Scope of Work Manifesto

www.FortuneBuilders.com

New Haven, CT

Page 2

Single family Old Style home, 1525 sq/ft with 5 bedrooms and 1 bath. House built in 1900 on .10 ac lot in a nice, quite working class neighborhood near Yale University and downtown.

West Haven, CT

Page 11

Single family Conventional style home, 1650 sq/ft, with 3 bedrooms, and 2.5 bathrooms. The house was built in 1938. Was subject to major fire damaged and was vacant for 2 years. In a nice, quiet, single family, residential, neighborhood plotted on a large lot of land. It was one of the first homes built in the area and still stands as the marquee property for its neighborhood.

El Cajon, CA

Page 19

Single family, Ranch Style home with over 2100 sq/ft, and 3 bedrooms and 2 bathrooms. House built in 1976 on .51 ac lot in an exclusive section called Fletcher Hills. The home has Panoramic canyon views.

San Diego, CA

Page 25

1435 square foot ranch style home built in 1955. The home has 3 bedrooms and 2 baths with a more contemporary feel and design. Located in the Rolando neighborhood of San Diego near SDSU.

San Diego, CA

Page 31

1657 square foot ranch style home build in 1957. The home has 3 bedrooms and 2 and half bathrooms with a more contemporary feel and design. The home is located in the Rolando Hills neighborhood of San Diego near San Diego State University.

El Cajon, CA

Page 38

Single family home, 1288 sq/ft with 3 bedrooms and 2 Baths. The home was built in 1952 on a .16ac lot. The house is in a quiet neighborhood of the Fletcher Hills section of El Cajon.

Scope of Work Manifesto

www.FortuneBuilders.com

Scope of Work: Single Family Home The Caddie Shack Episode of A&Es Flip This House New Haven, CT
Project Introduction and Overview
Description
Single family Old Style home, 1525 sq/ft with 5 bedrooms and 1bath. House built in 1900 on .10 ac lot in a nice, quite working class neighborhood near Yale University and downtown.

Rehab Overview

Property in need of extensive interior and exterior renovations. A new roof with skylights and new gutters along with new exterior paint and landscaping needed to be installed. The rear deck needed extensive repairs as well as the front steps. The kitchen was completely renovated with new cabinets, countertops, custom tile and appliances. The bathroom was completely redesigned with a Whirlpool tub, custom tile and fixtures. A new forced warm air furnace was installed as well as a new hot water heater.

Contractor Overview

Multiple contractors were needed to complete this project. A licensed general contractor was hired for the flooring, kitchen, bathroom, painting and all carpentry. A licensed plumber was hired for all new plumbing and hot water heater. A licensed electrician was hired for all electrical upgrades. A licensed roofing contractor was hired for the new roof.

EXTERIOR:
GENERAL: 1. Replace all exterior doors (prep and paint front door accent color) 2. Install brass kick plate, new hardware and house numbers to match 3. Repair glass storm door 4. Replace front porch light Lowes item #156440 5. Install new doorbell front and back doors 6. Replace all wood windows. Order from East Shore Glass 7. Paint entire foundation and steps (same as house color)

Scope of Work Manifesto

www.FortuneBuilders.com

EXTERIOR: (contd.)
GENERAL: (contd.) 8. Repair any wood damaged on front porch and paint 9. Repair all wood damage on existing rear porch and paint to match house 10. Repair all damaged clapboard exterior and paint (All exterior paint from Benjamin Moore) a. Body of house Wedgewood Gray HC-146 b. Trim White 01 c. Accents- Van Deusen Blue HC-156 11. Install new gutters around perimeter of roof ROOF: 1. Rip existing roof material 2. Re-plywood entire house (1/2 inch, 4ply plywood) 3. Install (2) skylights in middle room (will discuss location at property) a. Insula-Dome, Sunrise Select Vented, model #SVS2138CT 21x38 4. Install new roof metal on perimeter of house, ice/water barrier on all gutter line, walls, valleys and penetrations of roof 5. Install new 15lb tar paper 6. Install 30 year architectural style shingles with ridge vent (black) LANDSCAPING: 1. Remove all trash and debris from entire property 2. Remove chain link and install new white picket fence in front, no gate 3. Trim existing bushes in front, plant annuals and add wood chips 4. Cut down all weeds and grass in back yard, trim trees (will discuss at property) 5. Install new 6 fence along back of property

INTERIOR:
DEMO: 1. Remove all loose trash and debris from all floors 2. Remove portion of wall between kitchen and living room (see diagrams) 3. Remove portion of wall between entry and living room (see diagrams) 4. Remove portion of wall in stair well (see diagrams) 5. Remove all kitchen cabinets, appliances and flooring

Scope of Work Manifesto

www.FortuneBuilders.com

Interior: (contd.)
GENERAL: 1. Remove layers of wallpaper, patch and prep for paint 2. Sheetrock all walls were needed 3. Paint all rooms as per color scheme below Paint scheme: Navajo eggshell walls, semi-gloss white trim & doors, flat white ceilings, white closets o Purchase all interior paint from Pratt & Lambert Color Navajo Eggshell Ceiling White Trim White Haze Green Name Gold Pro Hide Eggshell Base 1- Walls Gold Flat Super One Coat White Gold Semi-Gloss Super 1-Coat White Gold Pro Hide Eggshell Base 1 Color Code 33-32 Product Code Z8291 Z8100 Z8300 Z8291

18-30

4. Reuse all doors and existing antique hardware 5. Add railing with spindles on stairs to 2nd floor were wall was removed 6. Install new carpet in all rooms except kitchen, bathroom, living and dinning 7. Repair and replace sub-floor were needed 8. Install overhead lights in all rooms were needed KITCHEN: 1. Gut entire kitchen and adjust layout as per diagram 2. Paint as per house color scheme ( Walls will be Haze Green see color chart) 3. Install new maple cabinets as per kitchen layout a. 18x30 upper cabinet Lowes item #161140 - $112.00 b. 12x30 upper cabinet Lowes item #155104 - $94.40 c. 30x12 upper cabinet Lowes item #280285 - $98.33 d. 15x 30 upper cabinet Lowes item # 155361 - $105.22 e. 30 sink base cabinet Lowes item #280058- $151.44 f. 15 base cabinet Lowes item #155361 - $105.22

Scope of Work Manifesto

www.FortuneBuilders.com

INTERIOR: (contd.)
4. Cut window in half, over sink, to allow new layout and patch exterior and paint 5. Install new appliances (stainless steel appearance) a. Frigidaire refrigerator Lowes item #293510 - $538.00 b. Frigidaire gas range Lowes item #273662 - $538.00 c. Frigidaire dishwasher Lowes item #226379 - $298.00 d. Frigidaire microwave Lowes item #180278 - $248.00 6. Install new counter top with 8 deep sink with single handle faucet and sprayer a. 10 counter top Lowes item #202016 - $100.00 b. 6 counter top Lowes item #201986 - $60.00 c. Miter bolt kit Lowes item #095077 - $5.46 d. End cap Kit Lowes item #065433 - $10.88 e. SS Sink 8 deep Lowes item #007575 - $96.37 7. Tile floor with brick pattern layout (Daltile Salerno #SL83 Marrone Chiaro 12x12) 8. Tile countertop backsplash (Daltile Salerno #SL83 Marrone Chiaro 2x2)

Scope of Work Manifesto

www.FortuneBuilders.com

INTERIOR: (contd.)
BATHROOM ADDITION - 1ST FLOOR: 1. Demo existing pantry space off kitchen for new half bathroom 2. Install rough plumbing for washing machine, toilet and sink as per attached layout 3. Paint as per house color scheme ( Walls will be Haze Green, see color chart) 4. Tile floor with brick pattern (Daltile Salerno #SL83 Marrone Chiaro 12x12) 5. Install new window, make sure it is frosted glass 6. Install plug and vent for dryer 7. Install new sink base with faucet, medicine cabinet, toilet and towel bars 1 Sink base and vanity top combo 30 Lowes item #147558 - $194.94 2 25 medicine cabinet Lowes item #155760 - $88.00 3 Sutter towel ring Lowes item #034144 - $9.81 4 Sutter 18 towel bar Lowes item #037107 - $14.73 5 Sutter toilet paper holder Lowes item #041680 - $12.76 6 Crane toilet to go- Lowes item #000746 - $69.00 8. Repair existing door

BATHROOM - 2nd FLOOR: 1. Demo existing bathroom and portion of bedroom closet (as per layout) 2. Paint as per house color scheme ( Walls will be Haze Green, see color chart) 3. Relocate tub surround (as per layout), install new a. Sterling Ensemble Whirlpool Lowes item #286050 - $499.00 4. Relocate sink location (as per layout) 5. Tile tub surround with mosaic picture window a. Field tile (Daltile Salerno #SL82 Cremona Caffe 6x6) 6. Mosaic picture window - (Daltile Salerno #SL83 Marrone Chiaro 2x2) 7. Tile floor (Daltile Salerno #SL83 Marrone Chiaro 2x2) 8. Remove window, patch exterior and paint

Scope of Work Manifesto

www.FortuneBuilders.com

7
BATHROOM - 2nd FLOOR: (contd.) 9. Install new sink bas with faucet, medicine cabinet, toilet and towel bars a. Sink base and vanity top combo 30 Lowes item #147558 - $194.94 b. 25 medicine cabinet Lowes item #155760 - $88.00 c. Sutter towel ring Lowes item #034144 - $9.81 d. Sutter 18 towel bar Lowes item #037107 - $14.73 e. Sutter toilet paper holder Lowes item #041680 - $12.76 f. Crane toilet to go- Lowes item #000746 - $69.00

BEDROOMS: 1. Paint all rooms as per house color scheme above 2. New carpet in all room, including 3rd floor (color - Marble Teal) 3. Remove walls on 3rd floor room (see layout) 4. Frame in closet in front bedroom on 3rd floor 5. Install overhead light fixtures in all rooms

Scope of Work Manifesto

www.FortuneBuilders.com

8
THIRD FLOOR: 1. Remove portion of wall in unfinished room (see layout) 2. Insulate and sheetrock unfinished room and prep for paint 3. Prep remaining 2 rooms for paint 4. Paint all rooms as per house color scheme and install new carpet (color Marble Teal)

PLUMBING: 1. Re-plumb entire house and tie into existing main drain 2. Check existing drain in basement, repair as needed 3. Relocate kitchen sink and stove as per attached layout 4. Install new kitchen sink w/ single handle faucet and sprayer 5. Install rough plumbing for new bathroom off kitchen (see layout) 6. Install new direct vent hot water heater 50gallon 7. Relocate rough plumbing for bathroom fixtures 2nd floor (see layout) 8. Repair main plumbing stack in basement 9. Install new washing machine hook ups in 1st floor bathroom 10. Install new toilets, tubs, and sinks and make all finish connections 11.Coordinate all inspections ELECTRICAL: 1. Make sure all rooms have overhead light with switches 2. Replace all plugs and switches install GFCI were needed 3. Install new light fixtures in all rooms (2 bulb with brush nickel finish from Lowes) 4. Install larger 100amp panel box to accommodate additional circuits 5. Supply electric whip for dishwasher and above stove microwave in kitchen (see layout) 6. Install whip for under cabinet lighting 7. Make sure all exterior lights work and replace w/ new black fixtures 8. Install exhaust fan in bathroom 9. Supply whips for light above medicine cabinets in both bathroom 10. Install dryer outlet in 1st floor bath 11. Repair and Install lights in basement 12. Coordinate all inspections

Scope of Work Manifesto

www.FortuneBuilders.com

HVAC: 1. Install new gas fired direct vent furnace 2. Modify existing duct work as needed to install 3. Install/repair existing ductwork as needed 4. Inspect all duct work as well as returns 5. Install new thermostat 6. Give me a quote on installing AC

Scope of Work Manifesto

www.FortuneBuilders.com

10 COMPLETION OF THE FINAL PUNCH LIST

Cost Breakdown
General Contracting - $40,000.00 All framing material and labor Sheetrock, Insulation and Interior and Exterior Painting Window Replacement Kitchen Remodel including cabinets, countertop, appliances All Flooring hardwood, carpet and ceramic tile All finish work coordinate all inspections Electrical - $5,500.00 New 100amp panel box New rough wiring, including smoke and CO2 detectors to code Add electric baseboard heat on 3rd floor All fixtures coordinate all inspections Plumbing - $4,500.00 All new rough plumbing, fixtures and finish work Coordinate all inspections HVAC - $3,500.00 New forced warm air direct vent furnace Coordinate all inspection Roof - $6,000.00 Misc. and Permits - $1500.00 TOTAL - $61,000.00

Scope of Work Manifesto

www.FortuneBuilders.com

11

Scope of Work: Single Family Home May 10, 2008 Episode of A&Es Flip This House West Haven, CT
Project Introduction and Overview
Description
Single family Conventional style home, 1650 sq/ft, with 3 bedrooms, and 2.5 bathrooms. The house was built in 1938. Was subject to major fire damaged and was vacant for 2 years. In a nice, quiet, single family, residential, neighborhood plotted on a large lot of land. It was one of the first homes built in the area and still stands as the marquee property for its neighborhood.

Rehab Overview

Property in need of major renovations. Extensive exterior work included a new roof, new windows, demolition of garage structure, abatement of an abandoned well, installation of a city water supply, reconstruction of an existing enclosed porch, and the addition of a 15 foot deck. Interior work included new floors and sheetrock throughout, new insulation, all new plumbing, hvac, and electrical. The first floor layout was completely remodeled in order to create a more spacious and inviting feel. Brand new kitchen including cabinets, counters, appliances, and tile flooring. Completely renovated bathrooms as well as the addition of a new master bathroom that includes a tiled shower with rain showerhead and body sprays.

Contractor Overview

Multiple contractors were needed to complete this project. A licensed general contractor was hired for the windows, flooring, kitchen, bathroom, painting and all carpentry. A licensed plumber was hired for all new rough plumbing and finishing. A licensed electrician was hired for all the wiring. A licensed HVAC contractor was hired for all the new heating and duct work needs.

EXTERIOR:
ROOF: 1. Remove existing roof 2. Replywood the entire house with plywood 3. Install new roof metal on the perimeter of the house, ice/water barrier to be installed on all gutter lines, walls, valleys, and penetrations of the roof. Remaining roof to be covered with 15lb tar paper. Install 30 year GAF shingles with matching ridge cap.

Scope of Work Manifesto

www.FortuneBuilders.com

12

EXTERIOR:
GENERAL: 1. Replace exterior doors with new metal pre hung, paint and install kick plate (Lowes item #66868) 2. Install shutters on 2nd floor windows and match to front door (Burgundy) 3. Repair missing and damaged siding (CT Homes has siding that may match) 4. Repair gutters and downspouts 5. Paint front railing - Black 6. Repair concrete on front and rear steps 7. Install deck in back (will discuss at property) 8. Installation of new windows to be done by Rich The Rehabber 9. Repair foundation walls below enclosed porch in back and install door 10. Replace Bilco door and paint 11. Paint entire foundation including steps Cape Cod Grey

INTERIOR:
1. Re frame rooms as per new layout, call for inspection 2. Repair framing in back mud room and replace sub floor 3. Insulate all rooms and call for inspection 4. Sheetrock all rooms and prep for paint (Sheetrock will be provided) 5. Paint all rooms with house color scheme Paint scheme: Navajo eggshell walls, white trim, white ceilings, white closets, white doors Purchase all paint from Pratt & Lambert Color Name Product Code Navajo Eggshell Gold Eggshell Navajo Wall Z8291 Ceiling White Gold Flat Super 1-Coat White Z8100 Trim White Gold Semi-Gloss Super 1-Coat White Z8300 6. Re Frame 3 windows and install (2 in kitchen and 1 in laundry room) 7. Install new baseboard trim were needed 8. Repair sub floor were needed 9. Install new 6 panel doors with new brushed nickel hardware 10. Repair hardwood in living room, repair hardwood in dinning room from stain and refinish 11. Hardwood in hallway on 2nd floor 12. Clean out all remaining construction debris and fire damage debris

Scope of Work Manifesto

www.FortuneBuilders.com

13

Scope of Work Manifesto

www.FortuneBuilders.com

14

INTERIOR: (contd.)
KITCHEN: (Layouts attached to this document) 1. Re frame as per layout 2. Install all rough plumbing (plumber) 3. Repair sub floor were needed 4. Tile floor (18x18, Salmon Roman Stone, Lowes item #235903) 5. Install new appliances (refrigerator, stove, microwave CT Homes will select) 6. Install dishwasher (Fisher&Paykel DishDrawer) (plumber) 7. Install kitchen sink (Artisan-A3220-D9/7) with faucet (Danze-D456513SS), garbage disposal 8. Install Electric Range (Lowes item #225489) 9. Install overhead microwave (Lowes item #263008) 10. Install refrigerator (Lowes item #59764) 11. Supply water line to refrigerator (plumber) 12. Install 2 windows and adjust framing 13. Viking Kitchen Cabinets, LLC will install cabinets (Merillat Classic Cabinetry) and countertops (DuPont certified Tan Brown granite with ogee edge) Door Style LaBelle Maple with Artisan Bronze Finish Hardware Venetian Bronze Cup Pull on drawers and Venetian Bronze Round Knob 14. Install puck style under cabinet lighting (electrician) 15. Install 3 pendant lights over the kitchen island (electrician, Lowes item #142360) 16. Install recessed lighting for kitchen ceiling (electrician) 17. Tile Backsplash (12x12 sheet, Mixed Glazed Porcelain Mosaic, Lowes item #239475) 18. Replace back door and new hardware

HALF BATHROOMS: 1. Tile Floor (12x12, Salmon Roman Stone, Lowes item #235895) 2. Paint room 3. Frame all spaces including laundry room 4. Install window 5. Install washer and dryer hookup (we will discuss location) (plumber) 6. Install all rough plumbing (plumber) 7. Install toilet elongated bowl (plumber) 8. Install sink base with faucet (plumber) 9. Install vanity lighting (electrician, brushed nickel)

Scope of Work Manifesto

www.FortuneBuilders.com

15

INTERIOR: (contd.)
FULL BATHROOM IN HALLWAY: 1. Close window in bathroom 2. Repair all framing 3. Install all rough plumbing (plumber) 4. Install toilet elongated bowl (plumber) 5. Install sink base with faucet (plumber) 6. Install shower/tub combo (plumber) 7. Tile surround for tub white tile (standard 4 white glaze) with accent strip (4x4, Gold Angora) 8. Install new shower door provided by The Shower Door Store Basco 4400-4500 Infinity sliding enclosure Clear glass Brushed Nickel AquaGlide glass coating Std. Towel Bars 58 w X 63 h 9. Tile floor 12 beige 10. Paint room 11. Install vanity lighting (electrician, brushed nickel)

MASTER BATHROOM: 1. Tile floor (12x12, Standard Beige) and paint room 2. Install all rough plumbing (plumber) 3. Plumbing for stand up shower (plumber) 4. Install/adjust all framing 5. Install body sprays and set shower pan (plumber) 6. Finish shower pan with mud and tile surround (12x12,Chairo Tumbled Marble Sheet, Lowes item #96470) with Accent tile (4x4, Gold Agora, Lowes item #23625) 7. Install new shower door provided by The Shower Door Store

Scope of Work Manifesto

www.FortuneBuilders.com

16
MASTER BATHROOM: (contd.) Basco 1413-1713 Infinity Door with Inline Panel Clear Glass Chrome AquaGlide glass coating C-pull / towel bar combo 52 w X 76 h 8. Install Resin Corner Shelf (Lowes item #69951) 9. Install Resin Soap Dish (Lowes item #68692) 10. Install toilet elongated bowl (plumber) 11. Install sink base with faucet (plumber) 12. Install vanity lighting (electrician, brushed nickel)

Scope of Work Manifesto

www.FortuneBuilders.com

17

INTERIOR: (contd.)
BEDROOMS: 1. Insulate all exterior walls, sheetrock and paint 2. Re arrange framing as per layouts 3. Install doors and trim

BASEMENT: 1. Install oil fire direct vent furnace (HVAC) 2. Install AC condenser and coil (HVAC) 3. Clean and paint walls and floor 4. Paint with waterproofing paint ELECTRICIAN: 1. New 200 AMP electric service 2. Rewire entire house to current building code 3. Hard wire smoke and CO2 detectors to designated areas of the house 4. Install new overhead lighting in every room 5. New switches and plugs in every room 6. Hard wire Phone and Cable to each room designated by owner 7. Light fixtures throughout the house including exterior lighting 8. Install puck style under cabinet lighting 9. Recessed kitchen lighting 10. Install Hi Voltage HVAC Connections 11. Wire Kitchen, living, and dining room for Surround Sound PLUMBING: 12. Install all rough plumbing a. 1 kitchen b. 2.5 bathroom 13. Install new oil tank in basement (price this item separate) 14. Install one 50 gal electric hot water heater 15. Install washing machine hook up in laundry room (we will discuss location) 16. Install body sprays in master bathroom shower and set shower pan a. Master bathroom will be located above front entrance

Scope of Work Manifesto

www.FortuneBuilders.com

18

INTERIOR: (contd.)
PLUMBING: (contd.) 17. Complete all finish plumbing a. 3 toilets elongated bowls b. 3 bathroom sink bases w/ faucet c. 1 stand up shower in master bathroom d. 1 shower/tub combo in hallway bathroom e. 1 kitchen sink with garbage disposal 18. Install dishwasher (we will provide) 19. Supply water line to refrigerator HVAC: 1. Install oil fired direct vent furnace 2. Install AC condenser and coil 3. Install all necessary trunk work for first floor 4. Install all necessary supplies with registers for each room on 1st floor 5. Install trunk through second floor to attic as per layout 6. Install all necessary supplies with registers for each room on 2nd floor 7. Install returns as necessary for entire system 8. Two zone heat/cooling with separate thermostat (1st and 2nd floors) 9. Electrician will supply low voltage and you will make final connections 10. Furnish CT Homes LLC with heat loss calculation sheet 11. Pull permit for job and supply copy to CT Homes LLC 12. Coordinate with West Haven city inspectors for rough and final inspections

COMPLETION OF THE FINAL PUNCH LIST


Carpenter - $52,000.00

Cost Breakdown
HVAC - $8,500.00
New forced warm air heat with AC Coordinate all inspection

All framing material and labor Sheetrock, Insulation and Interior Painting Window Replacement Kitchen Remodel including cabinets, countertop, appliances All Flooring hardwood, carpet and ceramic tile All finish work coordinate all inspections

Roof - $10,500.00 Garage Demo - $5,000.00 Well Abatement - $750.00 MISC -$4,450.00 Permits - $1800.00

Electrical - $8,000.00
New 200amp service All new rough wiring, including smoke and CO2 detectors to code All fixtures coordinate all inspections

= TOTAL - $100,000.00

Plumber - $9,000.00
All rough plumbing, fixtures and finish work Coordinate all inspections

Scope of Work Manifesto

www.FortuneBuilders.com

19

Scope of Work: Single Family Home El Cajon, CA


Project Introduction and Overview
Description
Single family, Ranch Style home with over 2100 sq/ft, and 3 bedrooms and 2 bathrooms. House built in 1976 on .51 ac lot in an exclusive section called Fletcher Hills. The home has Panoramic canyon views.

Rehab Overview

Property was extremely dated and in need of a major facelift. The property had water drainage issues that had caused foundation settling. The kitchen was completely renovated with refinished cabinets, granite countertops, and high end appliances. The bathrooms were completely upgraded with new bathtubs, custom tile, fixtures and flooring. New hardwood flooring throughout and carpet in all bedrooms, along with a 42 plasma TV & 5.1 surround sound speakers were installed to complete the rehab.

Contractor Overview

Multiple contractors were needed to complete this project. A licensed general contractor was hired for the flooring, kitchen, bathrooms, and all carpentry. A licensed engineer and licensed contractor were hired for all foundation work. A licensed electrician was hired for all electrical upgrades.

EXTERIOR:
GENERAL: 1. Paint front door an accent color (Sherwin Williams, Arresting Auburn #6034) 2. Clean existing kick plate- install new hardware and house numbers to match 3. Replace front porch light (Home Depot #196-629, Rustic w/ Antique Glass 2 pack for $39.97) 4. Install new doorbell 5. Repair any and all damaged wood on exterior of house (As per termite report) 6. Repair all gutters around perimeter of roof and down spouts 7. Power wash exterior and paint entire body of house (Match existing color) 8. Paint rear deck and overhangs (Sherwin Williams, Urbane Bronze #7048)

Scope of Work Manifesto

www.FortuneBuilders.com

20
FOUNDATION: 1. Repair existing foundation damage as per engineers report and plan. 2. Repair Drainage situation on entire property 3. Repair any and all portions of deck that are removed 4. Structural Engineer to approve all and provide letter of completion LANDSCAPING: 1. Inspect and repair all sprinklers as needed 2. Install new sod in front yard 3. Set timer so front grass is watered on a regular basis 4. Trim existing bushes in front, plant annuals and add dark brown wood chips in flower beds 5. Plant new Red Fountain Grass (6) in front flower beds 6. Cut all weeds at back of property and scope 7. Repair fence at bottom of slope

INTERIOR:
DEMO: 1. Remove all loose trash and debris from house and garage 2. Save washer and dryer to leave at home 3. Remove all fixtures from master bath 4. Remove kitchen counters, appliances and flooring GENERAL: 1. Patch all walls and Paint all rooms as per color scheme below a. Purchase all paint thru Sherwin Williams Color Location Color Code Softer Tan All Walls 6141 Alabaster Ceiling & Trim 7008 Black Fox Lower Kitchen Cabinets 7020 Sohji White Upper Kitchen Cabinets 7042 Urbane Bronze Exterior Trim & Deck 7048

Finish Semi Gloss Flat Semi Gloss Semi Gloss Semi Gloss

Scope of Work Manifesto

www.FortuneBuilders.com

21

INTERIOR: (contd.)
GENERAL: (contd.) 3. Install new brushed nickel hardware throughout 4. Hand texture all walls (Imperfect Smooth finish) 5. Install rounded corner bead entire house 6. Have 2 fireplaces cleaned by professional provide owner with report 7. Face both fireplaces with 22 Travertine (CT Homes will select) 8. Install new carpet in all bedrooms (Mesa carpet, color Cocoa Latte Home Depot) 9. Install hardwood in living rooms, dining room and kitchen -(Ecoplantation color Jatoba) 10. Install overhead lights in all rooms - Home Depot 13 dome #701-704 Nickel 2 Pack for $19.77 KITCHEN: 1. Remove counter top be careful not to damage cabinets 2. Paint as per house color scheme 3. Clean, sand and paint cabinetry as per color scheme above 4. Replace all cabinet hardware (brushed nickel - TDB) 5. Install granite countertop (Color Tiger Skin) 6. Install new 8 deep sink Home Depot #755-731, Neptune 8 double bowl, $109.00 7. Install new single handle faucet and sprayer Home Depot #453-090, $138.00 8. Install new appliances (stainless steel from Pacific Sales) a. Frigidaire re frigerator model #FGHS234KF - $1221.00 b. Maytag double oven model #MEW5627DDS - $1300.00 c. Frigidaire Gas Cooktop model #FGGC3645KS - $677.00 d. Frigidaire dishwasher model #FGBD2432KF - $422.00 e. GE Profile microwave model #PEB2060SNSS - $277.00 f. GE Profile 36 Hood model #PV977NSS - $1128.00 9. New wood flooring - (Ecoplantation color Jatoba)

Scope of Work Manifesto

www.FortuneBuilders.com

22

INTERIOR: (contd.)
BATHROOM (Hallway): 1. Remove fixtures bathroom 2. Paint as per house color scheme 3. Install new fixtures a. Deep soaking tub 60x 32x 21deep- Lowes item #1039078 - $260.00 b. Toilet Wellworth Home Depot #692-8258 - $169.00 c. Medicine cabinet Home Depot item #019-611 - $99.00 d. Vanity light - Hampton Bay, 3 light, #237-544 - $89.97 e. Install ceramic tile surround i. Field Tile - #340-275, 6x6 Briton Field - $2.08 sq/ft ii. Accent Strip - #608-314, 12 Travertine Medley - $9.72/ea iii. Cut accent tile into strips 4 wide, lay end to end way up the wall iv. Soap Dish - #762-332 - $14.90/ea 4. Tile floor (12 beige, brick layout) Hacienda Home Depot #051-260 - $.77/ea BATHROOM (Master): 1. Remove Fixtures 2. Install new dual bowl sink base with granite top 3. Install (2) recessed medicine cabinets Lowes #687-572 - $128.00/ea 4. Install shower body spray system (See attached sheet) 5. New lighting - Hampton Bay wall sco nce, Home Depot #295-650 - $39.97 (2) 6. Tile shower stall a. Field Tile - #668-521, 6x6 Almond - $1.89 sq/ft b. Accent Walls - #686-181, Onyn Studio Glass Moasic 12- $12.99/ea c. Lay full sheets of Onyx on floor and wet wall d. Corner Shelf matching Almond color 7. Tile floor (12 beige, brick layout) Hacienda Home Depot #051-260 $.77/ea

Scope of Work Manifesto

www.FortuneBuilders.com

23

INTERIOR: (contd.)
BEDROOMS: 1. Paint all rooms as per house color scheme 2. Install new carpet in all rooms - Mesa carpet, color Cocoa Latte Home Depot 3. Make sure all doors work properly 4. Replace all mirrored closet doors - (Raised 6 panel White) 5. Install new brushed nickel hardware 6. Install overhead light fixtures in all rooms PLUMBING: 1. Check all existing plumbing and repair as needed 2. Install new faucets and replace shut off valves ELECTRICAL: 1. Replace all outlets 2. Install recessed lighting in living room and den (see attached diagram) 3. Inspect main panel and service as needed HVAC: 1. Service existing heating and AC unit (provide owner with service receipt)

Scope of Work Manifesto

www.FortuneBuilders.com

24 COMPLETION OF THE FINAL PUNCH LIST

Cost Breakdown
General Contracting and Foundation Work - $54,700.00 Hand texture, new corner bead through entire house All Interior and Exterior Painting Kitchen Remodel including cabinet work, countertops, appliances Foundation & Water Drainage improvements All finish work coordinate all inspections Surround sound install Electrical - $3,000.00 New Plugs and Switches throughout and all new fixtures Add Recessed Cans, final trim and all material & labor Home Staging (for 1 month) - $1,600.00 Plumbing - $3,700.00 All fixtures and faucets, including body sprays, all labor Flooring (Hardwood, carpet and tile) - $7,500.00 Landscaping - $3,000.00 Sprinklers, sod, plants and back yard slope clean up Misc. and Permits - $2,500.00 TOTAL - $76,000.00

Scope of Work Manifesto

www.FortuneBuilders.com

25

Scope of Work: Single Family Home San Diego, CA


Project Introduction and Overview
Description
1435 square foot ranch style home built in 1955. The home has 3 bedrooms and 2 baths with a more contemporary feel and design. Located in the Rolando neighborhood of San Diego near SDSU.

Rehab Overview

The home had minor foundation issues & water drainage problems. The house needed a new roof, complete kitchen and bathroom renovations. Electrical and plumbing upgrades were needed as well.

Contractor Overview

Multiple contractors were needed to complete this project. A licensed general contractor was hired for the flooring, kitchen, bathrooms, roofing and all carpentry. A licensed engineer and licensed contractor were hired for all foundation work. A licensed electrician was hired for all electrical upgrades.

EXTERIOR:
GENERAL: 1. Repair any damaged wood and stucco on exterior of house & garage. 2. Haul away trash on East side of house. 3. Touch up exterior paint as needed, leave existing color. ROOF: 1. Repair any damaged wood and stucco on exterior of house & garage. 2. Haul away trash on East side of house. 3. Touch up exterior paint as needed, leave existing color. LANDSCAPING: 1. Clean front & back yards & remove debris. 2. Install draught tolerant landscape in front yard. 3. Plant annuals in front yard. 4. Add dark brown wood chips in all beds.

Scope of Work Manifesto

www.FortuneBuilders.com

INTERIOR:
DEMO: 1. Bath by garage- toilet, sink, tile. 2. Kitchen backsplash and countertop. Leave cabinets 3. Remove all appliances 4. Flooring in living room 5. West wall mural. 6. Parquet flooring in all bedrooms 7. Hall bath- remove toilet, sink, vanity, tile and tub. GENERAL: 1. Patch walls/ceilings, then apply Santa Fe hand texture throughout. 2. Prep & paint all rooms per color scheme All paint through Sherwin Williams. 3. Prep/paint all interior doors, including closet (s). 4. New hardware on all doors. (satin finish) Color Accessible Beige Alabaster Shoji White Match Existing Repose Gray Alabaster Location
Living/Dining, Halls/Laundry/Kitchen/Bedrooms

26

Trim Doors and Windows Existing Cabinets All Exterior and Trim Bathrooms All Ceilings

Color Code 7036 7008 7042 7015 7008

Finish Semi Gloss Semi Gloss Semi Gloss Satin Flat

Scope of Work Manifesto

www.FortuneBuilders.com

27

INTERIOR: (contd.)
KITCHEN: 1. Install new Black Quartz countertops 2. Install backsplash Arizona Tile, SL/Cosmopolitan 1x1, grout #333 Alabaster (non-sanded) 3. Install new stainless steel appliances A. Refrigerator Sears #6023, Kenmore 20.9 cu. ft Top Freezer Fridge, $832.99
B. Microwave/Hood Sears #8503, Kenmore 30in Micro/Hood Combo $188.99 C. Dishwasher Sears #1523, Kenmore 24in Built In Dishwasher $339.99 D. Range Sears #02260903000, Maytag 30in Self Clean Freestanding Gas Range/Oven $522.49

1. Install new single handle faucetsatin finish 2. Paint cabinets according to house color scheme 3. Tile floorArizona Tile, Metro Platinum 12x24, grout #19 Pewter (non-sanded) 4. Paint room as per color scheme. 5. Install new recessed lightingsee layout

Scope of Work Manifesto

www.FortuneBuilders.com

INTERIOR: (contd.)

28

SMALL BATH: 1. Install new toilet Home Depot, Kohler Wellworth -Round Bowl, White, $128 2. Install sink Home Depot, Glacier Bay Aragon Pedestal w/ Sink, #333-025/#592-680, $24 & $30 3. Install faucet Home Depot, Pegasus Dorset 4in 2 Handle Faucet -Chrome, #478-234, $54.00 4. Tile FloorsArizona Tile, Fibra Linen 12x24, grout #382 Bone (non-sanded) 5. Tile Shower Enclosure Arizona Tile, Fibra Linen 12X12Lay subway style , Grout #382 Bone 6. Paint room per color scheme. 7. Install new shower fixtures Home Depot, Shower Valve#248-087. 8. Install accessories: Home Depot, Dcor Bathware, Greenwich 3 pc kit in Chrome, $39.98 9. Install new lighting Home Depot, 2 Light Vanity Light , #837-292, $64.97

HALL BATH: 1. Reframe into 2 baths as per drawing. Paint as per color scheme 2. Install tile floor Arizona Tile, Fibra Linen 12x24, grout #382 Bone (non-sanded) 3. Install new toilet Home Depot, Kohler Wellworth -Round Bowl, White, $128 4. New VanityHome Depot #897-705 and sink #923-715 5. Install New countersame as kitchen counter 6. Install faucet Home Depot, Pegasus Dorset 4in 2 Handle -Chrome, #478-234, $54.00 7. Tile FloorsArizona Tile, Fibra Linen 12x24, grout #382 Bone (non-sanded) 8. Install New Tub 60L X 30W x21D soaking tub in white 9. Tile Tub Enclosure Control Wall Arizona Tile, Fibra Linen 12X24, #381 Bright White (non-sanded) 10. Tile Enclosure Remaining Wall Arizona Tile SL-White Glossy 3x6 Sheet, grout #381 Bright White 11. Install new shower fixtures Home Depot, Shower Valve#248-087 12. Install accessories: Home Depot, Dcor Bathware, Greenwich 3 pc kit in Chrome, $39.98 13. Install new lighting Home Depot, 2 Light Vanity Light , #837-292, $64.97

Scope of Work Manifesto

www.FortuneBuilders.com

29

INTERIOR: (contd.)
MASTER BATH: 1. Reframe Hall bath into 2 baths as per drawingcreate the master bathroom. 2. Install tile floor Arizona Tile, Fibra Linen -12x24, grout #382 Bone (non-sanded) 3. Install tile in surround Arizona Tile, SL/White Matte 1x1 sheet, #381 Bright White (non-sanded) 4. Install new vanity Double sink model, dark cherry wood color 5. Install counter Granite, style TBD by owner 6. Sink- Home Depot, #923-715 (2) 7. Install faucet Home Depot, Pegasus Dorset 4in 2 Handle Faucet -Chrome, #478-234, $54.00 (2) 8. Toilet- Home Depot, Kohler Wellworth, Elongated BowlWhite, $128 9. Accessories Home Depot, #695-127 10. Install new light fixtures Home Depot, 2 Light Vanity Light, #837-292, $64.97 (2) 11. Paint as per color scheme. BEDROOMS: 1. Install new flooring Select Carpet in Fawn 2. Install new light fixtures Home Depot, 2 Light Flushmount With Opal Glass, #534-435, $39.97ea 3. Make sure all doors are operating properly. 4. Keep existing hardware 5. Paint as per color scheme.

PLUMBING: 1. Check all plumbing & repair & replace as needed per code. 2. Install waste/water lines for new bath. 3. Reconfigure waste/water lines for existing bath. 4. Check hose bibs & make sure they are all working properly. ELECTRICAL: 1. Upgrade panel to 200amp and relocate to exteriorper code. 2. Replace all outlets & switches. 3. Upgrade all wiring as needed per code 4. Replace all light fixtures through out house 5. Install recessed lights per lighting plan.

Scope of Work Manifesto

www.FortuneBuilders.com

30 COMPLETION OF THE FINAL PUNCH LIST

Cost Breakdown
General Contracting and Foundation Work - $27,200.00 Kitchen Remodel - New countertops, appliances, tile backsplash Bathroom - New counters and all framing changes Hand texture and paint all walls and ceilings All finish work and coordinate all inspections Foundation Repairs - $7,000.00 Engineers plans, epoxy injection, moister barrier Electrical - $3,000.00 New 200amp panel w/ plugs and switches throughout. Update wiring to code, new fixtures throughout Plumbing - $4,000.00 New plumbing and fixtures for existing bathrooms. New plumbing for master bathroom Upgrade kitchen and laundry areas as needed per code Flooring (Hardwood, carpet, tile) - $4,900.00 Hardwood in living rooms, carpet in bedrooms and custom tile in kitchen and baths Landscaping - $1,100.00 Roofing - $1,100.00 New 30 year comp architectural shingle roof Misc. and Permits - $3,500.00 TOTAL - $59,000.00

Scope of Work Manifesto

www.FortuneBuilders.com

31

Scope of Work: Single Family Home San Diego, CA


Project Introduction and Overview
Description
1657 square foot ranch style home build in 1957. The home has 3 bedrooms and 2 and half bathrooms with a more contemporary feel and design. The home is located in the Rolando Hills neighborhood of San Diego near San Diego State University.

Rehab Overview

The home has minor fire damage. The house needs minor roof repair, complete kitchen and bathroom renovations. Electrical and plumbing upgrades were needed as well.

Contractor Overview EXTERIOR:

Licensed contractors were used to complete all work. GENERAL: 1. Repair any damaged wood and stucco on the exterior of the house and garage. 2. Paint entire house. (ValsparStone Manor #6006-2A) 3. Install White Picket Fence in front yard 4. Install a wood deck in the back yard. (approximately 15 X 15) ROOF: 1. Inspect and patch as needed LANDSCAPING: 1. Clean front and back yards and remove debris. 2. Install draught tolerant landscape in front yard 3. Plant annuals in front yard 4. Add dark brown wood chips in all planter beds. 5. Possibly remove par of tree root in front yard to level walk way.

Scope of Work Manifesto

www.FortuneBuilders.com

32

INTERIOR:
DEMO: 1. Bath by garage remove toilet and flooring 2. Kitchen backsplash and countertop. Leave cabinets 3. Remove all appliances 4. Master bath remove toilet, sink, vanity, tile and tub 5. Hall bath remove toilet, sink, vanity, tile and tub 6. Demo fire damaged hall closet 7. Remove cabinets on wall between kitchen and entryway. (Do not damage going to a new location) GENERAL: 1. Patch walls/ceilings, then apply Santa Fe hand texture throughout. 2. Prep and paint all rooms per color scheme All paint through Sherwin Williams 3. Prep/paint all interior doors including closets. 4. Close in doorway going from kitchen to garage. 5. Close in doorway going from master bedroom to living room. 6. Rebuild fire damaged hallway closet. 7. Sand and refinish all existing hardwood floors. 8. Carpet living room and bedrooms. Wisteria Lane, Shaw Carpet, Style Northern Parkway, Color 201 Vintage Gold 9. New hardware on all doors. (Satin finish) 10. Add safe Home Depot, Mesa Safe Adjustable Hidden Wall Safe, Model #MAWS2113ECSD , $119 each Color
Valspar/Lowes Stone Manor

Extra White Navajo White Navajo White Extra White

Location Exterior All Ceilings Bathrooms


Living/ Dining/ Halls, Laundry, Kitchen, Bedrooms

Extra White

Color Code 6006-2A 7006 SW 6126 SW 6126 SW 7006

Finish Flat Flat Semi Gloss Flat Semi Gloss

Scope of Work Manifesto

www.FortuneBuilders.com

33

INTERIOR: (contd.)
KITCHEN: 1. Install new countertops. Granite Uba Tuba 2. Install new backsplash. #860-331 12x12 Milano Brown (pencil glass) - $15.99/ea 3. Re-install removed cabinets at the location of the previous door that was closed in. 4. Install new stainless steel appliances. A. Refrigerator Sears #6023, Kenmore 20.9 cu. ft Top Freezer Fridge, $832.99 B. Microwave/Hood Sears #8503, Kenmore 30in Micro/Hood Combo $188.99 C. Dishwasher Sears #1523, Kenmore 24in Built In Dishwasher $339.99 D. Range Sears #02260903000, Maytag 30in Self Clean Freestanding Gas Range/Oven $522.49

Scope of Work Manifesto

www.FortuneBuilders.com

34

INTERIOR: (contd.)
HALL BATHROOM / LAUNDRY BATHROOM: 1. Install tile floor (Home Depot, Hacienda 12x12) 2. Install new toilet Home Depot, Kohler Wellworth -Round Bowl, White, $128 3. New Vanity Home Depot #897-705 and sink #923-715 4. Install New countersame as kitchen counter 5. Install faucet LuxArt, Aerro 4 Centerset Lavatory Faucet 6. Install New Tub 7. Field Tile/ Accent Strip Home Depot, #340-275, 6x6 Briton Field - $2.08 sq/ft , #686-181, Onyn Studio Glass Moasic 12- $12.99/ea 8. Soap Dish Home Depot, #762-332 - $14.90/ea 9. Install new shower fixtures 10. Install accessories - LuxArt Aerro Towel Bar, Towel Ring, Tissue Holder, all Polished Chrome 11. Install new lighting Home Depot, 2 Light Vanity Light , #837-292, $64.97

Scope of Work Manifesto

www.FortuneBuilders.com

35

INTERIOR: (contd.)
MASTER BATHROOM: 1. Install tile floor (Hacienda 12x12 or similar) 2. Re use existing vanity 3. Install counter Granite, color Ubatuba 4. Sink undermount square bowl 5. Install faucet LuxArt, Aerro 4 Centerset Lavatory Faucet 6. Toilet - Home Depot, Kohler Wellworth -Round Bowl, White, $128 7. Install New Tub Home Depot 18 deep 8. Accent wall and shower niche tile - # 860-331 12x12 Milano Brown (pencil glass) 9. Field tile - #668-521, 6x6 Almond - $1.89 sq/ft 10. Install new shower fixtures 11. Accessories LuxArt Aerro Towel Bar, Towel Ring, Tissue Holder, all Polished Chrome 12. Install new light fixtures Home Depot, 2 Light Vanity Light , #837-292, $64.97 13. Paint as per color scheme.

Scope of Work Manifesto

www.FortuneBuilders.com

36

INTERIOR: (contd.)
BEDROOMS: 1. Sand and refinish existing wood flooring 2. Install new light fixtures Home Depot, 2 Light Flushmount With Opal Glass, #534-435, $39.97ea 3. Install new fan - Home Depot, Hunter - The Stratford, 44, item 119-340, $99/ea 4. Make sure all doors are operating properly. 5. Paint as per color scheme.

Scope of Work Manifesto

www.FortuneBuilders.com

37

INTERIOR: (contd.)
PLUMBING: 1. Check all plumbing & repair & replace as needed per code. 2. Remove existing hot water heater and replace with new one 3. Check hose bibs & make sure they are all working properly. ELECTRICAL: 1. Replace all outlets & switches. 2. Upgrade all wiring as needed per code 3. Replace all light fixtures through out house 4. Install recessed lights per lighting plan. HVAC: 1. Install new forced air heat unit in lower level 2. Perform all work to code

COMPLETION OF THE FINAL PUNCH LIST

Cost Breakdown
General Contracting Work - $27,700.00 Kitchen Remodel - New countertops, appliances, tile backsplash Bathroom - New counters and all framing changes Hand texture and paint all walls and ceilings All finish work and coordinate all inspections Electrical - $2,800.00 Plumbing - $3,000.00 Flooring (Hardwood, carpet, tile) - $8,000.00 New Bamboo in living, dining, kitchen and family room. New carpet in all bed rooms, New tile in all bathrooms Landscaping - $1,500.00 Misc. and Permits - $3,500.00 TOTAL - $51,000.00

Scope of Work Manifesto

www.FortuneBuilders.com

38

Scope of Work: Single Family Home El Cajon, CA


Project Introduction and Overview
Description
Single family home, 1288 sq/ft with 3 bedrooms and 2 Baths. The home was built in 1952 on a .16ac lot. The house is in a quite neighborhood of the Fletcher Hills section of El Cajon.

Rehab Overview

This home needed minor exterior work which included painting, landscaping and new roof and windows. The interior work included new kitchen cabinets, granite counters and new flooring and paint throughout. Both bathrooms were completely renovated and a new deck was built in the back yard as well.

Contractor Overview EXTERIOR:

A Licensed general contractor, electrician, roofer and plumber were used to complete all work. GENERAL: 1. New front & back doors (French door at back entrance). 2. Prep & paint exterior of house. 3. Repair any damaged wood as per termite report. 4. Replace porch lights. 5. Repair gate/fence in front yard. 6. Haul away all debris. 7. Demo patio & build pergola off back porch; to include side yard. 8. Install siding on North side of garage, facing neighboring property. 9. Demo all existing material/chicken pens, etc in backyard. ROOF: 1.Rip existing roof. 2.Install new plywood where needed. 3.Install drip edge at perimeter. 4.Cover with 15 lb. paper, then install architectural style shingles. (Charcoal color)

Scope of Work Manifesto

www.FortuneBuilders.com

LANDSCAPING: 1. Trim bushes in front & back yards. 2. Clean up & remove all debris. 3. Change existing sprinkler valves, add drip irrigation, trim bushes. 4. Plant annuals in beds at front of house. 5. Repair fence in front yard.

39

INTERIOR:
DEMO: 1. Kitchen wall to dining room (as per drawing) 2. Kitchen island 3. Kitchen soffit & dropped ceiling. 4. Cabinets, tile, fixtures. 5. All windows. 6. Hall bath cabinets, tile, fixtures. 7. Demo & widen entry in front room (as per drawing) 8. Closet in Master Bedroom. 9. Interior shelving in room off garage. GENERAL: 1. Install heating/air system. 2. Frame new closet wall to create 2nd bath in Master Bedroom. 3. Narrow Master Bedroom door opening. 4. Frame opening for French door off dining area. 5. Frame kitchen island as per drawings. 6. Frame new wall in kitchen @ countertop height. 7. Patch walls/ceilings, then apply Santa Fe hand texture throughout. 8. Install new retrofit windows. Install base molding throughout. Prep & paint as per color scheme. Color Location Valspar/Lowes Stone Manor Exterior AlabasterSherwin Williams All Ceilings Accessible Beige All Interior Walls Color Code 6006-2A SW7008 SW7008 Finish Flat Flat Eggshell

Scope of Work Manifesto

www.FortuneBuilders.com

INTERIOR: (contd.)
KITCHEN: 1. Install backsplash Home Depot light green Subway Glass Tile 2. Install new stainless steel appliances Pacific Sales Stainless Steel Package
A. Refrigerator Frigidaire 26 Cu. Ft. Refrigerator Model: FFHS2612LS B. Microwave/Hood Frigidaire 1.6 Cu. Ft. Over-The-Range Microwave Model: FFMV164LS C. Dishwasher Frigidaire 24 Built-In Dishwasher Model: FFBD2407LS D. Range Frigidaire 30 Freestanding Gas Range Model: FFGF3047LS

40

3. Install new faucet Home Depot 4. Install new countertops Rainbow Stone Uba Tuba Granite 5. Install new cabinets Kitchen Kompact Maple Mellowood Cabinets 6. Tile floor Home Depot Hacienda 12x12in tile 7. Paint as per color scheme.

Scope of Work Manifesto

www.FortuneBuilders.com

41

INTERIOR: (contd.)
HALL BATH: 1. Install new vanity/sink/hardware. 2. New toilet Fergusons Plumbing Pure Flow elongated bowl 3. New tub Fergusons 60x30 Advant tub 4. Install Tile surround Home Depot #478-640, 6x6 - Briton Field$2.08 sq/ft 5. Accent Tile Home Depot - #608-314, 12 sheets, Travertine Medley - $9.97/ea 6. Tile floor Home Depot Hacienda 12x12

MASTER BATH: 1. New toilet Fergusons Plumbing Pure Flow elongated bowl 2. New tub Fergusons 60x30 Advant tub 3. Install new vanity counter top Rainbow Stone (Granite TBD) 4. Install new vanity Lowes Estate Java Avalon 60 5. Faucet is Delta Pasadena style 4 6. Install Tile Surround Home Depot - #668-521, 6x6 Almond - $1.89 sq/ft 7. Accent Tile - Home Depot - #686-181, Onyx Studio Glass, 12 sheets, $12.99/ea 8. Tile floor- Home Depot Hacienda 12x12

Scope of Work Manifesto

www.FortuneBuilders.com

42

INTERIOR: (contd.)
BEDROOMS: 1. Sand and refinish existing hardwood floors 2. Install carpet in Master 3. Lighting Home Depot Hampton Bay 2- Light Flush mount With Opal Glass, #534-435, $39.97/ea

PLUMBING: 1. Check all existing plumbing & repair/replace as needed, per code. 2. Remove water heater & replace w/tankless. 3. Install new shower diverter (s). 4. New angle stops on all water lines. 5. Check gas lines & repair/replace as needed. 6. Check all drain lines & repair/replace as needed ELECTRICAL: 1. Replace all outlets & switches. 2. Check all wiring & replace where needed, per code. 3. Install recessed lighting as per drawing. 4. Check panel & repair/replace as needed. HVAC: 1. New Forced Air heat unit with all new duct work 2. New AC condenser

Scope of Work Manifesto

www.FortuneBuilders.com

43 COMPLETION OF THE FINAL PUNCH LIST

Cost Breakdown
General Contracting Work - $35,000.00 Kitchen remodel, 2 bath remodels, framing, doors, trim, windows, all paint & texture All finish work, fixtures, etc Electrical - $5,200.00 Roofing - $6,800.00 HVAC - $5,000.00 Home Staging (for 1 month) - $1,500.00 Plumbing - $6,500.00 Flooring (Hardwood, carpet, tile) - $4,000.00 New Bamboo in living, dining, kitchen and family room. New carpet in all bed rooms, New tile in all bathrooms Landscaping - $1,500.00 Misc. and Permits - $3,000.00 TOTAL - $68,500.00

Scope of Work Manifesto

www.FortuneBuilders.com

44

Scope of Work Manifesto

www.FortuneBuilders.com

FortuneBuilders | 960 Grand Avenue, San Diego, CA 92109 2013 FortuneBuilders, Inc. All rights reserved.

This information is for educational purposes. We dont believe in push-button profitswe believe in proven business systems, education, drive and hard work. We are committed to teaching you how to reach your goals. In promoting our educational programs, we illustrate success stories. We want you to know, students are not compensated for their testimonials. However, many of our most successful students join our team as Coaches and Trainers. As stipulated by law, we cannot and do not guarantee results or offer legal advice. As with any business, your results will vary and will be based on your drive, effort, follow-through and other variables beyond our control. We believe in full transparency, and a high standard of integrity, that is why we encourage you to read our full earnings and income disclaimer by visiting www.fortunebuilders.com/earnings-income-disclaimers/