HVAC Calculation (Base On ASHRAE)

Tag No.

Unit

Equipment Description

SNO-C-8002A SNO-C-9062A SNO-C-9062B SNO-P-6003A SNO-P-6003B SNO-C-8072A SNO-C-8072A-LO1 SNO-E-8074A

UNIT 86 TBA TBA UNIT 16 UNIT 16 UNIT 61 TBA UNIT 61

INSTRUMENT AIR INJECTION PACKAGE : AIR COMPRESSOR A NITROGEN SYSTEM - AIR COMPRESSOR A NITROGEN SYSTEM - AIR COMPRESSOR B CONDENSATE TRANSFER PUMP A CONDENSATE TRANSFER PUMP B INSTRUMENT AIR COMPRESSOR PACKAGE : INSTRUMENT AIR COMPRESSOR A LUBE OIL PUMP FOR INSTRUMENT AIR COMPRESSOR A INSTRUMENT AIR COMPRESSOR PACKAGE : INSTRUMENT AIR COMP. COOLERS A

Operating duty (JOB)


C/I/S

Operating duty (TSC)


C/I/S

I I I I S I I I

C C C C S C C C

TSC will develop load list schedule base on HMB normal case As per Bid Bulletin no. 10/Errata electrical design basis

2 3 4

For Normal Load, based on HMB normal cases, Electrical Load Schedule is calculate with considering adding 30% Inte For the peak load (based on HMB design cases), Electrical only considering Electrical Normal Load which is only consid STG shall be included to Power Generated System and shown in overall single line diagram If STG shutdown, it should be shotdown all WSA system, no Acid Gas removal Unit is shotdown. TSC shall be immadiatelly send Overall Single Line Diagram.

onsidering adding 30% Intermitten and 10 % Standby load and 10% design margin. mal Load which is only considering 30% intermittent Load.