637.0656 452.3166 19749.03 0.309375 24.75 17.775 Assign 0.3 hrs

176 15 480.13

992.25

1165.5 254.25 270 100

160 15 310.5

682.5

24.75 17.75

3000.25 150.01 30.0025 30.0025 3210.27 481.5401 3691.81 0.833694

18.75 12.5

Rate analysis
Site: 0 Computer Code No. : Item No. : Description : Location : Pune Default Date : Revised on Date
Unit :

Jan 0, 00

Sr.No. Particulars 1 Materials :

Quantity 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Unit

Rate per 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Amount 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00

2 Labours :

3 Centering & Shuttering

4 Others

TOTAL (A)
4 Tools & Plants Charges 5 Water charges 6 Electricity Charges 5.00% 1.00% 1.00% on total (A) on total (A) on total (A)

TOTAL (B)
7 Over head & Profit 15.00% on total (B)

TOTAL Say Rs.


Prepared by : Name : _________________________________

0 /-

Per

Sign: ________________

Assumptions Tools and plants fixed charges Eleciticity Charges Water Charges Profit ( Overheads + Profit )

3% 0.50% 0.50% 15%

Summary of Rateanalysis (MKS system)


Default date : Revision Date : Item. No.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42

Description

01.03.06 09.12.06 Rate in Unit Rs.


90.02 106.61 289.25 777.03 192.72 63.96 248.75 1272.15 42.85 68.03 353.66 3311.94 2342.07 2543.77 2213.56 3281.18 4787.63 5171.26 5296.52 4428.25 5426.55 6280.99 4840.19 5483.82 5896.03 4998.77 6208.14 4883.83 5015.69 5837.16 135.66 49.76 1099.18 262.79 163.15 210.23 176.15 530.85 306.19 513.94 390.33 663.62

Excavation in soil and soft murum upto 1.5m depth per cum Excavation in Hard Murum & boulders per cum Excavation in Soft Rock per cum Excavation in Hard Rock by chiselling per cum Soling 230 thk below floor per Sqm Filling with selected murum obtained from excavation per Cum Filling with outside murum per Cum Fillind with sand per Cum Antitrmite treatment per Sqm Carting away surplus xcavated work per Cum Excavation in hard rock by blasting per cum P.C.C. (1 :2:4 ) per cum P.C.C.(1: 5: 10 ) per cum P.C.C. (1 : 4: 8 ) per cum P.C.C.(1 :4: 8 ) Plum Concrete per cum C.C. M20 for Footing, raft per cum C.C. M20 for column below plinth per cum C.C. M20 for superstructure Columns per cum C.C. M20 for floor Beams per cum C.C. M20 for slab per cum C.C. M20 for Staircase per cum RCC M20 for Pardi, fins per cum C.C.M20 for plith Beam per cum C.C.M20 for lintels & Chajja per cum C.C.M20 for Grid Beam per cum C.C.M20 for RCC walls per cum M20 for folded Steps upto 150mm thk. per cum M20 for sloping slabs per cum M20 for cantilever slabs upto 2.0m span per cum M20 for Copings & sills per cum P/F PVC sleeves 40mm dia. in concrete Rmt. Welding of bars to existing reinforcement Rmt. Providing shalitex board expansion joint per sqm Ac trafford 6mm thk.sheets per Sqm. Ac 6mm thk.ridges per Rmt. Ac trafford 6mm thk.sheets cladding per Sqm. Ac gutter per Rmt. MS precoated sheets per Sqm. MS precoated ridges per Rmt. MS precoated .55mm thk.sheets cladding per Sqm. MS precoated gutter per Rmt. Alluminium sheets per Sqm.

Default date :
43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99

=Rateanalysis!B11

01.03.06
per Rmt. per Sqm. per Rmt. per Sqm. per Rmt. per Sqm. per Rmt. per Sqm. per cum per cum per cum per cum per cum per cum per sqm per sqm per cum per sqm per sqm per sqm per sqm per sqm per sqm per sqm per sqm per sqm per sqm per sqm per sqm per sqm per sqm per sqm per sqm per sqm per sqm per rmt per rmt per rmt per rmt per sqm per sqm per sqm per Rmt. per sqm per Rmt. per sqm per Rmt per sqm per Rmt. per sqm per sqm per sqm per sqm per Rmt per sqm per sqm per Rmt. 374.26 676.40 497.21 674.18 263.96 686.59 413.90 1949.83 1984.99 2020.34 2335.22 2438.95 2085.80 2151.57 405.61 343.43 1967.96 451.31 615.32 1828.73 135.21 137.64 136.15 166.52 111.94 135.99 268.20 63.90 89.84 0.00 93.98 334.03 446.20 468.71 625.65 69.47 80.66 87.06 105.72 173.66 690.21 1462.74 153.85 606.28 68.94 590.30 63.21 2438.35 268.72 285.58 358.07 674.99 725.03 71.20 1188.05 1262.44 1225.37

Alluminium ridges Alluminium sheets cladding Alluminium gutter FRP sheets FRP ridges FRP sheets cladding FRP gutter Polycarbonate sheets UCR In plinth Uncoursed rubble masonry in superstructure Brick masonary 35cm thk. Below plinth Brick work 35cm thk. In superstructure Plinth Masonry 23cm thk BBM 23cm thk in superstructure P/F 15cm thk. Brick Wall (C.M. 1:4) P/F 10cm thk. Brick Wall (C.M. 1:4) Coursed rubble masonary 150mm thk. C.C. Solid block masonry 200mm thk. C.C. Solid block masonry 100mm thk. Siporex block masonry 150mm thk. Siporex block masonry 200mm thk. Siporex block masonry Ext. Plaster single coat mortor ratio (1:5) External Plastering Double coat Internal Neeru Plaster CM (1:4)-12mm thk. Internal Neeru Plaster CM (1:4) - 20mm thk. Waterproof plaster Pointing to brick masonary Pointing to Stone masonary P/A POP plaster to walls Back coat for dado work 1:4) Grey Mosaic Tile Flooring of 25cm x 25cm Grey Mosaic Tile Flooring of 30x30 White Mosaic Tile Flooring of 25x25 White Mosaic Tile Flooring of 30 x 30 Grey Mosaic Tile Skirting of 125 mm ht. Grey Mosaic Tile Skirting of 150 mm ht. White Mosaic Tile Skirting of 125 mm ht. White Mosaic Tile Skirting of 150 mm ht. P/L IPS 50mm thk. Ceramic Tile Flooring Marble Flooring Marble Skirting Kota Flooring Kota Skirting Tandoor Flooring Tandoor Skirting Granite Flooring Granite Skirting Rough Shahabad flooring Polished Shahabad flooring Ceramic tiles flooring Ceramic tiles Dado Ceramic tiles Skirting Vitrified tiles flooring Vitrified tiles Dado Vitrified tiles Skirting

Default date :
100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145

=Rateanalysis!B11

01.03.06
per sqm 707.57 per sqm 399.42 per sqm 578.39 per sqm 307.84 per Rmt 162.61 per sqm 653.57 per sqm 1395.58 per sqm 2681.12 per sqm 609.21 Rmt. 5005.23 Rmt. 3388.21 Rmt. 1800.22 per sqm 604.85 per Cum 2818.39 per sqm 344.17 per sqm 4.71 per sqm 19.39 per sqm 35.59 per sqm 46.26 per sqm 66.92 per sqm 36.19 per sqm 70.77 per sqm 91.34 per sqm 71.68 per sqm 327.32 Rmt. 468.23 Rmt. 934.46 Rmt. 579.47 Sqmt. 1097.63 Sqmt. 1138.66 Sqmt. 1284.05 Sqmt. 432.01 Door. 135.56 Door. 268.17 Door. 268.17 Door. 268.17 Door. 70.73 Door. 70.73 Door. 35.36 Sqm. 1018.76 Sqm. 797.86 Sqm. 1274.64 MT 45499.46 per Sqm. 43578.09 per No. 31.75 per Sqm. 259.20

Designer tiles flooring Paving blocks flooring (regular) Paving blocks heavy duty (M40 & above) Chequered tiles flooring Marble for steps Kota for sill & Jams Marble for Sills & jams Granite for sills & Jams Tandoor for sills & jams Granite Kitchen otta Marble Kitchen otta Kadappa Kitchen otta Box type W/P to RCC raft, walls Brickbat water proofing for toilets Brickbat water proofing for terrace White wash Dry distemper Oil bound distemper Synthetic enamel paint Lustre paint Cement paint Sandtex paint Antifungal paint Plastic emulsion paint Chemical w/p for terrace, toilets Providing & fixing TW frame (4"x 2.5") P/F Granite frame (170x20) P/F Marble frame (170x20) P/F flush shutter 35mm P/F flush shutter 35mm (internal door) P/F flush shutter 35mm (internal door) P/F Laminate of appr. shade & colour P/F MS powder coated fittings P/F Alluminium fittings P/F stainless steel fittings P/F Brass fittings P/F Night latch P/F Automatic door closer P/F eye piece P/F MS powder coated grills & railing P/F MS grills & railing with enamel paint P/F MS Z section windows Reinforcement works Structural steel works 12mm dia. Fan hook Chainlink fencing

Standard rate of materials considered for rate analysis


Sr. No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 List of Materials Per Unit Rate (inRs.) 245.00 28000.00 40.00 1060.00 500.00 340.00 575.00 2.25 4.00 3.00 34.00 16.00 Rate (inRs.) Remarks

Cement Per Bag Reinforcement steel CTD Per MT Binding wire Per Kg Sand Per cum Metal (18 to 20)mm Per cum Metal (12mm) Per cum Metal (25mm) Per cum Bricks (230mm) Per No Bricks (150mm) Per No Bricks (100mm) Per No Concrete Blocks (20x20x40)cm Per No Concrete Blocks (15x15x30)cm Per No (M15 grade @ 2200/-) Siporex blocks (10x10x20) cm Per No Siporex blocks (15x15x30) cm Per No Siporex blocks (20x20x40) cm Per No Brick Bats Per cum Rubble Per cum Murum Per cum Neeru Per Bag Lime Per Bag White cement Per Kg. M.M. Tile (White) 25cm X 25cm Per sqm M.M. Tile (White) 25cm X 12cm Per rmt M.M. Tile (White) 30cm X 30cm Per sqm M.M. Tile (White) 30cm X 15cm Per rmt M.M. Tile (Grey) 25cm X 25cm Per sqm M.M. Tile (Grey) 25cm X 12cm Per rmt M.M. Tile (Grey) 30cm X 30cm Per sqm M.M. Tile (Grey) 30cm X 15cm Per rmt Marble Per sqm Tandoor Per sqm Granite Per sqm Rough Shahabad Per sqm Polished Shahabad Per sqm Ceramic tiles(30cm X 30cm)colour Per sqm Glazed Tiles (15cm X 15cm) White Per sqm Vitrified rough tiles Per sqm Vitrified polished tiles Per sqm Designer tiles(25mm) Per sqm Paver blocks (regular) 60mm Per sqm Paver blocks (heavy duty) Per sqm Chequered tiles Per sqm Kota steps Per sqm Marble steps Per sqm Granite steps Per sqm Tandoor steps Per sqm Kaddappa one side polish (40mm) Per sqm Shahabad stone 25mm Per sqm Broken glazed tiles Per Kg. Water proofing Compound Per Kg. Shalitex board 25mm Per sqm Kotah stone cut to size Sqm Sub frame Per Kg. Main frame Per Kg. Shutter members Per Kg. a) Beadings Per Kg. b) Glass Per sqm Page 226 of 332

53 grade O.P.Cem

18 gauge binding w

250.00 500.00 120.00 50.00 55.00 30.00 244.00 30.00 350.00 45.00 150.00 23.00 220.00 32.00 860.00 291.00 1695.00 75.00 110.00 380.00 400.00 800.00 800.00 430.40 242.10 386.00 102.00 377.68 1032.00 2118.75 378.30 220.00 82.50 10.00 40.00 800 290.52

each bag of 25k each bag of 30k

Sr. No. 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116

List of Materials c) Gasket,wool piles d) Concealed lock PVC Pipe Chlordane 20% emulsion Blasting powder Safety fuse Detonating fuse Detonator Teak wood frame 4"x2.5" MS Holdfast Coal tar Flush shutter 35mm (90/- per sft.) Brass hinges 75mm Brass hinges 100mm Brass hinges 125mm Brass screws25mm Brass screws25mm Laminate 1mm Fevicol MS tubular Nails MS Z sections (1.5 kg @ 30) 10mm sq. bars (.785 x 30) 4mm float glass Lime Ultramarine blue Glue Sodium chloride Distemper Whitning Primer Putty Oil bound distemper Synthetic enamel Luster paint Cement paint Sandtex paint Antifungal paint Plastic emulsion AC trafford 6mm thk. Bitminous washers 3mm GI flat washers 2mm GI - 6mm J hooks AC -ridges pair AC Gutter MS precoated sheets MS precoated -ridges (0.6m width ) MS precoated Gutter Alluminium sheets Alluminium -ridges (0.6m width ) Alluminium Gutter Structural steel FRP FRP -ridges (0.6m width ) FRP gutter Chain link Polycarbonate sheets

Per Unit Per m. Per No Ltr. kg. Rmt Rmt No Cft. No. Kg. Sqm. No No No No No. sqm. Kg. Kg. Kg. Rmt. Rmt. Sqm. Kg. Kg. Kg. Kg. Kg. kg. Lts Kg. Kg. Ltr. Ltr. Kg. Kg. kg. ltr. Sqm. Kg. Kg. No. Rmt. Rmt. Sqm. Rmt. Rmt. Sqm. Rmt. Rmt. Mt. Sqm. Rmt. Rmt. sqm. sqm.

Rate (inRs.)

Rate (inRs.)

Remarks

51.75 66.15 78.75 4.725 6.5 8 1200 10 25 968 20 26 35 1.5 2 310 250 32 30 45 23.55 325 1.5 114.98 48.825 10 67 20 60.9 40.95 90.00 141.75 218.75 49.35 86.3625 123.375 205.15 149.1 32 47.25 6.3 94.5 105 319 181.5 216.15 415.8 236.5 302.5 30500 423.5 154 209 156 1400

Click on the button for Labour rates Page 227 of 332

Labour Rate

Remarks 53 grade O.P.Cement 18 gauge binding wire

each bag of 25kg. each bag of 30kg.

Page 228 of 332

Remarks

Page 229 of 332

Standard rate of Labour considered for rate analysis Revised on Date : 14-08-06
Sr.No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 36 37 37 38 38 39 39 40 40 41 Description Unskilled coolie (Male) Unskilled coolie (Female) Beldar mazdoor Breaker Operator Helper for Breaker operator Rent for Pneumatic Breaker Needle (8 hr.) Machinaries on Hire basis Mixer Lift Vibrator Mixing & pouring for P.C.C. footing M15 grade footing M20 grade Columns M15 grade Beams M15 grade Slabs M15 grade Columns M20 grade Beams M20 grade Slabs M20 grade Staircase Pardi works Levelling & finishing for P.C.C. footing Columns Beams Slabs Staircase Pardi works Only Labour rate for Shuttering works P.C.C. Footing Columns Beams Slabs Staircase Pardi works (15cm thk.) Masonry & Plaster works U.C.R. masonry works in plinth U.C.R. masonry for c.wall pillars etc. BBM 350thk. below plinth 23cm B.B.Masonry works 15cm Tokla Brick Masonry works 10cm B.B.Masonry works 15cm C.C.Block Masonry works External plastering single coat External plastering double coat External plastering (Scaffolding Charges) Internal plastering Internal platering (Scaffolding Charges) Tile Fixing / Polisher Unit per day per day per day per day per day per day Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per sqm Per sqm Per sqm Per sqm Per sqm Per sqm Per sqm Per sqm Per sqm Per sqm Per rmt Per sqm Rate 100.00 75.00 80.00 120.00 80.00 1040.00 Remarks

17.75 Rate is derived from average 17.75 out put of machine (cft) per 7.00 day 120.00 107.20 107.20 176.00 176.00 150.00 176.00 176.00 160.00 190.00 225.00 7.50 16.50 0.00 15.00 15.00 17.50 7.50 57.50 86.25 359.38 480.13 310.50 621.00 575.00 165.00 252.00 164.00 33.48 40.00 41.50 25.30 45.00 47.60 6.64 36.00 4.00 32.00 10.00 75.00

42 Mosaic Tile fixing 43 Mosaic Tile Skirting fixing 43 Ceramic Tile fixing

Revised on Date :
Sr.No. 44 44 45 45 46 46 47 47 48 48 49 49 50 50 51 51 52 52 53 53 54 54 55 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 Description Marble Flooring Ceramic /Glazed dado Tile fixing Mosaic Tile polishing (3 coats) Mosaic Tile Skirting polishing Marble floor Polishing (regular) Marble skirting polishing Marble skirting fixing Kota floor fixing & polishing Kota skirting fixing & polishing Tandoor floor fixing & polishing Tandoor skirting fixing & polishing Rough shahabad Polished shahabad Vitrified tiles flooring Vitrified tiles Dado Granite floor fixing Granite skirting fixing Kota Steps fixing Marble Steps fixing Granite Steps fixing Tandoor steps Kota sill & jams fixing Marble sill & jams fixing Granite sill & jams fixing Tandoor sill & jams Water proofing Works for Box type Toilets / Bathroom (for 200mm sunk) Terrace (roof) Chemical waterproofing Shuttering material charges for P.C.C. works for footing for columns for beams for slabs for Staircase for pardi Reinforcement Works KOTAH STONE Polishing of kotah stone Door frame charges Frame making Powder coating (at 15/- per sft) Enamel painting including red oxide AC sheets fixing MS precoated sheets fixing FRP sheets Alluminium sheets fixing Unit Per sqm Per sqm Per sqm Per rmt Per Sqm Per Sqm Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per Sqm. Per sqm Per sqm Per sqm Per sqm Per cum Per cum Per cum Per cum Per cum Per cum Per cum Per MT Per Sqm Per Sqm Rate 100.00 90.00 20.00 9.00 129.00 148.35 110.00 100.00 110.00 86.00 94.60 65.00 80.00 80.00 96.00 172.00 215.00 130.00 167.70 223.60 111.80 132.00 132.00 258.00 113.52 325.00 170.00 125.00 130.00 80.00 136.20 1040.00 992.25 682.50 800.00 1520.00 2000.00 100.00 60.00

14-08-06
Remarks

Per Sqm Per sqm. Per sqm. Per sqm. Per sqm. Per sqm.

161.40 35.00 35.00 72.80 72.80 72.80

Click on the button for entering into "ITEM LIST FOR SELECTION"

Item List

WELCOME TO ITEM SELECTION SHEET


Sr. No. 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 Computer code Blank format Earth work Earth work Earth work Earth work Earth work Concreting Concreting Concreting Concreting Concreting Concreting Concreting Concreting Concreting Concreting Masonry Masonry Masonry Masonry Masonry Plastering Plastering Plastering Plastering Flooring Flooring Flooring Flooring Dado W/P W/P W/P Re ITEMS Earth work in ordinary soil Earth work in Shadu Earth work in Murum Earth work in Soft Rock Earth work in Hard Rock P.C.C. (1:3:6) P.C.C. (1:4:8) C.C. M15 for footing C.C. M20 for footing C.C. M15 for columns C.C. M20 for columns C.C. M15 for Beams C.C. M20 for Beams C.C. M15 for Slabs C.C. M20 for Slabs U.C.R. Masonry 15" thk. B.B.Masonry 9" thk. B.B.Masonry 6" thk. B.B.Masonry 4" thk. C.C. Block masonry 6" thk. External Plastering Single coat External Plastering Double coat Internal Plastering with C.M.1:4 Internal Plastering with C.M.1:5 Mosaic Tile flooring Mosaic Tile Skirting Ceramic Tile flooring Marble Flooring Ceramic /Glazed tile Dado Brickbat waterproofing for Toilet Brickbat waterproofing for Terrace Glazed china mosaic w/p for terrace Reinforcement works Summary of rate analysis Selection button _1 E1 E2 E3 E4 E5 C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 B1 B2 B3 B4 B5 P1 P2 P3 P4 F1 F2 F3 F4 D1 W/P1 W/P2 W/P3 R1 SR

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/EX/I/1 Description : Location : Pune Default Date : Revised on Date : Unit :

14-08-06 per cum

Excavation in soil and soft murum upto 1.5m depth

Excavation upto 1.5 M depth in ordinary soil or soft murum, old foundations etc. in pits, over areas and in trenches by machinery or otherwise including removing the excavated materials upto a distance of 100 M beyond building premises, stacking as directed dewatering manually or mechanically if required, shoring, strutting, preparing the bed for foundation and necessary back filling in layers including dry and wet compaction etc. complete. Sr.No. Particulars 1 Materials : Quantity Unit Rate per Amount

Labours : a) Unskilled coolie for excn. b) Labour for backfilling Assuming that one pair to do excavation of 125 cft.

0.56 0.08

No No

100.00 100.00

56.00 8.00

Centering & Shuttering NIL Others Shoring Dewatering

1.00 1.00

L/S L/s

10.00 2.00 TOTAL (A)

10.00 2.00 76.00 1.52 0.38 0.38 78.28 11.74 90.02

5 6 7 8

Tools & Plants Charges Water charges Electricity Charges Over head & Profit

2.00% 0.50% 0.50% 15.00%

on total (A) on total (A) on total (A) TOTAL (B) on total (B) TOTAL

Say Rs.

90 /- Per

per cum

Prepared by : Name : _________________________________ Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/EX/I/3 Location : Pune Default Date : E3 Revised on Date : Unit : Excavation in Hard Murum & boulders

Jan 0, 00 14-08-06 per cum

Description :

Excavation upto 1.5 M depth in hard murum & boulders etc. in pits, over areas and in trenches by machinery or otherwise including removing the excavated materials upto a distance of 100 M beyond building premises, stacking as directed dewatering manually or mechanically if required, shoring, strutting, preparing the bed for foundation and necessary back filling in layers including dry and wet compaction etc. complete.

Sr.No. Particulars 1 Materials : NIL 2 Labours : a) Unskilled coolie (Male) ( It is assumed that 1 m/c + 1 f/c can excavate nearly 100cft of murum in a day with specified lead and lift) c) Add for backfilling & compaction

Quantity

Unit

Rate per

Amount

0.70

No

100.00

70.00

0.08

No

100.00

8.00

Centering & Shuttering NIL

Others Shoring Dewatering

1.00 1.00

L/S L/s

10.00 2.00

10.00 2.00

TOTAL (A) 5 Tools & Plants Charges 2.00% on total (A)

90.00 1.80

6 7

Water charges Electricity Charges

0.50% 0.50%

on total (A) on total (A) TOTAL (B)

0.45 0.45 92.70 13.91 106.61

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

107 /- Per

per cum

Sign: ________________

Site:

0 Computer Code No. : Item No. : FDAPL/EX/I/5 Description :

Rate analysis Location : Pune Default Date : E4 Revised on Date : Unit : Excavation in Soft Rock

Jan 0, 00 14-08-06 per cum

Excavation upto 1.5 M depth in soft rock in pits and trenches by machinery or otherwise including removing the excavated materials upto a distance of 100 M beyond building premises,stacking as directed dewatering manually or mechanically if required, shoring, strutting, preparing the bed for foundation and necessary back filling in layers including dry and wet compaction etc. complete. Sr.No. Particulars 1 Materials : Nil 2 Labours : a) 1 Breaker Needle with breaker operator ( It is assumed that with a breaker needle in a day we can excavate nearly 200cft and the same with lead & lift as specified.) i.e. For 1 cum. It requires 0.18 days of breaker b) Unskilled coolie 2 nos. (Male) For 150 cft ( 4.25cum) 2 persons are required, therefore for one cum 0.71 person is required Labour for backfilling 3 Centering & Shuttering NIL Quantity Unit Rate per Amount

0.18

Per day

1040.00

187.20

0.47

No

100.00

47.00

0.08

No

100.00

8.00

Others Dewatering

1.00

L/s

2.00

2.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL Say Rs. Prepared by : Name : _________________________________ Sign: ________________ 289 /- Per per cum

244.20 4.88 1.22 1.22 251.53 37.73 289.25

Site:

0 Computer Code No. : Item No. : FDAPL/EX/I/8

Rate analysis Location : Pune Default Date : E5 Revised on Date : Unit :

Jan 0, 00 14-08-06 per cum

Description : Excavation in Hard Rock by chiselling Excavation upto 1.5 M depth in hard rock in pits and trenches by machinery or otherwise including removing the excavated materials upto a distance of 100 M beyond building premises,stacking as directed dewatering manually or mechanically if required, shoring, strutting, preparing the bed for foundation and necessary back filling in layers including dry and wet compaction etc. complete.

Sr.No. Particulars 1 Materials : NIL 2 Labours : a)1 Breaker Needle with operator ( It is assumed that with a breaker needle in a day we can excav-ate nearly 65cft (1.84cum.) with lead & lift as specified.) i.e. For 1 cum. It requires 0.54 days of breaker c) Unskilled coolie (Male) For 100 cft ( 2.83cum) 3 persons are required, therefore for one

Quantity

Unit

Rate per

Amount

0.54

Per day

1000.00

540.00

1.06

No

100.00

106.00

cum1.06 person for 1cum. d) Backfilling 3 Centering & Shuttering NIL Others Dewatering

0.08

No

100.00

8.00

1.00

L/s

2.00

2.00

5 6 7

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.50% 0.50%

TOTAL (A) on total (A) on total (A) on total (A) TOTAL (B) on total (B) TOTAL 777 /- Per per cum

656.00 13.12 3.28 3.28 675.68 101.35 777.03

Over head & Profit

15.00%

Say Rs. Prepared by : Name : ________________________________

Sign : _______________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/EX/I/15 Description : Soling 230thk. Below floor Location : 0 Default Date : E1 Revised on Date : Unit :

Jan 0, 00 14-08-06 per Sqm

Providing and laying 230 mm thick dry trap rubble soling in plinth including filling the interstices with murum and stone chips, watering,compacting, ramming etc complete with all labour and material.

Sr.No. Particulars 1 Materials : a)Rubble b)Murrum

Quantity 0.30 0.02

Unit Cum Cum

Rate per 500.00 120.00

Amount 149.50 2.40

Labours : a) Unskilled coolie (Male) b) Unskilled coolie (Female) Assuming that one pair

0.05 0.05

No No

100.00 100.00

5.40 5.40

to do 200 sft. (18.59 sqm.)Of soling area 3 Centering & Shuttering NIL Others NIL 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL Say Rs. Prepared by : Name : _________________________________ Sign: ________________ 193 /- Per per Sqm

162.70 3.25 0.81 0.81 167.58 25.14 192.72

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/EX/I/12 Description : Location : 0 Default Date : E1 Revised on Date : Unit :

Jan 0, 00 14-08-06 per Cum

Filling with selected murrum obtained from excavation

Providing & filling in plinth selected murrum obtained from excavation including spreading, levelling, watering, and ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for payment)

Sr.No. Particulars 1 Materials : NIL NIL 2 Labours :

Quantity 0.00

Unit

Rate per 0.00

Amount 0.00

a) Unskilled coolie (Male) Assuming that one male coolie to do100 cft. (2.83cum.) b) Unskilled coolie (for watering & compactor) for 2 hours Net labour required = (2 / 2.83)/8 3 Centering & Shuttering NIL Others (m/c compactor) Hire charges at 10/- per hour

0.35

No

100.00

35.00

0.09

No

100.00

9.00

1.00

10.00

10.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

54.00 1.08 0.27 0.27 55.62 8.34 63.96

Say Rs. Prepared by : Name : _________________________________

64 /- Per

per Cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/EX/I/13 Description : Filling with outside murrum Location : 0 Default Date : E1 Revised on Date : Unit :

Jan 0, 00 14-08-06 per Cum

Providing & filling in plinth murrum brought from outside including spreading, levelling, watering, and ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for payment)

Sr.No. Particulars 1 Materials :

Quantity

Unit

Rate per

Amount

a) Murrum Assuming the difference of loose volume & compacted volume = 30% 2 Labours : a) Unskilled coolie (Male) Assuming that one male coolie to do100 cft. (2.83cum.) b) Unskilled coolie (for watering & compactor) for 2 hours Net labour required = (2 / 2.83)/8

1.30

Cum

120.00

156.00

0.35

No

100.00

35.00

0.09

No

100.00

9.00

Centering & Shuttering NIL Others (m/c compactor) Hire charges at 10/- per hour

1.00

10.00

10.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

210.00 4.20 1.05 1.05 216.30 32.45 248.75

Say Rs. Prepared by : Name : _________________________________

249 /- Per

per Cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : 1 Item No. : FDAPL/EX/I/14 Filling with sand Location : 0 Default Date : E1 Revised on Date : Unit :

Jan 0, 00 14-08-06 per Cum

Providing & filling in plinth with approved sand including spreading, levelling, watering, and ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for payment)

Providing & filling in plinth with approved sand including spreading, levelling, watering, and ramming (in layers of 15 cms) etc. all complete (consolidated depth will be measured for payment)

Sr.No. Particulars 1 Materials : a) Sand Assuming the difference of loose volume & compacted volume = 20% 2 Labours : a) Unskilled coolie (Male) Assuming that one male coolie to do 100 cft. (2.83cum.) b) Unskilled coolie (for watering & compactor) for 2 hours Net labour required = (2 / 2.83)/8 Centering & Shuttering NIL Others (m/c compactor) Hire charges at 10/- per hour

Quantity 1.20

Unit Cum

Rate per 850.00

Amount 1020.00

0.35

No

100.00

35.00

0.09

No

100.00

9.00

1.00

10.00

10.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

1074.00 21.48 5.37 5.37 1106.22 165.93 1272.15

Say Rs. Prepared by : Name : _________________________________

1,272 /- Per

per Cum

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Location : 0 Default Date : E1 Revised on Date :

Jan 0, 00 14-08-06

Item No. : FDAPL/EX/I/16 Description : Antitermite treatment

Unit :

per Sqm

Providing & applying preconstructional anti termite treatment to bottom and sides of excavated surfaces by approved agency (MODE of Measurement will be on plinth area basis.)

Sr.No. Particulars 1 Materials : Chemical Assuming the treatment with 10 ltr. Per sqm. Of area & 0.5 ltr. Of chemical Per 10 ltr of water (i.e 5% concentration) 2 Labours : a) Unskilled coolie (for spreading) for 1 hours for one footing of 4 sqm. Area Net labour required = (1 / 4)/8

Quantity 0.50

Unit Ltr.

Rate per 66.15

Amount 33.08

0.03

No

100.00

3.10

Centering & Shuttering NIL Others (m/c compactor) 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

36.18 0.72 0.18 0.18 37.26 5.59 42.85

Say Rs. Prepared by : Name : _________________________________

43 /- Per

per Sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/EX/I/17 Description : Location : 0 Default Date : E1 Revised on Date : Unit : Carting away surplus excavated earth

Jan 0, 00 14-08-06 Cum

Carting away the unwanted excavated,/ demolished material outside the premises and unloading and spreading it as and where required as per the rules of local authority including loading, unloading, carting, spreading etc complete.

Sr.No. Particulars 1 Materials : NIL 2 Labours : a) Unskilled coolie 2 nos. do filling of tractor (100cft) in 15 minutes Net labour required = (0.5 / 2.83)

Quantity

Unit

Rate per

Amount 0.00

0.18

No

100.00

18.00

Centering & Shuttering NIL

Others (m/c tractor) Tractor hire charges at 40/- per trip 1.00 1 40.00 40.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

58.00 1.16 0.00 0.00 59.16 8.87 68.03

Say Rs. Prepared by : Name : _________________________________

68

per Cum

Sign: ________________

Site:

0 Computer Code No. : Item No. : FDAPL/EX/I/11

Rate analysis Location : 0 Default Date : E5 Revised on Date : Unit :

Jan 0, 00 14-08-06 per cum

Description : Excavation in Hard Rock by blasting Excavation in Hard Rock for foundation by blasting including removing the excavated material upto a distance of 10m with normal lift upto 1.5m and stacking & spreading in such a way as to not disturd any site activity or as directed. Dewatering Preparing the bed for foundation & necessary back filling, watering including shoring & Shuttering etc. complete.

Sr.No. Particulars 1 Materials : Per hole approx. 250 gm. Of blasting powder & one detonator is required a) Blasting powder b) Detonator c) Safety fuse d) Detonating fuse 2 Labours : a) Unskilled coolie (Male) For 100 cft ( 2.83cum) 3 persons are required, therefore for one cum1.06 person for 1cum.

Quantity

Unit

Rate per

Amount

0.7 2 2 8

Kg. No rmt rmt

78.75 8 4.725 6.5

55.13 16.00 9.45 52

1.06

No

100.00

106.00

Centering & Shuttering NIL Others Compressor for drilling holes

0.50

120 TOTAL (A)

120.00

60.00 298.58 5.97 1.49 1.49 307.53 46.13 353.66

5 6 7

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.50% 0.50%

on total (A) on total (A) on total (A) TOTAL (B) on total (B) TOTAL 354 /- Per per cum

Over head & Profit

15.00%

Say Rs.

Prepared by : Name : ________________________________

Sign : _______________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/MISC/XI/2 Description : Structural steel works Location : 0 B1 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Sqm.

Providing, fabricating & erecting & fixing, cutting, bending, grinding, welding the structural steel work consisting of m.s. plates I beams channels, angles, chequered plates, including fabricating as per shop drawing including erection to required line and level and providing and fixing buts, bolts and required appropriate washers etc. complete including painting

Sr.No. 1

Particulars Quantity Assuming area of 15 x 4 = 60 sqm. Materials : a) Structural steel 1.05 (adding 5% for wastage) 155.00 b) Welding rods c) Oxygen Gas 1.50 d) DA 0.50 c) Bolts, nuts & washers 1.00 d) Primer Painting 2.00 d) Enamel Painting 5.00

Unit

Rate per

Amount

Mt. No. Cyli. Cyli. Kg. lts. lts.

30500.00 3.50 250.00 800.00 47.25 40.00 110.00

32025.00 542.50 375.00 400.00 47.25 80.00 550.00

Labours : For fabrication & errection For painting

1.00 1.00

Mt. Mt.

2250.00 450.00

2250.00 450.00

Centering & Shuttering Nil

Others Welding M/C 1.00 Day 250.00 250.00

TOTAL (A) 5 Tools & Plants Charges 2.00% on total (A)

36969.75 739.40

6 7

Water charges Electricity Charges

0.00% 0.50%

on total (A) on total (A) TOTAL (B)

0.00 184.85 37893.99 5684.10 43578.09

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/MISC/XI/3 Description : 12mm dia. Fan hook

43,578 /- Per

per Sqm.

Sign: ________________

Location : 0 B1 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per No.

Providing & fixing and securing in position box type fan hooks of 12 mm diameter MS rods 30 cm long as directed Sr.No. 1 Particulars Quantity Assuming area of 15 x 4 = 60 sqm. Materials : a) MS rods 12mm 0.28 (adding 5% for wastage) 1.00 b) Sand c) Binding wire 0.05 Unit Rate per Amount

Kg. L/s Kg.

27.50 2.00 32.00

7.71 2.00 1.60

Labours : For preparing the hook & fixing in place Fitter (0.5 hrs.) Helper (0.5hrs.) Others

0.06 0.06

No. No.

150.00 100.00

9.38 6.25

TOTAL (A)

26.93

4 5 6

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.00% 0.50%

on total (A) on total (A) on total (A) TOTAL (B)

0.54 0.00 0.13 27.61 4.14 31.75

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/MISC/XI/5 Description : Chainlink fencing

32 /- Per

per No.

Sign: ________________

Location : 0 B1 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per Sqm.

Providing and erecting in position chain link fencing of GI 18 gauge, 50 mm opening size as required including fixing the angle supports in bed blocks of C:M 1:3:6 at 2.4 m c/c, ms 6 mm dia at top, U nails for fixing, etc complete with all labour and material. - 1.2 m high fencing ( Structural steel for angles,flats will be paid separately) Sr.No. 1 Particulars Quantity Consider lengthof 24 x 1.2 = 28.8 sqm. Materials : a) Chain link 18 guage 30.24 (adding 5% for wastage) 2.00 b) U nails c) 6mm dia. Wire 12.40 d) Concrete 1:3:6 0.40 Labours : For excavation For poles errecting (0.5 mason & 0.5 helpers) For fixing chain link (.5 mason & 1 helpers) Others Unit Rate per Amount

Sqm. Kg. Kg. Cum.

156.00 40.00 32.00 1979.00

4717.44 80.00 396.80 783.68

11 0.50 0.50 0.50 1.00

Nos. No. No. No. No.

5 150.00 100.00 150.00 100.00

55.00 75.00 50.00 75.00 100.00

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit Costing for 28.8 sqm. 15.00% on total (B) TOTAL

6332.92 126.66 0.00 31.66 6491.25 973.69 7464.93

Say Rs. Prepared by : Name : _________________________________

259 /- Per

per Sqm.

Sign: ________________

300 mm 46.15385 per mt. 0.3 mm 153.8462 total rods 538.4615

28.8

12.4 33

CODE

NO

STANDARD ITEMS OF BOQ BRIEF DESCRIPTION OF ITEMS SECTION I -Work Below Plinth

UNIT

Rate

SNJ/EX/ SNJ/EX/I SNJ/EX/I SNJ/EX/I SNJ/EX/I SNJ/EX/I SNJ/EX/I SNJ/EX/I SNJ/EX/I SNJ/EX/I SNJ/EX/I SNJ/EX/I SNJ/EX/I SNJ/EX/I SNJ/EX/I SNJ/EX/I SNJ/EX/I

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Excavation in soil and soft murum upto 1.5m depth Excavation in soil and soft murum from 1.51 m to 3.0m depth Excavation in hard murum and boulders upto 1.5 m depth Excavation in hard murum and boulders from 1.51 to 3.0 m depth Excavation in soft rock upto 1.5 m depth Excavation in soft rock from 1.51 to 3.0 m depth Excavation in soft rock from 3.1 m to 6.0 m depth Excavation in hard rock upto 1.5m depth ( by chiselling) Excavation in hard rock from 1.51m to 3m depth ( by chiselling) Excavation in hard rock from 3.1m to 6.0m( by Chiselling) Excavation in hard rock by blasting Filling in plinth with selected murum obtained from excavation Filling in plinth with murum brought from outside ( labour+material) Filling in plinth sand 230 mm thick dry rubble soling in plinth Providing preconstructional antitermite treatment to plinth Carting away unwanted excavated material outside the premises SECTION II-PCC Work

Cum Cum Cum Cum Cum Cum Cum Cum Cum Cum Cum Cum Cum Cum Sqm Sqm Cum

90.02 99.02 106.61 117.27 289.25 318.18 350.00 777.03 854.74 940.21 353.66 63.96 248.75 1272.15 192.72 42.85 68.03

SNJ/PCC/II SNJ/PCC/II SNJ/PCC/II SNJ/PCC/II SNJ/PCC/II SNJ/PCC/II

1 2 3 4 5 6

Providing and laying PCC 1:5:10 beddintg Providing and laying PCC 1:4:8 bedding Providing and laying PCC 1:3:6 bedding Providing and laying PCC 1:2:4 bedding Providing and laying PCC 1:1.5:3 bedding Providing and laying 1:4:8 plum concrete SECTION III-RCC Work

Cum Cum Cum Cum Cum Cum

2342.07 2543.77 3311.94

2213.56

SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III

1 Providing and casting RCC M20 for footings, foundations, combined footings, eccentric footings, raft, pedastals,pile caps 2 Providing and casting RCC M20 for columns ( of any size and shpe)upto plinth and in basement 3 Providing and casting RCC M20 for columns ( fo any size and shape) in superstructure at all levels 4 Providing and casting RCC M20 for plinth beams 5 Providing and casting RCC M20 for beams ( of any shape and size) at all levels 6 Providing and casting RCC M20 for beams in grid system 7 Providing and casting RCC M20 for lintels 8 Providing and casting RCC M20 for piles 9 Providing and casting RCC M20 for standard slab(thk upto 200 mm) 10 Providing and casting RCC M20 slab for loft 11 Providing and casting RCC M20 for cantilever slab upto 2.0 m span

Cum 3281.18 Cum 4787.63 Cum Cum Cum Cum Cum Cum Cum Cum 4428.25 5483.82 5015.69 5171.26 4840.19 5296.52 5896.03 5483.82

SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III

12 13 14 15 16 17 18

SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III SNJ/RCC/III

19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

Providing and casting RCC M20 for sloping slab Providing and casting RCC M20 for pyramidal slab Providing and casting RCC M20 for hordi slab Providing and casting RCC M20 for folded slab upto thickness of 150mm Providing and casting RCC M20 for chajjas at any level , of projection upto 0.75m Providing and casting RCC M20 for pardies, parapets, fins, upstands of thickness upto 100 mm Providing and casting RCC M20 for staircase steps and waist slab with riser upto 170 mm and tread upto 300 mm and waist slab thickness upto 200 mm.at all levels. Providing and constructing RCC M20 for coping at all levels Providing and constructing RCC M20 for sills at all levels Providing and constructing RCC walls in M20 Providing and constructing RCC M20 floor Extra for addition or deduction in thickness of the structural members as mentioned above , excluding form work Less for providing concrete of grade M15 in lieu of M20 Extra for providing concrete of grade M25 in lieu of M20 Extra for providing concrete of grade M30 in lieu of M20 Extra for providing concrete of grade M35 in lieu of M20 Extra for providing concrete of grade M40 in lieu of M20 Providing, cutting, bending, laying reinfocement of mild steel, tor steel of various diameters including binding wire Welding of bars to existing reinforcement Expansion joint for columns Expansion joint for beams Expansion joint for slab Providing post tensioning of beams and slab Providing anticorrosive treatment to reinforcement SECTION IV-Stone /Brick masonry/Block/Siporex Masonry

Cum Cum Cum Cum Cum

4883.83

6208.14 5483.82 Cum 6280.99 Cum 5426.55 5837.16 5837.16 4998.77

Cum Cum Cum Cum

Cum Cum Cum Cum Cum MT RM RM RM RM Sqm MT

331.88

45499.46 49.76 1099.18 1099.18 1099.18

SNJ/MAS/IV SNJ/MAS/IV SNJ/MAS/IV SNJ/MAS/IV SNJ/MAS/IV SNJ/MAS/IV SNJ/MAS/IV SNJ/MAS/IV SNJ/MAS/IV SNJ/MAS/IV SNJ/MAS/IV

1 Providing and constructing 350 mm or above brick masorny below plinth (C:M 1:6) 2 Providing and constructing UCR masonry in C: M 1:6 below plinth for foundation 3 Providing and constructing UCR masonry in C:M 1:6 for compound wall, steps, pillars in superstructure etc 4 Providing and constructing 350 mm thick BB masonry in superstructure for steps, walls, pillars (C:M 1:4) 5 Providing and constructing 230 mm thick BB masonry for walls below plinth (C:M1:6) 6 Providing and constructing 230 mm thick BB masorny for wall in superstructure at all levels(C:M1:6) 7 Providing and constructing 115 mm thick BB masorny in super structure at all levels (C:M 1:4) 8 Providing and constructing 150 mm thick BB masorny in super structure at all levels (C:M 1:4) 9 Providing and constructing coursed rubble masonry 10 Providing and constructing 'Khandki' masonry 11 Providing and constructing 150 mm thk concrete block masonry

Cum 2335.22 Cum 1984.99 Cum 2020.34 Cum 2438.95 Sqm 2085.80 Sqm 2151.57 Sqm 343.43 Sqm Cum Cum Sqm 405.61 1967.96 451.31

SNJ/MAS/IV SNJ/MAS/IV SNJ/MAS/IV SNJ/MAS/IV

12 Providing and constructing 200 mm thk concrete block masonry 13 Providing and constructing siporex block masonry 100 mm thick 14 Providing and constructing siporex block masonry 150 mm thick 15 Providing and constructing siporex block masonry 200 mm thick

Sqm Sqm Sqm Sqm

615.32 1828.73 135.21 137.64

SECTION V- PLASTERING AND POINTING SNJ/PLAST/V SNJ/PLAST/V SNJ/PLAST/V SNJ/PLAST/V SNJ/PLAST/V SNJ/PLAST/V SNJ/PLAST/V SNJ/PLAST/V SNJ/PLAST/V SNJ/PLAST/V SNJ/PLAST/V 1 Providing and applying 12 mm thick internal cement plaster C:M 1:4 Sqm 111.94 2 Providing and applying 20 mm thick sandface cement plaster C:M 1:5 in Sqm one coat 3 Providing and applying 12mm back coat plaster behind dado C:M 1:4 Sqm 4 Providing and applying 20 mm thick sand faced cement plaster in two coats first coat with 1:5 & second with 1:4 5 Provding and applying 25 mm thick plaster to toilet sunks and sides, internally to water tanks with waterproofing compound 6 Providing and applying 20 mm thick rough cast plaster 7 Providing and applying pebble dash plaster 8 Providing and applying special finish RENOVO or other such plasters 9 Providing and making flush groove pointing to brick/block masonry 10 Providing and making flush groove pointing to stone masonry 11 Providing and making sunk pointing to stone masonry SECTION VI-FLOORING WORK SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI 1 Providing and laying IPS floor 50 mm thick with ghotai 2 Providing and laying marble mosaic tile flooring 25cmx25cm size - grey cement based 3 Providing and laying marble mosaic tile flooring 30cmx30cm size - grey cement based 4 Providing and laying marble mosaic tile flooring 25cmx25cm size - white cement based 5 Providing and laying marble mosaic tile flooring 30cmx30cm size - white cement based 6 Providing and laying marble stone flooring 7 Providing and laying Kotah stone flooring 8 Providing and laying granite stone flooring 9 Providing and laying tandur stone flooring 10 Providing and laying polished shahabad flooring 11 Providing and laying rough shahabad flooring 12 Providing and laying Jaisalmer stone flooring 13 Providing and laying ceramic tile flooring 14 Providing and laying vitrified tile flooring 15 Providing and laying rough vitrified tile flooring 16 Providing and laying designer tiles - interlocking type 17 Provding and laying interlocking paving blocks 18 Provding and laying chequered tiles 19 Providing and laying marble mosaic tile skirting 125mm size - grey cement based Sqm Sqm Sqm 446.20 Sqm 468.71 Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm 625.65 1462.74 606.28 2438.35 590.30 358.07 285.58 674.99 1188.05 1188.05 707.57 399.42 307.84 555.77 173.66 334.03 Sqm 166.52 Sqm 268.20 Sqm Sqm Sqm Sqm Sqm Sqm 63.90 91.88 89.84 136.15 93.98

SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI SNJ/FLOOR/VI

20 Providing and laying marble mosaic tile skirting 150 mm size - grey cement based 21 Providing and laying marble mosaic tile skirting 125mm size - white cement based 22 Providing and laying marble mosaic tile skirting 150 mm size - white cement based 23 Providing and laying marble stone skirting 24 Providing and laying Kotah stone skirting 25 Providing and laying granite stone skirting 26 Providing and laying tandur stone skirting 27 Providing and laying polished shahabad skirting 28 Providing and laying rough shahabad skirting 29 Providing and laying Jaisalmer stone skirting 30 Providing and laying ceramic tile skirting 31 Providing and laying vitrified tile skirting 32 Providing and laying rough vitrified tile skirting 33 Providing and laying ceramic tile dado 34 Providing and laying marble stone dado 35 Providing and laying Kotah stone dado 36 Providing and laying granite stone dado 37 Providing and laying tandur stone dado 38 Providing and laying marble stone for treads and risers 39 Providing and laying Kotah stone for treads and risers 40 Providing and laying granite stone for treads and risers 41 Providing and laying tandur stone for treadsand risers 42 Providing and laying Jaisalmer stone for treads and risers 43 Providing marble for window sills and jambs 44 Provding kotah stone for window sills and jambs 45 Providing granite stone for window sills and jambs 46 Providing tandur stone for window sills and jambs 47 Providing, making and erecting in position kitchen platform with following specifications. Width of platform 2'3" and height 32" top a. Kadappa slab 40 mm thick as base to granite stone slab. b. Granite stone slab 20 mm thick with polishing, c. Making hole for single bowl stainless steel sink with edge polishing to cut surface of stones d. One shelf of granite below platform e. 2 no of vertical supports of kadappa stone with both side polish and edge polish f. 4" height granite fascia with edge polish As per item no 56 above but with marble stone top slab

Sqm 537.76 Sqm 696.49 Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm RM 704.78 153.85 68.94 268.72 63.21

71.20 1225.37 1225.37 725.03

162.61 895.36 306.70 72.94 1395.58 653.57 2681.12 609.21 5005.23

RM

3388.21

SNJ/FLOOR/VI SNJ/FLOOR/VI

As per item no 56 above but with polished kadappa top slab 50 mm RM thick. 50 Providing and laying vitrified tile dado Sqm 51 Provding and laying interlocking paving blocks (heavy duty) Sqm

1800.22 1262.44 578.39

SECTION V :DOORS & WINDOWS

Providing and fixing in position door frames in correct line, level and plumb of Teak Wood of size 4" x2.5" including applying coal tar to the surface coming in contact with masorny including 6 no of MS hold fasts fixed in concrete bedblocks in masonry ( 6"x6" size), MS rod at bottom to keep the frame in position etc complete with all labour and material. door size 750mm x 2100 mm

RM

468.23

2 3 4 5 6

As per item no 1 above but for door size 900 x 2100 mm As per item no 1 above but for door size1000 x 2100 mm As per item no 1 above but for door size1200 x 2100 mm As per item no 1 above but for door size1500 x 2100 mm As per item no 01 but with granite door frame of size 170 mm x 20 mm and extra patti for rebate formation for 35 mm thick shutter. Door size 750 x 2100 mm As per item no 6 above but for door size 900 x 2100 mm As per item no 6 above but for door size1000 x 2100 mm As per item no 6 above but for door size1200 x 2100 mm As per item no 6 above but for door size1500 x 2100 mm As per item no 01 but with marble door frame of size 170 mm x 20 mm and extra patti for rebate formation for 35 mm thick shutter. Door size 750 x 2100 mm As per item no11 above but for door size 900 x 2100 mm As per item no 11 above but for door size1000 x 2100 mm As per item no 11 above but for door size1200 x 2100 mm As per item no11 above but for door size1500 x 2100 mm

RM RM RM RM

RM

934.46

7 8 9 10 11

RM RM RM RM

RM

579.47

12 13 14 15 16

RM RM RM RM

Providing and fixing in position flush block board door shutters 35 mm thick including 25 mm lipping patti, both faces finished with commercial teak ply, including fixing with 4 no of hinges, required screws etc Sq.M complete. - single shutter - size of door - 750 x 2100 mm

1097.63

17 18 19

As per item no 16 above but for door size of 900 x 2100 mm As per item no 16 above but for door size of 1000 x 2100 mm As per item no 16 above but for double shutter door of size 1200 x 2100

Sq.M Sq.M Sq.M

1138.66 1284.05

20

As per item no 16 above but for double shutter door of size 1500 x 2100

Sq.M

21

Providing and fixing laminate of approved colour and shade to doors including all labour and material Providing and fixing following MS powder coated fittings and fixtures for doors a. Aldrop 250 mm size b. Tadipatti c. Tower bolts d. PVC gattu e. Door stopper f. D type handles Providing and fixing following Aluminium fittings and fixtures for doors a. Aldrop 250 mm size b. Tadipatti c. Tower bolts d. PVC gattu e. Door stopper f. D type handles

Sq.M

432.01

22

No No No No No No

23

No No No No No No

24

Providing and fixing following stainless steel fittings and fixtures of Dline or equivalent make for doors a. Aldrop 250 mm size b. Tadipatti c. Tower bolts d. PVC gattu e. Door stopper f. D type handles Providing and fixing following brass fittings and fixtures of D-line or equivalent make for doors a. Aldrop 250 mm size b. Tadipatti c. Tower bolts d. PVC gattu e. Door stopper f. D type handles

No No No No No No

25

No No No No No No

26

Providing and fixing night latch of approved brand to door with all hardware and accessories required Providing and fixing in position automatic door closure of approved make including all labour and material complete. Providing and fixing peep hole / eye piece of approved make to doors including all labour and material complete

No

27

No

28

29

Providing, making and erection in correct line, level and plumb aluminium sliding window with powder coated sections as per detail design and drawing including all accessories such as locking arrangement, rollers, wool pile in tracks, EPDM gaskets, screws, 4 mm thick clear float glass etc complete with all labour and material.- 2 track sliding window As per item no 29 above but with aluminium colour anodised sections doProviding, making and erection in correct line, level and plumb aluminium sliding window with powder coated sections as per detail design and drawing including all accessories such as locking arrangement, rollers, wool pile in tracks, EPDM gaskets, screws,4 mm thick clear float glass etc complete with all labour and material.- 3 track sliding window with mosquito net As per item no 31 above but with colour anodised aluminium sections doProviding, making and erection in correct line, level and plumb aluminium sliding window with powder coated sections as per detail design and drawing including all accessories such as locking arrangement, rollers, wool pile in tracks, EPDM gaskets, screws, 6 mm thick clear float glass etc complete with all labour and material.- 4 track sliding window, with mosquito net As per item no 33 above but with colour anodised aluminium sections doProviding, making and erection in correct line, level and plumb aluminium sliding window with powder coated sections as per detail design and drawing including all accessories such as locking arrangement, rollers, wool pile in tracks, EPDM gaskets, screws,6 mm thick clear float glass etc complete with all labour and material.- 5 track sliding window, with mosquito net As per item no 35 above but with colour anodised aluminium sections doProviding and fixing in position aluminium openable windows with powder coated sections, with all accessories such as hinges, peg stays, 4 mm thick clear float glass, beading, EPDM gaskets, etc complete with all labour and material As per item no 37 above but with colour anodised sections -doProviding and fixing in position aluminium louvered windows with powder coated sections as per detail design and drawing with all accessories and 4 mm thick frosted glass for louvers etc complete.

30

31

32

33

34

35

36

37

38 39

40

Providing and fixing in position aluminium louvered windows with colour anodised sections as per detail design and drawing with all accessories and 4 mm thick frosted glass for louvers etc complete.

41

Providing and erecting in position fixed glazing with aluminium powder coated sections as per detail design and drawing, including all accessories such as polysulphide sealants, stainless steel clips, 12 mm thick glass, all required scaffolding other labour and material complete the item in all respects. As per item no 31 above but with colour anodised aluminium sections

42

43

Providing, fabricating and fixing in position for grills & railings in Powder coated MS tubular sections of all shapes and size, with weight upto 15 kg / sqm, as per detail design and drawing, all labour and material complete. Providing, fabricating and fixing in position for grills & railings in MS tubular sections with enamel paint of all shapes and size, with weight upto 15 kg / sqm, as per detail design and drawing, all labour and material complete. Providing and fixing in position MS glazed windows with Z section, 4 mm thick clear float glass, 10 mm MS square bars at 120 mm c/c, reqired springs, putty and two coats of oilpaint etc complete.

1018.76

44

797.86

45

1274.64

46

Providing and fixing in position Sintex door shutters to already fixed granite frame for toilet doors with all accessories complete.

SECTION VIII - WATERPROOFING WORKS SNJ/WP/VIII SNJ/WP/VIII SNJ/WP/VIII SNJ/WP/VIII 1 Waterproofing of terrace with brick bat coba upto 115 mm thk 2 Waterproofing of toilet sunks with brick bat coba filling 3 Box type waterproofing for basement walls and wherever required 4 Chemical waterproofing to terrace and toilet sunks Sqm Cum Sqm Sqm 344.17 2818.39 604.85 344.17

SECTION IX - PAINTING SNJ/PAINT/IX 1 White wash Sqm 4.71

SNJ/PAINT/IX SNJ/PAINT/IX SNJ/PAINT/IX SNJ/PAINT/IX SNJ/PAINT/IX SNJ/PAINT/IX SNJ/PAINT/IX SNJ/PAINT/IX SNJ/PAINT/IX

2 3 4 5 6 7 8 9 10

Dry distemper Oil bound distemper Synthetic enamel (oil paint) Plastic emulsion Lustre paint Cement paint Sandtex paint Anti fungal paint such as ACE Aluminium paint to structural steel SECTION X - ROOFING WORK

Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm Sqm

19.39 35.59 46.26 71.68 66.92 36.19 70.77 91.34

SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X SNJ/ROOF/X

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

AC sheet roofing AC ridges AC sheet cladding AC flashig AC gutters Precoated sheet roofing Precoated ridges Precoated sheet cladding Precoated sheet flashing Precoated sheet gutters Aluminium sheet roofing Aluminium ridges Aluminium sheet cladding Aluminium flashings Aluminium gutters FRP sheet roof FRP ridges FRP sheet cladding FRP sheet flashing FRP gutters Mangalor tiles with frame work Pan tile roofing on exsting slab FRP domes Polycarbonate sheet domes/ roof covering

Sqm RM Sqm Sqm Sqm Sqm RM Sqm Sqm Sqm Sqm RM Sqm Sqm Sqm Sqm RM Sqm Sqm Sqm Sqm Sqm Sqm Sqm

SECTION XI - MISCELLANEOUS WORKS SNJ/MISC/XI SNJ/MISC/XI SNJ/MISC/XI SNJ/MISC/XI SNJ/MISC/XI SNJ/MISC/XI SNJ/MISC/XI SNJ/MISC/XI 1 Structural steel fabrication and erection wherever required for trusses, stanchions, and such other industrial activities. 2 Box type fan hooks 3 Anchor fasteners 4 Fabrication and erection of steel required for railings of balconies, staircases, terraces etc with painting 5 ACP sheet cladding 6 Chain link fencing 4' height 7 Chain link fencing 8' height 8 Barbed wire fencing MT

1.73 136.42 330.40 No No Kg Sqm Sqm Sqm Sqm

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/DW/VII/1 Location : Pune D1 Default Date : Revised on Date: Unit :

Jan 0, 00 14-08-06 Rmt.

Description : Providing & fixing TW frame (4"x 2.5") Providing and fixing in position door frames in correct line, level and plumb of Teak Wood of size 4" x2.5" including applying coal tar to the surface coming in contact with masorny including 6 no of MS hold fasts fixed in concrete bedblocks in masonry ( 6"x 6" size), MS rod at bottom to keep the frame in position etc complete with all labour and material. - door size 900mm x 2100 mm Sr.No. Particulars 1 Materials : a) Cement b) Sand ( as approved) c) MS Holdfast d) Teak wood (4*2.5/144*17.83)*1.1 = 1.362 e) MS Tie rod 8mm f) Coal tar 2 Labours : Carpenter for frame making Helper for frame making (0.5 carp + 0.2 help are required per cft of frame making) Mason for fixing of frame Unskilled labour Others Nil 0.00 0.00 TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit Total costing for (0.9+2.1*2 = 5.1Rmt.) Say Rs. Prepared by : 15.00% on total (B) TOTAL 468 /- Per Rmt. 0.00 2025.86 40.52 0.00 10.13 2076.51 311.48 2387.98 Quantity 0.18 0.01 6.00 1.36 0.34 0.50 Unit Bags Cum Nos. Cft Kg. Kg. Rate per 245.00 1060.00 10.00 1200.00 27.50 25.00 Amount 44.10 13.78 60.00 1632.00 9.28 12.50

0.68 0.27

Nos. Nos.

200.00 100.00

136.00 27.20 0.00 75.00 16.00

0.50 0.20

Nos. Nos.

150.00 80.00

Name : _________________________________

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/DW/VII/1 Location : 0 D1 Default Date : Revised on Date: Unit :

Jan 0, 00 14-08-06 Rmt.

Description : P/F Granite frame (170x20) As per item no 01 but with granite door frame of size 170 mm x 20 mm and extra patti for rebate formation for 35 mm thick shutter. Door size 900x 2100 mm Sr.No. Particulars 1 Materials : a) Cement b) Sand ( as approved) c) MS Holdfast d) Granite with 10% wastage ((0.9+.09*2+2.1*2+.05*2)*.17) + ((.86+2.08*2+.05*2)*(.17-.035)) = 1.606 x 1.1 = 1.77 e) MS Tie rod 8mm f) White / colour cement 2 Labours : Labour rate for cutting, fixing & moulding of frame Others Nil 0.00 0.00 TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit Total costing for (0.9+2.1*2 = 5.1 Rmt.) 15.00% on total (B) TOTAL 0.00 4043.04 80.86 0.00 20.22 4144.12 621.62 4765.74 Quantity 0.18 0.01 6.00 1.77 Unit Bags Cum Nos. Sqm. Rate per 245.00 1060.00 10.00 1695.00 Amount 44.10 13.78 60.00 2995.07

0.34 0.25

Kg. Kg.

27.50 30.00

9.28 7.50

1.77

Sqm.

516.00

913.32

Say Rs. Prepared by :

934 /- Per

Rmt.

Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/DW/VII/3 Description : P/F Marble frame (170x20)

Sign: ________________

Location : 0 D1 Default Date : Revised on Date: Unit :

Jan 0, 00 14-08-06 Rmt.

As per item no 01 but with marble door frame of size 170 mm x 20 mm and extra patti for rebate formation for 35 mm thick shutter. Door size 900x 2100 mm Sr.No. Particulars 1 Materials : a) Cement b) Sand ( as approved) c) MS Holdfast d) Marble with 10% wastage ((0.9+.09*2+2.1*2+.05*2)*.17) + ((.86+2.08*2+.05*2)*(.17-.035)) = 1.606 x 1.1 = 1.77 e) MS Tie rod 8mm f) White / colour cement 2 Labours : Labour rate for cutting, fixing & moulding of frame Others Nil 0.00 0.00 TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 7 Over head & Profit Total costing for (0.9+2.1*2 = 5.1 Rmt.) 15.00% on total (B) TOTAL 0.00 2507.16 50.14 0.00 12.54 2569.84 385.48 2955.32 Quantity 0.18 0.01 6.00 1.77 Unit Bags Cum Nos. Sqm. Rate per 245.00 1060.00 10.00 946.00 Amount 44.10 13.78 60.00 1671.58

0.34 0.25

Kg. Kg.

27.50 30.00

9.28 7.50

1.77

Sqm.

396.00

700.92

Say Rs.

579 /- Per

Rmt.

Prepared by : Name : _________________________________ Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/DW/VII/4 Description : P/F flush shutter 35mm Location : 0 D1 Default Date : Revised on Date: Unit :

Jan 0, 00 14-08-06 Sqmt.

Providing and fixing in position flush block board door shutters 35 mm thick including 25 mm lipping patti, both faces finished with commercial teak ply, including fixing with 4 no of hinges, required screws etc complete. - single shutter - size of door - 750 x 2100 mm Sr.No. Particulars 1 Materials : a) Shutter 35mm thk. (2.055 x 0.66 = 1.356 b) Brass Hinges 75mm c) Brass screws 25mm 2 Labours : Carpenter for fixing shutter Helper for fixing shutter (0.2 carp + 0.2 help are required per cft of frame making) Others Nil 0.00 0.00 0.00 Quantity 1.36 4.00 16.00 Unit Sqm. No No Rate per 968.00 20.00 1.50 Amount 1312.61 80.00 24.00

0.20 0.10

Nos. Nos.

200.00 100.00

40.00 10.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit Total costing for (0.75*2.1 = 1.575 sqmt.) 15.00% on total (B) TOTAL

1466.61 29.33 0.00 7.33 1503.27 225.49 1728.76

Say Rs.

1,098 /- Per

Sqmt.

Prepared by : Name : _________________________________ Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : 31 Description : Location : 0 D1 Default Date : Revised on Date: Unit : P/F flush shutter 35mm (internal door)

Jan 0, 00 14-08-06 Sqmt.

Providing and fixing in position flush block board door shutters 35 mm thick including 25 mm lipping patti, both faces finished with commercial teak ply, including fixing with 4 no of hinges, required screws etc complete. - single shutter - size of door - 900 x 2100 mm Sr.No. Particulars 1 Materials : a) Shutter 35mm thk. (2.055 x 0.81 = 1.356) b) Brass Hinges 100mm c) Brass screws 25mm Labours : Carpenter for fixing shutter Helper for fixing shutter (0.2 carp + 0.2 help are required per cft of frame making) 3 4 Centering & Shuttering Nil Others Nil Quantity 1.67 4.00 16.00 Unit Sqm. No No Rate per 968.00 35.00 1.50 Amount 1611.72 140.00 24.00

0.20 0.10

Nos. Nos.

200.00 100.00

40.00 10.00

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B)

1825.72 36.51 0.00 9.13 1871.36 280.70

Total costing for (0.9*2.1 = 1.89 sqmt.)

TOTAL

2152.07

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/DW/VII/5 Description :

1,139 /- Per

Sqmt.

Sign: ________________

Location : 0 D1 Default Date : Revised on Date: Unit : P/F flush shutter 35mm (internal door)

Jan 0, 00 14-08-06 Sqmt.

Providing and fixing in position flush block board door shutters 35 mm thick including 25 mm lipping patti, both faces finished with commercial teak ply, including fixing with 8 no of hinges, required screws etc complete. - double shutter - size of door - 1500 x 2100 mm Sr.No. Particulars 1 Materials : a) Shutter 35mm thk. (2.055 x 1.41 = 1.356 b) Brass Hinges 125mm c) Brass screws 50mm 2 Labours : Carpenter for fixing shutter Helper for fixing shutter (0.2 carp + 0.2 help are required per cft of frame making) Quantity 2.89 8.00 32.00 Unit Sqm. No No Rate per 1016.40 35.00 2.00 Amount 2937.40 280.00 64.00

0.50 0.50

Nos. Nos.

200.00 100.00

100.00 50.00

Others Nil 0.00 0.00 0.00

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B)

3431.40 68.63 0.00 17.16 3517.18

Over head & Profit Total costing for (1.5*2.1 = 2.52 sqmt.)

15.00%

on total (B) TOTAL

527.58 4044.76

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/DW/VII/6 Description :

1,284 /- Per

Sqmt.

Sign: ________________

Location : 0 D1 Default Date : Revised on Date: Unit : P/F Laminate of appr. shade & colour

Jan 0, 00 14-08-06 Sqmt.

Providing and fixing laminate of approved colour and shade to doors including all labour and material Sr.No. Particulars 1 Materials : a) Laminate sheet of 1 mm thk. b) Fevicol c) Sundry material (plywood pieces & 0.5" nail) Quantity 1.00 0.05 1.00 Unit Sqm. Kg. L/S Rate per 310.00 250.00 10.00 Amount 310.00 12.50 10.00

Labours : Carpenter for fixing & polishing of laminates Helper (0.2 carp + 0.2 help are required for fixing the sheet of 4'x8' I.e = 2.88 sqm.) & 0.25 help for polishing

0.07 0.20

Nos. Nos.

200.00 100.00

14.00 20.00

Others Nil 0.00 0.00 0.00

TOTAL (A) 4 5 6 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A)

366.50 7.33 0.00 1.83

TOTAL (B) 7 Over head & Profit 15.00% on total (B) TOTAL

375.66 56.35 432.01

Say Rs. Prepared by : Name : _________________________________

432 /- Per

Sqmt.

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : 31 Description : P/F MS powder coated fittings Location : 0 D1 Default Date : Revised on Date: Unit :

Jan 0, 00 14-08-06 Door.

Providing and fixing following MS powder coated fittings and fixtures for doors, including Aldrop 250mm, tadipatti, towerbolts, PVC gattu, door stopper, D type handle. Sr.No. Particulars 1 Materials : a. Aldrop 300 x 16mm size b. Tadipatti c. Tower bolts d. PVC gattu e. Door stopper f. D type handles g) Screws 2 Labours : Carpenter for fixing Helper (0.2 carp + 0.75 help are required for fixing the fittings for one door) Quantity 1.00 1.00 1.00 1.00 1.00 2.00 24.00 Unit Nos. Nos. Nos. Nos. Nos. Nos. Nos. Rate per 0.00 Amount 0.00 0.00 0.00

0.20 0.75

Nos. Nos.

200.00 100.00

40.00 75.00

Others Nil 0.00 0.00 0.00

TOTAL (A)

115.00

TOTAL (A) 5 6 7 8 Tools & Plants Charges Water charges Electricity Charges Over head & Profit 2.00% 0.00% 0.50% 15.00% on total (A) on total (A) on total (A) TOTAL (B) on total (B) TOTAL

115.00 2.30 0.00 0.58 117.88 17.68 135.56

Say Rs. Prepared by : Name : _________________________________

136 /- Per

Door.

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : 31 Description : P/F Alluminium fittings Location : 0 D1 Default Date : Revised on Date: Unit :

Jan 0, 00 14-08-06 Door.

Providing and fixing following Alluminium fittings and fixtures for doors, including Aldrop 250mm, tadipatti, towerbolts, PVC gattu, door stopper, D type handle.

Sr.No. Particulars 1 Materials : a. Aldrop 300 x 16mm size b. Tadipatti c. Tower bolts d. PVC gattu e. Door stopper f. D type handles g) Screws

Quantity 1.00 1.00 1.00 1.00 1.00 2.00 24.00

Unit Nos. Nos. Nos. Nos. Nos. Nos. Nos.

Rate per 112.50

Amount 112.50 0.00 0.00

Labours : Carpenter for fixing

0.20

Nos.

200.00

40.00

Helper (0.2 carp + 0.75 help are required for fixing the fittings for one door)

0.75

Nos.

100.00

75.00

Centering & Shuttering Nil

Others 4 Nil 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

227.50 4.55 0.00 1.14 233.19 34.98 268.17

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : 31 Description :

268 /- Per

Door.

Sign: ________________

Location : 0 D1 Default Date : Revised on Date: Unit : P/F stainless steel fittings

Jan 0, 00 14-08-06 Door.

Providing and fixing following stainless steel fittings and fixtures for doors, including Aldrop 250mm, tadipatti, towerbolts, PVC gattu, door stopper, D type handle.

Sr.No. Particulars 1 Materials : a. Aldrop 300 x 16mm size b. Tadipatti c. Tower bolts d. PVC gattu e. Door stopper f. D type handles g) Screws

Quantity 1.00 1.00 1.00 1.00 1.00 2.00 24.00

Unit Nos. Nos. Nos. Nos. Nos. Nos. Nos.

Rate per 112.50

Amount 112.50 0.00 0.00

Labours : Carpenter for fixing Helper (0.2 carp + 0.75 help are required for fixing the fittings for one door)

0.20 0.75

Nos. Nos.

200.00 100.00

40.00 75.00

Centering & Shuttering Nil

Others 4 Nil 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

227.50 4.55 0.00 1.14 233.19 34.98 268.17

Say Rs.

268 /- Per

Door.

Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : 31 Description : P/F Brass fittings Location : 0 D1 Default Date : Revised on Date: Unit : Sign: ________________

Jan 0, 00 14-08-06 Door.

Providing and fixing following Brass fittings and fixtures for doors, including Aldrop 250mm, tadipatti, towerbolts, PVC gattu, door stopper, D type handle.

Sr.No. Particulars 1 Materials : a. Aldrop 300 x 16mm size b. Tadipatti c. Tower bolts d. PVC gattu e. Door stopper f. D type handles g) Screws

Quantity 1.00 1.00 1.00 1.00 1.00 2.00 24.00

Unit Nos. Nos. Nos. Nos. Nos. Nos. Nos.

Rate per 112.50

Amount 112.50 0.00 0.00

Labours : Carpenter for fixing Helper (0.2 carp + 0.75 help are required for fixing the fittings for one door)

0.20 0.75

Nos. Nos.

200.00 100.00

40.00 75.00

Centering & Shuttering Nil

Others 4 Nil 0.00 0.00 0.00 0.00 0.00 0.00

0.00

0.00

0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

227.50 4.55 0.00 1.14 233.19 34.98 268.17

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : 31 Description : P/F Night latch

268 /- Per

Door.

Sign: ________________

Location : 0 D1 Default Date : Revised on Date: Unit :

Jan 0, 00 14-08-06 Door.

Providing and fixing night latch of approved brand to door with all hardware and accessories required

Sr.No. Particulars 1 Materials : a) Night Latch b) Screws

Quantity 1.00 24.00

Unit Nos. Nos.

Rate per

Amount 0.00

Labours : Carpenter for fixing Helper

0.20 0.20

Nos. Nos.

200.00 100.00

40.00 20.00

(0.2 carp + 0.2 help are required for fixing the latch for one door)

Centering & Shuttering Nil

Others 4 Nil 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

60.00 1.20 0.00 0.30 61.50 9.23 70.73

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : 31 Description :

71 /- Per

Door.

Sign: ________________

Location : 0 D1 Default Date : Revised on Date: Unit : P/F Automatic door closer

Jan 0, 00 14-08-06 Door.

Providing and fixing in position automatic door closure of approved make including all labour and material complete.

Sr.No. Particulars 1 Materials : a) Automatic door closer (godrej or equivalent) b) Screws

Quantity

Unit

Rate per

Amount

1.00 24.00

Nos. Nos.

0.00

Labours : Carpenter for fixing Helper (0.2 carp + 0.2 help are required for fixing )

0.20 0.20

Nos. Nos.

200.00 100.00

40.00 20.00

Centering & Shuttering Nil

Others 4 Nil 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

60.00 1.20 0.00 0.30 61.50 9.23 70.73

Say Rs. Prepared by : Name : _________________________________ Rate analysis

71 /- Per

Door.

Sign: ________________

Site:

0 Computer Code No. : Item No. : 31 Description :

Location : 0 D1 Default Date : Revised on Date: Unit : P/F eye piece

Jan 0, 00 14-08-06 Door.

Providing and fixing peep hole / eye piece of approved make to doors including all labour and material complete

Sr.No. Particulars 1 Materials : a) Eye piece b) Screws

Quantity 1.00 24.00

Unit Nos. Nos.

Rate per

Amount 0.00

Labours : Carpenter for fixing Helper (0.1 carp + 0.1 help are required for fixing the latch for one door)

0.10 0.10

Nos. Nos.

200.00 100.00

20.00 10.00

Centering & Shuttering Nil

Others 4 Nil 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.00% 0.50% on total (A) on total (A) on total (A) TOTAL (B)

30.00 0.60 0.00 0.15 30.75

Over head & Profit

15.00%

on total (B) TOTAL

4.61 35.36

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : 31

35 /- Per

Door.

Sign: ________________

Location : 0 D1 Default Date : Revised on Date: Unit :

Jan 0, 00 14-08-06 Sqm.

Description : P/F MS powder coated grills & railing Providing, fabricating and fixing in position for grills & railings in Powder coated MS tubular sections of all shapes and size, with weight upto 15 kg / sqm, as per detail design and drawing, all labour and material complete. Sr.No. Particulars 1 Materials : a) Steel sections b) Nails c) Cement 2 Labours : For fabricating & fixing in position Mason for finishing For powder coating (Assuming ave. 40x40x1.5mm section of medium wt. Surface area for 1.884 kg. = 0.16 sqm.)Surface area for 15kg. = 1.274 sqm. For paint touch up 1.00 L/s 20.00 20.00 Quantity 15.00 0.20 0.05 Unit Kg. Kg. Bag Rate per 32.00 32.00 245.00 Amount 480.00 6.40 12.25

15.00 0.10 1.27

Kg. No. Sqm.

8.00 200.00 161.40

120.00 20.00 205.62

Others Nil 0.00 0.00 TOTAL (A) 0.00 864.27 17.29 0.00

5 6

Tools & Plants Charges Water charges

2.00% 0.00%

on total (A) on total (A)

Electricity Charges

0.50%

on total (A) TOTAL (B)

4.32 885.88 132.88 1018.76

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________ Rate analysis Site: 0 Computer Code No. : Item No. : 31 Description :

1,019 /- Per

Sqm.

Sign: ________________

Location : 0 D1 Default Date : Revised on Date: Unit : P/F MS grills & railing with enamel paint

Jan 0, 00 14-08-06 Sqm.

Providing, fabricating and fixing in position for grills & railings in MS tubular sections of all shapes and size, with weight upto 15 kg / sqm, as per detail design and drawing, painted with one coat of zinc chromate & two coats of enamel paint,all labour and material complete. Sr.No. Particulars 1 Materials : a) Steel sections b) Nails c) Cement 2 Labours : For fabricating & fixing in position Mason for finishing For enamel painting (Assuming ave. 40x40x1.5mm section of medium wt. Surface area for 1.884 kg. = 0.16 sqm.)Surface area for 15kg. = 1.274 sqm. 3 Others Nil 0.00 0.00 0.00 0.00 TOTAL (A) 0.00 0.00 676.87 Quantity 15.00 0.20 0.05 Unit Kg. Kg. Bag Rate per 32.00 32.00 245.00 Amount 480.00 6.40 12.25

15.00 0.10 1.27

Kg. No. Sqm.

8.00 200.00 30.00

120.00 20.00 38.22

4 5 6

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.00% 0.50%

on total (A) on total (A) on total (A) TOTAL (B)

13.54 0.00 3.38 693.79 104.07 797.86

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

798 /- Per

Sqm.

Sign: ________________

Site:

0 Computer Code No. :

Rate analysis Location : 0 D1 Default Date : Revised on Date:

Unit : Item No. : 31 Description : P/F MS Z section windows Providing and fixing in position MS glazed windows with Z section, 4 mm thick clear float glass, 10 mm MS square bars at 120 mm c/c, required springs, putty and two coats of oilpaint etc complete. Sr.No. 1 Particulars Quantity Assuming the window size to be = 1.2 x 1.2m Materials : 9.60 a) MS Zsections (25mm) 8.00 b) 10mm Sq. bars c) 4mm thk. Float glass (with 5% 1.44 wastage) 4.00 d) MS holdfast e) 0.10 f) Nails g) Cement 0.05 h) Fittings (stopper, handle, pin hinges 1.00 I.e = 26+10+20) 0.80 I) Putty Labours : For fabricating & fixing in position (9.6*1.53+8*.785 = 14.2 kg. Mason for finishing For enamel painting For fixing glass (0.22 glazier reqd. for each Sqm.) Others Unit Rate per Amount

Jan 0, 00 14-08-06 Sqm.

Rmt. Rmt. Sqm. Nos Kg. Bag L/s Kg.

45.00 23.55 325.00 20.00 32.00 78.75 56.00 20.00

432.00 188.40 468.00 80.00 3.20 3.94 56.00 16.00

20.97 0.10 1.08 0.32

Kg. No. Sqm. No.

10.00 200.00 30.00 150.00

209.68 20.00 32.40 47.52

Nil

0.00

0.00 TOTAL (A)

0.00 1557.14 31.14 0.00 7.79 1596.07 239.41 1835.48 Sqm.

5 6 7

Tools & Plants Charges Water charges Electricity Charges

2.00% 0.00% 0.50%

on total (A) on total (A) on total (A) TOTAL (B)

Over head & Profit Total costing for 1.2 x 1.2m

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

1,275 /- Per

Sign: ________________

backup calculation

Item / description PCC (1:3:6) Labour For pouring Male coolie Female coolie

Qty.

Rate

Amount

Remarks

0.75 0.75

80 80

60 60 120 7.5 26 20 11.5 57.5 One carpenter can do 10 sqm. Per day One helper can do 10 sqm. Per day 2.2 sqm Assuming 75mm thk. For 2x2 size ftg. Con = 2.15*2.15*.075 = 0.35 shutt. = 0.0192 2.15*4*.075 = .65 For wooden runner (2.15x4*3.28*4*4/144)*225 = (705) / 30 = 2.6m 23.5 rs. Per 0.65 sqm. 4x3Wooden runner at 225/- per cft. = 939.1392 (4*3/144)*8*5*225/78.2616 152.4528

Mason for finishing Carpenter for shuttering ( 2sqm per cum.) Helper for shuttering Add for deshuttering @ 25%

0.05 0.2 0.2

150 130 100

Material cost of shuttering Area of shuttering = 2 sqm. Per cum of concrete, for each Sqm. Cost = 23.5 / .65 = 36.15 add 4 rs. For nails & oil etc.

80

RCC M20 for footings Assuming Size of 1.5x1.5x.4 Labour For pouring Male coolie Female coolie

0.67 0.67

80 80

53.6 53.6 107.2

Mason for finishing

0.11

150

16.5

1.6 Conc. = 1.5*1.5*.4 = 0.9cum shutt = 1.5 * 4 *.4 = 2.4 shutt / cum = 2.4/0.9 =2.67 0.9 One mason can do finishing of 9 cum. ( 10 ftgs. )

Page 1

backup calculation

Carpenter for shuttering (approx = 3.0 sqm) Helper for shuttering Add for deshuttering @ 25% Material cost of shuttering

0.3 0.3

130 100

39 30 17.25 86.25

One carpenter can do 10 sqm. Per day One helper can do 10 sqm. Per day 0.3

Area of shuttering = 3 sqm. Per cum of concrete, for each Sqm. Cost = 45.4/136.2

1000 rs. For plywood + 750 rs. For wooden runner = (1000+750)/2.88 = 608 rs. Per Sqm. With 20 uses cost per sqm = 608/20 = 30.4, Add 5/- for supports & 10/-. For nails & oil etc. Total = 30.4+5+10 =45.4 4x3Wooden runner at 225/- per cft. = (4*3/144)*8*5*225/-

RCC M20 for Columns superstrucure Assuming col. Of 600x230 Labour For pouring Male coolie Female coolie

1.1 1.1

80 80

88 88 176 0 162.5 125 71.875 359.375 One carpenter can do 8 sqm. Per day One helper can do 8 sqm. Per day

Mason for finishing Carpenter for shuttering (10 sqm. Shutt / cum) Helper for shuttering Add for deshuttering @ 25% Material cost of shuttering Area of shuttering = 10 sqm. Per cum of concrete, for each Sqm. Cost = 93.9 + 10/- for wirenails & shuttering oil

0 1.25 1.25

150 130 100

1040

4.98 1000 rs. (for plywood) + 900 rs. (for wooden runner) = (1000+900)/2.88 = 659 rs. Per Sqm. + Rs.4 for supports + 24Rs. For chavis

Page 2

backup calculation

4x3Wooden runner at 225/- per cft. = (4*3/144)*8*6*225/(65.9+4+24)


RCC M20 for Columns below plinth assuming column size of 600*230 Labour For pouring Male coolie Female coolie 0.083333333 900

0.9 0.9

80 80

72 72 144 One mason can do finishing of 12 cum. (4 ftgs. ) One carpenter can do 10 sqm. Per day One helper can do 10 sqm. Per day

Mason for finishing Carpenter for shuttering (10sqm / cum. Of conc.) Helper for shuttering Add for deshuttering @ 25% Material cost of shuttering

0 1 1

150 130 100

0 130 100 57.5 287.5

Area of shuttering = 10 sqm. Per cum of concrete, for each Sqm. Cost = 71.9 + 10/- for wirenails & shuttering oil 820

1000 rs. (for plywood) + 900 rs. (for wooden runner) = (1000+900)/2.88 = 659 rs. Per Sqm. Assuming 15 uses rate per use = 43.9/- add Rs.4 for supports + 24Rs. for chavis. Total = 43.9+4+24 = 71.9/4x3Wooden runner at 225/- per cft. = (4*3/144)*8*4*225/-

6713.599 671.3599 44.7573267

RCC M20 for beams Labour For pouring Male coolie Female coolie

1.1 1.1

80 80

88 88 176

Page 3

backup calculation

Mason for finishing Carpenter for shuttering (10sqm percum.) Helper for shuttering Add for deshuttering @ 25% Material cost of shuttering

0.1 1.67 1.67

150 130 100

15 217.1 167 96.025 480.125

One mason can do finishing of 10 cum. One carpenter can do 6 sqm. Per day One helper can do 6 sqm. Per day

Area of shuttering = 10.5 sqm. Per cum of concrete, for each Sqm. Cost =97.3, add 10/- for shuttering oil & nails, total = 84.5+10 =94.5 992.25

1000 rs. (for plywood) + 1200 rs. (for wooden runner) = (1000+1200)/2.88 = 763 rs. Per Sqm. With 12 repetetion rate per sqm = 63.58, add Rs.5 for supports + 16 Rs. For chavis Total = 63.5+5+16 = 84.5 4x3Wooden runner at 225/- per cft. = (4*3/144)*8*8*225/- =1200/4*4 chavis of 4 feet in length (4 nos). with 25uses, cost = ((4*4*4*4/144)*225) /25

RCC M20 for Plinth & tie beams Labour For pouring Male coolie Female coolie

63.58333333 84.5 1.1 1.1 80 80 88 88 176 10.5 162.5 125 71.875 359.375 One mason can do finishing of 15 cum. One carpenter can do 8 sqm. Per day One helper can do 8 sqm. Per day

Mason for finishing Carpenter for shuttering ( 10sqm per cum.) Helper for shuttering Add for deshuttering @ 25% Material cost of shuttering

0.07 1.25 1.25

150 130 100

Page 4

backup calculation

Area of shuttering = 10 sqm. Per cum of concrete, for each Sqm. Cost =65, add 10/- for shuttering oil & nails, total = 65+10 =75 750

1000 rs. (for plywood) + 1200 rs. (for wooden runner) = (1000+900)/2.88 = 659rs. Per Sqm. With 15 repetetion rate per sqm = 43.9, add Rs.5 for supports + 16 Rs. For chavis Total = 44+5+16 = 65 4x3Wooden runner at 225/- per cft. = (4*3/144)*8*6*225/- =1200/-

RCC M20 for lintel beams Labour For pouring Male coolie Female coolie

1.5 1.5

80 80

120 120 240 10.5 260 200 115 575 One mason can do finishing of 15 cum. 1.75 One carpenter can do 6 sqm. Per day One helper can do 6 sqm. Per day

Mason for finishing Carpenter for shuttering ( 12sqm per cum.) Helper for shuttering Add for deshuttering @ 25% Material cost of shuttering Area of shuttering = 12sqm. Per cum of concrete, for each Sqm. Cost = 731 / 10 =73, add 10/- for shuttering oil & nails

0.07 2 2

150 130 100

996

1000 rs. For plywood + 900 rs. For wooden runner = (1000+900)/2.88 = 659 rs. Per Sqm. + 2x(120/10) for 2 no. for supports Total = (659+72) 4x3Wooden runner at 225/- per cft. = (4*3/144)*8*6*225/731

RCC M20 for grid beams Labour For pouring Male coolie Female coolie

1.5 1.5

80 80

120 120

Page 5

backup calculation

240 Mason for finishing Carpenter for shuttering ( 12qm per cum.) Helper for shuttering Add for deshuttering @ 25% Material cost of shuttering Area of shuttering = 12sqm. Per cum of concrete, for each Sqm. Cost = 102 , add 10/- for shuttering oil & nails 1344 1000 rs. For plywood + 1200 rs. For wooden runner = (1000+1200)/2.88 = 764 rs. Assuming 12uses rate Per Sqm. = 63.6, Add 8/- for supports + 30rs for chavis Total = (63.6+8+30) 4x3Wooden runner at 225/- per cft. = (4*3/144)*8*8*225/- & Chavis 4' long 6 nos with 20 uses (4*4*4/144*225*6/20) 0.07 2 2 150 130 100 10.5 260 200 115 575 0.066666667 One mason can do finishing of 15 cum. 1.75 One carpenter can do 6 sqm. Per day One helper can do 6 sqm. Per day

RCC M20 for lift walls Labour For pouring Male coolie Female coolie

1.1 1.1

80 80

88 88 176 0 208 160 92 460 One mason can do finishing of 15 cum. 1.6 One carpenter can do 5 sqm. Per day One helper can do 5 sqm. Per day

Mason for finishing Carpenter for shuttering ( 8sqm per cum.) Helper for shuttering Add for deshuttering @ 25% Material cost of shuttering Area of shuttering = 8sqm. Per cum of concrete, for each Sqm. Cost = 87, add 10/-for shuttering oil & nails

0 1.6 1.6

150 130 100

776

1000 rs. For plywood + 900 rs. For wooden runner = (1000+900)/2.88 = 659 rs. Assuming 12 uses rate Per Sqm. = 54.91, Add 8/- for supports + 24rs for chavis Total = (55+8+24)

Page 6

backup calculation

4x3Wooden runner at 225/- per cft. = (4*3/144)*8*6*225/RCC M20 for slab Labour For pouring Male coolie Female coolie

1 1

80 80

80 80 160 15 130 100 80.5 310.5 One mason can do finishing of 10cum. 1.75 One carpenter can do 7 sqm. Per day One helper can do 7 sqm. Per day

Mason for finishing Carpenter for shuttering ( 7sqm per cum.) Helper for shuttering Add for deshuttering @ 35% Material cost of shuttering Area of shuttering = 7sqm. Per cum of concrete, for each Sqm. Cost = 87.5 , add 10/- for shuttering oil & nails

0.1 1 1

150 130 100

682.5 RCC M20 for parapet fins drop walls upto 125mm thk. Labour For pouring Male coolie Female coolie

Hire charges for plate = 20/- per month, we have two uses per month, i.e rate per sqm = 20, add for wooden runners 4x4 @ 3no. per sqm.(37.5/-), add for ballies at 2.5*120/10(30) = 20+37.5+30 = 87.5/-

1.5 1.5

80 80

120 120 240 7.5 260 200 115 575 One mason can do finishing of 20cum. 1.75 One carpenter can do 8 sqm. Per day One helper can do 8 sqm. Per day

Mason for finishing Carpenter for shuttering ( 16sqm per cum.) Helper for shuttering Add for deshuttering @ 25% Material cost of shuttering

0.05 2 2

150 130 100

Page 7

backup calculation

Area of shuttering = 16sqm. Per cum of concrete, for each Sqm. Cost = 85 , add 10/- for shuttering oil & nails 1520

1000 rs. For plywood + 900 rs. For wooden runner = (1000+900)/2.88 = 659 rs. With 12 uses rate per Sqm. =54.91 Add 6/- for supports + 24rs for chavis Total = (55+6+24) = 85

RCC M20 forStaircases regular(with waist slab upto 175mm) Labour For pouring Male coolie 1.25 Female coolie 1.25

80 80

100 100 200 37.5 260 200 161 621 One mason can do finishing of 4cum. One carpenter can do 4 sqm. Per day One helper can do 4 sqm. Per day

Mason for finishing Carpenter for shuttering ( 8sqm per cum.) Helper for shuttering Add for deshuttering @ 35% Material cost of shuttering Area of shuttering = 8sqm. Per cum of concrete, for each Sqm. Cost = 89 , add 11/- for shuttering oil & nails

0.25 2 2

150 130 100

800

1000 rs. For plywood + 1200 rs. For wooden runner = (1000+1200)/2.88 = 764 rs. Per Sqm. + 8x(120/10) for 8 no. for supports + 32rs for chavis Total = (764+96+32) 892 763.8888889

RCC M20 for folded Staircases (with thickness upto 150mm) Labour For pouring Male coolie 1.5 Female coolie 1.5

80 80

120 120 240 37.5 One mason can do finishing of 4cum.

Mason for finishing

0.25

150

Page 8

backup calculation

Carpenter for shuttering (12sqm per cum.) Helper for shuttering Add for deshuttering @ 35% Material cost of shuttering Area of shuttering = 12sqm. Per cum of concrete, for each Sqm. Cost = 91 , add 11/- for shuttering oil & nails

3 3

130 100

390 300 241.5 931.5

One carpenter can do 4 sqm. Per day One helper can do 4 sqm. Per day

1224

1000 rs. For plywood + 1200 rs. For wooden runner = (1000+1200)/2.88 = 764 rs. Per Sqm. + 8x(120/10) for 8 no. for supports + 48rs for chavis Total = (764+96+48) 908

Reinforcement steel cutting, bending & fixing Labour for 1Mt. Of steel Fitter Helper Foremen Add for straightning & transportation @ 25% 8 8 0.2 110 100 175 880 800 35 428.75 2143.75 For ave. 125 kg. Of steel we require one pair of F/H

Providing & fixing PVC sleeve of 40mm dia. Material cost of sleeves Labour Carpenter 0.43 130 55.9 55.9 0.434782609 One carpenter can do 10 sleeves of 230mm length i.e total = 2.3m 13.75

Providing & fixing UCR masonary in plinth 1.25 times rubble required than the actual Labour mason Unskilled labour (2 nos) 0.23557126 4.245 0.176678445 One mason pair to do 150cft. (I.e.4.245cum) of UCR

0.46 1.2

150 80

69 96

Page 9

backup calculation

165

Providing & fixing UCR masonary for Compound wall etc. 1.25 times rubble required than the actual Labour mason Unskilled labour ( 2 nos per mason) Add for corner stones &

0.46 1.2

150 80

69 96 87

87.71929825 One mason pair to do 150cft. (I.e.4.245 cum) of UCR add for corner stones preparation , assuming 3.0m length & 1.5m height, corner stones required 30nos @ 5/- for (.38*3*1.5 = 1.71 cum. I.e 150/1.71 = 87rs. Per cum.

252

Providing & laying 350mm thk. Below plinth 500 nos. bricks required for one cum of 194.3462898 BBM. 2.3206 Labour mason Unskilled labour ( 2 nos per mason) 0.56 1 150 80 84 80 164 1.219512195 3.5375 One mason pair to do 125ft. (I.e.3.53 cum) of BBM

Providing & laying 350mm thk. In superstructure 500 nos. bricks required for one cum of BBM. Labour mason

0.35

150

52.5

Page 10

backup calculation

Unskilled labour ( 2 nos per mason)

0.7

80

56 108.5 45.6

One mason pair to do 200cft. (I.e.5.66 cum) of BBM Unskilled labour 2 nos. for 1 hour for 10 sqm area ( 3.5cum.)

Scaffolding / sand screening etc. Providing & laying 230mm thk. Below plinth

0.57

80

500 nos. bricks required for one cum of BBM. Labour mason Unskilled labour ( 2 nos per mason)

0.108 0.216

150 80

16.2 17.28 33.48 One mason pair to do 150cft. (I.e.4.25 cum = 18.5 sqm.) of BBM

Providing & fixing 230thk. BBM in superstructure 500 nos. of bricks per cum. Of masonary Labour mason Unskilled labour ( 2 nos per mason)

0.162 0.216

150 80

24.3 17.28 41.58 One mason pair to do 150cft. (I.e.4.25 cum = 18.5 sqm.) of BBM

Scaffolding etc. Sand screening

0.083 0.0552

80 53

6.64 2.9 9.6

Unskilled labour 2 nos. for 1 hour for 3 sqm area For 1sqm. I.e .23 x .2 = 0.046 cum of sand required. (150 per brass)

Providing & fixing 115 thk.BBM in superstructure 500 nos. of bricks per cum. Of masonary Labour

Page 11

backup calculation

mason Unskilled labour (2 nos)

0.17 0.2

150 80

25.5 16 41.5 6.64 1.1 7.7 One mason pair & 3 male coolie to do 12sqm.. Of BBM Unskilled labour 2 nos. for 1 hour for 3 sqm area For 1sqm. I.e .1 x .2 = 0.02 cum of sand required. (150 per brass)

Scaffolding etc. Sand screening

0.083 0.02

80 53

Providing & fixing 150 thk.BBM in superstructure 48nos. Of bricks of 230*150*75 are required for 1sqm. Labour mason Unskilled labour (2 nos)

0.2 0.2

150 80

30 16 46 6.64 1.6 8.2 One mason pair & 3 male coolie to do 10sqm.. Of BBM Unskilled labour 2 nos. for 1 hour for 3 sqm area For 1sqm. I.e .15 x .2 = 0.03 cum of sand required. (rate 150/- per brass) 0.03

Scaffolding etc. Sand screening

0.083 0.03

80 53

Providing & laying coursed rubble masonary 1.25 times rubble required than the actual Labour mason Unskilled labour ( 2 nos per mason) Add for corner stones

0.46 0.7

150 80

69 56 87 One mason pair to do 150cft. (I.e.4.52 cum) of rubble masonary

Page 12

backup calculation

add for face dressing of stones

0.24

175.00

41.22

One mason can do 150 cft. Of face dressing For corner stones preparation , assuming 3.0m length & 1.5m height, corner stones required 30nos @ 5/- for (.38*3*1.5 = 1.71 cum. I.e 150/1.71 = 87rs. Per cum. Unskilled labour 2 nos. for 1 hour for 3 sqm area For 1sqm. I.e .35 x .2 = 0.07 cum of sand required. (150 per brass) Rate per cum.

253.22 Scaffolding etc. Sand screening 0.083 0.07 80 53 6.64 3.7 10.4 29.7

Providing & fixing 150 thk.hollow block 24nos. Of blocks of 150*150*300 are required for 1sqm. Labour mason Unskilled labour (2 nos)

0.11 0.11

150 80

16.5 8.8 25.3 6.64 1.6 8.2 One mason pair & 2 male coolie to do 18sqm.. Of BBM (2 brass) Unskilled labour 2 nos. for 1 hour for 3 sqm area For 1sqm. I.e .15 x .2 = 0.03 cum of sand required. (150 per brass) 18.5873606

Scaffolding etc. Sand screening

0.083 0.03

80 53

0.193

Providing & fixing 200 thk.hollow block 13nos. Of blocks of 200*200*400 are required for 1sqm. Labour mason Unskilled labour (2 nos)

0.11 0.11

150 80

16.5 8.8 One mason pair & 2 male coolie to do 18sqm.. Of BBM

Page 13

backup calculation

25.3 Scaffolding etc. Sand screening 0.083 0.04 80 53 6.64 2.1 8.8 Unskilled labour 2 nos. for 1 hour for 3 sqm area For 1sqm. I.e .2 x .2 = 0.04 cum of sand required. (150 per brass)

Providing & fixing 100 thk.Siporex block 24nos. Of blocks of 150*150*300 are required for 1sqm. Labour mason Unskilled labour (2 nos)

0.11 0.11

150 80

16.5 8.8 25.3 6.64 1.1 7.7 One mason pair & 2 male coolie to do 18sqm.. Of BBM (2 brass) Unskilled labour 2 nos. for 1 hour for 3 sqm area For 1sqm. I.e .1 x .2 = 0.02 cum of sand required. (150 per brass)

Scaffolding etc. Sand screening

0.083 0.02

80 53

Providing & fixing 150 thk.Siporex block 24nos. Of blocks of 150*150*300 are required for 1sqm. Labour mason Unskilled labour (2 nos)

0.122 0.122

150 80

18.3 9.76 28.06 6.64 1.6 8.2 One mason pair & 2 male coolie to do 18sqm.. Of BBM (150 sft. = 16.4 Sqm.) Unskilled labour 2 nos. for 1 hour for 3 sqm area For 1sqm. I.e .15 x .2 = 0.03 cum of sand required. (150 per brass)

Scaffolding etc. Sand screening

0.083 0.03

80 53

Page 14

backup calculation

Providing & fixing 200 thk.Siporex block 13nos. Of blocks of 200*200*400 are required for 1sqm. Labour mason Unskilled labour (2 nos)

0.122 0.122

150 80

18.3 9.76 28.06 6.64 2.1 8.8 One mason pair & 2 male coolie to do 18sqm.. Of BBM (150 sft. = 16.4 Sqm.) Unskilled labour 2 nos. for 1 hour for 3 sqm area For 1sqm. I.e .2 x .2 = 0.04 cum of sand required. (150 per brass) 18.75

Scaffolding etc. Sand screening

0.083 0.04

80 53

Providing & laying 12mmthk. Internal neeru plaster

Labour mason Unskilled labour (2 nos)

0.1 0.2

200 80

20 16 36 6.64

One mason can do 10 sqm. Of plaster Unskilled labour 2 nos. for 1 hour for 3 sqm area For 1sqm. I.e 1 x .012 = 0.012 cum of sand required. (150 per brass I.e. 53 / cum)

Scaffolding etc.

0.083

80

Sand screening

0.012

53

0.6 7.3

Providing & laying 25mmthk. Double coat plaster 19mm of Ist coat in 1:5 & 6mm 2nd coat of 1:4 Labour mason

0.13

200

26

Page 15

backup calculation

Unskilled labour (2 nos)

0.27

80

21.6 47.6 6.64 1.3 8.0

One mason can do 7to 8 sqm. Of plaster & unskilled labour @2 per mason Unskilled labour 2 nos. for 1 hour for 3 sqm area For 1sqm. I.e 1 x .025 = 0.025 cum of sand required. (150 per brass)

Scaffolding etc. Sand screening

0.083 0.025

80 53

Providing & laying waterproof plaster for toiletsun/sides & Tanks 19mm of Ist coat in 1:4 & 6mm Final coat of cement Labour mason Unskilled labour (2 nos) Unskilled labour (2 nos)

0.2 0.27 0.2

225 80 80

45 21.6 16 82.6 6.64 1.3 8.0 One mason can do 5 sqm. Of plaster & unskilled labour @2 per mason Unskilled labour at 2 nos can clean upto 10sqm. Area for receiving plaster Unskilled labour 2 nos. for 1 hour for 3 sqm area For 1sqm. I.e 1 x .025 = 0.025 cum of sand required. (150 per brass)

Scaffolding etc. Sand screening

0.083 0.025

80 53

Providing & laying sunk pointing to brickwork

Labour mason Unskilled labour (2 nos) Unskilled labour (2 nos)

0.1 0.1 0.05

225 80 80

22.5 8 4 34.5 6.64 One mason can do 10 sqm. Of pointing & unskilled labour @1 per mason Unskilled labour at 1 nos can clean upto 20sqm. Area for receiving poitnting Unskilled labour 2 nos. for 1 hour for 3 sqm area

Scaffolding etc.

0.083

80

Page 16

backup calculation

Sand screening

0.008

53

0.4 7.1

For 1sqm. I.e (1 x .025)*.3 = 0.008 cum of sand required. (150 per brass)

Providing & laying sunk pointing to Stone masonary Labour mason Unskilled labour (2 nos) Unskilled labour (2 nos)

0.1 0.13 0.05

225 80 80

22.5 10.4 4 36.9 6.64 0.4 7.1 One mason can do 7.5 sqm. Of pointing & unskilled labour @1 per mason Unskilled labour at 1 nos can clean upto 20sqm. Area for receiving poitnting Unskilled labour 2 nos. for 1 hour for 3 sqm area For 1sqm. I.e (1 x .025)*.3 = 0.008 cum of sand required. (150 per brass)

Scaffolding etc. Sand screening

0.083 0.008

80 53

Providing & laying 20mmthk. single coat plaster 20mm one coat in 1:5 Labour mason Unskilled labour (2 nos)

0.1 0.27

200 80

20 21.6 41.6 6.64 1.1 7.7 One mason can do 10 sqm. Of plaster & unskilled labour @2 per mason Unskilled labour 2 nos. for 1 hour for 3 sqm area For 1sqm. I.e (1 x .02) = 0.02 cum of sand required. (150 per brass)

Scaffolding etc. Sand screening

0.083 0.02

80 53

Providing & laying 12mmthk.backcoat to dado works

Labour mason

0.07

200

14

Page 17

backup calculation

Unskilled labour (2 nos)

0.2

80

16 30 6.64 0.6 7.3

One mason can do 15 sqm. Of plaster Unskilled labour 2 nos. for 1 hour for 3 sqm area For 1sqm. I.e (1 x .012) = 0.012 cum of sand required. (150 per brass)

Scaffolding etc. Sand screening

0.083 0.012

80 53

Providing & laying POP over walls & ceiling 20mm one coat in 1:5 Labour mason Unskilled labour (2 nos)

0.1 0.1

225 80

22.5 8 30.5 8 One mason can do 10 sqm. Of plaster & unskilled labour @1 per mason Unskilled labour 1 nos. for 0.5 hour for 4.35 sqm area ( 1 / .23 = 4.35 sqm.)

Scaffolding / sand screening etc. Providing & laying 230thk. Soling

0.1

80

20mm one coat in 1:5 Labour mason Unskilled labour (2 nos)

0.1 0.1

225 80

22.5 8 30.5 8 One mason can do 10 sqm. Of plaster & unskilled labour @1 per mason Unskilled labour 1 nos. for 0.5 hour for 4.35 sqm area ( 1 / .23 = 4.35 sqm.)

Scaffolding / sand screening etc. RCC M20 for sloping slab Labour For pouring Male coolie Female coolie

0.1

80

1.25 1.25

80 80

100 100 200

Assuming that one pair of labour to 0.8 cum of slab concreting 1.25

Page 18

backup calculation

Mason for finishing Carpenter for shuttering ( 8sqm per cum.) Helper for shuttering Add for deshuttering @ 35% Material cost of shuttering Area of shuttering = 7sqm. Per cum of concrete, for each Sqm. Cost = 87.5 , add 10/- for shuttering oil & nails

0.13 1.33 1.33

150 130 100

19.5 172.9 133 107.065 412.965

Two masons can do finishing of 150 sqm. Of slab One carpenter can do 6 sqm. Per day One helper can do 6 sqm. Per day

682.5 RCC M20 for Cantilever slabs upto 2.0m span Labour For pouring Male coolie Female coolie 1 1 80 80 80 80 160

Hire charges for plate = 20/- per month, we have two uses per month, i.e rate per sqm = 20, add for wooden runners 4x4 @ 3no. per sqm.(37.5/-), add for ballies at 2.5*120/10(30) = 20+37.5+30 = 87.5/-

Assuming that one pair of labour to 1 cum of slab concreting 1.25

Mason for finishing Carpenter for shuttering ( 7 sqm per cum.) Helper for shuttering Add for deshuttering @ 35% Material cost of shuttering Area of shuttering = 7 sqm. Per cum of concrete, for each Sqm. Cost = 117.5 , add 10/- for shuttering oil & nails

0.07 1.17 1.17

150 130 100

10.5 152.1 117 94.185 363.285

Two masons can do finishing of 200 sqm. Of slab of 150mm thk. One carpenter can do 6 sqm. Per day One helper can do 6 sqm. Per day

892.5

Hire charges for plate = 20/- per month, we have two uses per month, i.e rate per sqm = 20, add for wooden runners 4x4 @ 3no. per sqm.(37.5/-), add for ballies at (2.5*120)*2/10 i.e. Rs.(60) = 20+37.5+60 = 117.5/117.5

Page 19

backup calculation

RCC M20 forCopings & sills Labour For pouring Male coolie Female coolie 1.33 1.33 80 80 106.4 106.4 212.8

20 66.66666667 Size of coping = 0.15 x .10 Assuming that one pair of labour to 50 Rmt of Coping 1.333333333

Mason for finishing Carpenter for shuttering (20sqm per cum.) Helper for shuttering Add for deshuttering @ 35% Material cost of shuttering Area of shuttering =13 sqm. Per cum of concrete, for each Sqm. Cost = 764 / 15 = 50.93 , add 10/for shuttering oil & nails

0.44 2 2

150 130 100

66 260 200 161 621

one masons can do finishing of 100 Rmt. Of coping One carpenter can do 10 sqm. Per day One helper can do 10 sqm. Per day

1220

1000 rs. For plywood + 1200 rs. For wooden runner = (1000+1200)/2.88 = 764 rs. Per Sqm. 50.93333333

IPS 50mm thk. Labour For pouring Assuming that one pair of labour to 10 sqm of IPS (4 panels of 2.5 sqm I.e. =1.58x1.58)

Male coolie Female coolie

0.1 0.1

80 80

8 8 16

Mason for finishing Mason helper

0.1 0.1

150 80

15 8 23

one masons can do finishing of above 4 panels of 10 sqm.

Page 20

backup calculation

Carpenter for shuttering ( 7 sqm per cum.) Helper for shuttering Add for deshuttering @ 35%

0.034 0.034

130 100

4.42 3.4 2.737 10.557

One carpenter can do shuttering of about 6.0sqm per day One carpenter can do shuttering of about 6.0sqm per day area = 4x1.58x3x.05 = .948 sqm. Shutt per sqm of IPS = 1.264/10 = 0.0948 Wooden runners of 4"x3" of 2.0m long cost = (4x3/144)*1.58*3.28*12*225 = 467/-, with 20uses = 23.35

Material cost of shuttering Area of shuttering = 0.1sqm. Per sqm of IPS Cost of shutt =23.35 x.1 = 2.35, add 1/- for shuttering oil & nails

IPS 50mm thk. Labour For pouring Assuming that one pair of labour to 10 sqm of IPS (4 panels of 2.5 sqm I.e. =1.58x1.58)

Male coolie Female coolie

0.1 0.1

80 80

8 8 16

Mason for finishing Mason helper

0.1 0.1

150 80

15 8 23

one masons can do finishing of above 4 panels of 10 sqm.

For Kitchen Otta ; Assuming the size of Kitchen otta = 3.0m x 0.75m x 0.810m Ht. Material cost Kaddappa Base 2.46 vertical support 1.215 Granite 3.675 top 2.34 Facia in length & Ht. 0.376 Granite shelf (1.5x.75) 1.125 3.85 4.0425

812.8

220.00 220.00 1695.00 1695.00 1695.00

541.2 267.3 3973.72 637.32 1906.88

Page 21

backup calculation

4.2299125

Box type waterproofing Labour For laying shahabad over mortar bed of 40mm Assuming that one pair of labour to 10 sqm of IPS (4 panels of 2.5 sqm I.e. =1.58x1.58)

Male coolie Mason

0.1 0.1

80 80

8 8 16

Mason for finishing Mason helper

0.1 0.1

150 80

15 8 23

one masons can do finishing of above 4 panels of 10 sqm.

Page 22

backup calculation

ply battem

ballies

1.34

Page 23

backup calculation

0.375

1.5625

Page 24

backup calculation

Page 25

backup calculation

2.0875

Page 26

backup calculation

Page 27

backup calculation

2.00

Page 28

backup calculation

1.25

Page 29

Rate analysis Site: 0 Computer Code No. : Item No. : 23 Description : Ext. Plaster single coat mortor ratio (1:5) Location : Pune Default Date : P1 Revised on Date : Unit : Jan 0, 00 14-08-06 per sqm

Providing sand faced plaster externally in cement mortor in all position for a coat of 15 to 20mm thk. in c.m. 1:5 finishing the surface taking out grains and curing for twenty one days scaffolding etc. complete.

Sr.No. Particulars 1 Materials : a) Cement b) Sand

Quantity 0.16 0.03

Unit Bags Cum

Rate per 215.00 1060.00

Amount 34.40 31.80

Labours : for Plastering

1.00

Sqm

41.60

41.60

Centering & Shuttering Nil Others Scaffolding & sand screening charges

1.00

Sqm

7.70

7.70

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

115.50 2.31 0.58 0.00 118.39 17.76 136.15

Say Rs.

136 /- Per

per sqm

Prepared by : Name : _________________________________ Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/PLAST/V/4 Description : External Plastering Double coat Location : Pune Default Date : P2 Revised on Date : Unit : Jan 0, 00 14-08-06 per sqm

Providing & applying 23 mm av. Th 1:3 c.m. sand faced plaster in 2 coats (base coat of 15 mm th and finishing coat of 8 mm th) to concrete & brick surfaces, risers or otherwise including mixing plasticizers & waterproofing compound supplied free as directed as including curing, scaffolding, corners, & edges, bands, splays, grroves, drips, offsets (for which no extra payment will be made) curing etc. complete.

Sr.No. Particulars 1 Materials : a) Cement b) Sand

Quantity 0.22 0.03

Unit Bags Cum

Rate per 245.00 1060.00

Amount 53.90 31.80

Labours : for Plastering

1.00

Sqm

47.60

47.60

Centering & Shuttering Nil

Others Scaffolding & sand screening charges

1.00

Sqm

7.97

7.97

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B)

141.27 2.83 0.71 0.00 144.80

Over head & Profit

15.00%

on total (B) TOTAL

21.72 166.52

Say Rs. Prepared by : Name : _________________________________

167 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/PLAST/V/2 Description : Location : Pune Default Date : P3 Revised on Date : Unit : Internal Neeru Plaster CM (1:4)-12mm thk. Jan 0, 00 14-08-06 per sqm

Providing & applying av. 12 mm thick 1:4 C.M. plaster with Neeru finish to concrete and brick surfaces including scaffolding, curing etc. complete and also including corners, edge bands, splays, grooves, offsets etc. for which which no extra payment will be made.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Neeru

Quantity 0.13 0.01 0.10

Unit Bags Cum Bags

Rate per 245.00 1060.00 50.00

Amount 31.85 14.84 5.00

Labours : for Plastering

1.00

Sqm

36.00

36.00

Centering & Shuttering Nil

Others Scaffolding charges

1.00

Sqm

7.28

7.28

TOTAL (A) 5 Tools & Plants Charges 2.00% on total (A)

94.97 1.90

6 7

Water charges Electricity Charges

0.50% 0.00%

on total (A) on total (A) TOTAL (B)

0.47 0.00 97.34 14.60 111.94

Over head & Profit

15.00%

on total (B) TOTAL

Say Rs. Prepared by : Name : _________________________________

112 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/PLAST/V/1 Description : Location : Pune Default Date : P4 Revised on Date : Unit : Internal Neeru Plaster CM (1:4) - 20mm thk. Jan 0, 00 14-08-06 per sqm

Providing & applying av. 2 cm thick 1:4 C.M. plaster with Neeru finish to concrete and brick surfaces including scaffolding, curing etc. complete and also including corners, edge bands, splays, grooves, offsets etc. for which which no extra payment will be made.

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Neeru

Quantity 0.17 0.02 0.10

Unit Bags Cum Bags

Rate per 245.00 1060.00 50.00

Amount 41.65 25.44 5.00

Labours : for Plastering work

1.00

Sqm

36.00

36.00

Centering & Shuttering

Others Scaffolding charges

1.00

Sqm

7.28

7.28

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

115.37 2.31 0.58 0.00 118.25 17.74 135.99

Say Rs. Prepared by : Name : _________________________________

136 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : ITEM NO - FDAPL/PLAST/V/10 Unit : Description : Waterproof plaster per sqm Location : 0 Default Date : P2 Revised on Date :

14-08-06

Extra for providing chemical admixtures in plastering for waterproofing as per manufacturer's specifications.( Pidilite / Laticrete / Roffee/ Fosroc or any other approved make)

Sr.No. Particulars 1 Materials : a) Cement b) Sand c) Waterproofing compound

Quantity 0.34 0.03 0.34

Unit Bags Cum Kg.

Rate per 245.00 1060.00 40.00

Amount 83.30 31.80 13.60

Labours : for Plastering

1.00

Sqm

90.86

90.86

Centering & Shuttering

Nil 4 Others Sand screening & material shifting

1.00

Sqm

7.97

7.97

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

227.53 4.55 1.14 0.00 233.21 34.98 268.20

Say Rs. Prepared by : Name : _________________________________

268 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item no - FDAPL/PLAST/V/8 Location : 0 Default Date : P2 Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Description : Pointing to brick masonary Providing and making flush groove pointing to brick / block / stone masonry in C:M 1:3 including scaffolding, curing, cleaning complete with all labour and material.

Sr.No. Particulars 1 Materials : a) Cement b) Sand

Quantity 0.03 0.01

Unit Bags Cum

Rate per 245.00 1060.00

Amount 7.35 5.30

Labours : for Pointing

1.00

Sqm

34.50

34.50

Centering & Shuttering Nil

Others Sand screening & scaffolding

1.00

Sqm

7.06

7.06

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

54.21 1.08 0.27 0.00 55.57 8.34 63.90

Say Rs. Prepared by : Name : _________________________________

64 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : 24 / IV 6 Description : Pointing to Stone masonary Providing and making sunk pointing to brick or stone masonry in C:M 1:3 including scaffolding, curing, cleaning etc complete with all labour and material. Sr.No. Particulars Quantity Unit 1 Materials : a) Cement 0.11 Bags b) Sand 0.01 Cum 0.00 0.00 0.00 Location : 0 Default Date : P2 Revised on Date : Unit :

14-08-06 per sqm

Rate per 245.00 1060.00 0.00 0.00 0.00 0.00

Amount 26.95 5.30 0.00 0.00 0.00 0.00

Labours : for Pointing

1.00 0.00 0.00 0.00

Sqm

36.90 0.00 0.00 0.00

36.90 0.00 0.00 0.00

Centering & Shuttering Nil

Others Sand screening & scaffolding

1.00 0.00 0.00

Sqm

7.06 0.00 0.00

7.06 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

76.21 1.52 0.38 0.00 78.12 11.72 89.84

Say Rs. Prepared by : Name : _________________________________

90 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : 26 / IV 10 Description : Providing POP plaster to walls P/A POP plaster to walls Location : 0 Default Date : P4 Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Sr.No. Particulars 1 Materials : a) POP

Quantity 0.13 0.00 0.00 0.00 0.00 0.00

Unit Bags Cum Bags

Rate per 0.00 0.00 0.00 0.00 0.00 0.00

Amount 0.00 0.00 0.00 0.00 0.00 0.00

Labours : for POP work

1.00 0.00 0.00 0.00

Sqm

0.00 0.00 0.00 0.00

0.00 0.00 0.00 0.00

Centering & Shuttering

Others Scaffolding charges

1.00 0.00 0.00

Sqm

0.00 0.00 0.00

0.00 0.00 0.00

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.50% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 0.00% on total (B) TOTAL

0.00 0.00 0.00 0.00 0.00 0.00 0.00

Say Rs. Prepared by : Name : _________________________________

0 /- Per

per sqm

Sign: ________________

Rate analysis Site: 0 Computer Code No. : Item No. : 26 Location : 0 P4 Default Date : Revised on Date : Unit :

Jan 0, 00 14-08-06 per sqm

Description :

Back coat for dado work 1:4)

Providing & applying av. 12 cm thick 1:4 C.M. plaster without Neeru finish to concrete and brick surfaces including scaffolding, curing etc. complete and also including corners, edge bands, splays, grooves, offsets etc. for which which no extra payment will be made.(behind tile dado)

Sr.No. Particulars 1 Materials : a) Cement b) Sand

Quantity 0.13 0.01

Unit Bags Cum

Rate per 245.00 1060.00

Amount 31.85 10.60

Labours : for Plastering work

1.00

Sqm

30.00

30.00

Centering & Shuttering

Others Scaffolding charges

1.00

Sqm

7.28

7.28

TOTAL (A) 5 6 7 Tools & Plants Charges Water charges Electricity Charges 2.00% 0.50% 0.00% on total (A) on total (A) on total (A) TOTAL (B) 8 Over head & Profit 15.00% on total (B) TOTAL

79.73 1.59 0.40 0.00 81.72 12.26 93.98

Say Rs.

94 /- Per

per sqm

0.013

0.304 0.00608 0.17024 0.02432 0.1354

0.034

Rate analysis Site: 0 Computer Code No. : Item No. : FDAPL/RCC/III/22 Description : Location : Pune Default Date : R1 Revised on Date : Unit : Reinforcement works

14-08-06 MT

Providing and laying in position reinforcemnt steel of various diameters incluidng cutting bending, binding with binding wire for all RCC work like footings, columns, beams, slabs, paradise staircases, chajjas, walls, etc. as per RCC Specialist's design & drawing details with necessary bending, laying, binding, with binding wire, etc. complete. Rate to include all lead & lift.

Sr.No. Particulars 1 Materials : a) Reinforcement steel b) Binding wire

Quantity 1.00 12.00

Unit MT Kg

Rate per 36000.00 38.00

Amount 36000.00 456.00

Labours : for reinforcement works including cutting, bending, binding etc. including T & P etc. complete.

1.00

MT

2143.75

2143.75

Centering & Shuttering Nil Others

TOTAL (A) 5 6 7 8 Tools & Plants Charges Water charges Electricity Charges Over head & Profit 2.00% 0.00% 0.50% 15.00% on total (A) on total (A) on total (A) TOTAL (B) on total (B) TOTAL

38599.75 772.00 0.00 193.00 39564.74 5934.71 45499.46

Say Rs. Prepared by :

45,499 /- Per

MT

Name : _________________________________

Sign: ________________

Site Name : 0 Location : Pune SINGLE LINE ESTIMATION Sr.No.


1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50

Description

Unit

Quantity
0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Rate
90 #REF! 107 289 777 3312 2544 #REF! 3281 #REF! 5171 #REF! 5297 #REF! 4428 5427 6281 1985 2335 2439 2086 #REF! 136 167 112 #REF! 334 #REF! #REF! #REF! #REF! 2818 344 327 45499 43578 32 259 0 0 0 0

Excavation in soil and soft murum upto 1.5m depth per cum #REF! #REF! Excavation in Hard Murum & boulders per cum Excavation in Soft Rock per cum Excavation in Hard Rock by chiselling per cum P.C.C. (1 :2:4 ) per cum P.C.C. (1 : 4: 8 ) per cum #REF! #REF! C.C. M20 for Footing, raft per cum #REF! #REF! C.C. M20 for superstructure Columns per cum #REF! #REF! C.C. M20 for floor Beams per cum #REF! #REF! C.C. M20 for slab per cum C.C. M20 for Staircase per cum RCC M20 for Pardi, fins per cum UCR In plinth per cum Brick masonary 35cm thk. Below plinth per cum Brick work 35cm thk. In superstructure per cum Plinth Masonry 23cm thk #REF! #REF! #REF! Ext. Plaster single coat mortor ratio (1:5) per sqm External Plastering Double coat per sqm Internal Neeru Plaster CM (1:4)-12mm thk. per sqm #REF! #REF! Grey Mosaic Tile Flooring of 25cm x 25cm per sqm #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! Brickbat water proofing for toilets per Cum Brickbat water proofing for terrace per sqm Chemical w/p for terrace, toilets per sqm Reinforcement works MT Structural steel works per Sqm. 12mm dia. Fan hook per No. Chainlink fencing per Sqm. 0 0 0.03 0 0.005 0 0.005

Total :

0 Pune SINGLE LINE ESTIMATION Amount


0.00 #REF! 0.00 0.00 0.00 0.00 0.00 #REF! 0.00 #REF! 0.00 #REF! 0.00 #REF! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #REF! 0.00 0.00 0.00 #REF! 0.00 #REF! #REF! #REF! #REF! 0.00 0.00 0.00 0.00 0.00 0.00

#REF!

You might also like