INSTRUCTION: This examination will test your comprehension onArchitectural Professional Practice. Write your answers in the space provided for the Identification and Explanation types, and shade the letter of your answer in the answer sheet for the Multiple Choice type. PART 1 PART 2 PROFESSIONAL REGULATORY LAWS ARCHITECTURAL SERVICES SCORE

PART 1: PROFESSIONAL REGULATORY LAWS


1. Statutory Laws are: a. Canon Laws b. Civil laws c. Common Laws d. Legislative Laws

2. Non-statutory Laws are: a. Canon Laws b. Civil laws a. Administrative Code c. Law on Eminent Domain

c. Common Lawsd. Legislative Laws b. Law on Absolute Acquisition d. Law on Variance

3. The common law giving the state an absolute right to acquire private properties for government development projects.

4. An administrative exception to land use regulations in order to compensate for a deficiency in a real property. a. Administrative Code b. Law on Absolute Acquisition c. Law on Eminent Domain d. Law on Variance 5. 6. 7. 8. 9. The Philippine Environmental Code. a. PD 442b. PD 1152 c. RA 6639 The Condominium Law of 1966. a. BP 220 b. PD 957 The Philippine Arbitration Law. a. EO 546 b. PD 1067 Intellectual Property Code of the Philippines a. RA 3019 b. RA 7160 d. RA 10000 c. RA 386 c. RA 876 c. RA 8293 d. RA 4726 d. RA 7160 d. RA 8974

Law on Acquisition of Right-of-Way, Site or Location for National Government Infrastructure Project. a. RA 3019 b. RA 8293 c. RA 8797 d. RA 8974

10. Civil liability of the architect for the structures he or she designs, under article 1723 of the Civil Code of the Philippines. a. 10 years b. 15 years c. 20 years d. 25 years

PP+G.1

thebrown bauhausSTUDIO ARCHITECTURE


COMPREHENSIVE ARCHITECTURE LICENSURE EXAMINATION REVIEW + PREPARATION PROGRAM

COMPREHENSIVE EVALUATION COURSE


All rights reserved. No part of this study material may be reproduced, stored in a retrieval system, or transmitted by any means, electronic, photocopying, recording, or otherwise, without the prior permission of The Brown Bauhaus Studio Architecture. CEC-CALERPP SERIES OF 2012

PD 1096: NATIONAL BUILDING CODE OF THE PHILIPPINES 11. How many years of diversified and professional experience in building design and construction is the qualification requirement for a Building Official? a. 3 years b. 5 years c. 7 years d. 10 years 12. What is the minimum least dimension for kitchen? a. 1.20 m b. 1.40 m c. 1.50 m d. 1.80 m

13. What is the minimum floor-ceiling height of a habitable room, in a 1-strorey building, provided with artificial ventilation? a. 2.10 m b. 2.40 m c. 2.70 m d. 2.90 m 14. What is the minimum floor-ceiling height of the 1st floor of a building more than 1 floor of a building, provided with artificial ventilation? a. 2.10 mb. 2.40 m c. 2.70 m d. 2.90 m 15. What is the minimum floor-ceiling height of the 2nd floor of a building more than 1 floor, provided with artificial ventilation? a. 2.10 m b. 2.40 m c. 2.70 m d. 2.90 m 16. What is the minimum floor-ceiling height of the floors after the 2nd in a building more than 2 floors, provided with artificial ventilation? a. 2.10 m b. 2.40 m c. 2.70 m d. 2.90 m 17. What is the minimum floor-ceiling height of the habitable rooms in a building utilizing natural ventilation? a. 2.10 m b. 2.40 m c. 2.70 m d. 2.90 m 18. What us the minimum headroom clearance for a mezzanine? a. 1.60 m b. 1.70 m c. 1.80 m d. 1.90 m 19. What is the minimum allowed projection of footing beyond the property line along a public highway? a. 300 mm b. 400 mm c. 500 mm d. 600 mm 20. What is the required minimum depth of the footing in the above item in order for projection beyond the property line is allowed? a. 1,500 mm b. 2,000 mm c. 2,400 mm d. 2,800 mm 21. What is the minimum horizontal clear distance between the curb and the outermost edge of a marquee? a. 150 mm b. 200 mm c. 250 mm d. 300 mm 22. What is the height required for railings for temporary walkways to give protection to pedestrian during construction? a. 800 mm b. 1,000 mm c. 1,200 mm d. 1,400 mm 23. What us the required width of a temporary walkway for pedestrian during construction? a. 800 mm b. 1,000 mm c. 1,200 mm d. 1,400 mm 24. What is the minimum possible number of entrance/exit door for any building? a. 1 b. 2 c. 3 d. 4 25. How many exits are required for an enclosed stand with occupant load more than 1000? a. 2 b. 3 c. 4 d. 5 26. What is the minimum least dimension for toilets? a. 700mm b. 800 mm c. 900 mm d. 1000 mm

27. What is the minimum floor-ceiling height of a habitable room, in a 1-storey building, without artificial ventilation? a. 2.10 m b. 2.40 m c. 2.70 m d. 2.90 m

PP+G.2

thebrown bauhausSTUDIO ARCHITECTURE


COMPREHENSIVE ARCHITECTURE LICENSURE EXAMINATION REVIEW + PREPARATION PROGRAM

COMPREHENSIVE EVALUATION COURSE


All rights reserved. No part of this study material may be reproduced, stored in a retrieval system, or transmitted by any means, electronic, photocopying, recording, or otherwise, without the prior permission of The Brown Bauhaus Studio Architecture. CEC-CALERPP SERIES OF 2012

28. Abutments shall be allowed on only one (1) side for any R-2 lot type/location. a. True b. FalseNO FIREWALLS/ABUTMENTS ON THE FORNT AND REAR 29. How much open space is required of a corner-through lot for a proposed restaurant? a. 5% b. 10% c. 15% d. 20%APPLICABLE FOR ALL OCCUPANCIES 30. How much open space is required of an end lot for a proposed museum building? a. 20-50% b. 30-50% c. 40-50% d. 50-60%FOR A, B, C, D, E-2, H (INSTITUTIONAL) OCCUPANCY 31. What is the minimum ceiling height of habitable rooms of the second storey of a building? a. 2.10 m b. 2.40 m c. 2.70 m d. 2.90 mSECTION 805 32. What is the least dimension of the minimum size of kitchens? a. 1.00 m b. 1.20 m c. 1.50 m 33. What is the least dimension of the minimum size of toilet and bath? a. 700 mm b. 800 mm c. 900mm d. 1.70 m MINIMUM AREA : 3 SQM d. 1000 mmMINIMMUM AREA : 1.20 SQM

34. What is the least dimension of the minimum size of room for human habitations? a. 2.00 m b. 2.50 m c. 3.00 m d. 3.50 m MINIMUM AREA : 6 SQM 35. Window openings must serve as emergency egress in cases of extreme emergencies. What is the minimum width of the clear opening of such windows? a. 760 mm b. 820 mm c. 870 mm d. 900 mmHEIGHT : 1 M 36. What is the minimum width of easement for it to be allowed with a driveway/carriageway? a. 6.00 m b. 7.00 m c. 8.00 m d. 9.00m 37. What is the required minimum width of easement at urban areas per side of waterway? a. 2.00 m b. 3.00 m c. 4.00 m d. 5.00 m 38. What is the required minimum width of easement at agricultural areas per side of waterway? a. 20.00 m b. 30.00 m c. 40.00 m d. 50.00 m FOREST AREAS : 40 M 39. What is the minimum width of roadway/carriageway of multiple dwelling units of up to six (6) units? a. 3.00 m b. 3.50 m c. 4.00 m d. 4.50 m 40. What is the minimum width of sidewalk on each side of multiple dwelling units of up to six (6) units? a. 500 mm b. 600 mm c. 750 mm d. 800 mm 41. What is the minimum total width of Road Right-of-Way of multiple dwelling units of more than 35 units? a. 7.80 m b. 8.70 m c. 9.60 m d. 10.00 mROADWAY: 6.70 M SW: 1.00 M 42. A minimum total width of Road Right-of-Way of 7.00 m is required for how many units of multiple dwelling units? a. 7-15 units b. 16-25 units c. 26-35 units d. 31-40 unis 43. What is the minimum width of access road for turn coats and cul-de-sacs? a. 3.00 m b. 4.00 m c. 5.00 m d. 6.00 m 44. What is the Range of Required Sidewalk and Planting Strip Widths (total of both sides of RROW) for a RROW 30.00 m and above? a. From 1/4 up to 1/3 of RROW width b. From 1/6 up to 1/4 of RROW width c. From 1/6 up to 1/3 of RROW width d. From 1/8 up to RROW width 45. What is the total minimum planting strip width (within and per sides of RROW) for a 25.00-29.00-meter wide RROW? a. 400 mm b. 500 mm c. 600 mm d. 700 mm

PP+G.3

thebrown bauhausSTUDIO ARCHITECTURE


COMPREHENSIVE ARCHITECTURE LICENSURE EXAMINATION REVIEW + PREPARATION PROGRAM

COMPREHENSIVE EVALUATION COURSE


All rights reserved. No part of this study material may be reproduced, stored in a retrieval system, or transmitted by any means, electronic, photocopying, recording, or otherwise, without the prior permission of The Brown Bauhaus Studio Architecture. CEC-CALERPP SERIES OF 2012

46. What is the total minimum planting strip width (within and per sides of RROW) for a 10.00-19.00-meter wide RROW? a.400 mm b. 500 mm c. 600 mm d. 700 mm 47. A planting strip is optional for a RROW with a width below: a. 6.00 m b. 7.00 m c. 8.00 m d.10.00 m

48. What is the minimum clear distance of the central light well and ventilation shaft for basements? a. 2.00 m b. 2.50 m c. 3.00 m d. 3.50 m 49. What is the minimum clear distance of the secondary/support angular light well and ventilation shaft for basements? a. 1.20 m b. 1.50 m c. 1.80 m d. 2.00 m 50. What is the required angle of the angular shaft for basements? a. 40 b. 50 c. 60 51. What is the allowed maximum encroachment of foundations into sidewalk areas? a. 300 mm b. 400 mm c. 500 mm
THE FOUNDATION IS NOT LESS THAN 600 MM BELOW THE ESTABLISHED GRADE

d. 70% d. 600 mm

52. What is the maximum total projection of balconies and appendages to a 4.50 m street? a. 500 mm b. 600 mm c. 700 mm d. 900 mm 53. What is the maximum total projection of balconies and appendages to a 12.00 m street? a. 1,000 mm b. 1,100 mm c. 1,200 mm d. 1,300TABLE X.1 54. What is the minimum clear height of arcaded pedestrian walkways? a. 3.00 m b. 4.00 m c. 5.00 m d. 6.00 m 55. What is the minimum length of a chaflan of a building? a. 3.00 m b. 4.00 m c. 5.00 m d. 6.00 m

56. A 20-seater beer garden pub isrequired to have how many exit(s)? a. 1 b. 2 c. 3 d. 4 57. Which of the following statements is not among the six (6) Grave Violations stipulated in the law? a. Change in the existing use or occupancy without Certificate of Change of Occupancy/Use/Occupation. b. Excavations left open without any work being done in the site for more than one hundred (120) days. c. Non-compliance with order to abate or demolish. d. Non-compliance with work stoppage order for construction/demolition without permit. 58. What is the minimum height requirement of pedestrian railings during construction or demolition in the site? a. 700 mm b. 800 mm c. 900 mm d. 1000 mm 59. What are the three (3) Light Violations stipulated in the law? 60. What are the two (2) Less Grave Violations stipulated in the law? 61. What are the required minimum setbacks for commercial, industrial, institutional and recreational buildings with Road Right-of-Way (RROW) width of 25-29 meters?6 : 3 : 3 62. What are the required minimum setbacks for commercial, industrial, institutional and recreational buildings with Road Right-of-Way (RROW) width of 10-19 meters?5 : 2 : 2
63. Can a footing located at least 2.40 m below grade along national roads be allowed to project beyond the property line? State two (2) conditions.IT MAY PROJECT BUT NOT MORE THAN 300 MM AND IT WILL NOT OBSTRUCT ANY EXISTING UTILITIES/SERVICES

64. What types of structures are exempted from payment of building permit fees? PUBLIC BUILDINGS & INDIGENOUS FAMILY DWELLINGS & INDIGENOUS FAMILY DWELLINGS (THE TOTAL COST SHOULD NOT EXCEED Php 15,000.00)

PP+G.4

thebrown bauhausSTUDIO ARCHITECTURE


COMPREHENSIVE ARCHITECTURE LICENSURE EXAMINATION REVIEW + PREPARATION PROGRAM

COMPREHENSIVE EVALUATION COURSE


All rights reserved. No part of this study material may be reproduced, stored in a retrieval system, or transmitted by any means, electronic, photocopying, recording, or otherwise, without the prior permission of The Brown Bauhaus Studio Architecture. CEC-CALERPP SERIES OF 2012

65. What is the requirement for signs written in any foreign language? SHALL HAVE A CORRESPONDING TRANSLATION IN ENGLISH OR IN THE LOCAL DIALECT Choose A if allowed and B if not allowed the Lot Location/Type of each Building Use/Occupancy. 66. Interior lot for R-1 A 67. End lot for R-2 (medium density housing, BHL of 10 m) A 68. Interior lot for Maximum R-2 (BHL of 15 m) B 69. End lot for Maximum R-3 (high density housing, BHL of 36 m) A 70. Interior lot for R-4 (individual townhouse) B 71. Interior lot for C-1 B 72. Corner-Through lot for C-1 A 74. End lot for C-2 B 73. Interior lot for C-2 B 75. Corner-Through lot for C-3 A

BP 344: LAW TO ENHANCE MOBILITY OF DISABLED PERSONS 76. Ramps must have a slope of not a greater than: a. 1:6 b. 1:10c. 1:12 d. 1:15

77. Ramps must have a intermediate landing of length not less than: a. 1.00 m b. 1.50 m c. 2.00 m d. 2.50 m 78. Ramps must have an intermediate landing at very how many meters in length? a. 2.00 m b. 3.00 m c. 5.00 m d. 6.00 m 79. What is the topmost landing of a ramp must have a length no less than? a. 1.50 m b. 1.80 m c. 2.00 m d. 2.20 m 80. Entrance vestibule must have a width not less than: a. 1.50 m b. 1.80 m c. 2.00 m 81. What is the minimum clear width of ramps? a. 1.00 m b. 1.20 m c. 1.50 m d. 2.20 m d. 1.70 m

82. A length or busy walkways should be provided with points where wheelchair may pass another or maneuver at every: a. 8.00 m b. 10.00 m c. 12.00 m d. 14.00 m 83. To guide the blind, walkways should follow a straight routes with: a. Long sweep turns b. Right angle turns c. Truncated turns 84. Walkway headroom should not be less than: a. 2.00 m b. 2.10 m c. 2.40 m d. 3.00 m d. 1000 mm d. None of the following

85. Handrails should be installed at walkways at no less than: a. 700 mm b. 800 mm c. 900 mm

86. Handrails should be installed at no less than how many millimeters above ramps or steps? a. 700 mm b. 800 mm c. 900 mm d. 1000 mm 87. Handrails should have how many millimeter protective extensions at the beginning and end of ramps or stairs? a. 100 mm b. 200 mm c. 300 mm d. 400 mm 88. All doors shall have a minimum clear width of: a. 800 mm b. 900 mm c. 1000 mm 89. Corridors shall have a minimum clear width of: a. 1.00 m b. 1.20 m c. 1.50 m d. 1200 mm d. 1.80 m

PP+G.5

thebrown bauhausSTUDIO ARCHITECTURE


COMPREHENSIVE ARCHITECTURE LICENSURE EXAMINATION REVIEW + PREPARATION PROGRAM

COMPREHENSIVE EVALUATION COURSE


All rights reserved. No part of this study material may be reproduced, stored in a retrieval system, or transmitted by any means, electronic, photocopying, recording, or otherwise, without the prior permission of The Brown Bauhaus Studio Architecture. CEC-CALERPP SERIES OF 2012

90. A circle of 1.20 m in diameter is a suitable guide in the planning of wheelchair turning spaces. a. True b. False1.50 M 91. How many wheelchair seating spaces are required for a 70-seater assembly place? RULE 3, 7.1.1 (B) a. 2 b. 4 c. 6 d. 8 92. How many wheelchair seating spaces are required for a 470-seater assembly place? a. 2 b. 4 c. 6 d. 8 93. What is the maximum lowest point of a dropped curb from the road or gutter? a. 25 mm b. 30 mm c. 50 mm d. 75 mm 94. What is the minimum width of curb cut-out? a. 600 mm b. 700 mm c. 800 mm d. 900 mm

95. What is the minimum headroom of signages protruding into a walkway or route? a. 1.80 m b. 2.00 m c. 2.20 m d. 2.40 m RA 9514: FIRE CODE OF THE PHILIPPINES 96. A fire involving ordinary combustible materials such as wood, cloth, paper, rubber, and plastic. a. Class A fire b. Class B fire c. Class C fire d. Class D fire 97. A fire involving flammable liquids and gasses. a. Class A fire b. Class B fire c. Class C fire 98. A fire involving energized electrical equipment. a. Class A fire b. Class B fire c. Class C fire d. Class D fire d. Class D fire

99. A fire involving combustible metal such as magnesium, sodium, and potassium. a. Class A fire b. Class B fire c. Class C fire d. Class D fire 100. Who is the official duly designated to head the local fire service where policemen are also performing fire service function? a. Fire Chief b. Fire Director c. Fire General d. Fire Marshal 101. What is the maximum travel distance from any point of a building to the nearest exit if the building is provided with AFSS? a. 41 m b. 46 m c. 61 m d. 70 m 102. What is the maximum number of seats allowed in a row if bounded by aisles? a. 7 b. 14 c. 21 d. 29 103. What is the maximum number of seats allowed in a row if bounded by aisles at one end and a wall at the other end? a. 7 b. 14 c. 21 d. 29 104. In an assembly place serving more than 60 seats, the minimum width of an aisle if it serves seats at both sides. a. 910 mm b. 1,000 mm c. 1,200 mm d. 1,400 mm 105. What is the required size of hose connections for full-scale firefighting of Class I standpipe system? a. 32 mm b. 38 mm c. 64 mm d. 75 mm 106. What is the required size of hose connections for first-aid firefighting of Class II standpipe system? a. 32 mm b. 38 mm c. 64 mm d. 75 mm 107. No point within a building, requiring dry standpipes, shall be more than how many meters of travel distance from a dry standpipe outlet connection? a. 30 m b. 40 m c. 50 m d. 60 m

PP+G.6

thebrown bauhausSTUDIO ARCHITECTURE


COMPREHENSIVE ARCHITECTURE LICENSURE EXAMINATION REVIEW + PREPARATION PROGRAM

COMPREHENSIVE EVALUATION COURSE


All rights reserved. No part of this study material may be reproduced, stored in a retrieval system, or transmitted by any means, electronic, photocopying, recording, or otherwise, without the prior permission of The Brown Bauhaus Studio Architecture. CEC-CALERPP SERIES OF 2012

108. Dry standpipes can be concealed in building walls or built into pilasters. a. True b. False 109. Fittings and connections of dry standpipes are required to withstand how much water pressure during service? a. 100 psi b. 200 psi c. 250 psi d. 300 psi 110. What is the required slope of the horizontal runs of dry standpipes? a. 5% b. 10% c. 15% d. 20% 111. What is the required minimum area per floor of hazardous storage and business and mercantile occupancies to have wet standpipe system? a. 1,860 sqm b. 2,350 sqm c. 2,760 sqm d. 3,140 sqm 112. What is the minimum diameter of wet standpipes? a. 32 mm b. 38 mm c. 64 mm 113. What is the minimum diameter of hose of every wet standpipe outlet? a. 32 mm b. 38 mm c. 64 mm d. 75 mm d. 75 mm

114. Where the occupant load served does not exceed three, spiral stairs shall be permitted, provided that the following criteria are met that the clear width of the stairs shall be not less than: a. 585 mm b. 660 mm c. 700 mm d. 745 mm 115. Referring to the item above, what is the maximum height of risers? a. 180 mm b. 210 mm c. 240 mm 116. What is the minimum size of handrails on stairs? a. 67 cm b. 70 cm c. 76 cm d. 2.70 m d. 80 cm

117. Metal latches should be provided to lock swinging stairs section in up position shall be installed. a. True b. False 118. What is the minimum size of ladder rungs as fire escape? a. 22 mm b. 25 mm c. 27 mm d. 29 mm

119. The lowest rung of any ladder shall be not more than how many millimeters above the level of the ground or balcony floor beneath it? a. 305 mm b. 405 mm c. 505 mm d. 605 mm 120. Emergency lighting facilities shall be arranged to maintain the specified degree of illumination in the event of failure of the normal lighting for a period of at least how many hours? a. 1 hr b. 1.5 hrs c. 2 hrs d. 2.5 hrs 121. What is the minimum dimension of emergency evacuation plan posted on every strategic locations of a building? a. 8.5 X 11 b. 8.5 X 13 c. 8.5 X 15 d. 8.5X`6 122. What is the minimum size of combination standpipe system? a. 100 mm b. 150 mm c. 200 mm d. 250 mm

123. For a moderate type A hazard, what is the maximum travel distance to a fire extinguisher? a. 10 m b. 12 m c. 15 m d. 18 m 124. What is the maximum travel distance to an exit from any point in a building without an approved, supervised automatic sprinkler system? a. 46 m b. 53 m c. 61 m d. 66 m

PP+G.7

thebrown bauhausSTUDIO ARCHITECTURE


COMPREHENSIVE ARCHITECTURE LICENSURE EXAMINATION REVIEW + PREPARATION PROGRAM

COMPREHENSIVE EVALUATION COURSE


All rights reserved. No part of this study material may be reproduced, stored in a retrieval system, or transmitted by any means, electronic, photocopying, recording, or otherwise, without the prior permission of The Brown Bauhaus Studio Architecture. CEC-CALERPP SERIES OF 2012

Give six (6) building types that are mandatory to have automatic fire department notification. 125. ALL HIGH RISE BUILDINGS 126. SHOPPING MALLS 127. SCHOOLS 128. HOTELS 129. HOSPITAL 130. HAZARDOUS OCCUPANCIES

PART 2: ARCHITECTURAL SERVICES 131. The minimum Basic Fee of Architects for the design of simple structures. a. 6% b. 8% c. 10% d. 12% 132. The minimum Basic Fee of Architects for the design of complex structures. a. 6% b. 7% c. 8% 133. The Minimum Basic Fee of Architects for the design of residential structures. a. 8% b. 10% c. 12% 134. The Minimum Basic Fee of Architects for the design of monumental structures. a. 8% b. 10% c. 12% d. 10% d. 15% d. 15%

135. The Minimum Basic Fee of Architects for the design of structures of moderate complexity. a. 7% b. 10% c. 12% d. 15% 136. The minimum Basic Fee of Architects for people involving intricate designs. a. 10% b. 12% c. 15% d. 17%

137. The Minimum Basic Fee of Architects for the 11th unit in a housing project. a. 20% of the MBF for the 1st unit b. 25% of the MBF for the 1st unit st c. 30% of the MBF for the 1 unit d. 35% pf the MBF for the first unit 138. The Minimum Basic Fee of Architects for the 11th unit in a repetitive project. a. 30% of the MBF for the 1st unit b. 40% of the MBF for the 1st unit st c. 45% of the MBF for the 1 unit d. 60% of the MBF for the 1st unit 139. How much can an architect bill for a design upon signing of agreement? a. 3% of the MBF b. 5% of the MBF c. 8% of the MBF d. 10% of the MBF

140. As per new SPP, if a project is not constructed for any reason, how much is due for the architect as professional fee? a. 80% of the MBF b. 85% of the MBF c. 90% of the MBF d. 95% of the MBF 141. Per diem means: a. Per day b. Per delivery c. Per dime d. Per week

142. How much is the Professional Fee of an architect serving as expert witness? a.Php 300.00 per appearance b. Php 500.00 per appearance c. Php 1,000.00 per appearance d. Php 2,000.00 per appearance 143. How are architects paid for the pre-design services? a. Gratis b. Lump Sum c.Multiple of direct expense d. Pro-rata Basis 144. The part of the contract documents consisting of a detailed description of the technical nature of the materials, standards, and quality of execution of the work to be placed under contract. a. Estimate b. Bill of materials c. Material order d. Specification 145. Which of the following is not a function of a construction manager? a. Coordination and supervision b. Cost and time control c. Prepare shop drawings d. Quality control of work

PP+G.8

thebrown bauhausSTUDIO ARCHITECTURE


COMPREHENSIVE ARCHITECTURE LICENSURE EXAMINATION REVIEW + PREPARATION PROGRAM

COMPREHENSIVE EVALUATION COURSE


All rights reserved. No part of this study material may be reproduced, stored in a retrieval system, or transmitted by any means, electronic, photocopying, recording, or otherwise, without the prior permission of The Brown Bauhaus Studio Architecture. CEC-CALERPP SERIES OF 2012

146. In a simple project costing Php 1 billion, how much is the architects minimum Professional Fee? a. Php 18.5 million b. Php 28.5 million c. Php 32.5 million d. Php 42.5 million 147. The approved form of security furnished by the Contractor and his Surety as a guarantee of good faith on the part of the Contractor to pay all obligations arising from the Contract. a. Guaranteed bond b. Payment bond c. Performance bond d. Proposal bond 148. A written form of security executed by the bidder as principal and by a surety for the purpose of guaranteeing that the bidder will sign the contract, if awarded the contract, for the stated bid amount. a. Bid bond b. Guaranteed bond c. Proposal bond d. Security bond 149. A specification that stipulates the use of specific products, systems, or processes without provision for substitution. a. Descriptive specification b. Performance specification c. Propriety specification d. Reference specification 150. In the Design-Build by Administration, who is responsible for the compensation of the construction superintendent, purchasing agent, timekeeper, and property clerk rightfully assigned in the project? a. Architect b. Architect + Owner c. Contractor d. Owner 151. The schedule of activities for a project. It shows start and finish dates, critical and non-critical activities, slack time, and predecessor relationships. a. Allele chart b. Gant chart c. Nolan chart d. PERT chart 152. Retention is released within how many months from the date of Final Payment? a. 2 b. 3 c. 4 153. 154. 155. 156. 157. 158. 159. 160. 161. Examining local laws, codes, and ordinances for a Planned Unit Development project falls under what service of the architect? PRE-DESIGN SERVICES d. 5

162. A written communication issued by an owner authorizing a contractor to proceed with the work and establishing the date of commencement of work. 163. A legally enforceable agreement, usually in written form, between two or more parties to do or not to do something specified.

NOTICE TO PROCEED

CONTRACT

PP+G.9

thebrown bauhausSTUDIO ARCHITECTURE


COMPREHENSIVE ARCHITECTURE LICENSURE EXAMINATION REVIEW + PREPARATION PROGRAM

COMPREHENSIVE EVALUATION COURSE


All rights reserved. No part of this study material may be reproduced, stored in a retrieval system, or transmitted by any means, electronic, photocopying, recording, or otherwise, without the prior permission of The Brown Bauhaus Studio Architecture. CEC-CALERPP SERIES OF 2012

164. A method for planning, scheduling, and managing a project, combining all relevant information into a flow chart. 165. Written information adding to, clarifying or modifying the bidding documents. 166. A term used to describe partial construction work performed within an existing structure. Remodeling without a building addition. 167. An offer or proposal of a price. 168. A contractors or consultants overhead expense; expenses indirectly incurred and not chargeable to a specific project or task. 169. Contract drawings marked up to reflect changes made during the construction process. 170. A written document between the owner and the contractor signed by the owner and the contractor authorizing a change in the work or an adjustment in the contract sum or the contract time. 171. All drawings, specifications and addenda associated with a specific construction project. 172. All costs for a specific project including costs for land, professionals, construction, furnishings, fixtures, equipment, financing and any other project related costs. 173. A written range of view or action; outlook; hence, room for the exercise of faculties or function; capacity for achievement; all in connection with a designated project. 174. A section of the conditions of the contract, other than the General Conditions and Supplementary Conditions, which may be prepared for a particular project. Specific clauses setting forth conditions or requirements peculiar to the project under consideration, and covering work or materials involved in the proposal and estimate, but not satisfactorily covered by the General Conditions. What are the activities that under the Pre-Design Services of an 175. Economic feasibility 176. Project financing studies 179. Site selection and 180. Site utilization and landanalysis use studies What is the breakdown of fee of an architect for repetitive documents? 182. 1st structure: MBF 183. 2nd structure: 80% of BF

CRITICAL PATH METHOD

ADDENDUM ALTERATIONS

BID INDIRECT COST (OR EXPENSE)


AS-BUILT DRAWINGS (ALSO KNOWN AS RECORD DRAWINGS)

CHANGE ORDER

CONSTRUCTION DOCUMENTS PROJECT COST

SCOPE OF WORK

SPECIAL CONDITIONS

architect? 177. Architectural programming 181. Promotional services

178. Space studies

management

construction project without amending the original drawing 185. 4th structure: 40% of BF

184. 3rd structure: 60% of BF 186. A landscape design project costing to Php 640, 300 is requiring a submission of the final design, how much will the architect be paid? a. Php 19 209 b. Php 28 813.50 c. Php 48 022.50 d. Php 64 300 187. A design team worked on a master development plan of a housing project in Central

PP+G.10

thebrown bauhausSTUDIO ARCHITECTURE


COMPREHENSIVE ARCHITECTURE LICENSURE EXAMINATION REVIEW + PREPARATION PROGRAM

COMPREHENSIVE EVALUATION COURSE


All rights reserved. No part of this study material may be reproduced, stored in a retrieval system, or transmitted by any means, electronic, photocopying, recording, or otherwise, without the prior permission of The Brown Bauhaus Studio Architecture. CEC-CALERPP SERIES OF 2012

Luzon. The architect rendered 158 hours with a rate of Php 550/hr. His design team includes a design consultant and a staff of five. The consultant charges a rate of Php 800/hr and spent 48 hours in the project. The five members of the staff are to be paid according to the minimum wage policy and they spent 180 hours in the project development. The design team went to the project site thrice and cost the entire travel Php 2 250. What is the method of compensation for this kind of service? a. Mixed method b. Multiple of direct personal expenses c. Percentage fee methodd. Professional fee + expenses 188. Compute for the total fee of the design team? a. Php 19 209 b. Php 28 813.50 c. Php 48 022.50 d. Php 64 300 189. How much is the fee of the architect? a. Php 32 600 b. Php 38 400 c. Php 64 800 d. Php 86 900 190. How much is the fee of the consultant? a. Php 32 600 b. Php 38 400 c. Php 64 800 d. Php 86 900 Identify the five (5) Basic Architectural Documents. 191. 192. 193. 195. Identify the Seven (7) Pre-Design Services of the architect 196. 197. 198. 200. 202. C. Identify the four phases under design services of the architect. 203. 204. 205. 206. 199. 201. 194.

Identify at least five (5) Specialized Allied Services of the architect. 207. 208. 209. 211. Identify three (3) services of the architect during Building Construction. 212. 213. 214. Identify three (3) services of the architect after Building Construction. 215. 216. 217. 210.

PP+G.11

thebrown bauhausSTUDIO ARCHITECTURE


COMPREHENSIVE ARCHITECTURE LICENSURE EXAMINATION REVIEW + PREPARATION PROGRAM

COMPREHENSIVE EVALUATION COURSE


All rights reserved. No part of this study material may be reproduced, stored in a retrieval system, or transmitted by any means, electronic, photocopying, recording, or otherwise, without the prior permission of The Brown Bauhaus Studio Architecture. CEC-CALERPP SERIES OF 2012

Identify the classifications of buildings by occupancy under the National Building Code. 218. 221. 224. 219. 222. 225. 220. 223. 226.

Identify the types of Building construction under the National Building Code. 227. 228. 229. 230.

For ten (10) points, which of the two laws shall prevail over the 1 meter discrepancy on the provision on maximum travel distance from any point of a structure to the nearest exit or exitway? Justify your answer.

For five (5) points, explain the difference between a Project Manager and a Construction Manager.

PP+G.12

thebrown bauhausSTUDIO ARCHITECTURE


COMPREHENSIVE ARCHITECTURE LICENSURE EXAMINATION REVIEW + PREPARATION PROGRAM

COMPREHENSIVE EVALUATION COURSE


All rights reserved. No part of this study material may be reproduced, stored in a retrieval system, or transmitted by any means, electronic, photocopying, recording, or otherwise, without the prior permission of The Brown Bauhaus Studio Architecture. CEC-CALERPP SERIES OF 2012

You might also like