Owner:

Mr. & Mrs. Meyburgh

(Sample Only)
Schedule E3:

COST ESTIMATION / BILL OF QUANTITIES

BILL NO

1
Unit Rate Qty Amount

PRELIMINARY & GENERAL


NOTES

The Preliminaries are to be the JBCC Series 2000 Preliminaries prepared by the Joint Building Contracts Committee, January 2003 edition and shall be deemed to be incorporated herein. Tenderers are referred to the abovementioned documents for the full intend and meaning of each clause thereof (hereinafter referred to by heading and clause number only) for which such allowance must be made as may be considered necessary Where standard clauses or alternatives are not entirely applicable to this contract such modifications, corrections or supplements as will apply are given under each relevant clause heading

Site Establishment
1 2 3 4

Site Office Equipment Site Office/Shed Site Security / Watchman Site Toilet

item month month month item

Total Amount

item

Administration Costs
5 6 7

Signboards Head Office Administration Costs General

item item item item

Total Amount

item

Supervision
8

Site Foreman

month item

Total Amount

item

Total Carried Forward:

Page 2 of 11

Insurances
9

Total Brought Forward:


item item item item item

Insurance on Project

10 Public Liability Insurance 11 Contractors all Risk

Total Amount

item

Cleaning-up Expenses
12 Site Cleaning on Completion 13 Building Cleaning before Occupation 14 Cleaning Site During Construction

item item month item

Total Amount

item

Temporary Works
15 Enclosure of works 16 Water 17 Electricity

item item item item

Total Amount

item

Other
18 Setting out of the works 19 Inspection of the site

item item item

Total Amount

item

Additional Preliminaries.
20 21 22 23 24 Total Amount for Preliminaries & General

item item item item item item

Total Amount

Total Carried Forward to Summary:

Page 3 of 11

BILL NO

2
Unit Rate Qty Amount

PLANT & EQUIPMENT


Plant & Equipment
25 26 27 28 29 Total Amount for Plant & Equipment

item item item item item item

Total Amount

Total Carried Forward to Summary:

BILL NO

3
Unit Rate Qty Amount

EARTHWORKS & EXCAVATIONS


SUBLEMENTARY PREAMBLE

The nature of the ground is assumed to be loose sandy material, therefore "earth", but possibly interspersed with "soft rock" or "hard rock"

Clear site for the whole area of the ground to be built upon up to a distance of at least 1,5m beyond the perimeter of the structure of building's) and/or extent of steps, paving's, etc.

SITE CLEARANCE Site Clearance etc.


30 Clear site for the whole area of the ground to be built upon.
m m Total Amount item 589

FILLING ETC. Filling (Material Only)


31 Earth filling supplied by the contractor (not compacted)

m m

412

Total Amount

item

Total Carried Forward to Summary:

Page 4 of 11

BILL NO

CONCRETE, FORMWORK & REINFORCEMENT


CONCRETE WORK
SUBLEMENTARY PREAMBLE Unit Rate Qty Amount

Standard Strip Footings of the various widths and thickness shown and figured on the drawings or as directed by Engineer

CONCRETE (STRIP FOOTINGS)


Pre-Mix Concrete (Strip Footings) Material Only
25 Mpa Cement Concrete in Strip Footings
32 Ground Floor

m m

82

Total Amount

item

SUBLEMENTARY PREAMBLE
Cast concrete surface beds at least 85mm thick, on waterproofing membrane on compacted fill, halfway on external walls and over internal walls. Compact concrete properly to an even, rough surface to receive cement screeds.

Unit

Rate

Qty

Amount

CONCRETE SURFACE BEDS


Ready Mix Concrete: Surface Beds (Material Only
20 MPa Concrete in:
33 Ground Floor Surface Beds 34 Patio Surface Beds

m m m

38.4 20.4

Total Amount

item

CONCRETE SUSPENDED SLABS AND BEAMS


Suspended Concrete Slabs & Roofs - Rib and Block (Supply and Fit) Complete

35 Suspended Concrete Roofs: 230 mm - Ground Floor 36 Suspended Concrete Roofs: 230 mm - First Floor 37 Suspended Concrete Slabs: 230 mm - First Floor 38 Concrete Roofs: 170 mm - Covered Patio's & Balcony 's 39 Concrete Slab: 170 mm - Open Balcony

m m m m m m

63 15 175 32 31

Total Carried Forward:

Page 5 of 11

Total Brought Forward: Suspended Con. Slabs & Roofs - Rib and Block (Labour)
40 Labour to install Block & Lintels Complete

m m

315

Total Amount

item

Suspended Con. Slabs & Roofs - Rib and Block (Sundries)


41 Pumping Concrete 42 25 Mpa Ready Mix Concrete 43 Transport 44 Engineer 45 Ref. 156 (100 x 100 x 3.55mm) 6 x 2.4 m Sheet

m m item item m m

54 54 315 315 378

Total Amount

item

Concrete Beams and Nibs Complete (Supply & Fit)


46 200 w x 400 h: mm Upstand Beam 47 200 w x 400 h: mm Circular Upstand Beam. 48 200 w x 400 h: mm Circular Upstand Beam.

m m m m

86 26 13

Total Amount

item

Unit

Rate

Qty

Amount

STAIRCASES AND LANDINGS COMPLETE

Insitu Concrete Staircases (Supply & Fit)


49 Concrete 3 to 5 Steps 50 Concrete Dog - Leg Stairs

No No No

3 1

Total Amount

item

Total Carried Forward:

Page 6 of 11

SUBLEMENTARY PREAMBLE
Reinforcement to be protected from the weather, all loose flakes, rust or oiliness to be cleaned of and in coastal situations must be rinsed free of any salt deposits.

Total Brought Forward:

REINFORCEMENT

Unit

Rate

Qty

Amount

Fabric Reinforcement in Concrete Surface Beds.


Material Only
51 Ref: 193 (200 x 200 x 5.6 mm) 6 x 2.4 m Sheet

m item

677

Total Amount

Foundation Reinforcement (Tensile Steel) Supply & Fit


52 Provisional Amount
Attendance item item R 31,463.10 R 31,463.10

Total Carried Forward to Summary:

R 31,463.10

BILL NO
MASONRY

5
Unit Rate Qty Amount

SUBLEMENTARY PREAMBLE
Minimum compressive strength for bricks to a single storey building to be 7MPa and to a multiple storey to be 14MPa to foundations and ground floor. Cement bricks are to comply with SABS 527 and clay bricks with SABS 277.

BRICKWORK Stock Brick - NFP Non-Facing Plaster (Material Only) Patio & Superstructure Foundations (Plinth)
Clay Stock Brick (220w: 105h: 75)
53 Ground Floor

th item

48

Total Amount

Superstructure Brickwork
Clay Stock Brick (220w: 105h: 75)
54 Ground Floor 55 First Floor

th th item

94 53

Total Amount

Total Carried Forward:

Page 7 of 11

Total Brought Forward: Face Brick FBS - Face Brick Standard (Material Only) Brick-on-edge header course copings, sills, etc
56 Brick-on-edge header course copings, sills, etc of Stock bricks

th th

Total Amount

item

Unit

Rate

Qty

Amount

AGGREGATES (SAND, STONE & CEMENT)


Sand, Stone & Cement Building Sand: Foundations Brickwork
Building Sand
57 Ground Floor

m m

53

Total Amount

item

Building Sand: Superstructure Brickwork


Building Sand
58 Lower Basement 59 Ground Floor 60 First Floor

m m m item 104 59

Total Amount

Building Sand: Gable Walls & Extra Over Brickwork


Building Sand
61 Brick-on-edge header course copings, sills, etc .

m item

1.3

Total Amount

Cement (Foundation Brickwork)


Cement Buildcrete 42.5N
62 Ground Floor

bag bag

201

Total Amount

item

Cement (Superstructure Brickwork)


Cement Buildcrete 42.5N
63 Ground Floor 64 First Floor

bag bag item

395 223

Total Amount

Total Carried Forward:

Page 8 of 11

Total Brought Forward: Cement (Gable Walls & Extra Over Brickwork)
Cement Buildcrete 42.5N
65 Brick-on-edge header course copings, sills, etc.

bag bag

Total Amount

item

Unit

Rate

Qty

Amount

BRICKWORK SUNDRIES

Galvanised Brick Reinforcement With Minimum 100mm Laps At Joints and Angles - Material Only
In Foundation Brickwork
66 150 x 2.8 mm Brickeforce (20m) 67 230 x 2.8 mm Brickeforce (20m)

roll roll

53 9

In Superstructure Brickwork
68 75 x 2.8 mm Brickeforce (20m) 69 150 x 2.8 mm Brickeforce (20m) 70 230 x 2.8 mm Brickeforce (20m)

roll roll roll

15 175 8

Total Amount

item

Unit

Rate

Qty

Amount

PRECAST CONCRETE PRESTRESSED LINTELS BEDDED IN CEMENT MORTAR.


100 mm Prestressed fabricated concrete lintels including necessary temporary supports
71 0.9 m 72 1.2 m 73 1.5 m 74 1.8 m 75 2.1 m 76 2.4 m 77 2.7 m 78 3 .0m 79 3.3 m 80 5.4 m 81 Running Meters of Precast Lintels - 110 mm

No No No No No No No No No No No No

4 24 31 4 4 2 10 10 4 12 59

Total Amount

item

Total Carried Forward:

Page 9 of 11

Total Brought Forward: WALL CLADDING Wall Cladding - Stone (Supply & Fit)
Cancel Program Prices
82 Provisional Amount 83 Attendance

Unit

Rate

Qty

Amount

item item

R 131,526.32

R 131,526.32

BRICKLAYER Clear Site & Set Out Project


84 Setting out of the Works 85 Clear Site not exceeding 200 mm girth.

m m m

589 765

Total Amount

item

Bricklayer (Rate / m2 Wall Area) / Item Build Foundations & Patio Brickwork
Lay Brickwork / 1000 Stock Bricks:
86 Ground Floor

th th

48

Total Amount

item

Build Superstructure Brickwork


Lay Brickwork / 1000 Stock Bricks:
87 Ground Floor 88 First Floor

th th th

94 53

Total Amount

item

Extra Over Labour Backfill (Labour Only)


89 Backfilling and Compact under surface beds - 93% AASHTO density

m m

412

Total Amount

item

Total Carried Forward:

Page 10 of 11

Concrete (Labour Only)


90 Lay Concrete Surface bed / m3 (Ready Mix) 91 Cast Ready Mix Concrete: Foundations / m3

Total Brought Forward:


m m m 58.9 81.6

Total Amount

item

Excavation (Labour Only)


Excavation in earth for Strip Footings Trenches and Holes not exceeding
92 1.5m

m m

176

Total Amount

item

Brickwork (Labour Only)


93 Build Braai & Chimney (Stock Bricks) 94 Brick-on-edge header course copings, sills, etc of Stock bricks

item m m

1 57

Total Amount

item

Labour - Other
95 Place Fabric Reinforcement in Position 96 Place USB Green in Position
No m m Total Amount item 677 648

Total Carried Forward to Summary: R 131,526.32

Page 11 of 11

BILL NO

6
Unit Rate Qty Amount

WATERPROOFING
SUBLEMENTARY PREAMBLE

In the event where retaining walls are required between differing floor levels, and in cellars, damp-proofing is to be done by an company approved by the Principal Agent in accordance with the consulting engineers instructions and the Contractor must provide for this. A 10 year guarantee must be supplied in respect of all such waterproofing.

In Walls

One layer 375 micron embossed polyethylene dampproof course (SABS)


roll roll roll item 14 1 3

97 375 Mic. w:225 x 40 m DPC - SABS 98 375 Mic. w:300 x 40 m DPC - SABS 99 375 Mic 225 x 40 m to External Window Sills - SABS

Total Amount

One layer 250 micron green polyethylene waterproof sheeting (SABS) sealed at laps with PVC self-adhesive tape
100 USB Green Sheeting under Surface Beds 250 mic. (Material Only)

m m

648

Total Amount

item

WATERPROOFING (Supply & Fit)

Unit

Rate

Qty

Amount

SUBLEMENTARY PREAMBLE

Waterproofing of roofs, basements, etc shall be laid under a ten year guarantee. Waterproofing to roofs shall be laid to even falls to outlets etc with necessary ridges, hips and valleys. Descriptions of sheet or membrane waterproofing shall be deemed to include additional labour to turn-ups and turn-downs

Waterproofing to Roofs, Basements, etc (Supply & Fit)


Waterproofing on Flat Roofs, screeded to falls and crossfalls to rainwater
101 outlets

m m item

126 35

Waterproofing on Balconys, screeded to falls and crossfalls to rainwater


102 outlets

Total Amount

Waterproofing to Brick & Concrete Walls


103 Waterproofing on Shower Floors

No item

Total Amount

Total Carried Forward to Summary: