Professional Documents
Culture Documents
Owner:
(Sample Only)
Schedule E3:
BILL NO
1
Unit Rate Qty Amount
The Preliminaries are to be the JBCC Series 2000 Preliminaries prepared by the Joint Building Contracts Committee, January 2003 edition and shall be deemed to be incorporated herein. Tenderers are referred to the abovementioned documents for the full intend and meaning of each clause thereof (hereinafter referred to by heading and clause number only) for which such allowance must be made as may be considered necessary Where standard clauses or alternatives are not entirely applicable to this contract such modifications, corrections or supplements as will apply are given under each relevant clause heading
Site Establishment
1 2 3 4
Site Office Equipment Site Office/Shed Site Security / Watchman Site Toilet
Total Amount
item
Administration Costs
5 6 7
Total Amount
item
Supervision
8
Site Foreman
month item
Total Amount
item
Page 2 of 11
Insurances
9
Insurance on Project
Total Amount
item
Cleaning-up Expenses
12 Site Cleaning on Completion 13 Building Cleaning before Occupation 14 Cleaning Site During Construction
Total Amount
item
Temporary Works
15 Enclosure of works 16 Water 17 Electricity
Total Amount
item
Other
18 Setting out of the works 19 Inspection of the site
Total Amount
item
Additional Preliminaries.
20 21 22 23 24 Total Amount for Preliminaries & General
Total Amount
Page 3 of 11
BILL NO
2
Unit Rate Qty Amount
Total Amount
BILL NO
3
Unit Rate Qty Amount
The nature of the ground is assumed to be loose sandy material, therefore "earth", but possibly interspersed with "soft rock" or "hard rock"
Clear site for the whole area of the ground to be built upon up to a distance of at least 1,5m beyond the perimeter of the structure of building's) and/or extent of steps, paving's, etc.
m m
412
Total Amount
item
Page 4 of 11
BILL NO
Standard Strip Footings of the various widths and thickness shown and figured on the drawings or as directed by Engineer
m m
82
Total Amount
item
SUBLEMENTARY PREAMBLE
Cast concrete surface beds at least 85mm thick, on waterproofing membrane on compacted fill, halfway on external walls and over internal walls. Compact concrete properly to an even, rough surface to receive cement screeds.
Unit
Rate
Qty
Amount
m m m
38.4 20.4
Total Amount
item
35 Suspended Concrete Roofs: 230 mm - Ground Floor 36 Suspended Concrete Roofs: 230 mm - First Floor 37 Suspended Concrete Slabs: 230 mm - First Floor 38 Concrete Roofs: 170 mm - Covered Patio's & Balcony 's 39 Concrete Slab: 170 mm - Open Balcony
m m m m m m
63 15 175 32 31
Page 5 of 11
Total Brought Forward: Suspended Con. Slabs & Roofs - Rib and Block (Labour)
40 Labour to install Block & Lintels Complete
m m
315
Total Amount
item
m m item item m m
Total Amount
item
m m m m
86 26 13
Total Amount
item
Unit
Rate
Qty
Amount
No No No
3 1
Total Amount
item
Page 6 of 11
SUBLEMENTARY PREAMBLE
Reinforcement to be protected from the weather, all loose flakes, rust or oiliness to be cleaned of and in coastal situations must be rinsed free of any salt deposits.
REINFORCEMENT
Unit
Rate
Qty
Amount
m item
677
Total Amount
R 31,463.10
BILL NO
MASONRY
5
Unit Rate Qty Amount
SUBLEMENTARY PREAMBLE
Minimum compressive strength for bricks to a single storey building to be 7MPa and to a multiple storey to be 14MPa to foundations and ground floor. Cement bricks are to comply with SABS 527 and clay bricks with SABS 277.
BRICKWORK Stock Brick - NFP Non-Facing Plaster (Material Only) Patio & Superstructure Foundations (Plinth)
Clay Stock Brick (220w: 105h: 75)
53 Ground Floor
th item
48
Total Amount
Superstructure Brickwork
Clay Stock Brick (220w: 105h: 75)
54 Ground Floor 55 First Floor
th th item
94 53
Total Amount
Page 7 of 11
Total Brought Forward: Face Brick FBS - Face Brick Standard (Material Only) Brick-on-edge header course copings, sills, etc
56 Brick-on-edge header course copings, sills, etc of Stock bricks
th th
Total Amount
item
Unit
Rate
Qty
Amount
m m
53
Total Amount
item
m m m item 104 59
Total Amount
m item
1.3
Total Amount
bag bag
201
Total Amount
item
395 223
Total Amount
Page 8 of 11
Total Brought Forward: Cement (Gable Walls & Extra Over Brickwork)
Cement Buildcrete 42.5N
65 Brick-on-edge header course copings, sills, etc.
bag bag
Total Amount
item
Unit
Rate
Qty
Amount
BRICKWORK SUNDRIES
Galvanised Brick Reinforcement With Minimum 100mm Laps At Joints and Angles - Material Only
In Foundation Brickwork
66 150 x 2.8 mm Brickeforce (20m) 67 230 x 2.8 mm Brickeforce (20m)
roll roll
53 9
In Superstructure Brickwork
68 75 x 2.8 mm Brickeforce (20m) 69 150 x 2.8 mm Brickeforce (20m) 70 230 x 2.8 mm Brickeforce (20m)
15 175 8
Total Amount
item
Unit
Rate
Qty
Amount
No No No No No No No No No No No No
4 24 31 4 4 2 10 10 4 12 59
Total Amount
item
Page 9 of 11
Total Brought Forward: WALL CLADDING Wall Cladding - Stone (Supply & Fit)
Cancel Program Prices
82 Provisional Amount 83 Attendance
Unit
Rate
Qty
Amount
item item
R 131,526.32
R 131,526.32
m m m
589 765
Total Amount
item
Bricklayer (Rate / m2 Wall Area) / Item Build Foundations & Patio Brickwork
Lay Brickwork / 1000 Stock Bricks:
86 Ground Floor
th th
48
Total Amount
item
th th th
94 53
Total Amount
item
m m
412
Total Amount
item
Page 10 of 11
Total Amount
item
m m
176
Total Amount
item
item m m
1 57
Total Amount
item
Labour - Other
95 Place Fabric Reinforcement in Position 96 Place USB Green in Position
No m m Total Amount item 677 648
Page 11 of 11
BILL NO
6
Unit Rate Qty Amount
WATERPROOFING
SUBLEMENTARY PREAMBLE
In the event where retaining walls are required between differing floor levels, and in cellars, damp-proofing is to be done by an company approved by the Principal Agent in accordance with the consulting engineers instructions and the Contractor must provide for this. A 10 year guarantee must be supplied in respect of all such waterproofing.
In Walls
97 375 Mic. w:225 x 40 m DPC - SABS 98 375 Mic. w:300 x 40 m DPC - SABS 99 375 Mic 225 x 40 m to External Window Sills - SABS
Total Amount
One layer 250 micron green polyethylene waterproof sheeting (SABS) sealed at laps with PVC self-adhesive tape
100 USB Green Sheeting under Surface Beds 250 mic. (Material Only)
m m
648
Total Amount
item
Unit
Rate
Qty
Amount
SUBLEMENTARY PREAMBLE
Waterproofing of roofs, basements, etc shall be laid under a ten year guarantee. Waterproofing to roofs shall be laid to even falls to outlets etc with necessary ridges, hips and valleys. Descriptions of sheet or membrane waterproofing shall be deemed to include additional labour to turn-ups and turn-downs
m m item
126 35
Total Amount
No item
Total Amount