You are on page 1of 80

Facts and Lessons of the Fukushima Nuclear Accident and Safety Improvement -The Operator Viewpoints-

February, 2012 Tokyo Electric Power Company

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

What I will present


1Overview of the Earthquake and Tsunami
- Damages at Fukushima NPSs -What made the difference between Fukushima Daiichi(1F) and Fukushima daini(2F) ?

2. How we responded ?
- How the accident developed - What difficulties existed

3. Other Relevant Items


-Accident Management -Presumption of Reactor Core State by Analysis Code -Hydrogen Explosion -Spent Fuel Pool

4. Current Status and Roadmap toward Decommissioning 5. Lessons Learned and Countermeasures
1

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Overview of the Earthquake and Tsunami


Fukushma Daiichi(1F) Fukushma Daini(2F)

Unit 1Unit 5 Unit 6 Unit 2 Unit 3 Unit 4

Unit 4 Unit 3 Unit 2 Unit 1

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Overview of Fukushima Daiichi NPS (1F) and Fukushima Daini NPS (2F) Plant
In Unit Operation Since 1 2 3 1971.3 1974.7 1976.3 1978.10 1978.4 1979.10 1982.4 1984.2 1985.6 1987.8 Power Main Output Contractor (MWe) BWR-3 460 GE Plant Type BWR-4 BWR-4 BWR-4 BWR-4 BWR-5 BWR-5 BWR-5 BWR-5 BWR-5 784 784 784 784 1100 1100 1100 1100 1100 GE/Toshiba Toshiba Hitachi Toshiba Pre-earthquake Status Operating Operating Operating Shutdown for maintenance Full core offloaded to spent fuel pool Shutdown for maintenance

1F

4 5 6 1

GE/Toshiba Shutdown for maintenance Toshiba Hitachi Toshiba Toshiba Operating Operating Operating Operating
3

2F

2 3 4

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Great East Japan Earthquake


Time: Place: 2:46 pm on Fri, March 11, 2011. Offshore Sanriku coast (northern latitude of 38 degrees, east longitude of 142.9), 24km in depth, Magnitude 9.0 Intensity: Level 7 at Kurihara in Miyagi Miyagi prefecture Upper 6 at Naraha, Tomioka, Okuma, and Futaba in Fukushima pref. Lower 6 at Ishinomaki and Onagawa in Miyagi pref., Tokai in Ibaraki pref. Lower 5 at Kariwa in Niigata pref. Level 4 at Rokkasho, Higashidori, Mutsu and Ohma in Aomori pref., Kashiwazaki in Niigata pref.

Issued at 14:53 on March 11, 2011

1F 2F

epicenter

Seismic Intensity Distribution

Hypocenter Distribution
by Earthquake Research Institute, the University of Tokyo

4th-largest magnitude on record in the world


All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Seismic Observed Data


Comparison between Basic Earthquake Ground Motion and the record of intensity
Observed data Observation Point (The lowest basement of reactor buildings) Maximum Response Acceleration (Gal) Horizontal (N-S) 460 348 322 281 311 298 254 243 277 210 Horizontal (E-W) 447 550 507 319 548 444 230 196 216 205 Vertical 258 302 231 200 256 244 305 232 208 288 Maximum Response Acceleration against Basic Earthquake Ground Motion (Gal) Horizontal (N-S) 487 441 449 447 452 445 434 428 428 415 Horizontal (E-W) 489 438 441 445 452 448 434 429 430 415 Vertical 412 420 429 422 427 415 512 504 504 504

Unit 1 Unit 2

1F

Unit 3 Unit 4 Unit 5 Unit 6 Unit 1

2F

Unit 2 Unit 3 Unit 4

: The recording time was about 130-150 seconds


All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Tsunami observed at 1F

Height: about 10m

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Flooding in 1F

Tank(Height:5.5m)

2011/3/11 15:42 Date 2011/3/11 15:42

2011/3/11 15:42 Date 2011/3/11 15:42

Date 2011/3/11 15:43

2011/3/11 15:43

2011/3/11 15:43 Date 2011/3/11 15:43

2011/3/11 15:43 Date 2011/3/11 15:43

2011/3/11 15:44 Date 2011/3/11 15:44 7

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Damages by Tsunami at 1F
Heavy oil tank floated

Large size crane moved

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Damages by Tsunami at 1F
Sea water pumps are all damaged.

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Inundated Areas at 1F
Inundation throughout almost all areas where main buildings sited
Units 1~4: Inundation height in areas where principal buildings sited: OP approx. 11.5m~15.5m (Localized inundation height in southwest area: OP approx. 16m~17m) Unit 5 & 6: Inundation height in areas where principal buildings sited: OP approx. 13m~14.5m

Almost whole area was flooded

Fukushima Daiichi

Unit 6

Unit 5

Unit 1

Unit 2

Unit 3

Unit 4 Radwaste Processing building

Elevation of major Unit-5,6 buildings: O.P.13m

Elevation of major Unit-1-4 buildings: O.P.10m

C)GeoEye
10

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Location of Sea Water Ingression into Buildings at 1F

O.P.+4m O.P.+4m

Unit 6

Unit 5

Turbine building Reactor building

Unit 1

Unit 2

Unit 3

Unit 4

O.P.+10m

O.P.+13m

Unit 6 D/G building


Openings at the ground level from which sea water could flow into buildings Openings connected to underground trenches/ducts where sea water could flow into buildings
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

3u Emergency D/G air inlet louver

11

Inundated Areas at 2F
Inundation occurred throughout all areas along the sea, but it was not observed to have inundated over the slope and into areas where major buildings are sited. Run up of tsunami centered on the south side of Unit 1
Inundation height in sea side area: OP approx. +7.0~7.5m Inundation height in areas where principal buildings sited: OP approx. 12~14.5m Inundation height in area south of Unit 1: OP approx. + 15~16m

Limited area was flooded

Inflowed intensively
Unit 4 Unit 3 Unit 2 Unit 1

Elevation of major Unit-1-4 buildings: O.P.12m

C)GeoEye
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

12

Tsunami damage at 2F
[Overall view of 2F]
(2) (3) (1)Tsunami run-up

(1)
C)GeoEye

(2)Tsunami damage in lowlying areas (shallow draft quay)

(3) No damage to the Unit 3 and 4 Turbine Building

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

13

Location of Sea Water Ingression into Buildings at 2F


Units 3 & 4 Sea side of turbine building Inside Unit 1 heat exchanger building

Heat exchanger building


Unit 4 Unit 3 Unit 2 Unit 1

Turbine building Reactor building

Openings at the ground level from which sea water could flow into buildings Openings connected to underground trenches/ducts where sea water could flow into buildings
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

14

Tsunami Height 1F v.s. 2F


1F
Ocean-side area

Inundation height apx. O.P. +11.5 15.5m


Main building area Inundation height Safety measures has apx. O.P. +14-15m taken against 5.7m Tsunami height Turbine building Site level O.P. +4m
Water Pump

Reactor building

Design basis Assumed highest tsunami water heightlevel tsunami O.P.+5.7m O.P. +6.1m +5.7m

49

Assumed highest Base level tsunami water level O.P. 0m O.P. +5.7m

Site level O.P. +10m (Units 1-4*) * Site level on Units 5 and 6 is O.P. +13m

breakwater Water intake

Base level O.P. 0m

Inundation height apx. O.P. +7.0 ~ 7.5m Ocean-side area Main building area

2F
Design basis tsunami height O.P.+5.2m

Reactor building

Safety measures has taken against 5.2m Tsunami height Site level Hx building O.P. +4m Site level O.P. +12m breakwater Water intake

Turbine building

Base level O.P.0m

O.P.Onahama Peil

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

15

Differences in Tsunami between 1F and 2F


Fukushima Daiichi Tsunami of various magnitudes at a depth of around 150m were amplified at the same rate and struck at each nuclear power station Peaks coinciding Tsunami height: High Fukushima Daini
14 12 10 8 6 4 2 0 10

Postulated Tsunami Source Model

Maximum tsunami heightm

Same amplification rate


50 [m] Water depth [m] 100

150

Peaks not coinciding Tsunami height: Low

Sea floor displacement [m]

Time T

Water level fluctuation from each block

Warm colored blocks generated massive tsunami wave heights 16

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Permitted Design Basis(1) Tsunami assessment


Historical tsunamis of Iwate and Miyagi coast were larger than that of Fukushima Approved design basis at Fukushima NPS was 3.1-3.7m
3.11.2011 tsunami heights (m) Historical tsunami heights (m)
Inundation Run-up

Fukushima NPSs Fukushima NPSs


Preliminary results by The 2011 Tohoku Earthquake Tsunami Joint Survey Group( http://www.coastal.jp/ttjt/) 07 May 2011

Tsunami assessment in construction permit


Unit Ground Level R/B,Tb/B m 1F 1-4 1F 5-6 2F1-4 10.2 13.2 12 Pumps m 4 4 7 Tsunami Heightm Design Basis 3.1 3.1 3.7 5.2 7-7.5 17 Modified in 2002 (2009) 5.7 (6.1) 11 march 2011 14-15

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Permitted Design Basis(2) Tsunami assessment


Tsunami Assessment was revised based on the JSCE (Japan Society of Civil Engineers) Method,2002
English edition http://www.jsce.or.jp/committee/ceofnp/Tsunami/eng/tsuna mi_eng.html

In JSCE- 2002, assumed 8 earthquakes individually. March 11 Earthquake occurred over several areas simultaneously.
Earthquake #1 #2 #3 #4 #5 #6 #7 #8 2011/3/11 source area Magnitude 8.2 8.4 8.3 8.6 8.2 7.7 7.9 8.1 Earthquake 1952 Nemuro-oki 1968 Tokachi-oki 1896 Meiji-Sanriku 1611 Keicho-Sanriku 1793 Miyagi-oki 1978 Miyagi-oki 1938 Fukushima-oki 1677 Enpo-Bousou 18

All Rights Reserved 2012The Tokyo Electric http://outreach.eri.u-tokyo.ac.jp/eqvolc/201103_tohoku/#Inversion 2011/3/18 Power Company, Inc.

Damages of transmission line & Shinfukushima substation by earthquake


Collapse of filled soil & sand Transmission tower collapse

Tower collapse

Collapse
CGeoEye

- About 10 km away from both 1F and 2F site - Important switchgear station from which electricity of 1F & 2F is transmitted to Tokyo area

500kV Disconnector

275kV Circuit Breaker


19

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Power supply of Unit 1-4 @ 1F after Tsunami


Okuma Line 1L, 2L: Receiving circuit breaker damaged in earthquake Okuma Line 3L: Renovation work in progress Okuma Line 4L: Circuit breaker shutdown by protection relay activation Ohkuma 4L Ohkuma 3L Ohkuma 2L
Shutdown by earthquake Shutdown by Tsunami

Ohkuma 1L

3SB 4B 4A

3SA 3B 3A 2B 2A

2SB

2SA

1S 1B 1A

4D 4E

4C

3D

3C

2D 2E

2C

1D

1C

DG 4B

DG 4A

DG 3B

DG DG 3A 2B

DG 2A

DG 1B

DG 1A

The DG lost the function due to either M/C failure, loss of sea water system, or DG main unit failure.
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

20

Power supply of Unit 5/6 @ 1F after Tsunami


For transmitting generated power

Futaba 1L

Futaba 2L Yonomori 2L

For transmitting generated power

Yonomori 1L

5A

5B

5SA-1

5SA-2

5SB-1

5SB-2

6A-1

6A-2

6B-1

6B-2

5C

5D HPCS Shutdown by earthquake

6C

6D

DG 5A

DG 5B

Shutdown by Tsunami Survived after Tsunami DG HPCS DG 6A

DG 6B

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

21

2F Offsite Power was secured after the Tsunami


Offsite Power
Tomioka Line Iwaido Line 66kV

One 500 kV line was available. 66 kV lines were outage because of scheduled maintenance and substation trouble but recovered.
P
/

500kV H STr

: Cooling Pumps : Diesel Generator

Unit #1, 2 STr

Unit #3, 4 STr

6.9kV

6.9kV

6.9kV

6.9kV

P
/ /

P
/ /

P
/

P
/ /

P
/

P
/ /

P
/

P
/

1H

1A

1B

2H

2A

2B

3H

3A

3B

4H

4A

4B

Emergency Power for Unit #1

Emergency Power for Unit #2

Emergency Power for Unit #3

Emergency Power for Unit #4

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

22

Integrity of Power Supply System After the Tsunami at 1F and 2F


1F:No off-site power available
Fukushima Daiichi
Unit 1 Power panel Emergency DG DG 1A DG 1B Emergency use Regular use
Emergency use
Can/can not be used

2F:Off-site power survived


Fukushima Daini
Unit 6
Can/can not be used

Unit 2 Power panel DG 2A


Can/can not be used

Unit 3 Power panel DG 3A DG 3B M/C 3C M/C 3D M/C 3A M/C 3B M/C 3SA M/C 3SB P/C 3C P/C 3D P/C 3A P/C 3B P/C 3SA P/C 3SB DC125V main bus panel 3A DC125V main bus panel 3B RHRS A RHRS B
Can/can not be used

Unit 4 Power panel DG 4A


Can/can not be used

Unit 5 Power panel DG 5A(*2) DG 5B(*2) M/C 5C M/C 5D M/C 5A M/C 5B M/C 5SA-1

Unit 1
Can/can not be used

Unit 2
Can/can not be used

Unit 3
Can/can not be used

Unit 4
Can/can not be used

Power panel DG 6A DG 6B air-cooled HPCS DG M/C 6C M/C 6D HPCS DG M/C M/C 6A-1 M/C 6A-2 M/C 6B-1 M/C 6B-2

Power panel DG 1A DG DG 1 M/C 1C M/C 1D M/C 1H M/C 1A-1 M/C 1A-2 M/C 1-1 M/C 1-2 M/C 1SA-1 M/C 1SA-2 M/C 1SB-1 M/C 1SB-2

Power panel DG 2A DG 2 DG 2 M/C 2C M/C 2D M/C 2H M/C 2A-1 M/C 2A-2 M/C 2-1 M/C 2-2

Power panel DG 3A DG 3 DG 3 M/C 3C M/C 3D M/C 3H M/C 3A-1 M/C 3A-2 M/C 3-1 M/C 3-2 M/C 3SA-1 M/C 3SA-2 M/C 3SB-1 M/C 3SB-2

Power panel DG 4A DG 4 DG 4 M/C 4C M/C 4D M/C 4H M/C 4A-1 M/C 4A-2 M/C 4-1 M/C 4-2

Can/can not be used

(*2)

(*2) (*2) (*2)

(*2)

(*2) (*2)

DG
M/C 6.9KV M/C

DG 2B (*1) air-cooled M/C 2C M/C 2D M/C 2E M/C 2A M/C 2B M/C 2SA

DG 4B (*1) air-cooled M/C 4C M/C 4D M/C 4E M/C 4A M/C 4B

(*2)

M/C 1C M/C 1D M/C 1A M/C 1

M/C 1S

M/C 2SB

M/C 5SA-2 M/C 5SB-1 M/C 5SB-2 P/C 5C P/C 5D P/C 5A P/C 5A-1 P/C 5B P/C 5B-1 P/C 5SA P/C 5SA-1 P/C 5SB DC125V P/C 5A DC125V P/C 5B RHRS A RHRS B

P/C 1C P/C 1D P/C 1A

P/C 2C P/C 2D P/C 2E P/C 2A P/C 2A-1 P/C 2B P/C 2SB DC125V P/C 2A DC125V P/C 2B RHRS A

P/C 4C P/C 4D P/C 4E P/C 4A P/C 4B DC125V main bus panel 4A DC125V main bus panel 4B RHRS A RHRS B

P/C 6C P/C 6D P/C 6E P/C 6A-1 P/C 6A-2 P/C 6B-1 P/C 6B-2 DC125V DIST CENTER 6A DC125V DIST CENTER 6B RHRS A RHRS B

P/C 1C-1 P/C 1C-2 P/C 1D-1 P/C 1D-2 P/C 1A-1 P/C 1A-2 P/C 1B-1 P/C 1B-2 P/C1SA P/C1SB DC125V main bus panel A DC125V main bus panel B RHRS A RHRS B

P/C 2C-1 P/C 2C-2 P/C 2D-1 P/C 2D-2 P/C 2A-1 P/C 2A-2 P/C 2B-1 P/C 2B-2 DC125V main bus panel A DC125V main bus panel B RHRS A RHRS B

P/C 3C-1 P/C 3C-2 P/C 3D-1 P/C 3D-2 P/C 3A-1 P/C 3A-2 P/C 3B-1 P/C 3B-2 P/C 3SA P/C 3SB DC125V main bus panel A DC125V main bus panel B RHRS A RHRS B

P/C 4C-1 P/C 4C-2 P/C 4D-1 P/C 4D-2 P/C 4A-1 P/C 4A-2 P/C 4B-1 P/C 4B-2 DC125V main bus panel A DC125V main bus panel B RHRS A RHRS B

480V P/C PC
DC power supply Sea water system

Regular use
125V DC

P/C 1B P/C 1S DC125V main bus panel A DC125V main bus panel B

DC

A SW B

RHRS B

Sea Water System

O: operable

X:

damaged
*2 functionality lost due to the damage of sea water system

*1 functionality lost due to inundation of power panels

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

23

1F Unit 1 Schematic System Diagram (After Tsunami )


Stack
D/W vent valve

SRV

IC
RPV

Tb
Condenser H/W SLC

Gen
W

Sea :Operable

S/C vent valve

RFP

CP

CRD

:Inoperative due to power loss : Briefly


Operative

CS CCSW

CCS Sea

from CST H/W

CST HPCI

MUWC DD FP Filtrated Water Tank

D/G

Sea
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

24

1F Unit 2 Schematic System Diagram (After Tsunami)


Stack
SRV D/W vent valve

Tb
RPV
Condenser H/W

Gen
W

Sea :Operable :Inoperative due to power loss :Inoperative

SLC
MDMDRFP S/C vent valve TDTDRFP LPCP

CRD

HPCP

CS RHRS Sea

RHR

from CST H/W

HPCI RCIC

CST CST

D/G

MUWC DD FP

Filtrated Water Tank

Sea
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

25

1F Unit 3 Schematic System Diagram (After Tsunami)


Stack

D/W vent valve RPV

SRV

Tb
Condenser H/W

Gen
W

Sea :Operable :Inoperative due to power loss :Inoperative

SLC
MDMDRFP S/C vent valve TDTDRFP LPCP

CRD

HPCP

HPCI
from CST H/W CST CST

CS RHRS Sea

RHR

RCIC

D/G

MUWC DD FP

Filtrated Water Tank

Sea
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

26

2. How we responded ?
- How the accident developed - What difficulties existed - What were effectively utilized

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

27

Status of 1F 1-3 immediately after the Tsunami


Fallen into the Station Black Out (SBO):
All safety and non-safety systems driven by electricity were unavailable. No lights in the control rooms, R/Bs, T/Bs, etc. No important instrumentations for Unit 1 &2 due to loss of AC power sources and DC 125V batteries; the reactor water level/ pressure, drywell pressure, wet-well (S/C) pressure, etc. ; Operators were totally blind!
The instrumentation of Unit 3 was available immediately after the tsunami but only lasted for about 30hours.

Almost no communication tools between the Emergency Response Room and workers at the field: only hotline and land-line phone were available between the ERR and each control room.

The sea water systems were totally destroyed: no ultimate heat sink
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

28

Progress made by each plant towards cold shutdown (outline)


1F Units 1 - 4
Units 1-3 in operation Unit 4: outage in progress
[Power supply] Total loss of off-site power supply and DG [Sea water system] Total loss

1F Units 5 & 6
Outage in progress

2F Units 1 - 4
In operation
[Power supply] One off-site power supply system secured [Sea water system] Total loss apart from Unit 3

[Power supply] Emergency DG 6B start up [Sea water system] Total loss

Water injection using RCIC


Water injection using IC, RCIC, HPCI

Water makeup by MUWC (DG6B power used for Units 5, 6)


Installation of temporary RHRS Installation of temporary power supply 3/19 Alternative RHRS was started and the spent fuel pool and reactor were cooled

PCV Venting, SRV operation & Sea water injection Switch to freshwater
Heat removal route has been continuously improved Currently the closed cycle cooling is in function
Sea water was initially injected into the spent fuel pool; currently injecting freshwater

3/12 Unit 3 cold shutdown

Units 1, 2, 4 Water injection using MUWC


RHRC motor was replaced Installation of temporary power supply

3/14

RHR startup

3/20 Units 5, 6 cold shutdown

3/14 Units 1, 2 cold shutdown 3/15 Unit 4 cold shutdown 29

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Chronology of Accident (Fukushima Daiichi)


SF Pool Unit 1 Unit 2 Unit 3 Unit 4 Reactor
Power Supply

Unit 5-6
One D/G survived

Common SF Pool

March 11, 14:46

Earthquake
Cooling by injecting fresh water

12th 13th 14th 15th 17th 20th 21th 22th 23th 24th 25th 26th 27th 31st

Start injecting
Rx Building Explosion

sea water
Start injecting
Suppression Chamber Depressurization

Start injecting sea water


Rx Building Explosion Rx Building Explosion

sea water Start watering (sea water, fresh water)

Start injecting sea water

Start watering (sea water, fresh water)

Reactor cooling shutdown Switched from D/G to offsite power Fresh water injection

Recover Main Control Room lighting

Recover Main Control Room lighting


Recover Main Control Room lighting Switch from sea water to fresh water

Received electricity from offsite Start cooling by existing system


Recover Main Control Room lighting

Switch from sea water to fresh water

Switch from seawater to fresh water Switch from seawater to fresh water

Start watering fresh water

Switch from sea water to fresh water

Switch from sea water to fresh water

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

1F Unit 1 Plant Parameter and Operation


Earthquake Tunami 15:27 14:46
Core Damage Started due to MAAP Analysis

Unit 1 R/B Explosion 15:36


Fuel Range (A) (mm) Fuel )(Bmm Range (B) (mm)
)(Amm

Rx Water Level [mm]

500 0 300 0 100 0

In Ope ration(Ove r Scale )

Rx water level data revealed incorrect afterward


3/11 18:00 3/1 2 0 :0 0 3 /12 6:00 3/12 12:00

0(TAF)
-100 03 /11 -300 0 12:00 3/1 2 1 8:00 3 /13 0:00

Rx Pressure [MPa]

1 0.00 8.00 6.00 4.00 2.00 0.00

8.7 MPa abs 7 .2 8,7 .3 5 ,7 .4 1 MPa abs 7.0 MPa abs

Rx Pressure (A) (MPa) Rx Pressure (B) (MPa)

3/ 11 12:00

3/11 18:00

3/12 0:00

3/1 2 6:0 0

3/12 12:00

3 /12 18:00

3/1 3 0:0 0

D/W & S/C Pressure [MPa]

1.000 0. 954MPa abs 0.800 0.600 0. 53MPa abs 0.400 0.200 0.000 3/11 12:00

S/C Pressure (A) (MPa) D/W Pressure (B) (MPa)

3/11 18:00

3/12 0:00

3/12 6:00

3/12 12:00

3/12 18:00

3/13 0:00

IC HPCI SRV
FP/Fire Engine

14:52 No Operation No Operation

18:18 - 25 21:30 Operation Unclear

4:00 Fresh Water Order for Vent Preparation 0:06

80t

14:53 19:04Sea Water 14:30 D/W Pr decrease confirmed

PCV Vent

Order for Vent 8:03

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

31

1F Unit 2 Plant Parameter and Operation


Earthquake 14:46 Tunami 15:27 Unit1 R/B Explosion 15:36 Unit3 R/B Explosion 11:01
Core Damage Started due to MAAP Analysis

Impact sound 6:00-6:10

Rx Water Level [mm]

6000 4000 2000


In Operation (Over Scale)

Fuel Range (A) (mm) Fuel Range (B) (mm)

0(TAF) 0
-2000 3/11 12:00 -4000 3/11 18:00 3/12 0:00 3/12 6:00 3/12 12:00 3/12 18:00 3/13 0:00 3/13 6:00 3/13 12:00 3/13 18:00 3/14 0:00 3/14 6:00 3/14 12:00 3/14 18:00 3/15 0:00 3/15 6:00 3/15 12:00 3/15 18:00 3/16 0:00

Rx Pressure [MPa]

10.00 8.00 6.00 4.00 2.00 0.00

8 .7 M Pa abs 7 .4 4 ,7 .5 1 ,7 .5 8 M Pa abs 7 .0 M Pa abs

Rx Pressure (A) (MPa) Rx Pressure (B) (MPa)

3/11 12:00
1.000 0.800 0.600 0.400 0.200 0.000 3/11 12:00

3/11 18:00

3/12 0:00

3/12 6:00

3/12 12:00

3/12 18:00

3/13 0:00

3/13 6:00

3/13 12:00

3/13 18:00

3/14 0:00

3/14 6:00

3/14 12:00

3/14 18:00

3/15 0:00

3/15 6:00

3/15 12:00

3/15 18:00

3/16 0:00

D/W & S/C Pressure [MPa]

0 .9 5 4 MPa abs

S/C Pressure (MPa) D/W Pressure (MPa)

0 5 . 3 MPa abs

3/11 18:00

3/12 0:00

3/12 6:00
(2:55)

3/12 12:00

3/12 18:00

3/13 0:00

3/13 6:00

3/13 12:00

3/13 18:00

3/14 0:00

3/14 6:00

3/14 12:00

3/14 18:00

3/15 0:00

3/15 6:00

3/15 12:00

3/15 18:00

3/16 0:00

RCIC HPCI SRV FP/Fire Engine PCV Vent

Operation confirmed

(13:25)Out of Service Judged

No Operation

Depressurization
~18:00

Valve Condition Unclear


2Valves Open

Order for Sea Water Injection 19:Sea Water Preparation 12:05 (11:00 Vent Line Small Vent Valves Opened Configuration Completed Order for Vent Preparation 17:30 All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

32

1F Unit 3 Plant Parameter and Operation


Earthquake Tunami 14:46 15:27

Rx Water Level [mm]

6000 4000 2000

Unit1 R/B Explosion 15:36

Core Damage Started due to MAAP Analysis

Unit3 R/B Explosion 11:01

I n O pe ra tion (O ve r Sc ale )


3/14 18:00 3/15 0:00

Fuel Range (A) (mm) Fuel Range (B) (mm) Fuel Range (mm) Wide Range (mm)
3/15 6:00 3/15 12:00 3/15 18:00 3/16 0:00

0(TAF) 0
-2000 3/11 12:00 -4000
10.00 8.00 6.00 4.00 2.00 0.00

3/11 18:00

3/12 0:00

3/12 6:00

3/12 12:00

3/12 18:00

3/13 0:00

3/13 6:00

3/13 12:00

3/13 18:00

3/14 0:00

3/14 6:00

3/14 12:00

Rx Pressure [MPa]

8 .7 MPa 7 .4 4 MPa,7 .5 1 MPa,7 .5 8 MPa 7 .0 MPa

Rx Pressure (A) (MPa) Rx Pressure (B) (MPa)

3/11 12:00

3/11 18:00

3/12 0:00

3/12 6:00

3/12 12:00

3/12 18:00

3/13 0:00

3/13 6:00

3/13 12:00

3/13 18:00

3/14 0:00

3/14 6:00

3/14 12:00

3/14 18:00

3/15 0:00

3/15 6:00

3/15 12:00

3/15 18:00

3/16 0:00

D/W & S/C Pressure [MPa]

1.000 0.800 0.600 0.400 0.200 0.000

0 .9 5 4 MPa

S/C Pressure (MPa) D/W Pressure (MPa)

0 .5 3 MPa

3/11 12:00

3/11 18:00
(16:03)

3/12 0:00

3/12 6:00

3/12 12:00

3/12 18:00

3/13 0:00

3/13 6:00

3/13 12:00

3/13 18:00

3/14 0:00

3/14 6:00

3/14 12:00

3/14 18:00

3/15 0:00

3/15 6:00

3/15 12:00

3/15 18:00

3/16 0:00

RCIC HPCI SRV


D/D-FP FP/Fire Engine

(11:36) Trip

Automatic Start
(12:35)

(2:42) Stop

~9:08Depressurization Order for Preparation 17:12

After HPCI shut down, water injection using D/D FP was implemented, however not possible due to high reactor pressure

(22:15) Stop due to running out of fuel

PCV Vent

Fresh Water 9:2513:12Sea Water 16:30Sea Water Order for Vent Preparation 17:30 (8:41 Vent Line Configuration Completed All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

33

(Ref.) Fukushima Daini Unit 1 Plant Parameter and Operation


Earthquake Tunami 14:46 15:23 Cold Shut Down14:46 Overscale

Rx Water Level [mm]

7000 5000 3000 1000 -1000 3/11 12:00

0(TAF)
10.00 8.00 6.00 4.00 2.00 0.00

3/11 18:00

3/12 0:00

3/12 6:00

3/12 12:00

3/12 18:00

3/13 0:00

3/13 6:00

3/13 12:00

3/13 18:00

3/14 0:00

3/14 6:00

3/14 12:00

3/14 18:00

3/15 0:00

3/15 6:00

3/15 12:00

3/15 18:00

3/16 0:00

D/W & S/C Rx Pressure Pressure [MPa] [MPa]

8 .7 M Pa abs 7 .4 7 ,7.5 4 ,7 .6 1 MPa abs 7 .0 MPa abs

3/11 12:00

3/11 18:00

3/12 0:00

3/12 6:00

3/12 12:00

3/12 18:00

3/13 0:00

3/13 6:00

3/13 12:00

3/13 18:00

3/14 0:00

3/14 6:00

3/14 12:00

3/14 18:00

3/15 0:00

3/15 6:00

3/15 12:00

3/15 18:00

3/16 0:00

1.000 0.800 0.600 0.400 0.200 0.000

0 .7 2 3 MPa abs

S/C Pressure (MPa) D/W Pressure (MPa)

0 .3 8 MPa abs

3/11 12:00

3/11 18:00

3/12 0:00

3/12 6:00

3/12 12:00

3/12 18:00

3/13 0:00

3/13 6:00

3/13 12:00

3/13 18:00

3/14 0:00

3/14 6:00

3/14 12:00

3/14 18:00

3/15 0:00

3/15 6:00

3/15 12:00

3/15 18:00

3/16 0:00

RCIC HPCS SRV MUWC RHR PCV Vent No Operation(


Inoperative due to submersion of power source and inoperative auxiliary cooling system)

Pressure Control 3:50 ~ Depressurization 0:00 ~ Restoration of RHR system


(18:30 Vent Line Configuration Completed

3:45 ~

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

34

Major Activities at 1F Factors disturbing the recovery work (inside the building)
Due to lack of power sources, initial recovery activities had to be conducted in complete darkness, without any instrumentation, and without most communications means.

Scram response

Deteriorated operability due to the tsunami Preparations for water injection Preparations for venting Water injection started Venting

Work in complete darkness. Many scattered objects were also on the floor.

Connected temporary batteries to recover instrumentations.

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

35

Major Activities at 1F Factors disturbing the recovery work (inside the buildings)
Instruments were monitored wearing a full face mask with a flashlight in complete darkness Checking indicated values only with a flashlight in complete darkness

Scram response

Deteriorated operability due to the tsunami Preparations for water injection Preparations for venting Water injection started Venting
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Supervising at a deputy supervisors desk wearing a full face mask in complete darkness
36

Major Activities at 1F Factors disturbing initial recovery of instrumentations and power supply
Used batteries taken from cars for recovery of important instrumentations. Put Engine-Generators to provide power for the control room lightings and PCV vent valve actuation.
Deteriorated operability due to the tsunami Preparations for water injection Preparations for venting Water injection started Venting
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Scram response

Tried to connect a mobile power truck to P/C 2C with temporary cable. The hydrogen explosion of Unit 1 caused damage of the temporary cable. Hurdles for the work: Darkness and suspensions due to aftershocks, tsunami alarms, Puddles, openings of manholes, debris and other obstacles caused by the tsunami, Influence of the hydrogen explosions

Image of mobile power truck

37

Major Activities at 1F Factors disturbing alternative water injection into the reactors
Scram response

1. Tried to inject fresh water using the diesel driven fire protection pump (DDFP): failed.
Unit 1: mechanical problem of the DDFP Unit 2: the DDFP was flooded Unit 3: the RPV pressure was too high

Deteriorated operability due to the tsunami Preparations for water injection Preparations for venting Water injection started Venting

2. Injection of fresh water from underground water tank (16units/site40m3/unit) using the fire engine pumps : succeeded but did not last for long time 3. Injection of sea water using the fire engine pumps. Hurdles for the work:
Interruptions due to aftershocks and tsunami alarms Damages of the fresh water lines due to the earthquake Debris and damages of the gates caused by the tsunami R/B explosions (debris, damage of fire engines and other devices, injury of field workers and fear of another explosion) No lights. Problem with the PHS telephone and radio communication
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

38

Major Activities at 1F Factors disturbing the recovery work (outside the buildings)
Many obstacles on access routes disturbed access to the field.
Scram response

Vehicles had to avoid passing over fire protection hoses laid in the field. Almost no communication tools between the ERC and workers at the field were available.

Deteriorated operability due to the tsunami Preparations for water injection Preparations for venting Water injection started Venting
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

39

Major Activities at 1F Factors disturbing the Primary Containment Vessel Venting Operation
Scram response

No power source for the MO-valve No power source to the solenoid valve Low IA pressure to actuate the AO-valve High radiation level in R/B

Manual operation Engine driven generator Engine driven air compressor

Deteriorated operability due to the tsunami Preparations for water injection Preparations for venting
IA

MO MO 210

Ruptured Broke at disc 0.549MPabs 0.549MPabs

Exhaust stack

Shift workers operation to AO AO Closed 83 manually open valve

D/W maximum operating pressure: D/W 0.528MPaabs 0.528MPabs Venting pressure: 0.954MPabs 0.954MPaabs
Cylinder
RPV

Solenoid valve

AO 1
AO AO 90 Closed

AO

Closed

Water injection started


Cylinder

D/W

IA
AO MO 213

Venting

AO Closed 72 Solenoid valveReserved 2012The Tokyo Electric Power Company, Inc. All Rights

AO

Self-contained breathing apparatus 40

3.Other Relevant Items

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

41

How the Pre-planed Accident Management Worked


(The Tsunami was beyond AM )
Facilities Shutdown Injecting water Outline
Recirculation Pump Trip Alternative Rod Insertion Alternative Injection by MUWC /FP Automatic ADS

Practical use at 1F-13


:CRs are fully inserted :Injected from AM coupler :Using Fire engineMUWC & FP are downed as loss of AC power etc. :Manual operated as loss of power :Inoperable as loss of AC power

at 2F-1

.Containment Alternative Cooling by Drywell Cooler Cooling


Restoration of CCS Hardened Vent

: Manual operated : Inoperable as loss of power including the next(1~4) plant (But operable 1F5,6 BUS tie) : Cooling and Electric supply facilities are Inoperable
apply

(prepared line up)

Support of Safety Facilities

Interchangeability of 6.9kV & 480V Power Sources Restoration Procedure Guidelines (RHR & D/G)

no relation couldn't apply partially apply


All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

42

Presumption of Reactor Core State by Analysis Code (MAAP ) etc. Unit 1


Almost no fuel was left at the original position, and fuel completely moved downward after it damaged. The moved fuel likely damaged RPV and is assumed that most of it had dropped to the bottom of PCV. Dropped fuel is assumed to have caused core concrete reaction. As of Nov.21, water injection is conducted through the feed water system and the temperature at bottom as well as inside the PCV remain stable below 100. Therefore, it is evaluated that all the moved fuel is expected to be cooled directly by water injection. It is also evaluated that the core concrete reaction has been stopped. Erosion depth by core concrete reaction: 0.65m
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

43

Presumption of Reactor Core State by Analysis Code (MAAP ) etc. Unit 2 & 3
Even though the fuel was damaged, it is assumed that there has been no large damage of the RPV that would make a large amount of fuel dropped to the bottom of PCV. There is a range in the evaluation result from part of damaged fuel dropped to the bottom of PCV to Almost all the fuel is left inside RPV. If the part of damaged fuel were to have dropped to the bottom of PCV, it can be assumed that core concrete reaction was caused. Currently, water injection is conducted through the feed water system and CS system. The temperature in the PCV remain stable below 100. Therefore, it is evaluated that all the moved fuel is expected to be cooled directly by water injection. It is also Erosion depth by core concrete reaction: Unit 2: 0.12m evaluated that the core concrete reaction has been stopped. Unit 3: 0.20m
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

44

Hydrogen Explosions at Units 1 and 3 R/B


Hydrogen is supposed to have leaked through heat affected seals on the D/W flange, hatch and electric penetrations.
Reactor building
5th floor

D/W flange

4th floor 3rd floo r

Move to upper floor by stairs or through hatches


2nd floor

RPV

Hatch Electric penetration


1st floor

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

45

Hydrogen Explosion at Units 4 R/B


Hydrogen generated in the Unit 3 reactor back-flowed into Unit 4 through SGTS line.
Unit 4 reactor building

5th floor south5 side exhaust duct

Exhaust stack

4th level west-side 4 exhaust duct

5F

4F

4th 4 level east-side exhaust duct

Venting gas flow


3 -----4 GL

3F

Back-flow gas
SGTS A O A O AO

SGTS
A O

AO

AO

Unit 3 Unit 4

AO

AO

AO

2F

SGTS
SGTS

1F

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

46

Measurement Result of Unit 4 SGTS Radiation Dose

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

47

Number of Stored Fuel Assemblies and Decay Heat in Spent Fuel Pool (SFP)
LOPA caused loss of cooling Largest Heat load in Unit 4, but Rx well and DS pit was full Water injected by helicopter, fire engines, and then concrete pumps No fuel was uncovered in any pools Now all pools are cooled by heat exchangers
Water level (top of fuel rack =0m)

Unit 4 Spent Fuel Pool Evaluation

Stored fuel assemblies Irradiated fuel Unit 1 SFP Unit 2 SFP Unit 3 SFP Unit 4 SFP Unit 5 SFP Unit 6 SFP Common SFP 292 587 514 1331 946 876 6375 Fresh fuel 100 28 52 204 48 64 0

Decay heat (MW) As of March 11 0.18 0.62 0.54 2.26 1.01 0.87 1.13 As of June 11 0.16 0.52 0.46 1.58 0.76 0.73 1.12 48

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Conditions of SFPs
Unit 3 SFP (Water surface and underwater) Unit 4 SFP (Water surface and underwater)

As many debris have fallen into the SFP, the status of the fuel racks and fuels can not be confirmed.

Although some debris have fallen into the SFP, it can be confirmed that the status of the fuel racks and fuels are normal. 49

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

. Current Status and Roadmap towards Decommissioning

Inside wall Grating

Inside of 1F unit 2 PCV


All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

50

Accumulated Water Processing Facilities


Filtrate Tk
Conc. Waste liq. Storage Tk Evaporative Concentration

Apparatus

Conc. Saltwater Receiving


Tk Freshwater Receiving Tk

Desalination Plant

Reactor Bldg.

Buffer Tk
#1:91.2m3/d,FDW #2:187.2m3/d,FDW/CS #3:288m3/d,FDW /CS

Wastewater

Supply Tk
High Temp. Incinerator Bldg.

PCV RPV

Turbine Bldg.

SPT(B) Process Main Bldg.

Condenser

Cesium Adsorption Facility

Cumulative treated volume: approx.246,810m3


(As of Feb.21, 2012)

Sludge Vessels

Accumulated Water in Turbine Building


All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

51

Temperature inside PCV got low and stable

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

52

Monitoring Data (at Site Boundary of Fukushima Daiichi)


Monitoring data at the site boundary of Fukushima Daiichi shows continuous decrease at each monitoring post. Air dose rate measured at onsite monitoring posts :Sv/h as of 0:00 onJan. 16th , 2012 Dose Rate Trend at the Site Boundary of Fukushima Daiichi 4 19

12 11 14 11 West 32
Unit6 Unit5

284

Unit1 Unit2 Gate Unit3 Unit4 27 Main Gate

88 67

Monitoring Post(MP-1~8) Temporary Monitoring Post

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

53

Release Rate of Radioactive Cs from unit 1-3 Decreased Dramatically


Release rate (Bq/hour)
Approx. 800 trillion Bq/hour 1015
(approx. 8.0 1014 Bq/hour) *1
*1: Total release rate (Bq/hour) of Cs-134 and Cs-137 was calculated based on release rate (Bq/hour) of Cs-137 as of Mar 15 mentioned on the report of the 63rd Nuclear Safety Commi ssion of Japan. Total release rates (Bq/hour) of Cs-134 and Cs-137 as of Mar.25 and Apr.5 were calculated by the same way. *2: Total release rate (Bq/hour) of Cs-134 and Cs-137 was calculated based on average concentration of Cs-137 in the air measured near the west boundary of the site from June 20 to June 28. Total release rate (Bq/hour) of Cs-134 and Cs-137 was calculated based on average concentration of Cs-137 in the air measured near the west boundary of the site from July 26 to August 12. *3: Total release rate (Bq/hour) of Cs-134 and Cs-137 was estimated utilizing the results of dust concentration measurement at the upper parts of the reactor buildings and the sea. *4: Total release rate (Bq/hour) of Cs-134 and Cs-137 was estimated utilizing the results of dust concentration measurement at the upper parts of the reactor buildings (incl uding Unit 1 reactor building cover and Unit 2 PCV gas control system exit) and the sea.

1013

Approx. 2.5 trillion Bq/hour


(approx. 2.51012Bq/hour)*1

Approx. 0.29 trillion Bq/hour


(approx. 2.91011 Bq/hour)*1

Approx. 1 billion Bq/hour 1011


(approx. 1.0109Bq/hour)*2 (approx. 2108Bq/hour)*2

Approx. 1/13,000,000 of the release rate immediately after the accident

Approx. 0.2 billion Bq/hour Approx. 0.2 billion Bq/hour


(approx. 2108Bq/hour)*3

109

3/15

3/25 -3/26

4/4 -4/6

6/20 -6/28

7/26 -8/12

9/1 10/3 11/1 11/26 -9/17 -10/13 -11/10 -12/6

Evaluated period

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

54

Mid-and long term Roadmap towards the Decommissioning(1/2)


Dec. 16th 2011(Step 2 Completed) Step 1,2
<Achieved Stable Conditions> -Condition equivalent to cold shutdown

Within 2 years Phase 1

Period to the commencement of the fuel removal from the Spent Fuel Pools (Within 2 years) -Commence the removal of fuels from the spent fuel pools (Unit 4 in 2 years)

-Reduce the radiation impact due to additional emissions -Significant Suppression of from the whole site and radioactive waste generated after the accident (secondary waste materials via water processing Emissions and debris etc.) Thus maintain an effective radiation dose of less than 1 mSv/yr at the site boundaries caused by the aforementioned. -Maintain stable reactor cooling and accumulated water processing and improve their credibility. -Commence R&D and decontamination towards the removal of fuel debris -Commence R&D of radioactive waste processing and disposal Actions towards systematic staff training and allocation, improving motivation, and securing worker safety will be continuously implemented.
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

55

Mid-and long term Roadmap towards the Decommissioning(2/2)


Within 2 years Phase 2
Period to the commencement of the removal of fuel debris (Within 10 years) -Complete the fuel removal from the spent fuel pools at all Units -Complete preparations for the removal of fuel debris such as decontaminating the insides of the buildings, restoring the PCVs and filling the PCVs with water. Then commence the removal of fuel debris (Target: within 10 years) -Continue stable reactor cooling -Complete the processing of accumulated water -Continue R&D on radioactive waste processing and disposal, and commence R&D on the reactor facilities decommission Actions towards systematic staff training and allocation, improving motivation, and securing worker safety will be continuously implemented.
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Within 10 years

Within 30-40 years Phase 3

Period to the end of the decommissioning (In 30-40 years)

-Complete the fuel debris removal


(in 20-25 years) -Complete the decommission (in 3040 years) -Implement radioactive waste

56

5.Lessons Learned and Countermeasures

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

57

Lessons Learned and Countermeasures


Thorough equipment protection measures against tsunami to prevent power loss and loss of the heat removal function are important. Preventing the flooding of buildings
Embankment Flood Barriers & Walls

Preventing the flooding of important equipment


Water tight doors in R/B etc.
Embankment

Watertight Doors

Flood Barrier Wall


All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

58

Lessons Learned and Countermeasures


Regardless of the initial cause of the accident, flexible alternative measures with improved applications and mobility to prevent core damage against long simultaneous loss of AC and DC power and long loss of heat removal function are important.
Enhancing high-pressure & low-pressure cooling water injection Manual startup of steam-driven cooling water injection equipment Preparation of mobile power trucks and backup water source Establishment of water injection means using fire engines Enhancing reactor depressurization Preparation of spare batteries and gas cylinders Enhancing heat removal and cooling Mobile power trucks Backup AC power Preparation of spare replacement motor for emergency sea water systems Preparation of a portable mobile heat exchanger (pump, heat exchanger set) Securing power for monitoring instruments
To RHR To SFP Sea All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Heat exchanger truck 59

Lessons Learned and Countermeasures


From the perspective of defense-in-depth, it is important to take further measures in case core damage does occur.
Top vent

Preventing hydrogen accumulation in R/B


Opening holes on the roof of R/B (top vent) etc.

Suppressing the release of radioactive materials


Preparation for water injection to the PCV through fire engines, etc Backup AC power and modification of design to facilitate PCV venting

It is important to prepare further equipment and auxiliary facilities for support of on-site response.
Debris removal equipment Communication methods Lighting equipment Protective equipment (protective wears, masks, APDs etc.)

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

60

Lessons Learned and Countermeasures


Without newly built Emergency Response Center, the post-accident activities could not have been carried out.

Seismically Isolated ERC

Laminated rubber bearing

Sliding bearing

Measures taken after Niigata Chuetsu Oki Earthquake were effective: Emergency response center in robust building (Seismic isolation, Shielding, Communication, etc.) Underground water tank and Fire Engines (3/site)

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

61

Embankment (Kashiwazaki-Kariwa NPS)


Gate
Access road

Gate Access road Access road

T.P.+15.0m line

T.P.+15.0 lene

T.P.+15.0

Unit 11-4
T.P.+15.0

Unit 55-7

T.P.+15.0 3.0 T.P.+12.0

10.0 T.P.+5.0

: Reinforced concrete wall (image)

:Clay embankment image


62

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

Flooding barriers
R/B Louver

Louver Door

Ventilation hole

Flood barrier plate (balcony type) Flood barrier plate (closing type) Flood barrier wall

R/B

Flood barrier plate Watertight door


All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

63

Watertight doors

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

64

Penetrations sealed with silicon rubber

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

65

Backup AC Power (Air Cooling GTG & Mobile Power Truck )


Mobile power trucks Air cooling GTG

66kV BUS
Construction Power Tr

Emergency M/C

M/C 1C

500KVA Mobile power trucks

Air cooling GTG


4500KVA
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

66

Enhancing Reactor Depressurization


Manual switching by low pressure

2nd floor of R/B


System B
SRVs with ADS function

System A

Manual switching by low pressure

Stand-by

Regular use

Stand-by

Regular use

System B cylinders

System A cylinders

N2 supply

N2 supply

Spare cylinders

Temporary switch Temporary Spare Battery


SRV
NO

Temporary Battery

Accumulator

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

67

Low Pressure Injection by Fire Engine


R/B
MCC1C-1-2 MCC1C-1-3 O O O

Run out

Filtrated Water Tank

MCC1C-1-5 O

Inoperative

FPFP-MUWC Tie Line

RHR

Coupling for fire fighting

GTG
Emergency M/C
M/C1C P/C1C-1 MCC1C-1-2

Mobile Power Truck

Fire Engine

MCC1C-1-3

MCC1C-1-5

Sea water
All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

68

Water Reservoir

Fresh water tank T.P.+13.0m

Water pipe

Water reservoir T.P+45.0m 18,000m3

Well

Fresh water tank T.P.+12.0m

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

69

Alternative Heat Removal


Temporary Submerged Pump
Mobile Power Truck Tr Truck 500kVA6600V 6600V400V
To Submerged pump
75kW 75kW

Alternative Heat Exchanger Vehicle Temporary Submerged Pump

P Sea water Tr Hx

Alternative Heat Exchanger vehicle

Prepared connector

T/B

T/B
Temporary Submerged Pump

R/B
RHR Hx FPC Hx
Trench

MO

RHRIW Hx (A)

Sea water intake channel


All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

70

PCV Venting (Ensuring Actuation)


R/B
SGTS(A)

Vital UPS

PCV

Spare IA
AO

MCC1C-1-1

R/B BF1

Exhauster

Operation at Main Control Room

SGTS(B )

SGTS

Manual operation

MO

RPV

Rupture Disk

Stack
GTG Emergency M/C M/C1C

Vital UPS

D/W IA S/C
AO

Mobile power trucks

Spare
R/B BF4

P/C1C-1
MCC1C-1-1 MCC1C-1-4

Vital UPS

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

71

PCV Venting (Manual Operation at Field)


R/B
SGTS(B) SGTS(A) SGTS Exhauster

Manual Operation

PCV
AO

R/B BF1

Rupture Disk

RPV

Stack Manual operation possible

D/W S/C vent prior use


AO

S/C
R/B BF4

Open

AO-valves modified so that manual operation is possible with a ratchet wrench

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

72

R/B top vent

R/B Wire Lever block

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

73

Provision of Heavy Machinery


Crawler hydraulic shovel Crawler hydraulic shovel

Wheel hydraulic shovel

Wheel loader Wheel loader Wheel loader

Wheel loader

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

74

Image of Light Oil Storage Facility

GTG

GTG

Mobile power truck Other cars and MiniMini-tanker (900 ) heavy machinery

Fixed oil feed pump

Feed throat

Filler throat

Feed throat

Filler throat

Feed throat

Filler throat

Tank 1

Tank 2

Tank 3

Underground oil storage facility Underground light oil tank (50K:2.4mX11.7m)X3

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

75

Portable PHS Antenna (Image)

Cable drum 100m

Web camera (for future)

Storage rack Door 300mm 650mm 520mm

IP PHS antenna
IP phone

Junction box

To ERC
Switch
Fiber cable drum

Portable Generator

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

76

Added Monitoring Cars

Portable Monitoring Post

Ionisation chamber type survey meter

Dust Sampler

vane anemometer

Portable generator

Satellite cell-phone
77

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

In Closing
Achieved Stable Conditions Condition equivalent to cold shutdown Significant suppression of radioactivity emissions Commenced the phase 1of Mid-and-long-Term Roadmap towards the Decommissioning of Fukushima Daiichi Nuclear Power Units 1-4 Phase 1: Period to the commencement of the fuel removal from the Spent Fuel Pools (Within 2 years) Implementing measures to enhance safety of Kashiwazaki Kariwa NPS. Deployed mobile power trucks, additional fire engines, spare pumps and motors, etc.

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

78

Thank you for your attention!

All Rights Reserved 2012The Tokyo Electric Power Company, Inc.

79

You might also like