DISEO DE UN CANAL CIRCULAR

ALUMNO: RAMOS QUISPE RONALD


DOCENTE: ING. IVAN A. AYALA BIZARRO
ECUACION DE DARCY WEYBASH

Hf f

ECUACION DE NUMERO DE REYNOL

L V2

D 2g

Re D

Ecuacin de Haaland

ECUACION DE VISCOCIDAD

k/D
1
2,51
2 log

3
,
7
f
Re
f
D

DATOS
Q=
L=
g=
T=
Ks =
=
S=
H=

4Q
Do

k/D
2,51
V 2 2 g D J log

D 2 g D J
3,7

10l/s
1Km
9.806 m2/s
10
0.00000152
1.401E-06
0.1
100

Parmetros generales
ITER

1
2
3
4
5

Dimetro
interior
m
0.030
0.098
0.089
0.090
0.090

Caudal

Caudal

l/s
10
10
10
10
10

m3/s
0.010
0.010
0.010
0.010
0.010

Viscosidad

Area

kg / (ms) m2
1.40E-06 7.07E-04
1.40E-06 7.55E-03
1.40E-06 6.27E-03
1.40E-06 6.34E-03
1.40E-06 6.32E-03

Velocidad
m/s
14.1471
1.3253
1.5939
1.5776
1.5827

Colebrook
Nmero de Rugosidad longitud
Reynolds
m
m
302935.89 1.52E-06
1000
92721.86
1.52E-06
1000
101683.75 1.52E-06
1000
101161.83 1.52E-06
1000
101323.64 1.52E-06
1000

Hf

0.00007
0.02751
0.01744
0.01800
0.01795

Pa/m
25.000
25.139
25.279
25.420
25.561

RESULTADOS
D(m)
0.09801
0.08938
0.08984
0.08969
0.08959

error
PRESION
6.80E-02
75.000
-8.64E-03
74.861
4.61E-04
74.721
-1.43E-04
74.580
-1.01E-04
74.439

6
7
8
9
10
11
12
13
14
15
16
17
18
19
20

0.090
0.089
0.089
0.089
0.089
0.089
0.089
0.089
0.089
0.089
0.089
0.088
0.088
0.088
0.088

10
10
10
10
10
10
10
10
10
10
10
10
10
10
10

0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010
0.010

1.40E-06
1.40E-06
1.40E-06
1.40E-06
1.40E-06
1.40E-06
1.40E-06
1.40E-06
1.40E-06
1.40E-06
1.40E-06
1.40E-06
1.40E-06
1.40E-06
1.40E-06

6.30E-03
6.29E-03
6.28E-03
6.26E-03
6.25E-03
6.23E-03
6.22E-03
6.20E-03
6.19E-03
6.17E-03
6.16E-03
6.15E-03
6.13E-03
6.12E-03
6.10E-03

1.5862
1.5899
1.5936
1.5973
1.6010
1.6047
1.6085
1.6122
1.6159
1.6197
1.6234
1.6272
1.6310
1.6348
1.6385

101438.01
101555.83
101673.56
101791.44
101909.46
102027.61
102145.90
102264.32
102382.88
102501.58
102620.42
102739.39
102858.50
102977.75
103097.13

1.52E-06
1.52E-06
1.52E-06
1.52E-06
1.52E-06
1.52E-06
1.52E-06
1.52E-06
1.52E-06
1.52E-06
1.52E-06
1.52E-06
1.52E-06
1.52E-06
1.52E-06

1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000

0.01795
0.01795
0.01794
0.01794
0.01793
0.01793
0.01792
0.01792
0.01791
0.01791
0.01791
0.01790
0.01790
0.01789
0.01789

25.704
25.847
25.991
26.136
26.281
26.427
26.575
26.723
26.871
27.021
27.171
27.323
27.475
27.628
27.782

Diametro =
DIAMETRO COMERCIAL=
CALCULODE ALTURA Y ANCHO DE ZANJA
D=
0.088m
H=
0.788m
B=
0.588m
CALCULO DE REAS TRASVERSALES
AREA TUBERIA

0.0061

AREA TRASV. ARENA

0.0588

A. TRASV. MAT. SAR.

A. MAT. PROPIO

AREA TRASV. TOTAL

0.2221
0.1764
0.4634

0.08949
0.08938
0.08928
0.08918
0.08907
0.08897
0.08887
0.08877
0.08866
0.08856
0.08846
0.08836
0.08825
0.08815
0.08805

88.04855 mm
3.5069 pulg

-1.04E-04
-1.04E-04
-1.04E-04
-1.03E-04
-1.03E-04
-1.03E-04
-1.03E-04
-1.03E-04
-1.03E-04
-1.03E-04
-1.03E-04
-1.02E-04
-1.02E-04
-1.02E-04
-1.02E-04

74.296
74.153
74.009
73.864
73.719
73.573
73.425
73.277
73.129
72.979
72.829
72.677
72.525
72.372
72.218

SION

HOJA DE METRADOS
PRESUPUESTO:
CONSTRUCCION DE CANAL DE RIEGO
ESTUDIANTE:RAMOS QUISPE RONALD
DOCENTE:

ITEM

ING. IVAN A. AYALA BIZARRO

DESCRIPCION

01.00.00
01.01.00
01.01.01

LINEAS DE CONDUCCION
TRABAJOS PRELIMINARES
TRAZO, NIVELACION Y REPLANTEO DE ZANJAS/ML

01.02.00
01.02.01
01.02.02
01.02.03
01.00.04

MOVIMIENTO DE TIEERAS
EXCAVACION MANUAL DE ZANJA Y ELIMINACION MATERIAL EXCEDENTE
CAMA DE APOYO PARA TUBERIAS INC. CAMA DE ARENA
RELLENO Y COMPACTADO MANUAL CON MATERIAL SARANDEADO
RELLENO Y COMPACTADO MANUAL CON MATERIAL PROPIO

01.03.00
01.03.01

SUMINISTRO E INSTALACION DE TUBERIAS PVC


TUBERIAS PVC CLASE-10 D 2"

UND.

TOTAL

PREC. UNIT.

PREC.PARC.

PREC. TOT.
S/. 1,555.20

Km

1.00

S/. 1,555.20

S/. 1,555.20

m3

463.41

S/. 6.14

m3

58.80

S/. 12.14

m3

222.10

S/. 5.13

m3

176.41

S/. 4.12

S/. 2,845.34
S/. 713.89
S/. 1,139.39
S/. 727.00

ML

1,000.00

S/. 12.36

S/. 12,360.00

S/. 5,425.62

S/. 12,360.00

COSTO DIRECTO
GASTOS GENERALES 10%
UTILIDAD 10%
SUB TOTAL
IGV
PRESUPUESTO TOTAL

S/. 19,340.8238
S/. 1,934.0824
S/. 1,934.0824
S/. 23,208.9886
S/. 2,320.8989
S/. 25,529.88743

Ecuacin de Colebrook - White

Ecuacin de Haaland

Ecuacin de Swamee - Jain

Ecuacin de Hazen Williams

S: Prdida de carga (mca/m)

Ecuacin de Blasius

Ecuacin de Darcy

Wood Stave

Material
ABS - Acrylonite Butadiene Styrene
Aluminum
Asbestos Cement
Asphalt Lining
Brass
Brick sewer
Cast-Iron - new unlined (CIP)
Cast-Iron 10 years old
Cast-Iron 20 years old
Cast-Iron 30 years old
Cast-Iron 40 years old
Cast-Iron, asphalt coated
Cast-Iron, cement lined
Cast-Iron, bituminous lined
Cast-Iron, sea-coated
Cast-Iron, wrought plain
Cement lining
Concrete
Concrete lined, steel forms
Concrete lined, wooden forms
Concrete, old
Copper
Corrugated Metal
Ductile Iron Pipe (DIP)
Ductile Iron, cement lined
Fiber
Fiber Glass Pipe - FRP
Galvanized iron
Glass
Lead
Metal Pipes - Very to extremely smooth
Plastic
Polyethylene, PE, PEH
Polyvinyl chloride, PVC, CPVC
Smooth Pipes
Steel new unlined
Steel, corrugated
Steel, welded and seamless
Steel, interior riveted, no projecting rivets
Steel, projecting girth and horizontal rivets
Steel, vitrified, spiral-riveted
Steel, welded and seamless
Tin
Vitrified Clay
Wrought iron, plain
Wooden or Masonry Pipe - Smooth
Wood Stave

Hazen-Williams Coefficient
C
130
130 - 150
140
130 - 140
130 - 140
90 - 100
130
107 - 113
89 - 100
75 - 90
64-83
100
140
140
120
100
130 - 140
100 - 140
140
120
100 - 110
130 - 140
60
140
120
140
150
120
130
130 - 140
130 - 140
130 - 150
140
130
140
140 - 150
60
100
110
100
90 - 110
100
130
110
100
120
110 - 120

Rugosidades absolutas en micrmetros (Libro de Comentarios al RITE de 1998)

You might also like