You are on page 1of 38

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

W5J9JR-10-D-0005-0006 ANA Gardez


Total 773 158 68 26JUL11A 05SEP13 -32

Milestones
Contract Milestones

KEY-0001 KEY-0002 KEY-0003

Notice to Proceed (NTP) Project Duration End Date of Project

0 773* 0

0 158* 0

100 26JUL11A 0 26JUL11A 0

05SEP13 05SEP13

-32 -32

Project Milestones

KEY-0004 KEY-0005 KEY-0006

Start Work on Project Release Partial Letter for CON Release Letter for Full CON

0 1 1

0 0 1

100 27JUL11A 100 09MAY12A 0 01APR13

09MAY12A 01APR13

-7

Pre-construction
Pre-construction Meetings

KEY-0007 KEY-0008

Provide Documents for Pre-CON Hold Pre-CON Meeting

6 1

0 0

100 27JUL11A 100 02AUG11A

01AUG11A 02AUG11A

Pre-construction Submittals

KEY-0009 KEY-0010 KEY-0011 KEY-0012 KEY-0013 KEY-0014 KEY-0015 KEY-0016 KEY-0017 KEY-0018
Start Date Finish Date Data Date Run Date

Submit ActivityHazard Analysis Submit Baseline Schedule Submit Accidend PreventionPlan Submit Quality Control Plan Submit Security Plan Approve Activity Hazard Analysis Approve Baseline Schedule Approve AccidentPreventionPlan Approve QC Plan by USACE Approved Security Plan by AED
26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity

1 1 1 1 1 14 14 14 14 14
PS19

0 0 0 0 0 0 0 0 0 0

100 100 100 100 100 100 100 100 100 100

02AUG11A 02AUG11A 02AUG11A 02AUG11A 02AUG11A 03AUG11A 03AUG11A 03AUG11A 03AUG11A 03AUG11A

02AUG11A 02AUG11A 02AUG11A 02AUG11A 02AUG11A 16AUG11A 16AUG11A 16AUG11A 16AUG11A 16AUG11A
Sheet 1 of 38 Date Revision Checked Approved

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

DBA Insurance

KEY-0019

DBA Insurance

100 26JUL11A

26AUG11A

Design
10% Design Submittal

DES-0001 DES-0003 DES-0002 DES-0004 DES-0014

Site Survey 10% Site Design Submittal Geotechnical Report 10% Site Design Conference / Approval Pay Request 10% Desgin

22 13 12 14 1

0 0 0 0 0

100 100 100 100 100

10AUG11A 10OCT11A 26OCT11A 26OCT11A 09NOV11A

05SEP11A 25OCT11A 06NOV11A 08NOV11A 09NOV11A

65% Design Submittal

DES-0005 DES-0016 DES-0006

65% Design Submittal 65% Design Conference / Approval Pay Request 65% Design

4 14 1

0 0 0

100 24MAR12A 100 29MAR12A 100 05JUN12A

27MAR12A 08APR12A 05JUN12A

100% Design Submittall

DES-0009 DES-0010 DES-0020

100% Design Submittal 100% Design Conference / Approval Pay Request 100% Design

10 14 1

0 0 0

100 10OCT12A 100 25OCT12A 100 01NOV12A

24OCT12A 31OCT12A 01NOV12A

Procurement
Civil/Structural
Concrete Reinforecement

PRO-0001 PRO-0002 PRO-0003 PRO-0004


Start Date Finish Date Data Date Run Date

Submit Reinforcement Steel Approved Reinforcement Steel Issue Parchase Order for SS Delivery of SS to Jobsite
26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity

5 14 2 5
PS19

0 0 0 0

100 100 100 100

13NOV11A 18NOV11A 17DEC11A 08MAY12A

17NOV11A 01DEC11A 19DEC11A 11MAY12A


Sheet 2 of 38 Date Revision Checked Approved

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID PRO-0064 Production of Concrete

Activity Description

Orig Dur 10

Rem Dur 0

Early Start

Early Finish 21MAY12A

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

100 12MAY12A

3D Panel

PRO-0009 PRO-0010 PRO-0011 PRO-0072 PRO-0012

Submit 3D Data Sheet Approve 3D Data Issue Purchase Order for 3D Production of 3D for Project Deliver of 3D to Jobsite

5 14 5 10 5

0 0 0 0 0

100 100 100 100 100

21APR12A 25APR12A 05MAY12A 10MAY12A 21MAY12A

25APR12A 05MAY12A 09MAY12A 20MAY12A 25MAY12A

K Span

PRO-0060 PRO-0061 PRO-0062 PRO-0063

Submit K Span Approve K Span Manufacturing of K Span Deliver of K Span to Jobsite

5 14 10 5

0 0 0 0

100 100 100 100

21APR12A 25APR12A 09MAY12A 19MAY12A

25APR12A 08MAY12A 19MAY12A 23MAY12A

Architectural
Joint Sealant

PRO-0005 PRO-0006 PRO-0007 PRO-0068 PRO-0008

Submit Joint Sealants Approved Joint Sealants Issue Purchase Order for SJS Material's Production for Project Delivery of SJS at Jobsite

5 14 5 15 5

0 0 0 0 0

100 100 100 100 100

15APR12A 20APR12A 05MAY12A 09MAY12A 23MAY12A

19MAY12A 03MAY12A 09MAY12A 23MAY12A 27MAY12A

Doors & Frames

PRO-0013 PRO-0014 PRO-0015 PRO-0016 PRO-0017

Submit Doors & Frames Approved Doors & Frames Issue Purchase Order for DR Manufacturing of Doors Delivery of Doors to Jobsite

5 14 2 10 5

0 0 0 0 0

100 100 100 100 100

02OCT11A 12OCT11A 29OCT11A 12MAY12A 22JUN12A

11OCT11A 25OCT11A 30OCT11A 21MAY12A 01JUL12A

Windows and Frames

PRO-0018 PRO-0019 PRO-0020 PRO-0021 PRO-0022


Start Date Finish Date Data Date Run Date

Submit Windows & Frames Approved Windows & Frames Issue Pruchase Order for WDW Manufacturing of Windows Delivery of Windows to Jobsite
26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity

5 14 2 10 5
PS19

0 0 0 0 0

100 100 100 100 100

18SEP11A 12MAY12A 25MAY12A 10NOV12A 20NOV12A

27SEP11A 25MAY12A 26MAY12A 19NOV12A 01JAN13A


Sheet 3 of 38 Date Revision Checked Approved

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Stucco & Paint

PRO-0023 PRO-0024 PRO-0025 PRO-0066 PRO-0026

Sumbit Stucco, Paint&Coating Approve Stucco, Paint&Coating Purchase Order for Stucco & P Material's Manufacturing for Project Deliver Stucco & P at Jobsite

5 14 2 18 6

0 0 0 0 0

100 100 100 100 100

20APR12A 24APR12A 07MAY12A 01OCT12A 07OCT12A

24APR12A 07MAY12A 08MAY12A 07OCT12A 14OCT12A

Electrical
Generator

PRO-0027 PRO-0028 PRO-0029 PRO-0030 PRO-0031 PRO-0032

Submit Generator Product Data Approve Generator Product Data Purchase Order for Generator Manufacturing the Generators Shipment of Generator Deliver of Generator at site

10 14 2 30 20 15

0 0 0 30 20 15

100 100 100 0 0 0

31MAR12A 09APR12A 21APR12A 01APR13 01MAY13 21MAY13

09APR12A 16APR12A 22APR12A 30APR13 20MAY13 04JUN13

7 7 7

Lighting System

PRO-0033 PRO-0034 PRO-0035 PRO-0036 PRO-0037

Submit Lighting System Approve Lighting System Purchase Order for LTG SYS Shipment Lighting System Deliver of LTG SYS Material

10 14 2 20 8

0 0 0 0 0

100 100 100 100 100

03SEP11A 17SEP11A 01OCT11A 01DEC12A 01JAN13A

13SEP11A 30SEP11A 02OCT11A 01JAN13A 28FEB13A

Pannel Board and Transfer Switch

PRO-0038 PRO-0039 PRO-0040 PRO-0041 PRO-0042 PRO-0043

Submit EP & TRANS Switch Approve EP & TRANS Switch Purchase Order for EP/TRANS SW Manufacture EP/TRANS Switch Shipment of EP & TRANS Switch Delivere EP & TRANS SW at Site

1 14 2 60 40 10

0 0 0 60 40 10

100 100 100 0 0 0

29AUG11A 29AUG11A 10SEP11A 01APR13 31MAY13 10JUL13

29AUG11A 03SEP11A 11SEP11A 30MAY13 09JUL13 19JUL13

-31 -31 -31

Electrical Distribution System

PRO-0044 PRO-0045 PRO-0046


Start Date Finish Date Data Date Run Date

Submit ELECT Distribution MAT Approve ELECT Distribution MAT PurchaseOrder forELEC Material
26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity

1 14 1
PS19

0 0 0

100 08SEP11A 100 08SEP11A 100 15SEP11A


FCEC UIProjects JV

08SEP11A 13SEP11A 15SEP11A


Sheet 4 of 38 Date Revision Checked Approved

W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID PRO-0048 PRO-0049 PRO-0047

Activity Description Shipment of ELECT Material Deliver ELECT Material at site Manufacturing of ELEC Material

Orig Dur 6 3 5

Rem Dur 3 1 0

Early Start

Early Finish 03APR13 01APR13 05JUN12A

Total Float 41 41

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

50 23APR12A 50 28APR12A 100 25MAY12A

Mechanical

PRO-0055 PRO-0056 PRO-0057 PRO-0058 PRO-0059

Submit Mechcanical Matrials Approve Mechcanical Matrials Purchase Order Mechcanical Matrials Shipment of Mechcanical Matrials Deliver Mechcanical Matrials to the site

1 14 2 45 15

1 14 2 45 15

0 0 0 0 0

02APR13 03APR13 17APR13 19APR13 03JUN13

02APR13 16APR13 18APR13 02JUN13 17JUN13

-7 -7 -7 -7 -7

Plumbing
Water and Sewer Pipes

PRO-0050 PRO-0051 PRO-0052 PRO-0053 PRO-0054

Submit Water & Sewer Pipes Approve Water & Sewer Pipes Purchase Order-W & Sewer Pipes Shipment of W & Sewer Pipes Deliver W & Sewer Pipe at site

30 14 2 35 35

0 0 0 0 0

100 100 100 100 100

17SEP11A 23SEP11A 08OCT11A 16APR12A 22APR12A

22SEP11A 05OCT11A 09OCT11A 21MAY12A 26MAY12A

Construction
Mobilization

MOB-0001 MOB-0002 MOB-0012 MOB-0022

Grading/Leveling the Area Install. of Fence around Camp Area Installation of Conexes Construction of Buildings

19 20 10 20

0 0 0 0

100 100 100 100

10SEP11A 30SEP11A 16OCT11A 27OCT11A

29SEP11A 15OCT11A 26OCT11A 08DEC11A

Sitework
Site Demolition/Grading

SDG-0001 SDG-0002 SDG-0003

Grubbing of Site Grading & Demolising Removing Materials from site

10 9 12

0 0 0

100 01APR12A 100 04APR12A 100 10APR12A

05JUN12A 20OCT12A 23OCT12A

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 5 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Soccer Field Irrigation System

STO-0001 STO-0002 STO-0003 STO-0004 STO-0005

Layout for Irrigation Pipes Excavation/leveling/Lay Pipes Backfilling/Compaction Punchlist Correction Finish & Handover

10 20 20 8 1

10 20 20 8 1

0 0 0 0 0

01APR13 13APR13 06MAY13 29MAY13 08JUN13

11APR13 05MAY13 28MAY13 06JUN13 08JUN13

27 27 27 27 27

Road Network, Walkways, Parking


Roads
RPS-0007 RPS-0008 RPS-0009 RPS-0010 RPS-0011 RPS-0012 RPS-0024 RPS-0013 Road Layout Road Sub-Grade Compact Sub-Grade of Road Road Base Course Compact Base-Course of Road Asphalt pavement Soil Ditch Test & Completion 2 15 15 14 10 10 10 2 0 0 0 0 0 0 0 2 100 100 100 100 100 100 100 0 01MAY12A 07MAY12A 12MAY12A 17MAY12A 24MAY12A 12SEP12A 18SEP12A 01APR13 15MAY12A 23MAY12A 03JUN12A 22MAY12A 15SEP12A 23SEP12A 29SEP12A 02APR13

35

Crush Around Building


RPS-0014 RPS-0015 RPS-0017 RPS-0018 Layout/Level of Crush Sub Grade for Crush Compaction of Crush all arround Building Test & Completion for Crush 1 10 15 1 1 10 15 1 0 0 0 0 13APR13 14APR13 16APR13 04MAY13 13APR13 24APR13 02MAY13 04MAY13 57 57 57 57

Concrete walkways
RPS-0019 RPS-0020 RPS-0021 RPS-0022 RPS-0023 Layout for Sidewalks Sub Base for Sidewalks Base Course for Sidewalks Pour Concrete for Sidewalks Test & Completion of Sidewalks 2 15 15 15 2 2 15 15 15 2 0 0 0 0 0 03APR13 06APR13 23APR13 11MAY13 28MAY13 04APR13 22APR13 09MAY13 27MAY13 29MAY13 35 35 35 35 35

Athletic Field & Track


Field & Track
RPS-0025 RPS-0026 RPS-0027 RPS-0028 RPS-0029 Layout Athletic Field & Track Excavation Athletic Field & Track Backfiling/Compaction Athletic Field & Track Grass/Cursh for Athletic Test & Completion of Field & Track 1 10 14 10 1 0 0 0 10 1 100 100 100 0 0 12MAY12A 15MAY12A 21MAY12A 01APR13 13APR13 12MAY12A 26MAY12A 18JUL12A 11APR13 13APR13

75 75

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 6 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Volleyball Fields
1st Field
RPS-0030 RPS-0031 RPS-0032 RPS-0033 RPS-0034 Layout Volleyball Fields Excavation Volleyball Fields Backfiling / Compaction Volleyball Fields Sand for Volleyball Fields Test & Completion Volleyball Fields Layout Volleyball Fields Excavation Volleyball Fields Backfiling / Compaction Volleyball Fields Sand for Volleyball Fields Test & Completion Volleyball Fields 1 10 10 10 1 1 12 12 12 1 0 0 0 0 1 0 0 0 0 1 100 100 100 100 0 100 100 100 100 0 12MAY12A 20MAY12A 03JUL12A 22JUL12A 01APR13 12MAY12A 16MAY12A 04JUN12A 18NOV12A 01APR13 12MAY12A 16JUL12A 16JUL12A 26AUG12A 01APR13 12MAY12A 24JUL12A 26AUG12A 01DEC12A 01APR13

85

2nd Field
RPS-0035 RPS-0036 RPS-0037 RPS-0038 RPS-0039

85

Force Protection
Personnel Bunker
BUNKER #1,2,3
FPR-0001 FPR-0002 FPR-0003 FPR-0004 FPR-0005 FPR-0006 FPR-0007 FPR-0008 FPR-0009 FPR-0010 FPR-0012 FPR-0011 FPR-0013 FPR-0014 FPR-0015 FPR-0016 FPR-0017 FPR-0018 FPR-0019 FPR-0020 FPR-0021 FPR-0022
Start Date Finish Date Data Date Run Date

Layout for Bunker #1,2,3 Casting for Bunker #1,2,3 Construct Bunker #1,2,3 Cmplt Sandbag & T. Barriers of B. #1,2,3 Test & Completion of Bunker # 1,2,3 Layout for Bunker #4,5,6 Casting for Bunker #4,5,6 Construct Bunker #4,5,6 Cmplt Sandbag & T. Barriers of B. #4,5,6 Test & Completion of Bunker #4,5,6 Casting Bunker #7,8,9 Layout for Bunker #7,8,9 Construct Bunker #7,8,9 Cmplt Sandbag & T. Barriers of B. #7,8,9 Test & Completion of Bunker #7,8,9 Layout for Bunker #10,11,12,13 Casting for Bunker #10,11,12,13 Construct Bunker #10,11,12,13 Cmplt Sandbag & T.Barriers of B.#10,11,12,13 Test & Completion of Bunker#10,11,12,13 Layout for Bunker #14,15,16,17 Casting for Bunker #14,15,16,17
26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity

1 8 4 6 1 1 8 4 6 1 8 1 4 6 1 1 10 4 6 1 1 10
PS19

0 0 0 6 1 0 0 0 6 1 0 0 0 6 1 0 0 0 6 1 0 0

100 100 100 70 0 100 100 100 70 0 100 96 100 25 0 100 100 100 25 0

18NOV12A 19NOV12A 21NOV12A 10DEC12A 08APR13 02DEC12A 03DEC12A 18DEC12A 10FEB13A 08APR13 18DEC12A 18DEC12A 20DEC12A 10JAN13A 09APR13 31DEC12A 31DEC12A 06JAN13A 18MAR13A 08APR13

18NOV12A 27NOV12A 09JAN13A 07APR13 08APR13 02DEC12A 17DEC12A 09JAN13A 07APR13 08APR13 26DEC12A 31MAR13 14JAN13A 07APR13 09APR13 31DEC12A 03JAN13A 14JAN13A 07APR13 08APR13 31DEC12A 06JAN13A
Sheet 7 of 38

79 79

BUNKER #4,5,6

78 78

BUNKER #7,8,9
85 79 78

BUNKER #10,11,12,13

78 78

BUNKER #14,15,16,17
100 31DEC12A 100 31DEC12A
FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID FPR-0023 FPR-0024 FPR-0025 FPR-0026 FPR-0027 FPR-0028 FPR-0029 FPR-0030 FPR-0031 FPR-0032 FPR-0033 FPR-0034 FPR-0035

Activity Description Construct Bunker #14,15,16,17 Cmplt Sandbag & T.Barriers of B. #14,15,16,17 Test & Completion of Bunker #14,15,16,17 Layout for Bunker #18,19,20,21 Casting for Bunker #18,19,20,21 Construct Bunker #18,19,20,21 Cmplt Sandbag & T.Barriers of B.#18,19,20,21 Test & Completion of Bunker#18,19,20,21 Layout for Bunker #22,23,24,25 Casting for Bunker #22,23,24,25 Construct Bunker #22,23,24,25 Cmplt Sandbag & T.Barriers of B.#22,23,24,25 Test & Completion of Bunker#22,23,24,25

Orig Dur 4 6 1 1 10 4 6 1 1 10 4 6 1

Rem Dur 0 6 1 0 0 0 6 1 0 0 0 6 1

Early Start

Early Finish 14JAN13A 07APR13 09APR13 11DEC12A 22DEC12A 14JAN13A 07APR13 08APR13 11DEC12A 23DEC12A 14JAN13A 07APR13 08APR13

Total Float 79 78

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

100 06JAN13A 0 01APR13 0 09APR13 100 100 100 25 0 100 100 100 25 0 10DEC12A 12DEC12A 23DEC12A 18MAR13A 08APR13 10DEC12A 12DEC12A 24DEC12A 18MAR13A 08APR13

79 79

79 79

FPR-0036 FPR-0044 FPR-0037 FPR-0038 FPR-0039 FPR-0040 FPR-0042 FPR-0041 FPR-0043 FPR-0045

Area Layout for ECP ECP Construct Main Drop Gate ECP FDN Works Slab on Grade Work for ECP CMU Wall&Slab Work for ECP ECP Plaster & Insulation ECP Internal & External Paint ECP Install Doors & Windows ECP Install Barriers Test & Completion for ECP

1 7 8 12 14 15 10 4 12 2

0 0 0 0 0 0 10 4 12 2

100 100 100 100 100 100 50 0 0 0

12MAY12A 19MAY12A 02JUN12A 12AUG12A 15AUG12A 10NOV12A 14JAN13A 01APR13 05APR13 17APR13

12MAY12A 25MAY12A 09JUN12A 28AUG12A 28AUG12A 17MAR13A 10APR13 04APR13 16APR13 18APR13

86 82 82 82

FPR-0046 FPR-0047 FPR-0048 FPR-0049 FPR-0050 FPR-0051 FPR-0052 FPR-0053

Area Layout for Wall Excavation for Wall Wall Backfilling/Compaction Wall PCC Works Wall Masonary Work Wall Copping Wall-Install Concertina Wire Wall-Test & Completion

1 8 7 5 18 18 15 5

0 0 0 0 18 0 15 5

100 100 95 100 96 100 75 0

01APR12A 03APR12A 12APR12A 14MAY12A 14MAY12A 13SEP12A 10NOV12A 16APR13

12MAY12A 12MAY12A 31MAR13 12SEP12A 18APR13 31MAR13A 15APR13 20APR13

69 80 80 80

FPR-0054 FPR-0055 FPR-0057 FPR-0056 FPR-0058


Start Date Finish Date Data Date Run Date

FPs Layout FPs Excavation FPs HESCO Installation FPs Backfilling & Compaction FPs Sand Bag
26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity

1 4 14 5 9
PS19

0 0 0 0 9

100 100 100 100 0

12MAY12A 13MAY12A 28MAY12A 11SEP12A 01APR13

12MAY12A 13JAN13A 09JAN13A 14JAN13A 09APR13


Sheet 8 of 38

89
Date Revision Checked Approved

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID FPR-0059 FPs Test & Completion

Activity Description

Orig Dur 2

Rem Dur 2

Early Start 0 10APR13

Early Finish 11APR13

Total Float 89

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Guard Tower
FPR-0060 FPR-0061 FPR-0063 FPR-0062 FPR-0064 FPR-0065 FPR-0066 FPR-0067 FPR-0068 FPR-0070 FPR-0069 FPR-0071 FPR-0072 FPR-0073 GT - Layout GT - Excavation GT - Foundation & Ring Beam Works GT - Watering, Backfilling & Compaction GT - Formwork & RFT for Slab on Grade GT - Concrete Works for Slab on Grade GT - Installation of CMU Wall&Slab GT - Plaster and Insulation GT - Electrical Works GT - Internal & External Painting GT - Bitumens&Corregated Sheets Inst. GT - Door&Windows Installation GT - Test & Commissioning GT - Punch list Correction 1 4 10 5 15 7 10 15 8 10 6 4 1 4 0 0 0 0 0 0 0 15 8 10 6 4 1 4 100 100 100 100 100 100 100 65 80 70 0 0 0 0 08APR12A 12MAY12A 12MAY12A 14MAY12A 18JUN12A 23JUN12A 13SEP12A 10FEB13A 18FEB13A 27FEB13A 10APR13 17APR13 22APR13 23APR13 10MAY12A 15MAY12A 22MAY12A 19MAY12A 05JUL12A 02JUL12A 20DEC12A 17APR13 09APR13 11APR13 16APR13 21APR13 22APR13 27APR13

63 63 67 63 63 63 63

Trash Collection Point


Trash Collection Point #1,2,3,4,5
TCP-0001 TCP-0002 TCP-0003 TPT#1 - Construct TPT#1 - Install Fence TPT#1 - Inspection 14 4 1 14 4 1 80 06MAY12A 0 17APR13 0 22APR13 16APR13 21APR13 22APR13 67 67 67

Trash Collection Point #6,7,8,9


TCP-0004 TCP-0005 TCP-0006 TPT#2 - Construct TPT#2 - Install Fence TPT#2 - Inspection 14 4 1 14 4 1 80 07MAY12A 0 17APR13 0 22APR13 16APR13 21APR13 22APR13 67 67 67

Trash Collection Point #10,11,12


TCP-0007 TCP-0008 TCP-0009 TPT#3 - Construct TPT#3 - InstalI Fence TPT#3 - Inspection 14 4 1 14 4 1 80 08MAY12A 0 17APR13 0 22APR13 16APR13 21APR13 22APR13 67 67 67

Trash Collection Point #13,14,15


TCP-0010 TCP-0011 TCP-0012 TPT#4 - Construct TPT#4 - Install Fence TPT#4 - Inspection 14 4 1 14 4 1 80 08MAY12A 0 17APR13 0 22APR13 16APR13 21APR13 22APR13 67 67 67

Cover Walkway for Corps Headquarters


Foundations
CWW-0001 CW- Layout
Start Date Finish Date Data Date Run Date 26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity PS19

100 12MAY12A
FCEC UIProjects JV

12MAY12A
Sheet 9 of 38 Date Revision Checked Approved

W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID CWW-0002 CWW-0003 CWW-0004 CWW-0005

Activity Description CW- Excavation CW- Watering, Backfilling & Compaction CW- Graveling CW- Foundation & Ring Beam

Orig Dur 7 4 7 10

Rem Dur 0 4 7 10

% 100 25 0 0

Early Start 13MAY12A 20MAY12A 06APR13 14APR13

Early Finish 03OCT12A 04APR13 13APR13 24APR13

Total Float 36 36 36

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Superstructure & Close-in


CWW-0008 CW- Column Installation 10 10 0 25APR13 06MAY13 36

Architectural - Exterior
CWW-0009 CW- Corregated Sheet Inst. 8 8 0 07MAY13 15MAY13 36

Inspections, Punchlists
CWW-0010 CW- Test & Commission CWW-0011 CW- Punchlist Correction CWW-0012 CW- Finish and Handover 2 8 1 2 8 1 0 16MAY13 0 19MAY13 0 28MAY13 18MAY13 27MAY13 28MAY13 36 36 36

Bleacher Enclosures
Bleacher #1
OTH-0001 OTH-0002 OTH-0004 OTH-0005 OTH-0006 OTH-0003 OTH-0010 OTH-0011 OTH-0012 Bleacher #1- Layout Bleacher #1 - Construct FDN Bleacher #1- Construct COL Bleacher #1-Construct Stairs Bleacher #1- Install CORR Sheet Bleacher #1- Slab on Grade Bleacher #1 Test & Commission Bleacher #1 Punchlist Correction Bleacher #1 Finish and Handover 1 15 12 12 12 18 2 5 1 0 0 0 0 0 2 2 5 1 100 100 100 100 100 90 0 0 0 14MAY12A 15MAY12A 03JUN12A 07JUN12A 14AUG12A 18NOV12A 03APR13 06APR13 11APR13 14MAY12A 18JUL12A 18JUL12A 18JUL12A 30AUG12A 02APR13 04APR13 10APR13 11APR13

76 76 76 76

Bleacher #2
OTH-0013 OTH-0014 OTH-0015 OTH-0016 OTH-0017 OTH-0018 OTH-0019 OTH-0020 OTH-0021 Bleacher #2- Layout Bleacher #2 - Construct FDN Bleacher #2- Slab on Grade Bleacher #2- Construct COL Bleacher #2-Construct Stairs Bleacher #2- Install CORR Sheet Bleacher #2 Test & Commission Bleacher #2 Punchlist Correction Bleacher #2 Finish and Handover 1 15 18 12 12 12 2 5 1 0 0 18 12 12 12 2 5 1 100 100 0 0 0 0 0 0 0 14MAY12A 26JUN12A 01APR13 10APR13 17APR13 22APR13 06MAY13 08MAY13 14MAY13 25JUN12A 17JUL12A 21APR13 23APR13 30APR13 05MAY13 07MAY13 13MAY13 14MAY13

48 48 48 48 48 48 48

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 10 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Utilities
Water Supply and Distribution System
Water Distribution
WSD-0004 WSD-0005 WSD-0006 WSD-0008 WSD-0009 WSD-0007 WSD-0010 WSD-0011 Layout for Water Pipes Excavation for Water Pipes Lay Site Water Pipes Construction of Water Manholes Test & Completion for W Pipes Check W Pipes & Backfill Punchlist Correction - W Pipes Finish and Handover - W Pipes 1 8 10 12 10 2 5 1 0 8 10 12 10 2 5 1 100 96 90 70 60 80 0 0 07APR12A 25JUN12A 04JUL12A 09JUL12A 05OCT12A 02DEC12A 17APR13 23APR13 10JAN13A 09APR13 11APR13 14APR13 11APR13 16APR13 22APR13 23APR13

66 66 66 70 66 66 66

Sanitary Sewer System


Sewage Collection
SSS-0001 SSS-0002 SSS-0003 SSS-0004 SSS-0005 SSS-0006 SSS-0007 SSS-0008 Layout for Sewer Pipes Excavation for Sewer Pipe Install Sewer Pipes Checking & Backfill Sewer Pipe Construction of Sewer Manholes Test & Completion - Sewer Pipe Correct Punchlist - Sewer Pipe Finish & Handover - Sewer Pipe 1 8 10 10 18 18 5 1 0 8 10 10 18 18 5 1 100 97 96 96 83 75 0 0 04APR12A 07APR12A 13MAY12A 18JUN12A 27JUN12A 05OCT12A 22APR13 28APR13 21JUN12A 09APR13 11APR13 11APR13 21APR13 21APR13 27APR13 28APR13

62 62 62 62 62 62 62

Site Electrical Distribution Network


Power Distribution
ELE-0015 ELE-0016 ELE-0018 ELE-0019 ELE-0024 ELE-0017 ELE-0020 ELE-0021 ELE-0022 ELE-0023 Layout for ELECT Pipes Excavation for ELECT Pipes Lay Electrical Pipes Concrete Work for Duct Bank Checking & Backfill Elect Pipes Electrical Manholes Electrical Cable Pulling Test & Commission Puchlist Correction Finish and Handover 2 6 10 12 10 20 15 4 5 1 0 6 10 12 10 20 15 4 5 1 100 96 80 91 93 90 0 0 0 0 07APR12A 09APR12A 06MAY12A 18JUN12A 20JUN12A 23JUN12A 15APR13 02MAY13 07MAY13 13MAY13 16MAY12A 07APR13 11APR13 14APR13 11APR13 23APR13 01MAY13 06MAY13 12MAY13 13MAY13

35 35 35 42 42 35 47 49 49

Power Generation
Emergency Generator for Headquarter
ELE-0009 ELE-0010 ELE-0011 ELE-0012
Start Date Finish Date Data Date Run Date

Install Emergncy Generator Install Control Panel for Generator Test & Commission Puchlist Correction
26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity

9 12 2 5
PS19

9 12 2 5

0 0 0 0

05JUN13 10JUN13 24JUN13 26JUN13

15JUN13 23JUN13 25JUN13 01JUL13


Sheet 11 of 38

6 6 6 6

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID ELE-0013 Finishing & Handover

Activity Description

Orig Dur 1

Rem Dur 1

Early Start 0 02JUL13

Early Finish 02JUL13

Total Float 6

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Site Communication System

COM-0001 COM-0002 COM-0005 COM-0003 COM-0004 COM-0006 COM-0007 COM-0008

Layout for Communication SYS Excavation for Conduits Construct Communication Manholes Install Counduits Backfilling & Compaction Testing & Completion - Com Sys Punchlist Correction - Com Sys Finish & Handover - Com Sys

1 7 17 9 3 2 4 1

0 5 17 5 5 2 4 1

100 90 80 80 75 0 0 0

13MAY12A 16MAY12A 20JUN12A 11OCT12A 18OCT12A 21APR13 23APR13 28APR13

15MAY12A 06APR13 20APR13 06APR13 06APR13 22APR13 27APR13 28APR13

62 62 74 74 62 62 62

Buildings
Arms Storage Buildings #100
Foundations
AB1-0001 AB1-0002 AB1-0003 AB1-0004 AB1-0005 AB1-0006 100 S.ASB - Layout 100 S.ASB - Excavation Work 100 S.ASB - Concrete Work for Footings 100 S.ASB - Under Ground Electrical Works 100 S.ASB - Backfilling/Capillary Water Barrier 100 S.ASB - Slab on Grade 1 6 9 6 3 6 0 0 0 0 0 0 100 100 100 100 100 100 01JAN12A 03JAN12A 05JUN12A 09JUN12A 16JUN12A 13SEP12A 02JAN12A 12JAN12A 14JUN12A 17JUN12A 14JUL12A 19SEP12A

Superstructure & Close-in


AB1-0008 AB1-0007 AB1-0012 100 S.ASB - Construction of Shear walls 100 S.ASB - Construction of CMU Walls 100 S.ASB - Steel Joists, Welding Plate& Purlins 10 10 6 0 0 6 100 15OCT12A 100 10NOV12A 0 01APR13 25OCT12A 20NOV12A 07APR13

52

Architectural - Exterior
AB1-0010 AB1-0014 AB1-0015 AB1-0013 100 S.ASB - Exterior Door Installation 100 S.ASB - Roof insullation 100 S.ASB - External Paint 100 S.ASB - Seam Metal Roof (Corr. Sheet) 2 8 12 6 2 0 4 6 90 100 60 0 10FEB13A 20MAR13A 27MAR13A 14APR13 02APR13 28MAR13A 04APR13 20APR13 67 65 52

Architectural - Interior
AB1-0016 AB1-0017 100 S.ASB - Plastering 100 S.ASB - Internal Painting 10 10 0 4 100 29NOV12A 80 27FEB13A 30NOV12A 04APR13

65

Electrical
AB1-0018 AB1-0019 AB1-0020
Start Date Finish Date Data Date Run Date

100 S.ASB - Conduits & Fittings 100 S.ASB - Electrical Wiring Works 100 S.ASB - Lighting Fix ,Cover Plates Inst.
26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity

10 10 1
PS19

4 4 1

90 01DEC12A 50 28MAR13A 0 06APR13


FCEC UIProjects JV

04APR13 04APR13 06APR13


Sheet 12 of 38

63 63 63
Date Revision Checked Approved

W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID AB1-0022

Activity Description 100 S.ASB - Panel Boards

Orig Dur 5

Rem Dur 5

Early Start 0 20JUL13

Early Finish 24JUL13

Total Float -25

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Mechanical
AB1-0024 AB1-0021 100 S.ASB - Electric Heater Install 100 S.ASB - Exhaust Fans install 4 1 4 1 80 28MAR13A 0 07APR13 04APR13 07APR13 65 63

Inspections, Punchlists
AB1-0023 AB1-0025 AB1-0026 100 S.ASB - Test & Commission 100 S.ASB - Punchlist Works 100 S.ASB - Finishing & Handover 2 5 1 2 5 1 0 25JUL13 0 28JUL13 0 04AUG13 27JUL13 03AUG13 04AUG13 -25 -25 -25

Arms Storage Buildings #101


Foundations
AB2-0001 AB2-0002 AB2-0003 AB2-0004 AB2-0006 AB2-0005 101 S.ASB - Layout 101 S.ASB - Excavation Work 101 S.ASB - Concrete Work for Footings 101 S.ASB - Backfilling/Capillary Water Barrier 101 S.ASB - Slab On Grade 101 S.ASB - Under Ground Electrical Works 1 4 9 6 6 6 0 0 0 0 0 0 100 100 100 100 100 100 04APR12A 05APR12A 21APR12A 14MAY12A 23MAY12A 21JUN12A 07APR12A 09APR12A 02MAY12A 20MAY12A 02JUL12A 16JUL12A

Superstructure & Close-in


AB2-0007 AB2-0008 AB2-0009 101 S.ASB - Construction of CMU Walls 101 S.ASB - Construction of Shear walls 101 S.ASB - Steel Joists, Welding Plate& Purlins 10 10 7 0 0 7 100 03JUL12A 100 05JUL12A 90 18MAR13A 17JUL12A 17JUL12A 08APR13

61

Architectural - Exterior
AB2-0012 AB2-0010 AB2-0011 AB2-0013 101 S.ASB - External Paint 101 S.ASB - Roof insulation 101 S.ASB - Seam Metal Roof (Corr. Sheet) 101 S.ASB - Ext Door Installation 12 10 7 8 0 7 7 8 100 75 85 0 15OCT12A 09MAR13A 28MAR13A 01APR13 23JAN13A 08APR13 08APR13 09APR13

61 61 61

Architectural - Interior
AB2-0014 AB2-0015 101 S.ASB - Plastering 101 S.ASB - Internal Painting 10 10 0 7 100 30SEP12A 90 01NOV12A 09OCT12A 08APR13

61

Electrical
AB2-0016 AB2-0017 AB2-0018 AB2-0019 101 S.ASB - Conduits & Fittings 101 S.ASB - Electrical Wiring Works 101 S.ASB - Lighting Fix ,Cover Plates Inst 101 S.ASB - Panel Boards 10 10 7 9 7 7 7 9 95 95 10 0 01DEC12A 01JAN13A 05FEB13A 20JUL13 08APR13 08APR13 08APR13 29JUL13 61 61 61 -25

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 13 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Mechanical
AB2-0021 AB2-0020 101 S.ASB - Exhaust Fans inst 101 S.ASB - Electric Heater Inst 10 1 7 1 60 03JAN13A 0 09APR13 08APR13 09APR13 62 61

Inspections, Punchlists
AB2-0022 AB2-0023 AB2-0024 101 S.ASB - Test & Commission 101 S.ASB - Punchlist Works 101 S.ASB - Finishing & Handover 2 5 1 2 5 1 0 30JUL13 0 01AUG13 0 07AUG13 31JUL13 06AUG13 07AUG13 -25 -25 -25

Arms Storage Buildings #102


Foundations
AB3-0001 AB3-0002 AB3-0003 AB3-0004 AB3-0005 AB3-0006 102 S.ASB - Layout 102 S.ASB - Excavation Work 102 S.ASB - Concrete Work for Footings 102 S.ASB - Backfilling/Capillary Water Barrier 102 S.ASB - Under Ground Electrical Works 102 S.ASB - Slab on Grade 2 6 9 6 6 6 0 0 0 0 0 0 100 100 100 100 100 100 01JAN12A 03JAN12A 12MAY12A 04JUN12A 07JUN12A 09JUN12A 02JAN12A 09JAN12A 21MAY12A 21JUN12A 21JUN12A 23JUN12A

Superstructure & Close-in


AB3-0007 AB3-0008 AB3-0009 102 S.ASB - Construction of CMU Walls 102 S.ASB - Construction of Shear walls 102 S.ASB - Steel Joists, Welding Plate& Purlins 10 10 7 0 0 7 100 24JUN12A 100 05JUL12A 0 01APR13 04JUL12A 16JUL12A 08APR13

57

Architectural - Exterior
AB3-0012 AB3-0013 AB3-0010 AB3-0011 102 S.ASB - External Paint 102 S.ASB - Ext Door Instalation 102 S.ASB - Roof Insulation 102 S.ASB - Seam Metal Roof (Corr. Sheet) 18 10 12 8 0 10 0 8 100 90 100 0 01JAN13A 20FEB13A 27MAR13A 09APR13 30JAN13A 16APR13 29MAR13A 17APR13

57 57

Architectural - Interior
AB3-0014 AB3-0015 102 S.ASB - Plastering 102 S.ASB - Internal Painting 10 10 0 10 100 28OCT12A 90 10DEC12A 20NOV12A 11APR13

57

Electrical
AB3-0016 AB3-0017 AB3-0018 AB3-0019 102 S.ASB - Conduits & Fittings 102 S.ASB - Electrical Wiring Works 102 S.ASB - Lighting Fix ,Cover Plates Inst 102 S.ASB - Panel Boards 4 8 1 2 4 4 1 2 90 90 0 0 10NOV12A 20FEB13A 04APR13 19JUN13 04APR13 04APR13 04APR13 20JUN13 67 67 67 4

Mechanical
AB3-0021
Start Date Finish Date Data Date Run Date

102 S.ASB - Exhaust Fans Inst


26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity PS19

0 17APR13
FCEC UIProjects JV

17APR13
Sheet 14 of 38

57
Date Revision Checked Approved

W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID AB3-0020

Activity Description 102 S.ASB - Electric Heater Inst

Orig Dur 1

Rem Dur 1

Early Start 0 18JUN13

Early Finish 18JUN13

Total Float 4

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Inspections, Punchlists
AB3-0022 AB3-0023 AB3-0024 102 S.ASB - Test & Commission 102 S.ASB - Punchlist Works 102 S.ASB - Finishing & Handover 2 5 1 2 5 1 0 22JUN13 0 24JUN13 0 30JUN13 23JUN13 29JUN13 30JUN13 4 4 4

Arms Storage Buildings #103


Foundations
AB4-0001 AB4-0002 AB4-0003 AB4-0004 AB4-0005 AB4-0006 103 S.ASB - Layout 103 S.ASB - Excavation Work 103 S.ASB - Concrete Work for Footings 103 S.ASB - Backfilling/Capillary Water Barrier 103 S.ASB - Under Ground Electrical Works 103 S.ASB - Slab on Grade 1 6 4 6 6 6 0 0 0 0 0 0 100 100 100 100 100 100 02JAN12A 03JAN12A 14JAN12A 03JUN12A 06JUN12A 12JUN12A 02JAN12A 09JAN12A 20MAY12A 23JUN12A 23JUN12A 23JUN12A

Superstructure & Close-in


AB4-0007 AB4-0008 AB4-0009 103 S.ASB - Construction of CMU Walls 103 S.ASB - Construction of Shear walls 103 S.ASB - Steel Joists, Welding Plate& Purlins 15 18 10 0 0 10 100 24JUN12A 100 11JUL12A 0 01APR13 10JUL12A 30JUL12A 11APR13

50

Architectural - Exterior
AB4-0012 AB4-0013 AB4-0010 AB4-0011 103 S.ASB - External Paint 103 S.ASB - Ext Door Installation 103 S.ASB - Roof insullation 103 S.ASB - Seam Metal Roof (Corr. Sheet) 10 5 10 5 2 5 10 5 95 90 90 0 18NOV12A 21FEB13A 27MAR13A 13APR13 02APR13 06APR13 11APR13 17APR13 60 57 49 50

Architectural - Interior
AB4-0014 AB4-0015 103 S.ASB - Plastering 103 S.ASB - Internal Painting 10 10 0 5 100 18SEP12A 90 04DEC12A 28SEP12A 06APR13

57

Electrical
AB4-0017 AB4-0016 AB4-0018 AB4-0019 103 S.ASB - Electrical Wiring Works 103 S.ASB - Conduits & Fittings 103 S.ASB - Lighting Fix ,Cover Plates Inst 103 S.ASB - Panel Boards 12 10 2 9 12 10 2 9 95 90 0 0 03JAN13A 10JAN13A 15APR13 23JUN13 14APR13 11APR13 16APR13 02JUL13 47 49 47 -6

Mechanical
AB4-0021 AB4-0020 103 S.ASB - Exhaust Fans Inst 103 S.ASB - Electric Heater Inst 1 1 1 1 0 17APR13 0 18JUN13 17APR13 18JUN13 47 -6

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 15 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Inspections, Punchlists
AB4-0022 AB4-0023 AB4-0024 103 S.ASB - Test & Commission 103 S.ASB - Punchlist Works 103 S.ASB - Finishing & Handover 2 5 1 2 5 1 0 03JUL13 0 06JUL13 0 11JUL13 04JUL13 10JUL13 11JUL13 -6 -6 -6

Arms Storage Buildings #104


Foundations
AB5-0001 AB5-0002 AB5-0003 AB5-0004 AB5-0006 AB5-0005 104 S.ASB - Layout 104 S.ASB - Excavation Work 104 S.ASB - Concrete Work for Footings 104 S.ASB - Backfilling/Capillary Water Barrier 104 S.ASB - Slab on Grade 104 S.ASB - Under Ground Electrical Works 1 5 12 6 10 6 0 0 0 0 0 0 100 100 100 100 100 100 01APR12A 02APR12A 14APR12A 03JUN12A 05JUN12A 06JUN12A 01APR12A 07APR12A 20MAY12A 27JUN12A 30JUN12A 26JUN12A

Superstructure & Close-in


AB5-0008 AB5-0007 AB5-0009 104 S.ASB - Construction of Shear walls 104 S.ASB - Construction of CMU Walls 104 S.ASB - Steel Joists, Welding Plate& Purlins 10 10 8 0 0 8 100 01JUL12A 100 14AUG12A 0 01APR13 12JUL12A 27AUG12A 09APR13

54

Architectural - Exterior
AB5-0012 AB5-0013 AB5-0010 AB5-0011 104 S.ASB - External Paint 104 S.ASB - Ext Door Installation 104 S.ASB - Roof Insulation 104 S.ASB - Seam Metal Roof (Corr. Sheet) 13 6 12 6 10 6 10 6 70 90 90 0 03FEB13A 20FEB13A 27MAR13A 10APR13 11APR13 07APR13 11APR13 16APR13 57 62 57 54

Architectural - Interior
AB5-0014 AB5-0015 104 S.ASB - Plastering 104 S.ASB - Internal Painting 15 15 0 6 100 26NOV12A 90 10DEC12A 05DEC12A 07APR13

62

Electrical
AB5-0016 AB5-0017 AB5-0018 AB5-0019 104 S.ASB - Conduits & Fittings 104 S.ASB - Electrical Wiring Works 104 S.ASB - Lighting Fix ,Cover Plates Inst 104 S.ASB - Panel Boards 10 10 10 6 0 10 10 6 100 95 95 0 10DEC12A 21FEB13A 22FEB13A 19JUN13 20FEB13A 11APR13 11APR13 25JUN13

57 57 0

Mechanical
AB5-0020 AB5-0021 104 S.ASB - Electric Heater Inst 104 S.ASB - Exhaust Fans inst 1 1 1 1 0 13APR13 0 18JUN13 13APR13 18JUN13 57 0

Inspections, Punchlists
AB5-0022
Start Date Finish Date Data Date Run Date

104 S.ASB - Test & Commission


26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity PS19

0 26JUN13
FCEC UIProjects JV

27JUN13
Sheet 16 of 38

0
Date Revision Checked Approved

W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID AB5-0023 AB5-0024

Activity Description 104 S.ASB - Punchlist Works 104 S.ASB - Finishing & Handover

Orig Dur 5 1

Rem Dur 5 1

Early Start 0 29JUN13 0 04JUL13

Early Finish 03JUL13 04JUL13

Total Float 0 0

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Corps Headquarters (North)


Foundations
GFC-0001 GFC-0002 GFC-0003 GFC-0004 GFC-0005 GFC-0006 GFC-0007 GFC-0008 Nrth Prt GFCC Building Layout Nrth Prt GFCC Excavation Nrth Prt GFCC Watering, Backfilling & Compaction Nrth Prt GFCC Foundation & Ring Beam Works Nrth Prt GFCC BKFLNG, CMPCTN, CAP. & Vap. Bars Nrth Prt GFCC Formwork & RFT for Slab on Grade Nrth Prt San Sewer Piping under Slab on Grade Nrth Prt Concrete Works for Slab on Grade 1 8 5 15 5 14 8 6 0 0 0 0 0 0 0 0 100 100 100 100 100 100 100 100 07APR12A 10MAY12A 15MAY12A 11JUN12A 14JUN12A 18JUN12A 21JUN12A 25JUN12A 07APR12A 10JUN12A 10JUN12A 27JUN12A 27JUN12A 12JUL12A 12JUL12A 12JUL12A

Superstructure & Close-in


GFC-0009 GFC-0010 GFC-0011 GFC-0012 GFC-0013 GFC-0014 Nrth Prt Installation of Shear Walls Nrth Prt Installation of 3D Panels Walls Nrth Prt Scaffolding for 3D Roof Slab Nrth Prt Instalaltion of 3D Panels Roof Slabs Nrth Prt Shotcreting for 3D Panels Roof & Walls Nrth Prt Pouring Concrete on Roof 12 15 3 12 10 8 0 0 0 0 0 0 100 100 100 100 100 100 14JUL12A 18JUL12A 21JUL12A 23JUL12A 28JUL12A 04AUG12A 15AUG12A 15AUG12A 20AUG12A 16AUG12A 12SEP12A 12SEP12A

Architectural - Exterior
GFC-0015 GFC-0018 GFC-0016 GFC-0019 GFC-0017 Nrth Prt Exterior Doors Installation Nrth Prt Cold Asphalt Damp Proofing Nrth Prt External Painting Nrth Prt Corregated Sheet Installation Nrth Prt Window Installation 10 12 12 10 8 10 0 8 10 0 60 100 90 85 100 04AUG12A 22OCT12A 01NOV12A 24DEC12A 01JAN13A 11APR13 20FEB13A 09APR13 11APR13 21JAN13A 63 70 63

Architectural - Interior
GFC-0024 GFC-0021 GFC-0020 GFC-0022 GFC-0023 Nrth Prt Interior Doors Installation Nrth Prt Plaster Works Nrth Prt Internal Painting Nrth Prt Sealed Concrete Nrth Prt Terrazzo Tiles 10 18 18 10 15 10 0 10 10 15 80 100 90 20 0 04AUG12A 01OCT12A 01DEC12A 25MAR13A 13APR13 11APR13 03JAN13A 11APR13 11APR13 29APR13 43 44 68 43

Electrical
GFC-0025 GFC-0026 GFC-0028 GFC-0027 GFC-0041 Nrth Prt Ele PVC Conduits & Fittings & Boxes Nrth Prt Electrical Wiring Works Nrth Prt Duplex and switch installation Nrth Prt Lighting Fix. & Cover Plates Insta Nrth Prt Panel Board Installation 5 5 18 2 5 5 5 10 2 5 80 80 70 0 0 01DEC12A 01JAN13A 03JAN13A 13APR13 20JUL13 06APR13 06APR13 11APR13 14APR13 24JUL13 66 66 58 61 -21

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 17 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Mechanical
GFC-0029 GFC-0030 GFC-0031 Nrth Prt Exhaust Fan Installation Nrth Prt Unit Heater Installation Nrth Prt AC Split Installation 10 10 10 10 10 10 40 27MAR13A 10 28MAR13A 0 30APR13 29JUN13 29JUN13 11MAY13 1 1 43

Plumbing
GFC-0032 GFC-0034 GFC-0033 Nrth Prt Hot & Cold Water Piping Nrth Prt Toilet & Misc.Accessories Nrth Prt Toilet Sanitry Fixture Installation 15 4 15 15 4 15 25 01DEC12A 0 18APR13 0 23APR13 17APR13 22APR13 09MAY13 44 44 44

Fire Protection System


GFC-0035 GFC-0036 Nrth Prt Smoke Detector Installation Nrth Prt Fire Extinguisher Installation 1 1 1 1 10 29MAR13A 0 18JUN13 02APR13 18JUN13 83 10

Communications
GFC-0037 Nrth Prt Telephone and Data wall recepticle Inst 15 15 35 02JAN13A 17APR13 63

Inspections, Punchlists
GFC-0038 GFC-0039 GFC-0040 Nrth Prt Test & Commission Nrth Prt Punchlist Works Nrth Prt Finishing & Handover 2 5 1 2 5 1 0 25JUL13 0 28JUL13 0 03AUG13 27JUL13 01AUG13 03AUG13 -21 -21 -21

Corps Headquarters (West)


Foundations
GFC-0042 GFC-0043 GFC-0044 GFC-0047 GFC-0048 GFC-0045 GFC-0046 GFC-0049 West Prt GFCC Building Layout West Prt GFCC Excavation West Prt GFCC Watering, Backfilling & Compaction West Prt GFCC Formwork & RFT for Slab on Grade West Prt San Sewer Piping under Slab on Grade West Prt GFCC Foundation & Ring Beam Works West Prt GFCC BKFLNG, CMPCTN, CAP. & Vap. Bars West Prt Concrete Works for Slab on Grade 1 4 5 14 5 15 5 6 0 0 0 0 0 0 0 0 100 100 100 100 100 100 100 100 07APR12A 14MAY12A 20MAY12A 18JUN12A 21JUN12A 21JUN12A 25JUN12A 14JUL12A 07APR12A 17MAY12A 16JUN12A 12JUL12A 14AUG12A 12SEP12A 12JUL12A 15NOV12A

Superstructure & Close-in


GFC-0050 GFC-0051 GFC-0052 GFC-0053 GFC-0054 GFC-0055 GFC-0073
Start Date Finish Date Data Date Run Date

West Prt Installation of Shear Walls West Prt Installation of 3D Panels Walls West Prt Scaffolding for 3D Roof Slab West Prt Instalaltion of 3D Panels Roof Slabs West Prt Shotcreting for 3D Panels Roof & Walls West Prt Pouring Concrete on Roof West Prt Truss Installation
26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity

8 15 3 10 10 10 12
PS19

0 0 0 0 3 0 12

100 100 100 100 85 100 75

17JUL12A 04AUG12A 25SEP12A 28SEP12A 03OCT12A 06OCT12A 13DEC12A

22SEP12A 12DEC12A 12DEC12A 12DEC12A 03APR13 13JAN13A 14APR13


Sheet 18 of 38

50 53

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Architectural - Exterior
GFC-0058 GFC-0056 GFC-0057 GFC-0059 GFC-0060 GFC-0085 West Prt Exterior Doors Installation West Prt Cold Asphalt Damp Proofing West Prt Corregated Sheet Installation for 3D West Prt Window Installation West Prt External Painting West Prt Corregated Sheet Installation for Truss 10 15 12 10 15 12 10 0 10 10 10 12 40 100 67 50 30 50 01DEC12A 13DEC12A 13FEB13A 14FEB13A 27FEB13A 27MAR13A 11APR13 27JAN13A 11APR13 11APR13 11APR13 14APR13 68 68 68 68 53

Architectural - Interior
GFC-0062 GFC-0063 GFC-0064 GFC-0084 GFC-0061 GFC-0086 GFC-0065 West Prt Plaster Works West Prt Interior Doors Installation West Prt Internal Painting West Prt Glass Wool Insulation West Prt Terrazzo Tiles West Prt False Ceiling West Prt Sealed Concrete 15 10 15 12 15 15 7 10 10 10 12 15 15 7 80 36 55 70 0 0 0 21NOV12A 28JAN13A 01FEB13A 28MAR13A 04APR13 01APR13 20JUL13 11APR13 11APR13 11APR13 14APR13 21APR13 17APR13 27JUL13 55 60 60 53 50 53 -23

Electrical
GFC-0066 GFC-0068 GFC-0067 GFC-0069 GFC-0070 West Prt Elec PVC Conduits & Fittings & Boxes West Prt Duplex and switch installation West Prt Electrical Wiring Works West Prt Lighting Fix. & Cover Plates Inst West Prt Panel Board Installation 5 10 5 2 5 0 10 5 2 5 100 45 50 0 0 01JAN13A 03JAN13A 10JAN13A 22APR13 20JUL13 23MAR13A 11APR13 06APR13 23APR13 24JUL13

68 65 50 -23

Mechanical
GFC-0071 GFC-0072 West Prt AC Split Installation West Prt Exhaust Fan Installation 1 1 1 1 0 18JUN13 0 18JUN13 18JUN13 18JUN13 10 10

Plumbing
GFC-0074 GFC-0075 GFC-0076 West Prt Hot & Cold Water Piping West Prt Kitchen & Misc.Accessories West Prt Kithen Fixture Installation 15 5 8 15 5 8 25 01DEC12A 0 18APR13 0 18APR13 17APR13 23APR13 27APR13 55 57 55

Fire Protection System


GFC-0077 GFC-0078 West Prt Smoke Detector Installation West Prt Fire Extinguisher Installation 1 1 1 1 0 23APR13 0 18JUN13 23APR13 18JUN13 58 10

Communications
GFC-0079 West Prt Tele and Data wall receptacle Insta 15 15 40 02JAN13A 17APR13 63

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 19 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Inspections, Punchlists
GFC-0080 GFC-0081 GFC-0082 West Prt Test & Commission West Prt Punchlist Works West Prt Finishing & Handover 2 5 1 2 5 1 0 28JUL13 0 30JUL13 0 05AUG13 29JUL13 04AUG13 05AUG13 -23 -23 -23

Corps Headquarters (South)


Foundations
GFC-0087 GFC-0088 GFC-0089 GFC-0092 GFC-0091 GFC-0093 GFC-0090 GFC-0094 Sout Prt GFCC Building Layout Sout Prt GFCC Excavation Sout Prt GFCC Watering, Backfilling & Compaction Sout Prt GFCC Formwork & RFT for Slab on Grade Sout Prt GFCC BKFLNG, CMPCTN, CAP. & Vap. Bars Sout Prt San Sewer Piping under Slab on Grade Sout Prt GFCC Foundation & Ring Beam Works Sout Prt Concrete Works for Slab on Grade 1 5 5 14 5 8 15 6 0 0 0 0 0 0 0 0 100 100 100 100 100 100 100 100 07APR12A 12MAY12A 16MAY12A 20JUN12A 26JUN12A 01JUL12A 14JUL12A 16JUL12A 07APR12A 16MAY12A 16JUN12A 10JUL12A 18NOV12A 11JUL12A 12SEP12A 09JAN13A

Superstructure & Close-in


GFC-0095 GFC-0096 GFC-0097 GFC-0098 GFC-0099 GFC-0100 GFC-0101 Sout Prt Installation of Shear Walls Sout Prt Installation of 3D Panels Walls Sout Prt Scaffolding for 3D Roof Slab Sout Prt Instalaltion of 3D Panels Roof Slabs Sout Prt Shotcreting for 3D Panels Roof & Walls Sout Prt Pouring Concrete on roof Sout Prt Truss Installation 8 15 3 12 15 12 10 0 0 0 0 12 0 10 100 100 100 100 87 100 50 13AUG12A 13SEP12A 25SEP12A 28SEP12A 13OCT12A 20OCT12A 25MAR13A 22SEP12A 23JAN13A 12DEC12A 23DEC12A 14APR13 23JAN13A 11APR13

49 51

Architectural - Exterior
GFC-0105 GFC-0102 GFC-0103 GFC-0107 GFC-0104 GFC-0106 Sout Prt Exterior Doors Installation Sout Prt Cold Asphalt Damp Proofing Sout Prt Corregated Sheet Installation for 3D Sout PrtExternal Painting Sout Prt Corregated Sheet Installation for Truss Sout PrtWindow Installation 12 10 10 10 10 12 10 10 10 10 10 12 10 60 40 45 10 0 01DEC12A 24FEB13A 25FEB13A 26FEB13A 27MAR13A 01APR13 11APR13 11APR13 11APR13 11APR13 23APR13 14APR13 68 57 61 68 51 61

Architectural - Interior
GFC-0111 GFC-0109 GFC-0113 GFC-0110 GFC-0108 GFC-0112 GFC-0114 Sout Prt Interior Doors Installation Sout Prt Plaster Works Sout Prt Internal Painting Sout Prt Glass Wool Insulation Sout Prt Terrazzo Tiles Sout Prt False Ceiling Sout Prt Sealed Concrete 10 15 10 10 12 2 5 10 15 10 10 12 2 5 30 85 60 40 0 0 0 01DEC12A 03DEC12A 27FEB13A 27MAR13A 15APR13 24APR13 23JUL13 11APR13 17APR13 11APR13 23APR13 28APR13 25APR13 28JUL13 53 53 61 51 49 51 -24

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 20 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Electrical
GFC-0115 GFC-0116 GFC-0118 GFC-0117 GFC-0119 Sout Prt Ele PVC Conduits & Fittings & Boxes Sout Prt Electrical Wiring Works Sout Prt Duplex and switch installation Sout Prt Lighting Fix. & Cover Plates Inst Sout Prt Panel Board Installation 5 5 10 2 5 5 5 10 2 5 90 40 20 0 0 01FEB13A 21FEB13A 28FEB13A 13APR13 20JUL13 07APR13 07APR13 11APR13 14APR13 24JUL13 65 65 77 61 -21

Mechanical
GFC-0120 GFC-0121 GFC-0131 Sout Prt AC Split Installation Sout Prt Exhaust Fan Installation Sout Prt Unit Heater Installation 1 1 1 1 1 1 0 01APR13 0 18JUN13 0 18JUN13 01APR13 18JUN13 18JUN13 77 10 10

Plumbing
GFC-0122 GFC-0124 GFC-0123 Sout Prt Hot & Cold Water Piping Sout Prt Toilet Sanitry Fixture Installation Sout Prt Toilet & Misc.Accessories 15 3 5 15 3 5 25 01DEC12A 0 18APR13 0 18APR13 17APR13 21APR13 23APR13 53 55 53

Fire Protection System


GFC-0125 GFC-0126 Sout Prt Smoke Detector Installation Sout Prt Fire Extinguisher Installation 2 2 2 2 0 18JUN13 0 20JUN13 19JUN13 22JUN13 6 7

Communications
GFC-0127 Sout Prt Telephone and Data wall recepticle Inst 3 3 38 01MAR13A 23JUN13 6

Inspections, Punchlists
GFC-0128 GFC-0129 GFC-0130 Sout Prt Test & Commission Sout Prt Punchlist Works Sout PrtFinishing & Handover 2 5 1 2 5 1 0 29JUL13 0 31JUL13 0 06AUG13 30JUL13 05AUG13 06AUG13 -24 -24 -24

Kandak Headquarters
Foundations
KAN-0001 KAN-0002 KAN-0003 KAN-0004 KAN-0005 KAN-0006 KAN-0007 KHQ - Layout KHQ - Excavation Work KHQ - Watering, Backfilling & Compaction KHQ - Foundation & Ring Beam Works KHQ - BKFLNG, CMPCTN, CAP. & Vap. Barriers KHQ - Formwork & RFT for Slab on Grade KHQ - Concrete Works for Slab on Grade 1 4 5 7 7 8 2 0 0 0 0 0 0 0 100 100 100 100 100 100 100 08APR12A 09APR12A 17JUN12A 23JUN12A 10JUL12A 16JUL12A 11NOV12A 16JUN12A 20JUN12A 21JUN12A 11JUL12A 12AUG12A 12AUG12A 09JAN13A

Superstructure & Close-in


KAN-0008
Start Date Finish Date Data Date Run Date

KHQ - Inst of Steel Bar for Stem Wall


26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity

10
PS19

100 25JUL12A
FCEC UIProjects JV

12AUG12A
Sheet 21 of 38 Date Revision Checked Approved

W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID KAN-0009 KAN-0010

Activity Description KHQ - Concrete for Stem Walls KHQ - Installation of K Span

Orig Dur 12 15

Rem Dur 0 0

Early Start

Early Finish 09JAN13A 26FEB13A

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

100 10SEP12A 100 28OCT12A

Architectural - Exterior
KAN-0013 KAN-0011 KAN-0012 KHQ - Windows Installation KHQ - Ext Door Instalation KHQ - Ext Painting of Stem Wall 8 8 7 8 8 7 50 05DEC12A 40 05JAN13A 75 01MAR13A 09APR13 09APR13 08APR13 45 45 46

Architectural - Interior
KAN-0014 KAN-0015 KAN-0017 KAN-0016 KAN-0018 KAN-0019 KHQ - Plaster for Stem Wall KHQ - Spray Insulation KHQ - Inst. gypsum board KHQ - Inst. Suspended Ceiling KHQ - Interior Doors Inst KHQ - Sealed Concrete for floor 15 7 10 15 5 5 15 7 10 15 5 5 90 0 0 0 0 0 10NOV12A 18APR13 27APR13 27APR13 08MAY13 21MAY13 17APR13 25APR13 07MAY13 13MAY13 13MAY13 26MAY13 21 21 21 26 21 26

Electrical
KAN-0020 KAN-0021 KAN-0022 KAN-0023 KAN-0024 KHQ - Ele PVC Conduits/Fittings/Boxes KHQ - Electrical Wiring Works KHQ - Lighting Fix.&Cover Plates Inst KHQ - Duplex & Switch Inst KHQ - Panel Board Inst 6 7 6 8 3 0 7 6 8 3 100 0 0 0 0 01MAR13A 01APR13 14MAY13 14MAY13 20JUL13 08MAR13A 08APR13 20MAY13 22MAY13 22JUL13

56 26 21 -23

Mechanical
KAN-0026 KAN-0025 KAN-0027 KHQ - Exhaust Fan Inst. KHQ - AC Split Installation KHQ - Unit Heater Inst. 2 3 2 2 3 2 0 18JUN13 0 18JUN13 0 22JUN13 19JUN13 20JUN13 23JUN13 2 -1 -1

Plumbing
KAN-0028 KAN-0029 KAN-0030 KHQ - Hot&Cold Water Piping KHQ - Toilet & Misc. Accessories KHQ - Toilet Sanitry Fixture Inst. 9 5 8 9 5 8 50 05DEC12A 0 13APR13 0 13APR13 11APR13 17APR13 21APR13 51 54 51

Fire Protection System


KAN-0031 KHQ - Fire Extinguisher Inst. 3 3 0 20JUN13 23JUN13 2

Inspections, Punchlists
KAN-0032 KAN-0033 KAN-0034 KHQ - Test & Commission KHQ - Punchlist Works KHQ - Finishing & Handover 2 5 1 2 5 1 0 23JUL13 0 25JUL13 0 31JUL13 24JUL13 30JUL13 31JUL13 -23 -23 -23

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 22 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Administration Building #109


Foundations
ADM-0001 ADM-0002 ADM-0003 ADM-0004 ADM-0005 ADM-0006 ADM-0007 ADB 109 - Layout ADB 109 - Excavation Work ADB 109 - Watering, Backfilling & Compaction ADB 109 - Foundation & Ring Beam ADB 109 - BKFLNG, CMPCTN, CAP. & Vap. Barriers ADB 109 - Formwork & RFT for Slab on Grade ADB 109 - Concrete Works for Slab on Grade 2 4 4 10 8 10 4 0 0 0 0 0 0 0 100 100 100 100 100 100 100 09APR12A 12APR12A 16APR12A 10MAY12A 16JUN12A 19JUN12A 26JUN12A 10APR12A 16APR12A 22APR12A 18NOV12A 24JUN12A 30JUN12A 30JUN12A

Superstructure & Close-in


ADM-0008 ADM-0009 ADM-0010 ADB 109 - Inst. of Steel Bar for Stem Walls ADB 109 - Concrete for Stem Walls ADB 109 - Installation of K Span 4 7 13 0 0 0 100 01JUL12A 100 02JUL12A 100 01OCT12A 04JUL12A 20SEP12A 09OCT12A

Architectural - Exterior
ADM-0013 ADM-0012 ADM-0011 ADB 109 - Windows Inst ADB 109 - Ext. Painting of Stem Walls ADB 109 - Ext. Door Inst 6 13 5 0 13 5 100 29NOV12A 15 18MAR13A 0 09APR13 16JAN13A 15APR13 14APR13

39 57

Architectural - Interior
ADM-0014 ADM-0015 ADM-0017 ADM-0019 ADM-0018 ADM-0016 ADB 109 - Plaster Work for steam Walls ADB 109 - Spray Insulation ADB 109 - Inst. of gypsum Board ADB 109 - Sealed Concrete for Floor ADB 109 - Interior Doors Instalation ADB 109 - Inst. of Suspended Ceiling 8 7 8 4 5 8 0 7 8 4 5 8 100 70 10 20 0 0 10OCT12A 10DEC12A 18DEC12A 23MAR13A 10APR13 10APR13 18OCT12A 08APR13 09APR13 04APR13 15APR13 18APR13

37 37 68 39 39

Electrical
ADM-0020 ADM-0023 ADM-0021 ADM-0022 ADM-0024 ADB 109 - Ele PVC Conduits/Fittings/Boxes ADB 109 - Duplex & Switch Inst ADB 109 - Electrical Wiring Works ADB 109 - Lighting Fix. & Cover Plates Inst. ADB 109 - Panel Board Inst. 9 7 6 7 3 7 7 6 7 3 75 0 0 0 0 18FEB13A 10APR13 18APR13 22APR13 20JUL13 08APR13 17APR13 24APR13 29APR13 22JUL13 38 37 37 37 -25

Mechanical
ADM-0026 ADM-0025 ADM-0027 ADB 109 - Exhaust Fan Installation ADB 109 - AC Split Installation ADB 109 - Unit Heater Installation 3 5 2 3 5 2 30 28MAR13A 0 30APR13 0 06MAY13 20JUN13 05MAY13 07MAY13 -1 37 37

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 23 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Plumbing
ADM-0028 ADM-0029 ADM-0030 ADB 109 - Hot & Cold Water Piping ADB 109 - Toilet & Misc. Accessories ADB 109 - Toilet Sanitry Fixture Inst 7 5 6 7 5 6 50 01DEC12A 0 09APR13 0 09APR13 08APR13 14APR13 15APR13 54 54 54

Fire Protection System


ADM-0031 ADB 109 - Fire Extinguisher Inst. 3 3 0 08MAY13 11MAY13 37

Inspections, Punchlists
ADM-0032 ADM-0033 ADM-0034 ADB 109 - Test & Commission ADB 109 - Punchlist Works ADB 109 - Finishing & Handover 2 7 1 2 7 1 0 23JUL13 0 25JUL13 0 03AUG13 24JUL13 01AUG13 03AUG13 -25 -25 -25

Large Latrine #110


Foundations
LA1-0001 LA1-0002 LA1-0003 LA1-0004 LA1-0005 LA1-0006 LA1-0007 LTB 110- Layout LTB 110- Excavation Work LTB 110- Watering, Backfilling & Compaction LTB 110- Foundation & Ring Beam LTB 110- BKFLNG, CMPCTN, CAP. & Vap. Barriers LTB 110- Formwork & RFT for Slab on Grade LTB 110- Concrete Works for Slab on Grade 2 5 5 12 9 12 4 0 0 0 0 0 0 0 100 100 100 100 100 100 100 04APR12A 07APR12A 14APR12A 21APR12A 12JUN12A 14JUN12A 25JUN12A 05APR12A 11APR12A 19APR12A 11JUN12A 11JUL12A 11JUL12A 16SEP12A

Superstructure & Close-in


LA1-0008 LA1-0009 LA1-0010 LTB 110- Inst. Steel Bar for Stem Walls LTB 110- Concrete for Stem Walls LTB 110- Installation of K Span 13 15 20 0 0 0 100 17JUN12A 100 19JUN12A 100 01OCT12A 02JUL12A 27OCT12A 09OCT12A

Architectural - Exterior
LA1-0011 LA1-0013 LA1-0012 LTB 110- Exterior Door Installaion LTB 110- Windows Installation LTB 110- Ext. Painting of Stem Walls 6 7 10 6 0 7 45 18DEC12A 100 20DEC12A 90 18FEB13A 07APR13 26JAN13A 08APR13 56 56

Architectural - Interior
LA1-0014 LA1-0018 LA1-0015 LA1-0017 LA1-0016 LA1-0019 LTB 110- Plaster Work for Steam Walls LTB 110- Int. Doors Installation LTB 110- Spray Insulation LTB 110- Inst of gypsum Board LTB 110- Inst. of gypsum Board Ceiling LTB 110- Tiles for floor 12 7 7 12 12 10 0 7 7 12 12 10 100 30 0 0 0 0 18NOV12A 30DEC12A 01APR13 09APR13 23APR13 04MAY13 01DEC12A 08APR13 08APR13 22APR13 06MAY13 14MAY13

56 36 36 36 36

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 24 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Electrical
LA1-0020 LA1-0023 LA1-0021 LA1-0022 LA1-0024 LTB 110- Ele PVC Conduits/Fittings/Boxes LTB 110- Duplex & Switch Inst. LTB 110- Electrical Wiring Works LTB 110- Lighting Fix. & Cover Plates Inst. LTB 110- Panel Board Inst. 5 5 3 3 3 0 5 3 3 3 100 0 0 0 0 18FEB13A 23APR13 06APR13 04MAY13 20JUL13 23FEB13A 28APR13 08APR13 06MAY13 22JUL13

40 56 36 -24

Mechanical
LA1-0026 LA1-0027 LTB 110- Exhaust Fan Inst. LTB 110- Unit Heater Installation 1 1 1 1 90 01MAR13A 0 18JUN13 18JUN13 18JUN13 5 6

Plumbing
LA1-0028 LA1-0030 LA1-0029 LTB 110- Hot & Cold Water Piping LTB 110- Toilet Sanitry Fixture Inst. LTB 110- Toilet & Misc. Accessories 7 7 5 7 7 5 50 01DEC12A 50 02FEB13A 0 09APR13 08APR13 08APR13 14APR13 64 67 64

Fire Protection System


LA1-0031 LTB 110- Fire Extinguisher Inst. 1 1 0 19JUN13 19JUN13 5

Inspections, Punchlists
LA1-0032 LA1-0033 LA1-0034 LTB 110- Test & Commission LTB 110- Punchlist Works LTB 110- Finishing & Handover 2 5 1 2 5 1 0 23JUL13 0 25JUL13 0 31JUL13 24JUL13 30JUL13 31JUL13 -23 -23 -23

Large Latrine #111


Foundations
LA2-0001 LA2-0002 LA2-0003 LA2-0004 LA2-0005 LA2-0006 LA2-0007 LTB 111- Layout LTB 111- Excavation Work LTB 111- Watering, Backfilling & Compaction LTB 111- Foundation & Ring Beam Works LTB 111- BKFLNG, CMPCTN, CAP. & Vap. Barriers LTB 111- Formwork & RFT for Slab on Grade LTB 111- Concrete for Slab on Grade 2 5 5 12 2 12 7 0 0 0 0 0 0 0 100 100 100 100 100 100 100 05APR12A 08APR12A 14APR12A 15MAY12A 05JUN12A 12JUN12A 14JUL12A 07APR12A 12APR12A 09OCT12A 28MAY12A 11JUN12A 25JUN12A 17SEP12A

Superstructure & Close-in


LA2-0008 LA2-0009 LA2-0010 LTB 111- Inst of Steel Bar for Stem Walls LTB 111- Inst. of Concrete Stem Walls LTB 111- Installation of K Span 12 15 15 0 0 0 100 18JUN12A 100 04JUL12A 100 01OCT12A 03JUL12A 01OCT12A 09OCT12A

Architectural - Exterior
LA2-0013
Start Date Finish Date Data Date Run Date

LTB 111- Windows Installation


26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity PS19

100 24DEC12A
FCEC UIProjects JV

31JAN13A
Sheet 25 of 38 Date Revision Checked Approved

W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID LA2-0011 LA2-0012

Activity Description LTB 111- Ext. Door installaion LTB 111- Ext. Painting of Stem Walls

Orig Dur 5 15

Rem Dur 5 15

Early Start 40 19JAN13A 30 26MAR13A

Early Finish 06APR13 17APR13

Total Float 12 26

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Architectural - Interior
LA2-0014 LA2-0015 LA2-0016 LA2-0017 LA2-0018 LA2-0019 LTB 111- Plaster for Steam Walls LTB 111- Spray Insulation LTB 111- Inst of gypsum Board Ceiling LTB 111- Inst. of gypsum Board LTB 111- Int. Doors Installation LTB 111- Tiles for floor 7 7 6 10 7 15 0 7 6 10 7 15 100 0 0 0 0 0 18NOV12A 07APR13 15APR13 15APR13 27APR13 24APR13 25NOV12A 14APR13 21APR13 25APR13 04MAY13 11MAY13

12 39 12 12 39

Electrical
LA2-0020 LA2-0021 LA2-0022 LA2-0024 LA2-0023 LTB 111- Ele PVC Conduits/Fittings/Boxes LTB 111- Electrical Wiring Works LTB 111- Lighting Fix. & Cover Plates Inst. LTB 111- Panel Board Installation LTB 111- Duplex & Switch Inst. 4 5 2 6 2 0 5 2 6 2 100 0 0 0 0 18FEB13A 01APR13 22APR13 20JUL13 09JUN13 21FEB13A 06APR13 23APR13 25JUL13 10JUN13

52 39 -26 12

Mechanical
LA2-0025 LA2-0026 LTB 111- Exhaust Fan Installation LTB 111- Unit Heater Installation 1 1 1 1 90 01MAR13A 0 19JUN13 18JUN13 19JUN13 5 5

Plumbing
LA2-0027 LA2-0029 LA2-0028 LTB 111- Hot & Cold Water Piping LTB 111- Toilet Sanitry Fixture Inst. LTB 111- Toilet & Misc. Accessories 7 7 4 7 7 4 25 01DEC12A 10 01MAR13A 0 10APR13 09APR13 09APR13 14APR13 60 65 60

Fire Protection System


LA2-0030 LTB 111- Fire Extinguisher Inst. 1 1 0 18JUN13 18JUN13 6

Inspections, Punchlists
LA2-0031 LA2-0032 LA2-0033 LTB 111- Test & Commission LTB 111- Punchlist Works LTB 111- Finishing & Handover 2 5 1 2 5 1 0 27JUL13 0 29JUL13 0 04AUG13 28JUL13 03AUG13 04AUG13 -26 -26 -26

Large Latrine #112


Foundations
LA3-0001 LA3-0002 LA3-0003 LA3-0004 LA3-0005
Start Date Finish Date Data Date Run Date

LTB 112- Layout LTB 112- Excavation Work LTB 112- Watering, Backfilling & Compaction LTB 112- Foundation & Ring Beam Works LTB 112- BKFLNG, CMPCTN, CAP. & Vap. Barriers
26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity

2 5 5 15 9
PS19

0 0 0 0 0

100 100 100 100 100

07APR12A 11APR12A 21APR12A 12MAY12A 12JUN12A

08APR12A 16APR12A 25APR12A 11JUN12A 21JUN12A


Sheet 26 of 38 Date Revision Checked Approved

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID LA3-0006 LA3-0007

Activity Description LTB 112- Formwork & RFT for Slab on Grade LTB 112- Concrete Works for Slab on Grade

Orig Dur 12 8

Rem Dur 0 0

Early Start

Early Finish 05JUL12A 18SEP12A

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

100 23JUN12A 100 07JUL12A

Superstructure & Close-in


LA3-0008 LA3-0009 LA3-0010 LTB 112- Inst. of Steel Bar for Stem Walls LTB 112- Concrete Stem Walls LTB 112- Installation of K Span 12 12 15 0 0 0 100 25JUN12A 100 11JUL12A 100 02OCT12A 10JUL12A 02OCT12A 09OCT12A

Architectural - Exterior
LA3-0011 LA3-0012 LA3-0013 LTB 112- Ext. Door Installaion LTB 112- Ext. Painting of Stem Walls LTB 112- Windows Installation 8 15 9 8 15 0 50 17DEC12A 60 17DEC12A 100 25DEC12A 08APR13 17APR13 04FEB13A 29 29

Architectural - Interior
LA3-0014 LA3-0015 LA3-0016 LA3-0017 LA3-0019 LA3-0018 LTB 112- Plaster for Steam Walls LTB 112- Spray Insulation LTB 112- Inst. of gypsum Board ceiling LTB 112- Inst. of gypsum Board LTB 112- Tiles for floor LTB 112- Interior Doors Inst. 10 7 7 15 10 12 0 7 7 15 10 12 100 0 0 0 0 0 10NOV12A 09APR13 16APR13 23APR13 27APR13 08MAY13 20NOV12A 15APR13 22APR13 07MAY13 07MAY13 21MAY13

29 29 29 42 25

Electrical
LA3-0020 LA3-0021 LA3-0022 LA3-0023 LA3-0024 LTB 112- Ele PVC Conduits/Fittings/Boxes LTB 112- Electrical Wiring Works LTB 112- Lighting Fix. & Cover Plates Inst. LTB 112- Duplex & Switch Inst. LTB 112- Panel Board Inst. 4 5 3 2 3 0 5 3 2 3 100 0 0 0 0 17FEB13A 01APR13 23APR13 22MAY13 20JUL13 20FEB13A 06APR13 25APR13 23MAY13 22JUL13

56 42 25 -23

Mechanical
LA3-0025 LA3-0026 LTB 112- Exhaust Fan Inst. LTB 112- Unit Heater Inst. 1 1 1 1 80 01MAR13A 0 19JUN13 18JUN13 19JUN13 2 2

Plumbing
LA3-0027 LA3-0029 LA3-0028 LTB 112- Hot & Cold Water Piping LTB 112- Toilet Sanitry Fixture Inst. LTB 112- Toilet & Misc. Accessories 7 7 4 7 7 4 50 01DEC12A 10 01MAR13A 0 10APR13 09APR13 09APR13 14APR13 57 62 57

Fire Protection System


LA3-0030 LTB 112- Fire Extinguisher Inst. 1 1 0 19JUN13 19JUN13 5

Inspections, Punchlists
LA3-0031
Start Date Finish Date Data Date Run Date

LTB 112- Test & Commission


26JUL11 05SEP13 01APR13 13APR13 10:09 Early Bar Progress Bar Critical Activity PS19

0 23JUL13
FCEC UIProjects JV

24JUL13
Sheet 27 of 38

-23

W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID LA3-0032 LA3-0033

Activity Description LTB 112- Punchlist Works LTB 112- Finishing & Handover

Orig Dur 5 1

Rem Dur 5 1

Early Start 0 25JUL13 0 31JUL13

Early Finish 30JUL13 31JUL13

Total Float -23 -23

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Large Latrine #113


Foundations
L4-0001 L4-0002 L4-0003 L4-0004 L4-0005 L4-0006 L4-0007 LTB 113- Layout LTB 113- Excavation Work LTB 113- Watering, Backfilling & Compaction LTB 113- Foundation & Ring Beam Works LTB 113- BKFLNG, CMPCTN, CAP. & Vap. Barriers LTB 113- Formwork & RFT for Slab on Grade LTB 113- Concrete for Slab on Grade 1 5 5 12 9 12 12 0 0 0 0 0 0 0 100 100 100 100 100 100 100 07APR12A 11APR12A 17APR12A 01MAY12A 21MAY12A 03JUN12A 24JUN12A 07APR12A 16APR12A 22APR12A 20MAY12A 02JUN12A 23JUN12A 08JUL12A

Superstructure & Close-in


L4-0008 L4-0009 L4-0010 LTB 113- Inst. of Steel Bar for Steam Walls LTB 113- Inst. of Concrete Steam Walls LTB 113- Installation of K Span 10 12 15 0 0 0 100 30JUN12A 100 11JUL12A 100 02DEC12A 10JUL12A 09DEC12A 06DEC12A

Architectural - Exterior
L4-0011 L4-0013 L4-0012 LTB 113- Exterior Door Inst. LTB 113- Windows Installation LTB 113- Ext. Painting of Stem Walls 6 12 14 6 0 14 40 26DEC12A 100 01JAN13A 60 20MAR13A 07APR13 09FEB13A 16APR13 64 49

Architectural - Interior
L4-0014 L4-0015 L4-0016 L4-0017 L4-0019 L4-0018 LTB 113- Plaster Work for Steam Walls LTB 113- Spray Insulation LTB 113- Inst. of gypsum Board Ceiling LTB 113- Inst. of gypsum Board LTB 113- Tiles for floor LTB 113- Int. Doors Installation 7 7 10 14 10 15 7 7 10 14 10 15 20 0 0 0 0 0 10JAN13A 09APR13 17APR13 17APR13 01MAY13 04MAY13 08APR13 16APR13 28APR13 02MAY13 12MAY13 20MAY13 19 19 19 35 19 35

Electrical
L4-0020 L4-0021 L4-0022 L4-0023 L4-0024 LTB 113- Ele PVC Conduits/Fittings/Boxes LTB 113- Electrical Wiring Works LTB 113- Lighting Fix. & Cover Plates Inst LTB 113- Duplex & Switch Inst. LTB 113- Panel Board Inst. 4 5 2 5 3 0 5 2 5 3 100 0 0 0 0 26FEB13A 01APR13 29APR13 04MAY13 20JUL13 02MAR13A 06APR13 30APR13 08MAY13 22JUL13

39 19 35 -24

Mechanical
L4-0025 L4-0026 LTB 113- Exhaust Fan Inst. LTB 113- Unit Heater Inst. 2 2 2 2 90 27MAR13A 0 20JUN13 19JUN13 22JUN13 -1 -1

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 28 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Plumbing
L4-0029 L4-0027 L4-0028 LTB 113- Toilet Sanitry Fixture Inst. LTB 113- Hot & Cold Water Piping LTB 113- Toilet & Misc. Accessories 9 7 4 9 7 4 10 01MAR13A 0 13MAY13 0 21MAY13 10APR13 20MAY13 25MAY13 61 19 19

Fire Protection System


L4-0030 LTB 113- Fire Extinguisher Inst. 2 2 0 23JUN13 24JUN13 1

Inspections, Punchlists
L4-0031 L4-0032 L4-0033 LTB 113- Test & Commission LTB 113- Punchlist Works LTB 113- Finishing & Handover 2 5 1 2 5 1 0 23JUL13 0 25JUL13 0 31JUL13 24JUL13 30JUL13 31JUL13 -23 -23 -23

Large Latrine #114


Foundations
LA5-0001 LA5-0002 LA5-0003 LA5-0004 LA5-0005 LA5-0006 LA5-0007 LTB 114- Layout LTB 114- Excavation Work LTB 114- Watering, Backfilling & Compaction LTB 114- Foundation & Ring Beam Works LTB 114- BKFLNG, CMPCTN, CAP. & Vap. Barriers LTB 114- Formwork & RFT for Slab on Grade LTB 114- Concrete for Slab on Grade 1 5 5 12 9 12 4 0 0 0 0 0 0 0 100 100 100 100 100 100 100 08APR12A 14APR12A 21APR12A 28APR12A 12MAY12A 22MAY12A 06JUN12A 08APR12A 19APR12A 26APR12A 10MAY12A 21MAY12A 05JUN12A 11JUN12A

Superstructure & Close-in


LA5-0008 LA5-0009 LA5-0010 LTB 114- Inst. Steel Bar for Stem Walls LTB 114- Concrete for Stem Walls LTB 114- Installation of K Span 4 8 15 0 0 0 100 16JUN12A 100 11JUL12A 100 15AUG12A 09SEP12A 18SEP12A 26SEP12A

Architectural - Exterior
LA5-0011 LA5-0013 LA5-0012 LTB 114- Ext. Door Installaion LTB 114- Windows Installation LTB 114- Ext. Painting of Stem Walls 15 15 18 15 0 18 40 18DEC12A 100 05JAN13A 0 27APR13 17APR13 09FEB13A 16MAY13 8 26

Architectural - Interior
LA5-0014 LA5-0015 LA5-0016 LA5-0017 LA5-0018 LA5-0019 LTB 114- Plaster Work for Stem Walls LTB 114- Spray Insulation LTB 114- Inst. of gypsum Board Ceiling LTB 114- Inst. of gypsum Board LTB 114- Int. Doors Installation LTB 114- Tiles for Floor 7 7 6 15 10 15 0 7 6 15 10 15 100 0 0 0 0 0 10OCT12A 18APR13 27APR13 27APR13 18MAY13 12MAY13 17OCT12A 25APR13 02MAY13 13MAY13 28MAY13 28MAY13

8 8 29 26 8

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 29 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Electrical
LA5-0020 LA5-0021 LA5-0022 LA5-0023 LA5-0024 LTB 114- Ele PVC Conduits/Fittings/Boxes LTB 114- Electrical Wiring Works LTB 114- Lighting Fix. & Cover Plates Inst. LTB 114- Duplex & Switch Inst. LTB 114- Panel Board Inst. 4 5 3 5 3 0 5 3 5 3 100 0 0 0 0 18FEB13A 01APR13 04MAY13 20MAY13 20JUL13 21FEB13A 06APR13 06MAY13 25MAY13 22JUL13

31 8 26 -24

Mechanical
LA5-0025 LA5-0026 LTB 114- Exhaust Fan Inst. LTB 114- Unit Heater Inst. 1 1 1 1 90 28MAR13A 0 18JUN13 18JUN13 18JUN13 2 2

Plumbing
LA5-0028 LA5-0027 LA5-0029 LTB 114- Toilet & Misc. Accessories LTB 114- Hot & Cold Water Piping LTB 114- Toilet Sanitry Fixture Inst. 5 7 4 5 7 4 10 01MAR13A 0 29MAY13 0 06JUN13 06APR13 05JUN13 10JUN13 64 8 8

Fire Protection System


LA5-0030 LTB 114- Fire Extinguisher Inst. 1 1 0 19JUN13 19JUN13 5

Inspections, Punchlists
LA5-0031 LA5-0032 LA5-0033 LTB 114- Test & Commission LTB 114- Punchlist Works LTB 114- Finishing & Handover 2 5 1 2 5 1 0 23JUL13 0 25JUL13 0 31JUL13 24JUL13 30JUL13 31JUL13 -23 -23 -23

Large Latrine #115


Foundations
LA6-0001 LA6-0002 LA6-0003 LA6-0004 LA6-0005 LA6-0006 LA6-0007 LTB 115- Layout LTB 115- Excavation Work LTB 115- Watering, Backfilling & Compaction LTB 115- Foundation & Ring Beam LTB 115- BKFLNG, CMPCTN, CAP. & Vap. Barriers LTB 115- Formwork & RFT for Slab on Grade LTB 115- Concrete for Slab on Grade 1 5 5 12 9 12 4 0 0 0 0 0 0 0 100 100 100 100 100 100 100 09APR12A 14APR12A 21APR12A 26APR12A 12MAY12A 26MAY12A 11JUN12A 09APR12A 19APR12A 25APR12A 10MAY12A 24MAY12A 10JUN12A 16JUN12A

Superstructure & Close-in


LA6-0008 LA6-0009 LA6-0010 LTB 115- Inst. of Steel Bar for Stem Walls LTB 115- Concrete Stem Walls LTB 115- Installation of K Span 4 8 15 0 0 0 100 20JUN12A 100 26JUN12A 100 27NOV12A 25JUN12A 19JAN13A 05DEC12A

Architectural - Exterior
LA6-0013
Start Date Finish Date Data Date Run Date

LTB 115- Windows Installation


26JUL11 05SEP13 01APR13 13APR13 10:10 Early Bar Progress Bar Critical Activity

10
PS19

100 05JAN13A
FCEC UIProjects JV

09FEB13A
Sheet 30 of 38 Date Revision Checked Approved

W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID LA6-0011 LA6-0012

Activity Description LTB 115- Ext. Door Installaion LTB 115- Ext. Painting of Steam Walls

Orig Dur 15 15

Rem Dur 15 15

Early Start 40 05JAN13A 20 21MAR13A

Early Finish 17APR13 17APR13

Total Float 11 27

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Architectural - Interior
LA6-0014 LA6-0015 LA6-0016 LA6-0017 LA6-0018 LA6-0019 LTB 115- Plaster for Stem Walls LTB 115- Spray Insulation LTB 115- Inst. of gypsum Board Ceiling LTB 115- Inst. of gypsum Board LTB 115- Int. Doors Installation LTB 115- Tiles for Floor 7 7 6 14 10 15 0 7 6 14 10 15 100 0 0 0 0 0 18MAR13A 18APR13 27APR13 27APR13 13MAY13 07MAY13 25MAR13A 25APR13 02MAY13 12MAY13 23MAY13 23MAY13

11 11 23 23 11

Electrical
LA6-0020 LA6-0021 LA6-0022 LA6-0023 LA6-0024 LTB 115- Ele PVC Conduits/Fittings/Boxes LTB 115- Electrical Wiring Works LTB 115- Lighting Fix. & Cover Plates Inst. LTB 115- Duplex & Switch Inst. LTB 115- Panel Board Installation 4 5 3 4 3 0 5 3 4 3 100 0 0 0 0 26FEB13A 01APR13 04MAY13 20MAY13 20JUL13 20MAR13A 06APR13 06MAY13 23MAY13 22JUL13

34 11 23 -24

Mechanical
LA6-0025 LA6-0026 LTB 115- Exhaust Fan Installation LTB 115- Unit Heater Installation 1 1 1 1 90 26MAR13A 0 18JUN13 18JUN13 18JUN13 2 2

Plumbing
LA6-0027 LA6-0029 LA6-0028 LTB 115- Hot & Cold Water Piping LTB 115- Toilet Sanitry Fixture Inst. LTB 115- Toilet & Misc. Accessories 7 4 5 7 4 5 0 25MAY13 0 02JUN13 0 02JUN13 01JUN13 05JUN13 06JUN13 11 12 11

Fire Protection System


LA6-0030 LTB 115- Fire Extinguisher Inst. 1 1 0 19JUN13 19JUN13 5

Inspections, Punchlists
LA6-0031 LA6-0032 LA6-0033 LTB 115- Test & Commission LTB 115- Punchlist Works LTB 115- Finishing & Handover 2 5 1 2 5 1 0 23JUL13 0 25JUL13 0 31JUL13 24JUL13 30JUL13 31JUL13 -23 -23 -23

MWR Building #105D


Foundations
MWR-0001 MWR-0002 MWR-0003 MWR-0004 MWR-0005
Start Date Finish Date Data Date Run Date

MWR 105D- Layout MWR 105D- Excavation Work MWR 105D- Watering, Backfilling & Compaction MWR 105D- Foundation & Ring Beam MWR 105D- BKFLNG, CMPCTN, CAP. & Vap. Barriers
26JUL11 05SEP13 01APR13 13APR13 10:10 Early Bar Progress Bar Critical Activity PS19

1 3 4 8 8

0 0 0 0 0

100 100 100 100 100

01APR12A 02APR12A 05APR12A 14APR12A 10JUN12A

01APR12A 04APR12A 09APR12A 25APR12A 18JUN12A


Sheet 31 of 38 Date Revision Checked Approved

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur 10 7

Rem Dur 0 0

Early Start

Early Finish 30JUN12A 08JUL12A

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

MWR-0006 MWR 105D- Formwork & RFT for Slab on Grade MWR-0007 MWR 105D- Concrete for Slab on Grade

100 19JUN12A 100 01JUL12A

Superstructure & Close-in


MWR-0008 MWR 105D- Inst. of Steel Bar for Stem Walls MWR-0009 MWR 105D- Inst of Concrete Stem Walls MWR-0010 MWR 105D- Installation of K Span 6 9 13 0 0 0 100 09JUL12A 100 26SEP12A 100 03OCT12A 25SEP12A 19NOV12A 24NOV12A

Architectural - Exterior
MWR-0011 MWR 105D- Ext. Door Installation MWR-0012 MWR 105D- Ext. Painting of Stem Walls MWR-0013 MWR 105D- Windows Installation 9 16 6 9 16 6 90 14FEB13A 90 14FEB13A 50 25FEB13A 15APR13 23APR13 22APR13 44 43 44

Architectural - Interior
MWR-0014 MWR-0015 MWR-0016 DPW-0018 MWR-0019 MWR 105D- Plaster Work for Stem Walls MWR 105D- Spray Insulation MWR 105D- Fence Installation MWR 105D- Int. Doors Installation MWR 105D- Sealed Concrete for Floor 6 4 9 6 4 0 4 9 6 4 100 25 0 0 0 20NOV12A 25NOV12A 06APR13 24APR13 30APR13 26NOV12A 04APR13 15APR13 30APR13 04MAY13

43 47 43 46

Electrical
MWR-0020 MWR-0021 MWR-0022 MWR-0023 MWR-0024 MWR 105D- Ele PVC Conduits/Fittings/Boxes MWR 105D- Electrical Wiring Works MWR 105D- Lighting Fix. & Cover Plates Inst. MWR 105D- Duplex & Switch Inst. MWR 105D- Panel Board Inst. 8 11 10 6 5 0 11 10 6 5 100 0 0 0 0 14FEB13A 06APR13 18APR13 01MAY13 20JUL13 23FEB13A 17APR13 29APR13 07MAY13 24JUL13

45 45 43 -24

Mechanical
MWR-0026 MWR 105D- Exhaust Fan Inst. MWR-0027 MWR 105D- Unit Heater Inst. 2 2 2 2 0 18JUN13 0 20JUN13 19JUN13 22JUN13 2 2

Fire Protection System


MWR-0031 MWR 105D- Fire Extinguisher Inst. 2 2 0 23JUN13 24JUN13 2

Inspections, Punchlists
MWR-0032 MWR 105D- Test & Commission MWR-0033 MWR 105D- Punchlist Works MWR-0034 MWR 105D- Finishing & Handover 2 4 1 2 4 1 0 25JUL13 0 28JUL13 0 01AUG13 27JUL13 31JUL13 01AUG13 -24 -24 -24

DPW Building #116


Foundations
DPW-0001 DPW 116- Layout
Start Date Finish Date Data Date Run Date 26JUL11 05SEP13 01APR13 13APR13 10:10 Early Bar Progress Bar Critical Activity PS19

100 09APR12A
FCEC UIProjects JV

09APR12A
Sheet 32 of 38 Date Revision Checked Approved

W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID DPW-0002 DPW-0003 DPW-0004 DPW-0005 DPW-0006 DPW-0007

Activity Description DPW 116- Excavation Work DPW 116- Watering, Backfilling & Compaction DPW 116- Foundation & Ring Beam DPW 116- BKFLNG, CMPCTN, CAP. & Vap. Barriers DPW 116- Formwork & RFT for Slab on Grade DPW 116- Concrete for Slab on Grade

Orig Dur 8 5 16 9 15 10

Rem Dur 0 0 0 0 0 0

% 100 100 100 100 100 100

Early Start 11APR12A 22APR12A 22APR12A 20MAY12A 25JUN12A 13AUG12A

Early Finish 21APR12A 26APR12A 09JAN13A 21JUN12A 12AUG12A 09SEP12A

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Superstructure & Close-in


DPW-0008 DPW 116- Inst. of Steel Bar for Steam Walls DPW-0009 DPW 116- Inst. of Concrete Steam Walls DPW-0010 DPW 116- Installation of K Span 12 12 15 0 0 0 100 26JUN12A 100 10SEP12A 100 02OCT12A 08JUL12A 14JAN13A 26NOV12A

Architectural - Exterior
DPW-0013 DPW 116- Windows Installation DPW-0011 DPW 116- Ext. Door Installaion DPW-0012 DPW 116- Ext. Painting of Stem Walls 10 8 18 10 8 10 95 05DEC12A 30 01JAN13A 20 16FEB13A 11APR13 09APR13 11APR13 66 66 49

Architectural - Interior
DPW-0014 DPW-0015 DPW-0017 DPW-0016 DPW-0019 DPW 116- Plaster for Steam Walls DPW 116- Spray Insulation DPW 116- Inst. of gypsum Board DPW 116- Inst. of Suspended Ceiling DPW 116- Sealed Concrete for Floor 15 15 15 8 5 15 10 10 8 5 85 60 20 0 0 14NOV12A 10DEC12A 16FEB13A 18APR13 29APR13 17APR13 11APR13 11APR13 27APR13 04MAY13 35 40 66 35 35

Electrical
DPW-0020 DPW-0023 DPW-0021 DPW-0022 DPW-0024 DPW 116- Ele PVC Conduits/Fittings/Boxes DPW 116- Duplex & Switch Inst. DPW 116- Electrical Wiring Works DPW 116- Lighting Fix. & Cover Plates Inst. DPW 116- Panel Board Inst. 3 4 6 2 3 0 4 6 2 3 100 0 0 0 0 16FEB13A 01APR13 01APR13 28APR13 20JUL13 18FEB13A 04APR13 07APR13 29APR13 22JUL13

66 52 35 -23

Mechanical
DPW-0025 DPW 116- AC Split Installation DPW-0027 DPW 116- Unit Heater Installation DPW-0026 DPW 116- Exhaust Fan Installation 1 1 1 1 1 1 0 06APR13 0 12MAY13 0 18JUN13 06APR13 12MAY13 18JUN13 66 35 3

Plumbing
DPW-0028 DPW 116- Hot & Cold Water Piping DPW-0030 DPW 116- Toilet Sanitry Fixture Inst. DPW-0029 DPW 116- Toilet & Misc. Accessories 6 4 5 6 4 5 0 30APR13 0 07MAY13 0 07MAY13 06MAY13 11MAY13 12MAY13 35 35 35

Fire Protection System


DPW-0031 DPW 116- Fire Extinguisher Inst.
Start Date Finish Date Data Date Run Date 26JUL11 05SEP13 01APR13 13APR13 10:10 Early Bar Progress Bar Critical Activity PS19

0 30APR13
FCEC UIProjects JV

30APR13
Sheet 33 of 38

48
Date Revision Checked Approved

W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Inspections, Punchlists
DPW-0032 DPW 116- Test & Commission DPW-0033 DPW 116- Punchlist Works DPW-0034 DPW 116- Finishing & Handover 2 5 1 2 5 1 0 23JUL13 0 25JUL13 0 31JUL13 24JUL13 30JUL13 31JUL13 -23 -23 -23

Literacy Classroom #117A


Foundations
LCR1-001 LCR1-002 LCR1-003 LCR1-004 LCR1-005 LCR1-007 LCR1-006 LCR 117A - Layout LCR 117A - Excavation Work LCR 117A - Watering, Backfilling & Compaction LCR 117A - Foundation & Ring Beam LCR 117A - BKFLNG, CMPCTN, CAP. & Vap. Barriers LCR 117A - Concrete for Slab on Grade LCR 117A - Formwork & RFT for Slab on Grade 1 3 3 8 8 5 13 0 0 0 0 0 0 0 100 100 100 100 100 100 100 03APR12A 04APR12A 08APR12A 14APR12A 21MAY12A 25JUN12A 25JUN12A 03APR12A 07APR12A 10APR12A 25APR12A 05JUL12A 02JUL12A 08JUL12A

Superstructure & Close-in


LCR1-008 LCR1-009 LCR1-010 LCR 117A - Inst. of Steel Bar for Stem Walls LCR 117A - Concrete for Stem Walls LCR 117A - Installation of K Span 6 10 15 0 0 0 100 28JUN12A 100 05JUL12A 100 12AUG12A 04JUL12A 02OCT12A 08OCT12A

Architectural - Exterior
LCR1-013 LCR1-011 LCR1-012 LCR 117A - Windows Installation LCR 117A - Ext. Door Installaion LCR 117A - Ext. Painting of Stem Walls 5 5 11 0 5 0 100 01DEC12A 90 18DEC12A 100 18FEB13A 29JAN13A 06APR13 31MAR13A

60

Architectural - Interior
LCR1-014 LCR1-015 LCR1-017 LCR1-016 LCR1-018 LCR 117A - Plaster Work for Steam Walls LCR 117A - Spray Insulation LCR 117A - Int. Doors Installation LCR 117A - Fence Installation LCR 117A - Sealed Concrete for Floor 13 7 5 10 8 0 7 5 10 8 100 95 30 0 0 10OCT12A 25NOV12A 03MAR13A 09APR13 21APR13 24OCT12A 08APR13 06APR13 20APR13 29APR13

48 61 48 48

Electrical
LCR1-019 LCR1-020 LCR1-021 LCR1-022 LCR1-023 LCR 117A - Ele PVC Conduits/Fittings/Boxes LCR 117A - Electrical Wiring Works LCR 117A - Duplex & Switch Inst. LCR 117A - Lighting Fix. & Cover Plates Inst. LCR 117A - Panel Board Installation 7 6 5 5 3 0 5 5 5 3 100 30 30 50 0 18FEB13A 26MAR13A 26MAR13A 27MAR13A 20JUL13 25FEB13A 06APR13 06APR13 20APR13 22JUL13

60 61 48 -24

Mechanical
LCR1-024
Start Date Finish Date Data Date Run Date

LCR 117A - Exhaust Fan Installation


26JUL11 05SEP13 01APR13 13APR13 10:10 Early Bar Progress Bar Critical Activity PS19

60 27MAR13A
FCEC UIProjects JV

18JUN13
Sheet 34 of 38

W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID LCR1-025

Activity Description LCR 117A - Unit Heater Installation

Orig Dur 1

Rem Dur 1

Early Start 0 19JUN13

Early Finish 19JUN13

Total Float 4

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

LCR1-026

LCR 117A - Fire Extinguisher Inst.

0 21APR13

21APR13

55

LCR1-027 LCR1-028 LCR1-029

LCR 117A - Test & Commission LCR 117A - Punchlist Works LCR 117A - Finishing & Handover

2 6 1

2 6 1

0 23JUL13 0 25JUL13 0 03AUG13

24JUL13 01AUG13 03AUG13

-24 -24 -24

LCR2-001 LCR2-002 LCR2-003 LCR2-004 LCR2-005 LCR2-006 LCR2-007

LCR 117B- Layout LCR 117B- Excavation Work LCR 117B- Watering, Backfilling & Compaction LCR 117B- Foundation & Ring Beam LCR 117B- BKFLNG, CMPCTN, CAP. & Vap. Barriers LCR 117B- Formwork & RFT for Slab on Grade LCR 117B- Concrete for Slab on Grade

1 3 3 10 9 15 12

0 0 0 0 0 0 0

100 100 100 100 100 100 100

04APR12A 05APR12A 08APR12A 11APR12A 12MAY12A 04JUN12A 20JUN12A

04APR12A 07APR12A 10APR12A 23APR12A 21MAY12A 26JUN12A 05JUL12A

LCR2-008 LCR2-009 LCR2-010

LCR 117B- Inst. of Steel Bar for Stem Walls LCR 117B- Concrete for Stem Walls LCR 117B- Installation of K Span

10 15 15

0 0 0

100 20JUN12A 100 03JUL12A 100 13AUG12A

02JUL12A 02OCT12A 08OCT12A

LCR2-013 LCR2-011 LCR2-012

LCR 117B- Windows Installation LCR 117B- Ext. Door Installation LCR 117B- Ext. Painting of Stem Walls

8 8 12

0 8 0

100 01DEC12A 90 18DEC12A 100 18FEB13A

27JAN13A 09APR13 31MAR13A

56

LCR2-014 LCR2-015 LCR2-017 LCR2-016 LCR2-018

LCR 117B- Plaster for Stem Walls LCR 117B- Spray Insulation LCR 117B- Int. Doors Installation LCR 117B- Fence Installation LCR 117B- Sealed Concrete for Floor

10 7 5 10 8

0 7 5 10 8

100 90 30 0 0

10OCT12A 10DEC12A 04MAR13A 09APR13 10APR13

09FEB13A 08APR13 06APR13 20APR13 18APR13

52 61 52 56

LCR2-019 LCR2-020 LCR2-021 LCR2-022


Start Date Finish Date Data Date Run Date

LCR 117B- Ele PVC Conduits/Fittings/Boxes LCR 117B- Electrical Wiring Works LCR 117B- Duplex & Switch Inst. LCR 117B- Lighting Fix. & Cover Plates Inst.
26JUL11 05SEP13 01APR13 13APR13 10:10 Early Bar Progress Bar Critical Activity PS19

6 7 7 7

0 7 7 7

100 30 30 60

18FEB13A 25FEB13A 27MAR13A 27MAR13A

24FEB13A 08APR13 08APR13 08APR13


Sheet 35 of 38

57 61 57

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Date

Revision

Checked

Approved

Primavera Systems, Inc.

Activity ID LCR2-023

Activity Description LCR 117B- Panel Board Inst.

Orig Dur 3

Rem Dur 3

Early Start 0 20JUL13

Early Finish 22JUL13

Total Float -25

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Mechanical
LCR2-024 LCR2-025 LCR 117B- Exhaust Fan Inst. LCR 117B- Unit Heater Inst. 1 1 1 1 60 27MAR13A 0 19JUN13 18JUN13 19JUN13 0 0

Fire Protection System


LCR2-026 LCR 117B- Fire Extinguisher Inst. 1 1 0 10APR13 10APR13 63

Inspections, Punchlists
LCR2-027 LCR2-028 LCR2-029 LCR 117B- Test & Commission LCR 117B- Punchlist Works LCR 117B- Finishing & Handover 2 7 1 2 7 1 0 23JUL13 0 25JUL13 0 03AUG13 24JUL13 01AUG13 03AUG13 -25 -25 -25

Fire Station #118


Foundations
FSB-0001 FSB-0002 FSB-0003 FSB-0004 FSB-0005 FSB-0006 FSB-0007 FSB 118- Layout FSB 118- Excavation Work FSB 118- Watering, Backfilling & Compaction FSB 118- FDN & Ring Beam FSB 118- BKFLNG, CMPCTN, CAP. & Vap. Barriers FSB 118- Formwork & RFT for Slab on Grade FSB 118- Concrete for Slab on Grade 1 3 3 8 7 5 1 0 0 0 0 0 0 0 100 100 100 100 100 100 100 06APR12A 07APR12A 14APR12A 21APR12A 12MAY12A 07JUL12A 14JUL12A 07APR12A 09APR12A 19APR12A 03MAY12A 05JUL12A 12JUL12A 12AUG12A

Superstructure & Close-in


FSB-0010 FSB-0008 FSB-0009 FSB 118- Installation of K Span FSB 118- Inst. of Steel Bar for Stem Walls FSB 118- Concrete Stem Walls 13 12 10 0 0 0 100 12AUG12A 100 13AUG12A 100 03SEP12A 24NOV12A 29AUG12A 21JAN13A

Architectural - Exterior
FSB-0011 FSB-0013 FSB-0012 FSB 118- Ext. Door Installation FSB 118- Windows Installation FSB 118- Ext. Painting of Stem Walls 7 7 8 7 0 7 90 28DEC12A 100 30DEC12A 90 28FEB13A 07APR13 17JAN13A 08APR13 69 59

Architectural - Interior
FSB-0014 FSB-0015 FSB-0017 FSB-0016 FSB-0018 FSB 118- Plaster for Stem Walls FSB 118- Spray Insulation FSB 118- Int. Doors Instalation FSB 118- Fence Installation FSB 118- Sealed Concrete for Floor 10 7 7 8 5 0 7 7 8 5 100 25 20 0 0 10DEC12A 21FEB13A 01MAR13A 08APR13 28APR13 28MAR13A 07APR13 08APR13 15APR13 02MAY13

54 59 54 46

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:10

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 36 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Electrical
FSB-0019 FSB-0020 FSB-0021 FSB-0022 FSB-0023 FSB 118- Ele PVC Conduits/Fittings/Boxes FSB 118- Electrical Wiring Works FSB 118- Duplex & Switch Inst. FSB 118- Lighting Fix. & Cover Plates Inst. FSB 118- Panel Board Installation 10 12 9 10 5 0 12 9 10 5 100 0 0 0 0 23FEB13A 01APR13 16APR13 16APR13 20JUL13 01MAR13A 14APR13 25APR13 27APR13 24JUL13

47 53 46 -25

Mechanical
FSB-0024 FSB-0025 FSB 118- Exhaust Fan Inst. FSB 118- Unit Heater Inst. 3 3 3 3 45 28MAR13A 25 29MAR13A 20JUN13 20JUN13 -1 -1

Fire Protection System


FSB-0026 FSB 118- Fire Extinguisher Inst. 5 5 0 22JUN13 26JUN13 -1

Inspections, Punchlists
FSB-0027 FSB-0028 FSB-0029 FSB 118- Test & Commission FSB 118- Punchlist Works FSB 118- Finishing & Handover 2 5 1 2 5 1 0 25JUL13 0 28JUL13 0 03AUG13 27JUL13 01AUG13 03AUG13 -25 -25 -25

Contract Close-out
Close-out Inspections

CCO-0001 CCO-0002 CCO-0003

Prefinal Inspection & Correction Final Inspection Final Acceptance & Handover

10 3 1

10 3 1

0 11AUG13 0 22AUG13 0 26AUG13

21AUG13 25AUG13 26AUG13

-22 -22 -22

As-Built Drawings

CCO-0004 CCO-0005

Submit As-Built Drawings Approved As-Built Drawing by AED

6 14

6 14

0 04AUG13 0 10AUG13

09AUG13 23AUG13

-30 -30

O&M Manuals & Training

CCO-0006 CCO-0007

Submit O&M Manual Approved O&M Manual by AED

7 7

7 7

0 04AUG13 0 11AUG13

10AUG13 17AUG13

-24 -24

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:10

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 37 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

Activity ID

Activity Description

Orig Dur

Rem Dur

Early Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A SC

Demobilization

CCO-0012

Demobilization of Site office & Con. Equipments

10

10

0 27AUG13

05SEP13

-32

Start Date Finish Date Data Date Run Date

26JUL11 05SEP13 01APR13 13APR13 10:10

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects JV W5J9JR-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 38 of 38 Date Revision Checked Approved

Primavera Systems, Inc.

You might also like