GIS Monthly Project Status Report

August 2008
Project Status

September

Project Importance

Project Name/Description

Project Number

Project Start Date

Preliminary End Date

Adjusted End Date

Phase 6 -OR-Trans/Pooled Fund Project - Design and construct Web based check in and out - Check out system

GIS19

06/30/04

06/30/05

12/31/08

Medium

Phase 7 - OR-Trans FY 2007 - Statewide data partnership - Wasco County Pilot project - Develop/Coordinator QA/QC of data with Road Authorities - Continue Pooled Fund participation - Develop Routing data on State highways

GIS19 (TO #15)

05/01/07

06/30/08

Medium

Projected Status** G G

Status***

August

June

July

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

Project Status

September

Project Importance

Project Name/Description

Project Number

Project Start Date

Preliminary End Date

Adjusted End Date

Environmental Data Management System (formerly SR-SAM)

GIS31 (TO #4, TO #12)

Ongoing

Ongoing

Ongoing

Medium

TOC GIS Interface Phase 2 - Implementation of viewing tool - Provide GIS expertise to the project Traffic Mobility Management System Phase 2 Develop data models and business processes based on recommendations and findings from Phase 1. Create/capture and catalogue data (or secure access to data) that will be used and maintained for managing traffic mobility. Develop applications that assist in managing traffic and freight mobility. Prototype applications, data and business processes.

GIS42 High

05/01/06

05/01/07

On Hold6/1/2007

GIS39

03/01/06

On Hold6/1/2007

High

Projected Status** G

Status***

August

June

July

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

Project Status

September

Project Importance

Project Name/Description

Project Number

Project Start Date

Preliminary End Date

Adjusted End Date

STIP TransGIS Scoping Tool Phase 1 & 2

GIS47

5/10/2007

11/15/2007

11/30/2007 12/31/07 03/15/08 4/1/08 6/15/08 9/01/08

High

High

SPIS Pilot for OR-Trans - Proof of Concepts

GIS44

07/13/06

12/31/06

On-Hold

Alternate Fuels Corridor - I5 Potential Sites Research- PHASE 2 - GIS map and database of all available sites associated with the I-5 corridor.

GIS50-2

Mission Critical

Alternate Fuels Corridor - I5 Potential Sites Research - GIS map and database of all available sites associated with the I-5 corridor.

GIS50

01/10/08

02/29/08

2/25/2008

TPOD (Transportation Planning Online Database) - Use GIS interface to view scanned planning studies

GIS52

05/01/08

6/1/2008 07/15/08 9/31/08

High

Projected Status** Y G

Status***

August

June

July

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

Project Status

September

Project Importance

Project Name/Description

Project Number

Project Start Date

Preliminary End Date

Adjusted End Date

Mission Critical

ODOT Solar Highway - Identify ODOT R/W that Solar equipment can be tied into PGE transmission lines RWDMS II - GIS Component - Enhance GIS connection to R/W FileNet System.

GIS54

03/10/08

05/01/08

6/1/2008 7/31/08

Mission Critical

GIS55

03/10/08

05/01/08

Medium

Q ArcGIS ODOT GUI Update - Update existing template to improve efficiency and standardization.

GIS56

06/01/08

Traffic Counting Application Features Enhancement - Contractor will enhance application used by field traffic counting staff

TO #23

1/3/07

3/10/2008 06/01/08 9/1/08

High

Electric Vehicle Charging Stations Site Data Collection Assistance

GIS59

Medium

Interchange Diagramming in GIS

GIS58

8/1/08

9/1/08

Projected Status** Y G Y

Status***

August

June

July

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

Project Status

September

Project Importance

Project Name/Description

Project Number

Project Start Date

Preliminary End Date

Adjusted End Date

GIS Data In Progress Projects categorized as: OEM or Sum Assign sub-numbers (Sum)

GIS21

Ongoing

Ongoing

Ongoing

High

GIS Data Completed

GIS21

C Completed

Completed

Completed

High

Projected Status** G C

Status***

August

June

July

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

Project Status

September

Project Importance

Project Name/Description

Project Number

Project Start Date

Preliminary End Date

Adjusted End Date

GIS Infrastructure Support (cont.) Training

GIS11-01

Ongoing

Ongoing

Ongoing

High

GIS Infrastructure Support (cont.) Demonstrations (6 month drop-off cycle) Target: OTC Doug Tindall, Hwy Div Manager Additional PBLT groups Area Managers Project Manager GIS Infrastructure Support (cont.) Customer Support

GIS11-02

Ongoing

Ongoing

Ongoing

High

GIS11-03

Ongoing

Ongoing

Ongoing

High

GIS Infrastructure Support (cont.) Metadata

GIS11-04

Ongoing

Ongoing

Ongoing

High

Projected Status** G G G Y

Status***

August

June

July

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

Project Status

September

Project Importance

Project Name/Description

Project Number

Project Start Date

Preliminary End Date

Adjusted End Date

High

GIS Infrastructure Support (cont.) Standards GIS Infrastructure Support (cont.) Software Evaluation/Purchase/Implementation (E) - Evaluation (P) - Purchase (I) - Implementation

GIS11-05-01

Ongoing

Ongoing

Ongoing

GIS11-06

Ongoing

Ongoing

Ongoing

High

GIS Infrastructure Support (cont.) Process Guidelines

GIS11-08

High

GIS Infrastructure Support SDE Implementation Spatial Reference Populate Database

GIS11-09

6/1/2006

8/15/2006

High

GIS Infrastructure (cont.) Hardware

GIS11-14

Projected Status** G G G G

Status***

August

June

July

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

Project Status

September

Project Importance

Project Name/Description

Project Number

Project Start Date

Preliminary End Date

Adjusted End Date

GIS Infrastructure (cont.) Planning

GIS11-15

GIS Infrastructure Support OBDP Migration

GIS11-17

OEM & Small Projects (cont.) Scenic Byways GIS Implementation

GIS23-02

5/1/06

7/31/2006

Mission Critical

Active 12/1/07

11/15/2006 5/15/07 5/1/08 6/15/08 9/01/08 10/1/08

OEM & Small Projects (cont.) Access Management GIS Implementation

GIS23-03

1/29/2007

6/30/2007

6/30/07 6/30/08 9/01/08

3/1/08

Mission Critical

Projected Status** G G Y Y

Status***

August

June

July

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

Project Status

September

Project Importance

Project Name/Description

Project Number

Project Start Date

Preliminary End Date

Adjusted End Date

OEM & Small Projects (Cont) Traffic Counting Field Data Collection

GIS23-04 (TO#10)

1/11/2006

3/15/2006

12/31/2006 06/1/2006 07/15/06 08/01/07

OEM & Small Projects (cont.) Asset Management Safety Rating Pilot

GIS23-09 Mission Critical

6/9/2006

10/1/2006

5/1/2007

Transportation Model Development

Ongoing

Ongoing

Ongoing

High

Projected Status** G G

Status***

August

June

July

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

Project Status

September

Project Importance

Project Name/Description

Project Number

Project Start Date

Preliminary End Date

Adjusted End Date

* C=Complete H=On Hold

Requires Attention Requires Corrective Action Project complete or not started

Projected Status**

Status***

August

June

July

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

10

s Report

Comments

3/8/07: The first web page for the check in/out site has been created. Info gathered from JAD session was used to design interface and some of the functionality. At this point the web page is a mark up of information and the function of loading the data will be worked out after the overall design has been finished. 4/3/07: Pooled fund project meeting on 3/24/07 in Nashville TN. NE, TN, IO, WA and OR were all in attendance. California has joined the pooled fund. 7/9/07: ODOT has secured $30K per year for the next two years for the pooled fund. 10/31/07: ODOT has recommended agreement points to Walla Walla County on the Oregon boarder. Walla Walla has returned a revised set. Discrepancies were noted between line work ODOT used to establish points and line work the county used. Those are being looked into now. 2/19/08: The FME Workbench for the pilot is complete. Data has been translated from source data and back using the Workbench. 4/21/08: Pooled Fund (GISDC) annual mtg was on May 13-14 in Olympia Wa.. Partners from all participating states were their to discuss findings, goals, direction about the check in/out application. 8/25/08 WA_Trans Policy Advisory Commitee mtg on 9/4. This will address technical issues that will guide the tools and design for the load/extract/change detection software. 2/19/08: U of O is working on the QAQC phase of data validation. A snap shot dataset will be created as part of this process for interim needs and agreement points will be established for coordination with the local Road Authorities for the long term integration goal. 3/6/08: U of O is compiling statistics of issues for each road authority (RA) and will begin work on the QAQC using the GeoMedia platform per ODOTs request. Will meet with OEM and GeoSolve to discuss incorporating data requirements for ODOT's certified mileage reporting in OR-Trans process via local RA data. 4/21/08: UofO has had personnel changes and lost their project manager so they have recruited for a new project manager. A few weeks worth of work was lost with the transition but UofO has committed to trying to meet the previous deadlines. OR-Trans has received a 2008/09 grant for $50k from USGS for continued work on QAQC and distribution of OR-Trans to the National Map effort. 7-2008 Work is nearly complete developing a routing network, specification gathering for GIS routing software is underway with completion scheduled for Aug. 1. 8/25/08 OEM contract w/ counties at DOJ for review. OEM placed a hold on data distribution to OR-Trans until new contract is signed. Crash data for Wasco Pilot has been extracted and geocoded to OR-Trans data. Mid Sept. mtg is planned to demonstrate data to Wasco Co. Marion/Linn Co. pilot to resolve agreement points was scheduled for August but has been pushed back because of loss of resources (Loren Mueller). Chad N has taken over some tasks that Loren had but he also has GIS technical support functions for ODOT that take his time.

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

11

Comments

11/5/07: Currently meeting with Tech Center Environmental managers, GeoEnvironmental unit managers, maintenance environmental project managers to develop 2008 work plan goals. 2008 Work Plan will be submitted to EDMS Steering this winter. Prototype RES/RAZ products will be presented to RES/RAZ subcommittee for feedback early 2008. 1/9/08: Completed 2007 customer outreach and scheduled Steering Committee for February 2008. RES/RAZ revised prototypes currently in development. Archaeological field application recently completed. Biology and Mitigation field applications in revision at Mason Bruce & Girard through Spring 2008. EDMS web application development resumes at Alsea Geospatial Spring-Summer 2008. 4/17/08: EDMS Steering Committee met February 20. Archaeological GPS application development was completed in March. SRSAM mapping committee met April 14. RES/RAZ map rewrite in process through June 2008. 7/14/08: RES/RAZ map rewrite process through July 2008. Resource grade GPS training underway in Regions through mid-August. 9/8/08: GPS trainings completed. RES/RAZ map rewrite in progress, currently converting thematic Line Charts previously displayed in MicroStation to ArcMap for final draft review. 3/8/07: Prototype delivered, waiting for final requirements.

09/14/06: Placed on Hold by Motor Carrier Staff. 10/31/06: Project completed. Motor Carrier does not need any additional work at this time. 3/8/07: Dennis, Pete Randall, Erik Havig, OBDP Staff and Ron Winterrowd met to discuss future developer needs. Additional discussions will occur over the next few months. Invited Randall Thomas to May Steering Committee to discuss needs for project. 1/4/08: Randall Thomas reports that final database testing is underway. GIS portion of this project remains on hold.

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

12

Comments

11/28/06: Approved at GIS Steering Committee. 2/21/2007: First requirements meeting scheduled for March. 5/10/07: Met with customers, and received more direction from Cathy Nelson. 7/9/07: Project outline developed. Sample 'mxd' created. Waiting for customer team to be identified. 9/13/07: Application in refinement. Requirements defined at meetings with TLT, PBLT, STIP Coord. and System Managers. Data received and decoded. Workshop scheduled for Sept 12using ILink system. Training software acquired. 11/8/07: Training complete in Region 1,2,3,4,5. Customer generated reviews being addressed and data updates to be implemented before deployment. 1/3/08: Tested revised tools and database management. Preparing web accessible instructional resources. Base software installs are complete. Tools are being distributed to customers. 2/20/08: Distribution of tools continues. 3/20/08: Distribution of tools continues. Most delay due to FSU resourcing for software installation. 4/4/08: Distribution continues. FSU Software installs slow. 4/15/08: Distribution continues. Software installs nearly complete. 5/09/08: Completing distribution and preparing survey for user feedback. 7/09/08: Distribution continues. 25 customer installs remain. 6/17/08: Contact business (Safety Management System staff) for future direction of this project. 7/16/2008 This project is linked to TAD db project RFW # 16117 that has not started as if this date. 2/25/08: Project Complete. 4/15/08: Customer utilizing data and tools. Training set for map production tool. 6/5/08: Project database and security developed for customer use during research phase. Data use restrictions prompted this action. Customer continues research and mapping. Field work and site decisions planned for completion by customer, end of June 2008.

3/20/08: Waiting for allocation of resources. 4/4/08: First meeting scheduled to gain access to database and determine location of scanned documents. 4/15/08: Data and scanned documents located. Database schema in review as is document storage/access location. 5/09/08: No Change. Resources are scarce. 06/19/08: Database in revision to achieve functionality and meet GIS standards. Redundancy and organization of documents in review to prepare for action by temporary staff and to insure proper posting and updates. Temp staff begins work to add and update documents, update database, revise organization and document naming. GIS staff designs interface for database entries and link management.

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

13

Comments

3/20/08: Experiencing problems obtaining data from PGE (Portland General Electric). 4/4/08: No data from PGE. 04/15/08: Data received. Site maps in progress. 5/09/08: Data analysis and mapping in progress. 06/18/08: Data processing has increased due to data limitations. Additional map production required from GIS staff to provide detail for analysis. 3/20/08: Feasibility testing complete.

3/20/08: Waiting for allocation of resources. 4/4/08: Short discussions have begun. 4/15/08: Project scope and purpose to be reviewed. Possible split as two projects. 5/09/08: Project split confirmed. This project addresses desktop toolset. Navigation and data access toolbars in development. Data migration to SDE/SQL in process. Team reviewing modules developed by business partners and other agencies. 7/09/08: Resources unavailable. 1/3/08 - Project approved. 2/25/08 - Data provided to consultant. 3/7/08 - Project due to be delivered week of 3/10/08. Software delivered, working on software version issue. 4/18/08: Software out of iCARE. Working with contractor to fine tune bugs with program. 6/25/08: Tech's have program installed on their laptops and are testing program. 7/14/08: Sending issue log to contractor on 7-14-08. 9/1/08: Waiting on contractor to complete changes. 6/25/08: Waiting for resources. Resource will be available 8/1

9/4/08: Lynn Bailey has received ArcGIS 2 training and with the assistance of Sarah Abbott, Region 1 GIS support technician is doing the project themselves with a minor amount (four hours) of support from Ryan Johnson.

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

14

Comments

ODOT Areas ATR's 2007 Flow Map State AADT Expressways Nonstate Functional Class State Functional Class Freight Routes Highway Classification Highway ones, fives, tens, tenths, hundredths Lane Width and Type Left and Right Turns Maintenance Units Mileposts National Network (state on nonstate) NHS (state on nonstate) Nmber of LFanes Posted Speeds Rest Areas Routes x-ref (state on nonstate) Signals Viewpoints Weigh Stations
Ambulance Service Areas (for internal use only) Bridges 2008 ODOT Facilities State Airport Runways LIDAR Imagery Index Access Management Permits (CHAMPS) (8/08) Acess Management Permits (U Permit) (8/08) Cattle Guards and Passes (8/08) Engineering Stations (8/08) Highway Intersections (8/08) Highway Network Update (8/08) Medians (8/08) Public Use Airports (8/08) Public Use Runways (8/08) RLIS Update (8/08) Shoulder Width and Type (8/08) Surface Width and Type (8/08) SPIS 2005-2007 (8/08) Culverts Under 6 feet (8/08) Culverts 6 to 20 feet (8/08) Contracts (8/08) Scenic Byways (8/08)

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

15

Comments

TRAINING RECEIVED: GPS and ArcPAD (GIS Unit) (8/08) ArcGIS II - BM, MH (7/08) Data Editing and Manipulation - JS, MH (7/08) Advanced Project Management - CB (8/08) Making Projects Work - CB (7/08) Fast Start in Project Management - CB (6/08) GIS in Action Conference (RJ, BM, CC, LM, MH) (5/08) Advanced Project Management - P.S. (4/08)

TRAINING DELIVERED: R.J. gave training to 3 GeoHydro staff about taking GIS data into the field (06/08) EDMS through MG&J contract, Region enviro. staff using GPS for field data collection (7/08 thru 8/08) GIS web pages / tools - Geo/Hydro GIS Database Comm (03/08). STIP Scoping GIS tool - GIS Steering Committee (3/20/08) STIP Scoping GIS tool - Area Manager Team qrtly mtg (04/24/08) GIS Right-of-Way Parcel Access - D.Tindall / L.Young (4/2008)

CUSTOMER SUPPORT HOURS: 62 (03/08) 34 (04/08) 59 (05/08) 77 (06/08) 33 (07/08) 26 (08/08) METADATA: 01/08: No Resources 02/08: No Resources 03/08: No Resources 04/08: off_hwy_local_2008, signed_rtes, mileposts cemeteries, its_2007, agg_odot 05/08: No resources 06/08: No resources 07/08: Cattle Guards, Cemetery, highway fives, ones, hundredths, intersects, ITS 08/08: Aggregate Sites, Medians, Shoulders, Scenic Byways, Solar Power, Wind Power

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

16

Comments

In Progress: OpenLM for ArcGIS (license mgmt software) (E:GIS unit testing) "Where have all the license gone" (ArcScript utility for checking current license use) (E: ICARe in progress) Intergraph GeoMedia Professional 6.01 (E; GIS unit testing) Intergraph GeoMedia Transportatoin Manager 6.01 (E; GIS unit testing) Intergraph GeoMedia Fusion 6.01 (E; GIS unit testing) ArcGIS 9.2 - build 480 (E; ICARe complete; GIS unit testing) ArcGIS 9.2 - build 480 SDK (E; ICARe testing) Complete: LogLicenseUse (ArcScript utility that provides additional ESRI license server logging; Implementation) ArcPad 7.1.1 (ICARe complete) ArcPad Application Builder 7.1.1 (ICARe complete) FME 2008 (ICARe complete)

7/13/06: Spatial Reference: Review Spatial Reference set-ups and decisions with Business Partners and other agencies. Review extents vs. precision to determine with regards to ODOT needs / GIS Unit needs / Engineering needs. Recommendation forthcoming. Populate Database: Test files have been loaded and various interactions. 9/14/06: Spatial Reference settings in place. Image loading techniques in review and being documented.11/01/06: Data identified and copied to SQL/SDE environment. 1/03/07:Additional server storage acquired. 3/8/07: Image migration in process. 1/9/08: Image migration complete but have not been able to create pyramids; progress halted since 8/2007; waiting on support. 4/2/08: It has been decided that since some imagery is the same as that provided by the portal that there is no longer a need to host this imagery ourselves. 6/18/08: GIS Unit has requested creation of two new databases through I.S. DBA staff . 'ODOT' will host standard data tables, replacing shapefiles posted to 'NAS' server. 'PROJECTS' will contain project based file groupings. 9/2/08: The databases have been created and are in use.

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

17

Comments

8/31/08: Regions 3 and 5 NAS servers are full. The Salem server has more storage space and is reaching capacity. Region 5 now has a fiber connection so data sccess shold be much faster. We are investigating if perhaps the new connection is fast enough in combination with SDE to scale down the Region 5 NAS. Options for Region 3 are still being explore.

1/03/07: No resources at this time. 3/8/07: Sponsor ready to initialize TransGIS implementation. All data work is complete with a March meeting planned. 5/10/07: Met with customers for initial requirements. On hold for GIS - resources. Another meeting with the customers will be scheduled to refine the requirements and schedule the work. 9/13/07: Metadata in development. New production method scoped for distributed through TransGIS portal. 11/8/07: Still on hold pending resources. 12/4/07: Completed new GIS layer Scenic Byway layer for presentation to the OTC. Waiting for OTC approval of two new byways. Also waiting on metadata from customer. 03/20/08: Needs to be published on TransGIS and customer has not completed metadata. 4/4/08: Meeting scheduled to discuss TransGIS display requirements. 4/15/08: Project review team meeting scheduled. Data update in progress. 5/09/08: Web Page display requirements determined and in development. 7/09/08: ArcGIS mxd Draft prepared and implemented through TransGIS. Waiting for customer review. 01/03/07: No change in status. 3/8/07: New extract provided to GIS Unit. 'Mapping' of this data very difficult due to missing data. Resources need to be found to provide consultation to Access Management for data cleaning. Also, extracts need to be reconsidered. 5/10/2007: Met with customers in April and they have requested a demonstration of TransGIS (remotely) for the District Access Coordinators to assist in determining additional project requirements. A schedule will be set and a GIS/IS resource will be providing that demonstration. 11/8/07: Meeting was held in Region 2 Tech. Center. Resources have delayed any additional meetings. PM will speak with business and determine if enough requirements have been identified to begin development of site.1/03/2007 - PM is meeting to get an update on required data availability status with GIS data administrator and is scheduling a final requirements meeting in January with the Project team. 03/20/08: PM has scheduled April meeting to determine if customer will accept current data availability to meet project requirements. Need to set new end date. 04/15/08: Update meeting occurred. Scope reviewed; data layers in review and application needs solidified. New end date set. 05/09/08: No Change. 6/17/08: Surveyed field permit specialist for top 10 data layers most useful in their work . 7/16/2008 received 10 top layers, proto type is developed and will be sent to business for approval. 9/3/08: Application \\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office was reviewed dring an iLinc meeting and approved by business ownder.

18

Comments

3/13/06: Customers have received frequent training refresher courses. Data entry has been validated. Insufficient resources to address 'instant-update' to main database. Other report capability not distributed until resources available. 9/14/06: Continued GIS and data support delivered by GIS Unit. Data is received by GIS Unit as needed.11/01/06: Counting season complete. Data being received by GIS Unit as it becomes available. 01/03/07: Data received and in review. 2007 Hose Counts Sheets being prepared. Work with consultants continues. 3/8/07: 2007 count year application and data provided to field staff. Refresher training provided. TSM staff trained to support field staff. GIS will assist in copying datasets during collection season. GIS unit will append data to main database once approved by TSM staff. 7/13/06: GIS Team is awaiting data and value or rating system. 9/14/06: GIS Unit working with sponsor to convey data and GIS standards, identify various resources, review ongoing tests and define data responsibility. 2/21/07: This project on-hold awaiting direction from business sponsor. 3/8/07: No business resources at this time. 5/2/07: No business resources at this time. Contacted business (Safety Management System staff) for future direction on this project. 7/16/2008 This project has been on hold - Requested response from business to find out if they still had interest in moving forward with this project. They have several other related initatives in the queue at this time. 8/25/08: Deschutes County model: being updated in VISUM. Incorporating Prineville into model. Finalizing base year. Deschutes County HERS-ST: Process beginning to tie the VISUM model to HERS-ST (Highway Economic Requirements System-State Version). Brookings model: being updated in VISUM. Work progressing. Woodburn model: being updated in VISUM. Work progressing. SWIM2: The statewide model team is working to meet a November 1 deadline for beta version that will be used for analysis. The project is in the middle of the final tasks needed to meet this date. Several minor calibration tasks are being completed. Changes to file structure and data storage on the SDC cluster are being tested. A few changes are needed to the model GUI. During the testing phase several errors were identified and are being corrected. OHAS: the pilot test locations have been identifiedGrants Pass, Eugene, and Gresham. The pilot will test the survey instrument questions, recruitment methods random phone call, mailings, phone lists, etc) , non-reponse issues, sampling, etc. The information gleaned from the pilot will affect the design of the actual survey scheduled for ODOT Region 2 this fall. GreenSTEP passed a major milestone August 14th when i was peer reviewed. The consensus ws the model is robust and well designed. Significant amount of work must be done on the input side, but the bulk of the model is complete. The model overview was also presented to the Oregon Global Warming Commission August 19, 2008 and received favorably. GreenSTEP is getting more and more attention across agencies. The potential of this tool to be expanded and connected across agencies and other analytical tools is increasing. The may become more relevant to ODOT GIS efforts in the future.

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

19

Comments

OEM = Operations & Essential Maint. *Small Projects A*=Application

\\vboxsrv\conversion_tmp\scratch_3\145150619.xls.ms_office

20

COMPLETED PROJECTS

Project # GIS09

Project GIS Software Evaluation Process - Develop GIS software evaluation guidelines (complete) - Develop test plan template (complete) - Develop template for cost analysis (Life cycle costs) ITS Traffic Counting Equipment (Closed on 3/01/01)

Start Date

End Date 3/01/01 3/1/02

Adjusted End Date 9/30/02 1/23/03 5/22/03 7/24/03

DGIS04

10/1/00

3/1/01

DGIS05

TransGIS (Version 2.0) - Develop plan for next phase - Intermodal (Freight) - Pavement - Congestion - Bridge - Traffic Counting

9/1/01

DGIS06

Highway Layer for ArcView - Conversion program from MGE to ArcInfo. Allows users to dynamically segment, review and display their own highway data.

9/1/00

2/28/02

DGIS07

SMMS Web Based Access - (DGIS 10 is complete)

2/15/01

5/15/02

DGIS09

Automated Collision Diagram - Phase 1 - Study options

6/30/01

Revised 10/12/00

COMPLETED PROJECTS

DGIS09

Automated Collision Diagram - Phase 2 - Development/Testing

5/30/02

9/01/02 01/01/03

DGIS09

Automated Collision Diagram - Phase 3 - Implementation SMMS Metadata migration to SQL Server

3/1/03

4/01/03 5/22/03

DGIS10

2/15/01

6/1/01

DGIS11 DGIS15

DMV Project Access Control Demonstration - Incorporate resources - Changes to CHAMPS database and hyperlink to GIS tools - Database development for ROW research Base Layer Development

8/1/01 10/31/02

10/1/01 2/28/03

GIS01

3/24/98

9/22/98

GIS05

GIS05

GIS05

GIS07

Aggregate Sites Phase 1 Intranet database application Aggregate Sites Phase 2 Intranet GIS application Aggregate Sites Phase 3 Desktop GIS application Non-State Hwy Functional Classification System Attribution State Highway 1:24,000 road alignments

5/29/00

5/30/01

1/31/01

5/30/01

12/31/00

5/30/01

6/1/00

12/1/01

GIS13

6/30/01

7/31/01

Revised 10/12/00

COMPLETED PROJECTS

GIS14

GIS Base Layers Phase 2 - Select 6 new base layers 1-Pavement Conditions 1999 2-ITS 3-Bridge 4-Intermodal (FIMS) 5-Crash 6-Non State Highway Functional Class 7-Federal Urban Trans Boundary Cust.: All GIS users Non-State Hwy Functional Classification and National Highway System to SQL

1/24/01

3/1/3102

GIS15

1/9/01

5/31/02

GIS16

Wasco County Pilot Project Phase 1 6 target areas Wasco County Pilot Project Phase 2 All roads GIS coverage

5/01/2001

6/30/01

GIS16

7/23/01

9/30/01

GIS17 GIS17

Upgrade of GIS related software Phase 1 - testing Upgrade of GIS related software Phase 2 - implementation Road Authority Database Oregon Statewide Burial Site & Cemetery Base Layer (Phase 1) (Cultural framework) - Develop GIS layer for cemeteries from ODOT map bases. (Approx. 500) Oregon Statewide Burial Site & Cemetery Base Layer (Phase 2) (Cultural framework)

10/25/01 1/1/02

3/31/02 3/31/02

GIS18 GIS20

7/1/01 4/30/02

10/1/01 12/30/02

GIS20

4/30/02

Revised 10/12/00

COMPLETED PROJECTS

GIS21

GIS Layers Complete Projects categorized as: OEM or Sm Assign sub-numbers (Quarterly drop-off cycle) (Mar-Jun-Sept-Dec)

GIS23

OEM & Small Projects(OEM) - Other projects completed by the GIS Project Team (Quarterly drop-off cycle) (Mar-Jun-Sept-Dec)

Revised 10/12/00

COMPLETED PROJECTS

GIS24

Tsunami Inundation Mapping Analysis

3/5/2003

4/4/03

GIS26

On-Line Contractor Emergency Registry System - Build GIS interface to IS Web developed site

12/15/02

4/01/03 5/1/03

ArcView Lat/Long coordinates Arc View Display of DGN Files

08/01/00 09/01/00

9/15/00 09/15/00

ArcView Location Reference System (LRS) Highway Milepoint Readout GPS Standards Rail Network Rail Crossing

08/01/00

09/15/00

05/01/00 08/01/00 03/15/00

05/01/00 03/15/00 05/31/00

Federal benchmark layer (NGS) (Complete) Desktop GIS - STIP/SIP (DGIS03a) Joint Estimation Model Data Development (Medford) ODOT Injection Wells Inventory (Phase 1) (Complete) Statewide Model Application Project (Willamette Valley) Non-MPO Travel Model Data Support (Lebanon) Generation 2 Statewide Model

07/15/00 06/16/00 05/15/00 6/22/00 6/1/00 3/1/00 7/1/99 10/15/00 09/30/00 09/01/00 12/1/00 11/30/00 12/31/01

Urban Transportation Model Development - Coos Bay/North Bend

6/1/01

12/1/01

Revised 10/12/00

COMPLETED PROJECTS

Urban Transportation Model Development - Woodburn

9/1/01

6/1/02

Urban Transportation Model Development - Roseburg Urban Transportation Model Development - Wilsonville Urban Transportation Model Development - Newberg Urban Transportation Model Development - Redmond Urban Transportation Model Development - Brookings Urban Transportation Model Development - Central Oregon

3/13/02

5/30/02

5/1/02

6/1/02

12/31/02

12/31/02

7/1/02

7/1/03

5/1/03

7/1/03

Revised 10/12/00

COMPLETED PROJECTS

Comments Outside contracts reviewed. Software evaluated. Project Plan created. ARC IMS Web software received 9/25/00. Installed and sent through NPE. Approval received to purchase software. Placed on hold for lack of resources. Returned to active status 1/22/02. Draft of GIS Software Evaluation Guidelines presented to Steering Committee 3/28/02. Dennis will make revisions and bring to 1/23/03 committee meeting. Using purchase of SDE (spatial data engine) GIS server software to develop and test process. (Will not work with OTS software). Used proposed ArcSDE acquisition to demonstrate revised Life Cycle template which is currently being revised based on Steering Committee feedback. Complete TDD and ITS Unit developing project plan. Gave demo to ITS Unit and field technicians. Waiting for data needs assessment from ITS Unit. Roll-out database using Internet GIS viewing tool as pilot. Updating and cleaning data for pilot. Delivered prototype to customer for testing. Java script rewritten. Roll-out to additional users, distribute to ITS. The application has been delivered. Met with Pavement, STIP coordinators, Intermodal (Freight), Congestion, Traffic Safety, Bridge and Transportation Systems Monitoring. Re-scheduling to meet with Motor Carrier. Developing decision list to prioritize actions. Integrating data collection and storage for this and Region 2 Corridor Planning. Demo to Steering Committee 3/22/01. Met with Mgmt. System Managers to review data requests and formats. Continue to enhance and add features to the application (Shaded Relief, Print Functions, Save Settings, etc.). Work continues to enhance performance and implement changes. Receiving data for all Hwy's: 2000 Pavement Friction, ITS Devices, partial Bridge data for Hwy 162, ADT's and Speed data. Training complete, roll out from Mark Robinson on 9/28/01. Complete 10/22/01 will be distributed to 60-70 additional users. In maintenance - to develop project plan for next phase.

Conversion program from MGE to ArcInfo. Created Measured Shapefile that can be used in ArcView 3.1. Common alignments, equations and z mileages all displayed correctly. Minor problems uncovered, approx. 150 points did not plot. Documenting process, resolving problem areas. Testing by GISU is needed to determine if the file should be made available to others throughout ODOT. Two measured shapefiles of the highway network were created in January 2002 (1:24,000 network, production road network) with modified processes to improve accuracy. Testing by GISU continues. Complete 2/28/02 Loaded on test machine. Resources are needed. Software ready for testing, loading 10/2/01. Software DLL conflicts halted implementation. No conflicts in new version of software. NPE submitted and software testing is underway. Metaweb and GeoConnect Admin Tools to be loaded when serial number is received from Intergraph. NPE for new version complete. Loaded on test web. Bruce Westcott from Intergraph is working on problems with software/hardware connections. Met with DBA and security on 5/3/02, web problem resolved. Testing under way with Regions 1, 4 and 5. Change Mgmt. scheduled for May 28th, will then implement on production server. Complete

Software reviews complete, demo for Chuck complete, considering re-make of the Maryland model. City of Portland's negative experience with the newest version of Intersection Magic and our crash data has discouraged its use. Traffic Engineers requested that we create our own package. The decision was made to design a new package using the Maryland system as a model. Complete

Revised 10/12/00

COMPLETED PROJECTS

Prototype in place and will make it similar to the in-house application (Visual Basic). Possible software to use for the actual drawing (Visio, MapObjects, MS Paint, etc.). 10/23/01 resources identified. Re-writing software. Working on symbols to depict data. Should have prototype in May, first release in June and final release in September. Demo for Traffic Managers meeting scheduled for June. Setting up two employees in Region 2 to test the application. Delivered Beta version to R2 November 2nd. Testing and software revisions complete

Documentation nearly complete. Purchasing visio software. NPE review underway. Deploy 2 copies to each region HQ traffic management staff. Visio software delivered, Documentation complete, demo to OTMS Steering Committee 3/27/03. Distribution in process. Complete Replace SMMS 3.1 with SMMS 3.2. Migrate from SMMS database to an SQL server. An SQL (test) server has been built and the SMMS 3.2 SQL version is being tested. NPE in progress. Currently being placed on the SQL Server V7 (EXSQL7P2). Complete 6/12/01 Chuck met with DMV on July 18th to determine needs. Working on language breakdown. (I.e. Asian). System delivered to DMV. In warranty mode. Complete 9/18/01 (80 hour project). Resource materials have been acquired and sample sites chosen (The Dalles). Resources have been formatted into standard/uniform projection. Project on hold, resources dedicated to GIS19. Project reactivated 11/10/02. Right-ofWay images acquired. Adobe Photoshop software on order to complete processing. Pilot covered State Highways in 1 city. Pilot demo Complete .

Extended close date 11/30/00. Data Model approved, test data base has been created. Transferring data to new database. Creating Standard and user documentation. Transferring data to production database (State highways, County Boundaries, City limits, ATR sites). Finishing User documentation. (1) Most of the application functions are complete. Adding enhancements and fixes as identified by the GeoHydro users. GeoHydro forecasts completion by January 2002. Hired temp for data entry. Complete 7/13/01. 2.) Coordinating integration of the GIS portion. Application complete and in testing phase. Maintenance of aggregate source location data needs to be worked out between GeoHydro and the GIS Unit. Complete 7/13/01. 3.) Script created to allow GeoHydro users to map data based on latitude and longitude values stored in the database is waiting for review by Amy Landvoight and/or Mike Long. Scheduled review and acceptance June 7, 2001. Application is only for use by the GeoHydro personnel. Complete 7/13/01. 35,000 miles of road. 11/30/00 Attribution complete. Error checking in progress. Successfully developed and tested the new MGE project and access database. Complete 10/19/01. Plus or Minus 40' of state highways. Complete August 2001.

Revised 10/12/00

COMPLETED PROJECTS

(Dependant on the completion of GIS 17) Add new layers to GIS SQL database 6 at a time. Database modeling and data acquisition is under way. Layers changed to meet the needs of the Conditions Report and TransGIS version 2. Received 2001 Pavement Conditions data. Congestion data has been reviewed and released in TransGIS 2.1. Congestion data is being viewed again. Re-visit corporate GIS base layers and bring back to Dec. 5th meeting. Project reassigned to GIS21. Descriptions and guidelines rewritten. Complete

Project Statement (002,026,028), Context of the System (140), Definition of the System/Subsystems (200/210), in draft form awaiting approval. Began work on possible data model. Project Plan approved. Two prototype databases created on SQL server 7.0 for evaluation purposes on 8/31/01. Testing prototype SQL server database (HGIS15a) using COTS (commercial off the shelf) software. Querying, reporting and updating capabilities are being tested using GeoMedia Pro, Access and SQL Server utilities. Database model has been updated, preparing documentation (P Plus Deliverables 170, 180 and 190). Testing and migration complete. Complete

Partner with other authorities to build a GIS network of all Oregon roads. First project co-operative with University of Oregon for completion of Wasco County. Contract review and data analysis took longer than anticipated, scope was reduced. 6 target areas complete. Complete 6/26/01. Phase 2 slightly delayed by other projects at the University; dedicated resources stretched thin resulting in attaching attribution delays. Server crash caused some data loss. Other University obligations will end 10/5/01 at which time work will resume. Met with the University on 9/24/01 to resolve delays in phase 2 and discuss a potential phase 3 (additional counties). Complete 12/28/01 data sent to GPL and T-FIT for review. Test existing GIS software and databases. NPE and testing completed on all products . Complete Implementation plans are being developed. Migrate software and databases to SQL V7.0 adding capabilities and flexibility. Data structure modified and migrated to SQL 7. GeoMedia Pro is being used for production work. Complete Database built and book published. Enhancements and updates are ongoing. Complete. Met 9/24 to determine how to proceed with data compilation. Oregon Parks and Rec., ODOT Archeology and Mortuary Board providing data. Fields confirmed at meeting. Verifying data entries. Completed GIS layer from ODOT map base cemeteries.

Working with State Parks Div. who is adding Oregon Burial Guide cemeteries to our layer (additional 700 sites) and BLM to build State Historical Preservation Office (SHPO). Complete

Revised 10/12/00

COMPLETED PROJECTS

ATR 2002 locations (ATR's) (OEM) 10/02 ADT 2001 (Average Daily Traffic) (OEM) 10/02 ODOT Areas Boundaries (OEM) 11/02 ASIS Aggregate Sites (OEM) 10/02 Hwy Milepost Locations (OEM) 10/02 Schools Locations (All public schools) (OEM) 11/02 Hwy Tenths for updated Hwy Network (OEM) 11/02 US Corps of Engineers Navigable Waters (Complete 12/02) (OEM) Crash Segs 2001 (SIP) (Complete 12/02) (OEM) Crashes 5-yr composite by region (Complete 11/02) (OEM) Highways-lane widths (Complete 11/02) (OEM) Highway-number of lanes (Complete 11/02) (OEM) Culverts 2002 (Complete 11/02) (OEM) Truck Safety Corridors 2003 Truck A/M Corridors 2003 Culverts 6-20 ft (12/03) Culverts less than 6 ft (12/03) Highway Mileposts 2002 (Complete 10/02) (OEM) Unincorporated Urban Communities 2002 (Complete 11/02) (OEM) ODOT Regions Boundaries (Complete 1/03) (OEM) ODOT Districts Boundaries (Complete 1/03) (OEM) Highway Friction Values 2002 (Complete 2/03) (OEM) Highway Skid Factors 2002 (Complete 2/03) (OEM) Maintenance Crew Assignments (Complete 2/03) (OEM) SPIS Sites (OEM) 4/03 Tsunami ODOT Inundation Line (GIS21-04) (sm) 3/03

Complete: Access Mgmt ArcView (DGIS13-2) 11/01 Or State Hwy No. conversion (DGIS 13-17) 8/02 A* CARS ArcExplorer (and CD for home users) (DGIS14-2) 2/03 A* Video Log-ArcExplorer Training (GIS23-05) 2/03 D* Road Authority (GIS23-04)(Sm) 12/02 D* City Annexation Data Modeling (GIS23-02)(Sm) (6/03) A* Software acquisition and distribution (Sm) (9/03) A* Standard Data Display and Formatting (Sm) (10/03) A* Upgrade Crash Coder Desktop GIS tool and User Guide (OEM) (10/03) D* Bridge Location Project (11/03) D* 650 Map Project (11/03) A* Bridge Location to Web (11/03) D* Mapping Speed-monitoring Loops in Metro area for Traffic Condition

Revised 10/12/00

COMPLETED PROJECTS

Mapping project for statewide Tsunami exercise is complete. Maps show inundation line intersecting state highways, and lifeline routes. Being tested in statewide earthquake drill April 2nd and 3rd. Complete

Project development nearly complete. Mixture of techniques used to accomplish project. Internet use not yet approved. Draft model presented to ODOT end-users 3/20 by the IS team (Diane Powers). Waiting for XML templates from IS Development Team. Network testing underway. Application and data complete and provided to customer. P+ documentation in draft stage. Complete

Display Lat/Long coordinates and LRS in ArcView. The application is out for peer review. Ready to send through product approval and Intranet roll-out. Going through NPE. (Complete) Application complete. Ready to send through product approval and Intranet roll-out. (Complete)

Application complete. Ready to send through product approval and Intranet roll-out. Going through NPE. (Complete)

Document approved on April 20, 2000. Distribution is being planned Revisions made, forwarded to State Forestry for review. Complete and delivered to State Service Center and GIS User Group. User has accepted the ArcView Extension (application) software and installation instructions. Network testing of extension is complete. Extension given to user. Create National Geodetic Survey benchmark layer for Geometronics in ArcView & MGE software. (Complete) Software purchase complete, documentation under development. Roll-out scheduled to start the week of August 28th. Close after testing complete 10/10/00. Quality check household activity locations from travel survey buffer points to create environmental design variables. Building base layer of ODOT maintenance facilities (103) to satisfy Oregon's DEQ water permit requirements. (Complete) Produce presentation of output from first generation statewide model. Completed 11/1/00. Project Lead was Brian Gregor. Base year employment & housing distributions and network characteristics. Completed 6/1/00. Project Lead was Sam Ayash. Road layer comprised of State Highways and nonhighways Functional Class network, attributed with functional class, number of lanes, posted speeds as available. Preliminary work should be completed by July 2001. Will be migrated to statewide modeling software. Final review meeting scheduled in November 2001. GIS work for model is complete. Waiting for review from cities of the employment and household data. Recent vacancies in both City of Coos Bay and ODOT Region 3 have slowed progress on this project. Employment and household data complete. Entering traffic count data. Complete 12/31/01

Revised 10/12/00

COMPLETED PROJECTS

Transportation Analysis Zones (TAZ) defined. Count locations submitted to Region 2. Employer and household geocoding in progress. Region 2 will be hiring a consultant to perform field data collection. Employer and household geocoding complete. Region 2 has contracted with consultant to perform field data collection. TAZ and Network being finalized. Analyzing traffic counts to network links. Incorporated city's housing and employment revisions. Complete Scheduling with COG for update of existing model. Consultant compiling existing data. ODOT is collecting and reviewing traffic count data. Updating population and housing data for consultant. Complete 11/02 Reviewing consultant data. Complete

Providing preliminary TAZ, model road network, employment and housing data to City for review. Incorporating city housing and employment revisions and forecast data. Need City of Dundee to validate employment, household and forecast data. Complete Zone and network development in progress. Zones and network have been restructured. City has validated employment and household data. Waiting for city to provide forecast data. Forecast data under development. Complete Zone and network development in progress. Zones and network have been restructured. City has validated employment and household data. Waiting for city to provide forecast data. Forecast data under development. Complete Complete

Revised 10/12/00

ODOT Construction Plans and Right-of-Way Map Index

GIS22

Drainage Facility Management - Develop system for inventorying, evaluating and tracking condition of pipes, culverts and storm water facilities

GIS29

11/1/03

3/4/04

Truck Route Permit Mapping and Database Phase 3 - Outline processes for maintenance by data steward (MC) Region 1 Development Review

GIS29

11/1/03

3/4/04

On Hold - Intranet application to create a spacial index (map) of ODOT Construction projects and Right-of-Way files data stored in ITIS. Resources need to be assigned. Data from ITIS for Map information has been obtained. Basic intranet application has been developed in ArcIMS but does not include the Construction Projects or Right-of-Way Maps, reports or additional queries. Project approved by Cathy Nelson. Project delayed due to other project priorities and lack of resources. Phase 3 - On Hold - Motor Carrier is starting to maintain & update database. Route maps ready for State Printer. Completed 4 separate MAP/GIS Layers, 1 in progress. Motor Carrier resources have not been available. Dennis will meet with Mike Bollinger to determine direction.

Phase 3 - On Hold - Motor Carrier is starting to maintain & update database. Route maps ready for State Printer. Completed 4 separate MAP/GIS Layers, 1 in progress. Motor Carrier resources have not been available. Dennis will meet with Mike Bollinger to determine direction.

TRAINING RECEIVED: SQL training 3/8/01 GeoMedia Intro Class 6/5/01 GIS in Action GIS-T 2001 GeoMedia Pro 7/12/01-7/13/01-10/16/01-10/17/01-10/18/01 ArcIMS 6/28/01-6/29/01 TransGIS version 2 training Advanced Access 10/23/01-10/24/01 SQL training 9/1/02 TransGIS version 2 training 1/02 GIS in Action, addressing conf. 08/02 XML Fundamentals fall/02 MicroStation V8 - GIS Unit 1/04 Java - Chad N, Phil S 1/04

State Web dev Cert (HTML focus) fall/02 Sequal Server 2000 fall/02 ArcGIS 8 for Enviro Appl fall/02 Map Objects Basics0online fall/02 MSTN V8 for Admin/User update 10/02 Java Scripting 11/02 Visual Basic-(Phil & Chad N)GIS Unit 12/02 HTML basics-Sue/GIS Unit 1/03 Excel XP - Sue/GIS Unit (1/03) Cold Fusion - Lisa, Phil, Casey 4/03 ArcGIS - Casey, Phil, Lisa 4/03 Java Script - Lisa 4/03 Remote Control/Field Tach GIS course (8 GIS members) 5/03 Requirements Mgmt - Sue 6/03 GIS in Action workshps and seminars-GIS Unit 5/04 MS access, advanced & Excel, advanced- Lisa L. 4/04 ArcGIS 9.0, I and II, (GISU), Kim Taylor (GeoEnviro), Charlotte Gerkin (TSM), Chris Shearer and Diana Mann (RICS) 9/04 Java 1 Chad Nielsen (GISU)10/04 GPS Data Collection, Chad Nielsen, Casy Ragain (GISU), Marcia Malstrom (IS), Jim Gavin (RICS), 9/04 GIS-T Lincoln Nebraska - Susan Mead (GIS), 04/05

TRAINING DELIVERED: ArcView and ArcExplorer - Bridge Mgmt ArcView - Darla Stoneman / Acces Mgmt ArcExplorer - TSM First Round - TransGIS users GIS Tools-R1 6/02 ArcView-Darla Stoneman/Access Mgmt 6/02 TransGIS-initial users/R5 5/02 ArcExplorer - CAR 11/02 ONHP/ArcExplorer-Env at CCC and R3 10/02 GIS Tools R3 11/02 ArcExplorer-Access Mgmt (CHAMPS) 12/02 ArcExplorer - Motor Carrier 4/03 Resource Map Template production - Env. 4/03 Crash Viewer - Region 1- 5/03 ArcExplorer - 10 Approach Perm Spec 7/03 ArcExplorer - TSM staff 8/03 - IS staff 8/03

ArcView - Region 1 staff 10/03 Crash Coding - CAR staff 10/03 GIS Brownbags 11/03 ArcView-General Support to Region 1 (Lisa) 6/04 15 users in queue

DEMONSTRATIONS: ArcExplorer to GIS Steering Committee 3/22/01 ArcExplorer to OTMS Steering Committee 6/28/01 Aggregate Demo ESRI demo Collision Diagram demo to Region Traffic Managers 6/02 OTMS - TransGIS & DMV demo 9/25/01 DMV demo to IS quarterly mgmt team 10/19/01 DMV & Trans GIS demo to GIS Steering Comm. 10/25/01 GIS Tools - ODOT Directors office 09-02 Rural Lands database project to GeoHydro 10/02 VBCrash to IT Exec Steering Comm and R2 10/02 TransGIS demo for Eugene Public Worls 11/02 TransGIS demo for Eugene Public Worls 11/02 DMV App. & TransGIS - R2 Management 10/02 DMV App. & TransGIS - R2 Design Team 11/02 DMV App. & TransGIS - HR expanded staff 11/02 FC database demo-GIS Steering Comm 12/02

TransGIS demo for Traffic Recorder Techs 1/03 SR-SAM to GIS Steering Committee (1/03) Functional Classification - TDS expanded staff 4/03 GeoConnent/MetaWeb - GIS Steering Comm. 5/03 ArcGIS template - GIS Steering Comm. 5/03 TransGIS Web dev - TDS staff 6/03 ArcGIS 8.x template - TDS staff 6/03 TransGIS Web PP - Region1 Planners 6/03 TransGIS Web - OTMS SC - OTMS Exec SC - Trans. COI 6/03 TransGIS Web - GIS Steering Committee 7/03 TransGIS Web - TDS Expanded Staff 8/03 TransGIS PP - PBLT 8/03 TransGIS PP - Highway Division staff 12/03 TransGIS - Chief of staff Lori Sundstrom 12/03 TransGIS - TPAU 12/03 TransGIS - Traffic Count Field Techs 1/04 Traffic Count GIS and Metro relationship 2/04 TransGIS - Planning Business Line Team 4/04 TransGIS - Parametrix 4/04 Network Software - GIS Steering Committee 5/04 GPS-ArcView Script for Data collect Team 7/04 TransGIS - OBDT 6/04 TransGIS - Region 1 Project Delivery 6/04 Network Software - TPAU 6/04 TransGIS - Region 1 Traffic Mgmt 8/04 TransGIS - Region 1 Tech Center Managers 9/04 TransGIS - Region 4 Traffic Managers 9/04 TransGIS - DMV 10/04 TransGIS & Env TransGIS - OTMS Steering Comm 12/04 GIS File Storage System - GeoEnv Steering Comm 12/04

DMV App. & TransGIS - HR expanded staff 11/02 FC database demo-GIS Steering Comm 12/02 TransGIS demo for Traffic Recorder Techs 1/03 SR-SAM to GIS Steering Committee (1/03) Functional Classification - TDS expanded staff 4/03 GeoConnent/MetaWeb - GIS Steering Comm. 5/03 ArcGIS template - GIS Steering Comm. 5/03 TransGIS Web dev - TDS staff 6/03 ArcGIS 8.x template - TDS staff 6/03 TransGIS Web PP - Region1 Planners 6/03 TransGIS Web - OTMS SC - OTMS Exec SC - Trans. COI 6/03