Conduit Size/ No Wire Size/ Roll Boxes 13A Sockets other Value

Sl. Description Points 20mm 25mm 38mm 1.5mm2 2.5mm2 4mm2 6mm2 3x3 3x6 20ADP 45ADP 1,2,3Gang ISO 1 gang 2gang w/p
A 13A Socket 8 28 1 2
B Power point.W.M,W.D, 1 5 0 0 1 1
C W/H point 1 5 0 0 1 1
D A/C point(window) 1 5 0 0 1 1
E A/C C.Unit TPN 1 5 0 0 1 1
F A/C C.Unit SPN/chiller 0 0 0
G A/C F.C.U 1 5 0 0 1 1
H Cooker point 0 0 0
I Light points 53 146 5 9 53
J Chandelier piont 0 0 0
K Celining fan 0 0 0
L Exhaust fan/kitchen ho 6 17 1 1 6
M Door bell 0 0 0
N Pump connection 0 0 0
O CCTV/TV outlet 5 26 1 1950.000
P Data point 0
Q Telephone piont 1 5 1
R Intercom/music 0
S Light switches points 9 9 0 0 9
T Fire alarm system 0
U smp, D.B's, Meter,earthing&Cables 1300.000
V Labours 600.000
W Miscellaneous items, such as coupling, glue, 50mm ducts, pull wire etc. 1 200.000

Total Qty 231 26 0 6 13 3 0 75 0 4 0 1 1 0 0 0

Unit Price 0.250 0.390 0.700 5.800 8.900 14.080 21.120 0.150 0.250 1.350 1.900 40.000 0.900 0.650 1.150 5.000

Total Price 57.672 10.086 0.000 33.35 111.83 40.557 0.00 11.250 0.000 5.4 0.0 40.0 0.90 0.000 0.000 0.000 4050.00

l Material & Labour Cost for the project:-

B.D 4361.046
_________________. (Estimation)

Date: __.__.____
Conduit Size/ No Wire Size/ Roll Boxes 13A Sockets other Value

Sl. Description Points 20mm 25mm 38mm 1.5mm2 2.5mm2 4mm2 6mm2 3x3 3x6 20ADP 45ADP 1,2,3Gang ISO 1 gang 2gang w/p
1 13A Socket 137 472 15 30 137 137
2 Power point.W.M,W.D,etc 0 0 0
3 W/H point 25 129 4 8 25 25
4 A/C point(window) 1 5 0 0 1 1
5 A/C C.Unit TPN 56 290 9 27 56 56
6 A/C C.Unit SPN/chiller 0 0 0
7 A/C F.C.U 56 290 9 18 56 56
8 Cooker point 0 0 0
9 Light points 312 861 27 54 312 32
10 Chandelier piont 50 138 4 9 50
11 Celining fan 6 17 1 1 6
12 Exhaust fan/kitchen ho 32 88 3 6 32
13 Door bell 27 93 3 6 27
14 Pump connection 0 0 0
15 TV outlet 43 222 43
16 Data point 0
17 Telephone piont 39 202 39
18 Intercom/music 13 67 13
19 Light switches points 112 116 4 4 112
20 Fire alarm system 38 131 1662.000
21 smp, D.B's, Meter,earthing&Cables 7140.000
22 Labours
23 Miscellaneous items, such as coupling, glue, 50mm ducts, pull wire etc. 1

Total Qty 2899 222 0 60 136 46 0 909 0 25 57 1 56 169 0 0

Unit Price 0.250 0.390 0.700 5.800 8.900 14.080 21.120 0.150 0.250 1.350 1.900 380.000 0.900 0.650 1.150 5.000

Total Price 724.767 86.741 0.000 350.58 1207.40 647.374 0.00 136.350 0.000 33.8 108.3 380.0 50.40 109.850 0.000 0.000 8802.00

l Material & Labour Cost for the project:-

B.D 12637.518