You are on page 1of 5

I.

Registration Procedure
Description
Newly or for replacement pressure gauge that needs calibration shall be coordinated to QA-Calibration Section. A back-up pressure gauge must be provided prior the request to secure availability of machine and so as not to halt the sections productivity. Fill-out Registration Form (S-QR-343) signed and approved by section heads. Submit the form and the pressure gauge to QA-Calibration section Note: The instrument must be complete and in-good-running condition before handing it over to QA-Calibration. The form and the pressure gauge must be validated and passed with initial inspection before acceptance of request. The pressure-gauge shall then log, in the In and Out Instrument Logsheet. The validated pressure gauge shall be registered in the Calibration Program and shall have its control number assigned. Schedule of calibration shall be made upon accepting the request based on the need and availability of facility to be used. Record of registration shall be kept and maintained including S-QR-343. The pressure-gauge shall calibrate based on the given schedule. QA-Calibration Section QA-Calibration Section and Requesting Party

Responsible

I I I

Start Requesting Registration & Calibration

QA-Calibration Section to Maintenance Division

Requesting Party

No

Receivin g of Instrume nt

Yes

Registration

QA-Calibration Section

Calibration

Re-issuance of Pressure Gauge

A A Request of Installation

After calibration, the pressure-gauge shall haveofits calibration with its A request installation for seal the pressure next calibration and its remarks. gauge shall be date made depending on the sections prerogative, forward to Note: Result of calibration must be Maintenance Division. reported immediately to the section concern prior Division to use. shall A reference copy Maintenance schedule the of certificatebased of calibration given installation on the shall givenbe date of to the section concern after finalizing the section concern. the report. The pressure gauge shall be picked-up The section concern receive a at QA-Calibration and shall be log out notice getting through telephone that the upon it back using the In and pressure-gauge is ready to be pickedOut Instrument Logsheet. up. Maintenance in-charge and Calibration personnel assigned shall accompany the requesting party during the installation of the pressure gauge. Note: Back-up gauge shall surrender to Maintenance Division and must be validated before and after use.

Requesting Party to Maintenance QA-Calibration Section to Requesting Party

QA-Calibration Section, Maintenance to Requesting Party

End

II.
I I I

Recall Procedure Start


Schedule of re-calibration shall be made signed and approved by QA and Maintenance Division Head. Based on the given schedule, Maintenance a The pressureDivision gauge shall shallprepare calibrate replacement the schedule. pressure gauge that based on thefor given will be collected in the production. After calibration, the pressure gauge shall have its calibrationshall sealbe with its A notice of re-calibration given next calibration date and its remarks. to section concern two days ahead the scheduled date of Note: Result of re-calibration. calibration must be reported immediately to the section concern prior to use. A reference copy of certificate of calibration shall be given to the section concern after finalizing the Thereport. pressure gauge shall be collected and submitted to QA-Calibration a day before the date of re-calibration. The section concern shall receive a notice through telephone that the pressure-gauge is ready to be pickedup. The pressure gauge shall be initially inspected before receiving the instrument. A installation forin the The request pressure of gauge shall log-in the pressure-gauge shall be made Calibration Transaction Form S-QR-029 depending on the upon receiving it. sections prerogative, forward to Maintenance Division. Maintenance Division shall schedule the installation based on the given date of the section concern. The pressure gauge shall be picked-up at QA-Calibration and shall be log out upon getting it back using the Calibration Transaction Form S-QR029. Maintenance in-charge and Calibration personnel assigned shall accompany the requesting party during the installation of the pressure gauge. Note: Back-up gauge shall surrender to Maintenance Division for future use. QA-Calibration Section, Maintenance to Requesting Party QA-Calibration Section to Maintenance

QA-Calibration Section Section, Maintenance to Requesting Party

Issuance of Re-calibration Notice

Collection of Pressure Gauge subject for re-calibration

Maintenance with Requesting Party

coordination

to

QA-Calibration Section to Requesting Party

Maintenance to QA-Calibration Section

No

Receivin g of Instrume nt

Requesting Party to Maintenance

Yes

Calibration

Re-issuance of Pressure Gauge

Request of Installation

End

III.

Request for Re-calibration/Replacement Procedure Start


Any inadequacy observed in the pressure-gauge shall be reported immediately for corrective action. Section concern

Filing of Report

Fill-out Equipment Status Report (S-QR258) signed and approved by section head, forward to QA-Calibration.

Requesting Party

I I I

A
The request shall be validated by conducting initial inspection on the pressure-gauge concern. Corrective action might be replacement or re-calibration depending on the analysis and need. QA-Calibration Section

No

Validatio n of Request

Yes

Collection of Pressure Gauge concern

A notice shall be given to section head and Maintenance Division to schedule the collection of the pressure gauge. Note: Schedule of collection depends on the agreement between the section head and Maintenance Division.

QA-Calibration Section, Requesting Party to Maintenance Division.

No

Receivin g of Instrume nt

The pressure-gauge shall be initially inspected before receiving the instrument. The pressure gauge shall log-in in the In and Out Instrument Logsheet and the re-calibration date shall schedule upon receiving it.

Maintenance Division to QA-Calibration Section

Yes

Re-calibration

The pressure-gauge shall calibrate based on the given schedule. After calibration, the pressure gauge shall have its calibration seal with its next calibration date and its remark. Note: Result of calibration must be reported immediately to the section concern prior to use. A reference copy of certificate of calibration shall be given to the section concern after finalizing the report.

QA-Calibration Section

Re-issuance of Pressure Gauge

A A

The section concern shall receive a notice through telephone that the pressure-gauge is ready to be pickedup. A request of installation for the pressure gauge shall be made depending on the sections prerogative, forwarded to Maintenance Division. Maintenance Division shall schedule the installation based on the given date of the section concern. The pressure gauge shall be picked-up at QA-Calibration and shall be log out upon getting it back using the in and Out Instrument Logsheet. Maintenance in-charge and Calibration personnel assigned shall accompany the requesting party during the installation of the pressure gauge. Note: Back-up gauge shall surrender to Maintenance Division for future use.

QA-Calibration Section

Requesting Party to Maintenance

Request of Installation

QA-Calibration Section, Maintenance to Requesting Party

End